Method Statement 07
Method Statement 07
I
LIFTING SLING
(BY OTHERS)
C C
D SCHACKLE -
12 TON X 2 NOS
(BY OTHERS)
SPREADER BEAM - 20
TON SWL (BY OTHERS)
D SCHACKLE -
12 TON X 2 NOS
(BY OTHERS)
REV. DATE DESCRIPTION REV.BY
DOCUMENT STATUS:
A WORK MAY PROCEED.
B REVISE & RESUBMIT. WORK MAY PROCEED
B SUBJECT TO INCORPORATION OF CHANGES. B
C REVISE & RESUBMIT. WORK MAY NOT PROCEED.
LIFTING SLING - 10M LONG. LIFTING SLING - 10M LONG.
6 TON X 4 NOS 6 TON X 4 NOS D REVISION NOT REQUIRED. WORK MAY NOT PROCEED.
(BY OTHERS) (BY OTHERS)
SIGNATORY DATE:
UNIVERSAL ENGINEERING SERVICES LLC.
P.O.Box No: 2688, RUWI-112,
SULTANATE OF OMAN
TEL: +96824597531,+96824597537
FAX: +96824597514
e-mail : uesoman@omantel.net.com
I
SWITCH GEAR ENCLOSURE
ENCLOSURE WEIGHT : 15 TON JACK THE CRANE IN
APPROPRITE LOCATION AS
PER CRANE SUPPLIER
E3
ATTACH LIFTING GEARS TO
CRANE AND ENCLOSURE AS PROJECT TITLE:
PER LIFTING DRAWING CE3000D5 GENSET ENCLOSURE AND
CONTAINER PACKAGE
A A
SHEET TITLE:
M
METHOD STATEMENT FOR UNLOADING AND
PLACEMENT OF ALL THE CONTAINERS
D SCHACKLE - 6.5
COG 859
TON X 4 NOS PREPARED: PS DATE: 20.04.2020
(BY OTHERS)
DESIGNED: IM PROJECT NO. 300952
LOW BED TRAILER - 03 11
2
APPROVED: IM SCALE: 1:1
CUSTOMER: UES REV.: 00
COG 5750 DWG. NO.: SHEET NO.: 07 of 14
ACE-MS-300952-001
6 I 5 I 4 3 I 2 I 1