Professional Documents
Culture Documents
Section 2700 (Repair of Structures)
Section 2700 (Repair of Structures)
Page No.
2701 SCOPE 27-1
2702 GENERAL 27-1
2703 REPAIR OF MINOR DEFECT IN REINFORCED CONCRETE 27-1
2704 PLACEMENT OF CONCRETE FOR BRIDGE DECKS 27-3
2705 REPLACEMENT, CONCRETE FOR THE SIDES AND SOFFITS
OF DIAPHRAGMS, AND SOFFITS OF DECKS 27-4
2706 SEALING OF CRACKS BY INJECTION OF EPOXY RESIN 27-7
2707 EPOXY MORTAR FOR REPLACEMENT OF SPALLED
CONCRETE 27-13
2708 EPOXY BONDING OF NEW CONCRETE TO OLD CONCRETE 27-15
2709 CEMENT GROUTING 27-16
2710 GUNTTING/SHORTCRETE 27-17
2711 REPLACEMENT/RECTIFICATION OF BEARING 27-19
2712 DISMANTLING OF CONCRETE WEARING COAT 27-20
2713 PAINTING OF STEEL BRIDGES 27-21
2714 PROTECTION OF STEEL STRUCTURES AGAINST
CORROSION 27-27
2715 REPAIR OF STEEL BEARINGS 27-29
2716 MEASUREMENT 27-33
2717 PAYMENT 27-34
SECTION 2700 –REPAIR OF STRUCTURES
2701. SCOPE
This Section covers the works in connection with the repair of RCC structures
such as sealing of cracks, repair and replacement of concrete, cement grouting,
gunting/shortcrete. Repair of structures shall be carried out in accordance with
the repair plans and these Specifications or as directed by the Engineer.
2702. GENERAL
Care shall be taken to ensure suitable mitigation measures against noise and
dust, pollution and damages to the environs whether temporary or
permanent and shall be taken as incidentals to work.
(2) Phasing
Adequate precautions shall be taken for safety of personnel, road users and
existing services, which, during execution, shall be considered as incidentals
to work. Persons working shall wear safety helmets and rubber gloves and
shall be provided with other safety measures as needed.
(2) Materials
(c) The cement content shall not be less than 400 kg/m3 of
compacted concrete.
(4) Supervision
(1) General
(2) Concrete
The concrete shall comply with Section 2000 depending upon the nature of
the work or as directed by the Engineer.
(3) Admixtures
The Contractor shall demonstrate by means of trial mixes the action of the
admixture he proposes to use for the Engineer's approval.
The cement content shall not be less than 400 kg/m3 of compacted concrete
and the water cement ratio shall not be greater than 0.40.
The total chloride ion content of the materials shall not be exceed 0.1
percent of the mass of cement. Calcium chloride or admixture containing
chloride salts shall not be used.
(1) General
(e) The total chloride ion content of the materials shall not
exceed 0.1 per cent of the mass of the cement. Calcium chloride or
admixtures containing chloride salts shall not be used.
(f) The materials shall not be removed from the store for
use in the works unless it is immediately required for mixing.
(i) The water cement ratio shall not exceed 0.4. The water
content shall be determined during Approval Tests, approved
by the Engineer.
(i) The tests shall be carried out in the presence of and to the
satisfaction of the Engineer who shall receive certified copies
of the results of all tests.
(ii) The mixer and method of mixing shall be the same as that to be
used in the works.
(iv) The funnel shall be fitted with a rubber bung and charged
with 6 litres of concrete. On the release of the bung the
concrete shall flow along the trough and the length of the flow
shall be measured. The minimum length of flow along the
trough for each test shall be 450mm, without signs of
segregation or bleeding.
After 24 hours the top plate shall be removed and the exposed surface
shall be lightly brushed with a stiff bristle brush to remove any surface
cement skin which may be covering voids. The exposed surface of the
concrete shall be examined for air-pockets, cracks and other defects.
The temperature of the mixer and material for each test shall be as
in Sub-clause 2705 (4) (b).
