Section – 4, Bidding Forms (Price Schedules) 4-1

Letter of Price Bid


[Bidder’s Letterhead]

Date: ..........................

ICB No.: CHTHSS– 073/74-01

Invitation for Bid No.: CHTHSS– 073/74-01

To: [. . . insert complete name of the employer . . .]

We, the undersigned, declare that:

(a) We have examined and have no reservations to the Bidding Document, including Addenda
issued in accordance with Instructions to Bidders (ITB) 8.

(b) We offer to design, manufacture, test, deliver, install, pre-commission, and commission in
conformity with the Bidding Document the following Plant and Services: [. . . insert narrative . . .]

(c) The total price of our Bid, excluding any discounts offered in item (d) below is the sum of

[amount of foreign currency in words], [amount in figures], and [amount of local currency in words],
[amount in figures]

The total bid price from the Grand Summary (Schedule No. 8 should be entered by the Bidder inside this box.
Absence of the total bid price in the Letter of Price Bid may result in the rejection of the bid.

(d) The discounts offered and the methodology for their application are as follows: [. . . insert
discounts and methodology for their application if any . . .]

(e) Our Bid shall be valid for a period of [. . . insert bid validity period as specified in ITB 20.1 of the BDS . .
.] days from the date fixed for the submission deadline in accordance with the Bidding
Documents, and it shall remain binding upon us and may be accepted at any time before the
expiration of that period.

(f) If our Bid is accepted, we commit to obtain a performance security in accordance with the
Bidding Document.

(g) We understand that this bid, together with your written acceptance thereof included in your
notification of award, shall constitute a binding contract between us, until a formal contract is
prepared and executed.

(h) We understand that you are not bound to accept the lowest evaluated bid or any other bid that
you may receive.

Bidding Document for Substation Package-2 for 220/132/33kV Chilime Hub GIS Single-Stage: Two-Envelope
new substation (Part-I) and 220(Hybrid)/132/33kV
Trishuli-3B Hub AIS new substation (Part-II) under
220kV Chilime-Trishuli Transmission System
Project
Section – 4, Bidding Forms (Price Schedules) 4-2

Name ...........................................................................................................................................
In the capacity of ..........................................................................................................................
Signed .........................................................................................................................................
Duly authorized to sign the Bid for and on behalf of ......................................................................
Date .............................................................................................................................................

Bidding Document for Substation Package-2 for 220/132/33kV Chilime Hub GIS Single-Stage: Two-Envelope
new substation (Part-I) and 220(Hybrid)/132/33kV
Trishuli-3B Hub AIS new substation (Part-II) under
220kV Chilime-Trishuli Transmission System
Project
Section – 4, Bidding Forms (Price Schedules) 4-3

Price Schedules
PREAMBLE
General
1. The Price Schedules are divided into separate Schedules as follows:
Schedule No. 1: Plant and Equipment including mandatory Spares to be supplied from abroad.
Schedule No. 2: Plant and Equipment including mandatory Spares to be supplied from within
Employer's Country
Schedule No. 3:Local Transportation, Insurance and other incidental services (including port
clearance etc.) applicable for supply of Plant & Equipment.
Schedule No. 4: Installation Services
Schedule No. 5a: Training Charges for Training to be imparted abroad
Schedule No. 5b: Training Charges for Training to be imparted within Employer’s Country.
Schedule No. 5c: Maintenance Charges for Communication Equipment
Schedule No. 6a: Type Test Charges for Type Tests to be conducted abroad
Schedule No. 6b: Type Test Charges for Type Tests to be conducted in Employer’s Country
Schedule No. 7: Taxes and Duties
Schedule No. 8: Grand Summary
Schedule No. 9: Recommended/Optional Spare Parts
2. The Schedules do not generally give a full description of the plant to be supplied and the services
to be performed under each item. Bidders shall be deemed to have read the Employer’s
Requirements and other sections of the Bidding Document and reviewed the Drawings to
ascertain the full scope of the requirements included in each item prior to filling in the rates and
prices. The entered rates and prices shall be deemed to cover the full scope as aforesaid,
including overheads and profit.

3. If bidders are unclear or uncertain as to the scope of any item, they shall seek clarification in
accordance with ITB 7 prior to submitting their bid.

Pricing

4. Prices shall be filled in indelible ink, and any alterations necessary due to errors, etc., shall be
initialed by the Bidder.
As specified in the Bid Data Sheet and Special Conditions of Contract, prices shall be fixed and
firm for the duration of the Contract, or prices shall be subject to adjustment in accordance with
the corresponding Appendix (Price Adjustment) to the Contract Agreement.

5. Bid prices shall be quoted in the manner indicated and in the currencies specified in the
Instructions to Bidders in the Bidding Document.
For each item, bidders shall complete each appropriate column in the respective Schedules,
giving the price breakdown as indicated in the Schedules.
Prices given in the Schedules against each item shall be for the scope covered by that item as
detailed in Section 6 (Employer’s Requirements) or elsewhere in the Bidding Document.

Bidding Document for Substation Package-2 for 220/132/33kV Chilime Hub GIS Single-Stage: Two-Envelope
new substation (Part-I) and 220(Hybrid)/132/33kV
Trishuli-3B Hub AIS new substation (Part-II) under
220kV Chilime-Trishuli Transmission System
Project
Section – 4, Bidding Forms (Price Schedules) 4-4

6. Payments will be made to the Contractor in the currency or currencies indicated under each
respective item.

7. When requested by the Employer for the purposes of making payments or part payments, valuing
variations or evaluating claims, or for such other purposes as the Employer may reasonably
require, the Contractor shall provide the Employer with a breakdown of any composite or lump
sum items included in the Schedules.

Bidding Document for Substation Package-2 for 220/132/33kV Chilime Hub GIS Single-Stage: Two-Envelope
new substation (Part-I) and 220(Hybrid)/132/33kV
Trishuli-3B Hub AIS new substation (Part-II) under
220kV Chilime-Trishuli Transmission System
Project
Section – 4, Bidding Forms (Price Schedules) 4-5

Schedules of Rates and Prices

Schedule No. 1: Plant and Equipment including mandatory Spares to be supplied from abroad.
Schedule No. 2: Plant and Equipment including mandatory Spares to be supplied from within
Employer’s Country
Schedule No. 3:Local Transportation, Insurance and other incidental services (including Port
Clearance) applicable for supply of Plant & Equipment
Schedule No. 4: Installation Services
Schedule No. 5a: Training Charges for Training to be imparted abroad
Schedule No. 5b: Training Charges for Training to be imparted within Employer’s Country.
Schedule No. 5c: Maintenance Charges for Communication Equipment
Schedule No. 6a: Type Test Charges for Type Tests to be conducted abroad
Schedule No. 6b: Type Test Charges for Type Tests to be conducted in Employer’s Country
Schedule No. 7: Taxes and Duties
Schedule No. 8: Grand Summary
Schedule No. 9: Recommended/Optional Spare Parts

Bidding Document for Substation Package-2 for 220/132/33kV Chilime Hub GIS Single-Stage: Two-Envelope
new substation (Part-I) and 220(Hybrid)/132/33kV
Trishuli-3B Hub AIS new substation (Part-II) under
220kV Chilime-Trishuli Transmission System
Project
Specification No. Schedule-1 Page 1 of 145

Package-2 for 220/132/33kV Chilime Hub GIS new substation (Part-I) and 220(Hybrid)/132/33kV Trishuli-3B Hub AIS new substation (Part-II) under 220kV Chilime-Trishuli Transmission System Project

(Schedule of rates and prices)

Bidder's Name & Address:

Plant and Equipment including mandatory Spares to be supplied from abroad

1 2 3 4 5 6 7 8 9=6x8
Sl. No. Item Description Country of Type & Unit Quantity Currency Unit CIP Entry Border Point / Total CIP Entry Border Point
Origin Designation (As per ITB CIF Port of Entry Price (^), as / CIF Port of Entry Price (^),
19.1) applicable as applicable

I. 220/132/33kV CHILIME HUB GIS new Substation


(Package-2, Part-I)

PART - A: OWNER ASSESSED QUANTITIES


A POWER TRANSFORMER
A.1 1-Phase Auto Transformer
53.33MVA, 220/√3 / 132/√3 / 33kV Single Phase Auto
a) Nos. 7
Transformer (without transformer Oil)
Insulating oil for 53.33MVA , 220/132/33 KV, 1-phase
b) Autotransformer (* 1Lot = Oil for 1 Autotransformer ) Lot* 7

c) 33kV Current transformer (NCT) for autotrasnformer No 2

A.2 POWER TRANSFORMER


50 MVA, 132 /33kV Three Phase Power Transformer
a) Nos. 1
(without transformer Oil)
Insulating oil for 50MVA , 132/33 KV, 3-phase Power
b) Transformer (* 1Lot = Oil for 1 Autotransformer ) Lot* 1

A.3 Testing & Maintenance Equipments


a) Oil Storage Tank of 20KL No. 1
b) Transformer Oil Filtration plant (6KLPH) No 1

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-1 Page 2 of 145

B) LT Transformer
a) 630KVA, 33/0.400 kV Nos. 2

C 245 KV EQUIPMENTS
C1 245KV GIS Equipment
1.1 245kV, SF6 GIS Bus Bars Module as per section project

a) 3000A, 40kA for 1 sec Sets 2


1.2 245kV, SF6 GIS Bus Coupler feeder bay Module as per
section project
a) 3000A, 40kA for 1 sec Sets 1
1.3 245kV, SF6 GIS Line feeder bay Module as per section
project
a) 1600A, 40kA for 1 sec Sets 2
1.4 245kV, SF6 GIS spare Line feeder bay Module as per
section project
a) 1600A, 40kA for 1 sec Sets 1
1.5 245kV, SF6 GIS ICT feeder bay Module as per section
project
a) 1600A, 40kA for 1 sec Sets 2
1.6 245kV, SF6 GIS Auxiliary Bus Module as per section
project to connect spare unit of Transformer
a) 1600A, 40kA for 1 sec Set 1
1.7 SF6 Gas Insulated Bus Duct (GIB) outside GIS Hall
alongwith associated support structure and accessories
(for Transformer bays)
a) 1600A, 40kA for 1 sec. Single Phase Mtr. 460
1.8 SF6 Gas Insulated Bus Duct (GIB) outside GIS Hall
alongwith associated support structure and accessories
(for Line bays)
a) OPTION-I
1600A, 40kA for 1 sec. Single Phase Mtr. 225
b) OPTION-II
1600A, 40kA, 1sec three phase Mtr. 75
Note : Bidder is required to quote for either option-I or
Option-II
1.9 220kV, SF6 to Air Bushing alongwith associated support
structure (for Transformer bays)
a) 1600A, 40kA for 1 sec. Single Phase Nos. 7
1.10 220kV, SF6 to Air Bushing alongwith associated support
structure (for line bays)

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-1 Page 3 of 145

a) OPTION-I
1600A, 40kA for 1 sec. Single Phase Nos. 9
b) OPTION-II
1600A, 40kA, 1sec three phase Nos. 3
Note : Bidder is required to quote for either option-I or
Option-II

C.2 245KV Outdoor AIS Equipment


1.1 216 KV Surge Arrester (1-phase) Nos. 16
1.2 4400pF, 245 kV Capacitive Voltage Transformer (1- Nos. 9
1.3 Phase)
245kV Bus Post Insulator (1-Phase) Nos. 9

D 145kV Equipment
D.1 145KV GIS Equipment
1.1 145kV, SF6 GIS Bus Bars Module as per section project

a) 2000A, 40kA for 1 sec Set 2


1.2 145kV, SF6 GIS Bus Coupler feeder bay Module as per
section project
a) 2000A, 40kA for 1 sec Set 1
1.3 145kV, SF6 GIS Line feeder bay Module as per section
project
a) 1250A, 40kA for 1 sec Sets 4
1.4 145kV, SF6 GIS Spare Line feeder bay Module as per
section project
a) 1250A, 40kA for 1 sec Set 1
1.5 145kV, SF6 GIS ICT feeder bay Module as per section
project for 220/132 kV Transformer
a) 1250A, 40kA for 1 sec Set 2
1.4 145kV, SF6 GIS ICT feeder bay Module as per section
project for 132/33 kV Transformer
a) 1250A, 40kA for 1 sec Set 1
1.6 145kV, SF6 GIS Auxiliary Bus Module as per section
project to connect spare unit of Transformer
a) 1250A, 40kA for 1 sec Set 1
1.7 SF6 Gas Insulated Bus Duct (GIB) outside GIS hall
including Bus Duct support structure and associated
a) 1250A, 40kA 1sec single phase (for 7x53.33MVA 1-
Mtr 395
Phase Transformer bays)
b) 1250A, 40kA 1sec three phase Mtr 300
1.8 145kV, SF6 to Air Bushing alongwith associated support
structure
a) 1250A, 40kA 1sec three phase Set 5
b) 1250A, 40kA 1sec single phase Set 7

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-1 Page 4 of 145

D.2 145kV Outdoor AIS EQUIPMENT


1.0 120 kV Surge Arrestors (1-Phase) Nos. 25
2.0 8800pF, 145 kV Capacitive Voltage Transformer (1-
Nos. 15
Phase)
3.0 8800pF, 145 kV Capacitive Voltage Transformer (1-
Nos. 15
Phase) (for tariff metering)
4.0 145KV Bus Post Insulator Nos. 9

E 72.5kV EQUIPMENT
1.1 72.5 kV, 1250A, 25kA Circuit Breaker (3-phase) with No. 1
support structure
1.2 72.5 kV, 1250A, 25kA Isolators with earth switch (3- No. 1
phase, DBR type)
1.3 72.5kV, 50A, 25 kA with 120% extended rating CT (1- Nos. 3
phase)
1.4 72.5kV PT (1-phase) Nos. 3
1.5 72.5 kV BPI (1-phase) Nos. 6

F 33kV Equipments
1.1 33 kV, 630A, 25kA Isolators with out earth switch (3- No. 1
phase, DBR type)
1.2 30 kV Surge Arrestors (1-phase) Nos. 3
1.3 36 kV BPI (1-phase) Nos. 3
1.4 36 kV HG Fuse along with support insulator (1-phase) Nos. 3

G 33kV, 25 kA (3 Phase) Indoor switch gear panel


including control, relay & protection
i) 33kV Line bay Module Nos 2
ii) 33kV Incomer Transformer Module Nos 1
iii) 33kV LT Transformer Module Nos 1
iv) 33kV Bus Sectionalizer Module Nos 1
v) 33kV Bus PT Module Nos 2

H Testing & Maintenance Equipment for GIS


1.1 SF6 Gas processing Unit Set 1
1.2 Partial Discharge Monitoring System (Portable type) Set 1
1.3 Dew Point Meter Set 1
1.4 SF6 Gas Leak Detector Set 1
1.5 Portable Ladder with adustable height as per TS Nos. 1

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-1 Page 5 of 145

1.6 EOT crane for 220kV GIS Hall Set 1


1.7 EOT crane for 132kV GIS Hall Set 1

I RELAY PANELS (WITH AUTOMATION)


1 245kV
1.1 Circuit Breaker Relay Panel
a) CB Relay Panel With Auto Reclose Nos. 3
b) CB Relay Panel Without Auto Reclose Nos. 3
1.2 Line Protection Panel
Line Protection Panel with Distance Protection and
a) Nos. 3
Current Differential Protection at Chilime GIS End
1.3 Transformer Protection Panel (For both HV & MV side) Nos. 2

1.4 Bus Bar Protection Panel set 1


2 145kV
2.1 Circuit Breaker Relay Panel
a) CB Relay Panel With Auto Reclose Nos. 5
b) CB Relay Panel Without Auto Reclose Nos. 4
2.2 Line Protection Panel

Line Protection Panel with Current Differential Protection


a) Nos. 5
and Back up O/C & E/F Protection at Chilime GIS End

Line Protection Panel housing two nos. Current


b) Differential Protection relays & accessories at Rasuagadi Nos. 1
HPP End

Line Protection Panel housing one no. Current Differential


c) Nos. 1
Protection relay & accessories at Upper Sanjen HPP End

Line Protection Panel housing one no. Current Differential


d) Nos. 1
Protection relay & accessories at Lower Sanjen HPP End

2.3 Transformer Protection Panel (For both HV & MV side) Nos. 1

2.4 Bus Bar Protection Panel set 1

3 Other/Common equipments Pertaining to C & R System

a) Time Synchronisation Equipment No. 1


b) Relay Test kit No. 1

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-1 Page 6 of 145

J SUBSTATION AUTOMATION
Substation Automation System as per Technical
1
Specification:
a) 220kV System (Nos. of bays) Nos. 6
b) 132 kV System (Nos. of bays) Nos. 9
c) BCU for auxilary system set 1
d) 33 kV HT Indoor Switchgear set 1
K Digital Protection Coupler& PBAX
a) Digital Protection Coupler* Nos 2
b) PBAX with following configuration as per TS Set 1
i 2 wire subscriber interface card with capacity 32 local
subscribers (along with 32 nos. Instruments)
ii) E-1 interface with 2 trunks G-703
iii) 2 wire interface with 1 trunk (For PSTN)
*Digital Protection coupler for 220kV Chilime Hub -
Trishuli-3B D/c Line have been considered at respective
substation end.
L LT Switchgear (As per Technical specification)
a 400V Main switchboard Set 1
b 400V ACDB Set 1
c 400V MLDB Set 1
d 400V Emergency LDB Set 1
e 220V DCDB Sets 2
g 48V DCDB Set 2

M Batteries
a 220V
i 800 AH Nos 2
b 48V
i 600AH Nos 2

N Float Cum Boost Battery Charger


a 220V Float Cum Boost Battery Charger
i 90A/90A Nos 2
b 48V Float Cum Boost Battery Charger
i 90A/90A Nos 2

O Diesel Generator with control Panel


a 250 kVA Set 1

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-1 Page 7 of 145

P Fire Protection System


a Portable /Trolley/Wheel mounted extinguishers
i 9 litre water type Nos 2
ii 50 litre foam type Nos 2
iii 4.5 kg CO2 type Nos 10
iv 4.5 kg Dry Chemical Power (DCP) type Nos 6
b Smoke detection system Set 1
c Fire detection and Alarm System Set 1

Q Cables along with clamps, glands, lugs and straight


joints etc.
a 33kV HT XLPE Power Cable alongwith accessories and
termination equipments
i) 1Cx600 Sq.mm KM 2.5
ii) 1Cx300 Sq.mm KM 2
b Power Cables - (1.1kV grade)
i 3.5Cx300 sqmm (XLPE) cable for filter Machine along
KM 1
with 2 nos outdoor receptacles -250A

R Air conditioning
High wall type split AC unit of 2 TR capacities for control
1 Nos. 25
room, relay room and battery room

S STEEL STRUCTURES (Tower,Gantry structures&


Equipment support structures)
a Lattice/pipe Structure for towers,beams and equipments
including peak plates/pack washers and guest paltes
including foundation bolts(nuts,washers,MS plate welded
at the bottom)
i) Lattice stucture & foundation bolts MT 90
ii Pipe structure & foundation bolts MT 10
b Fastners for towers,beams and equipment support
MT 6
strcutures

T Communication Equipment for Chilime Hub GIS


1.0 Telecom Equipments
SDH Equipment (STM-4 MADM upto 5 MSP protected
A1
directions)
(i) Base Equipment (Common cards, Cross Connect/control cards,
optical base cards, power supply cards, power cabling, other
Nos. 1
hardware and accessories including sub racks, patch cord, DDF etc
fully equiped excluding (ii) & (iii) below

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-1 Page 8 of 145

(ii) Optical Interface Cards/SFP


a S4.1 SFP Nos. 6
b L4.1 SFP Nos. 2
c L4.2 SFP Nos.

(iii) Tributary cards


a E1 Interface card (Min.16 interfaces per card) Set 2
b Ethernet Interface 10/100 Base T with Layer-2 switching (Min 8
Nos. 2
Interfaces per card)

B Equipment Cabinets No. 1

2.0 VOIP telephone instrument with one common switch (min. 8


Nos. 2
port)

SUB TOTAL PART-A

PART-B: VENDOR ASSESSED QUANTITIES

Erection Hardware :-Insulator strings, Disc Insulators,


Hardware, conductor, bus-bar materials, cable trays,
clamps, spacers, connectors including conectors for Auto
A
Transformer , Junction box, earthwire, earthing material
risers, buried cable trenches/pipe of equipment & lighting,
all accessories etc. for the following:
220 kV DM-type layout for GIS termination
1
arrangement
1.1 Line Bay Set 3
1.2 Transformer Bay Sets 2

132 kV DM-type layout for GIS termination


2
arrangement
1.1 Line Bay Sets 5
1.2 Transformer Bay Sets 3

3 33 KV
3.1 Line Bay Set 2
3.1 Transformer Bay Set 1
3.3 LT Transformer Bay Set 1

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-1 Page 9 of 145

Erection Hardware etc for 72.5kV equipments & LT


4 Set 1
Transformer connection

For spare unit of 220/132/33kV auto transformer


connection through auxiliary buses, Neutral formation and
delta formation (for two banks): Required 245kV BPI,
132 kV BPI, 72.5kV BPI for tertiary auxilary bus & delta
B formation, 36kV BPI for Neutral formation & Neutral Set 1
auxiliary bus including Al tube, bus-bar materials,
clamps, spacers, connectors, including equipment
connectors, support structures , Earthing of spare unit as
per technical specification

C Ventilation & heating System


Ventilation & heating system (as per technical
2
specification)
(i) 220kV GIS Hall LS 1
(ii) 132 kV GIS Hall LS 1

D Illumination System
1.1 Substation Lighting
Control Room cum administrative building illumination
(i) LS 1
(1000 sqmm)
(ii) 220kV GIS Building (620 sqmm) LS 1

(iii) 132kV GIS Building (350 sqmm) LS 1

(iv) 33kV Indoor Switchyrad Panel Room (160 sqmm) LS 1


(v) Fire Fighting Pump house (100 sqmm) LS 1
(vi) Outdoor Switchyard Lighting LS 1
(vii) Street Lighting LS 1
(viii) Occupancy sensor LS 1
1.2 Transit Camp (420 sqmm) LS 1
1.3 Township Area (Staff Quarter area) Lighting LS 1
(i) B type (250 sqmm) LS 1
(ii) C type (300 sqmm) LS 1
(iii) D type (200 sqmm) LS 1
1.4 Security room (10 sqmm) LS 1
1.5 Car parking shed (for 10 cars) LS 2

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-1 Page 10 of 145

E Fire Protection System (as per technical set 1


1 Specification)
Pumping arrangement inside pump house set 1
2 Hydrant system outside the Pump House. set 1
3 HVW spray system & Hydrant system for Transformer :
53.33MVA, 220/132 kV Single Phase Auto Transformer
a nos 7

b 50 MVA,132/33 kV Three phase transformer nos 1

F POWER & CONTROL CABLES


i For 220/132/33kV Chilime Hub GIS Substation:
a Power Cables(PVC) - (1.1kV grade) LS 1
b Power Cables (XLPE) - (1.1kV grade) LS 1
c Control Cable (PVC) - (1.1kV grade) LS 1
Cable glands, lugs & straight through joints for Power & Control LS 1
d
cables
ii For 132kV Upper Sanjen HPP Switchyard:
a Power Cables(PVC) - (1.1kV grade) LS 1
b Control Cable (PVC) - (1.1kV grade) LS 1
Cable glands, lugs & straight through joints for Power & Control LS 1
c
cables
iii For 132kV Lower Sanjen HPP Switchyard:
a Power Cables(PVC) - (1.1kV grade) LS 1
b Control Cable (PVC) - (1.1kV grade) LS 1
Cable glands, lugs & straight through joints for Power & Control LS 1
c
cables
iv For 132kV Lower Rasuagadi HPP Switchyard:
a Power Cables(PVC) - (1.1kV grade) LS 1
b Control Cable (PVC) - (1.1kV grade) LS 1
Cable glands, lugs & straight through joints for Power & Control LS 1
c
cables

G
Visual Monitoring System for watch & ward as per LS 1
technical specification

H Earthing and lightning protection including necesaary


connectors/connections, risers etc. complete in all
respect
i Earth Conductor (copper) LS 1
ii Earth Rod (copper clad steel) LS 1
iii Equipment for lightning protection LS 1

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-1 Page 11 of 145

I SUBSTATION AUTOMATION
a Integration of all 220/132kV Bays under present scope LS 1
with the SCADA of SIEMENS (SINAUT Spectrum) at Load
Dispatch Centre, Kathmandu including supply of
Hardware, Software, accessories etc. as per TS Section
Project.
SUB TOTAL PART-B

PART-C: MANDATORY SPARES


(I) Mandatory Spare List for Autotransformer
A.
For 53.33MVA , 220/132/33 KV, 1-phase Autotransformer
a) Bushing of each rating with metal parts & gaskets and
Set 1
lifting tools
b) Cooler fan with Motor No. 1
c) Buchholz Relay(Main Tank) complete with floats and
Set 1
contacts
d) Local and Remote WTI with sensing device and
Set 1
contact(each)
e) Magnetic oil level gauge No. 1
f) Strarters, contactors,switches & Relays for Electrical
Set 1
control panels(One ste of each type)
g) Remote Tap postion Indiactor No. 1
h) Spare insulating oil to be handed over to Owner after
KL 10
commisioning for O&M requirement
B.
For 50MVA , 132/33 KV, 3-phase Power Transformer
a) Bushing of each rating with metal parts & gaskets and
Set 1
lifting tools
b) Cooler fan with Motor No. 1
c) Buchholz Relay(Main Tank) complete with floats and
Set 1
contacts
d) Local and Remote WTI with sensing device and
Set 1
contact(each)
e) Magnetic oil level gauge No. 1
f) Strarters, contactors,switches & Relays for Electrical
Set 1
control panels(One ste of each type)
g) Remote Tap postion Indiactor No. 1
h) Spare insulating oil to be handed over to Owner after
KL 5
commisioning for O&M requirement
(II) SPARES FOR 245kV & 145kV GIS
1 General

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-1 Page 12 of 145

1.1 SF6 gas Pressure Relief Devices, 1Nos. of each type Set 1
1.2 SF6 Pressure gauge cum switch OR Density monitors and
pressure switch as applicable (1 no. of each type) Set 1

1.3 Coupling device for pressure gauge cum switch for


Set 1
connecting Gas handling plant
1.4 Rubber Gaskets, “O” Rings and Seals for SF6 gas of each
Set 1
type
1.5 Molecular filter for SF6 gas with filter bags(20% of total
Set 1
weight)
1.6 All types of Control Valves for SF6 gas of each type Set 1
1.7 SF6 gas (20 % of total gas quantity) Set 1
1.8 All types of coupling for SF6 gas (1 no. of each type)
Set 1
1.9 Covers with all accessories necessary to close a
compartment in case of dismantling of any part of the
Enclosure to ensure the sealing of this compartment

1.9.1 For 3 Phase Enclosure if applicable No. 1


1.9.2 For Single phase enclosure if applicable No. 1
1.10 Locking device to keep the Dis-connectors (Isolators) and
Earthing switches in close or open position in case of
Set 1
removal of the driving Mechanism

1.11 Bus Support insulator of each type for 3 phase/single


No. 1
phase enclosure.
1.12 SF6 to air bushing (220kV & 132kV - 1 No. of each type &
Set 1
rating) as applicable

2.A 245KV SF6 CIRCUIT BREAKER:


2.1 Complete Circuit Breaker pole of each type & rating
complete with interrupter, main circuit enclosure and No. 1
Marshalling Box with operating mechanism
2.2 Rubber gaskets, `O' rings and seals for SF6 gas (1 No. of
Set 1
each type)
2.3 Trip coil assembly with resistor as applicable Set 1
2.4 Closing coil assembly with resistor as applicable . Set 1
2.5 Relays, Power contactors, push buttons, timers & MCBs
Set 1
etc (1 No. of each type & rating)
2.6 Closing coil assembly (including valve, if applicable)
Set 1
2.7 Trip coil assembly (including valve, if applicable) Set 1

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-1 Page 13 of 145

2.8 Auxiliary switch assembly of each type Set 1


2.B 145KV SF6 CIRCUIT BREAKER:
2.1 Complete Circuit Breaker pole of each type & rating
complete with interrupter, main circuit enclosure and
No. 1
Marshalling Box with operating mechanism

2.2 Rubber gaskets, `O' rings and seals for SF6 gas (1 No. of
Set 1
each type)
2.3 Trip coil assembly with resistor as applicable Set 1
2.4 Closing coil assembly with resistor as applicable Set 1
2.5 Relays, Power contactors, push buttons, timers & MCBs
Set 1
etc (1 No. of each type & rating)
2.6 Closing coil assembly (including valve, if applicable)
Set 1
2.7 Trip coil assembly (including valve, if applicable) Set 1
2.8 Auxiliary switch assembly of each type Set 1

3.A 245KV ISOLATORS :


3.1 Complete set of 3-phase dis-connector including main
Set 1
circuit, enclosure, driving mechanism
3.2 3-phase Earthing switch including main circuit, enclosure,
Set 1
driving mechanism.
3.3 Copper contact fingers for dis-connector male & female
contact for dis-connector of each type and rating Set 1

3.4 Copper contact fingers for earthing switch male & female
contacts, for one complete earthing switch of each type Set 1
and rating
3.5 Open / Close contactor assembly, timers, key interlock for
one complete (3 phase) dis-connector and (3 phase)
Set 1
earthing switch (1 No. of each type and rating)

3.6 Push button switch - (1 No. of each type & rating) as


Set 1
applicable
3.7 Limit switch and Aux. Switches for complete 3 phase
1
equipment
3.7.1 For isolator Set 1
3.7.2 For earth switch Set 1
3.B 145KV ISOLATORS :
3.1 Complete set of 3-phase dis-connector including main
Set 1
circuit, enclosure, driving mechanism

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-1 Page 14 of 145

3.2 3-phase Earthing switch including main circuit, enclosure,


Set 1
driving mechanism.
3.3 Copper contact fingers for dis-connector male & female
contact for dis-connector of each type and rating Set 1

3.4 Copper contact fingers for earthing switch male & female
contacts, for one complete earthing switch of each type Set 1
and rating
3.5 Open / Close contactor assembly, timers, key interlock for
one complete (3 phase) dis-connector and (3 phase)
Set 1
earthing switch(1 No. of each type and rating)

3.6 Push button switch - (1 No. of each type & rating) as


Set 1
applicable
3.7 Limit switch and Aux. Switches for complete 3 phase
equipment
3.7.1 For isolator Set 1
3.7.2 For earth switch Set 1

4.0 A 245KV CURRENT TRANSFORMER


4.1 Gas insulated complete CT of each type and rating with
No. 1
enclosure.
4.2 Secondary bushing of each type Set 1
4.0 B 145KV CURRENT TRANSFORMER
4.1 Gas insulated complete CT of each type and rating with
No. 1
enclosure.
4.2 Secondary bushing of each type Set 1

5.0 A 245kV Voltage Transformer


5.1 Gas insulated complete PT of each type and rating with
No. 1
enclosure.
5.0 B 145 kV Voltage Transformer
5.1 Gas insulated complete PT of each type and rating with
No. 1
enclosure.

