PERMOHONAN PINDAAN KEBENARAN MERANCANG TERHADAP PELAN YANG
TELAH DILULUSKAN MPKj: NO. RUJUKAN (5) dim.MPKj.JPP/BPB/KM1/14-2018
BERTARIKH 1 OKTOBER 2018 BAGI CADANGAN PEMBANGUNAN SEPERTI BERIKUT:
1 1 BLOK 188 UNIT PANGSAPURI RUMAH SELANGORKU (JENIS D) - 17
TINGKAT (TERMASUK 5 TINGKAT PODIUM TEMPAT LETAK KERETA &
KEMUDAHANNYA),
2. 1 UNIT PONDOK PENGAWAL
3. 1 UNIT PENCAWANG ELEKTRIK
4. 1 UNIT KEBUK SAMPAH
DI ATAS LOT 41152 & LOT 41153, PEKAN KAMPUNG SUNGAI TANGKAS, DAERAH
HULU LANGAT, SELANGOR DARUL EHSAN.
UNTUK TETUAN EXCLUSIVE EXPANSION SDN BHD.
STORM MANAGEMENT AND DESIGN CALCULATION REPORT FOR
PROPOSED ON-SITE DETENTION (MSMA 2)
hereby certify that these works have
been designed by me in accordance with
sound engineering practice and that I take
full responsibility for the design, and
sroper performance of the same.
JURUTERA PERUNDING: PI
ICON CONSULTING ENGINEERS SDN BHD
CO, NO.852977-M
NO. 1-78, JALAN PUJ 3/8,
TAMAN PUNCAK JALIL,
BANDAR PUTRA PERMAI
43300 SERI KEMBANGAN,
EXCLUSIVE EXPANSION SDN BHD
CO. NO. 1247059-H
UNIT A-3A-10, BLOK A,
PLAZA MONT’ KIARA,
NO. 2, JALAN KIARA,
MONT’ KIARA
SELANGOR DARUL EHSAN 80480 KUALA LUMPUR
TEL : 03 - 8999 1133/1166/1188 TEL : 03 - 6412 9150
FAX : 03 - 8999 1122 FAX : 03 - 6412 9151
MAY 2020PERMOHONAN PINDAAN KEBENARAN MERANCANG TERHADAP PELAN YANG TELAH DILULUSKAN MPKj: NO.
RUJUKAN (5) dim.MPKj.JPP/BP8/KM1/14-2018 BERTARIKH 1 OKTOBER 2018 BAG! CADANGAN PEMBANGUNAN
SEPERTI BERIKUT:
1.1 BLOK 188 UNIT PANGSAPURI RUMAH SELANGORKU (JENIS D) ~ 17 TINGKAT (TERMASUK 5 TINGKAT PODIUM
‘TEMPAT LETAK KERETA & KEMUDAHANNYA),
2. UNIT PONDOK PENGAWAL
3. UNIT PENCAWANG ELEKTRIK
4, LUNIT KEBUK SAMPAH
DI ATAS LOT 41152 & LOT 41153, PEKAN KAMPUNG SUNGAI TANGKAS, DAERAH HULU LANGAT, SELANGOR DARUL
EHSAN.
UNTUK TETUAN EXCLUSIVE EXPANSION SDN BHD
Table of Content
> Key plan
* Location Plan
1.0 Introduction
2.0 Description of The Site
3.0 Guidelines And Design Criteria
4.0 Proposed Detention System
5.0 Proposed Discharge
6.0 Conclusion
APPENDICES
APPENDIX A - OSD CalculationPERMOHONAN PINDAAN KEBENARAN MERANCANG TERHADAP PELAN YANG TELAH DILULUSKAN MPKj: NO.
RUJUKAN (5) dim.MPKj.JPP/BPB/KM1/14-2018 BERTARIKH 1 OKTOBER 2018 BAG! CADANGAN PEMBANGUNAN
‘SEPERT! BERIKUT:
1.1 BLOK 188 UNIT PANGSAPURI RUMAH SELANGORKU (JENIS D) ~ 17 TINGKAT (TERMASUK 5 TINGKAT PODIUM
‘TEMPAT LETAK KERETA & KEMUDAHANNYA),
2.1 UNIT PONDOK PENGAWAL
3.1 UNIT PENCAWANG ELEKTRIK
4, 1 UNIT KEBUK SAMPAH
DI ATAS LOT 41152 & LOT 41153, PEKAN KAMPUNG SUNGAI TANGKAS, DAERAH HULU LANGAT, SELANGOR DARUL
EHSAN.
UNTUK TETUAN EXCLUSIVE EXPANSION SDN BHD
1) Introduction
The objective of this report is to outline the concept of storm water management system for the
proposed development on Lot 41152 and Lot 41153, Sg Tangkas, Mukim Kajang, Daerah Hulu
Langat, Selangor Darul Ehsan.