Three cubes from each batch mixed for placing in the Works shall be tested
for compressive strength.
(1) General
The work of epoxy adhesive for the Structural Concrete Bonding Process
shall conform to these Specifications.
(2) Personnel
(i) The mixing ratio of resin and hardener shall generally be between 1
to 1 and 2 to 1 by volume subject to manufacturer’s recommendation.
(ii) Neither the mixed epoxy adhesives nor their individual components
shall contain solvents and thinners.
* In the case of two component injection system where resin and hardener
get mixed at point of injection pot life at 25 degrees Celsius shall be not
greater than 15 min ± 10 minutes.
(5) Preparation
Entry ports shall be provided along the crack at intervals of not more than
the thickness of concrete at the location.
Surface seal material shall be applied to the face of the crack between the
entry ports. For through cracks, surface seal shall be applied to both faces.
Before proceeding with the injection, the surface seal material must gain
adequate strength with respect to concrete strength of the member and
injection pressure
Injection of epoxy adhesive shall begin at lowest entry port and continue
until there is an appearance of epoxy adhesive at the next entry port adjacent
to the entry port being pumped.
If port to port travel or epoxy adhesive is not indicated the work shall be
immediately stopped. In case the volume of the injected exceeds 2 litres for
a particular entry port, the work shall be stopped and the Specifications shall
be reviewed.
(8) Testing
(i) Viscosity test for resin and hardener and the mix - three
specimens each.
(iv) Shear test - six specimens each, 3 after 24 hours and the other
three after 72 hours of curing.
Where the resin and hardener get mixed at point of injection, the pot
life is not important and no tests may be required
Bond Test
Shear Tests
The Contractor shall obtain 5cm diameter initial core samples in the
first 50 linear metres. Thereafter, frequency of core sampling shall be
as specified or as agreed by the Engineer.
If the cores taken in first 5am length pass tests as specified above,
epoxy adhesive injection work at area represented by cores shall be
accepted.
At all times during the course of the work the Contractor shall keep
complete and accurate records and make available to the Engineer of
the pressure and ratio tests specified above so that the efficacy and
accuracy of the injection equipment is verified.
The pressure test shall be run for each injection unit at the beginning
and after break of every shift
(1) Material
(a) Formulation
The epoxy resins for use in the mortar shall be obtained from a reputed
manufacturer and the mortar shall be prepared in conformity with the
manufacturer's recommendations.
The Contractor shall carry out tests on the samples made out or
requirements indicated above. The sand content in the mortar shall be
in accordance with the desired consistency.
The resin and hardener shall be mixed before adding the dry filler. The
mixed ready to use mortar shall not contain lumps of unwetted filler and
should be uniform in colour. For a total weight of 1 kg or less, hand mixing
shall be sufficient. For quantities in excess of 1 kg, the component shall be
mixed for 3 minutes with a slow speed 400-600 rpm electric drill with a
Jiffy mixer. The stirrer shall be moved up and down and along the sides
until an even steak free colour is obtained. Whipping In an excessive
amount of air shall be avoided. If no power is available, a flat putty knife
may be used to reach into the corners of the can and hand mixing done for at
least 5 minutes.
Surface upon which epoxy is to be placed shall be free of rust, grease, oil,
paint, asphalt, loose or material, unsound concrete, dust or any other
deleterious material.
Since cured epoxy does not provide adequate bond with any material, all
overlay, whether epoxy or cement based, shall be done within pot life of the
base epoxy layer.
(4) Application
Epoxy primer coat shall be applied with the help of stiff nylon bristle
brushes or hard rubber rollers or spray gun depending upon the nature of
surface and extent of work area. As far as possible, the coating shall be
uniformly thick.
Before the primer coat is fully cured, epoxy mortar shall be applied by
means of trowels and floats. The interval between the application of primer
coat and epoxy mortar shall be approximately 15/30 minutes depending
upon the ambient temperature.
Seal coat shall be applied after 24 hours curing, after mild roughening of the
surface of the mortar.
