You are on page 1of 8

PRV % .

To flare header

FIGURE 1. Even
a relatively sim
ple f ractionation
system, such as
the one shown
here, can have
the consideration of the power failure,
many potential the contingency case should be called
overpressure a power failure. Similarly, if the reflux
scenarios, in- failure is caused by condenser failure,
eluding blocked
the contingency case should be called
outlets; full and
partial power fail a condenser failure.
ures; external As a general rule of thumb, if the
fire; control- potential outcomes of a given failure
valve and con are not likely to occur simultaneously,
trol-loop failures;
then the PRV should be sized sepa
loss of Instru-
- ment air, cooling rately for these two individual cases
water or steam; Feed — not oversized by adding together
thermal expan the two relief capacities required for
Bottom product
sion and many
different potential outcomes of a given
more. The sce
PRV Pressure-relief valve failure mode. By way of example: if
nario with the CW
TRC Temperature-record control
largest required the pressure-relief capacity calculated
LIC Level-indication control
relief load should PRC Pressure-record control for a single reflux failure case is
be used to size CW Cooling water 80,000 lb/h for a given unit, and the
the pressure- re FRC Flow-record control
required relief load for a power failure
lief valve
at the same unit is 150,000 lb/h, then
sure scenario during PRV design, then be unrelated to other causes "if no to properly size the PRV, one should
the existing PRV may be undersized. process or mechanical or electrical assume that the power failure case in
The list of overpressure causes on p. linkages exist among them," or "if the cludes the effect of reflux failure. In
66 should be used to guide the PRV length of time that elapses between other words, the PRV needed to re
audit. However, this list should not be possible successive occurrences of spond to a potential reflux failure
considered all-inclusive. Plant man these causes is sufficient to make should be sized for the larger of the
agers and design engineers should use their classification unrelated." This two values (in this case 150,000 lb/h;
their own engineering judgement to means that one does not need to as not a cumulative 230,000 lb/h).
carefully assess site-specific hazards sume that every contingency case Automatic process control Gener
or uncommon factors that might also being analyzed during system design ally speaking, reliance on so-called fail
constitute an overpressure source. would occur simultaneously. safe instruments or control loops is not a
Ask a lot of questions during such a However, some contingency cases suitable substitute for installing a prop
system evaluation, particularly when are obviously related by cause and ef erly designed pressure-relief system.
you are aware of particular overpres fect. For instance, a "liquid-blocked Ideally, with the use of failsafe instru
sure scenarios that you think should outlet" can be the consequence of an ments or control loops, any abnormal
be included in the PRV audit, but are "inadvertent valve operation" that conditions will prompt an automatic ad
not. Never take for granted "common- was probably caused by "human justment of flowrate, pressure, tempera
sense things." For instance, question error." When one is performing the de ture or other factors. However, given the
why a large PRV is specified for a tailed overpressure analysis, such in potential unreliability or unpredictabil
small vessel, and vice versa. terrelated overpressure scenarios can ity of electronic signals — especially
Before getting into the detailed be summarized as a single potential during upset conditions — such protec
analysis of common overpressure sce overpressure scenario. Other oc- tion cannot be relied on in lieu of pres
narios, we must clarify three related curences, such as a "general power sure-relief devices. Similarly, auto
concepts — double jeopardy, auto failure," will cause reflux interrup matic-startup, equipment should not
matic process control, and administra tions if the reflux is driven by an elec replace the use'of pressure-relief valves
tive procedures. tric pump, and may cause the cooling as protection against overpressure.
Double jeopardy. The concept of duty of an air condenser to be lost, too. One exception is the use of a High
"no double jeopardy in overpressure The bottom line is that when per Integrity Protective System (HIPS).
assessment" is very important. The forming an overpressure analysis, en Using triple redundant signals, the
American Petroleum Inst.'s (API) Rec gineers must consider these cumula HIPS avoids the aforementioned defi
ommended Practice RP 521 Section tive effects, to deal with a ciencies of conventional failsafe sys
2.2 12] states that the causes of over representative cause of potential over tems for electronic process control.
pressure are typically unrelated. Ac pressure. For instance, the possibility Consider a control loop designed to
cording to API, "The simultaneous oc of reflux failure should be analyzed in maintain the liquid level in a tank or
currence of two or more conditions terms of a number of potential causes, reactor when feed increases or de
that could result in overpressure will including power failure, reflux pump creases. The level signal may fail or de
not be postulated, if the causes are un failure, control valve failure, or a con viate for some reason. To make sure
related." Even external fire, one of the denser blanketed by non-condensible. the signal would not be lost, a HIPS
overpressure causes, is considered to If the reflux failure is included in uses three independent signals in-