(III) SPARES FOR AIS EQUIPMENTS


6.0A 220kV, 4400pF CVT No. 1
6.0B 132kV, 8800pF CVT No. 1

7.0A 216kV Surge Arrestor with insulating base, terminal


Set 2
connector , Surge counter & accessories
7.0B 120kV Surge Arrestor with insulating base, terminal
Set 2
connector , Surge counter & accessories

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-1 Page 15 of 145

7.0C 30kV Surge Arrestor with insulating base, terminal


Set 2
connector , Surge counter & accessories

(IV) Relay & Protection panel


A Line Protection Panel
1 Numerical distance relay Set 1
2 Current Differential Relay No. 1
B Transformer Protection Panel
1 Transformer differential protection No. 1
Restricted earth fault protection relay with non-linear
No. 1
2 resistor
3 Directional O/C & E/F relay No. 1
C COMMON SPARES
1 Power supply module for Bus Bar protection. No. 1
2 Bay unit module Set 1

(V) Sub-Station Automation


A Bay control unit (IED) of each type Set 1
B Ethernet switch of each type Set 1

(VI) Digital Protection Coupler for Chilime Hub substation No 1

(VII) LT Transformer
i) Bushing (1 no. of each type) Set 1
ii) OTI & WTI with sensing device (1 no. of each type) Set 1
iii) Diaphragm for pressure relief vent No. 1
iv) Silica Gel container No. 1
v) Set of valves Set 1
vi) Buchholz realy (if applicable) No. 1

(VIII) Illumination System


i) 5% of each type of lighting fixture supplied Set 1

(IX) Erection Hardware items


5% spares of the actual quantities for Insulator strings
&hardwares, clamps & connectors (including equipment
Set 1
connectors), spacers, corona bell and welding sleeves
i)

(X) 33kV Indoor switchgear


i) CB Spring charge indicator (Mechanical) No. 1
ii) Mechanical ON/OFF indicator for CB No. 1
iii) Operation counter for CB No. 1

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-1 Page 16 of 145

iv) CT (1-Phase) (1 no. of each type) Set 1


v) VT (1-Phase) No. 1
vi) Multi Function Meter No. 1
vii) Control switch for breaker(T-N-C) No. 2
viii) Green Indicating lamp for CB Open No. 5
ix) Red indicating lampfor CB Close No. 5
x) DC healthy lamp (white) No. 5
xi) Trip circuit healthy lamp No. 5
xii) Voltmeter with selector switch No. 1
xiii) Numerical protection relay (IED) No. 1
xiv) Master Trip Relay (86) (1 no. of each type) Set 1
Semaphore Indicator for Line Isolator & Line Earth Switch
Set 5
xv) (1 no. of each type)
xvi) LAN Switches and LAN/FO Cables No. 1
xvii) Trip coil assembly No. 2
xviii) Closing coil assembly No. 2

(XI) Communication Equipments


3.0 Mandatory Spares for Chilime Hub GIS
SDH Equipment (STM-4 MADM upto 5 MSP protected
A
directions)
(i) Common cards, Cross-connect/control cards, Optical base card,
Power supply cards, power cabling, other hardware & accessories Set 1
(each).
(ii) Optical Interface Cards/SFP
a S4.1 SFP Nos. 1
c L4.1 SFP Nos. 1
h L4.2 SFP Nos. 1
(iii) Tributary cards
a E1 Interface card (Min.16 interfaces per card) Nos. 1
b Ethernet Interface 10/100 Base T with Layer-2 switching (Min 8
Nos. 1
Interfaces per card)
B VOIP telephone instrument Nos. 1
C Pre Connectorized Optical Fiber Patch Cords(10 Mtrs) – Pack of six
Set 1
Patch cords

SUB-TOTAL-C
Total for 220/132/33kV Chilime Hub GIS new
Substation (Package-2, Part-I) (I) (Part-A+ Part-B+ Part
C)

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-1 Page 17 of 145

II 220(Hybrid)/132/33KV TRISHULI-3B HUB AIS NEW S/S


(Package-2, Part-II)

PART -A: OWNER ASSESSED QUANTITIES


A POWER TRANSFORMER
A.1 1-Ph Autotransformers
a) 53.33MVA, 220/√3 / 132/√3 / 33kV Single Phase Auto Nos. 7
Transformer (without transformer Oil)
b) Insulating oil for 53.33MVA , 220/132/33 KV, 1-phase Lot* 7
Autotransformer (* 1Lot = Oil for 1 Autotransformer )
c) 33kV Current transformer (NCT) for autotrasnformer No 2

A.2 3-Phase Power Transformer


50 MVA, 132 /33kV Three Phase Power Transformer
a) Nos. 1
(without transformer Oil)
Insulating oil for 50MVA , 132/33 KV, 3-phase Power
b) Transformer (* 1Lot = Oil for 1 Autotransformer ) Lot* 1

A.3 Testing & Maintenance Equipments


a) Oil Storage Tank of 20KL No. 1
b) Transformer Oil Filtration plant (6KLPH) No 1

B LT TRANSFORMER
1.0 630 kVA, 33/0.400kV Nos 2
C 245 KV EQUIPMENTS
C.1 245KV GIS HYBRID Equipment
1.1 245kV, SF6 GIS Hybrid Bus Coupler bay Module as per
section project
a) 3000A, 40kA for 1 sec Set 1
1.2 245kV, SF6 GIS Hybrid Bus Transfer Bus Coupler bay
Module as per section project
a) 3000A, 40kA for 1 sec Set 1
1.3 245kV, SF6 GIS Hybrid Line feeder bay Module as per
section project
a) 1600A, 40kA for 1 sec Set 6
1.4 245kV, SF6 GIS Hybrid ICT feeder bay Module as per
section project
a) 1600A, 40kA for 1 sec Set 2

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-1 Page 18 of 145

C.2 245KV Outdoor AIS Equipment (40kA for 1 sec)


1.1 216 KV Surge Arrester (1-phase) Nos. 25
1.2 245 kV, 4400pFCapacitive Voltage Transformer (1-Phase) Nos. 24
1.3 245 kV, 1600A, 40kA, DBR Isolator (Tandem type) (3- Nos. 8
1.4 Phase)Bus Post Insulator (1-Phase) (Except auxiliary
245kV
Nos. 50
buses of transformer)

Testing & Maintenance Equipment for 220kV GIS


C.3
Hybrid
1.1 SF6 Gas processing Unit Set 1
1.2 Partial Discharge Monitoring System (portable type) Set 1
1.3 Dew Point Meter Set 1
1.4 SF6 Gas Leak Detector Set 1

D 145 kV Equipment
1.0 145 kV Circuit Breakers (3-Phase) with support structure
a 1250A, 40kA Nos 7
b 2000A, 40kA Nos 1

2.0 145kV Isolator (3-phase)-Double Break


a 1250A, 40kA Isolator without E/S Nos 7
b 1250A, 40kA Isolator with one E/s Nos 14
c 1250A, 40kA Isolator without E/s (Tandem) Nos 7
d 1250 A, 40kA Isolator without E/S (Beam mounted) Nos 7
e 2000A, 40kA Isolator with two E/s Nos 2

3.0 145 kV Current Transformer (1-Phase)


a 1200A, 40kA with 120% extended current rating Nos 6
b 1200 A, 40kA with 150% extended current Nos 3
c 600 A, 40kA with 120% extended current Nos 15
d 600 A, 40kA with 120% extended current for tariff metering Nos 12

4.0 145 kV Capacitive Voltage Transformer (1- Phase)


a 8800 pF Nos. 18
b 8800 pF for tariff metering Nos. 12
5.0 120 kV Surge Arrestors
a 120 kV Surge Arrestors (1-phase) - Pedestal mounted Nos. 22
b 120 kV Surge Arrestors (1-phase) - suitable for mounting on Nos. 6
transmission line dead end tower

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-1 Page 19 of 145

6.0 145 kV Bust Post Insulator (Except auxiliary buses of Nos 42


transformer)

E 33 kV Equipment
1.0 36kV Circuit Breakers (3-Phase) with support structure
a 1250A, 25kA Nos 5

2.0 36kV Isolator (3-phase)-Double Break


a 1250A, 25kA, Isolator without E/S Nos 8
b 1250A, 25kA, Isolator with one E/s Nos 3
c 1250A, 25kA, Isolator without E/s (Tandem) Nos 5

3.0 36 kV HG Fuse along with support insulator (1-phase) Nos. 3

4.0 36kV Current Transformer (1-Phase)


a 1000A, 25kA with 120% extended current rating Nos 3
b 600 A, 25kA with 120% extended current Nos 12

5.0 36kV Voltage Transformer (1- Phase) Nos 3

6.0 30kV Surge Arrestors (1-phase) Nos. 12


7.0 36kV Bust Post Insulator (Except auxiliary & neutral buses of Nos 18
transformer)
F 72.5kV EQUIPMENT
1.1 72.5 kV, 1250A, 25kA Circuit Breaker (3-phase) with support structure No. 1

1.2 72.5 kV, 1250A, 25kA Isolators with earth switch (3-phase, DBR No. 1
type)

1.3 72.5kV, 50A, 25 kA with 120% extended rating CT (1-phase) Nos. 3


1.4 72.5kV PT (1-phase) Nos. 3
1.5 72.5 kV BPI (1-phase) Nos. 6

G RELAY PANELS (WITH AUTOMATION)


1.0 220 kV
a Circuit Breaker Relay Panel
i With Auto Reclose Nos. 7
ii With out Auto Reclose Nos. 3
b Line Protection Panel
i Line Protection Panel with Distance Protection and Current Nos. 6
Differential Protection at Trishuli-3B Hub End

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-1 Page 20 of 145

ii Line Protection Panel housing two nos. Current Differential Protection Nos. 1
relays & accessories at Matatirtha End
iii Line Protection Panel housing two nos. Current Differential Protection Nos. 1
relays & accessories at Upper Trishuli-1 End
c Transformer Protection Panel (For both HV & MV side) Nos. 2
d Bus Bar Protection Panel Set 1

2.0 132 kV
a Circuit Breaker Relay Panel
i With Auto Reclose Nos. 4
ii With out Auto Reclose Nos. 4
b Line Protection Panel
i) Line Protection Panel with Current Differential Protection and Back up Nos. 4
O/C & E/F Protection at Trishuli-3B Hub End
ii) Line Protection Panel housing two nos. Current Differential Protection Nos. 1
relays & accessories at Trishuli-3A HPP End
iii) Line Protection Panel housing two nos. Current Differential Protection Nos. 1
relays & accessories at Trishuli-3B HPP End

c Transformer Protection Panel (For both HV & MV side) Nos. 1


d Bus Bar Protection Panel Set 1
3.0 33 kV
a Line Protection Panel Nos. 3
b Protection Panel for TBC bay Nos. 1
c Transformer Protection Panel Nos. 1
4.0 COMMON EQUIPMENTS
a Relay tool kit Set 1
b Time synchronisation equipment No. 1
H SUBSTATION AUTOMATION
H.1 Complete Substation Automation System (SAS) for substation
including hardware and software for the substation & remote control
stations alongwith associated equipments for the following bays as
per Technical Specification
a Main bays to be automated
i 220 kV system Bay Nos 10

ii Bays to be automated of existing 132 kV substation Bay Nos 8

iii Bays to be automated of existing 33 kV substation Bay Nos 5


iv BCU for controlling & monitoring of Auxilary System Set 1

I Digital Protection Coupler & PBAX


a) Digital Protection Coupler* Nos 12

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-1 Page 21 of 145

b) PBAX with following configuration as per TS Set 1


i 2 wire subscriber interface card with capacity 32 local subscribers
(along with 32 nos. Instruments)
ii) E-1 interface with 2 trunks G-703
iii) 2 wire interface with 1 trunk (For PSTN)
* Digital protection Coupler for both ends for all 220kV Lines are
considered. However, Digital Protection coupler for 220kV Chilime
Hub - Trishuli-3B D/c Line have been considered at respective
substation end.

J LT Switchgear (As per Technical specification)


a 400V Main switchboard Set 1
b 400V ACDB Set 1
c 400V MLDB Set 1
d 400V Emergency LDB Set 1
e 220V DCDB Sets 2
f 48V DCDB Set 2

K Batteries
a 220V
i 600 AH Nos 2
b 48V
i 600AH Nos 2

L Float Cum Boost Battery Charger


a 220V Float Cum Boost Battery Charger
i 90A/90A Nos 2
b 48V Float Cum Boost Battery Charger
i 90A/90A Nos 2

M Diesel Generator with control Panel


a 250 kVA Set 1

N Fire Protection System


a Portable /Trolley/Wheel mounted extinguishers
i 9 litre water type Nos 2
ii 50 litre foam type Nos 2
iii 4.5 kg CO2 type Nos 10
iv 4.5 kg Dry Chemical Power (DCP) type Nos 6
b Smoke detection system Set 1
c Fire detection and Alarm System Set 1

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-1 Page 22 of 145

O.1 Cables along with clamps, glands, lugs and straight joints etc.

b Power Cables - (1.1kV grade)


i 3.5Cx300 sqmm (XLPE) cable for filter Machine along with termination KM 1
arrangement as per TS

O.2 132kV XLPE Power Cable for interconnection of 132kV Trishuli-


3B HPP Line Bay with Dead end Tower

a) 132kV, XLPE insulated , 1C X 1600 sqmm size copper cable as per kM 1.5
technical specificaion.(Metallic sheath and PE outer sheathed with
graphite coating and short circuit current 40kA for 1 sec) including one
spare cable
b) Cable termination as per technical specification for interconnection Nos 12
with overhead transmission for cable at sl. No. 1 above (excluding
terminating structure)
c) Single phase earth link box Nos 12
d) 36kV grade 1Cx300 Sqmm Earth Continuity Cable kM 0.4

P Air conditioning System for Control room cum administrative


building
a High wall type split AC unit of 2 TR capacity Nos 20

Q Lattice/pipe Structure for towers,beams and equipments including


peak plates/pack washers and guest paltes including foundation
bolts(nuts,washers,MS plate welded at the bottom)
(a) Lattice stucture & foundation bolts MT 420
(b) Pipe structure & foundation bolts MT 30
(c ) Fastners for towers,beams and equipment support strcutures MT 20

R.1
Communication equipments for Trishuli-3B Hub Substation
1.0 Telecom Equipments
SDH Equipment (STM-4 MADM upto 5 MSP protected
A1
directions)
(i) Base Equipment (Common cards, Cross Connect/control cards,
optical base cards, power supply cards, power cabling, other
Nos. 2
hardware and accessories including sub racks, patch cord, DDF etc
fully equiped excluding (ii) & (iii) below

(ii) Optical Interface Cards/SFP


a S4.1 SFP Nos. 10
b L4.1 SFP Nos. 4
c L4.2 SFP Nos. 2

(iii) Tributary cards

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-1 Page 23 of 145

a E1 Interface card (Min.16 interfaces per card) Set 4


b Ethernet Interface 10/100 Base T with Layer-2 switching (Min 8
Nos. 4
Interfaces per card)

B Equipment Cabinets No. 1

2.0 Network Manager System - Craft Terminal


a Hardware Set 1
b Software Set 1

3.0 VOIP telephone instrument with one common switch (min. 8


Nos. 2
port)

R.2 Communication equipments for Trishuli-3B HPP


1.0 Telecom Equipments
SDH Equipment (STM-4 MADM upto 3 MSP protected
A1
directions)
(i) Base Equipment (Common cards, Cross Connect/control cards,
optical base cards, power supply cards, power cabling, other
Nos. 1
hardware and accessories including sub racks, patch cord, DDF etc
fully equiped excluding (ii) & (iii) below

(ii) Optical Interface Cards/SFP


a S4.1 SFP Nos. 2

(iii) Tributary cards


a E1 Interface card (Min.16 interfaces per card) Set 2
b Ethernet Interface 10/100 Base T with Layer-2 switching (Min 8
Nos. 2
Interfaces per card)

B Equipment Cabinets No. 1

2.0 Network Manager System - Craft Terminal


a Hardware Set
b Software Set

3.0 VOIP telephone instrument with one common switch (min. 8


Nos. 2
port)

Sub-Total Part-A

Part-B: VENDOR ASSESSED QUANTITIES

A Erection Hardware

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-1 Page 24 of 145

Insulator strings, Disc Insulators, Hardware, conductor, Al tube, bus-


bar materials, cable trays, Bay MB, clamps, spacers, connectors
including equipment connectors, Junction box, earthwire, buried cable
trenches/pipe equipment & lighting, all accessories etc. for the
following:
a 220 kV Layout (DMT Layout with GIS Hybrid)
i Line Bay Set 6
ii Transformer Bay Set 2
iii TBC Bay Set 1
iv BC bay Set 1
v Bus work (Three Bays) Set 1
vi Bus work (Four Bays) Set 1

b 132 kV (Double Main Layout with bypass breaker arrangement)

i Line Bay Set 4


ii Transformer Bay Set 3
iii BC bay Set 1
iv Bus work (Three Bays) Set 2
v Bus work (Four Bays) Set 1

c For spare unit of 220/132/33kV auto transformer connection through Set 1


auxiliary buses, Neutral formation and delta formation (for two banks):
Required 245 kV BPI for HV auxiliary bus, 132 kV BPI for 132 kV
Auxilary bus, 72.5 kV BPI for tertiary auxilary bus & delta formation,
36 kV BPI for Neutral formation & Neutral auxiliary bus including Al
tube, bus-bar materials, clamps, spacers, connectors, including
equipment connectors, support structures, Earthing of spare unit as
per technical specification.

d Erection Hardware etc for 72.5kV & 33kV equipments & LT Set 1
Transformer connection

e Earthing and lightning protection including necesaary


connectors/connections, risers etc. complete in all respect ( but
excluding LM structures for Lightning protection)
i Earth Conductor (copper) LS 1
ii Earth Rod (copper clad steel) LS 1
iii Equipment for lightning protection LS 1

B Fire Protection System


a Pumping arrangement for HVW system & hydrant system, complete
with all piping, valves, fittings,etc. inside pump house

i 220/132/33kV (New) Substation Set 1

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-1 Page 25 of 145

b Hydrant system, complete U/G piping and accessories etc. outside


the Pump House.
i 220/132/33kV (New) Substation Set 1
c HVW spray system, Hydrant system and complete U/G & O/G piping
and accessories etc. out side the pump house for Transformer :

c.1 Transformer
i 53.33MVA , 220/132/33 KV, 1-phase Autotransformer Set 7
i 50MVA , 132/33 KV, 3-phase Power Transformer Set 1

C Illumination System
a Fire fighting building illumination (100 sqmm) LS 1
b Illumination System for switchyard panel room
i 220KV Set 4
ii 132KV Set 3
iii 33kV Set 1
c Control room cum administrative building illumination (1000 sqmm) LS 1
d Switchyard lighting LS 1
e Street lighting LS 1
h Transit camp (420 sqmm) LS 1
j Security room (10 sqmm) LS 1
k Car parking shed (for 10 cars) LS 2

D Air conditioning System


a Air conditioning for S/Y panel room
i 220KV Set 4
ii 132KV Set 3
iii 33kV Set 1
E POWER & CONTROL CABLES
i For 220/132/33kV Trishuli-3B Hub Substation:
a Power Cables(PVC) - (1.1kV grade) LS 1
b Power Cables (XLPE) - (1.1kV grade) LS 1
c Control Cable (PVC) - (1.1kV grade) LS 1
Cable glands, lugs & straight through joints for Power & Control LS 1
d
cables
ii For 220kV Upper Trishuli-1 HPP Switchyard:
a Power Cables(PVC) - (1.1kV grade) LS 1
b Control Cable (PVC) - (1.1kV grade) LS 1
Cable glands, lugs & straight through joints for Power & Control LS 1
c
cables
iii For 220kV Matatirtha Substation:
a Power Cables(PVC) - (1.1kV grade) LS 1

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-1 Page 26 of 145

b Control Cable (PVC) - (1.1kV grade) LS 1


Cable glands, lugs & straight through joints for Power & Control LS 1
c
cables
iv For 132kV Upper Trishuli-3B HPP Switchyard:
a Power Cables(PVC) - (1.1kV grade) LS 1
b Control Cable (PVC) - (1.1kV grade) LS 1
Cable glands, lugs & straight through joints for Power & Control LS 1
c
cables
v For 132kV Trishuli-3A HPPSwitchyard:
a Power Cables(PVC) - (1.1kV grade) LS 1
b Control Cable (PVC) - (1.1kV grade) LS 1
Cable glands, lugs & straight through joints for Power & Control LS 1
c
cables
vi For 132kV Samundratar Substation:
a Power Cables(PVC) - (1.1kV grade) LS 1
b Control Cable (PVC) - (1.1kV grade) LS 1
Cable glands, lugs & straight through joints for Power & Control LS 1
c
cables

Sub-Total Part-B

Part-C: Mandatory Spares

(I) Mandatory Spare List for Autotransformer


A
For 53.33MVA , 220/132/33 KV, 1-phase Autotransformer
a) Bushing of each rating with metal parts & gaskets and Set 1
lifting tools
b) Cooler fan with Motor No. 1
c) Buchholz Relay(Main Tank) complete with floats and Set 1
contacts
d) Local and Remote WTI with sensing device and Set 1
contact(each)
e) Magnetic oil level gauge No. 1
f) Strarters, contactors,switches & Relays for Electrical Set 1
control panels(One ste of each type)
g) Remote Tap postion Indiactor No. 1
h) Spare insulating oil to be handed over to Owner after KL 10
commisioning for O&M requirement
B
For 50MVA , 132/33 KV, 3-phase Power Transformer

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-1 Page 27 of 145

a) Bushing of each rating with metal parts & gaskets and Set 1
lifting tools
b) Cooler fan with Motor No. 1
c) Buchholz Relay(Main Tank) complete with floats and Set 1
contacts
d) Local and Remote WTI with sensing device and Set 1
contact(each)
e) Magnetic oil level gauge No. 1
f) Strarters, contactors,switches & Relays for Electrical Set 1
control panels(One ste of each type)
g) Remote Tap postion Indiactor No. 1
h) Spare insulating oil to be handed over to Owner after KL 5
commisioning for O&M requirement

(II) 245kV GIS Hybrid


1 General
1.1 SF6 gas Pressure Relief Devices, 1Nos. of each type Set 1
1.2 SF6 Pressure gauge cum switch OR Density monitors and
pressure switch as applicable (1 no. of each type) Set 1

1.3 Coupling device for pressure gauge cum switch for


Set 1
connecting Gas handling plant
1.4 Rubber Gaskets, “O” Rings and Seals for SF6 gas of each
Set 1
type
1.5 Molecular filter for SF6 gas with filter bags(20% of total
Set 1
weight)
1.6 All types of Control Valves for SF6 gas of each type Set 1
1.7 SF6 gas (20 % of total gas quantity) Set 1
1.8 All types of coupling for SF6 gas (1 no. of each type)
Set 1
1.9 Pipe length (Copper or Steel as applicable) for SF6 Circuit
Set 1
of each type
1.10 Locking device to keep the Dis-connectors (Isolators) and
Earthing switches in close or open position in case of
Set 1
removal of the driving Mechanism

1.11 SF6 to air bushing (220kV - 1 No. of each type & rating) as
Set 1
applicable

2 245KV SF6 CIRCUIT BREAKER:

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-1 Page 28 of 145

2.1 Complete Circuit Breaker pole of each type & rating


complete with interrupter, main circuit enclosure and
No. 1
Marshalling Box with operating mechanism

2.2 Rubber gaskets, `O' rings and seals for SF6 gas (1 No. of
Set 1
each type)
2.3 Trip coil assembly with resistor as applicable Set 1
2.4 Closing coil assembly with resistor as applicable . Set 1
2.5 Relays, Power contactors, push buttons, timers & MCBs
Set 1
etc (1 No. of each type & rating)
2.6 Closing coil assembly (including valve, if applicable)
Set 1
2.7 Trip coil assembly (including valve, if applicable) Set 1
2.8 Auxiliary switch assembly of each type Set 1

3 245KV ISOLATORS :
3.1 Complete set of 3-phase dis-connector including main
Set 1
circuit, enclosure, driving mechanism
3.2 3-phase Earthing switch including main circuit, enclosure,
Set 1
driving mechanism.
3.3 Copper contact fingers for dis-connector male & female
contact for dis-connector of each type and rating Set 1

3.4 Copper contact fingers for earthing switch male & female
contacts, for one complete earthing switch of each type Set 1
and rating
3.5 Open / Close contactor assembly, timers, key interlock for
one complete (3 phase) dis-connector and (3 phase)
Set 1
earthing switch (1 No. of each type and rating)

3.6 Push button switch - (1 No. of each type & rating) as


Set 1
applicable
3.7 Limit switch and Aux. Switches for complete 3 phase
1
equipment
3.7.1 For isolator Set 1
3.7.2 For earth switch Set 1
4 245KV CURRENT TRANSFORMER
4.1 Gas insulated complete CT of each type and rating with
No. 1
enclosure.
4.2 Secondary bushing of each type Set 1
(III) 145kV CB

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-1 Page 29 of 145

i) Complete Pole of circuit breaker including pole column, interrupter,


with driving mechanism and Marshaling Box but without support
structure for
1250A, 31.5kA (No. of Pole) No. 1
ii) Rubber gaskets, `O' rings and seals ( for complete replacement of one Set 1
pole of CB)
iii) Trip coils with resistor Nos. 2
iv) Closing coils with resistor Nos. 1
v) Terminal Pads & connectors Nos. 2
vi) Molecular filter Nos. 2
vii) Relays, Power contactors, switch fuse units, limit switches, push Set 1
buttons, timers & MCB etc. (1 no. of each type)
viii) Pressure switches / Density monitor (1 no. of each type) Set 1
ix) Auxiliary switch assembly (for one pole of CB) Set 1
(III) 72.5kV CB
i) Complete Pole of circuit breaker including pole column, interrupter,
with driving mechanism and Marshaling Box but without support
structure for
1250A, 31.5 KA (No. of Pole) No. 1
ii) Rubber gaskets, `O' rings and seals ( for complete replacement of one Set 1
pole of CB)
iii) Trip coils with resistor Nos. 2
iv) Closing coils with resistor Nos. 1
v) Terminal Pads & connectors Nos. 2
vi) Molecular filter Nos. 2
vii) Relays, Power contactors, switch fuse units, limit switches, push Set 1
buttons, timers & MCB etc. (1 no. of each type)
viii) Pressure switches / Density monitor (1 no. of each type) Set 1
ix) Auxiliary switch assembly (for one pole of CB) Set 1
(IV) 245kV Isolator
i) One complete pole including support Insulator, motor operating
mechanism (MOM) with box but excluding structure
1600A, 40 KA, 1 E/S (no. of pole) No. 1
ii) Copper contact fingers for male & female contacts ( for one pole of Set 2
Isolator)
iii) Open/Close contactor assembly, timers, key interlock push button Set 1
switch & auxilliary switches (for one pole of Isolator)
iv) Limit Switch Nos. 2
v) Terminal Pads & Connectors Nos. 3
vi) Corona shield rings Nos. 3
(V) 145kV Isolator
i) One complete pole including support Insulator, motor operating
mechanism (MOM) with box but excluding structure
1250A, 31.5kA with1 E/S (no. of pole) No. 1
ii) Copper contact fingers for male & female contacts ( for one pole of Set 2
Isolator)

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-1 Page 30 of 145

iii) Open/Close contactor assembly, timers, key interlock push button Set 1
switch & auxilliary switches (for one pole of Isolator)
iv) Limit Switch Nos. 2
v) Terminal Pads & Connectors Nos. 3
vi) Corona shield rings Nos. 3
(VI) 72.5 kV Isolator
i) One complete pole including support Insulator, MANUAL operating
mechanism with box but excluding structure
1250A, 25kA, 1 E/S (no. of pole) No. 1
ii) Copper contact fingers for male & female contacts ( for one pole of Set 2
Isolator)
iii) Open/Close contactor assembly, timers, key interlock push button Set 1
switch & auxilliary switches (for one pole of Isolator)
iv) Limit Switch Nos. 2
v) Terminal Pads & Connectors Nos. 3

(VII) 36kV Isolator


i) One complete pole including support Insulator, MANUAL operating
mechanism with box but excluding structure
630A, 25KA, 1 E/S (no. of pole) No. 1
ii) Copper contact fingers for male & female contacts ( for one pole of Set 2
Isolator)
iii) Open/Close contactor assembly, timers, key interlock push button Set 1
switch & auxilliary switches (for one pole of Isolator)
iv) Limit Switch Nos. 2
v) Terminal Pads & Connectors Nos. 3

(VIII) 72.5kV, 1250A, 31.5 kA with 120% extended rating CT (1-phase) No. 1

(IX) CVT (245 kV,4400 pF) (1-phase) No. 1

(X) 72.5kV PT (1-phase) No. 1

(XI) 216 SA
i) Complete LA (1-phase) No. 1
ii) Surge counter/monitor Nos. 5
(XII) 120kV SA
i) Complete LA (1-phase) No. 1
ii) Surge counter/monitor Nos. 5
(XIII) 30kV SA
i) Complete LA (1-phase) No. 1
ii) Surge counter/monitor Nos. 5

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-1 Page 31 of 145

(XIV) C&R PANELS


i) Transformer protection panel :
a) Transformer differential protection No. 1
b) REF protection relay with non-linear resistor No. 1
c) Directional over current & E/F Protection Relay No. 1
ii) Line protection panel :
a) Distance Protection relay Set 1
b) Current differential Protection relay Set 1
iv) Breaker Relay panel:
a) Breaker failure relay No. 1
b) Trip circuit supervision relay Nos. 2
c) Self reset trip relay (relay of each type) Set 1
d) Hand reset trip relay(relay of each type) Set 1
e) Timer relay(relay of each type) Set 1
f) DC supervision relay(relay of each type) Set 1
g) Flag relays(relay of each type) Set 1
h) Auxiliary relays(relay of each type) Set 1

(XV) Teleprotection Equipments


i) Set of prints for protection coupler (digital ) Set 1

(XVI) SAS
i) Bay Control Unit (IED) of each type Set 1
ii) Ethernet Switch of each type Set 1

(XVII) BATTERY CHARGER( 220kV)


i) Set of control cards Set 1
ii) Set of relays Set 1
iii) Rectifier transformer No. 1
iv) Thyristor/diode Set 1
v) Fuses of Thyristor with indicators Set 6

(XVIII) COMMON SPARES


i) Bay unit Module No. 1
ii) 2 wire local subscriber interface card for PABX No. 1
iii) E1 Interface card for PABX No. 1
(XIX) Mandatory Spares of Communication Equipments
1.0 Mandatory Spares for Trishuli-3B Hub

SDH Equipment (STM-4 MADM upto 5 MSP protected


A
directions)

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-1 Page 32 of 145

(i) Common cards, Cross-connect/control cards, Optical base card,


Power supply cards, power cabling, other hardware & accessories Set 1
(each).

