You are on page 1of 76

ANALISA HARGA SATUAN PEKERJAAN MAKASAR

Kota : Makasar

No. URAIAN KOEFISIEN SAT HARGA SATUAN JUMLAH (RP)


I PEKERJAAN PERSIAPAN
1 1 M¹ PAGAR SENG GELOMBANG TINGGI : 2 M
a Tiang kayu borneo 4/6 0.05 m3 3,600,000.00 180,000.00
b Semen PC (abu-abu) 0.05 sak 42,000.00 2,100.00
c Seng gelombang 1.20 sak 53,800.00 64,560.00
d Pasir beton 0.01 m3 72,000.00 360.00
e Split (batu pecah) 0.01 m3 210,000.00 1,890.00
f Balok kayu borneo 4/6 0.05 m3 3,600,000.00 180,000.00
g Paku 5 - 10 cm 0.06 kg 14,700.00 882.00
h Meni Besi 0.45 kg 20,000.00 9,000.00
i Tukang kayu 0.20 org 55,000.00 11,000.00
j Pembantu tukang 0.10 org 40,000.00 4,000.00
Jumlah 453,792.00
Dibulatkan 453,790.00
2 1 M¹ PAGAR KAWAT BERDURI TINGGI : 1,8 M
a Tiang kayu borneo 4/6 0.05 m3 3,600,000.00 180,000.00
b Semen PC (abu-abu) 0.04 sak 42,000.00 1,680.00
c Kawat Duri 2.50 kg 166,000.00 415,000.00
d Pasir beton 0.01 m3 72,000.00 360.00
e Split (batu pecah) 0.01 m3 210,000.00 1,890.00
f Paku 5 - 10 cm 0.06 kg 14,700.00 882.00
g Tukang kayu 0.20 org 55,000.00 11,000.00
h Pembantu tukang 0.30 org 40,000.00 12,000.00
Jumlah 622,812.00
Dibulatkan 622,810.00
3 1 M1 PENGUKURAN & PEMASANGAN BOWPLANK
a Kayu kaso 5/7 borneo 0.02 m3 3,600,000.00 72,000.00
b Paku 5 - 10 cm 0.02 kg 14,700.00 294.00
c Papan papan kayu terentang 2/20 - m3 1,220,000.00 4,880.00
d Tukang kayu 0.10 org 55,000.00 5,500.00
e Pembantu tukang 0.10 org 40,000.00 4,000.00
Jumlah 86,674.00
Dibulatkan 86,670.00
4 1 M2 PEMBUATAN KANTOR DIREKSI
a Kayu kaso 5/7 borneo 0.02 m3 3,600,000.00 72,000.00
b Papan kayu terentang 0.18 m3 1,220,000.00 219,600.00
c Paku semua ukuran 0.85 kg 14,700.00 12,495.00
d Besi strip 1.10 kg 17,500.00 19,250.00
e Semen PC (abu-abu) 35.00 kg 42,000.00 1,470,000.00
f Pasir pasang 0.15 m3 68,000.00 10,200.00
g Pasir beton 0.10 m3 72,000.00 7,200.00
h Split (batu pecah) 0.15 m3 210,000.00 31,500.00
i Bata merah 30.00 bh 600.00 18,000.00
j Seng gelombang 180 x 90 x 0,05 cm 1.20 lbr 60,600.00 72,720.00
k Seng Plat BJLS 32 1.00 m2 33,000.00 33,000.00
l Kawat harmonika 2.00 m2 22,000.00 44,000.00
m Kaca polos 3 mm 0.08 m2 63,000.00 5,040.00
n Kunci tanam standart 0.15 bh 55,000.00 8,250.00
o Triplek 120 x 240 x 0,4 cm 0.06 lbr 51,000.00 3,060.00
p Tukang kayu 2.00 org 55,000.00 110,000.00
q Tukang batu 1.00 org 55,000.00 55,000.00
r Pembantu tukang 2.00 org 40,000.00 80,000.00
Jumlah 2,271,315.00
Dibulatkan 2,271,310.00
5 1 M2 PEMBUATAN GUDANG PROYEK
a Kayu kaso 5/7 borneo 0.02 m3 3,600,000.00 72,000.00
b Papan kayu terentang 0.10 m3 1,220,000.00 122,000.00
c Paku 0.30 kg 14,700.00 4,410.00
d Semen PC (abu-abu) 0.21 sak 42,000.00 8,820.00
e Pasir beton 0.03 m3 72,000.00 2,160.00
f Split (batu pecah) 0.05 m3 210,000.00 10,500.00
g Seng gelombang 180 x 90 x 0,05 cm 1.20 lbr 60,600.00 72,720.00
h Tukang kayu 1.00 org 55,000.00 55,000.00
i Pembantu tukang 1.00 org 40,000.00 40,000.00
Jumlah 387,610.00
Dibulatkan 387,610.00
6 1 M2 MEMBERSIHKAN LOKASI ROYEK
a Pembantu tukang 0.10 org 40,000.00 4,000.00
Jumlah 4,000.00
Dibulatkan 4,000.00
7 1 M2 MEMBERSIHKAN PUING-PUING
a Pembantu tukang 0.20 org 40,000.00 8,000.00
Jumlah 8,000.00
Dibulatkan 8,000.00
8 1 BH MEMBERSIHKAN TUNGGUL TANAMAN
a Pembantu tukang 2.00 org 40,000.00 80,000.00
Jumlah 80,000.00
Dibulatkan 80,000.00
9 1M2 PEMBUATAN JALAN MASUK PROYEK
a Batu belah 15/20 0.10 m3 72,000.00 7,200.00
b Koral 5/7 ( sirtu ) 0.05 m3 122,000.00 6,100.00
c Pasir urug 0.01 m3 66,000.00 660.00
d Pembantu tukang 1.00 org 40,000.00 40,000.00
Jumlah 53,960.00
Dibulatkan 53,900.00
10 1 M3 PEMBONGKARAN BETON
a Pembantu tukang 6.20 org 40,000.00 248,000.00
Jumlah 248,000.00
Dibulatkan 248,000.00
11 1 M3 PEMBONGKARAN DINDING BATA
a Pembantu tukang 4.60 org 40,000.00 184,000.00
Jumlah 184,000.00
Dibulatkan 184,000.00
12 1 M2 PEKERJAAN PAGAR PAPAN RANGKA BALOK
a Papan kayu borneo 0.02 m3 4,000,000.00 80,000.00
b Balok kayu borneo 5/7 0.02 m3 3,600,000.00 72,000.00
c Pasir beton 0.08 m3 72,000.00 5,760.00
d Split (batu pecah) 0.15 m3 210,000.00 31,500.00
e Semen abu - abu 0.50 sak 42,000.00 21,000.00
f Tukang kayu 0.13 org 55,000.00 7,150.00
g Pembantu tukang 0.38 org 40,000.00 15,200.00
Jumlah 232,610.00
Dibulatkan 232,600.00

II PEKERJAAN TANAH
1 1 M3 GALIAN TANAH SEDALAM 1 M
a Pembantu tukang 0.40 org 40,000.00 16,000.00
b Tukang gali 0.02 org 45,000.00 900.00
Jumlah 16,900.00
Dibulatkan 16,900.00
2 1 M3 GALIAN TANAH SEDALAM 2 M
a Pembantu tukang 0.53 org 40,000.00 21,200.00
b Tukang gali 0.02 org 45,000.00 900.00
Jumlah 22,100.00
Dibulatkan 22,100.00
3 1 M3 GALIAN TANAH SEDALAM 3 M
a Pembantu tukang 0.74 org 40,000.00 29,600.00
b Tukang gali 0.02 org 45,000.00 900.00
Jumlah 30,500.00
Dibulatkan 30,500.00
4 1 M3 GALIAN TANAH KERAS SEDALAM 1 M
a Pembantu tukang 0.45 org 40,000.00 18,000.00
b Tukang gali 0.02 org 45,000.00 900.00
Jumlah 18,900.00
Dibulatkan 18,900.00
5 1 M2 PEKERJAAN PENGUPASAN TANAH SETEBAL 10 CM
a Pembantu tukang 0.05 org 40,000.00 1,000.00
b Tukang gali 0.02 org 45,000.00 675.00
Jumlah 1,675.00
Dibulatkan 1,670.00
6 1 M3 PEMBUANGAN TANAH SEJAUH 150 M
a Pembantu tukang 0.42 org 40,000.00 16,800.00
b Tukang gali 0.02 org 45,000.00 900.00
Jumlah 17,700.00
Dibulatkan 17,700.00
7 1 M3 URUGAN TANAH KEMBALI
a Pembantu tukang 0.19 org 40,000.00 7,600.00
b Tukang gali 0.02 org 45,000.00 900.00
Jumlah 8,500.00
Dibulatkan 8,500.00
8 1 M3 PEMADATAN TANAH
a Pembantu tukang 0.50 org 40,000.00 20,000.00
b Tukang gali 0.02 org 45,000.00 900.00
Jumlah 20,900.00
Dibulatkan 20,900.00
9 1 M3 URUGAN PASIR
a Pasir urug 1.20 m3 66,000.00 79,200.00
b Pembantu tukang 0.30 org 40,000.00 12,000.00
c Tukang gali 0.02 org 45,000.00 900.00
Jumlah 92,100.00
Dibulatkan 92,100.00
10 1 M3 URUGAN TANAH
a Tanah urug 1.20 m3 70,000.00 84,000.00
b Pembantu tukang 0.30 org 40,000.00 12,000.00
c Tukang gali 0.02 org 45,000.00 900.00
Jumlah 96,900.00
Dibulatkan 96,900.00
11 1 M3 URUGAN SIRTU
a Sirtu ( koral ) 1.20 m3 122,000.00 146,400.00
b Pembantu tukang 0.25 org 40,000.00 10,000.00
c Tukang gali 0.02 org 45,000.00 900.00
Jumlah 157,300.00
Dibulatkan 157,300.00

III PEKERJAAN PONDASI


1 1 M3 PASANG PONDASI BT KALI , 1 Pc : 3 Ps
a Batu belah 1.10 m3 72,000.00 79,200.00
b Semen PC (abu-abu) 4.04 sak 42,000.00 169,680.00
c Pasir pasang 0.49 m3 68,000.00 32,980.00
d Pembantu tukang 1.50 org 40,000.00 60,000.00
e Tukang batu 0.60 org 55,000.00 33,000.00
Jumlah 374,860.00
Dibulatkan 374,860.00
2 1 M3 PASANG PONDASI BT KALI , 1 Pc : 4 Ps
a Batu belah 1.10 m3 72,000.00 79,200.00
b Semen PC (abu-abu) 3.26 sak 42,000.00 136,920.00
c Pasir pasang 0.52 m3 68,000.00 35,360.00
d Pembantu tukang 1.50 org 40,000.00 60,000.00
e Tukang batu 0.60 org 55,000.00 33,000.00
Jumlah 344,480.00
Dibulatkan 344,480.00
3 1 M3 PASANG PONDASI BT KALI , 1 Pc : 5 Ps
a Batu belah 1.10 m3 72,000.00 79,200.00
b Semen PC (abu-abu) 2.72 sak 42,000.00 114,240.00
c Pasir pasang 0.54 m3 68,000.00 36,992.00
d Pembantu tukang 1.50 org 40,000.00 60,000.00
e Tukang batu 0.60 org 55,000.00 33,000.00
Jumlah 323,432.00
Dibulatkan 323,430.00
4 1 M3 PASANG PONDASI BATU KOSONG ( AANSTAMPING )
a Batu belah 1.20 m3 72,000.00 86,400.00
b Pasir urug 0.30 m3 66,000.00 19,800.00
c Pembantu tukang 0.78 org 40,000.00 31,200.00
d Tukang batu 0.39 org 55,000.00 21,450.00
Jumlah 158,850.00
Dibulatkan 158,800.00
5 1 M3 MEMBUAT BETON BERTULANG UNTUK PONDASI 1 Pc : 2 Ps : 3 Kr
a Semen PC (abu-abu) 6.72 sak 42,000.00 282,240.00
b Pasir beton 0.54 m3 72,000.00 38,880.00
c Split (batu pecah) 0.81 m3 210,000.00 170,100.00
d Pembantu tukang 2.00 org 40,000.00 80,000.00
e Tukang batu 0.35 org 55,000.00 19,250.00
Jumlah 590,470.00
Dibulatkan 590,400.00
6 1 Kg PENULANGAN BETON PONDASI
a Besi beton polos 1.05 kg 8,800.00 9,240.00
b Kawat beton 0.02 kg 19,000.00 285.00
c Pembantu tukang 0.01 org 40,000.00 280.00
d Tukang besi 0.01 org 55,000.00 385.00
Jumlah 10,190.00
Dibulatkan 10,100.00
7 1 M2 PEKERJAAN BEKISTING UNTUK PONDASI
a Papan kayu terentang 0.04 m3 1,220,000.00 48,800.00
b Paku 5 - 12 cm 0.30 kg 1,925.00 577.50
c Pelumas begisting (oli/minyak) 0.10 Ltr 10,000.00 1,000.00
d Pembantu tukang 0.30 org 40,000.00 12,000.00
e Tukang kayu 0.26 org 55,000.00 14,300.00
Jumlah 76,677.50
Dibulatkan 76,600.00
8 1 M3 PASANG PONDASI CYCLOOP (60 %BETON : 40% BATU KALI)
a Besi beton polos 50.00 kg 8,800.00 440,000.00
b Semen PC (abu-abu) 4.04 sak 42,000.00 169,680.00
c Pasir beton 0.32 m3 72,000.00 23,040.00
d Split (batu pecah) 0.49 m3 210,000.00 102,900.00
e Kawat beton 0.80 kg 19,000.00 15,200.00
f Batu belah 0.40 m3 72,000.00 28,800.00
g Pembantu tukang 2.00 org 40,000.00 80,000.00
h Tukang batu 0.85 org 55,000.00 46,750.00
Jumlah 906,370.00
Dibulatkan 906,300.00
9 1 M3 PASANG PONDASI SUMURAN DIAMETER 100 cm
a Batu belah 0.45 m3 72,000.00 32,400.00
b Semen PC (abu-abu) 5.60 sak 42,000.00 235,200.00
3
c Pasir beton 0.45 m 72,000.00 32,400.00
d Split (batu pecah) 0.67 m3 210,000.00 140,700.00
e Pembantu tukang 2.38 org 40,000.00 95,200.00
f Tukang batu 0.30 org 55,000.00 16,500.00
Jumlah 552,400.00
Dibulatkan 552,400.00
10 1 M¹ PEMBUATAN PONDASI TIANG BETON BERTULANG UKURAN 40 X 40 Cm
a Pasir beton 0.10 m3 72,000.00 7,200.00
3
b Split (batu pecah) 0.15 m 210,000.00 31,500.00
c Semen PC (abu-abu) 1.21 sak 42,000.00 50,820.00
d Besi beton polos 45.00 kg 8,800.00 396,000.00
e Kawat beton 0.90 kg 19,000.00 17,100.00
3
f Balok kayu borneo super 5/7 0.03 m 3,600,000.00 115,200.00
g Papan kayu terentang 0.01 m3 4,000,000.00 40,000.00
h Paku 5 - 12 cm 0.12 kg 14,700.00 1,764.00
i Pelumas begisting (oli/minyak) 0.09 Ltr 10,000.00 900.00
j Plamir tembok 0.24 kg 27,000.00 6,480.00
k Pembantu tukang 1.00 org 40,000.00 40,000.00
l Tukang batu 0.67 org 55,000.00 36,850.00
Jumlah 743,814.00
Dibulatkan 743,800.00
11 1 M¹ PEMBUATAN PONDASI TIANG BETON BERTULANG UKURAN 35 X 35 CM
a Pasir beton 0.08 m3 72,000.00 5,760.00
3
b Split (batu pecah) 0.13 m 210,000.00 27,300.00
c Semen PC (abu-abu) 0.98 sak 42,000.00 41,160.00
d Besi beton polos 34.50 kg 8,800.00 303,600.00
e Kawat beton 0.70 kg 19,000.00 13,300.00
f Balok kayu borneo super 5/7 0.03 m3 3,600,000.00 108,000.00
3
g Papan kayu terentang 0.01 m 4,000,000.00 40,000.00
h Paku 5 - 12 cm 0.12 kg 14,700.00 1,764.00
i Pelumas begisting (oli/minyak) 0.09 Ltr 10,000.00 900.00
j Plamir tembok 0.20 kg 27,000.00 5,400.00
k Pembantu tukang 0.80 org 40,000.00 32,000.00
l Tukang batu 0.50 org 55,000.00 27,500.00
Jumlah 606,684.00
Dibulatkan 606,600.00
12 1 M3 MEMBUAT PONDASI TIANG PANCANG UKURAN 25 X 25
a Pasir beton 0.06 m3 72,000.00 4,320.00
3
b Split (batu pecah) 0.11 m 210,000.00 23,100.00
c Semen PC (abu-abu) 0.82 sak 42,000.00 34,440.00
d Besi beton polos 34.50 kg 8,800.00 303,600.00
e Kawat beton 0.60 kg 19,000.00 11,400.00
3
f Balok kayu borneo super 5/7 0.03 m 3,600,000.00 108,000.00
g Papan kayu terentang 0.01 m3 4,000,000.00 40,000.00
h Paku 5 - 12 cm 0.11 kg 14,700.00 1,617.00
i Pelumas begisting (oli/minyak) 0.08 Ltr 10,000.00 800.00
j Plamir tembok 0.20 kg 27,000.00 5,400.00
k Pembantu tukang 0.80 org 40,000.00 32,000.00
l Tukang batu 0.50 org 55,000.00 27,500.00
Jumlah 592,177.00
Dibulatkan 592,100.00
13 1 M3 MEMBUAT PONDASI PLAT BETON (PENULANGAN 125 kg + BEKISTING )
a Papan kayu terentang 0.20 m3 1,220,000.00 244,000.00
b Paku 5 - 12 cm 1.50 kg 14,700.00 22,050.00
c Pelumas begisting (oli/minyak) 0.40 Ltr 10,000.00 4,000.00
d Besi beton polos 125.00 kg 8,800.00 1,100,000.00
e Kawat beton 2.25 kg 19,000.00 42,750.00
f Semen PC (abu-abu) 6.46 sak 42,000.00 271,320.00
3
g Pasir beton 0.52 m 72,000.00 37,440.00
3
h Split (batu pecah) 0.78 m 210,000.00 163,800.00
i Pembantu tukang 3.90 org 40,000.00 156,000.00
j Tukang batu 0.35 org 55,000.00 19,250.00
k Tukang kayu 1.04 org 55,000.00 57,200.00
l Tukang besi 1.05 org 55,000.00 57,750.00
Jumlah 2,175,560.00
Dibulatkan 2,175,500.00
14 1 M3 MEMBUAT PONDASI PLAT BETON (PENULANGAN 150 kg + BEKISTING )
a Papan kayu terentang 0.20 m3 1,220,000.00 244,000.00
b Paku 5 - 12 cm 1.50 kg 14,700.00 22,050.00
c Pelumas begisting (oli/minyak) 0.40 ltr 10,000.00 4,000.00
d Besi beton polos Polos 150.00 kg 8,800.00 1,320,000.00
e Kawat beton 2.25 kg 19,000.00 42,750.00
f Semen PC (abu-abu) 6.46 sak 42,000.00 271,320.00
g Pasir beton 0.52 m3 72,000.00 37,440.00
3
h Split (batu pecah) 0.78 m 210,000.00 163,800.00
i Pembantu tukang 4.00 org 40,000.00 160,000.00
j Tukang batu 0.40 org 55,000.00 22,000.00
k Tukang kayu 1.00 org 55,000.00 55,000.00
l Tukang besi 1.00 org 55,000.00 55,000.00
Jumlah 2,397,360.00
Dibulatkan 2,397,300.00
15 1 M3 MEMBUAT PONDASI BETON BOREPILE (PENULANGAN 125 kg + BEKISTING )
a Papan kayu terentang 0.20 m3 1,220,000.00 244,000.00
b Paku 5 - 12 cm 1.50 kg 14,700.00 22,050.00
c Pelumas begisting (oli/minyak) 0.40 ltr 10,000.00 4,000.00
d Besi beton polos Polos 125.00 kg 8,800.00 1,100,000.00
e Kawat beton 2.10 kg 19,000.00 39,900.00
f Semen PC (abu-abu) 6.46 sak 42,000.00 271,320.00
3
g Pasir beton 0.52 m 72,000.00 37,440.00
3
h Split (batu pecah) 0.78 m 210,000.00 163,800.00
i Pembantu tukang 3.90 org 40,000.00 156,000.00
j Tukang batu 0.40 org 55,000.00 22,000.00
k Tukang kayu 1.00 org 55,000.00 55,000.00
l Tukang besi 1.00 org 55,000.00 55,000.00
Jumlah 2,170,510.00
Dibulatkan 2,170,500.00
16 1 M3 MEMBUAT PONDASI BETON BOREPILE (PENULANGAN 150 kg + BEKISTING )
a Papan kayu terentang 0.20 m3 1,220,000.00 244,000.00
b Paku 5 - 12 cm 1.50 kg 14,700.00 22,050.00
c Pelumas begisting (oli/minyak) 0.40 ltr 10,000.00 4,000.00
d Besi beton polos 150.00 kg 8,800.00 1,320,000.00
e Kawat beton 2.25 kg 19,000.00 42,750.00
f Semen PC (abu-abu) 6.46 sak 42,000.00 271,320.00
g Pasir beton 0.52 m3 72,000.00 37,440.00
3
h Split (batu pecah) 0.78 m 210,000.00 163,800.00
i Pembantu tukang 4.00 org 40,000.00 160,000.00
j Tukang batu 0.40 org 55,000.00 22,000.00
k Tukang kayu 1.00 org 55,000.00 55,000.00
l Tukang besi 1.00 org 55,000.00 55,000.00
Jumlah 2,397,360.00
Dibulatkan 2,397,300.00

