SN.NO PROJECT TASK ES.START DATE ES.

COMPLETION DATE
1 Project Feasibility Study 28-Jul-19 30-Jul-19
2 Cost Benefit Analysis 28-Jul-19 30-Jul-19

3 Project Definition 01-Aug-19 02-Aug-19


4 Block Diagram 03-Aug-19 06-Aug-19
5 Interface Design 04-Aug-19 06-Aug-19
6 Assembly 15-Sep-19 30-Sep-19

7 Proposal 10-Aug-19 14-Aug-19


8 HOD letter 16-Aug-19 17-Aug-19

9 Presentation 05-Sep-19 06-Sep-19


10 Demonstration 01-Nov-19 31-Dec-19

Colour Status
Planned Project Work Day
Task Completed ahead of schedule
Task Deficient
ACTUAL START DATE ACTUAL END DATE TASK OWNER Complete/Deficient
01-Aug-19 04-Aug-19 Kiran.V 04-Aug-19
01-Aug-19 04-Aug-19 Kiran.V 04-Aug-19

02-Aug-19 02-Aug-19 Kiruthika.R 02-Aug-19


03-Aug-19 07-Aug-19 Keren Naomi Devnesh 07-Aug-19
05-Aug-19 06-Aug-19 Kiruthiga.S 06-Aug-19
NIL NIL Kiran. V

11-Aug-19 14-Aug-19 Keren Naomi Devnesh 15-Aug-19


17-Aug-19 18-Aug-19 Kiruthiga.S 19-Aug-19

NIL NIL
NIL NIL