(ii) Optical Interface Cards/SFP


a S4.1 SFP Nos. 1
c L4.1 SFP Nos. 1
h L4.2 SFP Nos. 1

(iii) Tributary cards


a E1 Interface card (Min.16 interfaces per card) Nos. 1
b Ethernet Interface 10/100 Base T with Layer-2 switching (Min 8
Nos. 1
Interfaces per card)

B VOIP telephone instrument Nos. 1

C Pre Connectorized Optical Fiber Patch Cords(10 Mtrs) – Pack of six


Set 1
Patch cords

2.0 Mandatory Spares for Trishuli-3B HPP

SDH Equipment (STM-4 MADM upto 3 MSP protected


A
directions)
(i) Common cards, Cross-connect/control cards, Optical base card,
Power supply cards, power cabling, other hardware & accessories Set 1
(each).

(ii) Optical Interface Cards/SFP


a S4.1 SFP Nos. 1

(iii) Tributary cards


a E1 Interface card (Min.16 interfaces) Nos. 1
b Ethernet Interface 10/100 Base T with Layer-2 switching (Min 8
Nos. 1
Interfaces per card)

B VOIP telephone instrument Nos. 1

C Pre Connectorized Optical Fiber Patch Cords(10 Mtrs) – Pack of six


Set 1
Patch cords

SUB-TOTAL-C

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-1 Page 33 of 145

Total for 220/132/33kV Trishuli Hub AIS new


Substation (Package-2, Part-II) (II) (Part-A+ Part-B+
Part C)
Total of Schedule-1
Date: Signature:

Place: Printed Name:

Designation:

Common Seal:

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-2 Page 34 of 145

Package-2 for 220/132/33kV Chilime Hub GIS new substation (Part-I) and 220(Hybrid)/132/33kV Trishuli-3B Hub AIS new substation (Part-II) under 220kV Chilime-Trishuli Transmission System Project

(Schedule of rates and prices)

Bidder's Name & Address:

Plant and Equipment including mandatory Spares to be supplied from within Employer's Country

1 2 3 4 5 6 7 8 9=6x8 10
Sl. No. Item Description Country of Origin Type & Unit Quantity Currency Unit ExW Price Total ExW Price Mode of Transaction
Designation (As per ITB (Direct/ Bought-Out)
19.1)

I. 220/132/33kV CHILIME HUB GIS new Substation


(Package-2, Part-I)

PART - A: OWNER ASSESSED QUANTITIES


A POWER TRANSFORMER
A.1 1-Phase Auto Transformer
53.33MVA, 220/√3 / 132/√3 / 33kV Single Phase Auto
a) Nos. 7
Transformer (without transformer Oil)
Insulating oil for 53.33MVA , 220/132/33 KV, 1-phase
b) Autotransformer (* 1Lot = Oil for 1 Autotransformer ) Lot* 7

c) 33kV Current transformer (NCT) for autotrasnformer No 2

A.2 POWER TRANSFORMER


50 MVA, 132 /33kV Three Phase Power Transformer
a) Nos. 1
(without transformer Oil)
Insulating oil for 50MVA , 132/33 KV, 3-phase Power
b) Transformer (* 1Lot = Oil for 1 Autotransformer ) Lot* 1

A.3 Testing & Maintenance Equipments


a) Oil Storage Tank of 20KL No. 1
b) Transformer Oil Filtration plant (6KLPH) No 1

B) LT Transformer
a) 630KVA, 33/0.400 kV Nos. 2

C 245 KV EQUIPMENTS

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-2 Page 35 of 145

C1 245KV GIS Equipment


1.1 245kV, SF6 GIS Bus Bars Module as per section project

a) 3000A, 40kA for 1 sec Sets 2


1.2 245kV, SF6 GIS Bus Coupler feeder bay Module as per
section project
a) 3000A, 40kA for 1 sec Sets 1
1.3 245kV, SF6 GIS Line feeder bay Module as per section
project
a) 1600A, 40kA for 1 sec Sets 2
1.4 245kV, SF6 GIS spare Line feeder bay Module as per
section project
a) 1600A, 40kA for 1 sec Sets 1
1.5 245kV, SF6 GIS ICT feeder bay Module as per section
project
a) 1600A, 40kA for 1 sec Sets 2
1.6 245kV, SF6 GIS Auxiliary Bus Module as per section
project to connect spare unit of Transformer
a) 1600A, 40kA for 1 sec Set 1
1.7 SF6 Gas Insulated Bus Duct (GIB) outside GIS Hall
alongwith associated support structure and accessories
(for Transformer bays)
a) 1600A, 40kA for 1 sec. Single Phase Mtr. 460
1.8 SF6 Gas Insulated Bus Duct (GIB) outside GIS Hall
alongwith associated support structure and accessories
(for Line bays)
a) OPTION-I
1600A, 40kA for 1 sec. Single Phase Mtr. 225
b) OPTION-II
1600A, 40kA, 1sec three phase Mtr. 75
Note : Bidder is required to quote for either option-I or
Option-II
1.9 220kV, SF6 to Air Bushing alongwith associated support
structure (for Transformer bays)
a) 1600A, 40kA for 1 sec. Single Phase Nos. 7
1.10 220kV, SF6 to Air Bushing alongwith associated support
structure (for line bays)
a) OPTION-I
1600A, 40kA for 1 sec. Single Phase Nos. 9
b) OPTION-II
1600A, 40kA, 1sec three phase Nos. 3
Note : Bidder is required to quote for either option-I or
Option-II

C.2 245KV Outdoor AIS Equipment


1.1 216 KV Surge Arrester (1-phase) Nos. 16
1.2 4400pF, 245 kV Capacitive Voltage Transformer (1-Phase) Nos. 9
1.3 245kV Bus Post Insulator (1-Phase) Nos. 9

D 145kV Equipment

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-2 Page 36 of 145

D.1 145KV GIS Equipment


1.1 145kV, SF6 GIS Bus Bars Module as per section project

a) 2000A, 40kA for 1 sec Set 2


1.2 145kV, SF6 GIS Bus Coupler feeder bay Module as per
section project
a) 2000A, 40kA for 1 sec Set 1
1.3 145kV, SF6 GIS Line feeder bay Module as per section
project
a) 1250A, 40kA for 1 sec Sets 4
1.4 145kV, SF6 GIS Spare Line feeder bay Module as per
section project
a) 1250A, 40kA for 1 sec Set 1
1.5 145kV, SF6 GIS ICT feeder bay Module as per section
project for 220/132 kV Transformer
a) 1250A, 40kA for 1 sec Set 2
1.4 145kV, SF6 GIS ICT feeder bay Module as per section
project for 132/33 kV Transformer
a) 1250A, 40kA for 1 sec Set 1
1.6 145kV, SF6 GIS Auxiliary Bus Module as per section
project to connect spare unit of Transformer
a) 1250A, 40kA for 1 sec Set 1
1.7 SF6 Gas Insulated Bus Duct (GIB) outside GIS hall
including Bus Duct support structure and associated
a) 1250A, 40kA 1sec single phase (for 7x53.33MVA 1-Phase
Mtr 395
Transformer bays)
b) 1250A, 40kA 1sec three phase Mtr 300
1.8 145kV, SF6 to Air Bushing alongwith associated support
structure
a) 1250A, 40kA 1sec three phase Set 5
b) 1250A, 40kA 1sec single phase Set 7

D.2 145kV Outdoor AIS EQUIPMENT


1.0 120 kV Surge Arrestors (1-Phase) Nos. 25
2.0 8800pF, 145 kV Capacitive Voltage Transformer (1-Phase)
Nos. 15
3.0 8800pF, 145 kV Capacitive Voltage Transformer (1-Phase)
Nos. 15
(for tariff metering)
4.0 145KV Bus Post Insulator Nos. 9

E 72.5kV EQUIPMENT
1.1 72.5 kV, 1250A, 25kA Circuit Breaker (3-phase) with No. 1
support structure
1.2 72.5 kV, 1250A, 25kA Isolators with earth switch (3- No. 1
phase, DBR type)
1.3 72.5kV, 50A, 25 kA with 120% extended rating CT (1- Nos. 3
phase)
1.4 72.5kV PT (1-phase) Nos. 3
1.5 72.5 kV BPI (1-phase) Nos. 6

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-2 Page 37 of 145

F 33kV Equipments
1.1 33 kV, 630A, 25kA Isolators with out earth switch (3- No. 1
phase, DBR type)
1.2 30 kV Surge Arrestors (1-phase) Nos. 3
1.3 36 kV BPI (1-phase) Nos. 3
1.4 36 kV HG Fuse along with support insulator (1-phase) Nos. 3

G 33kV, 25 kA (3 Phase) Indoor switch gear panel


including control, relay & protection
i) 33kV Line bay Module Nos 2
ii) 33kV Incomer Transformer Module Nos 1
iii) 33kV LT Transformer Module Nos 1
iv) 33kV Bus Sectionalizer Module Nos 1
v) 33kV Bus PT Module Nos 2

H Testing & Maintenance Equipment for GIS


1.1 SF6 Gas processing Unit Set 1
1.2 Partial Discharge Monitoring System (Portable type) Set 1
1.3 Dew Point Meter Set 1
1.4 SF6 Gas Leak Detector Set 1
1.5 Portable Ladder with adustable height as per TS Nos. 1
1.6 EOT crane for 220kV GIS Hall Set 1
1.7 EOT crane for 132kV GIS Hall Set 1

I RELAY PANELS (WITH AUTOMATION)


1 245kV
1.1 Circuit Breaker Relay Panel
a) CB Relay Panel With Auto Reclose Nos. 3
b) CB Relay Panel Without Auto Reclose Nos. 3
1.2 Line Protection Panel
Line Protection Panel with Distance Protection and Current
a) Nos. 3
Differential Protection at Chilime GIS End
1.3 Transformer Protection Panel (For both HV & MV side) Nos. 2

1.4 Bus Bar Protection Panel set 1


2 145kV
2.1 Circuit Breaker Relay Panel
a) CB Relay Panel With Auto Reclose Nos. 5
b) CB Relay Panel Without Auto Reclose Nos. 4
2.2 Line Protection Panel

Line Protection Panel with Current Differential Protection


a) Nos. 5
and Back up O/C & E/F Protection at Chilime GIS End

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-2 Page 38 of 145

Line Protection Panel housing two nos. Current Differential


b) Nos. 1
Protection relays & accessories at Rasuagadi HPP End

Line Protection Panel housing one no. Current Differential


c) Nos. 1
Protection relay & accessories at Upper Sanjen HPP End

Line Protection Panel housing one no. Current Differential


d) Nos. 1
Protection relay & accessories at Lower Sanjen HPP End

2.3 Transformer Protection Panel (For both HV & MV side) Nos. 1

2.4 Bus Bar Protection Panel set 1

3 Other/Common equipments Pertaining to C & R System


a) Time Synchronisation Equipment No. 1
b) Relay Test kit No. 1

J SUBSTATION AUTOMATION
Substation Automation System as per Technical
1
Specification:
a) 220kV System (Nos. of bays) Nos. 6
b) 132 kV System (Nos. of bays) Nos. 9
c) BCU for auxilary system set 1
d) 33 kV HT Indoor Switchgear set 1
K Digital Protection Coupler& PBAX
a) Digital Protection Coupler* Nos 2
b) PBAX with following configuration as per TS Set 1
i 2 wire subscriber interface card with capacity 32 local
subscribers (along with 32 nos. Instruments)
ii) E-1 interface with 2 trunks G-703
iii) 2 wire interface with 1 trunk (For PSTN)
*Digital Protection coupler for 220kV Chilime Hub - Trishuli-
3B D/c Line have been considered at respective substation
end.
L LT Switchgear (As per Technical specification)
a 400V Main switchboard Set 1
b 400V ACDB Set 1
c 400V MLDB Set 1
d 400V Emergency LDB Set 1
e 220V DCDB Sets 2
g 48V DCDB Set 2

M Batteries
a 220V
i 800 AH Nos 2
b 48V

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-2 Page 39 of 145

i 600AH Nos 2

N Float Cum Boost Battery Charger


a 220V Float Cum Boost Battery Charger
i 90A/90A Nos 2
b 48V Float Cum Boost Battery Charger
i 90A/90A Nos 2

O Diesel Generator with control Panel


a 250 kVA Set 1

P Fire Protection System


a Portable /Trolley/Wheel mounted extinguishers
i 9 litre water type Nos 2
ii 50 litre foam type Nos 2
iii 4.5 kg CO2 type Nos 10
iv 4.5 kg Dry Chemical Power (DCP) type Nos 6
b Smoke detection system Set 1
c Fire detection and Alarm System Set 1

Q Cables along with clamps, glands, lugs and straight


joints etc.
a 33kV HT XLPE Power Cable alongwith accessories and
termination equipments
i) 1Cx600 Sq.mm KM 2.5
ii) 1Cx300 Sq.mm KM 2
b Power Cables - (1.1kV grade)
i 3.5Cx300 sqmm (XLPE) cable for filter Machine along with
KM 1
2 nos outdoor receptacles -250A

R Air conditioning
High wall type split AC unit of 2 TR capacities for control
1 Nos. 25
room, relay room and battery room

S STEEL STRUCTURES (Tower,Gantry structures&


Equipment support structures)
a Lattice/pipe Structure for towers,beams and equipments
including peak plates/pack washers and guest paltes
including foundation bolts(nuts,washers,MS plate welded at
the bottom)
i) Lattice stucture & foundation bolts MT 90
ii Pipe structure & foundation bolts MT 10
b Fastners for towers,beams and equipment support
MT 6
strcutures

T Communication Equipment for Chilime Hub GIS


1.0 Telecom Equipments
A1
SDH Equipment (STM-4 MADM upto 5 MSP protected directions)

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-2 Page 40 of 145

(i) Base Equipment (Common cards, Cross Connect/control cards, optical


base cards, power supply cards, power cabling, other hardware and
Nos. 1
accessories including sub racks, patch cord, DDF etc fully equiped
excluding (ii) & (iii) below

(ii) Optical Interface Cards/SFP


a S4.1 SFP Nos. 6
b L4.1 SFP Nos. 2
c L4.2 SFP Nos.

(iii) Tributary cards


a E1 Interface card (Min.16 interfaces per card) Set 2
b Ethernet Interface 10/100 Base T with Layer-2 switching (Min 8
Nos. 2
Interfaces per card)

B Equipment Cabinets No. 1

2.0
VOIP telephone instrument with one common switch (min. 8 port) Nos. 2

SUB TOTAL PART-A

PART-B: VENDOR ASSESSED QUANTITIES

Erection Hardware :-Insulator strings, Disc Insulators,


Hardware, conductor, bus-bar materials, cable trays,
clamps, spacers, connectors including conectors for Auto
A
Transformer , Junction box, earthwire, earthing material
risers, buried cable trenches/pipe of equipment & lighting,
all accessories etc. for the following:

1 220 kV DM-type layout for GIS termination arrangement


1.1 Line Bay Set 3
1.2 Transformer Bay Sets 2

2 132 kV DM-type layout for GIS termination arrangement


1.1 Line Bay Sets 5
1.2 Transformer Bay Sets 3

3 33 KV
3.1 Line Bay Set 2
3.1 Transformer Bay Set 1
3.3 LT Transformer Bay Set 1

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-2 Page 41 of 145

Erection Hardware etc for 72.5kV equipments & LT


4 Set 1
Transformer connection

For spare unit of 220/132/33kV auto transformer


connection through auxiliary buses, Neutral formation and
delta formation (for two banks): Required 245kV BPI, 132
kV BPI, 72.5kV BPI for tertiary auxilary bus & delta
B formation, 36kV BPI for Neutral formation & Neutral Set 1
auxiliary bus including Al tube, bus-bar materials, clamps,
spacers, connectors, including equipment connectors,
support structures , Earthing of spare unit as per technical
specification

C Ventilation & heating System


Ventilation & heating system (as per technical
2
specification)
(i) 220kV GIS Hall LS 1
(ii) 132 kV GIS Hall LS 1

D Illumination System
1.1 Substation Lighting
Control Room cum administrative building illumination
(i) LS 1
(1000 sqmm)
(ii) 220kV GIS Building (620 sqmm) LS 1
(iii) 132kV GIS Building (350 sqmm) LS 1

(iv) 33kV Indoor Switchyrad Panel Room (160 sqmm) LS 1


(v) Fire Fighting Pump house (100 sqmm) LS 1
(vi) Outdoor Switchyard Lighting LS 1
(vii) Street Lighting LS 1
(viii) Occupancy sensor LS 1
1.2 Transit Camp (420 sqmm) LS 1
1.3 Township Area (Staff Quarter area) Lighting LS 1
(i) B type (250 sqmm) LS 1
(ii) C type (300 sqmm) LS 1
(iii) D type (200 sqmm) LS 1
1.4 Security room (10 sqmm) LS 1
1.5 Car parking shed (for 10 cars) LS 2

E Fire Protection System (as per technical Specification) set 1


1 Pumping arrangement inside pump house set 1
2 Hydrant system outside the Pump House. set 1
3 HVW spray system & Hydrant system for Transformer :

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-2 Page 42 of 145

53.33MVA, 220/132 kV Single Phase Auto Transformer


a nos 7

b 50 MVA,132/33 kV Three phase transformer nos 1

F POWER & CONTROL CABLES


i For 220/132/33kV Chilime Hub GIS Substation:
a Power Cables(PVC) - (1.1kV grade) LS 1
b Power Cables (XLPE) - (1.1kV grade) LS 1
c Control Cable (PVC) - (1.1kV grade) LS 1
LS 1
d Cable glands, lugs & straight through joints for Power & Control cables
ii For 132kV Upper Sanjen HPP Switchyard:
a Power Cables(PVC) - (1.1kV grade) LS 1
b Control Cable (PVC) - (1.1kV grade) LS 1
LS 1
c Cable glands, lugs & straight through joints for Power & Control cables
iii For 132kV Lower Sanjen HPP Switchyard:
a Power Cables(PVC) - (1.1kV grade) LS 1
b Control Cable (PVC) - (1.1kV grade) LS 1
LS 1
c Cable glands, lugs & straight through joints for Power & Control cables
iv For 132kV Lower Rasuagadi HPP Switchyard:
a Power Cables(PVC) - (1.1kV grade) LS 1
b Control Cable (PVC) - (1.1kV grade) LS 1
LS 1
c Cable glands, lugs & straight through joints for Power & Control cables

G Visual Monitoring System for watch & ward as per LS 1


technical specification

H Earthing and lightning protection including necesaary


connectors/connections, risers etc. complete in all respect

i Earth Conductor (copper) LS 1


ii Earth Rod (copper clad steel) LS 1
iii Equipment for lightning protection LS 1
I SUBSTATION AUTOMATION
a Integration of all 220/132kV Bays under present scope with LS 1
the SCADA of SIEMENS (SINAUT Spectrum) at Load
Dispatch Centre, Kathmandu including supply of Hardware,
Software, accessories etc. as per TS Section Project.

SUB TOTAL PART-B

PART-C: MANDATORY SPARES


(I) Mandatory Spare List for Autotransformer
A. For 53.33MVA , 220/132/33 KV, 1-phase
Autotransformer

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-2 Page 43 of 145

a) Bushing of each rating with metal parts & gaskets and


Set 1
lifting tools
b) Cooler fan with Motor No. 1
c) Buchholz Relay(Main Tank) complete with floats and
Set 1
contacts
d) Local and Remote WTI with sensing device and
Set 1
contact(each)
e) Magnetic oil level gauge No. 1
f) Strarters, contactors,switches & Relays for Electrical
Set 1
control panels(One ste of each type)
g) Remote Tap postion Indiactor No. 1
h) Spare insulating oil to be handed over to Owner after
KL 10
commisioning for O&M requirement
B.
For 50MVA , 132/33 KV, 3-phase Power Transformer
a) Bushing of each rating with metal parts & gaskets and
Set 1
lifting tools
b) Cooler fan with Motor No. 1
c) Buchholz Relay(Main Tank) complete with floats and
Set 1
contacts
d) Local and Remote WTI with sensing device and
Set 1
contact(each)
e) Magnetic oil level gauge No. 1
f) Strarters, contactors,switches & Relays for Electrical
Set 1
control panels(One ste of each type)
g) Remote Tap postion Indiactor No. 1
h) Spare insulating oil to be handed over to Owner after
KL 5
commisioning for O&M requirement
(II) SPARES FOR 245kV & 145kV GIS
1 General
1.1 SF6 gas Pressure Relief Devices, 1Nos. of each type
Set 1
1.2 SF6 Pressure gauge cum switch OR Density monitors and
pressure switch as applicable (1 no. of each type) Set 1

1.3 Coupling device for pressure gauge cum switch for


Set 1
connecting Gas handling plant
1.4 Rubber Gaskets, “O” Rings and Seals for SF6 gas of each
Set 1
type
1.5 Molecular filter for SF6 gas with filter bags(20% of total
Set 1
weight)
1.6 All types of Control Valves for SF6 gas of each type
Set 1
1.7 SF6 gas (20 % of total gas quantity) Set 1
1.8 All types of coupling for SF6 gas (1 no. of each type)
Set 1

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-2 Page 44 of 145

1.9 Covers with all accessories necessary to close a


compartment in case of dismantling of any part of the
Enclosure to ensure the sealing of this compartment

1.9.1 For 3 Phase Enclosure if applicable No. 1


1.9.2 For Single phase enclosure if applicable No. 1
1.10 Locking device to keep the Dis-connectors (Isolators) and
Earthing switches in close or open position in case of
Set 1
removal of the driving Mechanism

1.11 Bus Support insulator of each type for 3 phase/single


No. 1
phase enclosure.
1.12 SF6 to air bushing (220kV & 132kV - 1 No. of each type &
Set 1
rating) as applicable

2.A 245KV SF6 CIRCUIT BREAKER:


2.1 Complete Circuit Breaker pole of each type & rating
complete with interrupter, main circuit enclosure and
Marshalling Box with operating mechanism No. 1

2.2 Rubber gaskets, `O' rings and seals for SF6 gas (1 No. of
Set 1
each type)
2.3 Trip coil assembly with resistor as applicable Set 1
2.4 Closing coil assembly with resistor as applicable . Set 1
2.5 Relays, Power contactors, push buttons, timers & MCBs
Set 1
etc (1 No. of each type & rating)
2.6 Closing coil assembly (including valve, if applicable)
Set 1
2.7 Trip coil assembly (including valve, if applicable) Set 1
2.8 Auxiliary switch assembly of each type Set 1
2.B 145KV SF6 CIRCUIT BREAKER:
2.1 Complete Circuit Breaker pole of each type & rating
complete with interrupter, main circuit enclosure and
No. 1
Marshalling Box with operating mechanism

2.2 Rubber gaskets, `O' rings and seals for SF6 gas (1 No. of
Set 1
each type)
2.3 Trip coil assembly with resistor as applicable Set 1
2.4 Closing coil assembly with resistor as applicable Set 1
2.5 Relays, Power contactors, push buttons, timers & MCBs
Set 1
etc (1 No. of each type & rating)
2.6 Closing coil assembly (including valve, if applicable)
Set 1
2.7 Trip coil assembly (including valve, if applicable) Set 1
2.8 Auxiliary switch assembly of each type Set 1

3.A 245KV ISOLATORS :

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-2 Page 45 of 145

3.1 Complete set of 3-phase dis-connector including main


Set 1
circuit, enclosure, driving mechanism
3.2 3-phase Earthing switch including main circuit, enclosure,
Set 1
driving mechanism.
3.3 Copper contact fingers for dis-connector male & female
contact for dis-connector of each type and rating Set 1

3.4 Copper contact fingers for earthing switch male & female
contacts, for one complete earthing switch of each type Set 1
and rating
3.5 Open / Close contactor assembly, timers, key interlock
for one complete (3 phase) dis-connector and (3 phase)
Set 1
earthing switch (1 No. of each type and rating)

3.6 Push button switch - (1 No. of each type & rating) as


Set 1
applicable
3.7 Limit switch and Aux. Switches for complete 3 phase
1
equipment
3.7.1 For isolator Set 1
3.7.2 For earth switch Set 1
3.B 145KV ISOLATORS :
3.1 Complete set of 3-phase dis-connector including main
Set 1
circuit, enclosure, driving mechanism
3.2 3-phase Earthing switch including main circuit, enclosure,
Set 1
driving mechanism.
3.3 Copper contact fingers for dis-connector male & female
contact for dis-connector of each type and rating Set 1

3.4 Copper contact fingers for earthing switch male & female
contacts, for one complete earthing switch of each type Set 1
and rating
3.5 Open / Close contactor assembly, timers, key interlock
for one complete (3 phase) dis-connector and (3 phase)
Set 1
earthing switch(1 No. of each type and rating)

3.6 Push button switch - (1 No. of each type & rating) as


Set 1
applicable
3.7 Limit switch and Aux. Switches for complete 3 phase
equipment
3.7.1 For isolator Set 1
3.7.2 For earth switch Set 1

4.0 A 245KV CURRENT TRANSFORMER


4.1 Gas insulated complete CT of each type and rating with
No. 1
enclosure.
4.2 Secondary bushing of each type Set 1
4.0 B 145KV CURRENT TRANSFORMER

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-2 Page 46 of 145

4.1 Gas insulated complete CT of each type and rating with


No. 1
enclosure.
4.2 Secondary bushing of each type Set 1

5.0 A 245kV Voltage Transformer


5.1 Gas insulated complete PT of each type and rating with
No. 1
enclosure.
5.0 B 145 kV Voltage Transformer
5.1 Gas insulated complete PT of each type and rating with
No. 1
enclosure.

(III) SPARES FOR AIS EQUIPMENTS


6.0A 220kV, 4400pF CVT No. 1
6.0B 132kV, 8800pF CVT No. 1

7.0A 216kV Surge Arrestor with insulating base, terminal


Set 2
connector , Surge counter & accessories
7.0B 120kV Surge Arrestor with insulating base, terminal
Set 2
connector , Surge counter & accessories
7.0C 30kV Surge Arrestor with insulating base, terminal
Set 2
connector , Surge counter & accessories

(IV) Relay & Protection panel


A Line Protection Panel
1 Numerical distance relay Set 1
2 Current Differential Relay No. 1
B Transformer Protection Panel
1 Transformer differential protection No. 1
Restricted earth fault protection relay with non-linear
No. 1
2 resistor
3 Directional O/C & E/F relay No. 1
C COMMON SPARES
1 Power supply module for Bus Bar protection. No. 1
2 Bay unit module Set 1

(V) Sub-Station Automation


A Bay control unit (IED) of each type Set 1
B Ethernet switch of each type Set 1

Digital Protection Coupler for Chilime Hub substation


(VI) No 1

(VII) LT Transformer
i) Bushing (1 no. of each type) Set 1
OTI & WTI with sensing device (1 no. of each type)
Set 1
ii)
iii) Diaphragm for pressure relief vent No. 1
iv) Silica Gel container No. 1
v) Set of valves Set 1
vi) Buchholz realy (if applicable) No. 1

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-2 Page 47 of 145

(VIII) Illumination System


i) 5% of each type of lighting fixture supplied Set 1

(IX) Erection Hardware items


5% spares of the actual quantities for Insulator strings
&hardwares, clamps & connectors (including equipment
Set 1
connectors), spacers, corona bell and welding sleeves
i)

(X) 33kV Indoor switchgear


i) CB Spring charge indicator (Mechanical) No. 1
ii) Mechanical ON/OFF indicator for CB No. 1
iii) Operation counter for CB No. 1
iv) CT (1-Phase) (1 no. of each type) Set 1
v) VT (1-Phase) No. 1
vi) Multi Function Meter No. 1
vii) Control switch for breaker(T-N-C) No. 2
viii) Green Indicating lamp for CB Open No. 5
ix) Red indicating lampfor CB Close No. 5
x) DC healthy lamp (white) No. 5
xi) Trip circuit healthy lamp No. 5
xii) Voltmeter with selector switch No. 1
xiii) Numerical protection relay (IED) No. 1
xiv) Master Trip Relay (86) (1 no. of each type) Set 1
Semaphore Indicator for Line Isolator & Line Earth
Set 5
xv) Switch (1 no. of each type)
xvi) LAN Switches and LAN/FO Cables No. 1
xvii) Trip coil assembly No. 2
xviii) Closing coil assembly No. 2

(XI) Communication Equipments


3.0 Mandatory Spares for Chilime Hub GIS
A
SDH Equipment (STM-4 MADM upto 5 MSP protected directions)
(i) Common cards, Cross-connect/control cards, Optical base card, Power
supply cards, power cabling, other hardware & accessories (each). Set 1

(ii) Optical Interface Cards/SFP


a S4.1 SFP Nos. 1
c L4.1 SFP Nos. 1
h L4.2 SFP Nos. 1
(iii) Tributary cards
a E1 Interface card (Min.16 interfaces per card) Nos. 1
b Ethernet Interface 10/100 Base T with Layer-2 switching (Min 8
Nos. 1
Interfaces per card)
B VOIP telephone instrument Nos. 1
C Pre Connectorized Optical Fiber Patch Cords(10 Mtrs) – Pack of six
Set 1
Patch cords

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-2 Page 48 of 145

SUB-TOTAL-C
Total for 220/132/33kV Chilime Hub GIS new
Substation (Package-2, Part-I) (I) (Part-A+ Part-B+ Part
C)

II 220(Hybrid)/132/33KV TRISHULI-3B HUB AIS NEW S/S


(Package-2, Part-II)

PART -A: OWNER ASSESSED QUANTITIES


A POWER TRANSFORMER
A.1 1-Ph Autotransformers
a) 53.33MVA, 220/√3 / 132/√3 / 33kV Single Phase Auto Nos. 7
Transformer (without transformer Oil)
b) Insulating oil for 53.33MVA , 220/132/33 KV, 1-phase Lot* 7
Autotransformer (* 1Lot = Oil for 1 Autotransformer )

c) No 2
33kV Current transformer (NCT) for autotrasnformer

A.2 3-Phase Power Transformer


50 MVA, 132 /33kV Three Phase Power Transformer
a) Nos. 1
(without transformer Oil)
Insulating oil for 50MVA , 132/33 KV, 3-phase Power
b) Transformer (* 1Lot = Oil for 1 Autotransformer ) Lot* 1

A.3 Testing & Maintenance Equipments


a) Oil Storage Tank of 20KL No. 1
b) Transformer Oil Filtration plant (6KLPH) No 1

B LT TRANSFORMER
1.0 630 kVA, 33/0.400kV Nos 2
C 245 KV EQUIPMENTS
C.1 245KV GIS HYBRID Equipment
1.1 245kV, SF6 GIS Hybrid Bus Coupler bay Module as per
section project
a) 3000A, 40kA for 1 sec Set 1
1.2 245kV, SF6 GIS Hybrid Bus Transfer Bus Coupler bay
Module as per section project
a) 3000A, 40kA for 1 sec Set 1
1.3 245kV, SF6 GIS Hybrid Line feeder bay Module as per
section project
a) 1600A, 40kA for 1 sec Set 6
1.4 245kV, SF6 GIS Hybrid ICT feeder bay Module as per
section project

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-2 Page 49 of 145

a) 1600A, 40kA for 1 sec Set 2

C.2 245KV Outdoor AIS Equipment (40kA for 1 sec)


1.1 216 KV Surge Arrester (1-phase) Nos. 25
1.2 245 kV, 4400pFCapacitive Voltage Transformer (1-Phase) Nos. 24
1.3 245 kV, 1600A, 40kA, DBR Isolator (Tandem type) (3- Nos. 8
1.4 Phase)
245kV Bus Post Insulator (1-Phase) (Except auxiliary
Nos. 50
buses of transformer)

