Perhitungan Cost Oprasional Boiler Ketika Stop Proses

Jumblah Rp
Upah karyawan 8 Orang 2,940,000
BL 120 3 Kg 190,334
BL 171 1 Kg 91,964
BL 1301 3 Kg 109,074
BL 1102 1 Kg 92,267
Polimer 600 Gr 72,000
Coustic soda 150 Kg 2,291,000
Air
Jumblah 5,786,899
Ket :
Lembur karyawan (10 jam) = 24,5 x 8 x 15.000 = 2.940.000
Harga Chemical/Kg BL 120 = 63.448
BL 171 = 91.964
BL 1102 = 92.267
BL 1301 = 36.358
polimer = 120.000
Coustic = 15.277
pemakaian Coustic Soda rata rata 75 Kg/5 jam
pemakaian Polimer rata rata 500-800 gr/shift
Perhitungan Cost Oprasional Genset Ketika Stop Boiler
Jumblah Rp
Upah Karyawan 1 orang 367,500
Kebutuhan Bahan Bakar 60 L/jam 7,200,000

Jumblah 7,567,500
Ket :
Beban = 200 Kw
Harga Solar = 12.000
Estimasi faktor ketetapan konsumsi solar per jam = 0,3 L/kW