PEKERJAAN BETON NON STRUKTUR DAN BETON


IV
STRUKTUR
A PEKERJAAN BETON
1 1 M3 MEMBUAT BETON NON STRUKTUR, 1 Pc : 3 Ps : 5 Splt
a Semen PC (abu-abu) 4.36 sak 42,000.00 183,120.00
b Pasir beton 0.52 m3 72,000.00 37,440.00
c Split (batu pecah) 0.87 m3 210,000.00 182,700.00
d Pembantu tukang 2.00 org 40,000.00 80,000.00
e Tukang batu 0.35 org 55,000.00 19,250.00
Jumlah 502,510.00
Dibulatkan 502,500.00
2 1 M3 MEMBUAT BETON STRUKTUR 1 Pc : 2 Ps : 4 Splt
a Semen PC (abu-abu) 4.64 sak 42,000.00 194,880.00
b Pasir beton 0.52 m3 72,000.00 37,440.00
c Split (batu pecah) 0.78 m3 210,000.00 163,800.00
d Pembantu tukang 2.00 org 40,000.00 80,000.00
e Tukang batu 0.35 org 55,000.00 19,250.00
Jumlah 495,370.00
Dibulatkan 495,300.00
3 1 M3 MEMBUAT BETON STRUKTUR 1 Pc : 2 Ps : 3 Splt
a Semen PC (abu-abu) 6.72 sak 42,000.00 282,240.00
b Pasir beton 0.54 m3 72,000.00 38,880.00
c Split (batu pecah) 0.81 m3 210,000.00 170,100.00
d Pembantu tukang 2.00 org 40,000.00 80,000.00
e Tukang batu 0.35 org 55,000.00 19,250.00
Jumlah 590,470.00
Dibulatkan 590,400.00
4 1 M3 MEMBUAT BETON STRUKTUR DENGAN MUTU K 225
a Semen PC (abu-abu) 7.76 sak 42,000.00 325,920.00
b Pasir beton 0.65 m3 72,000.00 46,800.00
c Split (batu pecah) 0.65 m3 210,000.00 136,500.00
d Pembantu tukang 2.00 org 40,000.00 80,000.00
e Tukang batu 0.35 org 55,000.00 19,250.00
Jumlah 608,470.00
Dibulatkan 608,400.00
5 1 M3 MEMBUAT BETON STRUKTUR DENGAN MUTU K 275
a Semen PC (abu-abu) 8.00 sak 42,000.00 336,000.00
b Pasir beton 0.55 m3 72,000.00 39,600.00
c Split (batu pecah) 0.70 m3 210,000.00 147,000.00
d Pembantu tukang 2.02 org 40,000.00 80,800.00
e Tukang batu 0.40 org 55,000.00 22,000.00
Jumlah 625,400.00
Dibulatkan 625,400.00
B PEKERJAAN PEMBESIAN
1 1 KG PENULANGAN BETON/BESI BETON POLOS
a Besi beton polos 1.05 kg 8,800.00 9,240.00
b Kawat beton 0.02 kg 19,000.00 380.00
c Pembantu tukang 0.01 org 40,000.00 400.00
d Tukang besi 0.01 org 55,000.00 550.00
Jumlah 10,570.00
Dibulatkan 10,500.00
2 1 KG PENULANGAN BETON/BESI BETON ULIR
a Besi Beton Ulir 1.10 kg 16,300.00 17,930.00
b Kawat beton 0.02 kg 19,000.00 285.00
c Pembantu tukang 0.01 org 40,000.00 400.00
d Tukang besi 0.02 org 55,000.00 1,100.00
Jumlah 19,715.00
Dibulatkan 19,700.00
C PEKERJAAN BEGISTING
1 1 M2 PASANG BEKISTING UNTUK SLOOF
a Papan kayu terentang 0.05 m3 1,220,000.00 54,900.00
b Paku 5 - 12 cm 0.30 kg 14,700.00 4,410.00
c Pelumas begisting (oli/minyak) 0.10 Ltr 10,000.00 1,000.00
d Pembantu tukang 0.30 org 40,000.00 12,000.00
e Tukang kayu 0.26 org 55,000.00 14,300.00
Jumlah 86,610.00
Dibulatkan 86,600.00
2 1 M2 PASANG BEKISTING UNTUK KOLOM
a Papan kayu terentang 0.04 m3 1,220,000.00 48,800.00
b Paku 5 - 12 cm 0.40 kg 14,700.00 5,880.00
c Pelumas begisting (oli/minyak) 0.20 Ltr 10,000.00 2,000.00
d Balok Kayu Borneo 0.04 m3 3,600,000.00 144,000.00
e Multiplex 120 x 240 x 9 mm 0.35 lbr 105,000.00 36,750.00
f Pembantu tukang 0.30 org 40,000.00 12,000.00
g Tukang kayu 0.33 org 55,000.00 18,150.00
Jumlah 267,580.00
Dibulatkan 267,500.00
3 1M2 PASANG BEKISTING UNTUK BALOK
a Papan kayu terentang 0.04 m3 1,220,000.00 48,800.00
b Paku 5 - 12 cm 0.40 kg 14,700.00 5,880.00
c Pelumas begisting (oli/minyak) 0.20 Ltr 10,000.00 2,000.00
d Balok Kayu Borneo 0.04 m3 3,600,000.00 144,000.00
e Multiplex 120 x 240 x 9 mm 0.35 lbr 105,000.00 36,750.00
f Pembantu tukang 0.32 org 40,000.00 12,800.00
g Tukang kayu 0.33 org 55,000.00 18,150.00
Jumlah 268,380.00
Dibulatkan 268,300.00
4 1 M2 PASANG BEKISTING UNTUK PLAT LANTAI
a Papan kayu terentang 0.04 m3 1,220,000.00 48,800.00
b Paku 5 - 12 cm 0.40 kg 14,700.00 5,880.00
c Pelumas begisting (oli/minyak) 0.20 Ltr 10,000.00 2,000.00
d Balok Kayu Borneo 0.04 m3 3,600,000.00 144,000.00
e Multiplex 120 x 240 x 9 mm 0.35 lbr 105,000.00 36,750.00
f Pembantu tukang 0.32 org 40,000.00 12,800.00
g Tukang kayu 0.33 org 55,000.00 18,150.00
Jumlah 268,380.00
Dibulatkan 268,300.00
5 1 M2 PASANG BEKISTING UNTUK TANGGA
a Papan kayu terentang 0.03 m3 1,220,000.00 36,600.00
b Paku 5 - 12 cm 0.40 kg 14,700.00 5,880.00
c Pelumas begisting (oli/minyak) 0.15 Ltr 10,000.00 1,500.00
d Balok kayu borneo 0.02 m3 3,600,000.00 72,000.00
e Multiplex 120 x 240 x 9 mm 0.35 lbr 105,000.00 36,750.00
f Pembantu tukang 0.32 org 40,000.00 12,800.00
g Tukang kayu 0.33 org 55,000.00 18,150.00
Jumlah 183,680.00
Dibulatkan 183,600.00
D PEKERJAAN BETON BERTULANG
1 1 M3 MEMBUAT SLOOF BETON BERTULANG ( 200 kg BESI + BEKISTING ) K225
a Papan kayu terentang 0.27 m3 1,220,000.00 329,400.00
b Paku 5 - 12 cm 2.00 kg 14,700.00 29,400.00
c Pelumas begisting (oli/minyak) 0.60 Ltr 10,000.00 6,000.00
d Besi beton polos 200.00 kg 8,800.00 1,760,000.00
e Kawat beton 3.00 kg 19,000.00 57,000.00
f Semen PC (abu-abu) 8.00 sak 42,000.00 336,000.00
3
g Pasir beton 0.52 m 72,000.00 37,440.00
3
h Split (batu pecah) 0.78 m 210,000.00 163,800.00
i Pembantu tukang 4.50 org 40,000.00 180,000.00
j Tukang batu 0.35 org 55,000.00 19,250.00
k Tukang kayu 1.56 org 55,000.00 85,800.00
l Tukang besi 1.40 org 55,000.00 77,000.00
Jumlah 3,081,090.00
Dibulatkan 3,081,000.00
2 1 M3 MEMBUAT KOLOM BETON BERTULANG ( 125 kg BESI + BEKISTING )
a Papan kayu terentang 0.40 m3 1,220,000.00 488,000.00
b Paku 5 - 12 cm 4.00 kg 14,700.00 58,800.00
c Pelumas begisting (oli/minyak) 2.00 Ltr 10,000.00 20,000.00
d Besi beton polos 125.00 kg 8,800.00 1,100,000.00
e Kawat beton 4.50 kg 19,000.00 85,500.00
f Semen PC (abu-abu) 6.45 sak 42,000.00 270,900.00
g Pasir beton 0.52 m3 72,000.00 37,440.00
h Split (batu pecah) 0.78 m3 210,000.00 163,800.00
i Balok kayu Borneo Super 0.30 m3 3,600,000.00 1,080,000.00
j Multiplex 120 x 240 x 9 mm 3.50 lbr 105,000.00 367,500.00
k Pembantu tukang 7.30 org 40,000.00 292,000.00
l Tukang batu 0.35 org 55,000.00 19,250.00
m Tukang kayu 3.30 org 55,000.00 181,500.00
n Tukang besi 2.10 org 55,000.00 115,500.00
Jumlah 4,280,190.00
Dibulatkan 4,280,100.00
3 1 M3 MEMBUAT KOLOM BETON BERTULANG (150 kg BESI + BEKISTING)
a Papan kayu terentang 0.40 m3 1,220,000.00 488,000.00
b Paku 5 - 12 cm 4.00 kg 14,700.00 58,800.00
c Pelumas begisting (oli/minyak) 2.00 Ltr 10,000.00 20,000.00
d Besi beton polos 150.00 kg 8,800.00 1,320,000.00
e Kawat beton 4.50 kg 19,000.00 85,500.00
f Semen PC (abu-abu) 6.45 sak 42,000.00 270,900.00
g Pasir beton 0.52 m3 72,000.00 37,440.00
h Split (batu pecah) 0.78 m3 210,000.00 163,800.00
i Balok kayu Borneo Super 0.30 m3 3,600,000.00 1,080,000.00
j Multiplex 120 x 240 x 9 mm 3.50 lbr 105,000.00 367,500.00
k Pembantu tukang 7.30 org 40,000.00 292,000.00
l Tukang batu 0.35 org 55,000.00 19,250.00
m Tukang kayu 3.30 org 55,000.00 181,500.00
n Tukang besi 2.10 org 55,000.00 115,500.00
Jumlah 4,500,190.00
Dibulatkan 4,500,100.00
4 1 M3 MEMBUAT KOLOM BETON BERTULANG ( 160 kg BESI + BEKISTING )
a Papan kayu terentang 0.40 m3 1,220,000.00 488,000.00
b Paku 5 - 12 cm 4.00 kg 14,700.00 58,800.00
c Pelumas begisting (oli/minyak) 2.00 Ltr 10,000.00 20,000.00
d Besi beton polos 160.00 kg 8,800.00 1,408,000.00
e Kawat beton 4.50 kg 19,000.00 85,500.00
f Semen PC (abu-abu) 6.45 sak 42,000.00 270,900.00
g Pasir beton 0.52 m3 72,000.00 37,440.00
h Split (batu pecah) 0.78 m3 210,000.00 163,800.00
i Balok kayu Borneo Super 0.30 m3 3,600,000.00 1,080,000.00
j Multiplex 120 x 240 x 9 mm 3.50 lbr 105,000.00 367,500.00
k Pembantu tukang 7.30 org 40,000.00 292,000.00
l Tukang batu 0.35 org 55,000.00 19,250.00
m Tukang kayu 3.30 org 55,000.00 181,500.00
n Tukang besi 2.10 org 55,000.00 115,500.00
Jumlah 4,588,190.00
Dibulatkan 4,588,100.00
5 1 M3 MEMBUAT KOLOM BETON BERTULANG ( 175 kg BESI + BEKISTING )
a Papan kayu terentang 0.40 m3 1,220,000.00 488,000.00
b Paku 5 - 12 cm 4.00 kg 14,700.00 58,800.00
c Pelumas begisting (oli/minyak) 2.00 Ltr 10,000.00 20,000.00
d Besi beton polos 175.00 kg 8,800.00 1,540,000.00
e Kawat beton 4.50 kg 19,000.00 85,500.00
f Semen PC (abu-abu) 6.45 sak 42,000.00 270,900.00
g Pasir beton 0.52 m3 72,000.00 37,440.00
h Split (batu pecah) 0.78 m3 210,000.00 163,800.00
i Balok kayu Borneo Super 0.30 m3 3,600,000.00 1,080,000.00
j Multiplex 120 x 240 x 9 mm 3.50 lbr 105,000.00 367,500.00
k Pembantu tukang 7.30 org 40,000.00 292,000.00
l Tukang batu 0.35 org 55,000.00 19,250.00
m Tukang kayu 3.30 org 55,000.00 181,500.00
n Tukang besi 2.10 org 55,000.00 115,500.00
Jumlah 4,720,190.00
Dibulatkan 4,720,100.00
6 1 M3 MEMBUAT KOLOM BETON BERTULANG ( 200 kg BESI + BEKISTING )
a Papan kayu terentang 0.40 m3 1,220,000.00 488,000.00
b Paku 5 - 12 cm 4.00 kg 14,700.00 58,800.00
c Pelumas begisting (oli/minyak) 2.00 Ltr 10,000.00 20,000.00
d Besi beton polos 200.00 kg 8,800.00 1,760,000.00
e Kawat beton 4.50 kg 19,000.00 85,500.00
f Semen PC (abu-abu) 6.45 sak 42,000.00 270,900.00
g Pasir beton 0.52 m3 72,000.00 37,440.00
h Split (batu pecah) 0.78 m3 210,000.00 163,800.00
i Balok kayu Borneo Super 0.30 m3 3,600,000.00 1,080,000.00
j Multiplex 120 x 240 x 9 mm 3.50 lbr 105,000.00 367,500.00
k Pembantu tukang 7.30 org 40,000.00 292,000.00
l Tukang batu 0.35 org 55,000.00 19,250.00
m Tukang kayu 3.30 org 55,000.00 181,500.00
n Tukang besi 2.10 org 55,000.00 115,500.00
Jumlah 4,940,190.00
Dibulatkan 4,940,100.00