CHEMICAL ENGINEERING WWW.CHE.COM JUNE 2001 67


Cover Story ;;':%

stalled in the same vessel. In addition, related sources of energy. The most should be added to the wetted sur
it uses a two-out-of-three logic system common example is the use of a steam face area of the main vessel when
(such a system relies on two out of turbine as standby for an electric calculating the potential vapor gen
three voting systems to determine if motor that is driving a pump to trans erated from an external fire. Be
the signal received is reliable), and ei port fluids. cause of the difficulty of calculating
ther an emergency-power-supply Since operator intervention (such as the wetted surface areas of con
(EPS) or an uninterrupted-power-sup reliance on manual cut-in of auxil nected piping and accessories, engi
ply (UPS) system. Using an UPS, when iaries by an operator) is time depen neers should add 15% to the overall
the normal power supply is inter dent, the potential impact of the time wetted surface area of the vessel [61
rupted, a standby power supply would lag required for the standby equip • Even if a vapor-depressuring sys
automatically start, in a fraction of a ment to get into normal position, and tem is installed along with the PRV,
second, to support critical equipment the potential impact of human error, the required fire-relief load through
or units. should be analyzed. the PRV should not be reduced. The
HIPS is not a pressure-relief sys vapor-depressuring system is basi
tem, but rather an automatic control Common overpressure sources cally used to rapidly reduce the in
system that can be used to guard Discussed below are each of the over- ternal pressure to a level where
against overpressure. It is now widely pressue scenarios listed on p. 66. stress rupture would not occur
accepted that the use of a HIPS, with 1. External fire. Fire is a common • Tanks and vessels with design pres
either EPS or UPS, can eliminate cause of overpressure in pipes and sure less than 15 psig need to follow
some (not all) potential overpressure vessels. According to API RP 520 [3] API Standard 2000 [8]
scenarios, and hence greatly reduce and 521 [2], operators should assume 2. Blocked outlets. The closure of a
the use of unnecessarily large relief that the effective fire-exposed area in block valve on the outlet of a pressure
valves and flares, which then reduces cludes an area of 2,500 to 5,000 ft2 vessel can cause the vessel's internal
both capital and operating costs . (this assumes a circle with a diameter pressure to exceed its MAWP, if the
However, operators should consult an of 58-80 ft) [6], with an effective fire source pressure exceeds the vessel de
expert before relying on a HIPS, and if height no more than 25 ft above the sign pressure. However, if the MAWP
the facility chooses this route, it must grade. In contrast, National Fire Pro of a vessel is higher than the source
implement a strict maintenance tection Assn. (NFPA) [4,6] guidelines supply pressure, the vessel has no
schedule for the HIPS, along with rig recommend that operators should as blocked-outlet case.
orous training for operators. sume a fire-exposure area with a fire A blocked outlet can be caused by