Testing & Maintenance Equipment for 220kV GIS


C.3
Hybrid
1.1 SF6 Gas processing Unit Set 1
1.2 Partial Discharge Monitoring System (portable type) Set 1
1.3 Dew Point Meter Set 1
1.4 SF6 Gas Leak Detector Set 1

D 145 kV Equipment
1.0 145 kV Circuit Breakers (3-Phase) with support structure
a 1250A, 40kA Nos 7
b 2000A, 40kA Nos 1

2.0 145kV Isolator (3-phase)-Double Break


a 1250A, 40kA Isolator without E/S Nos 7
b 1250A, 40kA Isolator with one E/s Nos 14
c 1250A, 40kA Isolator without E/s (Tandem) Nos 7
d 1250 A, 40kA Isolator without E/S (Beam mounted) Nos 7
e 2000A, 40kA Isolator with two E/s Nos 2

3.0 145 kV Current Transformer (1-Phase)


a 1200A, 40kA with 120% extended current rating Nos 6
b 1200 A, 40kA with 150% extended current Nos 3
c 600 A, 40kA with 120% extended current Nos 15
d 600 A, 40kA with 120% extended current for tariff metering Nos 12

4.0 145 kV Capacitive Voltage Transformer (1- Phase)


a 8800 pF Nos. 18
b 8800 pF for tariff metering Nos. 12
5.0 120 kV Surge Arrestors
a 120 kV Surge Arrestors (1-phase) - Pedestal mounted Nos. 22
b 120 kV Surge Arrestors (1-phase) - suitable for mounting on Nos. 6
transmission line dead end tower

6.0 145 kV Bust Post Insulator (Except auxiliary buses of Nos 42


transformer)

E 33 kV Equipment

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-2 Page 50 of 145

1.0 36kV Circuit Breakers (3-Phase) with support structure


a 1250A, 25kA Nos 5

2.0 36kV Isolator (3-phase)-Double Break


a 1250A, 25kA, Isolator without E/S Nos 8
b 1250A, 25kA, Isolator with one E/s Nos 3
c 1250A, 25kA, Isolator without E/s (Tandem) Nos 5

3.0 36 kV HG Fuse along with support insulator (1-phase) Nos. 3

4.0 36kV Current Transformer (1-Phase)


a 1000A, 25kA with 120% extended current rating Nos 3
b 600 A, 25kA with 120% extended current Nos 12

5.0 36kV Voltage Transformer (1- Phase) Nos 3

6.0 30kV Surge Arrestors (1-phase) Nos. 12


7.0 36kV Bust Post Insulator (Except auxiliary & neutral buses of Nos 18
transformer)
F 72.5kV EQUIPMENT
1.1 72.5 kV, 1250A, 25kA Circuit Breaker (3-phase) with support structure No. 1

1.2 72.5 kV, 1250A, 25kA Isolators with earth switch (3-phase, DBR type) No. 1

1.3 72.5kV, 50A, 25 kA with 120% extended rating CT (1-phase) Nos. 3


1.4 72.5kV PT (1-phase) Nos. 3
1.5 72.5 kV BPI (1-phase) Nos. 6

G RELAY PANELS (WITH AUTOMATION)


1.0 220 kV
a Circuit Breaker Relay Panel
i With Auto Reclose Nos. 7
ii With out Auto Reclose Nos. 3
b Line Protection Panel
i Line Protection Panel with Distance Protection and Current Differential Nos. 6
Protection at Trishuli-3B Hub End
ii Line Protection Panel housing two nos. Current Differential Protection Nos. 1
relays & accessories at Matatirtha End
iii Line Protection Panel housing two nos. Current Differential Protection Nos. 1
relays & accessories at Upper Trishuli-1 End
c Transformer Protection Panel (For both HV & MV side) Nos. 2
d Bus Bar Protection Panel Set 1

2.0 132 kV
a Circuit Breaker Relay Panel
i With Auto Reclose Nos. 4
ii With out Auto Reclose Nos. 4

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-2 Page 51 of 145

b Line Protection Panel


i) Line Protection Panel with Current Differential Protection and Back up Nos. 4
O/C & E/F Protection at Trishuli-3B Hub End
ii) Line Protection Panel housing two nos. Current Differential Protection Nos. 1
relays & accessories at Trishuli-3A HPP End
iii) Line Protection Panel housing two nos. Current Differential Protection Nos. 1
relays & accessories at Trishuli-3B HPP End

c Transformer Protection Panel (For both HV & MV side) Nos. 1


d Bus Bar Protection Panel Set 1
3.0 33 kV
a Line Protection Panel Nos. 3
b Protection Panel for TBC bay Nos. 1
c Transformer Protection Panel Nos. 1
4.0 COMMON EQUIPMENTS
a Relay tool kit Set 1
b Time synchronisation equipment No. 1
H SUBSTATION AUTOMATION
H.1 Complete Substation Automation System (SAS) for substation including
hardware and software for the substation & remote control stations
alongwith associated equipments for the following bays as per
Technical Specification
a Main bays to be automated
i 220 kV system Bay Nos 10

ii Bays to be automated of existing 132 kV substation Bay Nos 8

iii Bays to be automated of existing 33 kV substation Bay Nos 5

iv BCU for controlling & monitoring of Auxilary System Set 1

I Digital Protection Coupler & PBAX


a) Digital Protection Coupler* Nos 12
b) PBAX with following configuration as per TS Set 1
i 2 wire subscriber interface card with capacity 32 local subscribers
(along with 32 nos. Instruments)
ii) E-1 interface with 2 trunks G-703
iii) 2 wire interface with 1 trunk (For PSTN)
* Digital protection Coupler for both ends for all 220kV Lines are
considered. However, Digital Protection coupler for 220kV Chilime
Hub - Trishuli-3B D/c Line have been considered at respective
substation end.

J LT Switchgear (As per Technical specification)


a 400V Main switchboard Set 1
b 400V ACDB Set 1
c 400V MLDB Set 1
d 400V Emergency LDB Set 1
e 220V DCDB Sets 2

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-2 Page 52 of 145

f 48V DCDB Set 2

K Batteries
a 220V
i 600 AH Nos 2
b 48V
i 600AH Nos 2

L Float Cum Boost Battery Charger


a 220V Float Cum Boost Battery Charger
i 90A/90A Nos 2
b 48V Float Cum Boost Battery Charger
i 90A/90A Nos 2

M Diesel Generator with control Panel


a 250 kVA Set 1

N Fire Protection System


a Portable /Trolley/Wheel mounted extinguishers
i 9 litre water type Nos 2
ii 50 litre foam type Nos 2
iii 4.5 kg CO2 type Nos 10
iv 4.5 kg Dry Chemical Power (DCP) type Nos 6
b Smoke detection system Set 1
c Fire detection and Alarm System Set 1

O.1 Cables along with clamps, glands, lugs and straight joints etc.

b Power Cables - (1.1kV grade)


i 3.5Cx300 sqmm (XLPE) cable for filter Machine along with termination KM 1
arrangement as per TS

O.2 132kV XLPE Power Cable for interconnection of 132kV Trishuli-


3B HPP Line Bay with Dead end Tower
a) 132kV, XLPE insulated , 1C X 1600 sqmm size copper cable as per kM 1.5
technical specificaion.(Metallic sheath and PE outer sheathed with
graphite coating and short circuit current 40kA for 1 sec) including one
spare cable
b) Cable termination as per technical specification for interconnection with Nos 12
overhead transmission for cable at sl. No. 1 above (excluding
terminating structure)
c) Single phase earth link box Nos 12
d) 36kV grade 1Cx300 Sqmm Earth Continuity Cable kM 0.4

P Air conditioning System for Control room cum administrative


building
a High wall type split AC unit of 2 TR capacity Nos 20

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-2 Page 53 of 145

Q Lattice/pipe Structure for towers,beams and equipments including peak


plates/pack washers and guest paltes including foundation
bolts(nuts,washers,MS plate welded at the bottom)
(a) Lattice stucture & foundation bolts MT 420
(b) Pipe structure & foundation bolts MT 30
(c ) Fastners for towers,beams and equipment support strcutures MT 20

R.1
Communication equipments for Trishuli-3B Hub Substation
1.0 Telecom Equipments

A1
SDH Equipment (STM-4 MADM upto 5 MSP protected directions)
(i) Base Equipment (Common cards, Cross Connect/control cards, optical
base cards, power supply cards, power cabling, other hardware and
accessories including sub racks, patch cord, DDF etc fully equiped Nos. 2
excluding (ii) & (iii) below

(ii) Optical Interface Cards/SFP


a S4.1 SFP Nos. 10
b L4.1 SFP Nos. 4
c L4.2 SFP Nos. 2

(iii) Tributary cards


a E1 Interface card (Min.16 interfaces per card) Set 4
b Ethernet Interface 10/100 Base T with Layer-2 switching (Min 8
Nos. 4
Interfaces per card)

B Equipment Cabinets No. 1

2.0 Network Manager System - Craft Terminal


a Hardware Set 1
b Software Set 1

3.0
VOIP telephone instrument with one common switch (min. 8 port) Nos. 2

R.2 Communication equipments for Trishuli-3B HPP


1.0 Telecom Equipments
A1
SDH Equipment (STM-4 MADM upto 3 MSP protected directions)
(i) Base Equipment (Common cards, Cross Connect/control cards, optical
base cards, power supply cards, power cabling, other hardware and
Nos. 1
accessories including sub racks, patch cord, DDF etc fully equiped
excluding (ii) & (iii) below

(ii) Optical Interface Cards/SFP


a S4.1 SFP Nos. 2

(iii) Tributary cards


a E1 Interface card (Min.16 interfaces per card) Set 2

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-2 Page 54 of 145

b Ethernet Interface 10/100 Base T with Layer-2 switching (Min 8


Nos. 2
Interfaces per card)

B Equipment Cabinets No. 1

2.0 Network Manager System - Craft Terminal


a Hardware Set
b Software Set

3.0
VOIP telephone instrument with one common switch (min. 8 port) Nos. 2

Sub-Total Part-A

Part-B: VENDOR ASSESSED QUANTITIES

A Erection Hardware

Insulator strings, Disc Insulators, Hardware, conductor, Al tube, bus-bar


materials, cable trays, Bay MB, clamps, spacers, connectors including
equipment connectors, Junction box, earthwire, buried cable
trenches/pipe equipment & lighting, all accessories etc. for the
following:
a 220 kV Layout (DMT Layout with GIS Hybrid)
i Line Bay Set 6
ii Transformer Bay Set 2
iii TBC Bay Set 1
iv BC bay Set 1
v Bus work (Three Bays) Set 1
vi Bus work (Four Bays) Set 1

b 132 kV (Double Main Layout with bypass breaker arrangement)

i Line Bay Set 4


ii Transformer Bay Set 3
iii BC bay Set 1
iv Bus work (Three Bays) Set 2
v Bus work (Four Bays) Set 1

c Set 1
For spare unit of 220/132/33kV auto transformer connection through
auxiliary buses, Neutral formation and delta formation (for two banks):
Required 245 kV BPI for HV auxiliary bus, 132 kV BPI for 132 kV
Auxilary bus, 72.5 kV BPI for tertiary auxilary bus & delta formation, 36
kV BPI for Neutral formation & Neutral auxiliary bus including Al tube,
bus-bar materials, clamps, spacers, connectors, including equipment
connectors, support structures, Earthing of spare unit as per technical
specification.

d Erection Hardware etc for 72.5kV & 33kV equipments & LT Set 1
Transformer connection

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-2 Page 55 of 145

e Earthing and lightning protection including necesaary


connectors/connections, risers etc. complete in all respect ( but
excluding LM structures for Lightning protection)
i Earth Conductor (copper) LS 1
ii Earth Rod (copper clad steel) LS 1
iii Equipment for lightning protection LS 1

B Fire Protection System


a Pumping arrangement for HVW system & hydrant system, complete
with all piping, valves, fittings,etc. inside pump house

i 220/132/33kV (New) Substation Set 1


b Hydrant system, complete U/G piping and accessories etc. outside the
Pump House.
i 220/132/33kV (New) Substation Set 1
c HVW spray system, Hydrant system and complete U/G & O/G piping
and accessories etc. out side the pump house for Transformer :

c.1 Transformer
i 53.33MVA , 220/132/33 KV, 1-phase Autotransformer Set 7
i 50MVA , 132/33 KV, 3-phase Power Transformer Set 1

C Illumination System
a Fire fighting building illumination (100 sqmm) LS 1
b Illumination System for switchyard panel room
i 220KV Set 4
ii 132KV Set 3
iii 33kV Set 1
c Control room cum administrative building illumination (1000 sqmm) LS 1
d Switchyard lighting LS 1
e Street lighting LS 1
h Transit camp (420 sqmm) LS 1
j Security room (10 sqmm) LS 1
k Car parking shed (for 10 cars) LS 2

D Air conditioning System


a Air conditioning for S/Y panel room
i 220KV Set 4
ii 132KV Set 3
iii 33kV Set 1
E POWER & CONTROL CABLES
i For 220/132/33kV Trishuli-3B Hub Substation:
a Power Cables(PVC) - (1.1kV grade) LS 1
b Power Cables (XLPE) - (1.1kV grade) LS 1
c Control Cable (PVC) - (1.1kV grade) LS 1
LS 1
d Cable glands, lugs & straight through joints for Power & Control cables
ii For 220kV Upper Trishuli-1 HPP Switchyard:
a Power Cables(PVC) - (1.1kV grade) LS 1

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-2 Page 56 of 145

b Control Cable (PVC) - (1.1kV grade) LS 1


LS 1
c Cable glands, lugs & straight through joints for Power & Control cables
iii For 220kV Matatirtha Substation:
a Power Cables(PVC) - (1.1kV grade) LS 1
b Control Cable (PVC) - (1.1kV grade) LS 1
LS 1
c Cable glands, lugs & straight through joints for Power & Control cables
iv For 132kV Upper Trishuli-3B HPP Switchyard:
a Power Cables(PVC) - (1.1kV grade) LS 1
b Control Cable (PVC) - (1.1kV grade) LS 1
LS 1
c Cable glands, lugs & straight through joints for Power & Control cables
v For 132kV Trishuli-3A HPPSwitchyard:
a Power Cables(PVC) - (1.1kV grade) LS 1
b Control Cable (PVC) - (1.1kV grade) LS 1
LS 1
c Cable glands, lugs & straight through joints for Power & Control cables
vi For 132kV Samundratar Substation:
a Power Cables(PVC) - (1.1kV grade) LS 1
b Control Cable (PVC) - (1.1kV grade) LS 1
LS 1
c Cable glands, lugs & straight through joints for Power & Control cables

Sub-Total Part-B

Part-C: Mandatory Spares

(I) Mandatory Spare List for Autotransformer


A For 53.33MVA , 220/132/33 KV, 1-phase
Autotransformer
a) Bushing of each rating with metal parts & gaskets and Set 1
lifting tools
b) Cooler fan with Motor No. 1
c) Buchholz Relay(Main Tank) complete with floats and Set 1
contacts
d) Local and Remote WTI with sensing device and Set 1
contact(each)
e) Magnetic oil level gauge No. 1
f) Strarters, contactors,switches & Relays for Electrical Set 1
control panels(One ste of each type)
g) Remote Tap postion Indiactor No. 1
h) Spare insulating oil to be handed over to Owner after KL 10
commisioning for O&M requirement
B
For 50MVA , 132/33 KV, 3-phase Power Transformer
a) Bushing of each rating with metal parts & gaskets and Set 1
lifting tools
b) Cooler fan with Motor No. 1

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-2 Page 57 of 145

c) Buchholz Relay(Main Tank) complete with floats and Set 1


contacts
d) Local and Remote WTI with sensing device and Set 1
contact(each)
e) Magnetic oil level gauge No. 1
f) Strarters, contactors,switches & Relays for Electrical Set 1
control panels(One ste of each type)
g) Remote Tap postion Indiactor No. 1
h) Spare insulating oil to be handed over to Owner after KL 5
commisioning for O&M requirement

(II) 245kV GIS Hybrid


1 General
1.1 SF6 gas Pressure Relief Devices, 1Nos. of each type
Set 1
1.2 SF6 Pressure gauge cum switch OR Density monitors and
pressure switch as applicable (1 no. of each type) Set 1

1.3 Coupling device for pressure gauge cum switch for


Set 1
connecting Gas handling plant
1.4 Rubber Gaskets, “O” Rings and Seals for SF6 gas of each
Set 1
type
1.5 Molecular filter for SF6 gas with filter bags(20% of total
Set 1
weight)
1.6 All types of Control Valves for SF6 gas of each type Set 1
1.7 SF6 gas (20 % of total gas quantity) Set 1
1.8 All types of coupling for SF6 gas (1 no. of each type)
Set 1
1.9 Pipe length (Copper or Steel as applicable) for SF6 Circuit
Set 1
of each type
1.10 Locking device to keep the Dis-connectors (Isolators) and
Earthing switches in close or open position in case of
Set 1
removal of the driving Mechanism

1.11 SF6 to air bushing (220kV - 1 No. of each type & rating)
Set 1
as applicable

2 245KV SF6 CIRCUIT BREAKER:


2.1 Complete Circuit Breaker pole of each type & rating
complete with interrupter, main circuit enclosure and
No. 1
Marshalling Box with operating mechanism

2.2 Rubber gaskets, `O' rings and seals for SF6 gas (1 No. of
Set 1
each type)
2.3 Trip coil assembly with resistor as applicable Set 1
2.4 Closing coil assembly with resistor as applicable . Set 1
2.5 Relays, Power contactors, push buttons, timers & MCBs
Set 1
etc (1 No. of each type & rating)

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-2 Page 58 of 145

2.6 Closing coil assembly (including valve, if applicable)


Set 1
2.7 Trip coil assembly (including valve, if applicable) Set 1
2.8 Auxiliary switch assembly of each type Set 1

3 245KV ISOLATORS :
3.1 Complete set of 3-phase dis-connector including main
Set 1
circuit, enclosure, driving mechanism
3.2 3-phase Earthing switch including main circuit, enclosure,
Set 1
driving mechanism.
3.3 Copper contact fingers for dis-connector male & female
contact for dis-connector of each type and rating Set 1

3.4 Copper contact fingers for earthing switch male & female
contacts, for one complete earthing switch of each type Set 1
and rating
3.5 Open / Close contactor assembly, timers, key interlock
for one complete (3 phase) dis-connector and (3 phase)
Set 1
earthing switch (1 No. of each type and rating)

3.6 Push button switch - (1 No. of each type & rating) as


Set 1
applicable
3.7 Limit switch and Aux. Switches for complete 3 phase
1
equipment
3.7.1 For isolator Set 1
3.7.2 For earth switch Set 1
4 245KV CURRENT TRANSFORMER
4.1 Gas insulated complete CT of each type and rating with
No. 1
enclosure.
4.2 Secondary bushing of each type Set 1
(III) 145kV CB
i) Complete Pole of circuit breaker including pole column, interrupter,
with driving mechanism and Marshaling Box but without support
structure for
1250A, 31.5kA (No. of Pole) No. 1
ii) Rubber gaskets, `O' rings and seals ( for complete replacement of one Set 1
pole of CB)
iii) Trip coils with resistor Nos. 2
iv) Closing coils with resistor Nos. 1
v) Terminal Pads & connectors Nos. 2
vi) Molecular filter Nos. 2
vii) Relays, Power contactors, switch fuse units, limit switches, push Set 1
buttons, timers & MCB etc. (1 no. of each type)
viii) Pressure switches / Density monitor (1 no. of each type) Set 1
ix) Auxiliary switch assembly (for one pole of CB) Set 1
(III) 72.5kV CB
i) Complete Pole of circuit breaker including pole column, interrupter,
with driving mechanism and Marshaling Box but without support
structure for
1250A, 31.5 KA (No. of Pole) No. 1

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-2 Page 59 of 145

ii) Rubber gaskets, `O' rings and seals ( for complete replacement of one Set 1
pole of CB)
iii) Trip coils with resistor Nos. 2
iv) Closing coils with resistor Nos. 1
v) Terminal Pads & connectors Nos. 2
vi) Molecular filter Nos. 2
vii) Relays, Power contactors, switch fuse units, limit switches, push Set 1
buttons, timers & MCB etc. (1 no. of each type)
viii) Pressure switches / Density monitor (1 no. of each type) Set 1
ix) Auxiliary switch assembly (for one pole of CB) Set 1
(IV) 245kV Isolator
i) One complete pole including support Insulator, motor operating
mechanism (MOM) with box but excluding structure
1600A, 40 KA, 1 E/S (no. of pole) No. 1
ii) Copper contact fingers for male & female contacts ( for one pole of Set 2
Isolator)
iii) Open/Close contactor assembly, timers, key interlock push button Set 1
switch & auxilliary switches (for one pole of Isolator)
iv) Limit Switch Nos. 2
v) Terminal Pads & Connectors Nos. 3
vi) Corona shield rings Nos. 3
(V) 145kV Isolator
i) One complete pole including support Insulator, motor operating
mechanism (MOM) with box but excluding structure
1250A, 31.5kA with1 E/S (no. of pole) No. 1
ii) Copper contact fingers for male & female contacts ( for one pole of Set 2
Isolator)
iii) Open/Close contactor assembly, timers, key interlock push button Set 1
switch & auxilliary switches (for one pole of Isolator)
iv) Limit Switch Nos. 2
v) Terminal Pads & Connectors Nos. 3
vi) Corona shield rings Nos. 3
(VI) 72.5 kV Isolator
i) One complete pole including support Insulator, MANUAL operating
mechanism with box but excluding structure
1250A, 25kA, 1 E/S (no. of pole) No. 1
ii) Copper contact fingers for male & female contacts ( for one pole of Set 2
Isolator)
iii) Open/Close contactor assembly, timers, key interlock push button Set 1
switch & auxilliary switches (for one pole of Isolator)
iv) Limit Switch Nos. 2
v) Terminal Pads & Connectors Nos. 3

(VII) 36kV Isolator


i) One complete pole including support Insulator, MANUAL operating
mechanism with box but excluding structure
630A, 25KA, 1 E/S (no. of pole) No. 1
ii) Copper contact fingers for male & female contacts ( for one pole of Set 2
Isolator)
iii) Open/Close contactor assembly, timers, key interlock push button Set 1
switch & auxilliary switches (for one pole of Isolator)

iv) Limit Switch Nos. 2

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-2 Page 60 of 145

v) Terminal Pads & Connectors Nos. 3

(VIII) 72.5kV, 1250A, 31.5 kA with 120% extended rating CT (1-phase) No. 1

(IX) CVT (245 kV,4400 pF) (1-phase) No. 1

(X) 72.5kV PT (1-phase) No. 1

(XI) 216 SA
i) Complete LA (1-phase) No. 1
ii) Surge counter/monitor Nos. 5
(XII) 120kV SA
i) Complete LA (1-phase) No. 1
ii) Surge counter/monitor Nos. 5
(XIII) 30kV SA
i) Complete LA (1-phase) No. 1
ii) Surge counter/monitor Nos. 5

(XIV) C&R PANELS


i) Transformer protection panel :
a) Transformer differential protection No. 1
b) REF protection relay with non-linear resistor No. 1
c) Directional over current & E/F Protection Relay No. 1
ii) Line protection panel :
a) Distance Protection relay Set 1
b) Current differential Protection relay Set 1
iv) Breaker Relay panel:
a) Breaker failure relay No. 1
b) Trip circuit supervision relay Nos. 2
c) Self reset trip relay (relay of each type) Set 1
d) Hand reset trip relay(relay of each type) Set 1
e) Timer relay(relay of each type) Set 1
f) DC supervision relay(relay of each type) Set 1
g) Flag relays(relay of each type) Set 1
h) Auxiliary relays(relay of each type) Set 1

(XV) Teleprotection Equipments


i) Set of prints for protection coupler (digital ) Set 1

(XVI) SAS
i) Bay Control Unit (IED) of each type Set 1
ii) Ethernet Switch of each type Set 1

(XVII) BATTERY CHARGER( 220kV)


i) Set of control cards Set 1
ii) Set of relays Set 1

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-2 Page 61 of 145

iii) Rectifier transformer No. 1


iv) Thyristor/diode Set 1
v) Fuses of Thyristor with indicators Set 6

(XVIII) COMMON SPARES


i) Bay unit Module No. 1
ii) 2 wire local subscriber interface card for PABX No. 1
iii) E1 Interface card for PABX No. 1
(XIX) Mandatory Spares of Communication Equipments
1.0 Mandatory Spares for Trishuli-3B Hub

A
SDH Equipment (STM-4 MADM upto 5 MSP protected directions)
(i) Common cards, Cross-connect/control cards, Optical base card, Power
supply cards, power cabling, other hardware & accessories (each). Set 1

(ii) Optical Interface Cards/SFP


a S4.1 SFP Nos. 1
c L4.1 SFP Nos. 1
h L4.2 SFP Nos. 1

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-2 Page 62 of 145

(iii) Tributary cards


a E1 Interface card (Min.16 interfaces per card) Nos. 1
b Ethernet Interface 10/100 Base T with Layer-2 switching (Min 8
Nos. 1
Interfaces per card)

B VOIP telephone instrument Nos. 1

C Pre Connectorized Optical Fiber Patch Cords(10 Mtrs) – Pack of six


Set 1
Patch cords

2.0 Mandatory Spares for Trishuli-3B HPP

A
SDH Equipment (STM-4 MADM upto 3 MSP protected directions)
(i) Common cards, Cross-connect/control cards, Optical base card, Power
supply cards, power cabling, other hardware & accessories (each). Set 1

(ii) Optical Interface Cards/SFP


a S4.1 SFP Nos. 1

(iii) Tributary cards


a E1 Interface card (Min.16 interfaces) Nos. 1
b Ethernet Interface 10/100 Base T with Layer-2 switching (Min 8
Nos. 1
Interfaces per card)

B VOIP telephone instrument Nos. 1

C Pre Connectorized Optical Fiber Patch Cords(10 Mtrs) – Pack of six


Set 1
Patch cords

SUB-TOTAL-C
Total for 220/132/33kV Trishuli Hub AIS new Substation
(Package-2, Part-II) (II) (Part-A+ Part-B+ Part C)

Total of Schedule-2
Date: Signature:

Place: Printed Name:

Designation:

Common Seal:

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-3 Page 63 of 145

Package-2 for 220/132/33kV Chilime Hub GIS new substation (Part-I) and 220(Hybrid)/132/33kV Trishuli-3B Hub AIS new substation (Part-II) under 220kV Chilime-Trishuli Transmission System Project

(Schedule of rates and prices)

Bidder's Name & Address:

Local Transportation, Insurance and other incidental services (including port clearance etc.) applicable for supply of Plant & Equipment.