7 1 M3 MEMBUAT KOLOM BETON BERTULANG ( 250 kg BESI + BEKISTING )
a Papan kayu terentang 0.40 m3 1,220,000.00 488,000.00
b Paku 5 - 12 cm 4.00 kg 14,700.00 58,800.00
c Pelumas begisting (oli/minyak) 2.00 Ltr 10,000.00 20,000.00
d Besi beton polos 250.00 kg 8,800.00 2,200,000.00
e Kawat beton 4.50 kg 19,000.00 85,500.00
f Semen PC (abu-abu) 6.45 sak 42,000.00 270,900.00
g Pasir beton 0.52 m3 72,000.00 37,440.00
h Split (batu pecah) 0.78 m3 210,000.00 163,800.00
i Balok kayu Borneo Super 0.30 m3 3,600,000.00 1,080,000.00
j Multiplex 120 x 240 x 9 mm 3.50 lbr 105,000.00 367,500.00
k Pembantu tukang 7.30 org 40,000.00 292,000.00
l Tukang batu 0.35 org 55,000.00 19,250.00
m Tukang kayu 3.30 org 55,000.00 181,500.00
n Tukang besi 2.10 org 55,000.00 115,500.00
Jumlah 5,380,190.00
Dibulatkan 5,380,100.00
8 1 M3 MEMBUAT KOLOM BETON BERTULANG ( 300 kg BESI + BEKISTING )
a Papan kayu terentang 0.40 m3 1,220,000.00 488,000.00
b Paku 5 - 12 cm 4.00 kg 14,700.00 58,800.00
c Pelumas begisting (oli/minyak) 2.00 Ltr 10,000.00 20,000.00
d Besi beton polos 300.00 kg 8,800.00 2,640,000.00
e Kawat beton 4.50 kg 19,000.00 85,500.00
f Semen PC (abu-abu) 6.45 sak 42,000.00 270,900.00
g Pasir beton 0.52 m3 72,000.00 37,440.00
h Split (batu pecah) 0.78 m3 210,000.00 163,800.00
i Balok kayu Borneo Super 0.30 m3 3,600,000.00 1,080,000.00
j Multiplex 120 x 240 x 9 mm 3.50 lbr 105,000.00 367,500.00
k Pembantu tukang 7.30 org 40,000.00 292,000.00
l Tukang batu 0.35 org 55,000.00 19,250.00
m Tukang kayu 3.30 org 55,000.00 181,500.00
n Tukang besi 2.10 org 55,000.00 115,500.00
Jumlah 5,820,190.00
Dibulatkan 5,820,100.00
9 1 M3 MEMBUAT BALOK BETON BERTULANG ( 125 kg BESI + BEKISTING )
a Papan kayu terentang 0.32 m3 1,220,000.00 390,400.00
b Paku 5 - 12 cm 3.20 kg 14,700.00 47,040.00
c Pelumas begisting (oli/minyak) 1.60 Ltr 10,000.00 16,000.00
d Besi beton polos 125.00 kg 8,800.00 1,100,000.00
e Kawat beton 2.25 kg 19,000.00 42,750.00
f Semen PC (abu-abu) 6.45 sak 42,000.00 270,900.00
g Pasir beton 0.52 m3 72,000.00 37,440.00
h Split (batu pecah) 0.78 m3 210,000.00 163,800.00
i Balok kayu Borneo Super 0.12 m3 3,600,000.00 432,000.00
j Multiplex 120 x 240 x 9 mm 2.80 lbr 105,000.00 294,000.00
k Dolken Ø-8 Cm atau kayu 4 x 6 cm / 4m 32.00 btg 8,500.00 272,000.00
l Pembantu tukang 5.80 org 40,000.00 232,000.00
m Tukang batu 0.35 org 55,000.00 19,250.00
n Tukang kayu 2.80 org 55,000.00 154,000.00
o Tukang besi 1.05 org 55,000.00 57,750.00
Jumlah 3,529,330.00
Dibulatkan 3,529,300.00
10 1 M3 MEMBUAT BALOK BETON BERTULANG ( 150 kg BESI + BEKISTING )
a Papan kayu terentang 0.32 m3 1,220,000.00 390,400.00
b Paku 5 - 12 cm 3.20 kg 14,700.00 47,040.00
c Pelumas begisting (oli/minyak) 1.60 Ltr 10,000.00 16,000.00
d Besi beton polos 150.00 kg 8,800.00 1,320,000.00
e Kawat beton 2.25 kg 10,000.00 22,500.00
f Semen PC (abu-abu) 6.45 sak 42,000.00 270,900.00
g Pasir beton 0.52 m3 72,000.00 37,440.00
h Split (batu pecah) 0.78 m3 10,000.00 7,800.00
i Balok kayu Borneo Super 0.12 m3 3,600,000.00 432,000.00
j Multiplex 120 x 240 x 9 mm 2.80 lbr 105,000.00 294,000.00
k Dolken Ø-8 Cm atau kayu 4 x 6 cm / 4m 32.00 btg 8,500.00 272,000.00
l Pembantu tukang 5.80 org 40,000.00 232,000.00
m Tukang batu 0.35 org 55,000.00 19,250.00
n Tukang kayu 2.80 org 55,000.00 154,000.00
o Tukang besi 1.05 org 55,000.00 57,750.00
Jumlah 3,573,080.00
Dibulatkan 3,573,000.00
11 1 M3 MEMBUAT BALOK BETON BERTULANG ( 200 kg BESI + BEKISTING )
a Papan kayu terentang 0.32 m3 1,220,000.00 390,400.00
b Paku 5 - 12 cm 3.20 kg 14,700.00 47,040.00
c Pelumas begisting (oli/minyak) 1.60 Ltr 10,000.00 16,000.00
d Besi beton polos 200.00 kg 8,800.00 1,760,000.00
e Kawat beton 3.00 kg 19,000.00 57,000.00
f Semen PC (abu-abu) 6.45 sak 42,000.00 270,900.00
g Pasir beton 0.52 m3 72,000.00 37,440.00
h Split (batu pecah) 0.78 m3 140,000.00 109200
i Balok kayu Borneo Super 0.14 m3 4,000,000.00 560,000.00
j Multiplex 120 x 240 x 9 mm 2.80 lbr 105,000.00 294,000.00
k Dolken Ø-8 Cm atau kayu 4 x 6 cm / 4m 16.00 btg 18,000.00 288,000.00
l Pembantu tukang 5.96 org 27,500.00 163,900.00
m Tukang batu 0.35 org 42,000.00 14,700.00
n Tukang kayu 2.80 org 42,000.00 117,600.00
o Tukang besi 1.40 org 42,000.00 58,800.00
Jumlah 4,184,980.00
Dibulatkan 4,184,900.00
12 1 M3 MEMBUAT BALOK BETON BERTULANG (200 kg BESI + BEKISTING)
a Papan kayu terentang 0.32 m3 1,750,000.00 560,000.00
b Paku 5 - 12 cm 3.20 kg 14,700.00 47,040.00
c Pelumas begisting (oli/minyak) 1.60 Ltr 10,000.00 16,000.00
d Besi beton polos 225.00 kg 8,750.00 1,968,750.00
e Kawat beton 4.00 kg 15,000.00 60,000.00
f Semen PC (abu-abu) 6.45 sak 49,500.00 319,275.00
g Pasir beton 0.52 m3 140,000.00 72,800.00
3
h Split (batu pecah) 0.78 m 140,000.00 109,200.00
3
i Balok kayu Borneo Super 0.14 m 4,000,000.00 560,000.00
j Multiplex 120 x 240 x 9 mm 2.80 lbr 105,000.00 294,000.00
k Dolken Ø-8 Cm atau kayu 4 x 6 cm / 4m 16.00 btg 8,500.00 136,000.00
l Pembantu tukang 5.96 org 40,000.00 238,400.00
m Tukang batu 0.35 org 55,000.00 19,250.00
n Tukang kayu 2.80 org 55,000.00 154,000.00
o Tukang besi 1.40 org 55,000.00 77,000.00
Jumlah 4,631,715.00
Dibulatkan 4,631,700.00
13 1 M3 MEMBUAT BALOK BETON BERTULANG ( 250 kg BESI + BEKISTING )
a Papan kayu terentang 0.32 m3 1,220,000.00 390,400.00
b Paku 5 - 12 cm 3.20 kg 14,700.00 47,040.00
c Pelumas begisting (oli/minyak) 1.60 Ltr 10,000.00 16,000.00
d Besi beton polos 250.00 kg 8,800.00 2,200,000.00
e Kawat beton 6.00 kg 19,000.00 114,000.00
f Semen PC (abu-abu) 6.45 sak 42,000.00 270,900.00
3
g Pasir beton 0.52 m 72,000.00 37,440.00
3
h Split (batu pecah) 0.78 m 210,000.00 163,800.00
i Balok kayu Borneo Super 0.14 m3 3,600,000.00 504,000.00
j Multiplex 120 x 240 x 9 mm 2.80 lbr 105,000.00 294,000.00
k Dolken Ø-8 Cm atau kayu 4 x 6 cm / 4m 16.00 btg 8,500.00 136,000.00
l Pembantu tukang 5.96 org 40,000.00 238,400.00
m Tukang batu 0.35 org 55,000.00 19,250.00
n Tukang kayu 2.80 org 55,000.00 154,000.00
o Tukang besi 1.40 org 55,000.00 77,000.00
Jumlah 4,662,230.00
Dibulatkan 4,662,200.00
14 1 M3 MEMBUAT TANGGA BETON BERTULANG ( 200 kg BESI + BEKISTING )
a Papan kayu terentang 0.25 m3 1,220,000.00 305,000.00
b Paku 5 - 12 cm 3.00 kg 14,700.00 44,100.00
c Pelumas begisting (oli/minyak) 1.20 Ltr 10,000.00 12,000.00
d Besi beton polos 200.00 kg 8,800.00 1,760,000.00
e Kawat beton 3.00 kg 19,000.00 57,000.00
f Semen PC (abu-abu) 6.45 sak 42,000.00 270,900.00
3
g Pasir beton 0.52 m 72,000.00 37,440.00
3
h Split (batu pecah) 0.78 m 210,000.00 163,800.00
i Balok kayu Borneo Super 0.30 m3 3,600,000.00 1,080,000.00
j Multiplex 120 x 240 x 9 mm 2.50 lbr 105,000.00 262,500.00
k Pembantu tukang 5.60 org 40,000.00 224,000.00
l Tukang batu 0.35 org 55,000.00 19,250.00
m Tukang kayu 2.30 org 55,000.00 126,500.00
n Tukang besi 1.40 org 55,000.00 77,000.00
Jumlah 4,439,490.00
Dibulatkan 4,439,400.00
15 1 M3 MEMBUAT PLAT LANTAI Tb. 10 Cm BETON BERTULANG ( 100 kg BESI + BEKISTING )
a Beton bertulang camp. 1Pc : 2 Ps : 3 Kr 1.00 m3 590,400.00 590,400.00
2
b Pasang Bekisting untuk lantai 10.00 m 268,300.00 2,683,000.00
c Besi Beton rakit 100.00 kg 8,800.00 880,000.00
Jumlah 4,153,400.00
Dibulatkan 4,153,400.00
16 1 M3 MEMBUAT PLAT LANTAI Tb. 12 Cm BETON BERTULANG ( 115 kg BESI + BEKISTING )
a Beton bertulang camp. 1Pc : 2 Ps : 3 Kr 1.00 m3 590,400.00 590,400.00
b Pasang Bekisting untuk lantai 8.33 m2 268,300.00 2,234,939.00
c Besi Beton rakit 115.00 kg 10,500.00 1,207,500.00
Jumlah 4,032,839.00
Dibulatkan 4,032,800.00
17 1 M3 MEMBUAT PLAT LANTAI Tb. 12 Cm BETON BERTULANG ( 125 kg BESI + BEKISTING )
a Beton bertulang camp. 1Pc : 2 Ps : 3 Kr 1.00 m3 590,400.00 590,400.00
b Pasang Bekisting untuk lantai 8.33 m2 268,300.00 2,234,939.00
c Besi Beton rakit 125.00 kg 10,500.00 1,312,500.00
Jumlah 4,137,839.00
Dibulatkan 4,137,800.00
18 1 M3 MEMBUAT PLAT LANTAI Tb. 15 Cm BETON BERTULANG ( 100 kg BESI + BEKISTING )
a Beton bertulang camp. 1Pc : 2 Ps : 3 Kr 1.00 m3 590,400.00 590,400.00
b Pasang Bekisting untuk lantai 6.67 m2 268,300.00 1,789,561.00
c Besi Beton rakit 100.00 kg 10,500.00 1,050,000.00
Jumlah 3,429,961.00
Dibulatkan 3,429,900.00
19 1 M3 MEMBUAT PLAT LANTAI Tb. 20 Cm BETON BERTULANG ( 115 kg BESI + BEKISTING )
a Beton bertulang camp. 1Pc : 2 Ps : 3 Kr 1.00 m3 590,400.00 590,400.00
b Pasang Bekisting untuk lantai 7.50 m2 268,300.00 2,012,250.00
c Besi Beton rakit 115.00 kg 10,500.00 1,207,500.00
Jumlah 3,810,150.00
Dibulatkan 3,810,100.00
20 1M3 MEMBUAT RING BALK BETON BERTULANG ( 175 kg BESI + BEKISTING ) K225
a Papan kayu terentang 0.27 m3 1,220,000.00 329,400.00
b Paku 5 - 12 cm 2.00 kg 14,700.00 29,400.00
c Pelumas begisting (oli/minyak) 0.60 Ltr 10,000.00 6,000.00
d Besi beton polos 175.00 kg 8,800.00 1,540,000.00
e Kawat beton 3.00 kg 19,000.00 57,000.00
f Semen PC (abu-abu) 8.00 sak 42,000.00 336,000.00
3
g Pasir beton 0.52 m 72,000.00 37,440.00
h Split (batu pecah) 0.78 m3 210,000.00 163,800.00
i Pembantu tukang 4.85 org 40,000.00 194,000.00
j Tukang batu 0.40 org 55,000.00 22,000.00
k Tukang kayu 1.75 org 55,000.00 96,250.00
l Tukang besi 1.45 org 55,000.00 79,750.00
Jumlah 2,891,040.00
Dibulatkan 2,891,000.00