Administrative procedures. height of 35 ft above grade (details on control valve failure, inadvertent
Some refineries believe that reliance how to determine the area of a poten valve operation, instrument-air or
on strict administrative procedures is tial fire zone can be found in a previ power failure, and other factors. In
enough to prevent some overpressure ous article by this author, [6]). general, a pressure-relief valve must
scenarios, and, thus, they cite such Analyzing for an external fire case have sufficient capacity to pass a fluid
procedures to justify reducing the assumes that the vessel exposed to the flowrate that is equivalent to the dif
number of PRVs in the facility. While fire is blocked in. Potential vapors re ference between those of the incoming
strict administrative procedures are sulting from the fire must be relieved fluids and the outgoing fluids.
commendable, one should assume using a PRV on the vessel, or via a a. Blocked liquid outlet. When the
that the possibility of human error vent path that remains in a locked- liquid outlet is blocked, the liquid
can never be completely eliminated; open position between the vessel in level in the vessel may rise. If the
thus they should not be used in place question and an adjoining vessel 16}. surge time for liquid overflow from the
of a pressure-relief system. These issues need be considered: vessel is less than 15-20 min, then a
API RP 520 and-521 do allow engi- • Pressure-relief valves alone cannot blocked liquid-outlet is a valid poten
■ neers to take credit for so-called "car protect vessels filled with gas or tial overpressure scenario. When the
seals open (CSO)" or "car seals locked high-boiling-point liquids, so engi required surge I time is longer than
(CSL)" valves., With the installation of neers must carefully evaluate other 15-20 minutes, then operators pre
CSO block valves, operators do not protective measures [SI. Tradition sumably have sufficient time to take
have to drain the equipment after sys ally, design engineers use two ap action to avoid an overflow, so a
tem shutdown, since the valve main proaches to size PRVs for gas-filled blocked liquid outlet is not considered
tains an open position all the time. vessels. One is to use unwetted-sur- to be a potential overpressure source.
However, API RP 521 does not allow face equations, as shown in API RP For any pressure-relief valve in
engineers to take credit for standby 520. Another is to assume the pres stalled on the liquid-feed line, the re
pumps, because they cannot be con ence of some liquids in the vessel, so quired relieving capacity (in units of
sidered to be totally reliable. that wetted-surface equations can volume per time) should be the accu
Full or partial credit may be taken be used to size the PRV (for a de mulated liquid capacity of the vessel.
for normally operating, parallel, in tailed discussion of this, see [5]) When the feed input is a two-phase
strument air compressors and electric • The wetted surface areas of con fluid (i.e., the feed input for a separa
generators, whose drivers use two un nected piping and accessories tor, or flash or-, surge drum), the re-

