Professional Documents
Culture Documents
Can A Letter of Intent Be Construed As An Enforceable Contract PDF
Can A Letter of Intent Be Construed As An Enforceable Contract PDF
Can A Letter of Intent Be Construed As An Enforceable Contract PDF
In this instalment of this series, Entrusty Group will provide the answer to another frequently
asked question above.
L
etters of Intent are a common earlier so that manufacturing can by the parties on all the terms
feature in the construction and start early to minimise any delay and condition that is vital for the
engineering industry such that caused by the ordering of the particular project or purchase and
it is a useful tool for both parties goods under normal circumstances is recognised under Common Law
while negotiating a formal contract or the Employer in a construction as a legally binding document
or agreement, allows one party project requires the Contractor to where parties have the intention
to begin work on the basis of a mobilise into the site, pending to be legally bound. Letters of
Letter of Intent before the formal formal contract, to reduce any delay Intent do not have that capacity to
contract or agreement is concluded. in commencement of work. In other be a legally binding document as
In circumstances where Letters of words, the purpose of the Letter of the wordings and statements more
Intent are utilised, time constraints Intent is to enable work to proceed, often than not are incomplete and
often do not permit all the terms of to circumvent the long lead times vague. In most cases, a Letter of
the contract, design and costing to usually reserved for a particular Intent is binding on neither party
be finalised and concluded so that a part of the work, by providing an and has no contractual effect. So
formal contract exists between both intention that a formal contract in that case, would the answer to
parties before one party carry out would be agreed and finalised at a the question whether the Letter of
work under the formal contract. A later stage. Intent is enforceable contract is an
likely scenario is when it is known affirmative No?
to the Purchaser that the materials Letter of Intent – Enforceable
to be supplied by the Seller require or not? Before we delve into answering
long lead time to deliver and the the question, let us explore and
Purchaser by way of a Letter of Although the Letter of Intent’s understand the types of Letters of
Intent, instructs the Seller to place well meaning intended purpose is Intent which generally falls into
order for the materials in advance to avoid delay to the work, it has two types i.e. the traditional Letter
of and while a formal contract is one serious and fundamental flaw of Intent and the “If ” Contract.
being entered. Other scenarios – The Letter of Intent is neither an The traditional Letter of Intent
where Letters of Intent are used offer nor a contract. In the event basically contains instructions by
are situations where the Purchaser that there would not be a formal the Employer for particular works
requires the Seller to reserve for contract to be agreed and finalised to be carried out by the Contractor
them the goods or services that between both parties making the but typically the statements in such
may not be made available to the Letter of Intent the sole document Letters are vague and uncertain as
Purchaser if the Purchaser and Seller to bind the parties, there runs a such do not have the contractual
had followed through the usual risk that parties have to rely on the obligations to bind parties. The
process of negotiation of a formal wordings of the Letter of Intent to “If ” Contract contains not only
contract or the Purchaser wants the fight for their respective rights. A instructions to the Contractor to
Seller to place order for the goods formal contract requires agreement carry out work but also states that if
98
99
to manufacture and supply the Case Law – Where a Letter of a certain amount after completion
cast steel nodes to Cleveland Intent forms an “If” Contract of the works.
Bridge without a formal contract.
Complications arose when British Monk Construction Ltd. vs Norwich Mowlem plc vs Stena Line Ports Ltd
Steel could not meet certain Union Life Insurance Society CA (2004)
delivery schedule and there were (1992)
delays in delivery of the cast steel In this case, Mowlem carried out
nodes. British Steel claimed as Monk carried out work based on a works under a series of Letters of
quantum meruit the amount for the Letter of Intent issued by Norwich Intent issued by Stena, each with
cast steel nodes it had delivered which stated that the maximum maximum expenditure caps, the final
while Cleveland Bridge counter- expenditure for mobilisation and maximum cap in the final Letter of
claimed damages for breach of ordering of materials was limited Intent being £10 million. However,
contrac t for late deliver y and to £100,000.00 and if a formal Mowlem continued to carry out
out of sequence. The learned contract could not be concluded, works exceeding the maximum cap
Judge found in favour of British M onk ’s entitlement would be of £10 million although both parties
Steel that there was no contract limited to proven costs. No agreed that if Mowlem carried out
between parties since parties were contract was entered but Monk work under each Letter of Intent
still in negotiation and therefore, went on to carry out work and from Stena, it constituted to an
without a contract there could made a £4 million claim as offer to enter into a contract. The
not be damages out of a breach quantum meruit. Norwich argued dispute was whether Mowlem was
of contract. that an “If ” Contract was entered entitled to be paid more than £10
and Monk’s entitlement was not million for work done as quantum
Kitson Ltd vs Balfour Beatty (1991) based on quantum meruit but meruit or whether Stena’s £ 10
proven costs as stipulated in the million maximum cap applied. The
In this case, after submitting for a Letter of Intent. The Judge in the learned Judge found in favour of
tender and revising their pricing Court of Appeal held that Monk Stena’s arguments because the
after changes were made to the was entitled to the claim based maximum cap in the Letter of
tender, Kitson commenced work on quantum meruit as the Letter Intent clearly stated that Stena was
after a Letter of Intent was issued of Intent did not amount to an only obliged to pay for work done
by Balfour Beatty so that Kitson “If ” Contract because proven cost up to a maximum amount of £10
can start the work early pending was limited to mobilisation and million and imposes no obligation
acceptance of the revised tender ordering of materials but not for for Mowlem to carry out work more
by Balfour Beatty. Several months the execution of the works that than the maximum cap. As such,
later, Balfour B eatt y wrote to Monk had carried out. Therefore, Mowlem failed in their claim for
Kitson to accept the revised tender Monk was entitled to their claim quantum meruit.
