Site Survey

Site Cleaning
Bore well Digging
Temporary shed construction for storage
Preparation of Site and Site Marking
Excavation and Leveling
Preparation of Foundation Base
Construction of foundation
Earth Filling
Plinth Beam
earth filling till plinth Beam and soil compacting and leveling
Ground slab
Ground Floor column
Staircase
Beam and Slab of first floor
Deshuttering of Beam
infill wall masnory
Door Window Lintel-sill Construction
Terrace Beam and Slab
infill wall masnory
door Window Lintel-sill Construction
Stair Cabin and parapet wall
Electric consill work
plumbing consill work
plaster outside
plaster inside
Wall Tiles
floor finish
Skirting
electric work
door windows shutters and Sanitary fitting
paint
7-10 days
7-10 days
3 days
2-7 days
7 days

7 days with curring


days with curring

7 days of curring After 10 days slab Deshuttering


After 17 days Beam B
10 days slab Deshuttering
After 17 days Beam Bottom Deshuttering