1 2 3 4 5 6 7 8=6x7
Sl. No. Item Description Country of Origin Type & Unit Quantity Unit Price Total Price
Designation (NPR) (NPR)

I. 220/132/33kV CHILIME HUB GIS new Substation


(Package-2, Part-I)

PART - A: OWNER ASSESSED QUANTITIES


A POWER TRANSFORMER
A.1 1-Phase Auto Transformer
53.33MVA, 220/√3 / 132/√3 / 33kV Single Phase Auto
a) Nos. 7
Transformer (without transformer Oil)
Insulating oil for 53.33MVA , 220/132/33 KV, 1-phase
b) Autotransformer (* 1Lot = Oil for 1 Autotransformer ) Lot* 7

c) 33kV Current transformer (NCT) for autotrasnformer No 2

A.2 POWER TRANSFORMER


50 MVA, 132 /33kV Three Phase Power Transformer
a) Nos. 1
(without transformer Oil)
Insulating oil for 50MVA , 132/33 KV, 3-phase Power
b) Transformer (* 1Lot = Oil for 1 Autotransformer ) Lot* 1

A.3 Testing & Maintenance Equipments

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-3 Page 64 of 145

a) Oil Storage Tank of 20KL No. 1


b) Transformer Oil Filtration plant (6KLPH) No 1

B) LT Transformer
a) 630KVA, 33/0.400 kV Nos. 2

C 245 KV EQUIPMENTS
C1 245KV GIS Equipment
1.1 245kV, SF6 GIS Bus Bars Module as per section project

a) 3000A, 40kA for 1 sec Sets 2


1.2 245kV, SF6 GIS Bus Coupler feeder bay Module as per
section project
a) 3000A, 40kA for 1 sec Sets 1
1.3 245kV, SF6 GIS Line feeder bay Module as per section
project
a) 1600A, 40kA for 1 sec Sets 2
1.4 245kV, SF6 GIS spare Line feeder bay Module as per
section project
a) 1600A, 40kA for 1 sec Sets 1
1.5 245kV, SF6 GIS ICT feeder bay Module as per section
project
a) 1600A, 40kA for 1 sec Sets 2
1.6 245kV, SF6 GIS Auxiliary Bus Module as per section
project to connect spare unit of Transformer

a) 1600A, 40kA for 1 sec Set 1


1.7 SF6 Gas Insulated Bus Duct (GIB) outside GIS Hall
alongwith associated support structure and accessories
(for Transformer bays)
a) 1600A, 40kA for 1 sec. Single Phase Mtr. 460
1.8 SF6 Gas Insulated Bus Duct (GIB) outside GIS Hall
alongwith associated support structure and accessories
(for Line bays)
a) OPTION-I
1600A, 40kA for 1 sec. Single Phase Mtr. 225
b) OPTION-II
1600A, 40kA, 1sec three phase Mtr. 75

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-3 Page 65 of 145

Note : Bidder is required to quote for either option-I or


Option-II
1.9 220kV, SF6 to Air Bushing alongwith associated support
structure (for Transformer bays)
a) 1600A, 40kA for 1 sec. Single Phase Nos. 7
1.10 220kV, SF6 to Air Bushing alongwith associated support
structure (for line bays)
a) OPTION-I
1600A, 40kA for 1 sec. Single Phase Nos. 9
b) OPTION-II
1600A, 40kA, 1sec three phase Nos. 3
Note : Bidder is required to quote for either option-I or
Option-II

C.2 245KV Outdoor AIS Equipment


1.1 216 KV Surge Arrester (1-phase) Nos. 16
1.2 4400pF, 245 kV Capacitive Voltage Transformer (1- Nos. 9
1.3 Phase) Bus Post Insulator (1-Phase)
245kV Nos. 9

D 145kV Equipment
D.1 145KV GIS Equipment
1.1 145kV, SF6 GIS Bus Bars Module as per section project

a) 2000A, 40kA for 1 sec Set 2


1.2 145kV, SF6 GIS Bus Coupler feeder bay Module as per
section project
a) 2000A, 40kA for 1 sec Set 1
1.3 145kV, SF6 GIS Line feeder bay Module as per section
project
a) 1250A, 40kA for 1 sec Sets 4
1.4 145kV, SF6 GIS Spare Line feeder bay Module as per
section project
a) 1250A, 40kA for 1 sec Set 1
1.5 145kV, SF6 GIS ICT feeder bay Module as per section
project for 220/132 kV Transformer
a) 1250A, 40kA for 1 sec Set 2
1.4 145kV, SF6 GIS ICT feeder bay Module as per section
project for 132/33 kV Transformer
a) 1250A, 40kA for 1 sec Set 1

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-3 Page 66 of 145

1.6 145kV, SF6 GIS Auxiliary Bus Module as per section


project to connect spare unit of Transformer

a) 1250A, 40kA for 1 sec Set 1


1.7 SF6 Gas Insulated Bus Duct (GIB) outside GIS hall
including Bus Duct support structure and associated
a) 1250A, 40kA 1sec single phase (for 7x53.33MVA 1-
Mtr 395
Phase Transformer bays)
b) 1250A, 40kA 1sec three phase Mtr 300
1.8 145kV, SF6 to Air Bushing alongwith associated support
structure
a) 1250A, 40kA 1sec three phase Set 5
b) 1250A, 40kA 1sec single phase Set 7

D.2 145kV Outdoor AIS EQUIPMENT


1.0 120 kV Surge Arrestors (1-Phase) Nos. 25
2.0 8800pF, 145 kV Capacitive Voltage Transformer (1-
Nos. 15
Phase)
3.0 8800pF, 145 kV Capacitive Voltage Transformer (1-
Nos. 15
Phase) (for tariff metering)
4.0 145KV Bus Post Insulator Nos. 9

E 72.5kV EQUIPMENT
1.1 72.5 kV, 1250A, 25kA Circuit Breaker (3-phase) with No. 1
support structure
1.2 72.5 kV, 1250A, 25kA Isolators with earth switch (3- No. 1
phase, DBR type)
1.3 72.5kV, 50A, 25 kA with 120% extended rating CT (1- Nos. 3
phase)
1.4 72.5kV PT (1-phase) Nos. 3
1.5 72.5 kV BPI (1-phase) Nos. 6

F 33kV Equipments
1.1 33 kV, 630A, 25kA Isolators with out earth switch (3- No. 1
phase, DBR type)
1.2 30 kV Surge Arrestors (1-phase) Nos. 3
1.3 36 kV BPI (1-phase) Nos. 3
1.4 36 kV HG Fuse along with support insulator (1-phase) Nos. 3

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-3 Page 67 of 145

G 33kV, 25 kA (3 Phase) Indoor switch gear panel


including control, relay & protection
i) 33kV Line bay Module Nos 2
ii) 33kV Incomer Transformer Module Nos 1
iii) 33kV LT Transformer Module Nos 1
iv) 33kV Bus Sectionalizer Module Nos 1
v) 33kV Bus PT Module Nos 2

H Testing & Maintenance Equipment for GIS


1.1 SF6 Gas processing Unit Set 1
1.2 Partial Discharge Monitoring System (Portable type) Set 1
1.3 Dew Point Meter Set 1
1.4 SF6 Gas Leak Detector Set 1
1.5 Portable Ladder with adustable height as per TS Nos. 1
1.6 EOT crane for 220kV GIS Hall Set 1
1.7 EOT crane for 132kV GIS Hall Set 1

I RELAY PANELS (WITH AUTOMATION)


1 245kV
1.1 Circuit Breaker Relay Panel
a) CB Relay Panel With Auto Reclose Nos. 3
b) CB Relay Panel Without Auto Reclose Nos. 3
1.2 Line Protection Panel
Line Protection Panel with Distance Protection and
a) Nos. 3
Current Differential Protection at Chilime GIS End
1.3 Transformer Protection Panel (For both HV & MV side) Nos. 2

1.4 Bus Bar Protection Panel set 1


2 145kV
2.1 Circuit Breaker Relay Panel
a) CB Relay Panel With Auto Reclose Nos. 5
b) CB Relay Panel Without Auto Reclose Nos. 4
2.2 Line Protection Panel

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-3 Page 68 of 145

Line Protection Panel with Current Differential Protection


a) Nos. 5
and Back up O/C & E/F Protection at Chilime GIS End
Line Protection Panel housing two nos. Current
b) Differential Protection relays & accessories at Nos. 1
Rasuagadi HPP End
Line Protection Panel housing one no. Current
c) Differential Protection relay & accessories at Upper Nos. 1
Sanjen HPP End
Line Protection Panel housing one no. Current
d) Differential Protection relay & accessories at Lower Nos. 1
Sanjen HPP End
2.3 Transformer Protection Panel (For both HV & MV side) Nos. 1

2.4 Bus Bar Protection Panel set 1

3 Other/Common equipments Pertaining to C & R System


a) Time Synchronisation Equipment No. 1
b) Relay Test kit No. 1

J SUBSTATION AUTOMATION
Substation Automation System as per Technical
1
Specification:
a) 220kV System (Nos. of bays) Nos. 6
b) 132 kV System (Nos. of bays) Nos. 9
c) BCU for auxilary system set 1
d) 33 kV HT Indoor Switchgear set 1
K Digital Protection Coupler& PBAX
a) Digital Protection Coupler* Nos 2
b) PBAX with following configuration as per TS Set 1
i 2 wire subscriber interface card with capacity 32 local
subscribers (along with 32 nos. Instruments)
ii) E-1 interface with 2 trunks G-703
iii) 2 wire interface with 1 trunk (For PSTN)
*Digital Protection coupler for 220kV Chilime Hub -
Trishuli-3B D/c Line have been considered at respective
substation end.

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-3 Page 69 of 145

L LT Switchgear (As per Technical specification)


a 400V Main switchboard Set 1
b 400V ACDB Set 1
c 400V MLDB Set 1
d 400V Emergency LDB Set 1
e 220V DCDB Sets 2
g 48V DCDB Set 2

M Batteries
a 220V
i 800 AH Nos 2
b 48V
i 600AH Nos 2

N Float Cum Boost Battery Charger


a 220V Float Cum Boost Battery Charger
i 90A/90A Nos 2
b 48V Float Cum Boost Battery Charger
i 90A/90A Nos 2

O Diesel Generator with control Panel


a 250 kVA Set 1

P Fire Protection System


a Portable /Trolley/Wheel mounted extinguishers
i 9 litre water type Nos 2
ii 50 litre foam type Nos 2
iii 4.5 kg CO2 type Nos 10
iv 4.5 kg Dry Chemical Power (DCP) type Nos 6
b Smoke detection system Set 1
c Fire detection and Alarm System Set 1

Q Cables along with clamps, glands, lugs and straight


joints etc.
a 33kV HT XLPE Power Cable alongwith accessories and
termination equipments
i) 1Cx600 Sq.mm KM 2.5
ii) 1Cx300 Sq.mm KM 2
b Power Cables - (1.1kV grade)

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-3 Page 70 of 145

i 3.5Cx300 sqmm (XLPE) cable for filter Machine along KM 1


with 2 nos outdoor receptacles -250A

R Air conditioning
High wall type split AC unit of 2 TR capacities for control Nos. 25
1
room, relay room and battery room

S STEEL STRUCTURES (Tower,Gantry structures&


Equipment support structures)
a Lattice/pipe Structure for towers,beams and equipments
including peak plates/pack washers and guest paltes
including foundation bolts(nuts,washers,MS plate
welded at the bottom)
i) Lattice stucture & foundation bolts MT 90
ii Pipe structure & foundation bolts MT 10
b Fastners for towers,beams and equipment support MT 6
strcutures

T Communication Equipment for Chilime Hub GIS


1.0 Telecom Equipments

A1
SDH Equipment (STM-4 MADM upto 5 MSP protected directions)
(i) Base Equipment (Common cards, Cross Connect/control cards, optical
base cards, power supply cards, power cabling, other hardware and
accessories including sub racks, patch cord, DDF etc fully equiped Nos. 1
excluding (ii) & (iii) below

(ii) Optical Interface Cards/SFP


a S4.1 SFP Nos. 6
b L4.1 SFP Nos. 2
c L4.2 SFP Nos.

(iii) Tributary cards


a E1 Interface card (Min.16 interfaces per card) Set 2
b Ethernet Interface 10/100 Base T with Layer-2 switching (Min 8
Nos. 2
Interfaces per card)

B Equipment Cabinets No. 1

2.0
VOIP telephone instrument with one common switch (min. 8 port) Nos. 2

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-3 Page 71 of 145

SUB TOTAL PART-A

PART-B: VENDOR ASSESSED QUANTITIES

Erection Hardware :-Insulator strings, Disc Insulators,


Hardware, conductor, bus-bar materials, cable trays,
clamps, spacers, connectors including conectors for
A
Auto Transformer , Junction box, earthwire, earthing
material risers, buried cable trenches/pipe of equipment
& lighting, all accessories etc. for the following:

1
220 kV DM-type layout for GIS termination
arrangement
1.1 Line Bay Set 3
1.2 Transformer Bay Sets 2

132 kV DM-type layout for GIS termination


2
arrangement
1.1 Line Bay Sets 5
1.2 Transformer Bay Sets 3

3 33 KV
3.1 Line Bay Set 2
3.1 Transformer Bay Set 1
3.3 LT Transformer Bay Set 1

Erection Hardware etc for 72.5kV equipments & LT


4 Set 1
Transformer connection

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-3 Page 72 of 145

For spare unit of 220/132/33kV auto transformer


connection through auxiliary buses, Neutral formation
and delta formation (for two banks): Required 245kV
BPI, 132 kV BPI, 72.5kV BPI for tertiary auxilary bus &
B delta formation, 36kV BPI for Neutral formation & Set 1
Neutral auxiliary bus including Al tube, bus-bar
materials, clamps, spacers, connectors, including
equipment connectors, support structures , Earthing of
spare unit as per technical specification

C Ventilation & heating System


Ventilation & heating system (as per technical
2
specification)
(i) 220kV GIS Hall LS 1
(ii) 132 kV GIS Hall LS 1

D Illumination System
1.1 Substation Lighting
Control Room cum administrative building illumination LS 1
(i)
(1000 sqmm)
(ii) 220kV GIS Building (620 sqmm) LS 1

(iii) 132kV GIS Building (350 sqmm) LS 1

(iv) 33kV Indoor Switchyrad Panel Room (160 sqmm) LS 1


(v) Fire Fighting Pump house (100 sqmm) LS 1
(vi) Outdoor Switchyard Lighting LS 1
(vii) Street Lighting LS 1
(viii) Occupancy sensor LS 1
1.2 Transit Camp (420 sqmm) LS 1
1.3 Township Area (Staff Quarter area) Lighting LS 1
(i) B type (250 sqmm) LS 1
(ii) C type (300 sqmm) LS 1

(iii) D type (200 sqmm) LS 1


1.4 Security room (10 sqmm) LS 1
1.5 Car parking shed (for 10 cars) LS 2

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-3 Page 73 of 145

E Fire Protection System (as per technical set 1


1 Specification)
Pumping arrangement inside pump house set 1
2 Hydrant system outside the Pump House. set 1
3 HVW spray system & Hydrant system for Transformer :
53.33MVA, 220/132 kV Single Phase Auto Transformer
a nos 7

b 50 MVA,132/33 kV Three phase transformer nos 1

F POWER & CONTROL CABLES


i For 220/132/33kV Chilime Hub GIS Substation:
a Power Cables(PVC) - (1.1kV grade) LS 1
b Power Cables (XLPE) - (1.1kV grade) LS 1
c Control Cable (PVC) - (1.1kV grade) LS 1
LS 1
d Cable glands, lugs & straight through joints for Power & Control cables
ii For 132kV Upper Sanjen HPP Switchyard:
a Power Cables(PVC) - (1.1kV grade) LS 1
b Control Cable (PVC) - (1.1kV grade) LS 1
LS 1
c Cable glands, lugs & straight through joints for Power & Control cables
iii For 132kV Lower Sanjen HPP Switchyard:
a Power Cables(PVC) - (1.1kV grade) LS 1
b Control Cable (PVC) - (1.1kV grade) LS 1
LS 1
c Cable glands, lugs & straight through joints for Power & Control cables
iv For 132kV Lower Rasuagadi HPP Switchyard:
a Power Cables(PVC) - (1.1kV grade) LS 1
b Control Cable (PVC) - (1.1kV grade) LS 1
LS 1
c Cable glands, lugs & straight through joints for Power & Control cables

G Visual Monitoring System for watch & ward as per LS 1


technical specification
H Earthing and lightning protection including necesaary
connectors/connections, risers etc. complete in all
respect
i Earth Conductor (copper) LS 1

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-3 Page 74 of 145

ii Earth Rod (copper clad steel) LS 1


iii Equipment for lightning protection LS 1
I SUBSTATION AUTOMATION
a Integration of all 220/132kV Bays under present scope LS 1
with the SCADA of SIEMENS (SINAUT Spectrum) at
Load Dispatch Centre, Kathmandu including supply of
Hardware, Software, accessories etc. as per TS Section
Project.
SUB TOTAL PART-B

PART-C: MANDATORY SPARES


(I) Mandatory Spare List for Autotransformer
A. For 53.33MVA , 220/132/33 KV, 1-phase
Autotransformer
a) Bushing of each rating with metal parts & gaskets and
Set 1
lifting tools
b) Cooler fan with Motor No. 1
c) Buchholz Relay(Main Tank) complete with floats and
Set 1
contacts
d) Local and Remote WTI with sensing device and
Set 1
contact(each)
e) Magnetic oil level gauge No. 1
f) Strarters, contactors,switches & Relays for Electrical
Set 1
control panels(One ste of each type)
g) Remote Tap postion Indiactor No. 1
h) Spare insulating oil to be handed over to Owner after
KL 10
commisioning for O&M requirement
B.
For 50MVA , 132/33 KV, 3-phase Power Transformer
a) Bushing of each rating with metal parts & gaskets and
Set 1
lifting tools
b) Cooler fan with Motor No. 1
c) Buchholz Relay(Main Tank) complete with floats and
Set 1
contacts
d) Local and Remote WTI with sensing device and
Set 1
contact(each)
e) Magnetic oil level gauge No. 1
f) Strarters, contactors,switches & Relays for Electrical
Set 1
control panels(One ste of each type)

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-3 Page 75 of 145

g) Remote Tap postion Indiactor No. 1


h) Spare insulating oil to be handed over to Owner after
KL 5
commisioning for O&M requirement
(II) SPARES FOR 245kV & 145kV GIS
1 General
1.1 SF6 gas Pressure Relief Devices, 1Nos. of each type
Set 1

1.2 SF6 Pressure gauge cum switch OR Density monitors


and pressure switch as applicable (1 no. of each type) Set 1

1.3 Coupling device for pressure gauge cum switch for


Set 1
connecting Gas handling plant
1.4 Rubber Gaskets, “O” Rings and Seals for SF6 gas of each
Set 1
type
1.5 Molecular filter for SF6 gas with filter bags(20% of total
Set 1
weight)
1.6 All types of Control Valves for SF6 gas of each type
Set 1

1.7 SF6 gas (20 % of total gas quantity) Set 1


1.8 All types of coupling for SF6 gas (1 no. of each type)
Set 1

1.9 Covers with all accessories necessary to close a


compartment in case of dismantling of any part of the
Enclosure to ensure the sealing of this compartment

1.9.1 For 3 Phase Enclosure if applicable No. 1


1.9.2 For Single phase enclosure if applicable No. 1
1.10 Locking device to keep the Dis-connectors (Isolators)
and Earthing switches in close or open position in case
Set 1
of removal of the driving Mechanism

1.11 Bus Support insulator of each type for 3 phase/single


No. 1
phase enclosure.
1.12 SF6 to air bushing (220kV & 132kV - 1 No. of each type
Set 1
& rating) as applicable

2.A 245KV SF6 CIRCUIT BREAKER:

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-3 Page 76 of 145

2.1 Complete Circuit Breaker pole of each type & rating


complete with interrupter, main circuit enclosure and No. 1
Marshalling Box with operating mechanism
2.2 Rubber gaskets, `O' rings and seals for SF6 gas (1 No. of
Set 1
each type)
2.3 Trip coil assembly with resistor as applicable Set 1
2.4 Closing coil assembly with resistor as applicable . Set 1
2.5 Relays, Power contactors, push buttons, timers & MCBs
Set 1
etc (1 No. of each type & rating)
2.6 Closing coil assembly (including valve, if applicable)
Set 1

2.7 Trip coil assembly (including valve, if applicable) Set 1


2.8 Auxiliary switch assembly of each type Set 1
2.B 145KV SF6 CIRCUIT BREAKER:
2.1 Complete Circuit Breaker pole of each type & rating
complete with interrupter, main circuit enclosure and
No. 1
Marshalling Box with operating mechanism

2.2 Rubber gaskets, `O' rings and seals for SF6 gas (1 No. of
Set 1
each type)
2.3 Trip coil assembly with resistor as applicable Set 1
2.4 Closing coil assembly with resistor as applicable Set 1
2.5 Relays, Power contactors, push buttons, timers & MCBs
Set 1
etc (1 No. of each type & rating)
2.6 Closing coil assembly (including valve, if applicable)
Set 1

2.7 Trip coil assembly (including valve, if applicable) Set 1


2.8 Auxiliary switch assembly of each type Set 1

3.A 245KV ISOLATORS :


3.1 Complete set of 3-phase dis-connector including main
Set 1
circuit, enclosure, driving mechanism
3.2 3-phase Earthing switch including main circuit,
Set 1
enclosure, driving mechanism.
3.3 Copper contact fingers for dis-connector male & female
contact for dis-connector of each type and rating Set 1

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-3 Page 77 of 145

3.4 Copper contact fingers for earthing switch male &


female contacts, for one complete earthing switch of Set 1
each type and rating
3.5 Open / Close contactor assembly, timers, key interlock
for one complete (3 phase) dis-connector and (3 phase)
Set 1
earthing switch (1 No. of each type and rating)

3.6 Push button switch - (1 No. of each type & rating) as


Set 1
applicable
3.7 Limit switch and Aux. Switches for complete 3 phase
1
equipment
3.7.1 For isolator Set 1
3.7.2 For earth switch Set 1
3.B 145KV ISOLATORS :
3.1 Complete set of 3-phase dis-connector including main
Set 1
circuit, enclosure, driving mechanism
3.2 3-phase Earthing switch including main circuit,
Set 1
enclosure, driving mechanism.
3.3 Copper contact fingers for dis-connector male & female
contact for dis-connector of each type and rating Set 1

3.4 Copper contact fingers for earthing switch male &


female contacts, for one complete earthing switch of Set 1
each type and rating
3.5 Open / Close contactor assembly, timers, key interlock
for one complete (3 phase) dis-connector and (3 phase)
Set 1
earthing switch(1 No. of each type and rating)

3.6 Push button switch - (1 No. of each type & rating) as


Set 1
applicable
3.7 Limit switch and Aux. Switches for complete 3 phase
equipment
3.7.1 For isolator Set 1
3.7.2 For earth switch Set 1

4.0 A 245KV CURRENT TRANSFORMER


4.1 Gas insulated complete CT of each type and rating with
No. 1
enclosure.
4.2 Secondary bushing of each type Set 1
4.0 B 145KV CURRENT TRANSFORMER

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-3 Page 78 of 145

4.1 Gas insulated complete CT of each type and rating with


No. 1
enclosure.
4.2 Secondary bushing of each type Set 1

5.0 A 245kV Voltage Transformer


5.1 Gas insulated complete PT of each type and rating with
No. 1
enclosure.
5.0 B 145 kV Voltage Transformer
5.1 Gas insulated complete PT of each type and rating with
No. 1
enclosure.

(III) SPARES FOR AIS EQUIPMENTS


6.0A 220kV, 4400pF CVT No. 1
6.0B 132kV, 8800pF CVT No. 1

7.0A 216kV Surge Arrestor with insulating base, terminal


Set 2
connector , Surge counter & accessories
7.0B 120kV Surge Arrestor with insulating base, terminal
Set 2
connector , Surge counter & accessories
7.0C 30kV Surge Arrestor with insulating base, terminal
Set 2
connector , Surge counter & accessories

(IV) Relay & Protection panel


A Line Protection Panel
1 Numerical distance relay Set 1
2 Current Differential Relay No. 1
B Transformer Protection Panel
1 Transformer differential protection No. 1
Restricted earth fault protection relay with non-linear
No. 1
2 resistor
3 Directional O/C & E/F relay No. 1
C COMMON SPARES
1 Power supply module for Bus Bar protection. No. 1
2 Bay unit module Set 1

(V) Sub-Station Automation


A Bay control unit (IED) of each type Set 1
B Ethernet switch of each type Set 1

(VI) Digital Protection Coupler for Chilime Hub substation No 1

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-3 Page 79 of 145

(VII) LT Transformer
i) Bushing (1 no. of each type) Set 1
OTI & WTI with sensing device (1 no. of each type)
Set 1
ii)
iii) Diaphragm for pressure relief vent No. 1
iv) Silica Gel container No. 1
v) Set of valves Set 1
vi) Buchholz realy (if applicable) No. 1

(VIII) Illumination System


i) 5% of each type of lighting fixture supplied Set 1

(IX) Erection Hardware items


5% spares of the actual quantities for Insulator strings
&hardwares, clamps & connectors (including equipment
Set 1
connectors), spacers, corona bell and welding sleeves
i)

(X) 33kV Indoor switchgear


i) CB Spring charge indicator (Mechanical) No. 1
ii) Mechanical ON/OFF indicator for CB No. 1
iii) Operation counter for CB No. 1
iv) CT (1-Phase) (1 no. of each type) Set 1
v) VT (1-Phase) No. 1
vi) Multi Function Meter No. 1
vii) Control switch for breaker(T-N-C) No. 2
viii) Green Indicating lamp for CB Open No. 5
ix) Red indicating lampfor CB Close No. 5
x) DC healthy lamp (white) No. 5
xi) Trip circuit healthy lamp No. 5
xii) Voltmeter with selector switch No. 1
xiii) Numerical protection relay (IED) No. 1
xiv) Master Trip Relay (86) (1 no. of each type) Set 1
Semaphore Indicator for Line Isolator & Line Earth
Set 5
xv) Switch (1 no. of each type)
xvi) LAN Switches and LAN/FO Cables No. 1
xvii) Trip coil assembly No. 2
xviii) Closing coil assembly No. 2

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-3 Page 80 of 145

(XI) Communication Equipments


3.0 Mandatory Spares for Chilime Hub GIS

A
SDH Equipment (STM-4 MADM upto 5 MSP protected directions)
(i) Common cards, Cross-connect/control cards, Optical base card, Power
supply cards, power cabling, other hardware & accessories (each). Set 1

(ii) Optical Interface Cards/SFP


a S4.1 SFP Nos. 1
c L4.1 SFP Nos. 1
h L4.2 SFP Nos. 1
(iii) Tributary cards
a E1 Interface card (Min.16 interfaces per card) Nos. 1
b Ethernet Interface 10/100 Base T with Layer-2 switching (Min 8
Nos. 1
Interfaces per card)
B VOIP telephone instrument Nos. 1
C Pre Connectorized Optical Fiber Patch Cords(10 Mtrs) – Pack of six
Set 1
Patch cords

SUB-TOTAL-C
Total for 220/132/33kV Chilime Hub GIS new
Substation (Package-2, Part-I) (I) (Part-A+ Part-B+
Part C)

II 220(Hybrid)/132/33KV TRISHULI-3B HUB AIS NEW


S/S (Package-2, Part-II)

PART -A: OWNER ASSESSED QUANTITIES


A POWER TRANSFORMER
A.1 1-Ph Autotransformers
a) 53.33MVA, 220/√3 / 132/√3 / 33kV Single Phase Auto Nos. 7
Transformer (without transformer Oil)
b) Insulating oil for 53.33MVA , 220/132/33 KV, 1-phase Lot* 7
Autotransformer (* 1Lot = Oil for 1 Autotransformer )
c) 33kV Current transformer (NCT) for autotrasnformer No 2

A.2 3-Phase Power Transformer

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-3 Page 81 of 145

50 MVA, 132 /33kV Three Phase Power Transformer


a) Nos. 1
(without transformer Oil)
Insulating oil for 50MVA , 132/33 KV, 3-phase Power
b) Transformer (* 1Lot = Oil for 1 Autotransformer ) Lot* 1

A.3 Testing & Maintenance Equipments


a) Oil Storage Tank of 20KL No. 1
b) Transformer Oil Filtration plant (6KLPH) No 1

B LT TRANSFORMER
1.0 630 kVA, 33/0.400kV Nos 2
C 245 KV EQUIPMENTS
C.1 245KV GIS HYBRID Equipment
1.1 245kV, SF6 GIS Hybrid Bus Coupler bay Module as per
section project
a) 3000A, 40kA for 1 sec Set 1
1.2 245kV, SF6 GIS Hybrid Bus Transfer Bus Coupler bay
Module as per section project
a) 3000A, 40kA for 1 sec Set 1
1.3 245kV, SF6 GIS Hybrid Line feeder bay Module as per
section project
a) 1600A, 40kA for 1 sec Set 6
1.4 245kV, SF6 GIS Hybrid ICT feeder bay Module as per
section project
a) 1600A, 40kA for 1 sec Set 2

C.2 245KV Outdoor AIS Equipment (40kA for 1 sec)


1.1 216 KV Surge Arrester (1-phase) Nos. 25
1.2 245 kV, 4400pFCapacitive Voltage Transformer (1- Nos. 24
1.3 Phase)
245 kV, 1600A, 40kA, DBR Isolator (Tandem type) (3- Nos. 8
1.4 Phase)Bus Post Insulator (1-Phase) (Except auxiliary
245kV Nos. 50
buses of transformer)

Testing & Maintenance Equipment for 220kV GIS


C.3
Hybrid
1.1 SF6 Gas processing Unit Set 1
1.2 Partial Discharge Monitoring System (portable type) Set 1

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-3 Page 82 of 145

1.3 Dew Point Meter Set 1


1.4 SF6 Gas Leak Detector Set 1

D 145 kV Equipment
1.0 145 kV Circuit Breakers (3-Phase) with support structure
a 1250A, 40kA Nos 7
b 2000A, 40kA Nos 1

2.0 145kV Isolator (3-phase)-Double Break


a 1250A, 40kA Isolator without E/S Nos 7
b 1250A, 40kA Isolator with one E/s Nos 14
c 1250A, 40kA Isolator without E/s (Tandem) Nos 7
d 1250 A, 40kA Isolator without E/S (Beam mounted) Nos 7
e 2000A, 40kA Isolator with two E/s Nos 2

3.0 145 kV Current Transformer (1-Phase)


a 1200A, 40kA with 120% extended current rating Nos 6
b 1200 A, 40kA with 150% extended current Nos 3
c 600 A, 40kA with 120% extended current Nos 15
d 600 A, 40kA with 120% extended current for tariff metering Nos 12

4.0 145 kV Capacitive Voltage Transformer (1- Phase)


a 8800 pF Nos. 18
b 8800 pF for tariff metering Nos. 12
5.0 120 kV Surge Arrestors
a 120 kV Surge Arrestors (1-phase) - Pedestal mounted Nos. 22
b 120 kV Surge Arrestors (1-phase) - suitable for mounting on Nos. 6
transmission line dead end tower

6.0 145 kV Bust Post Insulator (Except auxiliary buses of transformer) Nos 42

E 33 kV Equipment
1.0 36kV Circuit Breakers (3-Phase) with support structure
a 1250A, 25kA Nos 5

2.0 36kV Isolator (3-phase)-Double Break


a 1250A, 25kA, Isolator without E/S Nos 8

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-3 Page 83 of 145

b 1250A, 25kA, Isolator with one E/s Nos 3


c 1250A, 25kA, Isolator without E/s (Tandem) Nos 5

3.0 36 kV HG Fuse along with support insulator (1-phase) Nos. 3

4.0 36kV Current Transformer (1-Phase)


a 1000A, 25kA with 120% extended current rating Nos 3
b 600 A, 25kA with 120% extended current Nos 12

5.0 36kV Voltage Transformer (1- Phase) Nos 3

6.0 30kV Surge Arrestors (1-phase) Nos. 12


7.0 36kV Bust Post Insulator (Except auxiliary & neutral buses of Nos 18
transformer)

F 72.5kV EQUIPMENT
1.1 72.5 kV, 1250A, 25kA Circuit Breaker (3-phase) with support structure No. 1

1.2 72.5 kV, 1250A, 25kA Isolators with earth switch (3-phase, DBR type) No. 1

1.3 72.5kV, 50A, 25 kA with 120% extended rating CT (1-phase) Nos. 3


1.4 72.5kV PT (1-phase) Nos. 3
1.5 72.5 kV BPI (1-phase) Nos. 6

G RELAY PANELS (WITH AUTOMATION)


1.0 220 kV
a Circuit Breaker Relay Panel
i With Auto Reclose Nos. 7
ii With out Auto Reclose Nos. 3
b Line Protection Panel
i Line Protection Panel with Distance Protection and Current Differential Nos. 6
Protection at Trishuli-3B Hub End
ii Line Protection Panel housing two nos. Current Differential Protection Nos. 1
relays & accessories at Matatirtha End
iii Line Protection Panel housing two nos. Current Differential Protection Nos. 1
relays & accessories at Upper Trishuli-1 End
c Transformer Protection Panel (For both HV & MV side) Nos. 2
d Bus Bar Protection Panel Set 1

2.0 132 kV

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-3 Page 84 of 145

a Circuit Breaker Relay Panel


i With Auto Reclose Nos. 4
ii With out Auto Reclose Nos. 4
b Line Protection Panel
i) Line Protection Panel with Current Differential Protection and Back up Nos. 4
O/C & E/F Protection at Trishuli-3B Hub End
ii) Line Protection Panel housing two nos. Current Differential Protection Nos. 1
relays & accessories at Trishuli-3A HPP End
iii) Line Protection Panel housing two nos. Current Differential Protection Nos. 1
relays & accessories at Trishuli-3B HPP End

c Transformer Protection Panel (For both HV & MV side) Nos. 1


d Bus Bar Protection Panel Set 1
3.0 33 kV
a Line Protection Panel Nos. 3
b Protection Panel for TBC bay Nos. 1
c Transformer Protection Panel Nos. 1
4.0 COMMON EQUIPMENTS
a Relay tool kit Set 1
b Time synchronisation equipment No. 1
H SUBSTATION AUTOMATION
H.1 Complete Substation Automation System (SAS) for substation including
hardware and software for the substation & remote control stations
alongwith associated equipments for the following bays as per
Technical Specification
a Main bays to be automated
i 220 kV system Bay Nos 10
ii Bays to be automated of existing 132 kV substation Bay Nos 8
iii Bays to be automated of existing 33 kV substation Bay Nos 5
iv BCU for controlling & monitoring of Auxilary System Set 1

I Digital Protection Coupler & PBAX


a) Digital Protection Coupler* Nos 12
b) PBAX with following configuration as per TS Set 1
i 2 wire subscriber interface card with capacity 32 local subscribers
(along with 32 nos. Instruments)
ii) E-1 interface with 2 trunks G-703
iii) 2 wire interface with 1 trunk (For PSTN)

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-3 Page 85 of 145

* Digital protection Coupler for both ends for all 220kV Lines are
considered. However, Digital Protection coupler for 220kV Chilime Hub
- Trishuli-3B D/c Line have been considered at respective substation
end.

