Comparison Sc

As Per MEI Contract As Per Planned / Revised Delay


Description
Start Finish Duration Start Finish Duration (Days
)

MEI Installation ETP 14-Jul-15 11-Oct-15 89 01-Nov-15 29-Jan-16 89 110

MEI Installation WTP 14-Apr-15 02-Sep-15 141 25-Oct-15 14-Mar-16 141 194

MEI Installation DMP 30-Mar-15 27-Jun-15 89 27-Sep-15 25-Dec-15 89 181


Comparison Schedule as per MEI Contract
2015 2016
% Delay
Jan Feb Mar Apr May June July Aug Sep Oct Nov Dec Jan Feb

As per MEI Contract 110 days Expected delay


124
Revised Schedule

As per MEI Contract 194 days Expected delay


138
Revised Schedule Line-2

As per MEI Contract 181 days Expected delay


203
Revised Schedule
2016
Mar

cted delay

Line-2