V PEKERJAAN DINDING
1 1 M2 PASANGAN Bata merah TEBAL 1 BATA, CAMPURAN 1 Pc : 3 Ps
a Bata merah 140.00 bh 600.00 84,000.00
b Semen PC (abu-abu) 0.65 sak 42,000.00 27,300.00
c Pasir pasang 0.09 m3 68,000.00 6,120.00
d Pembantu tukang 0.65 org 40,000.00 26,000.00
e Tukang batu 0.20 org 55,000.00 11,000.00
Jumlah 154,420.00
Dibulatkan 154,400.00
2 1 M2 PASANGAN Bata merah TEBAL 1 BATA, CAMPURAN 1 Pc : 4 Ps
a Bata merah 140.00 bh 600.00 84,000.00
b Semen PC (abu-abu) 0.55 sak 42,000.00 23,100.00
c Pasir pasang 0.09 m3 68,000.00 6,120.00
d Pembantu tukang 0.65 org 40,000.00 26,000.00
e Tukang batu 0.20 org 55,000.00 11,000.00
Jumlah 150,220.00
Dibulatkan 150,200.00
3 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA, CAMPURAN 1 Pc : 5 Ps
a Bata merah 140.00 bh 600.00 84,000.00
b Semen PC (abu-abu) 0.45 sak 42,000.00 18,900.00
c Pasir pasang 0.10 m3 68,000.00 6,800.00
d Pembantu tukang 0.65 org 40,000.00 26,000.00
e Tukang batu 0.20 org 55,000.00 11,000.00
Jumlah 146,700.00
Dibulatkan 146,700.00
4 1 M2 PASANGAN BATA MERAH TEBAL ½ BATA, CAMPURAN 1 Pc : 3 Ps
a Bata merah 70.00 bh 600.00 42,000.00
b Semen PC (abu-abu) 0.29 sak 42,000.00 12,180.00
c Pasir pasang 0.04 m3 68,000.00 2,720.00
d Pembantu tukang 0.32 org 40,000.00 12,800.00
e Tukang batu 0.10 org 55,000.00 5,500.00
Jumlah 75,200.00
Dibulatkan 75,200.00
5 1 M2 PASANGAN BATA MERAH TEBAL ½ BATA, CAMPURAN 1 Pc : 4 Ps
a Bata merah 70.00 bh 600.00 42,000.00
b Semen PC (abu-abu) 0.25 sak 42,000.00 10,500.00
c Pasir pasang 0.05 m3 68,000.00 3,400.00
d Pembantu tukang 0.32 org 40,000.00 12,800.00
e Tukang batu 0.10 org 55,000.00 5,500.00
Jumlah 74,200.00
Dibulatkan 74,200.00
6 1 M2 PASANGAN BATA MERAH TEBAL ½ BATA, CAMPURAN 1 Pc : 5 Ps
a Bata merah 70.00 bh 600.00 42,000.00
b Semen PC (abu-abu) 0.22 sak 42,000.00 9,240.00
c Pasir pasang 0.05 m3 68,000.00 3,400.00
d Pembantu tukang 0.32 org 40,000.00 12,800.00
e Tukang batu 0.10 org 55,000.00 5,500.00
Jumlah 72,940.00
Dibulatkan 72,900.00
7 1 M2 PASANG DINDING BATA ROOSTER / BATA TERAWANG
a Rooster / Terawang ukuran 12 x 11 x 24 37.00 bh 4,100.00 151,700.00
b Semen PC (abu-abu) 0.27 sak 42,000.00 11,340.00
c Pasir pasang 0.04 m3 68,000.00 2,720.00
d Pembantu tukang 0.30 org 40,000.00 12,000.00
e Tukang batu 0.10 org 55,000.00 5,500.00
Jumlah 183,260.00
Dibulatkan 183,200.00
8 1 M2 PASANG DINDING GLASSBLOCK
a Glassblock ukuran 18 x 18 cm 30.00 bh 20,000.00 600,000.00
b Semen putih 0.27 sak 12,700.00 3,429.00
c Pembantu tukang 0.30 org 40,000.00 12,000.00
d Tukang batu 0.10 org 55,000.00 5,500.00
Jumlah 620,929.00
Dibulatkan 620,900.00
9 1 M2 PASANGAN BATACO PUTIH, CAMPURAN 1 Pc : 5 Ps
a Bataco putih 15.00 bh 4,200.00 63,000.00
b Semen PC (abu-abu) 0.25 sak 42,000.00 10,500.00
c Pasir pasang 0.03 m3 68,000.00 2,040.00
d Pembantu tukang 0.30 org 40,000.00 12,000.00
e Tukang batu 0.15 org 55,000.00 8,250.00
Jumlah 95,790.00
Dibulatkan 95,700.00
10 1 M2 PASANGAN BATACO PRES SEMEN, CAMPURAN 1 Pc : 5 Ps
a Bataco press semen 15.00 bh 4,300.00 64,500.00
b Semen PC (abu-abu) 0.20 sak 42,000.00 8,400.00
c Pasir pasang 0.02 m3 68,000.00 1,360.00
d Pembantu tukang 0.30 org 40,000.00 12,000.00
e Tukang batu 0.15 org 55,000.00 8,250.00
Jumlah 94,510.00
Dibulatkan 94,500.00
11 1 M2 PASANGAN BATA RINGAN ( HEBEL/CELCON ).
a Bata Ringan ( hebel/celcon ) 8.00 bh 3,800.00 30,400.00
b Semen Instan 11.45 kg 2,450.00 28,052.50
c Pembantu tukang 0.30 org 40,000.00 12,000.00
d Tukang batu 0.20 org 55,000.00 11,000.00
Jumlah 81,452.50
Dibulatkan 81,400.00
VI PEKERJAAN PLESTERAN/ACCI
1 1 M2 PLESTERAN CAMPURAN 1 Pc : 2 Ps TEBAL 1,5 cm
a Semen PC (abu-abu) 0.14 sak 42,000.00 5,880.00
b Pasir pasang 0.02 m3 68,000.00 1,360.00
c Pembantu tukang 0.20 org 40,000.00 8,000.00
d Tukang batu 0.15 org 55,000.00 8,250.00
Jumlah 23,490.00
Dibulatkan 23,400.00
2 1 M2 PLESTERAN CAMPURAN 1 Pc : 3 Ps TEBAL 1,5 cm
a Semen PC (abu-abu) 0.13 sak 42,000.00 5,460.00
b Pasir pasang 0.02 m3 68,000.00 1,360.00
c Pembantu tukang 0.20 org 40,000.00 8,000.00
d Tukang batu 0.15 org 55,000.00 8,250.00
Jumlah 23,070.00
Dibulatkan 23,000.00
3 1 M2 PLESTERAN CAMPURAN 1 Pc : 4 Ps TEBAL 1,5 cm
a Semen PC (abu-abu) 0.10 sak 42,000.00 4,200.00
b Pasir pasang 0.02 m3 68,000.00 1,360.00
c Pembantu tukang 0.20 org 40,000.00 8,000.00
d Tukang batu 0.15 org 55,000.00 8,250.00
Jumlah 21,810.00
Dibulatkan 21,800.00
4 1 M2 PLESTERAN CAMPURAN 1 Pc : 5 Ps TEBAL 1,5 cm
a Semen PC (abu-abu) 0.09 sak 42,000.00 3,780.00
b Pasir pasang 0.02 m3 68,000.00 1,360.00
c Pembantu tukang 0.20 org 40,000.00 8,000.00
d Tukang batu 0.15 org 55,000.00 8,250.00
Jumlah 21,390.00
Dibulatkan 21,300.00
5 1 M2 PLESTERAN CAMPURAN 1 Pc : 4 Ps TEBAL 2,0 cm
a Semen PC (abu-abu) 0.17 sak 42,000.00 7,140.00
b Pasir pasang 0.03 m3 68,000.00 2,040.00
c Pembantu tukang 0.22 org 40,000.00 8,800.00
d Tukang batu 0.16 org 55,000.00 8,800.00
Jumlah 26,780.00
Dibulatkan 26,700.00
6 1 M2 PLESTERAN CAMPURAN 1 Pc : 5 Ps TEBAL 2,0 cm
a Semen PC (abu-abu) 0.15 sak 42,000.00 6,300.00
b Pasir pasang 0.03 m3 68,000.00 2,040.00
c Pembantu tukang 0.25 org 40,000.00 10,000.00
d Tukang batu 0.20 org 55,000.00 11,000.00
Jumlah 29,340.00
Dibulatkan 29,300.00
7 1 M2 BERAPEN CAMPURAN 1 Pc : 5 Ps TEBAL 1,5 cm
a Semen PC (abu-abu) 0.11 sak 42,000.00 4,620.00
b Pasir pasang 0.03 m3 68,000.00 1,700.00
c Pembantu tukang 0.15 org 40,000.00 6,000.00
d Tukang batu 0.07 org 55,000.00 3,850.00
Jumlah 16,170.00
Dibulatkan 16,100.00
8 1 M2 PLESTERAN BETON CAMPURAN 1 Pc : 2 Ps TEBAL 1,5 cm
a Semen PC (abu-abu) 0.19 sak 42,000.00 7,980.00
b Pasir pasang 0.02 m3 68,000.00 1,360.00
c Pembantu tukang 0.26 org 40,000.00 10,400.00
d Tukang batu 0.20 org 55,000.00 11,000.00
Jumlah 30,740.00
Dibulatkan 30,700.00
9 1 M2 PLESTERAN BETON CAMPURAN 1 Pc : 3 Ps TEBAL 1,5 cm
a Semen PC (abu-abu) 0.15 sak 42,000.00 6,300.00
b Pasir pasang 0.02 m3 68,000.00 1,360.00
c Pembantu tukang 0.26 org 40,000.00 10,400.00
d Tukang batu 0.20 org 55,000.00 11,000.00
Jumlah 29,060.00
Dibulatkan 29,000.00
10 1 M2 PLESTERAN SKONENG CAMPURAN 1 Pc : 2 Ps
a Semen PC (abu-abu) 0.01 sak 42,000.00 420.00
b Pasir pasang 0.01 m3 68,000.00 680.00
c Pembantu tukang 0.06 org 40,000.00 2,400.00
d Tukang batu 0.04 org 55,000.00 2,200.00
Jumlah 5,700.00
Dibulatkan 5,700.00
11 1 M2 ACCIAN PLESTERAN
a Semen PC (abu-abu) 0.08 sak 42,000.00 3,360.00
b Pembantu tukang 0.14 org 40,000.00 5,600.00
c Tukang batu 0.11 org 55,000.00 6,050.00
Jumlah 15,010.00
Dibulatkan 15,000.00
12 1 M2 PLESTERAN SIAR CAMPURAN 1 Pc : 2 Ps
a Semen PC (abu-abu) 0.09 sak 42,000.00 3,780.00
b Pasir pasang 0.02 m3 68,000.00 1,360.00
c Pembantu tukang 0.15 org 40,000.00 6,000.00
d Tukang batu 0.07 org 55,000.00 3,850.00
Jumlah 14,990.00
Dibulatkan 14,900.00

VII PEKERJAAN PELAPIS LANTAI


1 1 M2 PASANG LANTAI KERAMIK UKURAN 40 x 40 cm POLISHED
a Keramik ukuran 40 x 40 cm 1.00 m2 246,000.00 246,000.00
b Semen PC (abu-abu) 0.16 sak 42,000.00 6,720.00
c Pasir pasang 0.02 m3 68,000.00 1,462.00
d Semen warna 0.02 kg 12,700.00 254.00
e Pembantu tukang 0.25 org 40,000.00 10,000.00
f Tukang batu 0.12 org 55,000.00 6,600.00
Jumlah 271,036.00
Dibulatkan 271,030.00
2 1 M2 PASANG LANTAI KERAMIK UKURAN 40 x 40 cm UNPOLISH
a Keramik ukuran 40 x 40 cm 1.00 m2 205,000.00 205,000.00
b Semen PC (abu-abu) 0.16 sak 42,000.00 6,720.00
c Pasir pasang 0.02 m3 68,000.00 1,360.00
d Semen warna 0.02 kg 12,700.00 254.00
e Pembantu tukang 0.26 org 40,000.00 10,400.00
f Tukang batu 0.13 org 55,000.00 6,875.00
Jumlah 230,609.00
Dibulatkan 230,600.00
3 1 M2 PASANG LANTAI KERAMIK UKURAN 60 x 60 cm
a Keramik ukuran 60 x 60 cm 1.00 m2 290,000.00 290,000.00
b Semen PC (abu-abu) 0.18 sak 42,000.00 7,560.00
c Pasir pasang 0.02 m3 68,000.00 1,462.00
d Semen warna 0.01 kg 12,700.00 165.10
e Pembantu tukang 0.25 org 40,000.00 10,000.00
f Tukang batu 0.12 org 55,000.00 6,600.00
Jumlah 315,787.10
Dibulatkan 315,780.00
4 1 M2 PASANG LANTAI KERAMIK UKURAN 60 x 90 cm
a Keramik ukuran 60 x 90 cm 1.00 m2 336,000.00 336,000.00
b Semen PC (abu-abu) 0.17 sak 42,000.00 7,140.00
c Pasir pasang 0.02 m3 68,000.00 1,462.00
d Semen warna 0.02 kg 12,700.00 254.00
e Pembantu tukang 0.26 org 40,000.00 10,400.00
f Tukang batu 0.14 org 55,000.00 7,700.00
Jumlah 362,956.00
Dibulatkan 362,950.00
5 1 M2 PASANG LANTAI KERAMIK 10 x 20 cm
a Keramik lantai 10 x 20 cm 1.00 m2 32,000.00 32,000.00
b Semen PC ( abu-abu ) 0.18 sak 42,000.00 7,560.00
c Pasir pasang 0.02 m3 68,000.00 1,360.00
d Semen warna 0.02 kg 12,700.00 254.00
e Pembantu tukang 0.22 org 40,000.00 8,800.00
f Tukang batu 0.40 org 55,000.00 22,000.00
Jumlah 71,974.00
Dibulatkan 71,970.00
6 1 M2 PASANG LANTAI KERAMIK POLOS 20 x 20 cm
a Keramik polos 20 x 20 cm 1.00 m2 38,000.00 38,000.00
b Semen PC (abu-abu) 0.17 sak 42,000.00 7,140.00
c Pasir pasang 0.02 m3 68,000.00 1,462.00
d Semen warna 0.02 kg 12,700.00 254.00
e Pembantu tukang 0.30 org 40,000.00 12,000.00
f Tukang batu 0.15 org 55,000.00 8,250.00
Jumlah 67,106.00
Dibulatkan 67,100.00
7 1 M2 PASANG LANTAI KERAMIK MOTIF 20 x 20 cm
a Keramik motif 20 x 20 cm 1.00 m2 38,000.00 38,000.00
b Semen PC (abu-abu) 0.17 sak 42,000.00 7,140.00
c Pasir pasang 0.02 m3 68,000.00 1,462.00
d Semen warna 0.02 kg 12,700.00 254.00
e Pembantu tukang 0.30 org 40,000.00 12,000.00
f Tukang batu 0.15 org 55,000.00 8,250.00
Jumlah 67,106.00
Dibulatkan 67,100.00
8 1 M2 PASANG LANTAI KERAMIK POLOS 30 x 30 cm
a Keramik polos 30 x 30 cm 1.00 m2 38,500.00 38,500.00
b Semen PC (abu-abu) 0.16 sak 42,000.00 6,720.00
c Pasir pasang 0.02 m3 68,000.00 1,360.00
d Semen warna 0.02 kg 12,700.00 254.00
e Pembantu tukang 0.25 org 40,000.00 10,000.00
f Tukang batu 0.12 org 55,000.00 6,600.00
Jumlah 63,434.00
Dibulatkan 63,430.00
9 1 M2 PASANG LANTAI KERAMIK MOTIF 30 x 30 cm
a Keramik motif 30 x 30 cm 1.00 m2 41,000.00 41,000.00
b Semen PC (abu-abu) 0.16 sak 42,000.00 6,720.00
c Pasir pasang 0.02 m3 68,000.00 1,360.00
d Semen warna 0.02 kg 12,700.00 254.00
e Pembantu tukang 0.25 org 40,000.00 10,000.00
f Tukang batu 0.12 org 55,000.00 6,600.00
Jumlah 65,934.00
Dibulatkan 65,930.00
10 1 M2 PASANG LANTAI MARMER
a marmer standar 1.00 m2 200,000.00 200,000.00
b Semen PC (abu-abu) 0.48 sak 42,000.00 20,160.00
c Pasir pasang 0.10 m3 68,000.00 6,800.00
d Semen warna 0.20 sak 12,700.00 2,540.00
e Pembantu tukang 0.62 org 40,000.00 24,800.00
f Tukang batu 0.35 org 55,000.00 19,250.00
Jumlah 273,550.00
Dibulatkan 273,550.00
11 1 M2 PASANG LANTAI PARQUET JATI
a Parquet jati 1.05 m2 278,000.00 291,900.00
b Lem vinyl 0.60 kg 35,000.00 21,000.00
c Pembantu tukang 0.65 org 40,000.00 26,000.00
d Tukang 0.35 org 55,000.00 19,250.00
Jumlah 358,150.00
Dibulatkan 358,150.00
12 1 M2 PASANG LANTAI GRANIT
a Granit standar 1.00 m2 750,000.00 750,000.00
b Semen PC (abu-abu) 0.48 sak 42,000.00 20,160.00
c Pasir pasang 0.08 m3 68,000.00 5,440.00
d Semen warna 0.10 sak 12,700.00 1,270.00
e Pembantu tukang 0.60 org 40,000.00 24,000.00
f Tukang batu 0.48 org 55,000.00 26,400.00
Jumlah 827,270.00
Dibulatkan 827,270.00