The development comprises of three block of 17 storey apartment with 5 storey carpark and
facilities
Icon Consulting Engineers Sdn Bhd has been appointed as the Civil Consultant to provide
engineering consulting services for the entire development.
2) Description of The Site
In general, the development of this land covers an area of approximately 1.88 acres, which is
located at the rapid development area in Sg. Tangkas, Mukim Kajang, District of Hulu Langat,
Selangor Darul Ehsan.
At present, the site is undeveloped and covered with vegetation. The terrain of the site varies
from the lowest level 43.02m at the western comer to the highest level 54.0m at the eastern
boundary of the site.
3) Guidelines And Design Criteria
The planning and design of the proposed drainage concept and stormwater management
system is based on ‘Urban Stormwater Management Manual for Malaysia, 2012 (MSMA 2)'
published by Department of Irrigation and Drainage.
Design ARI
[__ Drainage Facil ‘Average Recurrence Interval (ARI)
{| Roadside Drains 5 years / 10 years
2 Main Drains 50 years / 100 years
3__| Detention Pond _ 5 years / 50 years / 100 years
‘4 | On-Site-Detention (OSD) using | 5 years / 10 years
open space / tanks and etc.
Design Criteria’
i) C value, pre-development 05
ii) C value,post-development 08
iii) SSr-value = Quo post
iv) Qu. = Quere
v) IDF. = Setor JPS KajangPERMOHONAN PINDAAN KEBENARAN MERANCANG TERHADAP PELAN YANG TELAH DILULUSKAN MPKj: NO.
RUJUKAN (5) dim.MPK).JPP/BPB/KM1/14-2018 BERTARIKH 1 OKTOBER 2018 BAG! CADANGAN PEMBANGUNAN.
‘SEPERTI BERIKUT:
41.1 BLOK 188 UNIT PANGSAPURI RUMAH SELANGORKU (JENIS D) ~ 17 TINGKAT (TERMASUK 5 TINGKAT PODIUM.
‘TEMPAT LETAK KERETA & KEMUDAHANNYA),
2. 1 UNIT PONDOK PENGAWAL
3. L UNIT PENCAWANG ELEKTRIK
4, 1 UNIT KEBUK SAMPAH
DI ATAS LOT 41152 & LOT 41153, PEKAN KAMPUNG SUNGAI TANGKAS, DAERAH HULU LANGAT, SELANGOR DARUL
EHSAN.
LUNTUK TETUAN EXCLUSIVE EXPANSION SON BHD
4) Proposed Detention System
i) The entire development area shall sub-divided and discharge to two catchments as
shown in layout plan attached.
ji.) Storm water from each sub-catchment is channel to roadside drains. The roadside drains
are design for 5 years ARI and check for 20 years ARI.
Storm water from each sub-catchment will be channelled a On Site Detention on the
north-eastern comer of the site.
iv.) A rectangular shape OSD tank with the size of 228m x 1.8m x 0.9m height is provided at
eastem of the site, boundary between Sewerage Treatment Plant and buffer zone, to
cater this 1.88 acres of catchment
5) Proposed Discharge
The proposed OSD discharge will be connected existing main drain located at Jalan Pintar.
The final discharge point is located at the existing river at Sg Tangkas.
6) Conclusion
A rectangular shape OSD tank with the size of 228m x 1.8m x 0.9m height is provided at
ground level for this 1.88 acres of catchment.
Detail hydraulic design calculation for the drainage and drawings will be submitted upon
approval of the layout plan and development order.
The area proposed for the storm water detention facilities and OSD is indicated in the plan
1912/OSDISILP1.PERMOHONAN PINDAAN KEBENARAN MERANCANG TERHADAP PELAN YANG TELAH DILULUSKAN MPKj: NO.
RUJUKAN (5) dim.MPKj.JPP/BPB/KM1/14-2018 BERTARIKH 1 OKTOBER 2018 BAGI CADANGAN PEMBANGUNAN
SEPERTI BERIKUT:
1.1 BLOK 188 UNIT PANGSAPURI RUMAH SELANGORKU (JENIS D) ~ 17 TINGKAT (TERMASUK 5 TINGKAT PODIUM
‘TEMPAT LETAK KERETA & KEMUDAHANNYA),
2. 1 UNIT PONDOK PENGAWAL
3. 1 UNIT PENCAWANG ELEKTRIK
4.1 UNIT KEBUK SAMPAH
DI ATAS LOT 41152 & LOT 41153, PEKAN KAMPUNG SUNGAI TANGKAS, DAERAH HULU LANGAT, SELANGOR DARUL
EHSAN.