68 CHEMICAL ENGINEERING WWW.CHE.COM JUNE 2001


A tank-farm fire and explosion at
Thai Oil resulted in 8 fatalities and
13 injuries
closed; or air-fail-last-position).
If a plant is well-designed, an in
strument air failure holds relatively
little risk of generating overpressure.
For instance, with proper care, it is
possible to design most control valves
When polymer deposits Inside this col so they will be locked in a safe position
umn caught fire accidentally, the heat in the event of instrument-air failure.
of the fire was sufficient to melt the col However, instrument-air failure
umn and cause it to collapse
quired pressure-relief capacity for the can cause many other problems re
. blocked-liquid-outlet case is not for lated to such things as the alarm or
just the liquid. In this case, a two- ever, if a HIPS is installed for the au shutdown system. The air-fail position
phase scenario should be considered, tomatic startup, and the time differ should not be designed as overpres
because the liquid level rising to a cer ence between the power outage and sure-relief protection. The reason is
tain height may make liquid and vapor the standby system getting up and obvious — other outcomes might re
separation impossible. Too often, engi running is insignificant for process sult from the same instrument-air
neers fail to recognize the potential for conditions deviating into the upset re failure. For instance, other failures in
two-phase separation, and hence, they gion, it might be possible to take the an instrument system could cause a
inadequately size the PRV in a credit for such an installation. control valve to move to a position op
blocked-liquid-outlet case to accommo b. Partial power failure. Partial posite from its originally designed air-
date just the liquid capacity [7]. power failure is limited to one process fail position, though not very often.
6. Blocked vapor outlet. When the unit, or may refer to the failure of ei d. Loss of cooling water. During the
vapor outlet is blocked, the vapor in ther low-voltage or' high-voltage case analysis for cooling-water fail
the vessel needs to be relieved. If power. Credit can be taken for contin ures, engineers often make mistakes
there is another available vent outlet uous parallel power-supply services if in adequately defining the required
on the vessel that would not be they have unrelated energy sources. overpressure-relief capacity. Using a
blocked by the same cause, the credit In the partial-power-failure case, heat balance approach to calculate the
for this relief capacity can be taken. one can assume that the general util relief capacity for a fractionation sys
3. Utility failures. Unlike other ity supply would not to be affected. tem is a must; nevertheless, without a
scenarios that can only affect one ves The feed, heating or cooling from detailed analysis for both normal op
sel at one time, utility failures, such other units would also not be affected. erating and relieving conditions, it is
as loss of power or cooling water or c. Loss of instrument air. As men easy to end up an oversized PRV.
those shown in the list on p. 66, can af tioned before, instrument-air failure A common mistake is the inappropri
fect all the equipment using power or may be caused by power failure, con ate use of the extra heat accumulation
cooling water at same time. To be safe, trol valve failure or other reasons. Me in the system (which can vaporize liq
the flare header should be designed chanical equipment failure can also uid in the system) when calculating the
and sized based on the maximum re result in the loss of instrument air. required relief load. La some cases, if
lief load that could result by a poten Engineers should be cautious with the cooling is not normally used for con
tial utility failure. the emergency electric power supply densing vapor, the extra heat buildup
a. General power failure (both an in (EPS) used to ensure uninterrupted in the system may not be enough to
terruption of power, and total power instrument air supply. As discussed, cause a pressure relief.
failure in a plant). The immediate only reliable EPS systems can take When the cooling is used to con
consequences are that: credit for overpressure protection. dense vapors, the required relief ca
• Electrical motor-driven pumps and Instrument air supplies that have a pacity must-be equivalent to the total
compressors — and hence, feed large air reserve and high air pressure vapor load being condensed. The im
input, product output and reflux — may, after a power failure, be able to portant point i§ that the calculation be
will stop maintain an adequate air supply for a based on the relieving conditions, not
• Motor-driven fans for air coolers, short period of time. The time frame the normal operating conditions.
cooling water towers and combus should be carefully evaluated. Nor Unlike normal operating condi
tion air will stop mally the air receiver should be able to tions, at the overpressure-relief condi
• Motor-operated valves will fail maintain 10-15 min of air supply after tions, more vapor may become con
• Instrument air will be interrupted the air compressor has stopped. To be densed because of higher pressure. A
Due to the risk of power failure, API safe, engineers are advised not to take rigorous simulation is typically re
RP 521 does not permit credit to be the credit unless the air supply is suffi quired to help engineers quantify the
taken for pumps with standby and au cient to last long enough for some cor required vapor-relief capacity. Simply
tomatic startup, even when the pump rective action to be taken. Generally, in using the normal condensed-vapor
has a separate power supply. In the strument air failure will cause all quantity may result in an oversized
event of a utility failure, such a setup control valves to assume their failsafe pressure-relief valve.
cannot be considered reliable. How- positions (either air-fail-open; air-fail- One more point needs be empha-