VIII PEKERJAAN PELAPIS DINDING


1 1 M2 PASANG DINDING KERAMIK MOTIF 10 x 20 cm
a Keramik motif 10 x 20 cm 1.00 m2 38,000.00 38,000.00
b Semen PC ( abu-abu ) 0.18 sak 42,000.00 7,560.00
c Pasir pasang 0.02 m3 68,000.00 1,360.00
d Semen warna 0.02 kg 12,700.00 254.00
e Pembantu tukang 0.22 org 40,000.00 8,800.00
f Tukang batu 0.40 org 55,000.00 22,000.00
Jumlah 77,974.00
Dibulatkan 77,970.00
2 1 M2 PASANG DINDING KERAMIK POLOS 10 x 20 cm
a Keramik polos 10 x 20 cm 1.00 m2 34,000.00 34,000.00
b Semen PC ( abu-abu ) 0.18 sak 42,000.00 7,560.00
c Pasir pasang 0.02 m3 68,000.00 1,360.00
d Semen warna 0.02 kg 12,700.00 254.00
e Pembantu tukang 0.22 org 40,000.00 8,800.00
f Tukang batu 0.40 org 55,000.00 22,000.00
Jumlah 73,974.00
Dibulatkan 73,970.00
3 1 M2 PASANG DINDING KERAMIK MOTIF 20 x 20 cm
a Keramik motif 20 x 20 cm 1.00 m2 38,000.00 38,000.00
b Semen PC ( abu-abu ) 0.17 sak 42,000.00 7,140.00
c Pasir pasang 0.02 m3 68,000.00 1,360.00
d Semen warna 0.02 kg 12,700.00 254.00
e Pembantu tukang 0.20 org 40,000.00 8,000.00
f Tukang batu 0.39 org 55,000.00 21,450.00
Jumlah 76,204.00
Dibulatkan 76,200.00
4 1 M2 PASANG DINDING KERAMIK POLOS 20 x 20 cm
a Keramik polos 20 x 20 cm 1.00 m2 38,000.00 38,000.00
b Semen PC ( abu-abu ) 0.17 sak 42,000.00 7,140.00
c Pasir pasang 0.02 m3 68,000.00 1,360.00
d Semen warna 0.02 kg 12,700.00 254.00
e Pembantu tukang 0.20 org 40,000.00 8,000.00
f Tukang batu 0.39 org 55,000.00 21,450.00
Jumlah 76,204.00
Dibulatkan 76,200.00
5 1 M2 PASANG DINDING KERAMIK POLOS 20 x 25 cm
a Keramik polos 20 x 25 cm 1.00 m2 38,000.00 38,000.00
b Semen PC ( abu-abu ) 0.16 sak 42,000.00 6,720.00
c Pasir pasang 0.02 m3 68,000.00 1,224.00
d Semen warna 0.01 kg 12,700.00 165.10
e Pembantu tukang 0.19 org 40,000.00 7,500.00
f Tukang batu 0.38 org 55,000.00 20,625.00
Jumlah 74,234.10
Dibulatkan 74,230.00
6 1 M2 PASANG DINDING KERAMIK MOTIF 20 x 25 cm
a Keramik motif 20 x 25 cm 1.00 m2 39,000.00 39,000.00
b Semen PC ( abu-abu ) 0.16 sak 42,000.00 6,720.00
c Pasir pasang 0.02 m3 68,000.00 1,224.00
d Semen warna 0.01 kg 12,700.00 165.10
e Pembantu tukang 0.19 org 40,000.00 7,500.00
f Tukang batu 0.38 org 55,000.00 20,625.00
Jumlah 75,234.10
Dibulatkan 75,230.00
7 1 M2 PASANG DINDING MARMER
a Marmer standar 1.00 m2 200,000.00 200,000.00
b Paku sekrup 4.00 bh 750.00 3,000.00
c Semen PC ( abu-abu ) 0.25 sak 42,000.00 10,500.00
d Pasir pasang 0.03 m3 68,000.00 1,700.00
e Semen warna 1.50 kg 12,700.00 19,050.00
f Kawat ikat 0.03 kg 19,000.00 475.00
g Paku 0.03 kg 14,700.00 367.50
h Pembantu tukang 0.72 org 40,000.00 28,800.00
i Tukang batu 0.65 org 55,000.00 35,750.00
Jumlah 299,642.50
Dibulatkan 299,640.00
8 1 M2 PASANG DINDING GRANIT
a Granit standar 1.00 m2 750,000.00 750,000.00
b Paku sekrup 2.00 bh 750.00 1,500.00
c Semen PC ( abu-abu ) 0.25 sak 42,000.00 10,500.00
d Pasir pasang 0.03 m3 68,000.00 1,700.00
e Semen warna 1.50 kg 12,700.00 19,050.00
f Kawat ikat 0.03 kg 19,000.00 475.00
g Paku 0.03 kg 14,700.00 367.50
h Pembantu tukang 0.72 org 40,000.00 28,800.00
i Tukang batu 0.65 org 55,000.00 35,750.00
Jumlah 848,142.50
Dibulatkan 848,140.00
9 1 M2 PASANG DINDING BATU TEMPEL HITAM
a Batu tempel hitam 1.00 m2 140,000.00 140,000.00
b Semen PC ( abu-abu ) 0.24 sak 42,000.00 10,080.00
c Pasir pasang 0.04 m3 68,000.00 2,380.00
d Pembantu tukang 0.32 org 40,000.00 12,800.00
e Tukang batu 0.25 org 55,000.00 13,750.00
Jumlah 179,010.00
Dibulatkan 179,010.00
10 1 M2 PASANG DINDING BATU ALAM
a Batu alam 1.00 m2 185,000.00 185,000.00
b Semen PC ( abu-abu ) 0.25 sak 42,000.00 10,500.00
c Pasir pasang 0.04 m3 68,000.00 2,380.00
d Pembantu tukang 0.32 org 40,000.00 12,800.00
e Tukang batu 0.25 org 55,000.00 13,750.00
Jumlah 224,430.00
Dibulatkan 224,430.00
11 1 M¹ PASANG PLINT KERAMIK UKURAN 10 x 40 cm
a Plint Keramik ukuran 10 x 40 cm 2.65 bh 9,000.00 23,850.00
b Semen PC (abu-abu) 0.02 sak 42,000.00 840.00
c Pasir pasang 0.01 m3 68,000.00 680.00
d Semen warna 0.10 kg 12,700.00 1,270.00
e Pembantu tukang 0.06 org 40,000.00 2,400.00
f Tukang batu 0.03 org 55,000.00 1,650.00
Jumlah 30,690.00
Dibulatkan 30,690.00
12 1 m¹ PASANG PLINT KERAMIK UKURAN 10 x 30 cm
a Plint Keramik ukuran 10 x 30 cm 3.30 bh 7,500.00 24,750.00
b Semen PC (abu-abu) 0.02 sak 42,000.00 840.00
c Pasir pasang 0.01 m3 68,000.00 680.00
d Semen warna 0.12 kg 12,700.00 1,524.00
e Pembantu tukang 0.06 org 40,000.00 2,400.00
f Tukang batu 0.03 org 55,000.00 1,650.00
Jumlah 31,844.00
Dibulatkan 31,840.00

