CUT OFF PROGRESS

Periode : 26-Apr-20 s.d 2-May-20


Progress (Physical)
CUMMULATIVE LAST INCREMENTAL THIS
CUMMULATIVE THIS PERIOD
PERIOD PERIOD
No CATEGORY WF DEVIATION
PLAN ACTUAL PLAN ACTUAL PLAN ACTUAL

1 PRELIMINARIES 52.95% 29.56% 28.85% 23.39% 0.79% 52.95% 29.65% -23.30%


2 PILING WORK 47.05% 41.16% 34.34% 5.89% 3.52% 47.05% 37.85% -9.20%
TOTAL 100.00% 70.71% 63.19% 29.29% 4.31% 100.00% 67.50% -32.50%

Progress (Individual)
CUMMULATIVE LAST INCREMENTAL THIS
CUMMULATIVE THIS PERIOD
PERIOD PERIOD
No CATEGORY WF DEVIATION
PLAN ACTUAL PLAN ACTUAL PLAN ACTUAL

1 PRELIMINARIES 52.95% 55.82% 54.49% 44.18% 1.50% 100.00% 55.99% -44.01%


3 PILING WORK 47.05% 87.47% 72.98% 12.53% 7.47% 100.00% 80.45% -19.55%