CHEMICAL ENGINEERING WWW.CHE.COM JUNE 2001 69


Cbver Story

sized here. API RP 521 suggests that vapor flow in a column or vessel, so
the required relief capacity is the total the loss of quench means a loss of cool
vapor capacity (typically measured as ing duty. A heat balance at the reliev
weight/time, such as lb/h) to the con ing condition must be performed, to
denser at relieving conditions. Actu determine the required relief capacity.
ally, it should be the difference be b. Air-cooled exchanger failure \14\.
tween vapor entering and leaving the When air-cooled exchangers fail, nat
condenser at relieving conditions. If ural convection continues. Therefore,
there is an existing vapor outlet in the a credit for 20 to 30% of normal duty is
system, and that outlet would not be often taken, to reduce the required re
The potential impact of human error on
blocked during a cooling-water fail lief capacity. However, louver closure plant safety should never be underesti
ure, then the available normal vapor is considered to be total loss of the mated. Wherever possible, the process
flowrate through the vapor outlet cooling duty. should be designed to be free from op
c. Loss of cold feed. Loss of cold feed portunities for human error
should be taken as a credit to reduce
the required relief load. is similar to the loss of quench. This The required relieving capacity for
e. Loss of steam. In general, steam item is often overlooked when no heat the failure of total condensing duty
has the following functions at a plant: balance is performed. can be calculated by performing a heat
• It is a driving force for pumps, tur d. Loss of reflux (top and intermedi balance on the system, based on the
bines, compressors, air blowers, and ate). Reflux failure is a common cause loss of the condensing duty. The con
so on. When steam supply is inter of overpressure in fractionation sequences of losing partial condensing
rupted, inlet flow and fluid dis columns. Power failure, pump shut duty should also consider the possibil
charge will be interrupted down, pump mechanical problems and ity of non-condensible blanketing in
• When used as a heating source for control valve failures are among the the condenser. When this occurs, all
reboilers, exchangers and direct in causes of reflux loss, which can result the condensing duties will be lost.
jection, loss of steam will interrupt in receiver and condenser flooding. The consequence of partial condens
heating functions The loss of reflux will cause the tem ing failure can be more severe than
• When used for stripping in fraction- perature in the column to rise, leading that of total condensing failure. The
ation columns, the loss of steam can to a vapor buildup and an increase in relief-capacity calculations might
have a similar impact as the loss of pressure drop in the column and over have to reconsider loss of upstream
cooling duty. Neglecting this might head receiver. Such failure often leads cooling duty if they were related.
lead to an undersized PRV to a loss of total condensing duty. 5. Thermal expansion (some'
f. Loss offuel gas or fuel oil. Except for Nevertheless, exceptions do exist. times call hydraulic expansion).
fuel gas or fuel oil that is used for dri One example is when the receiver has Pressure-relief valves for the case of
ving pumps or turbines that provide a vapor outlet that would not be thermal (or hydraulic) expansion, are
cooling duty, the loss of fuel gas or fuel blocked by the same reason that relatively easy to analyze and size. It
oil would not generally cause over caused the reflux failure. In this case, is rare that a vapor-filled pipeline or
pressure in a system. If fuel gas or fuel the condenser duty may be reduced to vessel would be overpressured by ex
oil is used for generating power, loss of a certain extent, or not even affected, ternal heat sources, other than fire.
such fuels should be evaluated as a depending on the system configura Therefore, no vapor thermal expan
power failure when sizing the PRVs. tion. Furthermore, if the receiver has sion is discussed here.
For fired heaters, the loss of fuel gas enough surge time, say, more than 15 When liquid is blocked in a vessel or
or fuel oil supply does not mean the min from its normal liquid level as a pipeline, external heat input can
clear cutoff of heat input to the sys safe assumption, one could assume cause liquid temperature, and hence
tem. The flow of the residual heat in that the condenser would not flood. volume, to rise. Common causes are:
the fired heater can significantly con In general, loss of cooling duty, by • The pipeline "is filled with liquid
tribute to a heat imbalance and over any of these mechanisms, can cause that is blocked in and heated by
pressure in the system. This state of heat buildup, which can result in steam or electrical heat tracing
affairs is especially significant when vapor buildup and system overpres • A heat-exchanger cold side is filled
the heat duty is large. Generally, sure. The loss of non-condensing cool while the hot side is still flowing
25-40% of normal heating duty shall ing will not generally lead to an over- • A pipeline or vessel is filled with liq
be used as the residual heat input to pressre situation. However, loss of uid at ambient temperature, and is
the fired heater, once power fails and cooling in a partial or total condenser heated by direct solar radiation
fuel gas or fuel oil input has stopped. would generally lead to a system un Usually, a nominal thermal-relief
4. Loss of cooling duty. There are balance, and potential overpressure. valve is adequate for most cases, ex
several different types of cooling du When condensing duty is stopped, if cept for large vessels and long piping.
ties (including the above-mentioned the condensed liquid inventory has Backpressure should be assessed
cooling-water failure), as shown here: more than 15 min to deplete, one can when the thermal-relief valve is dis
a. Loss of quench stream. Normally, assume that the operator has ade charging to another pressured
a quench stream is used to cool a quate time to take corrective action. pipeline or process vessel [11]. When