J LT Switchgear (As per Technical specification)


a 400V Main switchboard Set 1
b 400V ACDB Set 1
c 400V MLDB Set 1
d 400V Emergency LDB Set 1
e 220V DCDB Sets 2
f 48V DCDB Set 2

K Batteries
a 220V
i 600 AH Nos 2
b 48V
i 600AH Nos 2

L Float Cum Boost Battery Charger


a 220V Float Cum Boost Battery Charger
i 90A/90A Nos 2
b 48V Float Cum Boost Battery Charger
i 90A/90A Nos 2

M Diesel Generator with control Panel


a 250 kVA Set 1

N Fire Protection System


a Portable /Trolley/Wheel mounted extinguishers
i 9 litre water type Nos 2
ii 50 litre foam type Nos 2
iii 4.5 kg CO2 type Nos 10
iv 4.5 kg Dry Chemical Power (DCP) type Nos 6
b Smoke detection system Set 1
c Fire detection and Alarm System Set 1

O.1 Cables along with clamps, glands, lugs and straight joints etc.

b Power Cables - (1.1kV grade)

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-3 Page 86 of 145

i 3.5Cx300 sqmm (XLPE) cable for filter Machine along with termination KM 1
arrangement as per TS

O.2 132kV XLPE Power Cable for interconnection of 132kV Trishuli-3B


HPP Line Bay with Dead end Tower

a) 132kV, XLPE insulated , 1C X 1600 sqmm size copper cable as per kM 1.5
technical specificaion.(Metallic sheath and PE outer sheathed with
graphite coating and short circuit current 40kA for 1 sec) including one
spare cable
b) Cable termination as per technical specification for interconnection with Nos 12
overhead transmission for cable at sl. No. 1 above (excluding
terminating structure)
c) Single phase earth link box Nos 12
d) 36kV grade 1Cx300 Sqmm Earth Continuity Cable kM 0.4

P Air conditioning System for Control room cum administrative


building
a High wall type split AC unit of 2 TR capacity Nos 20

Q Lattice/pipe Structure for towers,beams and equipments including peak


plates/pack washers and guest paltes including foundation
bolts(nuts,washers,MS plate welded at the bottom)
(a) Lattice stucture & foundation bolts MT 420
(b) Pipe structure & foundation bolts MT 30
(c ) Fastners for towers,beams and equipment support strcutures MT 20

R.1
Communication equipments for Trishuli-3B Hub Substation
1.0 Telecom Equipments

A1
SDH Equipment (STM-4 MADM upto 5 MSP protected directions)
(i) Base Equipment (Common cards, Cross Connect/control cards, optical
base cards, power supply cards, power cabling, other hardware and
accessories including sub racks, patch cord, DDF etc fully equiped Nos. 2
excluding (ii) & (iii) below

(ii) Optical Interface Cards/SFP


a S4.1 SFP Nos. 10
b L4.1 SFP Nos. 4
c L4.2 SFP Nos. 2

(iii) Tributary cards


a E1 Interface card (Min.16 interfaces per card) Set 4

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-3 Page 87 of 145

b Ethernet Interface 10/100 Base T with Layer-2 switching (Min 8


Nos. 4
Interfaces per card)

B Equipment Cabinets No. 1

2.0 Network Manager System - Craft Terminal


a Hardware Set 1
b Software Set 1

3.0
VOIP telephone instrument with one common switch (min. 8 port) Nos. 2

R.2 Communication equipments for Trishuli-3B HPP


1.0 Telecom Equipments

A1
SDH Equipment (STM-4 MADM upto 3 MSP protected directions)
(i) Base Equipment (Common cards, Cross Connect/control cards, optical
base cards, power supply cards, power cabling, other hardware and
accessories including sub racks, patch cord, DDF etc fully equiped Nos. 1
excluding (ii) & (iii) below

(ii) Optical Interface Cards/SFP


a S4.1 SFP Nos. 2

(iii) Tributary cards


a E1 Interface card (Min.16 interfaces per card) Set 2
b Ethernet Interface 10/100 Base T with Layer-2 switching (Min 8
Nos. 2
Interfaces per card)

B Equipment Cabinets No. 1

2.0 Network Manager System - Craft Terminal


a Hardware Set
b Software Set

3.0
VOIP telephone instrument with one common switch (min. 8 port) Nos. 2

Sub-Total Part-A

Part-B: VENDOR ASSESSED QUANTITIES

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-3 Page 88 of 145

A Erection Hardware

Insulator strings, Disc Insulators, Hardware, conductor, Al tube, bus-bar


materials, cable trays, Bay MB, clamps, spacers, connectors including
equipment connectors, Junction box, earthwire, buried cable
trenches/pipe equipment & lighting, all accessories etc. for the following:

a 220 kV Layout (DMT Layout with GIS Hybrid)


i Line Bay Set 6
ii Transformer Bay Set 2
iii TBC Bay Set 1
iv BC bay Set 1
v Bus work (Three Bays) Set 1
vi Bus work (Four Bays) Set 1

b 132 kV (Double Main Layout with bypass breaker arrangement)

i Line Bay Set 4


ii Transformer Bay Set 3
iii BC bay Set 1
iv Bus work (Three Bays) Set 2
v Bus work (Four Bays) Set 1

c For spare unit of 220/132/33kV auto transformer connection through Set 1


auxiliary buses, Neutral formation and delta formation (for two banks):
Required 245 kV BPI for HV auxiliary bus, 132 kV BPI for 132 kV
Auxilary bus, 72.5 kV BPI for tertiary auxilary bus & delta formation, 36
kV BPI for Neutral formation & Neutral auxiliary bus including Al tube,
bus-bar materials, clamps, spacers, connectors, including equipment
connectors, support structures, Earthing of spare unit as per technical
specification.

d Erection Hardware etc for 72.5kV & 33kV equipments & LT Set 1
Transformer connection

e Earthing and lightning protection including necesaary


connectors/connections, risers etc. complete in all respect ( but
excluding LM structures for Lightning protection)
i Earth Conductor (copper) LS 1
ii Earth Rod (copper clad steel) LS 1
iii Equipment for lightning protection LS 1

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-3 Page 89 of 145

B Fire Protection System


a Pumping arrangement for HVW system & hydrant system, complete
with all piping, valves, fittings,etc. inside pump house

i 220/132/33kV (New) Substation Set 1


b Hydrant system, complete U/G piping and accessories etc. outside the
Pump House.
i 220/132/33kV (New) Substation Set 1
c HVW spray system, Hydrant system and complete U/G & O/G piping
and accessories etc. out side the pump house for Transformer :

c.1 Transformer
i 53.33MVA , 220/132/33 KV, 1-phase Autotransformer Set 7
i 50MVA , 132/33 KV, 3-phase Power Transformer Set 1

C Illumination System
a Fire fighting building illumination (100 sqmm) LS 1
b Illumination System for switchyard panel room
i 220KV Set 4
ii 132KV Set 3
iii 33kV Set 1
c Control room cum administrative building illumination (1000 sqmm) LS 1
d Switchyard lighting LS 1
e Street lighting LS 1
h Transit camp (420 sqmm) LS 1
j Security room (10 sqmm) LS 1
k Car parking shed (for 10 cars) LS 2

D Air conditioning System


a Air conditioning for S/Y panel room
i 220KV Set 4
ii 132KV Set 3
iii 33kV Set 1
E POWER & CONTROL CABLES
i For 220/132/33kV Trishuli-3B Hub Substation:
a Power Cables(PVC) - (1.1kV grade) LS 1
b Power Cables (XLPE) - (1.1kV grade) LS 1
c Control Cable (PVC) - (1.1kV grade) LS 1
LS 1
d Cable glands, lugs & straight through joints for Power & Control cables

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-3 Page 90 of 145

ii For 220kV Upper Trishuli-1 HPP Switchyard:


a Power Cables(PVC) - (1.1kV grade) LS 1
b Control Cable (PVC) - (1.1kV grade) LS 1
LS 1
c Cable glands, lugs & straight through joints for Power & Control cables
iii For 220kV Matatirtha Substation:
a Power Cables(PVC) - (1.1kV grade) LS 1
b Control Cable (PVC) - (1.1kV grade) LS 1
LS 1
c Cable glands, lugs & straight through joints for Power & Control cables
iv For 132kV Upper Trishuli-3B HPP Switchyard:
a Power Cables(PVC) - (1.1kV grade) LS 1
b Control Cable (PVC) - (1.1kV grade) LS 1
LS 1
c Cable glands, lugs & straight through joints for Power & Control cables
v For 132kV Trishuli-3A HPPSwitchyard:
a Power Cables(PVC) - (1.1kV grade) LS 1
b Control Cable (PVC) - (1.1kV grade) LS 1
LS 1
c Cable glands, lugs & straight through joints for Power & Control cables
vi For 132kV Samundratar Substation:
a Power Cables(PVC) - (1.1kV grade) LS 1
b Control Cable (PVC) - (1.1kV grade) LS 1
LS 1
c Cable glands, lugs & straight through joints for Power & Control cables

Sub-Total Part-B

Part-C: Mandatory Spares

(I) Mandatory Spare List for Autotransformer


A For 53.33MVA , 220/132/33 KV, 1-phase
Autotransformer
a) Bushing of each rating with metal parts & gaskets and Set 1
lifting tools
b) Cooler fan with Motor No. 1
c) Buchholz Relay(Main Tank) complete with floats and Set 1
contacts
d) Local and Remote WTI with sensing device and Set 1
contact(each)

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-3 Page 91 of 145

e) Magnetic oil level gauge No. 1


f) Strarters, contactors,switches & Relays for Electrical Set 1
control panels(One ste of each type)
g) Remote Tap postion Indiactor No. 1
h) Spare insulating oil to be handed over to Owner after KL 10
commisioning for O&M requirement
B
For 50MVA , 132/33 KV, 3-phase Power Transformer
a) Bushing of each rating with metal parts & gaskets and Set 1
lifting tools
b) Cooler fan with Motor No. 1
c) Buchholz Relay(Main Tank) complete with floats and Set 1
contacts
d) Local and Remote WTI with sensing device and Set 1
contact(each)
e) Magnetic oil level gauge No. 1
f) Strarters, contactors,switches & Relays for Electrical Set 1
control panels(One ste of each type)
g) Remote Tap postion Indiactor No. 1
h) Spare insulating oil to be handed over to Owner after KL 5
commisioning for O&M requirement

(II) 245kV GIS Hybrid


1 General
1.1 SF6 gas Pressure Relief Devices, 1Nos. of each type
Set 1

1.2 SF6 Pressure gauge cum switch OR Density monitors


and pressure switch as applicable (1 no. of each type) Set 1

1.3 Coupling device for pressure gauge cum switch for


Set 1
connecting Gas handling plant
1.4 Rubber Gaskets, “O” Rings and Seals for SF6 gas of each
Set 1
type
1.5 Molecular filter for SF6 gas with filter bags(20% of total
Set 1
weight)
1.6 All types of Control Valves for SF6 gas of each type Set 1
1.7 SF6 gas (20 % of total gas quantity) Set 1
1.8 All types of coupling for SF6 gas (1 no. of each type)
Set 1

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-3 Page 92 of 145

1.9 Pipe length (Copper or Steel as applicable) for SF6


Set 1
Circuit of each type
1.10 Locking device to keep the Dis-connectors (Isolators)
and Earthing switches in close or open position in case
Set 1
of removal of the driving Mechanism

1.11 SF6 to air bushing (220kV - 1 No. of each type & rating)
Set 1
as applicable

2 245KV SF6 CIRCUIT BREAKER:


2.1 Complete Circuit Breaker pole of each type & rating
complete with interrupter, main circuit enclosure and
No. 1
Marshalling Box with operating mechanism

2.2 Rubber gaskets, `O' rings and seals for SF6 gas (1 No. of
Set 1
each type)
2.3 Trip coil assembly with resistor as applicable Set 1
2.4 Closing coil assembly with resistor as applicable . Set 1
2.5 Relays, Power contactors, push buttons, timers & MCBs
Set 1
etc (1 No. of each type & rating)
2.6 Closing coil assembly (including valve, if applicable)
Set 1

2.7 Trip coil assembly (including valve, if applicable) Set 1


2.8 Auxiliary switch assembly of each type Set 1

3 245KV ISOLATORS :
3.1 Complete set of 3-phase dis-connector including main
Set 1
circuit, enclosure, driving mechanism
3.2 3-phase Earthing switch including main circuit,
Set 1
enclosure, driving mechanism.
3.3 Copper contact fingers for dis-connector male & female
contact for dis-connector of each type and rating Set 1

3.4 Copper contact fingers for earthing switch male &


female contacts, for one complete earthing switch of Set 1
each type and rating
3.5 Open / Close contactor assembly, timers, key interlock
for one complete (3 phase) dis-connector and (3 phase)
Set 1
earthing switch (1 No. of each type and rating)

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-3 Page 93 of 145

3.6 Push button switch - (1 No. of each type & rating) as


Set 1
applicable
3.7 Limit switch and Aux. Switches for complete 3 phase
1
equipment
3.7.1 For isolator Set 1
3.7.2 For earth switch Set 1
4 245KV CURRENT TRANSFORMER
4.1 Gas insulated complete CT of each type and rating with
No. 1
enclosure.
4.2 Secondary bushing of each type Set 1
(III) 145kV CB
i) Complete Pole of circuit breaker including pole column, interrupter, with
driving mechanism and Marshaling Box but without support structure for

1250A, 31.5kA (No. of Pole) No. 1


ii) Rubber gaskets, `O' rings and seals ( for complete replacement of one Set 1
pole of CB)
iii) Trip coils with resistor Nos. 2
iv) Closing coils with resistor Nos. 1
v) Terminal Pads & connectors Nos. 2
vi) Molecular filter Nos. 2
vii) Relays, Power contactors, switch fuse units, limit switches, push Set 1
buttons, timers & MCB etc. (1 no. of each type)
viii) Pressure switches / Density monitor (1 no. of each type) Set 1
ix) Auxiliary switch assembly (for one pole of CB) Set 1
(III) 72.5kV CB
i) Complete Pole of circuit breaker including pole column, interrupter, with
driving mechanism and Marshaling Box but without support structure for

1250A, 31.5 KA (No. of Pole) No. 1


ii) Rubber gaskets, `O' rings and seals ( for complete replacement of one Set 1
pole of CB)
iii) Trip coils with resistor Nos. 2
iv) Closing coils with resistor Nos. 1
v) Terminal Pads & connectors Nos. 2
vi) Molecular filter Nos. 2
vii) Relays, Power contactors, switch fuse units, limit switches, push Set 1
buttons, timers & MCB etc. (1 no. of each type)
viii) Pressure switches / Density monitor (1 no. of each type) Set 1
ix) Auxiliary switch assembly (for one pole of CB) Set 1
(IV) 245kV Isolator
i) One complete pole including support Insulator, motor operating
mechanism (MOM) with box but excluding structure

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-3 Page 94 of 145

1600A, 40 KA, 1 E/S (no. of pole) No. 1


ii) Copper contact fingers for male & female contacts ( for one pole of Set 2
Isolator)
iii) Open/Close contactor assembly, timers, key interlock push button Set 1
switch & auxilliary switches (for one pole of Isolator)
iv) Limit Switch Nos. 2
v) Terminal Pads & Connectors Nos. 3
vi) Corona shield rings Nos. 3
(V) 145kV Isolator
i) One complete pole including support Insulator, motor operating
mechanism (MOM) with box but excluding structure
1250A, 31.5kA with1 E/S (no. of pole) No. 1
ii) Copper contact fingers for male & female contacts ( for one pole of Set 2
Isolator)
iii) Open/Close contactor assembly, timers, key interlock push button Set 1
switch & auxilliary switches (for one pole of Isolator)
iv) Limit Switch Nos. 2
v) Terminal Pads & Connectors Nos. 3
vi) Corona shield rings Nos. 3
(VI) 72.5 kV Isolator
i) One complete pole including support Insulator, MANUAL operating
mechanism with box but excluding structure
1250A, 25kA, 1 E/S (no. of pole) No. 1
ii) Copper contact fingers for male & female contacts ( for one pole of Set 2
Isolator)
iii) Open/Close contactor assembly, timers, key interlock push button Set 1
switch & auxilliary switches (for one pole of Isolator)
iv) Limit Switch Nos. 2
v) Terminal Pads & Connectors Nos. 3

(VII) 36kV Isolator


i) One complete pole including support Insulator, MANUAL operating
mechanism with box but excluding structure
630A, 25KA, 1 E/S (no. of pole) No. 1
ii) Copper contact fingers for male & female contacts ( for one pole of Set 2
Isolator)
iii) Open/Close contactor assembly, timers, key interlock push button Set 1
switch & auxilliary switches (for one pole of Isolator)
iv) Limit Switch Nos. 2
v) Terminal Pads & Connectors Nos. 3

(VIII) 72.5kV, 1250A, 31.5 kA with 120% extended rating CT (1-phase) No. 1

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-3 Page 95 of 145

(IX) CVT (245 kV,4400 pF) (1-phase) No. 1

(X) 72.5kV PT (1-phase) No. 1

(XI) 216 SA
i) Complete LA (1-phase) No. 1
ii) Surge counter/monitor Nos. 5
(XII) 120kV SA
i) Complete LA (1-phase) No. 1
ii) Surge counter/monitor Nos. 5
(XIII) 30kV SA
i) Complete LA (1-phase) No. 1
ii) Surge counter/monitor Nos. 5

(XIV) C&R PANELS


i) Transformer protection panel :
a) Transformer differential protection No. 1
b) REF protection relay with non-linear resistor No. 1
c) Directional over current & E/F Protection Relay No. 1
ii) Line protection panel :
a) Distance Protection relay Set 1
b) Current differential Protection relay Set 1
iv) Breaker Relay panel:
a) Breaker failure relay No. 1
b) Trip circuit supervision relay Nos. 2
c) Self reset trip relay (relay of each type) Set 1
d) Hand reset trip relay(relay of each type) Set 1
e) Timer relay(relay of each type) Set 1
f) DC supervision relay(relay of each type) Set 1
g) Flag relays(relay of each type) Set 1
h) Auxiliary relays(relay of each type) Set 1

(XV) Teleprotection Equipments


i) Set of prints for protection coupler (digital ) Set 1

(XVI) SAS
i) Bay Control Unit (IED) of each type Set 1
ii) Ethernet Switch of each type Set 1

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-3 Page 96 of 145

(XVII) BATTERY CHARGER( 220kV)


i) Set of control cards Set 1
ii) Set of relays Set 1
iii) Rectifier transformer No. 1
iv) Thyristor/diode Set 1
v) Fuses of Thyristor with indicators Set 6

(XVIII) COMMON SPARES


i) Bay unit Module No. 1
ii) 2 wire local subscriber interface card for PABX No. 1
iii) E1 Interface card for PABX No. 1
(XIX) Mandatory Spares of Communication Equipments
1.0 Mandatory Spares for Trishuli-3B Hub

A
SDH Equipment (STM-4 MADM upto 5 MSP protected directions)

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-3 Page 97 of 145

(i) Common cards, Cross-connect/control cards, Optical base card, Power


supply cards, power cabling, other hardware & accessories (each). Set 1

(ii) Optical Interface Cards/SFP


a S4.1 SFP Nos. 1
c L4.1 SFP Nos. 1
h L4.2 SFP Nos. 1

(iii) Tributary cards


a E1 Interface card (Min.16 interfaces per card) Nos. 1
b Ethernet Interface 10/100 Base T with Layer-2 switching (Min 8
Nos. 1
Interfaces per card)

B VOIP telephone instrument Nos. 1

C Pre Connectorized Optical Fiber Patch Cords(10 Mtrs) – Pack of six


Set 1
Patch cords

2.0 Mandatory Spares for Trishuli-3B HPP

A
SDH Equipment (STM-4 MADM upto 3 MSP protected directions)
(i) Common cards, Cross-connect/control cards, Optical base card, Power
supply cards, power cabling, other hardware & accessories (each). Set 1

(ii) Optical Interface Cards/SFP


a S4.1 SFP Nos. 1

(iii) Tributary cards


a E1 Interface card (Min.16 interfaces) Nos. 1
b Ethernet Interface 10/100 Base T with Layer-2 switching (Min 8
Nos. 1
Interfaces per card)

B VOIP telephone instrument Nos. 1

C Pre Connectorized Optical Fiber Patch Cords(10 Mtrs) – Pack of six


Set 1
Patch cords

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-3 Page 98 of 145

SUB-TOTAL-C
Total for 220/132/33kV Trishuli Hub AIS new
Substation (Package-2, Part-II) (II) (Part-A+ Part-B+
Part C)
Total of Schedule-1
Date: Signature:

Place: Printed Name:

Designation:

Common Seal:

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-4 Page 99 of 145

Package-2 for 220/132/33kV Chilime Hub GIS new substation (Part-I) and 220(Hybrid)/132/33kV Trishuli-3B Hub AIS new substation (Part-II) under 220kV Chilime-Trishuli Transmission System Project

(Schedule of rates and prices)

Bidder's Name & Address:

Installation Charges

1 2 3 4 5 6 7 8 9=6x8 10 11 = 6 x 10
Sl. No. Item Description Country of Origin Type & Unit Quantity Portion in Foreign Currency Portion in Local Currency
Designation Currency (As Unit Charges Total Charges Unit Price Total Price
per ITB 19.1) (NPR) (NPR)

I. 220/132/33kV CHILIME HUB GIS new Substation (Package-


2, Part-I)
PART - A: OWNER ASSESSED QUANTITIES
A POWER TRANSFORMER
A.1 1-Phase Auto Transformer
53.33MVA, 220/√3 / 132/√3 / 33kV Single Phase Auto
a) Nos. 7
Transformer (without transformer Oil)
Insulating oil for 53.33MVA , 220/132/33 KV, 1-phase
b) Lot* 7
Autotransformer (* 1Lot = Oil for 1 Autotransformer )
c) 33kV Current transformer (NCT) for autotrasnformer No 2

A.2 POWER TRANSFORMER


50 MVA, 132 /33kV Three Phase Power Transformer
a) Nos. 1
(without transformer Oil)
Insulating oil for 50MVA , 132/33 KV, 3-phase Power
b) Lot* 1
Transformer (* 1Lot = Oil for 1 Autotransformer )

A.3 Testing & Maintenance Equipments


a) Oil Storage Tank of 20KL No. 1
b) Transformer Oil Filtration plant (6KLPH) No 1

B) LT Transformer
a) 630KVA, 33/0.400 kV Nos. 2

C 245 KV EQUIPMENTS
C1 245KV GIS Equipment

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-4 Page 100 of 145

1.1 245kV, SF6 GIS Bus Bars Module as per section project

a) 3000A, 40kA for 1 sec Sets 2


1.2 245kV, SF6 GIS Bus Coupler feeder bay Module as per section
project
a) 3000A, 40kA for 1 sec Sets 1
1.3 245kV, SF6 GIS Line feeder bay Module as per section project

a) 1600A, 40kA for 1 sec Sets 2


1.4 245kV, SF6 GIS spare Line feeder bay Module as per section
project
a) 1600A, 40kA for 1 sec Sets 1
1.5 245kV, SF6 GIS ICT feeder bay Module as per section project

a) 1600A, 40kA for 1 sec Sets 2


1.6 245kV, SF6 GIS Auxiliary Bus Module as per section project
to connect spare unit of Transformer
a) 1600A, 40kA for 1 sec Set 1
1.7 SF6 Gas Insulated Bus Duct (GIB) outside GIS Hall alongwith
associated support structure and accessories (for Transformer
bays)
a) 1600A, 40kA for 1 sec. Single Phase Mtr. 460
1.8 SF6 Gas Insulated Bus Duct (GIB) outside GIS Hall alongwith
associated support structure and accessories (for Line bays)

a) OPTION-I
1600A, 40kA for 1 sec. Single Phase Mtr. 225
b) OPTION-II
1600A, 40kA, 1sec three phase Mtr. 75
Note : Bidder is required to quote for either option-I or Option-
II
1.9 220kV, SF6 to Air Bushing alongwith associated support
structure (for Transformer bays)
a) 1600A, 40kA for 1 sec. Single Phase Nos. 7
1.10 220kV, SF6 to Air Bushing alongwith associated support
structure (for line bays)
a) OPTION-I
1600A, 40kA for 1 sec. Single Phase Nos. 9
b) OPTION-II
1600A, 40kA, 1sec three phase Nos. 3
Note : Bidder is required to quote for either option-I or Option-II

C.2 245KV Outdoor AIS Equipment


1.1 216 KV Surge Arrester (1-phase) Nos. 16
1.2 4400pF, 245 kV Capacitive Voltage Transformer (1-Phase) Nos. 9

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-4 Page 101 of 145

1.3 245kV Bus Post Insulator (1-Phase) Nos. 9

D 145kV Equipment
D.1 145KV GIS Equipment
1.1 145kV, SF6 GIS Bus Bars Module as per section project

a) 2000A, 40kA for 1 sec Set 2


1.2 145kV, SF6 GIS Bus Coupler feeder bay Module as per section
project
a) 2000A, 40kA for 1 sec Set 1
1.3 145kV, SF6 GIS Line feeder bay Module as per section project

a) 1250A, 40kA for 1 sec Sets 4


1.4 145kV, SF6 GIS Spare Line feeder bay Module as per section
project
a) 1250A, 40kA for 1 sec Set 1
1.5 145kV, SF6 GIS ICT feeder bay Module as per section project
for 220/132 kV Transformer
a) 1250A, 40kA for 1 sec Set 2
1.4 145kV, SF6 GIS ICT feeder bay Module as per section project
for 132/33 kV Transformer
a) 1250A, 40kA for 1 sec Set 1
1.6 145kV, SF6 GIS Auxiliary Bus Module as per section project
to connect spare unit of Transformer
a) 1250A, 40kA for 1 sec Set 1
1.7 SF6 Gas Insulated Bus Duct (GIB) outside GIS hall including
Bus Duct support structure and associated accessories

a) 1250A, 40kA 1sec single phase (for 7x53.33MVA 1-Phase


Mtr 395
Transformer bays)
b) 1250A, 40kA 1sec three phase Mtr 300
1.8 145kV, SF6 to Air Bushing alongwith associated support
structure
a) 1250A, 40kA 1sec three phase Set 5
b) 1250A, 40kA 1sec single phase Set 7

D.2 145kV Outdoor AIS EQUIPMENT


1.0 120 kV Surge Arrestors (1-Phase) Nos. 25
2.0 8800pF, 145 kV Capacitive Voltage Transformer (1-Phase) Nos. 15
3.0 8800pF, 145 kV Capacitive Voltage Transformer (1-Phase) (for Nos. 15
tariff metering)
4.0 145KV Bus Post Insulator Nos. 9

E 72.5kV EQUIPMENT
1.1 72.5 kV, 1250A, 25kA Circuit Breaker (3-phase) with support No. 1
structure
1.2 72.5 kV, 1250A, 25kA Isolators with earth switch (3-phase, No. 1
DBR type)

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-4 Page 102 of 145

1.3 72.5kV, 50A, 25 kA with 120% extended rating CT Nos. 3


1.4 72.5kV PT(1-phase) Nos. 3
1.5 72.5 kV BPI (1-phase) Nos. 6

F 33kV Equipments
1.1 33 kV, 630A, 25kA Isolators with out earth switch (3-phase, No. 1
DBR type)
1.2 30 kV Surge Arrestors (1-phase) Nos. 3
1.3 36 kV BPI Nos. 3
1.4 36 kV HG Fuse along with support insulator (1-phase) Nos. 3

G 33kV, 25 kA (3 Phase) Indoor switch gear panel including


control, relay & protection
i) 33kV Line bay Module Nos 2
ii) 33kV Incomer Transformer Module Nos 1
iii) 33kV LT Transformer Module Nos 1
iv) 33kV Bus Sectionalizer Module Nos 1
v) 33kV Bus PT Module Nos 2

H Testing & Maintenance Equipment for GIS


1.1 Partial Discharge Monitoring System (Portable type) Set 1
1.2 EOT crane for 220kV GIS Hall Set 1
1.3 EOT crane for 132kV GIS Hall Set 1

I RELAY PANELS (WITH AUTOMATION)


1 245kV
1.1 Circuit Breaker Relay Panel
a) CB Relay Panel With Auto Reclose Nos. 3
b) CB Relay Panel Without Auto Reclose Nos. 3
1.2 Line Protection Panel
Line Protection Panel with Distance Protection and Current
a) Nos. 3
Differential Protection at Chilime GIS End
Transformer Protection Panel (For both HV & MV side)
1.3 Nos. 2

1.4 Bus Bar Protection Panel set 1


2 145kV
2.1 Circuit Breaker Relay Panel
a) CB Relay Panel With Auto Reclose Nos. 5
b) CB Relay Panel Without Auto Reclose Nos. 4
2.2 Line Protection Panel
Line Protection Panel with Current Differential Protection and
a) Back up O/C & E/F Protection at Chilime GIS End Nos. 5

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-4 Page 103 of 145

Line Protection Panel housing two nos. Current Differential


b) Protection relays & accessories at Rasuagadi HPP End Nos. 1

Line Protection Panel housing one no. Current Differential


c) Protection relay & accessories at Upper Sanjen HPP End Nos. 1

Line Protection Panel housing one no. Current Differential


d) Protection relay & accessories at Lower Sanjen HPP End Nos. 1

Transformer Protection Panel (For both HV & MV side)


2.3 Nos. 1

2.4 Bus Bar Protection Panel set 1


Other/Common equipments Pertaining to C & R System
3

a) Time Synchronisation Equipment No. 1

J SUBSTATION AUTOMATION
Substation Automation System as per Technical Specification:
1

a) 220kV System (Nos. of bays) Nos. 6


b) 132 kV System (Nos. of bays) Nos. 9
c) BCU for auxilary system set 1
d) 33 kV HT Indoor Switchgear set 1
K Digital Protection Coupler& PBAX
a) Digital Protection Coupler* Nos 2
b) PBAX with following configuration as per TS Set 1
i 2 wire subscriber interface card with capacity 32 local
subscribers (along with 32 nos. Instruments)
ii) E-1 interface with 2 trunks G-703
iii) 2 wire interface with 1 trunk (For PSTN)
*Digital Protection coupler for 220kV Chilime Hub - Trishuli-
3B D/c Line have been considered at respective substation
end.
L LT Switchgear (As per Technical specification)
a 400V Main switchboard Set 1
b 400V ACDB Set 1
c 400V MLDB Set 1
d 400V Emergency LDB Set 1
e 220V DCDB Sets 2
g 48V DCDB Set 2

M Batteries
a 220V
i 800 AH Nos 2
b 48V

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-4 Page 104 of 145

i 600AH Nos 2

N Float Cum Boost Battery Charger


a 220V Float Cum Boost Battery Charger
i 90A/90A Nos 2
b 48V Float Cum Boost Battery Charger
i 90A/90A Nos 2

O Diesel Generator with control Panel


a 250 kVA Set 1

P Fire Protection System


a Portable /Trolley/Wheel mounted extinguishers
i 9 litre water type Nos 2
ii 50 litre foam type Nos 2
iii 4.5 kg CO2 type Nos 10
iv 4.5 kg Dry Chemical Power (DCP) type Nos 6
b Smoke detection system Set 1
c Fire detection and Alarm System Set 1

Q Cables along with clamps, glands, lugs and straight joints


etc.
a 33kV HT XLPE Power Cable alongwith accessories and
termination equipments
i) 1Cx600 Sq.mm KM 2.5
ii) 1Cx300 Sq.mm KM 2
b Power Cables - (1.1kV grade)
i 3.5Cx300 sqmm (XLPE) cable for filter Machine along with 2
KM 1
nos outdoor receptacles -250A

R Air conditioning
High wall type split AC unit of 2 TR capacities for control
1 Nos. 25
room, relay room and battery room

S STEEL STRUCTURES (Tower,Gantry structures&


Equipment support structures)
a Lattice/pipe Structure for towers,beams and equipments
including peak plates/pack washers and guest paltes
including foundation bolts(nuts,washers,MS plate welded at
the bottom)
i) Lattice stucture & foundation bolts MT 90
ii Pipe structure & foundation bolts MT 10
b Fastners for towers,beams and equipment support strcutures
MT 6

T Communication Equipment for Chilime Hub GIS


1.0 Telecom Equipments

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-4 Page 105 of 145

A1
SDH Equipment (STM-4 MADM upto 5 MSP protected directions)
(i) Base Equipment (Common cards, Cross Connect/control cards, optical base
cards, power supply cards, power cabling, other hardware and accessories
including sub racks, patch cord, DDF etc fully equiped excluding (ii) & (iii) Nos. 1
below

(ii) Optical Interface Cards/SFP


a S4.1 SFP Nos. 6
b L4.1 SFP Nos. 2
c L4.2 SFP Nos. 1

(iii) Tributary cards


a E1 Interface card (Min.16 interfaces per card) Set 2
b Ethernet Interface 10/100 Base T with Layer-2 switching (Min 8 Interfaces
Nos. 2
per card)

B Equipment Cabinets No. 1

2.0
VOIP telephone instrument with one common switch (min. 8 port) Nos. 2

SUB TOTAL PART-A

PART-B: VENDOR ASSESSED QUANTITIES

Erection Hardware :-Insulator strings, Disc Insulators,


Hardware, conductor, bus-bar materials, cable trays, clamps,
spacers, connectors including conectors for Auto Transformer ,
A
Junction box, earthwire, earthing material risers, buried cable
trenches/pipe of equipment & lighting, all accessories etc. for
the following:

1 220 kV DM-type layout for GIS termination arrangement


1.1 Line Bay Set 3
1.2 Transformer Bay Sets 2

2 132 kV DM-type layout for GIS termination arrangement

1.1 Line Bay Sets 5


1.2 Transformer Bay Sets 3

3 33 KV
3.1 Line Bay Set 2
3.1 Transformer Bay Set 1
3.3 LT Transformer Bay Set 1

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-4 Page 106 of 145

Erection Hardware etc for 72.5kV equipments & LT


4 Set 1
Transformer connection

For spare unit of 220/132/33kV auto transformer connection


through auxiliary buses, Neutral formation and delta formation
(for two banks): Required 245kV BPI, 132 kV BPI, 72.5kV BPI
for tertiary auxilary bus & delta formation, 36kV BPI for Neutral
B Set 1
formation & Neutral auxiliary bus including Al tube, bus-bar
materials, clamps, spacers, connectors, including equipment
connectors, support structures , Earthing of spare unit as per
technical specification.