IX PEKERJAAN KUSEN, PINTU, JENDELA, PARTISI


1 1 M3 PASANG KUSEN PINTU & JENDELA KAYU KAMPER SAMARINDA
a Balok kayu kamper samarinda 1.20 m3 5,766,800.00 6,920,160.00
b Pembantu tukang 6.00 org 40,000.00 240,000.00
c Tukang kayu 15.00 org 55,000.00 825,000.00
Jumlah 7,985,160.00
Dibulatkan 7,985,160.00
2 1 M3 PASANG KUSEN PINTU & JENDELA KAYU KAMPER MEDAN / KRUING
a Balok kayu kamper medan 1.20 m3 3,950,000.00 4,740,000.00
b Pembantu tukang 6.00 org 40,000.00 240,000.00
c Tukang kayu 15.00 org 55,000.00 825,000.00
Jumlah 5,805,000.00
Dibulatkan 5,805,000.00
3 1 M3 PASANG KUSEN PINTU & JENDELA KAYU BORNEO SUPER
a Kayu balok borneo super 1.20 m3 3,600,000.00 4,320,000.00
b Pembantu tukang 6.00 org 40,000.00 240,000.00
c Tukang kayu 15.00 org 55,000.00 825,000.00
Jumlah 5,385,000.00
Dibulatkan 5,385,000.00
4 1 M2 PASANG PINTU PANEL KAYU KAMPER SAMARINDA
a Papan kayu kamper samarinda 0.04 m3 5,000,000.00 200,000.00
b Pembantu tukang 1.00 org 40,000.00 40,000.00
c Tukang kayu 2.50 org 55,000.00 137,500.00
Jumlah 377,500.00
Dibulatkan 377,500.00
5 1 M2 PASANG PINTU PANEL KAYU KAMPER MEDAN / KRUING
a Papan kayu kamper medan 0.04 m3 3,800,000.00 152,000.00
b Pembantu tukang 1.00 org 40,000.00 40,000.00
c Tukang kayu 2.50 org 55,000.00 137,500.00
Jumlah 329,500.00
Dibulatkan 329,500.00
6 1 M2 PASANG PINTU DAN JENDELA KACA KAYU KAMPER MEDAN
a Papan kayu kamper medan 0.04 m3 3,800,000.00 154,000.00
b Pembantu tukang 0.80 org 40,000.00 57,750.00
c Tukang kayu 2.00 org 55,000.00 154,000.00
Jumlah 365,750.00
Dibulatkan 365,700.00
7 1 M2 PASANG PINTU DAN JENDELA KACA KAYU BORNEO
a Papan kayu borneo super 0.04 m3 4,000,000.00 47,040.00
b Pembantu tukang 0.80 org 40,000.00 16,000.00
c Tukang kayu 2.00 org 55,000.00 110,000.00
Jumlah 173,040.00
Dibulatkan 173,000.00
8 1 M2 PASANG PINTU DAN JENDELA JALUSI KAYU KAMPER MEDAN
a Papan kayu Kamper Medan 0.06 m3 3,800,000.00 243,200.00
b Pembantu tukang 1.00 org 40,000.00 40,000.00
c Tukang kayu 3.00 org 55,000.00 165,000.00
Jumlah 448,200.00
Dibulatkan 448,200.00
9 1 M2 PASANG PINTU TRIPLEK RANGKAP , RANGKA KAYU KAMPER MEDAN
a Papan kayu kamper medan 0.02 m3 3,800,000.00 74,480.00
b Paku 1 s/d 5 cm 0.03 kg 14,700.00 441.00
c Lem Kayu 0.30 Ltr 28,000.00 8,400.00
d Triplek 0,4 cm ukuran pintu 1.00 lbr 47,500.00 47,500.00
e Pembantu tukang 0.60 org 40,000.00 24,000.00
f Tukang kayu 2.00 org 55,000.00 110,000.00
Jumlah 264,821.00
Dibulatkan 264,800.00
10 1 M2 PASANG JALUSI MATI KUSEN KAYU KAMPER MEDAN
a Papan kayu kamper medan 0.06 m3 3,800,000.00 228,000.00
b Paku 1 s/d 5 cm 0.15 kg 14,700.00 2,205.00
c Pembantu tukang 0.50 org 40,000.00 20,000.00
d Tukang kayu 2.00 org 55,000.00 110,000.00
Jumlah 360,205.00
Dibulatkan 360,200.00
11 1 M2 PASANG PINTU TRIPLEK RANGKAP , RANGKA KAYU BORNEO SUPER
a Papan kayu borneo super 0.02 m3 4,000,000.00 78,400.00
b Paku 1 s/d 5 cm 0.03 kg 14,700.00 441.00
c Lem kayu 0.30 Ltr 28,000.00 8,400.00
d Triplek 0,4 cm ukuran pintu 1.00 lbr 47,500.00 47,500.00
e Pembantu tukang 0.60 org 40,000.00 24,000.00
f Tukang kayu 2.00 org 55,000.00 110,000.00
Jumlah 268,741.00
Dibulatkan 268,700.00
12 1 M2 PASANG PINTU TEAKWOOD RANGKAP , RANGKA KAYU KAMPER MEDAN
a Papan kayu Kamper Medan 0.02 m3 3,800,000.00 74,480.00
b Paku 1 s/d 5 cm 0.30 kg 14,700.00 4,410.00
c Lem Kayu 0.30 Ltr 28,000.00 8,400.00
d Teakwood 120 x 240 x 0,4 cm 1.00 lbr 80,000.00 80,000.00
e Pembantu tukang 0.60 org 40,000.00 24,000.00
f Tukang kayu 2.00 org 55,000.00 110,000.00
Jumlah 301,290.00
Dibulatkan 301,200.00
13 1 M2 PASANG PINTU TRIPLEK & FORMIKA RANGKA KAYU KAMPER MEDAN
a Papan kayu kamper medan 0.02 m3 3,800,000.00 74,480.00
b Paku 1 s/d 5 cm 0.30 kg 14,700.00 4,410.00
c Lem kayu 0.80 Ltr 28,000.00 22,400.00
d Triplek 0,4 cm ukuran pintu 1.00 lbr 47,500.00 47,500.00
e Formica 3" x 6" 0.50 lbr 150,000.00 75,000.00
f Pembantu tukang 0.80 org 40,000.00 32,000.00
g Tukang kayu 2.50 org 55,000.00 137,500.00
Jumlah 393,290.00
Dibulatkan 393,200.00
14 1 M2 PASANG PINTU TEAKWOOD & FORMIKA RANGKA KAYU KAMPER MEDAN
a Papan kayu kamper medan 0.02 m3 3,800,000.00 74,480.00
b Paku 1 s/d 5 cm 0.30 kg 14,700.00 4,410.00
c Lem Kayu 0.80 Ltr 28,000.00 22,400.00
d Teakwood 120 x 240 x 0,4 cm 0.50 lbr 80,000.00 40,000.00
e Vernis 0.50 Ltr 40,000.00 20,000.00
a Formica 4" x 8" 0.50 lbr 150,000.00 75,000.00
b Pembantu tukang 0.80 org 40,000.00 32,000.00
c Tukang kayu 2.50 org 55,000.00 137,500.00
Jumlah 405,790.00
Dibulatkan 405,700.00
15 1 M2 PASANG DINDING PEMISAH DOUBLE TEAKWOOD, RANGKA KAYU KAMPER MEDAN
a Balok kayu Kamper Medan 0.02 m3 3,950,000.00 77,025.00
b Papan kayu Kamper Medan 0.01 m3 3,800,000.00 26,600.00
c Paku 5 - 12 cm 0.10 kg 14,700.00 1,470.00
d Lem Kayu 0.56 Ltr 28,000.00 15,680.00
e Teakwood 120 x 240 x 0,4 cm 1.00 lbr 80,000.00 80,000.00
f Pembantu tukang 0.15 org 40,000.00 6,000.00
g Tukang kayu 0.45 org 55,000.00 24,750.00
Jumlah 231,525.00
Dibulatkan 231,500.00
16 1 M2 PASANG DINDING PEMISAH DOUBLE GRC, RANGKA KAYU KAMPER MEDAN
a Balok kayu Kamper Medan 0.02 m3 3,950,000.00 77,025.00
3
b Papan kayu Kamper Medan 0.01 m 3,800,000.00 26,600.00
c Paku 5 - 12 cm 0.10 kg 14,700.00 1,470.00
d Lem Kayu 0.56 Ltr 28,000.00 15,680.00
e Triplek 0,4 cm ukuran pintu 1.00 lbr 47,500.00 47,500.00
f Pembantu tukang 0.20 org 40,000.00 8,000.00
g Tukang kayu 0.60 org 55,000.00 33,000.00
Jumlah 209,275.00
Dibulatkan 209,200.00
17 1 BH PASANG PINTU ALUMINIUM / PINTU PVC
a Pintu Aluminium / Pintu PVC 1.00 bh 400,000.00 400,000.00
b Alat bantu 10 % harga material 1.00 ls 40,000.00 40,000.00
c Tukang kayu 0.02 org 55,000.00 1,155.00
Jumlah 441,155.00
Dibulatkan 441,100.00
18 1 M2 PASANG KUSEN PARTISI DOUBLE TRIPLEK
a Balok kayu borneo super 0.11 m3 3,600,000.00 378,000.00
b Triplek 0,4 cm ukuran pintu 5.00 lbr 47,500.00 237,500.00
c Paku 1 s/d 3 cm 2.00 kg 14,700.00 29,400.00
d Ampelas 2.00 lbr 2,500.00 5,000.00
e Engsel 4.00 bh 25,000.00 100,000.00
f Grendel / slot 4.00 bh 32,500.00 130,000.00
g Pembantu tukang 0.30 org 40,000.00 12,000.00
h Tukang kayu terampil 1.30 org 55,000.00 71,500.00
Jumlah 963,400.00
Dibulatkan 129,530.00
19 1 M2 PASANG KUSEN PARTISI DOUBLE GYPSUM + RANGKA KAYU
a Balok kayu borneo super 0.11 m3 3,600,000.00 378,000.00
b Gypsum board ( 120 x 240 x 9 ) mm 0.72 lbr 78,000.00 56,160.00
c Paku 1 s/d 3 cm 2.00 kg 14,700.00 29,400.00
d Ampelas 2.00 lbr 2,500.00 5,000.00
e Engsel 4.00 bh 25,000.00 100,000.00
f Grendel / Slot 4.00 bh 32,500.00 130,000.00
g Pembantu tukang 0.30 org 40,000.00 12,000.00
h Tukang kayu 1.30 org 55,000.00 71,500.00
Jumlah 782,060.00
Dibulatkan 129,530.00
20 1 M2 PASANG DINDING PARTISI GYPSUM BOARD + RANGKA BESI HOLLOW
a Hollow 4/4 Zincromate 0.42 btg 48,000.00 20,160.00
b Hollow 2/4 Zincromate 0.15 btg 35,000.00 5,250.00
c Gypsum board ( 120 x 240 x 9 ) mm 0.72 lbr 78,000.00 56,160.00
d Paku sekrup 25.00 bh 750.00 18,750.00
e Ramset / dina bolt 4.00 bh 2,200.00 8,800.00
f Cotton plaster 0.10 bh 58,000.00 5,800.00
g Compoun 0.13 kg 32,000.00 4,160.00
h Pembantu tukang 0.10 org 40,000.00 4,000.00
i Tukang kayu 0.05 org 55,000.00 2,750.00
Jumlah 125,830.00
Dibulatkan 125,830.00
X PEKERJAAN RANGKA ATAP DAN PENUTUP ATAP
A PEKERJAAN RANGKA ATAP
1 1 M3 PEKERJAAN KONSTRUKSI KUDA - KUDA KAYU KAMPER MEDAN
a Balok kayu kamper medan 1.10 m3 3,950,000.00 4,345,000.00
b Besi strip 15.00 kg 17,500.00 262,500.00
c Paku ukuran besar 0.80 kg 14,700.00 11,760.00
d Meni kayu 0.40 kg 16,000.00 6,400.00
e Pembantu tukang 4.00 org 40,000.00 160,000.00
f Tukang kayu 12.00 org 55,000.00 660,000.00
Jumlah 5,445,660.00
Dibulatkan 5,445,600.00
2 1 M3 PEKERJAAN KONSTRUKSI KUDA - KUDA KAYU BORNEO SUPER
a Balok kayu borneo super 1.10 m3 3,600,000.00 3,960,000.00
b Besi strip 15.00 kg 17,500.00 262,500.00
c Paku ukuran besar 0.80 kg 14,700.00 11,760.00
d Meni kayu 0.40 kg 16,000.00 6,400.00
e Pembantu tukang 4.00 org 40,000.00 160,000.00
f Tukang kayu 12.00 org 55,000.00 660,000.00
Jumlah 5,060,660.00
Dibulatkan 5,060,600.00
3 1 M2 PASANG KASO + RENG GENTENG PLENTONG KAYU BORNEO SUPER
a Balok kayu borneo super 0.01 m3 3,600,000.00 43,200.00
b Paku 7 - 10 cm 0.15 kg 14,700.00 2,205.00
c Pembantu tukang 0.10 org 40,000.00 4,000.00
d Tukang kayu 0.10 org 55,000.00 5,500.00
Jumlah 54,905.00
Dibulatkan 54,900.00
4 1 M2 PASANG KASO + RENG GENTENG BETON KAYU BORNEO SUPER
a Balok kayu borneo super 0.01 m3 3,600,000.00 50,400.00
b Paku 7 - 10 cm 0.15 kg 14,700.00 2,205.00
c Pembantu tukang 0.10 org 40,000.00 4,000.00
d Tukang kayu 0.10 org 55,000.00 5,500.00
Jumlah 62,105.00
Dibulatkan 62,100.00
5 1 M1 PASANG LISPLANG KAYU KAMPER MEDAN UKURAN 3 X 20 cm
a Papan kayu kamper medan 0.01 m3 3,800,000.00 27,360.00
b Paku 7 - 10 cm 0.05 kg 14,700.00 735.00
c Pembantu tukang 0.10 org 40,000.00 4,000.00
d Tukang kayu 0.20 org 55,000.00 11,000.00
Jumlah 43,095.00
Dibulatkan 43,000.00
6 1 M2 PASANG LISPLANG KAYU KAMPER MEDAN UKURAN 3 X 30 cm
a Papan kayu kamper medan 0.01 m3 3,800,000.00 41,800.00
b Paku 7 - 10 cm 0.05 kg 14,700.00 735.00
c Pembantu tukang 0.11 org 40,000.00 4,400.00
d Tukang kayu 0.22 org 55,000.00 12,100.00
Jumlah 59,035.00
Dibulatkan 59,000.00
7 1 M3 PEKERJAAN NOK/GORDING/JURAY KAYU BORNEO SUPER
a Balok kayu borneo super 1.05 m3 3,600,000.00 3,780,000.00
b Paku 10 - 15 cm 0.20 kg 14,700.00 2,940.00
c Pembantu tukang 2.00 org 40,000.00 80,000.00
d Tukang kayu 2.00 org 55,000.00 110,000.00
Jumlah 3,972,940.00
Dibulatkan 3,972,900.00
B PEKERJAAN PENUTUP ATAP
1 1 M2 PASANG ATAP GENTENG PLENTONG
a Genteng palentong 25.00 bh 800.00 20,000.00
b Pembantu tukang 0.15 org 40,000.00 6,000.00
c Tukang kayu 0.08 org 55,000.00 4,125.00
Jumlah 30,125.00
Dibulatkan 30,120.00
2 1 M2 PASANG NOK/BUBUNGAN GENTENG KERAMIK GLAZUR
a Genteng nok/bubungan plentong 5.00 bh 26,500.00 132,500.00
b Semen PC (abu-abu) 0.16 sak 42,000.00 6,720.00
c Pasir pasang 0.03 m3 68,000.00 2,176.00
d Pembantu tukang 0.30 org 40,000.00 12,000.00
e Tukang kayu 0.20 org 55,000.00 11,000.00
Jumlah 164,396.00
Dibulatkan 164,390.00
3 1 M2 PASANG ATAP FIBREGLASS UKURAN 180 X 90 cm
a Atap fibreglass 0.60 lbr 68,000.00 40,800.00
b Paku 2 - 5 cm 0.05 kg 14,700.00 735.00
c Pembantu tukang 0.14 org 40,000.00 5,600.00
d Tukang kayu 0.07 org 55,000.00 3,685.00
Jumlah 50,820.00
Dibulatkan 50,820.00
4 1 M2 PASANG ATAP ASBES GELOMBANG UKURAN 2,70 x 1,05 m TEBAL 4 mm
a Asbes gelombang 0.35 lbr 72,000.00 25,200.00
b Paku payung 0.12 kg 14,700.00 1,764.00
c Pembantu tukang 0.14 org 40,000.00 5,600.00
d Tukang kayu 0.07 org 55,000.00 3,850.00
Jumlah 36,414.00
Dibulatkan 36,410.00
5 1 M2 PASANG ATAP ASBES GELOMBANG UKURAN 2,40 x 1,05 m TEBAL 4 mm
a Asbes gelombang 0.42 lbr 65,000.00 27,300.00
b Paku payung 0.12 kg 14,700.00 1,764.00
c Pembantu tukang 0.14 org 40,000.00 5,600.00
d Tukang kayu 0.07 org 55,000.00 3,850.00
Jumlah 38,514.00
Dibulatkan 38,510.00
6 1 M2 PASANG ATAP ASBES GELOMBANG UKURAN 2,70 x 1,02 m TEBAL 5 mm
a Asbes gelombang 0.44 lbr 90,000.00 39,600.00
b Paku payung 0.12 kg 14,700.00 1,764.00
c Pembantu tukang 0.14 org 40,000.00 5,600.00
d Tukang kayu 0.07 org 55,000.00 3,685.00
Jumlah 50,649.00
Dibulatkan 50,640.00
7 1 M2 PASANG ATAP ASBES GELOMBANG UKURAN 2,40 x 1,02 m TEBAL 5 mm
a Asbes gelombang 0.51 lbr 81,000.00 41,310.00
b Paku payung 0.12 kg 14,700.00 1,764.00
c Pembantu tukang 0.14 org 40,000.00 5,600.00
d Tukang kayu 0.07 org 55,000.00 3,685.00
Jumlah 52,359.00
Dibulatkan 52,350.00
8 1 M2 PASANG ATAP ASBES GELOMBANG ( 1,50 x 1,02 m ) x 5 mm
a Asbes gelombang 0.80 lbr 48,000.00 38,400.00
b Paku payung 0.12 kg 14,700.00 1,764.00
c Pembantu tukang 0.14 org 40,000.00 5,600.00
d Tukang kayu 0.07 org 55,000.00 3,850.00
Jumlah 49,614.00
Dibulatkan 49,610.00
9 1 M¹ PASANG ATAP SIRAP
a Genteng sirap 80.00 bh 600.00 48,000.00
b Paku 0.20 kg 14,700.00 2,940.00
c Pembantu tukang 0.10 org 40,000.00 4,000.00
d Tukang kayu 0.20 org 55,000.00 11,000.00
Jumlah 65,940.00
Dibulatkan 65,940.00
10 1 M2 PASANG ATAP GENTENG BETON
a Genteng beton 1.10 bh 65,000.00 71,500.00
b Paku 5 - 12 cm 0.03 kg 14,700.00 441.00
c Pembantu tukang 0.20 org 40,000.00 8,000.00
d Tukang kayu 0.10 org 55,000.00 5,500.00
Jumlah 85,441.00
Dibulatkan 85,440.00
11 1 M2 PASANG ATAP GENTENG METAL + C301
a Genteng metal 1.02 lbr 129,800.00 132,396.00
b Paku 5 - 12 cm 0.20 kg 14,700.00 2,940.00
c Pembantu tukang 0.20 org 40,000.00 8,000.00
d Tukang kayu 0.10 org 55,000.00 5,500.00
Jumlah 148,836.00
Dibulatkan 148,830.00
12 1 M¹ PASANG NOK GENTENG BETON
a Nok genteng beton 3.50 bh 16,000.00 56,000.00
b Paku 5 - 12 cm 0.05 kg 14,700.00 735.00
c Semen PC (abu-abu) 0.22 sak 42,000.00 9,072.00
d Pasir pasang 0.03 m3 68,000.00 2,176.00
e Semen warna 1.00 kg 12,700.00 12,700.00
f Pembantu tukang 0.40 org 40,000.00 16,000.00
g Tukang kayu 0.20 org 55,000.00 11,000.00
Jumlah 107,683.00
Dibulatkan 107,680.00
13 1 M¹ PASANG NOK GENTENG METAL
a Nok genteng metal 1.10 bh 58,000.00 63,800.00
b Paku payung 0.05 kg 14,700.00 735.00
c Pembantu tukang 0.25 org 40,000.00 10,000.00
d Tukang kayu 0.15 org 55,000.00 8,250.00
Jumlah 82,785.00
Dibulatkan 82,780.00
14 1 M2 PASANG ATAP SENG GELOMBANG
a Seng gelombang 0.70 lbr 53,800.00 37,660.00
b Paku payung 0.02 kg 14,700.00 294.00
c Pembantu tukang 0.12 org 40,000.00 4,800.00
d Tukang kayu 0.06 org 55,000.00 3,300.00
Jumlah 46,054.00
Dibulatkan 46,050.00
15 1 M2 PASANG NOK SENG UNTUK ATAP SENG GELOMBANG
a Seng plat BJLS 1.05 M1 33,000.00 34,650.00
b Paku payung 0.04 kg 14,700.00 588.00
c Pembantu tukang 0.15 org 40,000.00 6,000.00
d Tukang kayu 0.07 org 55,000.00 3,850.00
Jumlah 45,088.00
Dibulatkan 45,080.00
16 1 M2 PASANG ATAP POLYCARBONATE
a Polycarbonate 1.05 m2 222,000.00 233,100.00
b Besi Hollow 1.50 btg 48,000.00 72,000.00
c Alat bantu 20 % harga material 1.00 ls 46,620.00 46,620.00
d Pembantu tukang 0.15 org 40,000.00 6,000.00
e Tukang kayu 0.05 org 55,000.00 2,750.00
Jumlah 360,470.00
Dibulatkan 360,470.00
17 1 M2 PASANG ALUMINIUM FOIL
a Aluminium foil 1.05 m2 5,600.00 5,880.00
b Alat bantu 20 % harga material 1.00 ls 1,176.00 1,176.00
c Pembantu tukang 0.15 org 40,000.00 6,000.00
d Tukang kayu 0.05 org 55,000.00 2,750.00
Jumlah 15,806.00
Dibulatkan 15,800.00