70 CHEMICAL ENGINEERING WWW.CHE.COM JUNE 2001


In general, the loss of coupled with proper operator training.
cooling duty can cause During the design phase, the use of
heat to accumulate In a double block valves, the avoidance of
system, which can re
water-collecting pockets, and the ap
sult in vapor buildup
and system overpres propriate use of steam condensate
sure. This vapor accu traps and bleeds on water connections
mulation needs to be should be all considered. If the possi
removed before system
bility of overpressure still exists, a
pressure reaches its
MAWP rupture disk may be the answer.
10. Accumulation of non-con
densibles. During normal operating
conditions, non-condensibles do not
the backpressure exceeds 10% of the able to discharge the extra vapor, accumulate in the system. They
valve set pressure, or is variable, a eventually, the extra vapor will cause should be discharged along with
balanced bellows may be required. system overpressure. The required re process streams or through a vent.
The case of blocked-in liquid with lieving capacity must be equal to or Non-condensibles will accumulate
thermal vaporization has not been greater than the amount of the vapor under the following conditions:
widely discussed. When the liquid accumulation expected under the re • The normal non-condensible vent is
being blocked in has a vapor pressure lieving conditions. blocked, or
higher than the PRV set pressure, 8. Loss of absorbent flow. In gen • The piping configuration or equip
thermal vaporization is a potential eral, loss of absorbent will not result ment has a pocket in which non-con
cause of overpressure. The PRV in an overpressure situation. How densibles accumulate
should be sized so that it can relieve ever, when gas removal by an ab The accumulation of non-condensibles
the vapor-generation rate, and should sorbent is more than 25% of the total can blanket a condenser and result in
be installed on the top of the equip inlet vapor flow, an interruption of ab the loss of cooling duty. Thus, the
ment, so as not to block the vapor dis sorbent flow could cause pressure to analysis should be no different from
charge. Liquid displacement should rise in the absorber. that done for loss of condensing duty.
also be avoided. In this case, the pressure-relief valve 11. Valve malfunction. Only one
6. Abnormal heat input. This case should be sized based on the net accu valve malfunction needs to be consid
is not commonly discussed, but it mulation of the vapor at the relieving ered at a time, if other valve malfunc
should be analyzed if the following in conditions. If the downstream equip tions are unrelated.
cidents might happen: ment would not be blocked at the same a. Check-valve malfunction (back
• The supply of heating medium, such time the absorbent flow has stopped, flow). This is a rare case, but should
as fuel oil or fuel gas to a fired then the design capacity of that equip be considered when a high pressure
heater, can be switched from ment can be used as a credit for reduc differential is present between the
medium heating value to higher ing the required relieving capacity. inlet and outlet of a check valve, a
heating value Some absorption systems are pump, or other piece of equipment. In
• Heat transfer occurs in a new and equipped with an automatic depres- general, though multiple check valves
clean heat exchanger after a revamp suring system (i.e., the use of an auto are installed for this application,
• The control valve for the fuel supply matic vent that is electroncially trig backflow does occur at huge pressure
fails fully open gered to open and relieve pressure differentials. When check valves mal
• The supply pressure of the heating buildup caused by a rapid temperature function, backflow can be from 5 to 25
steam is changed from its normal increase). However, credit for this can % of the normal operating flowrate.
range to its nnnrimiim pressure not be used to reduce the required re The required relief capacity is defined
In general, when considering this case lief capacity needed for this case, be based on eachcase.
for sizing a PRV, the maximum heat cause such an auto vent cannot be 6. Inadvertent valve operation
duty assumed for the abnormal case assumed to be completely reliable, un (open I close and bypass). This means
should be ho more than 125% of the less a HIPS is used to control the vent. that a valve was wrongly operated to a
normal heat duty. 9. Entrance of highly volatile position that is opposite its intended
7. Abnormal vapor input. Abnor material An example of this would normal operating position. This is a
mal vapor input to the process can be water or light hydrocarbons enter very common overpressure scenario,
occur when the upstream control ing into hot oil during a process upset and is the result .of human error.
valve fails fully open. Upstream re — a situation in which the instanta Bypass valves can also be either
lieving or inadvertent valve opening neous phase expansion can be enor closed or opened inadvertently, due to
can also cause abnormal vapor input mous. Pressure-relief devices may not human error. If this malfunction can
to a reactor, vessel or pipeline. open fast enough to relieve the rapidly cause downstream equipment over
In some situations, abnormal vapor generated vapors. Instead, to mini pressure, it is a valid potential over
input may not cause system overpres mize such risks, the facility should pressure scenario to consider.
sure. However, if the system is not rely on a properly designed process, Very often, a fully open bypass