(5) Coverage
The coverage of resin mix will depend on the system of resin used.
However, as a general guideline the coverage area shall be as under:
Tools and equipment are best cleaned immediately after use since the
removal of cured resin is difficult and time consuming. The bulk of resin
shall be removed using a scraper and remainder washed away completely
using solvents such as toluene, xylene or acetone. Equipments used for
epoxy shall always be cleaned before it hardens. Solvents used for this
purpose may be Acetone (flammable), Methy/Ethy/Kethone (flammable),
Methyle Chloride (non-flammable). Cured epoxies may be removed using
Methylene Chloride.
(7) Testing
Epoxy used for making mortar shall conform to all requirements and testing
procedures as laid down in Sub-clause 2706 (8).
Any skin contact with epoxy materials, solvents and epoxy strippers shall be
avoided. Epoxy resins and particularly epoxy hardeners (B component)
may cause a rash on the skin. The official toxicity classification on the
container labels should be looked for before starting work.
Rubber gloves with a cloth liner and protective clothing shall be worn.
Barrier creams are recommended but are not substitutes for protective
clothing. Eyes shall be protected where splashing could occur while
spraying or mixing. Good ventilation shall be ensured and inhalation of
vapours shall be avoided. If materials are sprayed, a respirator shall be
used.
All emptied, used buckets, rags and containers shall be removed from site.
These shall be stored in waste disposal bags and suitably disposed.
(1) Epoxy resin used bonding shall be obtained from a reputed manufactures.
The pot life of such bonding epoxy shall be more than 60 minutes at normal
temperature.
(2) The entire surface of the existing concrete member shall be thoroughly
cleaned by wire brush and then with compressed air to remove dust and
loose particles from the surface. Any crack or spalling of concrete shall be
seated by epoxy injection/epoxy mortar/grouting as decided by the
Engineer. A coating of suitable epoxy resin at the rate of 0.8 kg/sq.m
(minimum) shall then be applied on the surface of the existing concrete
members. Fresh concrete shall then be placed within the pot life of the resin
system.
(3) Testing
Epoxy used for bonding work shall satisfy the criteria mentioned in Clause
2706 (8).
Two concrete cubes of 150 mm size as per approved design mix shall be
placed, at a distance of 150 mm from each other. Epoxy resin system
suggested for bonding new to old concrete shall be applied on the opposite
faces of the cubes.
Fresh cement concrete cube of grade as per approved design mix shall be
water cement ratio of 0.4 or less in between two concrete cubes already
casted and epoxy resin applied bor bonding on a 12 mm thick steel spacer.
The assembly shall be cured in water for 28 days and steel spacer removed
thereafter.
(1) Material
(2) Preparation
The surface shall be cleaned with wire brush and compressed air 15 mm dia
and 150 to 200 mm deep holes along the length of the cracks at a spacing of
500 mm shall be drilled by wet drilling using rotary percussion drills.
Nipples shall be inserted in these holes.
(3) Proportioning, Mixing and Equipment for Grouting
Where the mixer and pump are combined in one unit, the dry material shall
be screened before mixing. If the mixer and pump are in separate units, the
grout shall pass through a screen before it enters the pump.
(4) Application
Highest practical pressure within the limits 0,10 - 0.40 N/mm 2 should be
used in order to force the surplus water from the grout. As the pressure may
be distributed hydraulically over considered areas, vigilance must be
exercised to prevent damage or the needless waste of grout. Grouting is to
be done by attaching a packer (consisting of expansible tube or rubber) to
the end of the grout supply pump through the holes and nipples.
(6) Testing
Percolation test done at the end of grouting operation shall give a value of
less than 2 lugions.
Note: For specialised treatment like polymer modified cementiitious grout
injection, manufacture's literature and Specification shall be
followed.
2710. GUNITING/SHOTCRETE
(1) Material
The gunite is a mixture of cement, sand and water. It shall comprise of 100
parts by weight of cement, 300 parts by weight of quartz sand, 35-50 parts
by weight of water and 2 parts by weight of approved quick setting
compound. In general, dry mix shortcrete shall be used.
