You are on page 1of 13

PROJECT: TOWER SCHED

Structure Structure Structure File


Station (m) Line Angle (deg)
Number Description Name
1 0 Gantry 00⁰00'00" GANTRY

2 40 BP1/0 20° 02' 43" LT TT4+0M

3 382.58 BP1/1 00⁰00'00" GST+6M

4 725.165 BP1/2 00⁰00'00" GST+0M

5 1062.748 BP1/3 00⁰00'00" GST+3M

6 1413.463 BP2/0 25° 33' 06" LT TT1+0M

7 1738.463 BP2/1 00⁰00'00" GST+0M

8 2063.463 BP2C 00⁰00'00" GST+0M

9 2373.463 BP2B 16° 06' 41" LT TT1+0M

10 2513.543 BP2A 00⁰00'00" GST+0M

11 2661.362 BP2NEW/0 48° 16' 04" RT TT2+0M

12 2812.212 BP2NEW1 57° 37' 58" RT 3S90spl_6m BE

13 2910.255 BP2NEW/2 57° 11' 57" LT 3S90spl_6m BE

14 3061.575 BP2C 28° 05' 24" LT TT1+0M

15 3349.302 BP2D/0 00⁰00'00" GST+6M

16 3668.681 BP2D/1 00⁰00'00" GST+6M

17 3956.925 BP2D/2 00⁰00'00" TT1+0M

18 4190.034 BP3/0 04° 04' 20" LT TT1+6M

19 4520.038 BP3/1 00⁰00'00" GST+3M

20 4865.038 BP3/2 00⁰00'00" GST+0M

21 5185.038 BP3/3 00⁰00'00" GST+3M

22 5520.038 BP3/4 00⁰00'00" GST+0M

23 5835.038 BP3/5 00⁰00'00" GST+3M

24 6155.038 BP3/6 00⁰00'00" GST+0M

25 6456.588 BP4/0 42° 38' 03" LT TT2+0M


26 6684.977 BP4/1 00⁰00'00" GST+0M

27 6933.281 BP4/2 00⁰00'00" TT1+0M

28 7136.513 BP4A 55° 21' 30" LT 3S90spl_6m BE

29 7236.47 BP4B 57° 44' 00" RT 3S90spl_6m BE

30 7386.684 BP4C 48° 09' 48" RT TT2+0M

31 7673.986 BP5/1 NEW 16° 04' 42" LT TT1+0M

32 7934.7 BP5/2 00⁰00'00" GST+0M

33 8200.27 BP5/3 00⁰00'00" GST+3M

34 8560.269 BP5/4 00⁰00'00" GST+3M

35 8930.269 BP5/5 00⁰00'00" GST+6M

36 9300.269 BP5/6 00⁰00'00" GST+3M

37 9670.269 BP5/7 00⁰00'00" GST+6M

38 10040.269 BP5/8 00⁰00'00" GST+3M

39 10390.269 BP5/9 00⁰00'00" GST+3M

40 10715.27 BP5/10 00⁰00'00" GST+3M

41 10960.269 BP5/11 00⁰00'00" TT1+6M

42 11336.163 BP5/12 00⁰00'00" GST+0M

43 11656.163 BP5/13 00⁰00'00" GST+3M

44 12036.163 BP5/14 00⁰00'00" GST+3M

45 12401.163 BP5/15 00⁰00'00" GST+3M

46 12776.163 BP5/16 00⁰00'00" GST+3M

47 13126.163 BP5/17 00⁰00'00" GST+0M

48 13419.164 BP5/18 00⁰00'00" GST+3M

49 13786.163 BP5/19 00⁰00'00" TT1+6M

50 14186.163 BP5/20 00⁰00'00" GST+3M

51 14541.163 BP5/21 00⁰00'00" GST+0M

52 14896.163 BP5/22 00⁰00'00" GST+3M


53 15251.163 BP5/23 00⁰00'00" GST+0M

54 15581.163 BP5/24 00⁰00'00" GST+0M

55 15916.163 BP5/25 00⁰00'00" GST+0M

56 16271.163 BP5/26 00⁰00'00" GST+3M

57 16653.389 BP6/0 03° 54' 45" LT TT1+6M

58 16862.295 BP7/0 20° 29' 39" LT TT1+6M

59 17101.179 TT2 11° 39' 27" LT TT4+0M

60 17151.255 Gantry 00⁰00'00" GANTRY


TOWER SCHEDULE FOR 220kV S/C OHL FOR ORAPA 2 - LETHLAHAKANE S/S LINE

Struct. Nomonation
BC/Clearance Backfilling Coping/Muffing
Height (m) Approved
14