XI PEKERJAAN PENUTUP PLAFON


1 1 M2 PASANG RANGKA PLAFON ( UKRN 0,50 X 1,00 ) M, KAYU BORNEO SUPER
a Balok kayu borneo super 4 x 6 cm 0.01 m3 3,600,000.00 43,200.00
b Paku 5 - 12 cm 0.10 kg 14,700.00 1,470.00
c Pembantu tukang 0.15 org 40,000.00 6,000.00
d Tukang kayu 0.25 org 55,000.00 13,750.00
Jumlah 64,420.00
Dibulatkan 64,400.00
2 1 M2 PLAFON GRC ( 60 X 1,20 ) M, TEBAL 4 MM
a Pelat GRC tebal 4 mm 1.10 lbr 47,500.00 52,250.00
b Paku 1 cm 0.01 kg 14,700.00 147.00
c Pembantu tukang 0.03 org 40,000.00 1,200.00
d Tukang kayu 0.07 org 55,000.00 3,850.00
Jumlah 57,447.00
Dibulatkan 57,440.00
3 1 M2 PLAFON Asbes ( 1,00 x 1,00 ) m, tebal 5 mm
a Pelat asbes tebal 5 mm 1.10 lbr 13,500.00 14,850.00
b Paku 1 cm 0.01 kg 14,700.00 147.00
c Pembantu tukang 0.03 org 40,000.00 1,200.00
d Tukang kayu 0.07 org 55,000.00 3,850.00
Jumlah 20,047.00
Dibulatkan 20,040.00
4 1 M2 PLAFON Akustik ( 60 x 120 ) cm
a Akustik 600 x 1200 x 15 mm 1.50 lbr 78,000.00 117,000.00
b Paku 2 - 5 cm 0.05 kg 14,700.00 735.00
c Pembantu tukang 0.06 org 40,000.00 2,400.00
d Tukang kayu 0.10 org 55,000.00 5,500.00
Jumlah 125,635.00
Dibulatkan 125,630.00
5 1 M2 PLAFON AKUSTIK ( 60 X 120 ) CM + RANGKA ALLUMINIUM
a Profil Alluminium "T" 3.60 M¹ 33,000.00 118,800.00
b Kawat seng polos 0.15 kg 19,000.00 2,850.00
c Ramset / dina bolt 1.00 bh 2,200.00 2,200.00
d Akustik 600 x 1200 x 15 mm 1.50 lbr 78,000.00 117,000.00
e Pembantu tukang 0.15 org 40,000.00 6,000.00
f Tukang kayu 0.20 org 55,000.00 11,000.00
Jumlah 257,850.00
Dibulatkan 257,850.00
6 1 M¹ LIST PLAFON PROFIL KAYU
a Listp profil kayu 1.10 M¹ 7,700.00 8,470.00
b Paku 2 cm 0.01 kg 14,700.00 147.00
c Pembantu tukang 0.05 org 40,000.00 2,000.00
d Tukang kayu 0.05 org 55,000.00 2,750.00
Jumlah 13,367.00
Dibulatkan 13,360.00
7 1 M¹ LIST PLAFON KAYU 1/4
a List kayu 1/4 1.10 M¹ 1,925.00 2,117.50
b Paku 2 cm 0.01 kg 14,700.00 147.00
c Pembantu tukang 0.05 org 40,000.00 2,000.00
d Tukang kayu 0.05 org 55,000.00 2,750.00
Jumlah 7,014.50
Dibulatkan 7,010.00
8 1 M2 PLAFON TRIPLEK 4 MM + RANGKA KAYU BORNEO SUPER
a Balok kayu borneo super 0.02 m3 3,600,000.00 82,800.00
b Paku 1- 12 cm 0.06 kg 14,700.00 882.00
c Triplek 120 cm x 240 cm x 0,4 cm 0.39 lbr 47,500.00 18,525.00
d Pembantu tukang 0.27 org 40,000.00 10,800.00
e Tukang kayu 0.40 org 55,000.00 22,000.00
Jumlah 135,007.00
Dibulatkan 135,000.00
9 1 M2 PLAFON TEAKWOOD 4 MM + RANGKA KAYU BORNEO SUPER
a Balok kayu borneo super 0.02 m3 3,600,000.00 82,800.00
b Paku 1 - 12 cm 0.06 kg 14,700.00 882.00
c Teakwood 120 cm x 240 cm x 0,4 cm 0.39 lbr 80,000.00 31,200.00
d Pembantu tukang 0.27 org 40,000.00 10,800.00
e Tukang kayu 0.40 org 55,000.00 22,000.00
Jumlah 147,682.00
Dibulatkan 147,680.00
10 1 M2 Plafon PAPAN 10 CM, TEBAL 1 CM + RANGKA KAYU BORNEO SUPER
a Balok kayu borneo super 0.02 m3 3,600,000.00 82,800.00
b Paku 2 - 12 cm 0.20 kg 14,700.00 2,940.00
c Papan kayu kamper 0.02 m3 5,000,000.00 100,000.00
d Pembantu tukang 0.35 org 40,000.00 14,000.00
e Tukang kayu 0.50 org 55,000.00 27,500.00
Jumlah 227,240.00
Dibulatkan 227,240.00
11 1 M2 Plafon GYPSUM BOARD, TEBAL 9 MM + RANGKA BESI HOLLOW
a Hollow 4/4 Zincromate 0.42 btg 48,000.00 19,920.00
b Hollow 2/4 Zincromate 0.15 btg 35,000.00 5,250.00
c Gypsum board ( 120 x 240 x 9 ) mm 0.36 lbr 78,000.00 28,392.00
d Paku sekrup 25.00 bh 750.00 18,750.00
e Ramset / dina bolt 4.00 bh 2,200.00 8,800.00
f Cotton plaster 0.07 bh 58,000.00 4,176.00
g Compoun 0.13 kg 32,000.00 4,000.00
h Pembantu tukang 0.10 org 40,000.00 4,000.00
i Tukang kayu 0.05 org 55,000.00 2,750.00
Jumlah 96,038.00
Dibulatkan 96,030.00

XII PEKERJAAN SANITAIR


1 MEMASANG 1 BUAH KLOSET DUDUK / MONOBLOK
a Kloset duduk / monoblok 1.00 bh 2,350,000.00 2,350,000.00
b Perlengkapan ( 10% hrg kloset ) 235,000.00 235,000.00
c Pembantu tukang 3.30 org 40,000.00 132,000.00
d Tukang batu 1.10 org 55,000.00 60,500.00
Jumlah 2,777,500.00
Dibulatkan 2,777,500.00
2 MEMASANG 1 BUAH KLOSET JONGKOK PORSELEN
a Kloset jongkok porselen 1.00 bh 173,000.00 173,000.00
b Semen PC (abu-abu) 0.12 sak 42,000.00 5,040.00
c Pasir pasang 0.01 m3 68,000.00 680.00
d Pembantu tukang 1.00 org 40,000.00 40,000.00
e Tukang batu 1.50 org 55,000.00 82,500.00
Jumlah 301,220.00
Dibulatkan 301,220.00
3 MEMASANG 1 BUAH URINOIR
a Urinoir 1.00 bh 400,000.00 400,000.00
b Perlengkapan ( 30% hrg urinoir ) 120,000.00 120,000.00
c Semen PC (abu-abu) 0.12 sak 42,000.00 5,040.00
d Pasir pasang 0.01 m3 68,000.00 680.00
e Pembantu tukang 1.00 org 40,000.00 40,000.00
f Tukang batu 1.00 org 55,000.00 55,000.00
Jumlah 620,720.00
Dibulatkan 620,720.00
4 MEMASANG 1 BUAH WASTAFEL DINDING
a Wastafel 1.00 bh 215,000.00 215,000.00
b Perlengkapan ( 12% hrg kloset ) 25,800.00 25,800.00
c Semen PC ( abu-abu ) 0.12 sak 42,000.00 5,040.00
3
d Pasir pasang 0.01 m 68,000.00 680.00
e Pembantu tukang 1.20 org 40,000.00 48,000.00
f Tukang batu 1.45 org 55,000.00 79,750.00
Jumlah 374,270.00
Dibulatkan 374,270.00
5 MEMASANG 1 BUAH WASTAFEL KAKI
a Wastafel 1.00 bh 260,000.00 260,000.00
b Perlengkapan ( 12% hrg kloset ) 31,200.00 31,200.00
c Semen PC ( abu-abu ) 0.12 sak 42,000.00 5,040.00
3
d Pasir pasang 0.01 m 68,000.00 680.00
e Pembantu tukang 1.20 org 40,000.00 48,000.00
f Tukang batu 1.45 org 55,000.00 79,750.00
Jumlah 424,670.00
Dibulatkan 424,670.00
6 MEMASANG 1 BH SHOWER DINDING
a Shower dinding 1.00 bh 145,000.00 145,000.00
b Pembantu tukang 0.01 org 40,000.00 400.00
c Tukang batu 0.10 org 55,000.00 5,500.00
Jumlah 150,900.00
Dibulatkan 150,900.00
7 MEMASANG BAK MANDI FIBERGLASS UKURAN SEDANG
a Bak fibreglass 1.00 bh 182,000.00 182,000.00
b Perlengkapan ( 20% hrg bak ) 32,760.00 32,760.00
c Pembantu tukang 1.80 org 40,000.00 72,000.00
d Tukang batu 2.70 org 55,000.00 148,500.00
Jumlah 435,260.00
Dibulatkan 435,260.00
8 MEMASANG BAK KONTROL PASANGAN BATU BATA UKURAN 30 X 30 CM, TINGGI 35 CM
a Batu bata 0.15 m3 600.00 90.00
b Semen PC (abu-abu) 0.88 sak 42,000.00 36,960.00
c Pasir pasang 0.07 m3 68,000.00 4,760.00
d Batu kerikil 0.07 m3 185,000.00 12,950.00
e Besi beton 1.60 kg 16,300.00 26,080.00
f Pasir beton 0.06 m3 72,000.00 4,320.00
g Pembantu tukang 3.20 org 40,000.00 128,000.00
h Tukang batu 1.02 org 55,000.00 56,100.00
Jumlah 269,260.00
Dibulatkan 269,260.00
9 MEMASANG KICHEN ZINK/BAK CUCI PIRING STAINLESS STEEL
a Bak cuci stainless steel 1.00 bh 192,000.00 192,000.00
b Water Drain + Asesories 1.00 Set 85,000.00 85,000.00
c Pembantu tukang 0.03 org 40,000.00 1,200.00
d Tukang batu 0.30 org 55,000.00 16,500.00
Jumlah 294,700.00
Dibulatkan 294,700.00
10 MEMASANG 1 BH KRAN DIAMETER 3/4 " ATAU 1/2 "
a Kran air 1.00 bh 56,000.00 56,000.00
b Perlengkapan ( 2% hrg kran ) 1.00 ls 1,120.00 1,120.00
c Pembantu tukang 0.01 org 40,000.00 400.00
d Tukang batu 0.10 org 55,000.00 5,500.00
Jumlah 63,020.00
Dibulatkan 63,020.00
11 MEMASANG 1 BH KRAN AIR ANGSA
a Kran air angsa 1.00 bh 155,500.00 155,500.00
b Perlengkapan ( 2% hrg kran ) 1.00 ls 3,110.00 3,110.00
c Pembantu tukang 0.01 org 40,000.00 400.00
d Tukang batu 0.10 org 55,000.00 5,500.00
Jumlah 164,510.00
Dibulatkan 164,510.00
12 MEMASANG 1 BH FLOOR DRAIN
a Floor drain 1.00 bh 63,000.00 63,000.00
b Pembantu tukang 0.01 org 40,000.00 400.00
c Tukang batu 0.10 org 55,000.00 5,500.00
Jumlah 68,900.00
Dibulatkan 68,900.00
13 MEMASANG 1 BH TEMPAT SABUN
a Tempat Sabun 1.00 bh 33,000.00 33,000.00
b Pembantu tukang 0.01 org 40,000.00 400.00
c Tukang batu 0.10 org 55,000.00 5,500.00
Jumlah 38,900.00
Dibulatkan 38,900.00

XIII PEKERJAAN PERPIPAAN DAN POMPA


1 MEMASANG 1 M¹ PIPA GALVANIS DIAMETER ½"
a Pipa galvanis dia 1/2" 1.10 M¹ 11,000.00 12,100.00
b Perlengkapan ( 30% harga pipa ) 3,300.00 3,300.00
c Pembantu tukang 0.05 org 40,000.00 2,160.00
d Tukang pipa 0.09 org 55,000.00 4,950.00
Jumlah 22,510.00
Dibulatkan 22,510.00
2 MEMASANG 1 M¹ PIPA GALVANIS DIAMETER ¾"
a Pipa galvanis 1.10 M¹ 18,500.00 20,350.00
b Perlengkapan ( 30% harga pipa ) 5,550.00 5,550.00
c Pembantu tukang 0.05 org 40,000.00 2,160.00
d Tukang pipa 0.09 org 55,000.00 4,950.00
Jumlah 33,010.00
Dibulatkan 33,010.00
3 MEMASANG 1 M¹ PIPA GALVANIS DIAMETER 1"
a Pipa galvanis 1.10 M¹ 30,250.00 33,275.00
b Perlengkapan ( 30% harga pipa ) 9,075.00 9,075.00
c Pembantu tukang 0.05 org 40,000.00 2,160.00
d Tukang pipa 0.09 org 55,000.00 4,950.00
Jumlah 49,460.00
Dibulatkan 49,460.00
4 MEMASANG 1 M¹ PIPA GALVANIS DIAMETER 1½"
a Pipa galvanis 1.10 M¹ 33,000.00 36,300.00
b Perlengkapan ( 30% harga pipa ) 9,900.00 9,900.00
c Pembantu tukang 0.11 org 40,000.00 4,320.00
d Tukang pipa 0.18 org 55,000.00 9,900.00
Jumlah 60,420.00
Dibulatkan 60,420.00
5 MEMASANG 1 M¹ PIPA PVC TYPE D DIAMETER 3"
a Pipa PVC type D 1.10 M¹ 6,700.00 7,370.00
b Perlengkapan ( 30% harga pipa ) 2,010.00 2,010.00
c Pembantu tukang 0.10 org 40,000.00 4,000.00
d Tukang pipa 0.18 org 55,000.00 9,900.00
Jumlah 23,280.00
Dibulatkan 23,280.00
6 MEMASANG 1 M¹ PIPA PVC TYPE D DIAMETER 4"
a Pipa PVC type D 1.10 M¹ 9,000.00 9,900.00
b Perlengkapan ( 30% harga pipa ) 2,700.00 2,700.00
c Pembantu tukang 0.13 org 40,000.00 5,200.00
d Tukang pipa 0.22 org 55,000.00 12,100.00
Jumlah 29,900.00
Dibulatkan 29,900.00
7 MEMASANG 1 M¹ PVC TIPE AW DIAMETER ½"
a Pipa PVC 1.10 M¹ 3,400.00 3,740.00
b Perlengkapan ( 30% harga pipa ) 1,020.00 1,020.00
c Pembantu tukang 0.04 org 40,000.00 1,440.00
d Tukang pipa 0.06 org 55,000.00 3,300.00
Jumlah 9,500.00
Dibulatkan 9,500.00
8 MEMASANG 1 M¹ PVC TIPE AW DIAMETER ¾"
a Pipa PVC 1.10 M¹ 6,675.00 7,342.50
b Perlengkapan ( 30% harga pipa ) 2,002.50 2,002.50
c Pembantu tukang 0.03 org 40,000.00 1,200.00
d Tukang pipa 0.06 org 55,000.00 3,300.00
Jumlah 13,845.00
Dibulatkan 13,840.00
9 MEMASANG 1 M¹ PVC TIPE AW DIAMETER 1"
a Pipa PVC 1.10 M¹ 13,400.00 14,740.00
b Perlengkapan ( 30% harga pipa ) 4,020.00 4,020.00
c Pembantu tukang 0.04 org 40,000.00 1,440.00
d Tukang pipa 0.06 org 55,000.00 3,300.00
Jumlah 23,500.00
Dibulatkan 23,500.00
10 MEMASANG 1 M¹ PVC TIPE AW DIAMETER 2"
a Pipa PVC 1.10 M¹ 18,000.00 19,800.00
b Perlengkapan ( 30% harga pipa ) 5,400.00 5,400.00
c Pembantu tukang 0.05 org 40,000.00 2,160.00
d Tukang pipa 0.09 org 55,000.00 4,950.00
Jumlah 32,310.00
Dibulatkan 32,310.00
11 MEMASANG 1 M¹ PVC TIPE AW DIAMETER 4"
a Pipa PVC 1.10 M¹ 39,000.00 42,900.00
b Perlengkapan ( 30% harga pipa ) 11,700.00 11,700.00
c Pembantu tukang 0.08 org 40,000.00 3,240.00
d Tukang pipa 0.14 org 55,000.00 7,425.00
Jumlah 65,265.00
Dibulatkan 65,260.00
12 MEMBUAT 1 BH SEPTICTANK PASANGAN BATU BATA DAN REMBESAN
a Galian tanah Septictank & rembesan 7.5 m3 30,500.00 228,750.00
b Pasir urug 0.21 m3 66,000.00 13,860.00
c Lantai kerja 2.25 m3 502,500.00 1,130,625.00
d Pasang bata 1 Pc : 2 Psr 15.00 m2 75,200.00 1,128,000.00
e Pelat beton penutup dan balok 0.30 m3 4,032,800.00 1,209,840.00
f Pipa PVC 4 inci AW & perlengkapannya 5.40 M1 39,000.00 210,600.00
g Plesteran 1 Pc : 3 Psr 30.00 m2 23,000.00 690,000.00
h Pasangan ijuk 5.00 IKAT 6,000.00 30,000.00
i Urugan kerikil 3,5 cm 1.05 m3 157,300.00 165,165.00
j Pipa PVC 4 inci AW dilobang 9.00 M1 39,000.00 351,000.00
k Urugan kembali 1.13 m3 8,500.00 9,605.00
l Pembantu tukang 4.00 org 40,000.00 160,000.00
m Tukang batu 3.00 org 55,000.00 165,000.00
Jumlah 5,492,445.00
Dibulatkan 5,492,440.00
13 MEMASANG 1 BH POMPA AIR
a Pompa Air 100 Watt 1.00 bh 925,000.00 925,000.00
b Perlengkapan ( 25% harga pompa ) 231,250.00 231,250.00
c Pembantu tukang 0.08 org 40,000.00 3,240.00
d Tukang Pipa 0.14 org 55,000.00 7,425.00
Jumlah 1,166,915.00
Dibulatkan 1,166,910.00