Sand for guniting shall comply with the requirements stipulated in IS:383.
In general, sand shall neither be too coarse to increase the rebound nor too
fine to increase the slump. Sand shall have a moisture content between 3 to
6 per cent.
The grading of sand shall lie within the limits given in Table 27.1.
4.75 mm 95 – 100
2.36 mm 65 – 90
1.18 mm 45 – 75
0.600 mm 30 – 50
0.300 mm 10 – 22
0.150 mm 2–8
Water/cement ratio for guniting shall fall within the range 0.35 to 0.50 by
mass, wet enough to reduce the rebound. Drying shrinkage may be between
0.06 percent to 0.10 percent. The quick setting compound shall be added at
the nozzle with water just before guniting.
(2) Workmanship
The cement and sand shall be batched and mixed and conveyed through a
hosepipe with the help of compressed air. A separate line shall bring the
water under pressure. The cement, sand water mix shall be passed through
and intimately mixed in a special manifold and then projected at high
velocity to the surface being repaired. The density of gunite shall not be less
than 2000 kg/cu.m. The strength of gunite shall not be less than 25 N/mm 2.
For effective guniting, the nozzle shall be kept 60 to 150 cm away from the
surface, preferably normal to that surface. While enclosing reinforcement
bars during repairs, the nozzle shall be held closer at a slight angle and the
mix shall be wetter than the normal.
The defective concrete shall be cut out to the full depth till sound concrete
surface is reached. Under no circumstances the thickness of concrete to be
removed shall be less than clear cover to the main reinforcement. No square
shoulders shall be left at the perimeter of the cut-off portion and all edges
shall be tapered. Thereafter, all loose and foreign materials shall be
removed and the surface be sand-blasted to make it rough to receive
shotcrete after applying a coat of bonding epoxy as per recommendation of
the manufacturer at the rate of 1.0 kg per 1.5 sq.m. of surface area.
Water shall be sprayed to reduce the dust while removing concrete wearing
course with jack hammer. No other work shall be taken up under the span
when dismantling work is in progress.
(1) General
The Contractor shall use the Paint System as described in Sub-clause 2713
(2) for the repainting of the existing bridge structure, to complete the work
in at least 4 separate coats as specified below.
The painting of the structure shall include the removal of existing paint
coats and preparation of the metal surfaces, the application, protection and
drying of the paint coats; the protection of pedestrian, vehicular or other
traffic on or underneath the structure; the supply of all tools, equipment,
scaffolding, labour and materials (including paint as specified) necessary for
completion of the work involved in painting the surfaces of the structure.
The system shall provide a total minimum dry film thickness of 200
microns, and shall include for all approved thinners and cleaning agents
necessary for the completion of the work in accordance with these
Specifications.
Where the Contractor requires to store paint, the paint shall be stored in a
secure paint store and ventilation provided as necessary to maintain the
temperature of the paint store at a temperature between 5 and 25 degrees
Celsius. If at any time whilst within the Contractors possession paint is
allowed to exceed these limits, the paint shall be removed from the Works at
the Contractors expense and the cost of the paint, as determined by the
Engineer, shall be debited to the Contractor.
Paint, which has not been used within 12 months of the date of manufacture
or the shelf life recommended by the manufacturer, whichever is the lesser,
shall not be used in the works.
At the end of each working period, paints which shall have exceeded their
"pot life" by the commencement of the next working period shall be mixed
with fresh paint but shall be removed from the works at the Contractor's
expense.
Other types of paints shall be returned to store and kept in sealed containers
with not more than 10% usage.
The Engineer shall have access to the Contractors secure paint store at all
times.
The surface shall be free from dust and grit and dry and ready for
painting.
Mill scale, rust and foreign matter shall be removed to the extent that
only slight traces are remaining as stains in the form of spots and
strips. The surface shall be cleaned with a vacuum cleaner, dry clean
compressed air or a clean brush.