21.75 SFR

30.02 SFR

24.02 SFR

27.02 SFR

21.75 SFR

24.02 SFR

24.02 SFR

21.75 SFR

24.02 SFR

21.75 SFR

34.67 SFR

34.67 SFR

21.75 SFR

30.02 SFR

30.02 SFR

21.75 SFR

27.75 SFR

27.02 SFR

24.02 SFR

27.02 E2/Type 1

24.02 E2/Type 1

27.02 E2/Type 1

24.02 E2/Type 1

21.75 E2/Type 1
24.02 E2/Type 1

21.75 E2/Type 1

34.67 Type 1

34.67 Type 1

21.75 E2/Type 1

21.75 E2/Type 1

24.02 E2/Type 1

27.02 E2/Type 1

27.02 E2/Type 1

30.02 SFR

27.02 E2/Type 1

30.02 E2/Type 1

27.02 E2/Type 1

27.02 SFR

27.02 SFR

27.75 SFR

24.02 SFR

27.02 SFR

27.02 SFR

27.02 SFR

27.02 SFR

24.02 SFR

27.02 SFR

27.75 SFR

27.02 SFR

24.02 SFR

27.02 SFR
24.02 SFR

24.02 SFR

24.02 SFR

27.02 SFR

27.75 SFR

27.75 SFR

21.75 SFR

14
AHAKANE S/S LINE

Bitumious CP Earthing if House


TT earthing Remarks
Paint any Keeping
PROJECT: TOWER SCHEDULE FOR 220kV S/C OHL FOR ORAPA 2 - LETHLAHAKANE S/S LINE

Structure Structure Structure File Struct. Deformed/Bucked/Missin N/B correct size N/B Punching & Blank Holes Tower
Station (m) Line Angle (deg) FAS TFR/Any CPE ACD Fixing Bird Guard
Number Description Name Height (m) g/Rusted members fixed and torqued Painting Fixed Accessories