CHEMICAL ENGINEERING WWW.CHE.COM JUNE 2001 71


valve can pass a greater fluid volume rule, the required relief capacity must • When high-pressure liquid could
than the main control valve. Analysis be greater than the vapor generated flash into the low-pressure system,
shows that a fully open bypass block because of heat buildup in the system. the DIERS (Design Inst. for Emer
valve, especially a control valve by 13. Exchanger tube rupture. API gency Relief Systems) methodology
pass, can provide a larger relief load states that complete tube rupture, in should be considered [12]
compared to failure of the control which a large quantity of high-pres • The impact of high-pressure fluids
valve itself. During the design stage, sure fluid will flow to the lower-pres flowing into a low-pressure system
the bypass valve should be carefully sure side of the exchanger, is a remote should not be ignored, especially the
sized to avoid an oversized relief but possible contingency. Because the impact on the. manifold on the low-
valve. test pressure normally is about 150% pressure side when the pressure dif
b. Control valve fails fully open or of the design pressure, a two-thirds ferential is too large
closed. This malfunction, caused by rule is established from it. The rule is • If a steam reboiler tube ruptures,
mechanical or electronic-signal fail this: pressure relief for tube rupture is consider the impact on the column
ure, and it often results in heat or not required where the low-pressure • For steam-generation systems that
mass accumulation in the system. exchanger side (including upstream use process fluids as a heating
However, this case is often confused and downstream systems) is designed medium, a tube rupture can have
with the air-failure position of the con at or above the two-thirds criteria. environmental consequences
trol valve. Mostly, air-fail positions for (Because ASMS changed the hydro • Heat exchangers, in most cases,
control valves are designed to protect static test pressure for pressure ves have a design pressure that is
the process system. sels from the 150% design pressure to higher on one side than on the other.
Be aware that two overpressure sce a new standard of 130% design pres If the design pressure of the low-
narios related to "control valve fails sure, the existing two-thirds rule will pressure side is less than 10/13 that
fully open or closed" do not relate to be changed to a ten-thirteenths rule of the high-pressure side, one can
the cases of instrument-air-failure po very soon. Many major oil companies assume a tube rupture is a valid
sitions discussed above. The analysis are already following this rule.) overpressure scenario. The PRV
of the instrument air failure is focused As a general rule, the required relief must be sized to handle the full
on whether the valve, at air-failure capacity is based on twice the tube high-pressure flow from the tube
position, could cause overpressure in cross-section area, and the assump rupture [10]
the system. Furthermore, instrument tion that high-pressure fluid can flow 14. Upstream relieving. The follow
air failure shall affect all the control through both the tube stub and the ing two scenarios should be evaluated:
valves in the system. other end of the tube [9). These as a. When an upstream vessel is re
In contrast, the "control valve fails pects need to be analyzed: lieving by discharging fluid into a
fully open or closed" situation may • The battery limits for upstream and downstream vessel, the downstream
only affect individual control valves in downstream equipment one should be designed to handle the
the system. Thus, only one control • When a high-pressure vapor gets pressure and the volume of the incom
valve is considered at a time. into a low-pressure vapor system, ing stream from the upstream vessel
If a control valve on a feed line fails the situation is different from, for without overpressuring itself.
fully open, it can result in overpres instance, getting into a low-pressure If the upstream vessel does not have
sure in a surge drum, flash drum or liquid system adequate relief capacity, the down
even distillation column. Tradition • When a high-pressure liquid enters stream vessel needs to have a PRV of
ally, when the liquid outlet or the liq a low-pressure vapor system with its own. The pressure drop between
uid inlet blocked valve fully opened, out flashing, if the velocity of the liq the two vessels should be carefully
engineers assumed that the required uid is high enough, the liquid acts evaluated, along with the proper pres
relieving fluid would be liquid. In real like a piston, pushing away the sure settings for the two PRVs. If the
ity, this may not be true [71. vapor until the liquid velocity has upstream vessel does have sufficient
12. Process control failure. This slowed down. Full flow credit can be relieving capacity, then the impact of
contingency case is important, espe taken for the vapor-handling capac the upstream relieving pressure on
cially with the wide use of program ity at the low-pressure side. Simi the downstream vessel should never
mable logic controllers (PLCs) and larly, when a high-pressure liquid theless be evaluated.
distributed control systems (DCS), but enters into a low-pressure, liquid- b. Two vessels are connected by an
is often overlooked during overpres full system, the inlet liquid would open path. The first has its own PRV
sure analysis. also initially act like a piston, dis and it discharges to a flare header or
The potential impact of the failure placing the lower-pressure liquid. other location. The second will experi
of every control loop — due, for in However, the high-pressure liquid ence the impact from the relieving pres
stance, to the loss of the digital signal would slow down quickly. Therefore, sure of the first vessel relieving. A pres
for whatever reason — should be ana only the credit of the volumetric sure profile between the two vessels at
lyzed, as should a situation in which flowrate of the low-pressure-side liq the time when the first vessel is reliev
all other loops continue to operate nor uid at its normal operating condi ing must be carefully evaluated. The
mally when one fails. As a general tions can be taken second vessel must be well-protected