Abrasives used for blast cleaning shall be either clean, dry sand,
mineral grit, steel shot or steel grit at the option of the Contractor and
shall be of a grading suitable to produce satisfactory results. The use
of other abrasives shall be permitted only with the approval of the
Engineer.
In all cases where paint coats only are to be restored, the edges of paint
coatings shall be bevelled back into sound paint
The Contractor shall provide 500 ml samples for laboratory testing purposes
of each type of paint to be used in the works. The samples shall be taken
from the first batch of each type of paint delivered to the site.
When instructed by the Engineer, the Contractor shall also provide a sample
of any replacement batch of paint.
Unless permitted by the Engineer, painting, except for procedure trials, shall
not start until the Engineer confirms that the samples are satisfactory.
The Contractor shall provide 500 ml tins with lids for the samples at the
start of painting or before any procedure trials. The quantity of containers
supplied shall be sufficient to avoid any delay in taking samples throughout
that work.
The Contractor shall also supply details of the overall wet film thickness of
each coat to be applied and of the coverage rates, in m 2,/litre, for each coat
of paint to be used in the works.
The calculations shall be based on the volume solids plus an allowance for
surface roughness, uneven application and wastage.
Prior to the commencement of painting on any coat, the Contractor shall
carry out painting procedure trials, in the presence of the Engineer, on a
suitably prepared surface up to 10 square metres or as agreed with the
Engineer, employing the paint, labour and equipment to be used in the
works.
The Contractor shall demonstrate his ability to apply the paint in accordance
with the Specification and manufacturers recommendations and shall obtain
the Engineer's approval to commence the application of a particular coat
before starting.
All paints shall be prepared and applied in strict accordance with the
manufacturers instructions and no thinners or cleaners shall be employed
other than those recommended by the manufacturer.
The Contractor shall execute the works only when the conditions at the site,
including temperature and humidity, are suitable for applying the paint to be
used and ensure that the structure to be painted is fully accessible to the
Contractor and to the Engineer for inspection prior to, during and after
painting operations.
(vii) When wind borne dust may have a harmful effect on the paint.
Paint shall be applied to surfaces, which have been prepared and cleaned in
accordance with the Specification and approved for painting in advance by
the Engineer.
Wet film thickness gauges shall be used where practicable to check that the
wet film thickness for each coat is not less than:
During the application of a paint system, the Contractor shall ensure that the
progressive total thickness of the applied coats shall allow the specified
minimum total DFT to be attained without exceeding overall the proposed
wet film thickness by more than 20%. The local dry film thickness for the
primer shall not exceed the specified minimum dry film thickness by ore
than 30% and for other paints by more than 75%.
Surfaces to be painted shall be free from moisture, dust, grease or any other
deleterious materials that would prevent the bond of the succeeding
application.
Each coat of the specified paint system shall be generally free from surface
defects, including cratering, pin-holing, blistering, rivalling, sagging,
bittiness, dry spray and cissing, as defined in BS 2015 "Glossary of Paint
Terms". Any deficiencies in the applied coat shall be rectified to the
satisfaction of the Engineer before the application of a subsequent coat. The
finished system shall have an even and uniform appearance.
Unless otherwise agreed with the Engineer, 1 no. Stripe Coat shall be
applied over all welds and fasteners including washers and to all external
corners excepting those of RHS members. The stripe coat shall be applied
over the primer.
Exposure Time for prepared steel surfaces and over-coating times for paints
shall be as follows:
(ii) Primed surfaces shall have the following coat applied within 7 days
or as recommended by the paint manufacturer.
(iii) Subsequent coats shall be applied within 14 days or such lesser time
as recommended by the paint manufacturer.
(9) Inspection
(1) General
Protective systems include grease and felt systems, grease packing and oil
systems.
The Contractor shall use the protective system as described in this Clause
for the existing suspension cables and hangers.
The protective system to the suspension cables and hangers shall include the
removal of existing protective system, either in whole or in part as indicated
in the contract, the preparation of the surfaces of the steel ropes, and the
application of the new protection system.
