PROJECT SCHEDULE

PT. OKS Indonesia


Storage Conveyor for FUJI Seat

Desember
No Description 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

Remaining Instllation Work


1 Inlet Lifter Front
Trial to A & B
Fine tuning A & b
2 Inlet Lifter Rear
Trial to D& F
Fine Tuning D & F
3 Repair Area
Trial To BCDEF
Fine Tuning to BCDEF
4 Emty Pallet
System For Single Pallet inlet
5 Lifter 1
Trial Level 2
Fine Tuning Level 2
6 Lifter 2
Trial Level 2
Fine Tuning Level 2
7 Lifter 3
Trial Level 2 3 4
Fine Tuning 2 3 4

Bekasi, 9 September 2019


Brepared By

Agung Hartadi
Remarks
Desember
16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3