72 CHEMICAL ENGINEERING WWW.CHE.COM JUNE 2001


when the first vessel is relieving. less properly controlled, the runaway impact of human error on plant safety
15. Runaway chemical reac reaction cannot be controlled and ex should never be underestimated.
tions. During runaway reactions, plosion will follow. Basically, PRVs When relying on operator interven
which tend to accelerate with rising may not provide protection at all be tion, the allowable time limit must be
temperature, extremely high volumes cause of their relatively slow response long enough for the particular plant
of non-condensibles with high energy time. In this case, vapor-depressuring situation. If operator intervention is
can cause the internal pressure of a systems, rupture disks and emergency difficult or impractical, then it should
vessel or pipeline to rise rapidly. Un- vents are better [13]. not be relied on at all. ■
16. Human error. The potential Edited by Suzanne Shelley

References
1. Wong, W.Y., Improve PRV Audits, Hydrocarb.
Proc., November 1998, pp.133-146.
2 American Petroleum Institute, API RP 521:
Guide for Pressure-Relieving and Dcpressur-
ing Systems, 4th ed., Washington, D.C.,
March 1997.
3. American Petroleum Institute, API RP 620:
Sizing, Selection, and Installation of Pres
sure-Relieving Devices in Refineries, 6th ed.,
WashingtonTD.C., March 1993.
4 NFPA 30, "Flammable and Combustibles
Code," National Fire Protection Assn.,
Boston, 1981.
6. Wong, W.Y., Improve the fire protection of
pressure vessels, Chem. Eng., October 1999,
pp.193-196.
6. Wong, W.Y., Fire, vessels and the pressure-re-
liefvalve, Chem. Eng., May 2000, pp. 84-92.
7. Wong, W.Y., Consider two-phase relief for liq
uid blockage of flash drums, Hydrocarb.
Proc, December 1997, pp.76-78.
8. American Petroleum Institute, API RP 2000:
Venting Atmospheric and Low-Prcssure
Storage Tanks, 4th ed., Washington, D.C.,
September 1992.
9. Wong, W.Y., PRV sizing for exchanger tube
rupture, Hydrocarb. Proc., February 1992,
pp. 59-64.
10. Wong, W.Y., Capacity credit calculation for
exchanger tube rupture, Hydrocarb. Proc.,
December 1992, pp.89-92.
11. Emerson, G., The effect of back pressure on
pressure-relief valves, Hydrocarb. Eng., Oc
tober 1999, pp. 77-79.
12. Leung, J.C., and Nazario, F.N., Two-phase FEHLAB CHEHICAL ENGINEERING PROVIDES KEY FEATURES
flashing flow evaluations based on DIEKS,
API, and ASME methodologies, AIChE Loss A POWERFUL WAT OF MODELING equip- ■ Tanored interface for chemical
Prevention Symposium, April 2-6,1989.
13. Fauake, H.K., and Leung, J.C., New experi ment and processes in the field of
mental technique for characterizing tun- Simultaneous solving of arbitrary
away chemical reactions, Chem. Eng. Prog.,
August 1985, pp.39-46.
chemical engineering. It lets you easily
14. Brown, P.P.M., and France, D.W., How to
protect air-cooled exchangers from overpres
model mass, heat and momentum , fnMiaii ^^ for mmiam
sure, Hydrocarb. Proc., August 1975.
transport coupled to chemical reac hut and pats transport coupled to

Author chemical reactions


Wing Y. Wong of WYWong
tions in ID, 2D or 3D geometries.
Engineering (7420 Bates Rd.,
Richmond, B.C. Canada
V7A1C7; Phone: 604-272-
8198; E-mail: wywengineer-
ing @home.com) is an inde Order a free FEMLAB Chemical
pendent consultant who
provides services for design, Engineering Literature Pack!
audit and training related to
pressure-relief systems for
the petroleum, natural %aa
and petrochemical industries
He current-, r consulting service for
UOP LLC (Dca Plaines, 111.). Wong has written
many articles on pressure-relief systems, and
has developed several new concepts and proce
dures for pressure-relief valve calculations. He Vuitwww.comsol.com/chempack or call 781-273-3322 www.comsol.com
holds an M.Eng. in chemical engineering from
the University of Alberta (Canada), and a B.Sc.
from East China Inst of Chemical Technology.
He is a registered professional engineer in both
Alberta and British Columbia.
Circle 60 or Reply Online
CHEMICAL ENGINEERING WWW.CHE.COM JUNE 2001 73

You might also like