1 0 Gantry 00⁰00'00" GANTRY 14

2 40 BP1/0 20° 02' 43" LT TT4+0M 21.75

3 382.58 BP1/1 00⁰00'00" GST+6M 30.02

4 725.165 BP1/2 00⁰00'00" GST+0M 24.02

5 1062.748 BP1/3 00⁰00'00" GST+3M 27.02

6 1413.463 BP2/0 25° 33' 06" LT TT1+0M 21.75

7 1738.463 BP2/1 00⁰00'00" GST+0M 24.02

8 2063.463 BP2C 00⁰00'00" GST+0M 24.02

9 2373.463 BP2B 16° 06' 41" LT TT1+0M 21.75

10 2513.543 BP2A 00⁰00'00" GST+0M 24.02

11 2661.362 BP2NEW/0 48° 16' 04" RT TT2+0M 21.75

12 2812.212 BP2NEW1 57° 37' 58" RT 3S90spl_6m BE 34.67

13 2910.255 BP2NEW/2 57° 11' 57" LT 3S90spl_6m BE 34.67

14 3061.575 BP2C 28° 05' 24" LT TT1+0M 21.75

15 3349.302 BP2D/0 00⁰00'00" GST+6M 30.02

16 3668.681 BP2D/1 00⁰00'00" GST+6M 30.02

17 3956.925 BP2D/2 00⁰00'00" TT1+0M 21.75

18 4190.034 BP3/0 04° 04' 20" LT TT1+6M 27.75

19 4520.038 BP3/1 00⁰00'00" GST+3M 27.02

20 4865.038 BP3/2 00⁰00'00" GST+0M 24.02

21 5185.038 BP3/3 00⁰00'00" GST+3M 27.02

22 5520.038 BP3/4 00⁰00'00" GST+0M 24.02

23 5835.038 BP3/5 00⁰00'00" GST+3M 27.02

24 6155.038 BP3/6 00⁰00'00" GST+0M 24.02

25 6456.588 BP4/0 42° 38' 03" LT TT2+0M 21.75

26 6684.977 BP4/1 00⁰00'00" GST+0M 24.02

27 6933.281 BP4/2 00⁰00'00" TT1+0M 21.75

28 7136.513 BP4A 55° 21' 30" LT 3S90spl_6m BE 34.67

29 7236.47 BP4B 57° 44' 00" RT 3S90spl_6m BE 34.67


30 7386.684 BP4C 48° 09' 48" RT TT2+0M 21.75

31 7673.986 BP5/1 NEW 16° 04' 42" LT TT1+0M 21.75

32 7934.7 BP5/2 00⁰00'00" GST+0M 24.02

33 8200.27 BP5/3 00⁰00'00" GST+3M 27.02

34 8560.269 BP5/4 00⁰00'00" GST+3M 27.02

35 8930.269 BP5/5 00⁰00'00" GST+6M 30.02

36 9300.269 BP5/6 00⁰00'00" GST+3M 27.02

37 9670.269 BP5/7 00⁰00'00" GST+6M 30.02

38 10040.269 BP5/8 00⁰00'00" GST+3M 27.02

39 10390.269 BP5/9 00⁰00'00" GST+3M 27.02

40 10715.27 BP5/10 00⁰00'00" GST+3M 27.02

41 10960.269 BP5/11 00⁰00'00" TT1+6M 27.75

42 11336.163 BP5/12 00⁰00'00" GST+0M 24.02

43 11656.163 BP5/13 00⁰00'00" GST+3M 27.02

44 12036.163 BP5/14 00⁰00'00" GST+3M 27.02

45 12401.163 BP5/15 00⁰00'00" GST+3M 27.02

46 12776.163 BP5/16 00⁰00'00" GST+3M 27.02

47 13126.163 BP5/17 00⁰00'00" GST+0M 24.02

48 13419.164 BP5/18 00⁰00'00" GST+3M 27.02

49 13786.163 BP5/19 00⁰00'00" TT1+6M 27.75

50 14186.163 BP5/20 00⁰00'00" GST+3M 27.02

51 14541.163 BP5/21 00⁰00'00" GST+0M 24.02

52 14896.163 BP5/22 00⁰00'00" GST+3M 27.02

53 15251.163 BP5/23 00⁰00'00" GST+0M 24.02

54 15581.163 BP5/24 00⁰00'00" GST+0M 24.02

55 15916.163 BP5/25 00⁰00'00" GST+0M 24.02

56 16271.163 BP5/26 00⁰00'00" GST+3M 27.02

57 16653.389 BP6/0 03° 54' 45" LT TT1+6M 27.75

58 16862.295 BP7/0 20° 29' 39" LT TT1+6M 27.75

59 17101.179 TT2 11° 39' 27" LT TT4+0M 21.75

60 17151.255 Gantry 00⁰00'00" GANTRY 14


PROJECT: TOWER SCHEDULE FOR 220kV S/C OHL FOR ORAPA 2 - LETHLAHAKANE S/S LINE

Insulator OPGW
Structure Structure Structure File Struct. Hardware Fittings as per Acsr & E/W ACSR & E/W Aviation OPGW
Station (m) Line Angle (deg) Numbers/Damage MS Joints Jumpers CLIPPING&
Number Description Name Height (m) Drawing Clipping VD Requirements Splicing
d JUMPERING

