CRITICAL PATH METHOD - LOGIC NETWORK

Activity A B C D E F G H I J K L M N O P Q
Description
Duration 1 2 2 3 3 1 4 3 3 4 4 1 2 4 2 1 1
IPA K,
- A A B,C D D D F,G E E I,J J M N O,L,H P
L
6 E 9 9 I

6 3 9 9 3
1
1013
0 A 1
1 B 3 3 D 6 6 F 7 9 J

0 1 1 2 3 3 6
1 3 6 1 7 9 4
3
1
21 22 17
16

1 C 3 6 G 1 10 H
0 1
1 2 3 10
6 4 1 1 3
0

18 22 25
22
Project Management OUM

Tabulate :

Activity ES (Early EF (Early LS (Late LF (Late TF (Total


Start) Finish) Start) Finish) Float)
A 0 1 0 1 -
B 1 3 1 3 -
C 1 3 1 3 -
D 3 6 3 6 -
E 6 9 6 9 -
F 6 7 21 22 15
G 6 10 18 22 12
H 10 13 22 25 12
I 9 12 10 13 1
J 9 13 9 13 -
K 13 17 13 17 -
L 13 14 24 25 11
M 17 19 17 19 -
N 19 23 19 23 -
O 23 25 23 25 -
P 25 26 25 26 -
Q 26 27 26 27 -
Project Management OUM

Critical Path:

1) A + B +D + F + H + P + Q = 12
2) A + B + D + G + H + P + Q = 15
3) A + C + D + F + H + P + Q = 12
4) A + C + D + G + H + P + Q = 15
5) A + B + D + E + I + K + M + N + O + P + Q = 26
6) A + B + D + E + J + K + M + N + O + P + Q = 27 : (Most of critical path) – Refer to the arrow
7) A + B + D + E + J + L + M + N + O + P + Q = 24
8) A + B + D + E + J + L + P + Q = 16
9) A + C + D + E + I + K + M + N + O + P + Q = 26
10) A + C + D + E + J + K + M + N + O + P + Q =27
11) A + C + D + E + J + L + P + Q = 16
12) A + C + D + E + J + L + M + N + O + P + Q = 24

Conclusion: