Professional Documents
Culture Documents
TA - Protect Plants Over Pressure Scenarios (2001) PDF
TA - Protect Plants Over Pressure Scenarios (2001) PDF
To flare header
FIGURE 1. Even
a relatively sim
ple f ractionation
system, such as
the one shown
here, can have
the consideration of the power failure,
many potential the contingency case should be called
overpressure a power failure. Similarly, if the reflux
scenarios, in- failure is caused by condenser failure,
eluding blocked
the contingency case should be called
outlets; full and
partial power fail a condenser failure.
ures; external As a general rule of thumb, if the
fire; control- potential outcomes of a given failure
valve and con are not likely to occur simultaneously,
trol-loop failures;
then the PRV should be sized sepa
loss of Instru-
- ment air, cooling rately for these two individual cases
water or steam; Feed — not oversized by adding together
thermal expan the two relief capacities required for
Bottom product
sion and many
different potential outcomes of a given
more. The sce
PRV Pressure-relief valve failure mode. By way of example: if
nario with the CW
TRC Temperature-record control
largest required the pressure-relief capacity calculated
LIC Level-indication control
relief load should PRC Pressure-record control for a single reflux failure case is
be used to size CW Cooling water 80,000 lb/h for a given unit, and the
the pressure- re FRC Flow-record control
required relief load for a power failure
lief valve
at the same unit is 150,000 lb/h, then
sure scenario during PRV design, then be unrelated to other causes "if no to properly size the PRV, one should
the existing PRV may be undersized. process or mechanical or electrical assume that the power failure case in
The list of overpressure causes on p. linkages exist among them," or "if the cludes the effect of reflux failure. In
66 should be used to guide the PRV length of time that elapses between other words, the PRV needed to re
audit. However, this list should not be possible successive occurrences of spond to a potential reflux failure
considered all-inclusive. Plant man these causes is sufficient to make should be sized for the larger of the
agers and design engineers should use their classification unrelated." This two values (in this case 150,000 lb/h;
their own engineering judgement to means that one does not need to as not a cumulative 230,000 lb/h).
carefully assess site-specific hazards sume that every contingency case Automatic process control Gener
or uncommon factors that might also being analyzed during system design ally speaking, reliance on so-called fail
constitute an overpressure source. would occur simultaneously. safe instruments or control loops is not a
Ask a lot of questions during such a However, some contingency cases suitable substitute for installing a prop
system evaluation, particularly when are obviously related by cause and ef erly designed pressure-relief system.
you are aware of particular overpres fect. For instance, a "liquid-blocked Ideally, with the use of failsafe instru
sure scenarios that you think should outlet" can be the consequence of an ments or control loops, any abnormal
be included in the PRV audit, but are "inadvertent valve operation" that conditions will prompt an automatic ad
not. Never take for granted "common- was probably caused by "human justment of flowrate, pressure, tempera
sense things." For instance, question error." When one is performing the de ture or other factors. However, given the
why a large PRV is specified for a tailed overpressure analysis, such in potential unreliability or unpredictabil
small vessel, and vice versa. terrelated overpressure scenarios can ity of electronic signals — especially
Before getting into the detailed be summarized as a single potential during upset conditions — such protec
analysis of common overpressure sce overpressure scenario. Other oc- tion cannot be relied on in lieu of pres
narios, we must clarify three related curences, such as a "general power sure-relief devices. Similarly, auto
concepts — double jeopardy, auto failure," will cause reflux interrup matic-startup, equipment should not
matic process control, and administra tions if the reflux is driven by an elec replace the use'of pressure-relief valves
tive procedures. tric pump, and may cause the cooling as protection against overpressure.
Double jeopardy. The concept of duty of an air condenser to be lost, too. One exception is the use of a High
"no double jeopardy in overpressure The bottom line is that when per Integrity Protective System (HIPS).
assessment" is very important. The forming an overpressure analysis, en Using triple redundant signals, the
American Petroleum Inst.'s (API) Rec gineers must consider these cumula HIPS avoids the aforementioned defi
ommended Practice RP 521 Section tive effects, to deal with a ciencies of conventional failsafe sys
2.2 12] states that the causes of over representative cause of potential over tems for electronic process control.
pressure are typically unrelated. Ac pressure. For instance, the possibility Consider a control loop designed to
cording to API, "The simultaneous oc of reflux failure should be analyzed in maintain the liquid level in a tank or
currence of two or more conditions terms of a number of potential causes, reactor when feed increases or de
that could result in overpressure will including power failure, reflux pump creases. The level signal may fail or de
not be postulated, if the causes are un failure, control valve failure, or a con viate for some reason. To make sure
related." Even external fire, one of the denser blanketed by non-condensible. the signal would not be lost, a HIPS
overpressure causes, is considered to If the reflux failure is included in uses three independent signals in-
stalled in the same vessel. In addition, related sources of energy. The most should be added to the wetted sur
it uses a two-out-of-three logic system common example is the use of a steam face area of the main vessel when
(such a system relies on two out of turbine as standby for an electric calculating the potential vapor gen
three voting systems to determine if motor that is driving a pump to trans erated from an external fire. Be
the signal received is reliable), and ei port fluids. cause of the difficulty of calculating
ther an emergency-power-supply Since operator intervention (such as the wetted surface areas of con
(EPS) or an uninterrupted-power-sup reliance on manual cut-in of auxil nected piping and accessories, engi
ply (UPS) system. Using an UPS, when iaries by an operator) is time depen neers should add 15% to the overall
the normal power supply is inter dent, the potential impact of the time wetted surface area of the vessel [61
rupted, a standby power supply would lag required for the standby equip • Even if a vapor-depressuring sys
automatically start, in a fraction of a ment to get into normal position, and tem is installed along with the PRV,
second, to support critical equipment the potential impact of human error, the required fire-relief load through
or units. should be analyzed. the PRV should not be reduced. The
HIPS is not a pressure-relief sys vapor-depressuring system is basi
tem, but rather an automatic control Common overpressure sources cally used to rapidly reduce the in
system that can be used to guard Discussed below are each of the over- ternal pressure to a level where
against overpressure. It is now widely pressue scenarios listed on p. 66. stress rupture would not occur
accepted that the use of a HIPS, with 1. External fire. Fire is a common • Tanks and vessels with design pres
either EPS or UPS, can eliminate cause of overpressure in pipes and sure less than 15 psig need to follow
some (not all) potential overpressure vessels. According to API RP 520 [3] API Standard 2000 [8]
scenarios, and hence greatly reduce and 521 [2], operators should assume 2. Blocked outlets. The closure of a
the use of unnecessarily large relief that the effective fire-exposed area in block valve on the outlet of a pressure
valves and flares, which then reduces cludes an area of 2,500 to 5,000 ft2 vessel can cause the vessel's internal
both capital and operating costs . (this assumes a circle with a diameter pressure to exceed its MAWP, if the
However, operators should consult an of 58-80 ft) [6], with an effective fire source pressure exceeds the vessel de
expert before relying on a HIPS, and if height no more than 25 ft above the sign pressure. However, if the MAWP
the facility chooses this route, it must grade. In contrast, National Fire Pro of a vessel is higher than the source
implement a strict maintenance tection Assn. (NFPA) [4,6] guidelines supply pressure, the vessel has no
schedule for the HIPS, along with rig recommend that operators should as blocked-outlet case.
orous training for operators. sume a fire-exposure area with a fire A blocked outlet can be caused by
Administrative procedures. height of 35 ft above grade (details on control valve failure, inadvertent
Some refineries believe that reliance how to determine the area of a poten valve operation, instrument-air or
on strict administrative procedures is tial fire zone can be found in a previ power failure, and other factors. In
enough to prevent some overpressure ous article by this author, [6]). general, a pressure-relief valve must
scenarios, and, thus, they cite such Analyzing for an external fire case have sufficient capacity to pass a fluid
procedures to justify reducing the assumes that the vessel exposed to the flowrate that is equivalent to the dif
number of PRVs in the facility. While fire is blocked in. Potential vapors re ference between those of the incoming
strict administrative procedures are sulting from the fire must be relieved fluids and the outgoing fluids.
commendable, one should assume using a PRV on the vessel, or via a a. Blocked liquid outlet. When the
that the possibility of human error vent path that remains in a locked- liquid outlet is blocked, the liquid
can never be completely eliminated; open position between the vessel in level in the vessel may rise. If the
thus they should not be used in place question and an adjoining vessel 16}. surge time for liquid overflow from the
of a pressure-relief system. These issues need be considered: vessel is less than 15-20 min, then a
API RP 520 and-521 do allow engi- • Pressure-relief valves alone cannot blocked liquid-outlet is a valid poten
■ neers to take credit for so-called "car protect vessels filled with gas or tial overpressure scenario. When the
seals open (CSO)" or "car seals locked high-boiling-point liquids, so engi required surge I time is longer than
(CSL)" valves., With the installation of neers must carefully evaluate other 15-20 minutes, then operators pre
CSO block valves, operators do not protective measures [SI. Tradition sumably have sufficient time to take
have to drain the equipment after sys ally, design engineers use two ap action to avoid an overflow, so a
tem shutdown, since the valve main proaches to size PRVs for gas-filled blocked liquid outlet is not considered
tains an open position all the time. vessels. One is to use unwetted-sur- to be a potential overpressure source.
However, API RP 521 does not allow face equations, as shown in API RP For any pressure-relief valve in
engineers to take credit for standby 520. Another is to assume the pres stalled on the liquid-feed line, the re
pumps, because they cannot be con ence of some liquids in the vessel, so quired relieving capacity (in units of
sidered to be totally reliable. that wetted-surface equations can volume per time) should be the accu
Full or partial credit may be taken be used to size the PRV (for a de mulated liquid capacity of the vessel.
for normally operating, parallel, in tailed discussion of this, see [5]) When the feed input is a two-phase
strument air compressors and electric • The wetted surface areas of con fluid (i.e., the feed input for a separa
generators, whose drivers use two un nected piping and accessories tor, or flash or-, surge drum), the re-
sized here. API RP 521 suggests that vapor flow in a column or vessel, so
the required relief capacity is the total the loss of quench means a loss of cool
vapor capacity (typically measured as ing duty. A heat balance at the reliev
weight/time, such as lb/h) to the con ing condition must be performed, to
denser at relieving conditions. Actu determine the required relief capacity.
ally, it should be the difference be b. Air-cooled exchanger failure \14\.
tween vapor entering and leaving the When air-cooled exchangers fail, nat
condenser at relieving conditions. If ural convection continues. Therefore,
there is an existing vapor outlet in the a credit for 20 to 30% of normal duty is
system, and that outlet would not be often taken, to reduce the required re
The potential impact of human error on
blocked during a cooling-water fail lief capacity. However, louver closure plant safety should never be underesti
ure, then the available normal vapor is considered to be total loss of the mated. Wherever possible, the process
flowrate through the vapor outlet cooling duty. should be designed to be free from op
c. Loss of cold feed. Loss of cold feed portunities for human error
should be taken as a credit to reduce
the required relief load. is similar to the loss of quench. This The required relieving capacity for
e. Loss of steam. In general, steam item is often overlooked when no heat the failure of total condensing duty
has the following functions at a plant: balance is performed. can be calculated by performing a heat
• It is a driving force for pumps, tur d. Loss of reflux (top and intermedi balance on the system, based on the
bines, compressors, air blowers, and ate). Reflux failure is a common cause loss of the condensing duty. The con
so on. When steam supply is inter of overpressure in fractionation sequences of losing partial condensing
rupted, inlet flow and fluid dis columns. Power failure, pump shut duty should also consider the possibil
charge will be interrupted down, pump mechanical problems and ity of non-condensible blanketing in
• When used as a heating source for control valve failures are among the the condenser. When this occurs, all
reboilers, exchangers and direct in causes of reflux loss, which can result the condensing duties will be lost.
jection, loss of steam will interrupt in receiver and condenser flooding. The consequence of partial condens
heating functions The loss of reflux will cause the tem ing failure can be more severe than
• When used for stripping in fraction- perature in the column to rise, leading that of total condensing failure. The
ation columns, the loss of steam can to a vapor buildup and an increase in relief-capacity calculations might
have a similar impact as the loss of pressure drop in the column and over have to reconsider loss of upstream
cooling duty. Neglecting this might head receiver. Such failure often leads cooling duty if they were related.
lead to an undersized PRV to a loss of total condensing duty. 5. Thermal expansion (some'
f. Loss offuel gas or fuel oil. Except for Nevertheless, exceptions do exist. times call hydraulic expansion).
fuel gas or fuel oil that is used for dri One example is when the receiver has Pressure-relief valves for the case of
ving pumps or turbines that provide a vapor outlet that would not be thermal (or hydraulic) expansion, are
cooling duty, the loss of fuel gas or fuel blocked by the same reason that relatively easy to analyze and size. It
oil would not generally cause over caused the reflux failure. In this case, is rare that a vapor-filled pipeline or
pressure in a system. If fuel gas or fuel the condenser duty may be reduced to vessel would be overpressured by ex
oil is used for generating power, loss of a certain extent, or not even affected, ternal heat sources, other than fire.
such fuels should be evaluated as a depending on the system configura Therefore, no vapor thermal expan
power failure when sizing the PRVs. tion. Furthermore, if the receiver has sion is discussed here.