C Ventilation & heating System


2 Ventilation & heating system (as per technical specification)

(i) 220kV GIS Hall LS 1


(ii) 132 kV GIS Hall LS 1

D Illumination System
1.1 Substation Lighting 0 0
Control Room cum administrative building illumination (1000
(i) LS 1
sqmm)
(ii) 220kV GIS Building (620 sqmm) LS 1

(iii) 132kV GIS Building (350 sqmm) LS 1

(iv) 33kV Indoor Switchyrad Panel Room (160 sqmm) LS 1


(v) Fire Fighting Pump house (100 sqmm) LS 1
(vi) Outdoor Switchyard Lighting LS 1
(vii) Street Lighting LS 1
(viii) Occupancy sensor LS 1
1.2 Transit Camp (420 sqmm) LS 1
1.3 Township Area (Staff Quarter area) Lighting LS 1
(i) B type (250 sqmm) LS 1
(ii) C type (300 sqmm) LS 1

(iii) D type (200 sqmm) LS 1


1.4 Security room (10 sqmm) LS 1
1.5 Car parking shed (for 10 cars) LS 2

E Fire Protection System (as per technical Specification) set 1


1 Pumping arrangement inside pump house set 1

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-4 Page 107 of 145

2 Hydrant system outside the Pump House. set 1


3 HVW spray system & Hydrant system for Transformer :
a 53.3 MVA, 220/132 kV Single Phase Auto Transformer Nos 7
b 50 MVA,132/33 kV Three phase transformer Nos 1

F POWER & CONTROL CABLES


i For 220/132/33kV Chilime Hub GIS Substation:
a Power Cables(PVC) - (1.1kV grade) LS 1
b Power Cables (XLPE) - (1.1kV grade) LS 1
c Control Cable (PVC) - (1.1kV grade) LS 1
d Cable glands, lugs & straight through joints for Power & Control cables
LS 1

ii For 132kV Upper Sanjen HPP Switchyard:


a Power Cables(PVC) - (1.1kV grade) LS 1
b Control Cable (PVC) - (1.1kV grade) LS 1
c Cable glands, lugs & straight through joints for Power & Control cables
LS 1

iii For 132kV Lower Sanjen HPP Switchyard:


a Power Cables(PVC) - (1.1kV grade) LS 1
b Control Cable (PVC) - (1.1kV grade) LS 1
c Cable glands, lugs & straight through joints for Power & Control cables
LS 1

iv For 132kV Lower Rasuagadi HPP Switchyard:


a Power Cables(PVC) - (1.1kV grade) LS 1
b Control Cable (PVC) - (1.1kV grade) LS 1
LS 1
c Cable glands, lugs & straight through joints for Power & Control cables

G Visual Monitoring System for watch & ward as per technical LS 1


specification
H Earthing and lightning protection including necesaary
connectors/connections, risers etc. complete in all respect

i Earth Conductor (copper) LS 1


ii Earth Rod (copper clad steel) LS 1
iii Equipment for lightning protection LS 1
I SUBSTATION AUTOMATION
a Integration of all 220/132kV Bays under present scope with the LS 1
SCADA of SIEMENS (SINAUT Spectrum) at Load Dispatch
Centre, Kathmandu including supply of Hardware, Software,
accessories etc. as per TS Section Project

SUB TOTAL PART-B

PART-C: Civil Works

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-4 Page 108 of 145

Excavation in all types of soil and rock (including crushing of


large sized stone boulders lying on substation plot surface and
1.0 Cu.M 23,200
underground) including backfilling disposal etc. for all leads and
lifts
Providing and laying of Plain Cement Concrete (PCC) (1:4:8)
2.0 Cu.M 1550
Providing and laying of Plain Cement Concrete (PCC) (1:2:4)
3.0 Cu.M 195
Providing and laying of Reinforced Cement Concrete Design
Mix M25 including pre cast, shuttering, Grouting of pockets &
4.0 underpinning but excluding steel reinforcement Cu.M 8000

Providing and laying Plain Cement Concrete 1:5:10 (1 cement :


5.0 Cu.M 1530
5 sand : 10 Stone aggregate)
6.0 Steel Reinforcement ( Fe 500) MT 700
Stone filling (40 mm size) over grating of transformer
7.0 foundation Cu.M 165

Misc. Structural steel including rails, embedments, edge


protection angles, gratings etc. but excluding the reinforcement
8.0 MT 175
steel and steel for lattice and pipe structures.

Stone spreading including antiweed treatment in switchyard


9.0 Sq. M. 20000
excluding PCC
All civil works for following buildings as per technical
specification and approved drawings but excluding excavation,
10.0 PCC, RCC and reinforcement steel (Fe-500), which shall be
measured and paid seperately under respective items of BPS :

i) Auxilliary building (33kV indoor switchgear room) Sq. M. 160


Fire fighting pump house building (excluding external finish)
ii) Sq. M. 100
iii) Water Tank (excluding external finish) LS 1
iv) Township (Quarters)
a C Type Sq. M. 600
v) Transit Camp Sq. M. 420
Control Room Building (Double Storey with plinth area of 500 sq.m.
vi) Sq. M. 1000
on each floor)
vii) Parking Shed (for 10 Cars) LS 2
11.0 External finish as per specification for following buildings:
i) Auxilliary building (33kV indoor switchgear room) Sq. M. 160
Fire fighting pump house building (excluding external finish)
ii) Sq. M. 100

iii) Water Tank (excluding external finish) LS 1


iv) Township (Quarters)
a B Type Sq. M. 250
b C Type Sq. M. 300
c D Type Sq. M. 200
v) Transit Camp Sq. M. 420

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-4 Page 109 of 145

Control Room Building (Double Storey with plinth area of 500 sq.m.
vi) Sq. M. 1000
on each floor)
vii) Parking Shed (for 10 Cars) LS 2
12.0 PRE ENGINEERED BUILDINGS
i) 220 KV GIS HALL
All Civil works including finishing, internal cable trench, etc.
complete as per technical specification and approved drawings,
excluding excavation, PCC, RCC and reinforcement steel which shall
be measured and paid seperately under respective items of BPS.

a) GIS Hall Sq. M. 620


b) AHU & Panel Room Sq. M. 100
ii) 132 KV GIS HALL
All Civil works including finishing, internal cable trench, etc.
complete as per technical specification and approved drawings,
excluding excavation, PCC, RCC and reinforcement steel which shall
be measured and paid seperately under respective items of BPS.

a GIS Hall Sq. M. 350


b AHU & Panel Room Sq. M. 100
13.0 Concrete road as per drawing except reinforcement & concrete
a) Road 3.75m wide Sq.M. 3200
Providing and laying 60mm thick factory made cement concrete
interlocking paver block of approved size, design & shape, laid in
required colour and pattern over and including 50mm thick
b)
compacted bed of coarse sand, filling the joints with fine sand etc. all Sq.M. 310
complete as per the direction of Engineer-in-charge.(3.1m width for
both side-for township and approach road only)

Construction of rail cum road as per drawing including all items such
14.0 as excavation, compaction, rolling, watering, WBM etc but excluding
concrete, reinforcement and structural steel.
a) Section having two rails Sq.M. 240
Chain link fencing as per technical sepcification and approved
15.0 RM 320
drawing excluding concrete
16.0 Switchyard Gate excluding Concrete Nos. 2
Septic tank and soak pit (for 50 users) complete as per technical
specification and approved drawing excluding concrete &
17.0 reinforcment which shall be measured and paid seperately under
respective items of BPS .
a) Control room Building (for 20 users) LS 1
b) Quarters & Transit Camp (for 50 users) LS 2
c) Security Room (for 10 users) LS 1
Supplying & laying hume pipe of grade (NP-3) excluding concrete
18.0
and reinforcement
a) 250mm dia RM 100

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-4 Page 110 of 145

b) 300mm dia RM 100


c) 450mm dia RM 100
d) 600mm dia RM 100
e) 900mm dia RM 50
19.0 Supplying and erecting dewatering pumps
a) 5 HP Nos. 2
b) 0.5 HP Nos. 7
20.0 Drains Excluding Concrete
a) Section A-A (300 mm wide X depth up to 600mm) RM 500
b) Section B-B ( 450 mm wideX depth from 600 mm to 900 mm) RM 500
c) Section C-C (600 mm wide X depth from 900 mm to 1200 mm) RM 400

d) Section D-D (750 mm wide X depth from 1200 mm to 1500mm ) RM 300


External water supply from borewell/main water supply point to Fire
21.0
water Tank, control room building, township buildings
a) 80 mm Dia GI pipe RM 100
b) 50 mm Dia GI pipe RM 80
c) 40mm Dia GI pipe RM 60
d) 25mm Dia GI pipe RM 40
All Civil works for Burried cable trenches for Auxilliary power
arrangement. However item excavation, PCC, RCC, Reinforcement
Steel required to complete the work shall be measured and paid
22.0 RM 150
seperately under respective items of BPS

External sewerage system including all item such as excavation,


23.0
piping, pipe fittings, manholes, gali trap, gali chamber etc.
a) 250 mm Dia. RM 100
b) 150 mm Dia. RM 100
All civil works for Boundary wall including excavation, concrete,
reinforcement steel ,structural steel, plaster, painting, barbed wire and
24.0 RM 380
concertina coil etc all complete as per technical specification (2.5 m
high brick masonary wall and 0.5 m high angle support on top)

Main boundary wall Gate (Steel ) including all works complete as


25.0 LS 1
per technical specification
26.0 Site levelling
Earth work in excavation and filling in all types of soils including
i soft/disintegrated rock with all leads and lifts within sub station Cu. M 40000
boundary
Earth work in filling with borrowed earth with all leads and lifts
ii Cu. M 10000
including royalty,taxes etc
All civil works for security room as per TS including septic tank and
soak pit. Internal and external finish, sanitary and plumbing works,
27.0 Sq. m. 18
plinth protection etc. to complete the building are included in the
item

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-4 Page 111 of 145

Construction of retaining wall with random rubble masonary in


cement sand mortar (1:6) including levelling up with cement concrete
(1:6:12), providing weep holes of PVC pipes (150 mm dia) with
necessary filter material at the mouth of weep holes, 50 mm thick
27.0 cement concrete (1:2:4) copping on the top of wall, 100 mm thick Cu. M 600
PCC (1:4:8) below RR masonary work, excavation of foundation for
all lifts up to 3m above lower level. Item of excavation, PCC (1:2:4
& 1:4:8) shall be measured and paid seperately under respective
items of BPS
28.0 Soil Investigation as per TS LS 1
29.0 Strenthening of existing Approach Road-
a) Construction of 3.75 m wide black top (Bituminous/asphalt) road
with 3.75 m wideblack top pavement over 100 mm thick WBM layer
after filling potholes with WBM and 1.3 m wide earthen shoulders on Sq. M 375
either side of road, WBM for pothole filling shall be measured and
paid separately
b) Supplying and providing WBM consisting of 90mm to 45mm stone
with interstices filled by 13.2 mm nominal size stone screening and
Cu. M 80
good earth for filling potholes in existing approach road including
compaction of WBM with road roller
Local sand filling around and under DG set foundation and other
30.0 Cu. M 300
foundations as applicable.
Stone soling below foundations wherever specified in approved
31.0 Cu. M 200
drawings during detailed engineering.

Earthwork in excavation in Hard rocks in open areas/nallas/channels,


to the required slopes, shapes,levels,elevationns and profile including
trimming of bottom and slopes of excavation and disposal and
stacking of rocks for lead upto 1000m beyond levelling boundary
32.0 Cu. M 50
and all lifts, with all labour, material, tools, tackles and equipment,
safeguards and incidentals, royalty , taxes etc. specification and
directions of Engineer-In-Charge. (50% void deduction from stack
measurement)

Demolition of RCC work in Foundations, Drains etc including


stacking of serviceable material at a place within S/S boundary as
per the direction of Engineer-in-charge and disposal of unserviceable
material at a place withinn 2 km from S/S boundary wall. Excavation
33.0 Cu. M 100
for and disposal of unserviceable materialat a place withinn 2 km
from S/S boundary wall. Excavation for RCC foundations to be
dismantled shall not be payable separately and deemed to be
included in the item of dismantling of RCC work

34.0 River protection works

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-4 Page 112 of 145

Supplying and providing stones (used in gabion wall/masonry


a) wall/checkwall/spurs/stone apron)-hard, sound, unweathered and Cu. M 2450
angular rock fragments or boulders

Supplying and Providing Gabion wire mesh of 80x100 mm as per TS


b) Sq. M 1100
complete in all respect for gabion wall and spur
c) Boulders packed with small stones or spalls into interstices Sq. M 2500

SUB-TOTAL-C
Total for 220/132/33kV Chilime Hub GIS new Substation
(Package-2, Part-I) (I) (Part-A+ Part-B)

II 220(Hybrid)/132/33KV TRISHULI-3B HUB AIS NEW S/S


(Package-2, Part-II)

PART -A: OWNER ASSESSED QUANTITIES

A POWER TRANSFORMER
A.1 1-Ph Autotransformers
a) 53.33MVA, 220/√3 / 132/√3 / 33kV Single Phase Auto Nos. 7
Transformer (without transformer Oil)
b) Insulating oil for 53.33MVA , 220/132/33 KV, 1-phase Lot* 7
Autotransformer (* 1Lot = Oil for 1 Autotransformer )
c) 33kV Current transformer (NCT) for autotrasnformer No 2

A.2 3-Phase Power Transformer


50 MVA, 132 /33kV Three Phase Power Transformer (without
a) Nos. 1
transformer Oil)
Insulating oil for 50MVA , 132/33 KV, 3-phase Power
b) Lot* 1
Transformer (* 1Lot = Oil for 1 Autotransformer )

A.3 Testing & Maintenance Equipments


a) Oil Storage Tank of 20KL No. 1
b) Transformer Oil Filtration plant (6KLPH) No 1

B LT TRANSFORMER
1.0 630 kVA, 33/0.400kV Nos 2

C 245 KV EQUIPMENTS
C.1 245KV GIS HYBRID Equipment
1.1 245kV, SF6 GIS Hybrid Bus Coupler bay Module as per
section project
a) 3000A, 40kA for 1 sec Set 1

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-4 Page 113 of 145

1.2 245kV, SF6 GIS Hybrid Bus Transfer Bus Coupler bay Module
as per section project
a) 3000A, 40kA for 1 sec Set 1
1.3 245kV, SF6 GIS Hybrid Line feeder bay Module as per section
project
a) 1600A, 40kA for 1 sec Set 6
1.4 245kV, SF6 GIS Hybrid ICT feeder bay Module as per section
project
a) 1600A, 40kA for 1 sec Set 2

C.2 245KV Outdoor AIS Equipment (40kA for 1 sec)


1.1 216 KV Surge Arrester (1-phase) Nos. 25
1.2 245 kV, 4400pFCapacitive Voltage Transformer (1-Phase) Nos. 24
1.3 245 kV, 1600A, 40kA, DBR Isolator (Tandem type) (3-Phase) Nos. 8
1.4 245kV Bus Post Insulator (1-Phase) (Except auxiliary buses of
Nos. 50
transformer)

C.3 Testing & Maintenance Equipment for 220kV GIS Hybrid

1.1 Partial Discharge Monitoring System (portable type) Set 1

D 145 kV Equipment
1.0 145 kV Circuit Breakers (3-Phase) with support structure
a 1250A, 40kA Nos 7
b 2000A, 40kA Nos 1

2.0 145kV Isolator (3-phase)-Double Break


a 1250A, 40kA Isolator without E/S Nos 7
b 1250A, 40kA Isolator with one E/s Nos 14
c 1250A, 40kA Isolator without E/s (Tandem) Nos 7
d 1250 A, 40kA Isolator without E/S (Beam mounted) Nos 7
e 2000A, 40kA Isolator with two E/s Nos 2

3.0 145 kV Current Transformer (1-Phase)


a 1200A, 40kA with 120% extended current rating Nos 6
b 1200 A, 40kA with 150% extended current Nos 3
c 600 A, 40kA with 120% extended current Nos 15
d 600 A, 40kA with 120% extended current for tariff metering Nos 12

4.0 145 kV Capacitive Voltage Transformer (1- Phase)


a 8800 pF Nos. 18
b 8800 pF for tariff metering Nos. 12
5.0 120 kV Surge Arrestors
a 120 kV Surge Arrestors (1-phase) - Pedestal mounted Nos. 22
b 120 kV Surge Arrestors (1-phase) - suitable for mounting on Nos. 6
transmission line dead end tower

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-4 Page 114 of 145

6.0 145 kV Bust Post Insulator (Except auxiliary buses of Nos 42


transformer)

E 33 kV Equipment
1.0 36kV Circuit Breakers (3-Phase) with support structure
a 1250A, 25kA Nos 5

2.0 36kV Isolator (3-phase)-Double Break


a 1250A, 25kA, Isolator without E/S Nos 8
b 1250A, 25kA, Isolator with one E/s Nos 3
c 1250A, 25kA, Isolator without E/s (Tandem) Nos 5

3.0 36 kV HG Fuse along with support insulator (1-phase) Nos. 3

4.0 36kV Current Transformer (1-Phase)


a 1000A, 25kA with 120% extended current rating Nos 3
b 600 A, 25kA with 120% extended current Nos 12

5.0 36kV Voltage Transformer (1- Phase) Nos 3

6.0 30kV Surge Arrestors (1-phase) Nos. 12


7.0 36kV Bust Post Insulator (Except auxiliary & neutral buses of Nos 18
transformer)
F 72.5kV EQUIPMENT
1.1 72.5 kV, 1250A, 25kA Circuit Breaker (3-phase) with support No. 1
1.2 structure
72.5 kV, 1250A, 25kA Isolators with earth switch (3-phase, No. 1
1.3 DBR type)
72.5kV, 50A, 25 kA with 120% extended rating CT Nos. 3
1.4 72.5kV PT.(1-phase) Nos. 3
1.5 72.5 kV BPI (1-phase) Nos. 6

G RELAY PANELS (WITH AUTOMATION)


1.0 220 kV
a Circuit Breaker Relay Panel
i With Auto Reclose Nos. 7
ii With out Auto Reclose Nos. 3
b Line Protection Panel
i Line Protection Panel with Distance Protection and Current Differential Nos. 6
Protection at Trishuli-3B Hub End
ii Line Protection Panel housing two nos. Current Differential Protection Nos. 1
relays & accessories at Matatirtha End
iii Line Protection Panel housing two nos. Current Differential Protection Nos. 1
relays & accessories at Upper Trishuli-1 End
c Transformer Protection Panel (For both HV & MV side) Nos. 2
d Bus Bar Protection Panel Set 1

2.0 132 kV

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-4 Page 115 of 145

a Circuit Breaker Relay Panel


i With Auto Reclose Nos. 4
ii With out Auto Reclose Nos. 4
b Line Protection Panel
i) Line Protection Panel with Current Differential Protection and Back up Nos. 4
O/C & E/F Protection at Trishuli-3B Hub End
ii) Line Protection Panel housing two nos. Current Differential Protection Nos. 1
relays & accessories at Trishuli-3A HPP End
iii) Line Protection Panel housing two nos. Current Differential Protection Nos. 1
relays & accessories at Trishuli-3B HPP End

c Transformer Protection Panel (For both HV & MV side) Nos. 1


d Bus Bar Protection Panel Set 1
3.0 33 kV
a Line Protection Panel Nos. 3
b Protection Panel for TBC bay Nos. 1
c Transformer Protection Panel Nos. 1
4.0 COMMON EQUIPMENTS
a Relay tool kit Set 1
b Time synchronisation equipment No. 1
H SUBSTATION AUTOMATION
H.1 Complete Substation Automation System (SAS) for substation including
hardware and software for the substation & remote control stations
alongwith associated equipments for the following bays as per Technical
Specification

a Main bays to be automated


i 220 kV system Bay Nos 10
ii 132 kV substation Bay Nos 8
iii 33 kV substation Bay Nos 5
iv BCU for controlling & monitoring of Auxilary System Set 1

I Digital Protection Coupler & PBAX


a) Digital Protection Coupler* Nos 10
b) PBAX with following configuration as per TS Set 1
i 2 wire subscriber interface card with capacity 32 local
subscribers (along with 32 nos. Instruments)
ii) E-1 interface with 2 trunks G-703
iii) 2 wire interface with 1 trunk (For PSTN)
* Digital protection Coupler for both ends for all 220kV Lines
are considered. However, Digital Protection coupler for 220kV
Chilime Hub - Trishuli-3B D/c Line have been considered at
respective substation end.

J LT Switchgear (As per Technical specification)


a 400V Main switchboard Set 1

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-4 Page 116 of 145

b 400V ACDB Set 1


c 400V MLDB Set 1
d 400V Emergency LDB Set 1
e 220V DCDB Sets 2
f 48V DCDB Set 2

K Batteries
a 220V
i 600 AH Nos 2
b 48V
i 600AH Nos 2

L Float Cum Boost Battery Charger


a 220V Float Cum Boost Battery Charger
i 90A/90A Nos 2
b 48V Float Cum Boost Battery Charger
i 90A/90A Nos 2

M Diesel Generator with control Panel


a 250 kVA Set 1

N Fire Protection System


a Portable /Trolley/Wheel mounted extinguishers
i 9 litre water type Nos 2
ii 50 litre foam type Nos 2
iii 4.5 kg CO2 type Nos 10
iv 4.5 kg Dry Chemical Power (DCP) type Nos 6
b Smoke detection system Set 1
c Fire detection and Alarm System Set 1

O.1 Cables along with clamps, glands, lugs and straight joints etc.

b Power Cables - (1.1kV grade)


i 3.5Cx300 sqmm (XLPE) cable for filter Machine along with termination KM 1
arrangement as per TS

O.2 132kV XLPE Power Cable for interconnection of 132kV Trishuli-3B


HPP Line Bay with Dead end Tower
a) 132kV, XLPE insulated , 1C X 1600 sqmm size copper cable as per kM 1.5
technical specificaion.(Metallic sheath and PE outer sheathed with
graphite coating and short circuit current 40kA for 1 sec) including one
spare cable
b) Cable termination as per technical specification for interconnection with Nos 12
overhead transmission for cable at sl. No.1 above (excluding terminating
structure)
c) Single phase earth link box Nos 12
d) 36kV grade 1Cx300 Sqmm Earth Continuity Cable kM 0.4

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-4 Page 117 of 145

e) Laying & Jointing etc for 4 nos,1C, 1600 sqmm size cables alongwith Route 0.4
all necessary installation material as per technical specification kM

f) Construction of buried cable trench for 132kV XLPE Cable including M 400
road crossing: All civil works alongwith back filling, restoration etc (as per
specification) including excavation, PCC, sand filling, PVC warning
tapes, RCC hume pipe(NP3) of suiatable diameter along with collars &
jointings etc required to complete buried cable trench shall be deemed
to be included in the item of work.

P Air conditioning System for Control room cum administrative


building
a High wall type split AC unit of 2 TR capacity Nos 20

Q Lattice/pipe Structure for towers,beams and equipments


including peak plates/pack washers and guest paltes including
foundation bolts(nuts,washers,MS plate welded at the bottom)

(a) Lattice stucture & foundation bolts MT 420


(b) Pipe structure & foundation bolts MT 30
(c ) Fastners for towers,beams and equipment support strcutures MT 20

R.1 Communication equipments for Trishuli-3B Hub Substation


1.0 Telecom Equipments

A1
SDH Equipment (STM-4 MADM upto 5 MSP protected directions)
(i) Base Equipment (Common cards, Cross Connect/control cards, optical base
cards, power supply cards, power cabling, other hardware and accessories
including sub racks, patch cord, DDF etc fully equiped excluding (ii) & (iii) Nos. 2
below

(ii) Optical Interface Cards/SFP


a S4.1 SFP Nos. 10
b L4.1 SFP Nos. 4
c L4.2 SFP Nos. 2

(iii) Tributary cards


a E1 Interface card (Min.16 interfaces per card) Set 4
b Ethernet Interface 10/100 Base T with Layer-2 switching (Min 8 Interfaces
Nos. 4
per card)

B Equipment Cabinets No. 1

2.0 Network Manager System - Craft Terminal


a Hardware Set 1
b Software Set 1

3.0
VOIP telephone instrument with one common switch (min. 8 port) Nos. 2

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-4 Page 118 of 145

R.2 Communication equipments for Trishuli-3B HPP


1.0 Telecom Equipments

A1
SDH Equipment (STM-4 MADM upto 3 MSP protected directions)
(i) Base Equipment (Common cards, Cross Connect/control cards, optical base
cards, power supply cards, power cabling, other hardware and accessories
including sub racks, patch cord, DDF etc fully equiped excluding (ii) & (iii) Nos. 1
below

(ii) Optical Interface Cards/SFP


a S4.1 SFP Nos. 2

(iii) Tributary cards


a E1 Interface card (Min.16 interfaces per card) Set 2
b Ethernet Interface 10/100 Base T with Layer-2 switching (Min 8 Interfaces
Nos. 2
per card)

B Equipment Cabinets No. 1

2.0 Network Manager System - Craft Terminal


a Hardware Set
b Software Set

3.0
VOIP telephone instrument with one common switch (min. 8 port) Nos. 2

Sub-Total Part-A

Part-B: VENDOR ASSESSED QUANTITIES

A Erection Hardware

Insulator strings, Disc Insulators, Hardware, conductor, Al tube, bus-bar


materials, cable trays, Bay MB, clamps, spacers, connectors including
equipment connectors, Junction box, earthwire, buried cable
trenches/pipe equipment & lighting, all accessories etc. for the following:

a 220 kV Layout (DMT Layout with GIS Hybrid)


i Line Bay Set 6
ii Transformer Bay Set 2
iii TBC Bay Set 1
iv BC bay Set 1
v Bus work (Three Bays) Set 1
vi Bus work (Four Bays) Set 1

b 132 kV (Double Main Layout with bypass breaker arrangement)

i Line Bay Set 4


ii Transformer Bay Set 3
iii BC bay Set 1

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-4 Page 119 of 145

iv Bus work (Three Bays) Set 2


v Bus work (Four Bays) Set 1

c
For spare unit of 220/132/33kV auto transformer connection through Set 1
auxiliary buses, Neutral formation and delta formation (for two banks):
Required 245 kV BPI for HV auxiliary bus, 132 kV BPI for 132 kV
Auxilary bus, 72.5 kV BPI for tertiary auxilary bus & delta formation, 36
kV BPI for Neutral formation & Neutral auxiliary bus including Al tube,
bus-bar materials, clamps, spacers, connectors, including equipment
connectors, support structures , Earthing of spare unit as per technical
specification.

d Erection Hardware etc for 72.5kV & 33kV equipments & LT Transformer Set 1
connection

e
Earthing and lightning protection including necesaary
connectors/connections, risers etc. complete in all respect (but
excluding LM structures for Lightning protection)
i Earth Conductor (copper) LS 1
ii Earth Rod (copper clad steel) LS 1
iii Equipment for lightning protection LS 1

B Fire Protection System


a Pumping arrangement for HVW system & hydrant system, complete
with all piping, valves, fittings,etc. inside pump house

i 220/132/33kV (New) Substation Set 1


b Hydrant system, complete U/G piping and accessories etc. outside the
Pump House.
i 220/132/33kV (New) Substation Set 1
c HVW spray system, Hydrant system and complete U/G & O/G piping and
accessories etc. out side the pump house for Transformer :

c.1 Transformer
i 53.33MVA , 220/132/33 KV, 1-phase Autotransformer Set 7
i 50MVA , 132/33 KV, 3-phase Power Transformer Set 1

C Illumination System
a Fire fighting building illumination (100 sqmm) LS 1
b Illumination System for switchyard panel room
i 220KV Set 4
ii 132KV Set 3
iii 33kV Set 1
c Control room cum administrative building illumination (1000 sqmm) LS 1
d Switchyard lighting LS 1
e Street lighting LS 1
h Transit camp (420 sqmm) LS 1
j Security room (10 sqmm) LS 1
k Car parking shed (for 10 cars) LS 2

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-4 Page 120 of 145

D Air conditioning System


a Air conditioning for S/Y panel room
i 220KV Set 4
ii 132KV Set 3
iii 33kV Set 1
E POWER & CONTROL CABLES
a Power Cables(PVC)- (1.1kV grade) LS 1
b Power Cables (XLPE) - (1.1kV grade) LS 1
c Control Cable (PVC)- (1.1kV grade) LS 1
d Cable glands, lugs & straight through joints for Power & Control cables
LS 1