but the documents enclosing the based on quantum meruit.
acceptance letter contained changes Allen Wilson Shopfitters vs Anthony
made after the Letter of Intent was J Jarvis & Sons PLC vs Galliard Buckingham (2005)
issued and as such was not the Homes Ltd (1999)
same as contained in the Letter Allen Wilson carried out extensive
of Intent, which Kitson promptly In another case of an “If” Contract, refurbishment works at Anthony
refuse to accept. The matter was the Court of Appeal agreed with Buckingham’s house pursuant to a
taken to Court when a dispute Jarvis that the words in the Letter Letter of Intent which stated among
arose which Kitson contended there of Intent issued by Galliard, “in other terms “works to be carried
was no binding contract but Balfour the event that we do not enter into out under the terms and conditions
Beatty contended otherwise when a formal contract with through no of the JCT 1998 Private Without
the Letter of Intent was issued and fault of Jarvis Interiors, you will be Quantities 1998 edition.” and “In
accepted by Kitson. The learned reimbursed all fair and reasonable the event that no formal Contract
Judge held that there is no binding costs incurred and these will be is entered into then the terms of
contract between the two when assessed on a quantum meruit this letter will apply to the whole of
both parties agreed that the Letter basis.”, held a basis for Jarvis to the works carried out by you. The
of Intent was issued solely for the claim for works on quantum meruit employer will pay for you any work
purpose that work can commence as opposed to Galliard’s contention so completed in accordance with the
and an eventual contract would that a gentlemen’s agreement was payment provisions of the Contract…”.
be made. agreed between the two parties at No formal contract was entered
100
and when the Employer failed to part of an agreement to agree to a understanding (MOU) was entered
pay, the Contractor obtained an future agreement. The Contractor, between parties. Although the
adjudication decision in its favour on the other hand, stated that all Plaintiff accepted the offer of
which the Employer challenged the terms and conditions were already RM178,000.00 for the shop house, no
enforcement of the decision on the agreed between parties, only to Sales and Purchase Agreement was
basis that there was no written be formalised into a contract. The executed as required by the MOU.
contract. The learned Judge found learned Judge in the Supreme The Plaintiff was forced to leave
that there was a contract pursuant Court held that arrangement made the temporary long shop house
to the Letter of Intent when the ‘subject to contract’ or ‘subject to the built by the Defendant after it was
Contractor agreed to carry out works preparation and approval of a formal demolished and by a civil suit, the
for the prices set out in and also contract’ and similar terms would Plaintiff sought an order against the
held that all terms of the JCT 1998 mean that the parties were still in Defendant for specific performance
edition, including adjudication were negotiations and did not intend to of the MOU and damages for
incorporated into the contract. be bound until a formal contract compensation. The High Court
was agreed. However, ‘subject to held the judgement in favour of the
ERDC Group Ltd vs Brunel University contract clause’ terms would not Plaintiff because the Defendant had
(2006) prevent the formation of a contract benefited from the MOU when the
in exceptional circumstances. He Plaintiff agreed to vacate the land
In this case, the Court found that found that with several essential without compensation and with the
the parties intended to enter into a matters remained to be settled subsequent acts by the Defendant
legal relation and that each Letter between the parties, the Letter is for the Plaintiff, the Court found that
of Intent issued by Brunel was not a binding contract but merely the MOU was a binding contract
an offer which ERDC accepted by a record of terms agreed by parties although no Sales and Purchase
commencing work which in turn, as a basis for contract negotiation. Agreement was entered between
resulted in a contract which JCT The Contractor was awarded a claim the two.
valuation rules and ERDC’s tender on quantum meruit subject to a
rates applied for each Letter of maximum limit. Lam Hong Hardware Co. Sdn Bhd vs
Intent. However, for works carried Incacon Sdn Bhd (2006)
out after the expiry of the last Letter Khaw Kim Chua & Anor vs Dayani
of Intent, there was no contract and Sdn Bhd (2005) The Judge held that the Letter of
ERDC was entitled to quantum meruit Intent was not a contract as it did
payments assessed by reference to This was a case where the Defendant not contain terms that would have
ERDC’s tender rates. Brunel was not agreed to sell completed shop existed in a formal contract such as
entitled to counterclaims since the houses to Plaintiff, all of whom were pricing, rates and payment method
defective works was not carried out squatters of the land which the for this case where Lam Hong had
pursuant to a contract. Defendant was developing, if the supplied materials to Incacon based
Plaintiff vacated the Land without on a Letter of Intent which Lam
Case Law – Letter of Intent on compensation. A memorandum of Hong had taken the matter to Court
the Local Front
101
102