For fired heaters, the loss of fuel gas enough surge time, say, more than 15 When liquid is blocked in a vessel or
or fuel oil supply does not mean the min from its normal liquid level as a pipeline, external heat input can
clear cutoff of heat input to the sys safe assumption, one could assume cause liquid temperature, and hence
tem. The flow of the residual heat in that the condenser would not flood. volume, to rise. Common causes are:
the fired heater can significantly con In general, loss of cooling duty, by • The pipeline "is filled with liquid
tribute to a heat imbalance and over any of these mechanisms, can cause that is blocked in and heated by
pressure in the system. This state of heat buildup, which can result in steam or electrical heat tracing
affairs is especially significant when vapor buildup and system overpres • A heat-exchanger cold side is filled
the heat duty is large. Generally, sure. The loss of non-condensing cool while the hot side is still flowing
25-40% of normal heating duty shall ing will not generally lead to an over- • A pipeline or vessel is filled with liq
be used as the residual heat input to pressre situation. However, loss of uid at ambient temperature, and is
the fired heater, once power fails and cooling in a partial or total condenser heated by direct solar radiation
fuel gas or fuel oil input has stopped. would generally lead to a system un Usually, a nominal thermal-relief
4. Loss of cooling duty. There are balance, and potential overpressure. valve is adequate for most cases, ex
several different types of cooling du When condensing duty is stopped, if cept for large vessels and long piping.
ties (including the above-mentioned the condensed liquid inventory has Backpressure should be assessed
cooling-water failure), as shown here: more than 15 min to deplete, one can when the thermal-relief valve is dis
a. Loss of quench stream. Normally, assume that the operator has ade charging to another pressured
a quench stream is used to cool a quate time to take corrective action. pipeline or process vessel [11]. When
References
1. Wong, W.Y., Improve PRV Audits, Hydrocarb.
Proc., November 1998, pp.133-146.
2 American Petroleum Institute, API RP 521:
Guide for Pressure-Relieving and Dcpressur-
ing Systems, 4th ed., Washington, D.C.,
March 1997.
3. American Petroleum Institute, API RP 620:
Sizing, Selection, and Installation of Pres
sure-Relieving Devices in Refineries, 6th ed.,
WashingtonTD.C., March 1993.
4 NFPA 30, "Flammable and Combustibles
Code," National Fire Protection Assn.,
Boston, 1981.
6. Wong, W.Y., Improve the fire protection of
pressure vessels, Chem. Eng., October 1999,
pp.193-196.
6. Wong, W.Y., Fire, vessels and the pressure-re-
liefvalve, Chem. Eng., May 2000, pp. 84-92.
7. Wong, W.Y., Consider two-phase relief for liq
uid blockage of flash drums, Hydrocarb.
Proc, December 1997, pp.76-78.
8. American Petroleum Institute, API RP 2000:
Venting Atmospheric and Low-Prcssure
Storage Tanks, 4th ed., Washington, D.C.,
September 1992.
9. Wong, W.Y., PRV sizing for exchanger tube
rupture, Hydrocarb. Proc., February 1992,
pp. 59-64.
10. Wong, W.Y., Capacity credit calculation for
exchanger tube rupture, Hydrocarb. Proc.,
December 1992, pp.89-92.
11. Emerson, G., The effect of back pressure on
pressure-relief valves, Hydrocarb. Eng., Oc
tober 1999, pp. 77-79.
12. Leung, J.C., and Nazario, F.N., Two-phase FEHLAB CHEHICAL ENGINEERING PROVIDES KEY FEATURES
flashing flow evaluations based on DIEKS,
API, and ASME methodologies, AIChE Loss A POWERFUL WAT OF MODELING equip- ■ Tanored interface for chemical
Prevention Symposium, April 2-6,1989.
13. Fauake, H.K., and Leung, J.C., New experi ment and processes in the field of
mental technique for characterizing tun- Simultaneous solving of arbitrary
away chemical reactions, Chem. Eng. Prog.,
August 1985, pp.39-46.
chemical engineering. It lets you easily
14. Brown, P.P.M., and France, D.W., How to
protect air-cooled exchangers from overpres
model mass, heat and momentum , fnMiaii ^^ for mmiam
sure, Hydrocarb. Proc., August 1975.
transport coupled to chemical reac hut and pats transport coupled to