Sub-Total Part-B

PART-C: Civil Works

Excavation in all types of soil and rock (including crushing of large


1.0 sized stone boulders lying on substation plot surface and Cu.M 31,500
underground) including backfilling disposal etc. for all leads and lifts

2.0 Providing and laying of Plain Cement Concrete (PCC) (1:4:8) Cu.M 2000
3.0 Providing and laying of Plain Cement Concrete (PCC) (1:2:4) Cu.M 215
Providing and laying of Reinforced Cement Concrete Design Mix
4.0 M25 including pre cast, shuttering, Grouting of pockets & Cu.M 10210
underpinning but excluding steel reinforcement
Providing and laying Plain Cement Concrete 1:5:10 (1 cement : 5
5.0 Cu.M 3445
sand : 10 Stone aggregate)
6.0 Steel Reinforcement ( Fe 500) MT 880
7.0 Stone filling (40 mm size) over grating of transformer/ reactor Cu.M 165
foundation
Misc. Structural steel including rails, embedments, edge protection
8.0 angles, gratings etc. but excluding the reinforcement steel and steel MT 220
for lattice and pipe structures.
Stone spreading including antiweed treatment in switchyard excluding
9.0 Sq. M. 45000
PCC
All civil works for following buildings as per technical specification
and approved drawings but excluding excavation, PCC, RCC and
10.0
reinforcement steel (Fe-500), which shall be measured and paid
seperately under respective items of BPS :
i) Auxilliary building (33kV indoor switchgear room) Sq. M. 0
ii) Fire fighting pump house building (excluding external finish) Sq. M. 100
iii) Water Tank (excluding external finish) LS 1
iv) Switchyard Panel Room (SPR) Sq. M. 180
v) Township (Quarters)
a B Type Sq. M. 0
b C Type Sq. M. 0
c D Type Sq. M. 0
vi) Transit Camp Sq. M. 420

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-4 Page 121 of 145

Control Room Building (Double Storey with plinth area of 500 sq.m.
vii) Sq. M. 1000
on each floor)
viii) Parking Shed (for 10 Cars) LS 2
11.0 External finish as per specification for following buildings:
i) Auxilliary building (33kV indoor switchgear room) Sq. M. 0
Fire fighting pump house building (excluding external finish)
ii) Sq. M. 100

iii) Water Tank (excluding external finish) LS 1


iv) Switchyard Panel Room (SPR) Sq. M. 180
v) Transit Camp Sq. M. 420
Control Room Building (Double Storey with plinth area of 500 sq.m.
vi) Sq. M. 1000
on each floor)
vii) Parking Shed (for 10 Cars) LS 2
12.0 Concrete road as per drawing except reinforcement & concrete
a) Road 3.75m wide Sq.M. 3825
Providing and laying 60mm thick factory made cement concrete
interlocking paver block of approved size, design & shape, laid in
required colour and pattern over and including 50mm thick
b) compacted bed of coarse sand, filling the joints with fine sand etc. all Sq.M. 310
complete as per the direction of Engineer-in-charge.(3.1m width for
both side-for township and approach road only)

Construction of rail cum road as per drawing including all items such
13.0 as excavation, compaction, rolling, watering, WBM etc but excluding
concrete, reinforcement and structural steel.
a) Section having two rails Sq.M. 240
Chain link fencing as per technical sepcification and approved
14.0 RM 205
drawing excluding concrete
15.0 Switchyard Gate excluding Concrete Nos. 2
Septic tank and soak pit (for 50 users) complete as per technical
specification and approved drawing excluding concrete &
16.0 LS 3
reinforcment which shall be measured and paid seperately under
respective items of BPS .
a) Control room Building (for 20 users) LS 1
b) Quarters & Transit Camp (for 50 users) LS 2
c) Security Room (for 10 users) LS 1
Supplying & laying hume pipe of grade (NP-3) excluding concrete
17.0
and reinforcement
a) 250mm dia RM 300
b) 300mm dia RM 200
c) 450mm dia RM 100
d) 600mm dia RM 100
e) 900mm dia RM 50
18.0 Supplying and erecting dewatering pumps
a) 5 HP Nos. 2
b) 0.5 HP Nos. 7
19.0 Drains Excluding Concrete

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-4 Page 122 of 145

a) Section A-A (300 mm wide X depth up to 600mm) RM 600


b) Section B-B ( 450 mm wideX depth from 600 mm to 900 mm) RM 600
c) Section C-C (600 mm wide X depth from 900 mm to 1200 mm) RM 400

d) Section D-D (750 mm wide X depth from 1200 mm to 1500mm ) RM 400


External water supply from borewell/main water supply point to Fire
20.0
water Tank, control room building, township buildings
a) 80 mm Dia GI pipe RM 100
b) 50 mm Dia GI pipe RM 100
c) 40mm Dia GI pipe RM 100
d) 25mm Dia GI pipe RM 50
All Civil works for Burried cable trenches for Auxilliary power
arrangement. However item excavation, PCC, RCC, Reinforcement
21.0
Steel required to complete the work shall be measured and paid RM 170
seperately under respective items of BPS

External sewerage system including all item such as excavation,


22.0
piping, pipe fittings, manholes, gali trap, gali chamber etc.
a) 250 mm Dia. RM 150
b) 150 mm Dia. RM 150
All civil works for Boundary wall including excavation, concrete,
reinforcement steel ,structural steel, plaster, painting, barbed wire and
23.0 RM 200
concertina coil etc all complete as per technical specification (2.5 m
high brick masonary wall and 0.5 m high angle support on top)

Main boundary wall Gate (Steel ) including all works complete as


24.0 LS 1
per technical specification
25.0 Site levelling
Earth work in excavation and filling in all types of soils including
i soft/disintegrated rock with all leads and lifts within sub station Cu. M 50000
boundary
Earth work in filling with borrowed earth with all leads and lifts
ii Cu. M 10000
including royalty,taxes etc
All civil works for security room as per TS including septic tank and
soak pit. Internal and external finish, sanitary and plumbing works,
26.0 Sq. m. 18
plinth protection etc. to complete the building are included in the
item.

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-4 Page 123 of 145

Construction of retaining wall with random rubble masonary in


cement sand mortar (1:6) including levelling up with cement concrete
(1:6:12), providing weep holes of PVC pipes (150 mm dia) with
necessary filter material at the mouth of weep holes, 50 mm thick
27.0 cement concrete (1:2:4) copping on the top of wall, 100 mm thick Cu. M 1400
PCC (1:4:8) below RR masonary work, excavation of foundation for
all lifts up to 3m above lower level. Item of excavation, PCC (1:2:4
& 1:4:8) shall be measured and paid seperately under respective
items of BPS

28.0 Soil Investigation as per TS LS 1


29.0 Strenthening of existing Approach Road-
a) Construction of 3.75 m wide black top (Bituminous/asphalt) road
with 3.75 m wideblack top pavement over 100 mm thick WBM layer
after filling potholes with WBM and 1.3 m wide earthen shoulders on Sq. M 375
either side of road, WBM for pothole filling shall be measured and
paid separately
b) Supplying and nproviding WBM consisting of 90mm to 45mm stone
with interstices filled by 13.2 mm nominal size stone screening and
Cu. M 50
good earth for filling potholes in existing approach road including
compaction of WBM with road roller
Local sand filling around and under DG set foundation and other
30.0 Cu. M 400
foundations as applicable.
Stone soling below foundations wherever specified in approved
31.0 Cu. M 200
drawings during detailed engineering.

Earthwork in excavation in Hard rocks in open areas/nallas/channels,


to the required slopes, shapes,levels,elevationns and profile including
trimming of bottom and slopes of excavation and disposal and
stacking of rocks for lead upto 1000m beyond levelling boundary
32.0 Cu. M 100
and all lifts, with all labour, material, tools, tackles and equipment,
safeguards and incidentals, royalty , taxes etc. specification and
directions of Engineer-In-Charge. (50% void deduction from stack
measurement)

38.0 River protection works


Supplying and providing stones (used in gabion wall/masonry
a) wall/checkwall/spurs/stone apron)-hard, sound, unweathered and Cu. M 7300
angular rock fragments or boulders
Supplying and Providing Gabion wire mesh of 80x100 mm as per TS
b) Sq. M 2500
complete in all respect for gabion wall and spur.
c) Boulders packed with small stones or spalls into interstices Sq. M 100

SUB-TOTAL-C
Total for 220/132/33kV Trishuli Hub AIS new Substation
(Package-2, Part-II) (II) (Part-A+ Part-B+ Part C)

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-4 Page 124 of 145

Total of Schedule-4

Date: Signature:

Place: Printed
Name:

Designatio
n:

Common
Seal:

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-5a Page 125 of 145

(Schedule of rates and prices)


Bidder's Name & Address:

Package-2 for 220/132/33kV Chilime Hub GIS new substation (Part-I) and 220(Hybrid)/132/33kV Trishuli-3B Hub AIS new substation (Part-II) under 220kV Chilime-Trishuli
Transmission System Project
Training Charges for Training to be imparted abroad
Sl. Country Nos. of Training Total Training Charges
No. where Trainee duration in
Description Item for which training is to be imparted training is to days Currency (As Total
be imparted per ITB 19.1) Training
Charges
1 2 3 4 5 6 7 = 4x5 x 6
I 220/132/33kV CHILIME HUB GIS new Substation
(Package-2, Part-I)
i) Control & Protection and Substation 3 2 days
Automation System
Training to Owners personnel on Design , testing
ii) GIS 3 5 days
A and Maintenance aspect as per Section Project,
iii) Telecommunication Equipment (SDH, MUX 3 2 days
Technical Specification at manufacturer's works
& NMS (Craft Terminal)) and PLCC
iv)Transformer 3 2 days
Total for Training Charges (I)
II 220(Hybrid)/132/33kV Trishuli-3B HUB AIS new
Substation (Package-2, Part-II)
i) Control & Protection and Substation 3 3 days
Automation System
ii) GIS Hybrid Switchgear 3 5 days
Training to Owners personnel on Design , testing
iii) Switchyard Equipment (Circuit Breaker, CT, 3 5 days
A and Maintenance aspect as per Section Project,
CVT & LA)
Technical Specification at manufacturer's works
iv) Telecommunication Equipment (SDH, MUX 3 3 days
& NMS (Craft Terminal)) and PLCC
v)Transformer 3 3 days
Total for Training Charges (II)
III Training on Project Administration for key staffs of i) Project Administration 4 5 days
projects in Accounts and Administration (training to
be imparted at Contractor’s Head Quarter in the
country of the Contractor) as per Section Project,
Technical Specification
Total for Training Charges (III)

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-5a Page 126 of 145

Total for Training Charges, Schedule-5(a)


(IA+IIA+III)
REMARKS:
1. Training at Manufacturer’s works & Contractor's Head Quarter: The Contractor shall include in the training charges payment of per Diem allowance to NEA trainees @ USD
100 per day per trainee for the duration of training abroad towards accommodation, meals and other incidental expenses and to and fro economy class air ticket from Nepal to
place of training. The duration of training shall be excluding travelling period.

Date:

Place:

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-5b Page 127 of 145

(Schedule of rates and prices)


Bidder's Name & Address:
Package-2 for 220/132/33kV Chilime Hub GIS new substation (Part-I) and 220(Hybrid)/132/33kV Trishuli-3B Hub AIS new
substation (Part-II) under 220kV Chilime-Trishuli Transmission System Project

Training Charges for Training to be imparted within Employer's Country


Sl. Training Training Charges for
No. duration Contractors Trainers
Description of the Test Item for which training is to be imparted. in days Currency Total
Training
4 5 Charges
6 = 4x 5
1 2 3
I 220/132/33kV CHILIME HUB GIS new
Substation (Package-2, Part-I)
i) Control & Protection 2
ii) Substation Automation System 2
including integration aspect of existing
SCADA (of Siemens supplied SINAUT
On Job training on operation, maintenance and Spectrum Software) at Load Dispatch
testing & commissioning aspect at one Center
A
Location in Nepal as per section Project, iii) GIS 5
Technical Specification iv) Telecommunication Equipment (SDH 2
,MUX & NMS (Craft Terminal)) and Digital
Protection Coupler
v) TRANSFORMERS 2

Total for Training Charges (I)


II 220(Hybrid)/132/33kV Trishuli-3B HUB AIS
new Substation (Package-2, Part-II)
i) Control & Protection 3

On Job training on operation, maintenance andunder 220kV Chilime-Trishuli Transmission System Project
Package-2
testing & commissioning aspect at one
A
Specification No. Schedule-5b Page 128 of 145

ii) Substation Automation System 3


including integration aspect of existing
SCADA (of Siemens supplied SINAUT
On Job training on operation, maintenance and Spectrum Software) at Load Dispatch
testing & commissioning aspect at one Center
A
Location in Nepal as per section Project, iii) GIS Hybrid Switchgear 5
Technical Specification iv) Telecommunication Equipment (SDH 3
,MUX & NMS (Craft Terminal)) and Digital
Protection Coupler
v) TRANSFORMERS 3

Total for Training Charges (II)


Total for Training Charges, Schedule-5(b)
(IA+IIA)
REMARKS:
2. On Job Training in Nepal: The traveling and living expenses of Owner’s personnel for the training programme conducted in Nepal shall be borne by the Owner.

Date: Signature:

Place: Printed
Name:

Designation:

Common
Seal:

NOTE: To and fro charges and accommodation for the Instructor (Trainer) and Training material for the Trainees shall be included in the
prices quoted by the bidder. However, arrangments for trainees and premises for conducting the training shall be arranged by OWNER.

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-5c Page 129 of 145

(Schedule of rates and prices)


Bidder's Name & Address:

Package-2 for 220/132/33kV Chilime Hub GIS new substation (Part-I) and 220(Hybrid)/132/33kV Trishuli-3B Hub AIS new
substation (Part-II) under 220kV Chilime-Trishuli Transmission System Project
Maintenance Charges for Communication Equipment
Total Maintenance Charges

Sl No Description Unit Qty. Currency (As per


Total Maintenance Charges
ITB 19.1)

I 220/132/33kV CHILIME HUB GIS new


Substation (Package-2, Part-I)

Maintenance Charges for Communication


1 Equipments including SDH & MUX. for One (1) Year 1
year during Warranty period

Maintenance Charges for Communication


2 Equipments including SDH & MUX. for Six (6) Year 6
years after Warranty period

Total Maintenance Charges for Communication


Equipment (I)
II
220(Hybrid)/132/33kV Trishuli-3B HUB AIS
new Substation (Package-2, Part-II)

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-5c Page 130 of 145

Maintenance Charges for Communication


1 Equipments including SDH & MUX. for One (1) Year 1
year during Warranty period

Maintenance Charges for Communication


2 Equipments including SDH & MUX. for Six (6) Year 6
years after Warranty period

Total Maintenance Charges for Communication


Equipment (II)

Total Maintenance Charges for Communication


Equipment Package (Total Schedule 5c) (I + II)

Date: Signature:

Place: Printed Name:

Designation:

Common Seal:

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-6a Page 131 of 145

Package-2 for 220/132/33kV Chilime Hub GIS new substation (Part-I) and 220(Hybrid)/132/33kV Trishuli-3B Hub AIS new substation (Part-II) under 220kV Chilime-Trishuli
Transmission System Project

(Schedule of rates and prices)

Bidder's Name & Address:

Type Test Charges for Type Tests to be conducted abroad

1 2 3 4 5 6 7 8=5x7
Sl. No. Description Testing Unit Qty Currency (As Unit Test Total Test
Location per ITB 19.1) Charges Charges

A 220/132/33kV CHILIME HUB GIS new Substation


(Package-2, Part-I)
I 220/132kV, 53.33MVA Single Phase Power
Transformer
a) Temperate rise test LS 1

b) Measurement of zero sequence reactance LS 1

c) Measurement of Accoustic Noise Level LS 1

d) Measurement of Harmonic Level at No-load current LS 1

e) Measurement of power taken by fans and pumps LS 1

II 132/33kV, 50 MVA Three Phase Power Transformer

a) Temperate rise test LS 1

b) Measurement of zero sequence reactance LS 1

c) Measurement of Accoustic Noise Level LS 1

d) Measurement of Harmonic Level at No-load current LS 1

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-6a Page 132 of 145

e) Measurement of power taken by fans and pumps LS 1

III 33/0.4kV, 630kVA Three Phase LT Transformer


a) Measurement of zero sequence impedance LS 1
b) Short Circuit test LS 1
c) Measurement of acoustic noise level LS 1
d) Measurement of capacitance and tan delta of transformer LS 1
winding
e) Temperature rise test. LS 1
Total for Type Test Charges (Package-2, Part-I)

B 220(Hybrid)/132/33kV Trishuli-3B HUB AIS new


Substation (Package-2, Part-II)
I Type tests on 220kV GIS Hybrid Switchgear as per
Clause 5.0 of Chapter: GIS Hybrid Switchgear of
Technical Specification as follow

a) Tests to verify the insulation level Dielectric tests (Lightning LS 1


impulse, Switching impulse and ac withstand test with PD)
test on each device (CB, Disconnector, etc).

b) Dielectric tests on auxiliary & control circuits. LS 1

c) Tests to prove the radio interference voltage (RIV) level. LS 1

d) Measurement of the resistance of the main circuit. LS 1

e) Tests to prove the Temperature rise of any part of the LS 1


equipment.
f) Tests to prove the ability of the main and earthing circuits to LS 1
carry the rated peak and the rated short time withstand
current and peak withstand current test
g) Tests to verify the making and breaking capacity of main ckt LS 1
including switching devices. Making & breaking tests

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-6a Page 133 of 145

i) Short circuit duty test ( T10,T30,T60,T100a, T100s)


ii) Short line fault test (L60 ,L75,L90)
iii) Out of phase making & breaking test
iv) Capacitive current swtiching test
v) Shunt reactor current switching test
h) Tests to prove the satisfactory operation of the included
switching devices.
h.1) Mechanical tests LS 1
i) Mechanical operation test
ii) Low and high temperature test
iii) Operation under severe ice condition
iv) Static terminal load test
h.2) Environment tests LS 1

i) Cold test
ii) Dry heat test
iii) Damp heat, steady state test
iv) Cyclic humidity test
v) Vibration response and seismic test
vi) Final condition check
i) Tests to prove the strength of enclosures. LS 1

j) Verification of the degree of protection of the enclosure. LS 1

k) Gas tightness tests LS 1

l) Tests to prove the satisfactory operation at limit temperatures. LS 1

m) Tests to prove performance under thermal cycling and gas LS 1


tightness tests on insulators.
n) Tests to assess the effects of arcing due to an internal fault. LS 1

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-6a Page 134 of 145

o) Seismic test LS 1

II Type tests on 132kV XLPE Power Cable:


a) Tests on conductor
i) Annealing test (for copper) LS 1

ii Resistance test LS 1

b) Physical test for Insulation


i Tests for thickness and dimenions of insulations LS 1

ii Tensile strength and elongation at break LS 1

iii Thermal Ageing in air oven LS 1

iv Hot set test LS 1

v Shrinkage test LS 1

c) Resistivity test for semi-conducting layers LS 1

d) Test for concentric metallic screed


i Test for concecntric copper wire LS 1

ii Test for concentric copper tape LS 1

e) Thickness of metallic sheath LS 1

f) Physical tests for other sheath


i Measurement of thickness LS 1

ii Tests on PVC sheath LS 1

iii Tensile strenght and elongation at break LS 1

iv Ageing in air oven LS 1

v Loss of mass in air oven only for PVC sheath LS 1

vi Heat shock test LS 1

vii Hot deformation test LS 1

viii Shrinkage test LS 1

ix Thermal stability LS 1

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-6a Page 135 of 145

g) Flammability test (for PVC outer sheathed cables only) LS 1

h) Water tightness test LS 1

i) 1. Thermal ageing on complete cable sample LS 1

2. Tensile strength and elongation at break for insulation and LS 1


other sheath

Total for Type Test Charges (Package-2, Part-II)

Total of Schedule 7(a) = (A+B)

Date: Signature:
Place: Printed Name:
Designation:
Common Seal:

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-6b Page 136 of 145

Package-2 for 220/132/33kV Chilime Hub GIS new substation (Part-I) and 220(Hybrid)/132/33kV Trishuli-3B Hub AIS new substation (Part-II) under 220kV Chilime-Trishuli
Transmission System Project

(Schedule of rates and prices)

Bidder's Name & Address:

Type Test Charges for Type Tests to be conducted in Employer’s Country

1 2 3 4 5 6 7=4x6
Sl. No. Description Unit Qty Currency (As Unit Test Total Test Charges
per ITB 19.1) Charges

A 220/132/33kV CHILIME HUB GIS new Substation


(Package-2, Part-I)
I 220/132kV, 53.33MVA Single Phase Power
Transformer
a) Temperate rise test LS 1

b) Measurement of zero sequence reactance LS 1

c) Measurement of Accoustic Noise Level LS 1

d) Measurement of Harmonic Level at No-load current LS 1

e) Measurement of power taken by fans and pumps LS 1

II 132/33kV, 50 MVA Three Phase Power Transformer

a) Temperate rise test LS 1

b) Measurement of zero sequence reactance LS 1

c) Measurement of Accoustic Noise Level LS 1

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-6b Page 137 of 145

d) Measurement of Harmonic Level at No-load current LS 1

e) Measurement of power taken by fans and pumps LS 1

III 33/0.4kV, 630kVA Three Phase LT Transformer


a) Measurement of zero sequence impedance LS 1
b) Short Circuit test LS 1
c) Measurement of acoustic noise level LS 1
d) Measurement of capacitance and tan delta of transformer LS 1
winding
e) Temperature rise test. LS 1
Total for Type Test Charges (Package-2, Part-I)

B 220(Hybrid)/132/33kV Trishuli-3B HUB AIS new


Substation (Package-2, Part-II)
I Type tests on 220kV GIS Hybrid Switchgear as per
Clause 5.0 of Chapter: GIS Hybrid Switchgear of
Technical Specification as follow

a) Tests to verify the insulation level Dielectric tests (Lightning LS 1


impulse, Switching impulse and ac withstand test with PD) test
on each device (CB, Disconnector, etc).

b) Dielectric tests on auxiliary & control circuits. LS 1

c) Tests to prove the radio interference voltage (RIV) level. LS 1

d) Measurement of the resistance of the main circuit. LS 1

e) Tests to prove the Temperature rise of any part of the LS 1


equipment.
f) Tests to prove the ability of the main and earthing circuits to LS 1
carry the rated peak and the rated short time withstand current
and peak withstand current test

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-6b Page 138 of 145

g) Tests to verify the making and breaking capacity of main ckt LS 1


including switching devices. Making & breaking tests

i) Short circuit duty test ( T10,T30,T60,T100a, T100s)


ii) Short line fault test (L60 ,L75,L90)
iii) Out of phase making & breaking test
iv) Capacitive current swtiching test
v) Shunt reactor current switching test
h) Tests to prove the satisfactory operation of the included
switching devices.
h.1) Mechanical tests LS 1
i) Mechanical operation test
ii) Low and high temperature test
iii) Operation under severe ice condition
iv) Static terminal load test
h.2) Environment tests LS 1

i) Cold test
ii) Dry heat test
iii) Damp heat, steady state test
iv) Cyclic humidity test
v) Vibration response and seismic test
vi) Final condition check
i) Tests to prove the strength of enclosures. LS 1

j) Verification of the degree of protection of the enclosure. LS 1

k) Gas tightness tests LS 1

l) Tests to prove the satisfactory operation at limit temperatures. LS 1

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-6b Page 139 of 145

m) Tests to prove performance under thermal cycling and gas LS 1


tightness tests on insulators.
n) Tests to assess the effects of arcing due to an internal fault. LS 1

o) Seismic test LS 1

II Type tests on 132kV XLPE Power Cable:


a) Tests on conductor
i) Annealing test (for copper) LS 1

ii Resistance test LS 1

b) Physical test for Insulation


i Tests for thickness and dimenions of insulations LS 1

ii Tensile strength and elongation at break LS 1

iii Thermal Ageing in air oven LS 1

iv Hot set test LS 1

v Shrinkage test LS 1

c) Resistivity test for semi-conducting layers LS 1

d) Test for concentric metallic screed


i Test for concecntric copper wire LS 1

ii Test for concentric copper tape LS 1

e) Thickness of metallic sheath LS 1

f) Physical tests for other sheath


i Measurement of thickness LS 1

ii Tests on PVC sheath LS 1

iii Tensile strenght and elongation at break LS 1

iv Ageing in air oven LS 1

v Loss of mass in air oven only for PVC sheath LS 1

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-6b Page 140 of 145

vi Heat shock test LS 1

vii Hot deformation test LS 1

viii Shrinkage test LS 1

ix Thermal stability LS 1

g) Flammability test (for PVC outer sheathed cables only) LS 1

h) Water tightness test LS 1

i) 1. Thermal ageing on complete cable sample LS 1

2. Tensile strength and elongation at break for insulation LS 1


and other sheath

Total for Type Test Charges (Package-2, Part-II)

Total of Schedule 7(a) = (A+B)

Date: Signature:
Place: Printed Name:
Designation:
Common Seal:

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-7 Page 141 of 145

Package-2 for 220/132/33kV Chilime Hub GIS new substation (Part-I) and 220(Hybrid)/132/33kV Trishuli-3B Hub AIS new substation (Part-II) under
220kV Chilime-Trishuli Transmission System Project

(SUMMARY OF TAXES & DUTIES not included in bid price)

Bidder's Name To:

Bidder's Address:

Sl. No. Item Nos. Total Price in Foreign Total Price in Local
Currency ( )* Currency( )*
1 ……...(indicate names of various Taxes and Duties in Employer's Country)……..
Total Duty, as applicable:
(a) On Schedule 1 @ rate of …………. on items nos. ……………………
(b) On Schedule 2 @ rate of …………. on items nos. ……………………

2 ……...(indicate names of various Taxes and Duties in Employer's Country)……..


Total Duty, as applicable:
(a) On Schedule 1 @ rate of …………. on items nos. ……………………
(b) On Schedule 2 @ rate of …………. on items nos. ……………………

3 ……...(indicate names of various Taxes and Duties in Employer's Country)……..


Total Duty, as applicable:
(a) On Schedule 1 @ rate of …………. on items nos. ……………………
(b) On Schedule 2 @ rate of …………. on items nos. ……………………

……………………………………………………………………………

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-7 Page 142 of 145

……………………………………………………………………….

GRAND TOTAL [1+2+3……..]

* Specify currency in accordance with ITB Clause 19.1 and corresponding BDS clauses, Vol.I of the Bidding Documents.
Note:

Date:
Place:

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-8 Page 143 of 145

Package-2 for 220/132/33kV Chilime Hub GIS new substation (Part-I) and 220(Hybrid)/132/33kV Trishuli-3B Hub AIS new substation (Part-II) under 220kV
Chilime-Trishuli Transmission System Project

(GRAND SUMMARY)

Sl. No. Description Total Price


in Foreign Currency in Local Currency
1 TOTAL SCHEDULE NO. 1
Plant and Equipment including mandatory Spares to be supplied from
abroad.
a) Total for Package-2, Part-I
b) Total for Package-2, Part-II
c) Total for Schedule No. 1 = (1a+1b)
2 TOTAL SCHEDULE NO. 2
Plant and Equipment including mandatory Spares to be supplied from
within Employer’s Country
a) Total for Package-2, Part-I
b) Total for Package-2, Part-II
c) Total for Schedule No. 2 = (2a+2b)
3 TOTAL SCHEDULE NO. 3
Local Transportation, Insurance and other incidental services (including
port clearance etc.) applicable for supply of Plant & Equipment.

a) Total for Package-2, Part-I


b) Total for Package-2, Part-II
c) Total for Schedule No. 3 = (3a+3b)
4 TOTAL SCHEDULE NO. 4
Installation Charges
a) Total for Package-2, Part-I
b) Total for Package-2, Part-II
c) Total for Schedule No. 4 = (4a+4b)
5a TOTAL SCHEDULE NO. 5a
Training Charges for Training to be imparted abroad
a) Total for Package-2, Part-I
b) Total for Package-2, Part-II
c) Total for Schedule No. 5a = [5a(a)+5a(b)]
5b TOTAL SCHEDULE NO. 5b
Training Charges for Training to be imparted within Employer’s Country

a) Total for Package-2, Part-I


b) Total for Package-2, Part-II
c) Total for Schedule No. 5b = [5b(a)+5b(b)]
5c TOTAL SCHEDULE NO. 5c
Maintenance Charges for Communication Equipment
a) Total for Package-2, Part-I
b) Total for Package-2, Part-II
c) Total for Schedule No. 5c = [5c(a)+5c(b)]
6a TOTAL SCHEDULE 6a
Type Test Charges for Type Tests to be conducted abroad
a) Total for Package-2, Part-I
b) Total for Package-2, Part-II
c) Total for Schedule No. 6a = [6a(a)+6a(b)]
6b TOTAL SCHEDULE 6b
Type Test Charges for Type Tests to be conducted in Employer's
Country
a) Total for Package-2, Part-I
b) Total for Package-2, Part-II
c) Total for Schedule No. 6b = [6b(a)+6b(b)]
7 TOTAL SCHEDULE NO. 7
Taxes and Duties
a) Total for Package-2, Part-I
b) Total for Package-2, Part-II
c) Total for Schedule No. 7 = (7a+7b)

GRAND TOTAL FOR PACKAGE-2, PART-I [Sch.1+Sch.


2+Sch. 3+Sch. 4+Sch. 5a+Sch. 5b+Sch. 5c+Sch.
6a+Sch. 6b + Sch. 7]
GRAND TOTAL FOR PACKAGE-2, PART-II [Sch.1+Sch.
2+Sch. 3+Sch. 4+Sch. 5a+Sch. 5b+Sch. 5c+Sch.
6a+Sch. 6b + Sch. 7]

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-8 Page 144 of 145

GRAND TOTAL FOR PACKAGE-2 (PART-I + PART-II)


[Sch.1+Sch. 2+Sch. 3+Sch. 4+Sch. 5a+Sch. 5b+Sch.
5c+Sch. 6a+Sch. 6b + Sch. 7]

Date: Signature: Signature:

Place: Printed Name: Printed Name:

Designation: Designation:

Common Seal: Common Seal:

Package-2 under 220kV Chilime-Trishuli Transmission System Project


Specification No. Schedule-9 Page 145 of 145

Package-2 for 220/132/33kV Chilime Hub GIS new substation (Part-I) and 220(Hybrid)/132/33kV Trishuli-3B Hub AIS new substation (Part-II) under 220kV Chilime-Trishuli
Transmission System Project

(Schedule of rates and prices)

Bidder's Name: To:

Bidder's Address:

Details of Recommended/Optional Spares parts and Recommended Test Equipment (in line with Technical Specifications) is furnished below:

Item No. Name & Description of Name of Original Part No. Number of Units in Total No. of Sets to Unit Price Total Price Remarks
Parts Manufacturer each set be provided

Date: Signature:
Place: Printed Name:
Designation:
Common Seal:

Package-2 under 220kV Chilime-Trishuli Transmission System Project