1 0 Gantry 00⁰00'00" GANTRY 14

2 40 BP1/0 20° 02' 43" LT TT4+0M 21.75

3 382.58 BP1/1 00⁰00'00" GST+6M 30.02

4 725.165 BP1/2 00⁰00'00" GST+0M 24.02

5 1062.748 BP1/3 00⁰00'00" GST+3M 27.02

6 1413.463 BP2/0 25° 33' 06" LT TT1+0M 21.75

7 1738.463 BP2/1 00⁰00'00" GST+0M 24.02

8 2063.463 BP2C 00⁰00'00" GST+0M 24.02

9 2373.463 BP2B 16° 06' 41" LT TT1+0M 21.75

10 2513.543 BP2A 00⁰00'00" GST+0M 24.02

11 2661.362 BP2NEW/0 48° 16' 04" RT TT2+0M 21.75

12 2812.212 BP2NEW1 57° 37' 58" RT 3S90spl_6m BE 34.67

13 2910.255 BP2NEW/2 57° 11' 57" LT 3S90spl_6m BE 34.67

14 3061.575 BP2C 28° 05' 24" LT TT1+0M 21.75

15 3349.302 BP2D/0 00⁰00'00" GST+6M 30.02

16 3668.681 BP2D/1 00⁰00'00" GST+6M 30.02

17 3956.925 BP2D/2 00⁰00'00" TT1+0M 21.75

18 4190.034 BP3/0 04° 04' 20" LT TT1+6M 27.75

19 4520.038 BP3/1 00⁰00'00" GST+3M 27.02

20 4865.038 BP3/2 00⁰00'00" GST+0M 24.02

21 5185.038 BP3/3 00⁰00'00" GST+3M 27.02

22 5520.038 BP3/4 00⁰00'00" GST+0M 24.02

23 5835.038 BP3/5 00⁰00'00" GST+3M 27.02

24 6155.038 BP3/6 00⁰00'00" GST+0M 24.02

25 6456.588 BP4/0 42° 38' 03" LT TT2+0M 21.75

26 6684.977 BP4/1 00⁰00'00" GST+0M 24.02

27 6933.281 BP4/2 00⁰00'00" TT1+0M 21.75

28 7136.513 BP4A 55° 21' 30" LT 3S90spl_6m BE 34.67

29 7236.47 BP4B 57° 44' 00" RT 3S90spl_6m BE 34.67


30 7386.684 BP4C 48° 09' 48" RT TT2+0M 21.75

31 7673.986 BP5/1 NEW 16° 04' 42" LT TT1+0M 21.75

32 7934.7 BP5/2 00⁰00'00" GST+0M 24.02

33 8200.27 BP5/3 00⁰00'00" GST+3M 27.02

34 8560.269 BP5/4 00⁰00'00" GST+3M 27.02

35 8930.269 BP5/5 00⁰00'00" GST+6M 30.02

36 9300.269 BP5/6 00⁰00'00" GST+3M 27.02

37 9670.269 BP5/7 00⁰00'00" GST+6M 30.02

38 10040.269 BP5/8 00⁰00'00" GST+3M 27.02

39 10390.269 BP5/9 00⁰00'00" GST+3M 27.02

40 10715.27 BP5/10 00⁰00'00" GST+3M 27.02

41 10960.269 BP5/11 00⁰00'00" TT1+6M 27.75

42 11336.163 BP5/12 00⁰00'00" GST+0M 24.02

43 11656.163 BP5/13 00⁰00'00" GST+3M 27.02

44 12036.163 BP5/14 00⁰00'00" GST+3M 27.02

45 12401.163 BP5/15 00⁰00'00" GST+3M 27.02

46 12776.163 BP5/16 00⁰00'00" GST+3M 27.02

47 13126.163 BP5/17 00⁰00'00" GST+0M 24.02

48 13419.164 BP5/18 00⁰00'00" GST+3M 27.02

49 13786.163 BP5/19 00⁰00'00" TT1+6M 27.75

50 14186.163 BP5/20 00⁰00'00" GST+3M 27.02

51 14541.163 BP5/21 00⁰00'00" GST+0M 24.02

52 14896.163 BP5/22 00⁰00'00" GST+3M 27.02

53 15251.163 BP5/23 00⁰00'00" GST+0M 24.02

54 15581.163 BP5/24 00⁰00'00" GST+0M 24.02

55 15916.163 BP5/25 00⁰00'00" GST+0M 24.02

56 16271.163 BP5/26 00⁰00'00" GST+3M 27.02

57 16653.389 BP6/0 03° 54' 45" LT TT1+6M 27.75

58 16862.295 BP7/0 20° 29' 39" LT TT1+6M 27.75

59 17101.179 TT2 11° 39' 27" LT TT4+0M 21.75

60 17151.255 Gantry 00⁰00'00" GANTRY 14