(b) A tar-felt sheet cover. The cover shall be fixed to prevent the
entry of water and shall be continuous spirally lapped in a method
approved by the Engineer.
The surfaces of the wire ropes shall be prepared by removing existing cover
in whole or in part as indicated in the contract, then cleaning the exposed
surface of the wire ropes to remove dirt, hardened grease and surface rust.
Broken or rusted wires and other damages shall be brought to the attention
of the Engineer before any further work is carried out on the affected area.
(4) Protective System for Bearings, Inside Cable Saddles, Hanger Saddles
and Hanger Sockets
Oil of an approved make shall be applied to all pins of top and bottom
hangers and bridge bearings. Cracks around any pins or bearing or plates
shall be brought to the attention of the Engineer before any further work is
carried out on the affected area.
The Contractor shall make good any damage to the original protective
system arising from his execution of the works.
(a) General
The work on the steel bearings comprises the repositioning of the free
roller bearings and the re-setting of the fixed bearings in the Bridges.
In the course of these operations jacking up of the bridge shall be
required to the method as provided or as directed by the Engineer. To
re-set the fixed bearings at their correct vertical load, additional
jacking operations shall be necessary at the free bearing location to
determine the magnitude of the vertical load.
Any oil or grease on the plinth where bearings are to be re-set shall
be removed with an approved de-greasing compound which shall
then be rinsed off with clean water. All loose particles of concrete,
rust, any dust on the plinths shall be removed by suction or by
using a properly filtered oil-free airline.
(a) General
(b) Material
(ii) For cementitious bedding mortars, the sub-strate shall be flushed clean
with water two hours before placing and maintained wet until placing
commences.
Any free standing water on the surface of the sub-strate shall be removed
before placing the mortar. The underside of the base plate shall be clean and
free from loose rust and loose mill scale at the time of bedding.
(iii) For resinous bedding mortars the sub-strate shall be dry, free from
loose dirt and dust and shall meet the conditions specified by the
manufacturer. The underside of the base plate shall be clean and free
from loose rust and loose mill scale at the time of bedding.
The mortar shall be placed in its final position within one hour
from its time of discharge from the mixer or lesser period as
specified by the manufacturer.
Only full packs of mortar or sub-packs as presented by the
supplier shall be mixed On-site proportioning shall not be
permitted.
(i) Mortar shall not be used in the Works until it has been approved by the
Engineer. The Contractor shall provide the Engineer with copies of
the manufacturer's Specification.
The mortar for each flow test shall be batched in one load
strictly according to the manufacturer's instructions.
Flow tests shall be conducted between concrete and a rusty
steel plate at ambient temperature of 5°C. The flow
characteristics shall be assessed with the rusty steel plate on
top, and with the pre-cast concrete slab on the bottom. The
surface of the concrete slab shall be washed thoroughly with
water and all traces of surface water removed.
The size of the test apparatus is to represent the actual site
condition. The mortar shall be poured in one corner of the
apparatus until the level of the mortar has reached at least 10
mm above the underside of the top plate. After 24 hours the
top plate shall be removed and the exposed surface lightly
brushed with a stiff bristle brush to remove any surface skin
which may be covering voids. The bedding mortar formed
shall be free from significant voids, cracks and other defects, at
both 5°C and 20°C.
If difficulty is experienced in achieving a satisfactory flow for
cementitious mortars the water content of the mix shall be
adjusted and the test described above repeated. The mortar
shall be rejected if further adjustments of the water content do
not produce an acceptable result
(iv) Compressive strength tests for resinous bedding mortars shall comply
with BS 6319: Part 2 and shall be carried out on six 40 mm cubes as
shown in Table 27.4.
2716. MEASUREMENT
The Measurement for minor repairs of defective concrete shall be made in cubic
meters. Measurement for replacement concrete shall be made in cubic meters.
Measurement for sealing cracks and injection shall be made by weight (in kg) of
epoxy consumed for grouting. Provision of nipples required for grouting shall be
measured in numbers.
2717. PAYMENT