You are on page 1of 4

SEWERAGE

A Drain pipe, unplasticized polyvinyl chloride (uPVC) to BS 3526, size 100mm


Ø, laid and jointed with collars and rubber rings [RM/M]

B EXTRA OVER ditto for 100mm Ø uPVC Class C bends [RM/Nr]

C Channel glazed vitrified clay half round 100mm Ø, 600mm long, straight, bedded and
jointed in cement and sand (1:3) mortar to bottom of manhole [RM/Nr].

Price Data (Delivered to site)

Material

100mm Ø uPVC drain pipe (supply length 6.00m long) –RM15/length

100mm Ø half round vitrified clay channel (supply length 300mm long) – RM3.00/nr

uPVC collar – RM5.00/Nr

Rubber ring – RM1.00/Nr

100mm Ø uPVC bend [300mm long] – RM8.00/Nr

Cement solvent (say) – RM1.00/joint

Labour

Drainlayer – RM10/hr

General labourer – RM7.50/hr

Gang size – 1 drain layer: 4 general labourers

Gang labour output

Laying and jointing drain pipes –0.55gang hr/length

Laying and jointing channel –0.30gang hr/manhole

Jointing bend– 0.23gang hr/joint

Overheads – 8%,

Profit – 2%
A Drain pipe, unplasticized polyvinyl chloride (uPVC) to BS 3526, size 100mm Ø, laid
and jointed with collar and rubber rings [RM/M]

[Take length of drain 6.00m]

A. Material

i. 100mm Ø uPVC drain pipe


1 length @RM15.00/length RM15.00

Allow for wastage – 2% RM 0.30 RM15.30

ii. 100mm Ø uPVC collar


1nr @RM5.00/nr RM 5.00

iii. 1nr rubber ring@RM1.00/nr RM 1.00

iv. Cement solvent per joint [say] RM 1.00 RM22.30

B. Plant & Equipments

Included in the preliminaries RM 0.00

C. Labour

Laying and jointing drain pipe


0.55gang hr/length@ [RM10.00/hr + 4(RM7.50/hr] RM22.00

RM44.30

Cost per metre – RM44.30 = RM7.38


6.00m

Allow for overheads – 8% RM0.59

Allow for profit – 2% RM0.15 RM0.74

Rate for this item/metre RM8.12


Extra over drain pipe, unplasticized polyvinyl chloride (uPVC) Class C to BS 3526, size 100mm
Ø laid and jointed with collars and rubber rings for 100mm Ø uPVC Class C bend [RM/Nr]

[Length of bend 300mm]

A. Material

i. 100mm Ø uPVC Class C bend


1 nr @RM8.00/nr RM 8.00

ii. Collar - 2 nr/bend @ RM5.00/nr RM10.00

iii. Rubber ring -4nr/bend @RM1.00/nr RM 4.00

iv. Cement solvent for 2 joints [say] RM 2.00 RM24.00

B. Plant & Equipments

Included in the preliminaries RM 0.00

C. Labour

Jointing bend
0.23gang hr/bend @ [RM10.00/hr + 4(RM7.50/hr] RM 9.20
RM33.20

Deduct drain pipes displaced by 300mm long bend


0.30m @RM7.38 RM 2.21
Extra over rate RM30.99

Allow for overhead – 8% RM2.48

Allow for profit – 2% RM0.62 RM 3.10

Rate for this item/nr RM34.09


C Channel glazed vitrified clay half round 100mm Ø, 600mm long, straight, bedded and
jointed in cement and sand (1:3) mortar to bottom of manhole [RM/Nr].

A. Material

i.100mm Ø half round glazed vitrified clay channel

|600mm| nr/manhole@RM3.00/nr RM6.00


|300mm|

ii.Unloading & Stacking

|2nr| hr/manhole @ RM7.50/hr RM0.30


|50.0nr|

iii.Cement and Sand (1:3) mortar per manhole RM1.00


for bedding & jointing channel (say) RM7.30

Allow for wastage [10%] RM0.73 RM8.03

B. Plant & Equipments

Included in the preliminaries RM 0.00

C. Labour

Bedding & jointing channel to bottom of manhole

0.30gang hr/manhole @ [RM10.00/hr + 4(RM7.50/hr] RM12.00


RM20.03

Allow for overhead – 8% RM1.60


Allow for profit – 2% RM0.40 RM 2.00

Rate for this item/nr RM22.03