XIV PEKERJAAN PENUTUP BESI DAN BAJA


1 1 KG PASANG RANGKA ATAP BAJA
a Besi profil WF 1.10 kg 12,000.00 13,200.00
b Meni besi 0.08 kg 19,000.00 1,520.00
c Peralatan las ( 5 % material ) 1.00 ls 660.00 660.00
d Elektroda 0.20 ls 18,000.00 3,600.00
e Tukang besi 0.04 org 55,000.00 2,200.00
f Pembantu tukang 0.06 org 40,000.00 2,400.00
Jumlah 23,580.00
Dibulatkan 23,580.00
2 1 KG PASANG RANGKA ATAP BESI SIKU
a Besi Siku 1.10 kg 12,000.00 13,200.00
b Meni besi 0.10 kg 19,000.00 1,900.00
c Peralatan las ( 5 % material ) 1.00 ls 660.00 660.00
d Elektroda 0.15 ls 18,000.00 2,700.00
e Baud 0.20 kg 16,300.00 3,260.00
f Tukang besi 0.04 org 55,000.00 2,200.00
g Pembantu tukang 0.06 org 40,000.00 2,400.00
Jumlah 26,320.00
Dibulatkan 26,320.00
3 1 KG PASANG GORDING BESI C
a Besi C 1.10 kg 17,500.00 19,250.00
b Meni besi 0.10 kg 19,000.00 1,900.00
c Peralatan las ( 5 % material ) 1.00 ls 962.50 962.50
d Elektroda 0.15 ls 18,000.00 2,700.00
e Baud 0.20 kg 16,300.00 3,260.00
f Tukang besi 0.04 org 55,000.00 2,200.00
g Pembantu tukang 0.06 org 40,000.00 2,400.00
Jumlah 32,672.50
Dibulatkan 32,670.00
4 1 M2 PASANG PINTU ROLLING DOOR BESI
a Rolling door besi 1.00 m2 680,000.00 680,000.00
b Tukang besi 1.50 org 55,000.00 82,500.00
c Pembantu tukang 1.05 org 40,000.00 42,000.00
Jumlah 804,500.00
Dibulatkan 804,500.00
5 1 BH PASANG PINTU BESI UKURAN 0,8 X 2 M
a Pintu besi jadi 1.00 bh 400,000.00 400,000.00
b Tukang besi 1.05 org 55,000.00 57,750.00
c Pembantu tukang 1.05 org 40,000.00 42,000.00
Jumlah 499,750.00
Dibulatkan 499,750.00
6 1 M2 PASANG TERALIS BESI
a Besi strip 2 mm x 3 cm 11.50 M¹ 17,500.00 201,250.00
b Tukang las 1.20 org 55,000.00 66,000.00
c Pembantu tukang 1.20 org 40,000.00 48,000.00
Jumlah 315,250.00
Dibulatkan 315,250.00
7 1 M2 PASANG KAWAT HARMONIKA
a Kawat harmonika 1.10 m2 18,000.00 19,800.00
b Paku 2 - 5 cm 0.02 kg 14,700.00 294.00
c Papan kayu kamper medan - m3 3,800,000.00 6,840.00
d Pembantu tukang 0.10 org 40,000.00 4,000.00
e Tukang kayu 0.10 org 55,000.00 5,500.00
Jumlah 36,434.00
Dibulatkan 36,430.00
8 1 M1 PASANG TALANG DATAR, SENG PLAT BJLS
a Seng plat BJLS 1.00 M1 33,000.00 33,000.00
b Paku 2 - 5 cm 0.02 kg 14,700.00 220.50
c Papan kayu borneo super 0.01 m3 4,000,000.00 38,400.00
d Flincote / meni besi 0.25 kg 20,000.00 5,000.00
e Pembantu tukang 0.15 org 40,000.00 6,000.00
f Tukang kayu 0.40 org 55,000.00 22,000.00
Jumlah 104,620.50
Dibulatkan 104,620.00
9 1 M1 PASANG TALANG MIRING, SENG PLAT BJLS
a Seng plat BJLS 0.50 M1 33,000.00 16,500.00
b Paku 2 - 5 cm 0.02 kg 14,700.00 220.50
c Papan kayu borneo super 0.02 m3 4,000,000.00 76,000.00
d Flincote / meni besi 0.30 kg 20,000.00 6,000.00
e Pembantu tukang 0.04 org 40,000.00 1,600.00
f Tukang kayu 0.40 org 55,000.00 22,000.00
Jumlah 122,320.50
Dibulatkan 122,320.00

XV PEKERJAAN ALUMINIUM
1 1 M2 PASANG PINTU ROLLING DOOR ALUMINIUM
a Rolling door aluminium 1.00 m2 680,000.00 680,000.00
b Tukang besi konstruksi 1.50 org 55,000.00 82,500.00
c Pembantu tukang 1.05 org 40,000.00 42,000.00
Jumlah 804,500.00
Dibulatkan 804,500.00
2 1 M2 PASANG PINTU ALUMINIUM PABRIKAN
a Pintu alluminium 1.00 bh 400,000.00 400,000.00
b Tukang batu 1.05 org 75,671.00 79,454.55
c Pembantu tukang 1.05 org 40,000.00 42,000.00
Jumlah 521,454.55
Dibulatkan 521,450.00
3 1 UNIT KUSEN JENDELA ALUMINIUM 2 LUBANG DGN 2 DAUN JENDELA (UKURAN 1,6 X 1,5 M)
a Profil aluminium 4" natural (+ spare 20 %) 9.24 M1 86,000.00 794,640.00
b Profil daun jendela alm.( + spare 20%) 11.04 M1 80,000.00 883,200.00
2
c Kaca polos 3 mm 2.40 m 63,000.00 151,200.00
d Engsel jendela 4.00 ps 22,000.00 88,000.00
e Grendel jendela 2.00 bh 19,500.00 39,000.00
f Kait angin 2.00 bh 14,000.00 28,000.00
g Acesories ( 6 % harga bahan) 1.00 ls 109,742.40 109,742.40
h Upah pembuatan profil ( 20 % bahan ) 1.00 ls 158,928.00 158,928.00
i Upah pembuatan daun jendela (20 % bahan) 1.00 ls 176,640.00 176,640.00
Jumlah 2,429,350.40
Dibulatkan 2,429,350.00
1 UNIT KUSEN JENDELA ALUMINIUM 3 LUBANG DGN 2 DAUN JENDELA DAN 1 KACA MATI (UKURAN 2 X
4
1,5 M)
a Profil aluminium 4" natural (+ spare 20 %) 12.00 M1 86,000.00 1,032,000.00
b Profil daun jendela alm.( + spare 20%) 11.04 M1 80,000.00 883,200.00
2
c Kaca polos 3 mm 3.00 m 63,000.00 189,000.00
d Engsel jendela 4.00 ps 22,000.00 88,000.00
e Grendel jendela 2.00 bh 19,500.00 39,000.00
f Kait angin 2.00 bh 14,000.00 28,000.00
g Acesories ( 6 % harga bahan ) 1.00 ls 126,252.00 126,252.00
h Upah pembuatan profil ( 20 % bahan ) 1.00 ls 206,400.00 206,400.00
i Upah pembuatan daun jendela (20 % bahan) 1.00 ls 176,640.00 176,640.00
Jumlah 2,385,452.00
Dibulatkan 2,385,450.00
1 UNIT KUSEN PINTU JENDELA GENDONG ALUMINIUM DGN 2 JNDL DAN 1 PNT TEAKWOOD (UKR 2,2 X
5
2,7 M)
a Profil aluminium 4" natural (+ spare 20 %) 17.04 M1 86,000.00 1,465,440.00
b Profil daun jendela alm.( + spare 20%) 14.88 M1 80,000.00 1,190,400.00
2
c Kaca polos 3 mm 3.96 m 63,000.00 249,480.00
2
d Daun pintu teakwood 1.80 m 301,200.00 542,160.00
e Engsel jendela 4.00 ps 22,000.00 88,000.00
f Grendel jendela 2.00 bh 19,500.00 39,000.00
g Kait angin 4.00 bh 14,000.00 56,000.00
h Engsel pintu 3.00 ps 25,000.00 75,000.00
i Grendel pintu 1.00 bh 32,500.00 32,500.00
j Kunci tanam 1.00 bh 20,000.00 20,000.00
k Acesories ( 6 % harga bahan ) 1.00 ls 145,266.00 145,266.00
l Upah pembuatan profil ( 20 % bahan ) 1.00 ls 17,600.00 17,600.00
m Upah pembuatan daun jendela (20 % bahan) 1.00 ls 7,800.00 7,800.00
Jumlah 3,928,646.00
Dibulatkan 3,928,640.00
6 1 UNIT KUSEN PINTU ALUMINIUM UKR 0.9 X 2,7 M
a Profil aluminium 4" natural (+ spare 20 %) 7.56 M1 86,000.00 650,160.00
2
b Kaca polos 3 mm untuk bovenlight 0.45 m 63,000.00 28,350.00
2
c Daun pintu tekwood 1.68 m 301,200.00 506,016.00
d Engsel pintu 3.00 ps 25,000.00 75,000.00
e Grendel pintu 1.00 bh 32,500.00 32,500.00
f Kunci tanam 1.00 bh 20,000.00 20,000.00
g Acesories ( 6 % ) 1.00 ls 40,710.60 40,710.60
h Upah pembuatan profil ( 20 % bahan ) 1.00 ls 130,032.00 130,032.00
Jumlah 1,482,768.60
Dibulatkan 1,482,760.00
7 1 BH BOVENLIGHT ALMUNIUM DENGAN KISI-KISI ALMUNIUM PLAT (UKURAN 0,5 X 1 M)
a Profil Aluminium 4" natural + upah 20% 3.60 M1 63,000.00 226,800.00
b Plat Aluminium untuk Jalusi 5.00 M1 18,000.00 90,000.00
c Acesories ( 6 % ) 1.00 ls 13,608.00 13,608.00
d Upah pembuatan profil ( 20 % bahan ) 1.00 ls 26,006.40 26,006.40
Jumlah 356,414.40
Dibulatkan 356,410.00
8 1 BH BOVENLIGHT ALMUNIUM UKURAN 0,5 X 1 M DENGAN BAGIAN DALAM KACA
a Profil Aluminium 4" natural + upah 20% 3.60 M1 86,000.00 309,600.00
b Kaca Polos 3 mm 0.50 m2 63,000.00 31,500.00
c Acesories ( 6 % ) 1.00 ls 18,576.00 18,576.00
d Upah pembuatan profil ( 20 % bahan ) 1.00 ls 5,201.28 5,201.28
Jumlah 364,877.28
Dibulatkan 364,870.00

XVI PEKERJAAN KACA & PENGGANTUNG


1 1 BUAH PASANG KUNCI TANAM BESAR
a Kunci tanam besar 1.00 bh 175,000.00 175,000.00
b Pembantu tukang 0.06 org 40,000.00 2,400.00
c Tukang kayu 0.60 org 55,000.00 33,000.00
Jumlah 210,400.00
Dibulatkan 210,400.00
2 1 BUAH PASANG KUNCI TANAM SEDANG
a Kunci tanam sedang 1.00 bh 55,000.00 55,000.00
b Pembantu tukang 0.01 org 40,000.00 400.00
c Tukang kayu 0.50 org 55,000.00 27,500.00
Jumlah 82,900.00
Dibulatkan 82,900.00
3 1 BUAH PASANG KUNCI BULAT PUTAR KAMAR MANDI
a Kunci bulat putar kamar mandi 1.00 bh 55,000.00 55,000.00
b Pembantu tukang 0.01 org 40,000.00 200.00
c Tukang kayu 0.50 org 55,000.00 27,500.00
Jumlah 82,700.00
Dibulatkan 82,700.00
4 1 BUAH PASANG ENGSEL PINTU
a Engsel pintu 1.00 bh 25,000.00 25,000.00
b Pembantu tukang 0.02 org 40,000.00 600.00
c Tukang kayu 0.15 org 55,000.00 8,250.00
Jumlah 33,850.00
Dibulatkan 33,850.00
5 1 BUAH PASANG ENGSEL JENDELA KUPU-KUPU
a Engsel jendela 1.00 bh 22,000.00 22,000.00
b Pembantu tukang 0.01 org 40,000.00 400.00
c Tukang kayu 0.10 org 55,000.00 5,500.00
Jumlah 27,900.00
Dibulatkan 27,900.00
6 1 BUAH PASANG KAIT ANGIN
a Kait angin 1.00 bh 14,000.00 14,000.00
b Pembantu tukang 0.02 org 40,000.00 600.00
c Tukang kayu 0.15 org 55,000.00 8,250.00
Jumlah 22,850.00
Dibulatkan 22,850.00
7 1 BUAH PASANG DOOR CLOSER
a Door closer 1.00 bh 412,000.00 412,000.00
b Pembantu tukang 0.05 org 40,000.00 2,000.00
c Tukang kayu 0.50 org 55,000.00 27,500.00
Jumlah 441,500.00
Dibulatkan 441,500.00
8 1 BUAH PASANG PEGANGAN PINTU / DOOR HOLDER
a Door holder 1.00 bh 50,000.00 50,000.00
b Pembantu tukang 0.05 org 40,000.00 2,000.00
c Tukang kayu 0.50 org 55,000.00 27,500.00
Jumlah 79,500.00
Dibulatkan 79,500.00
9 1 BUAH PASANG PENAHAN PINTU / DOOR STOPER
a Door stoper 1.00 bh 65,000.00 65,000.00
b Pembantu tukang 0.05 org 40,000.00 2,000.00
c Tukang kayu 0.50 org 55,000.00 27,500.00
Jumlah 94,500.00
Dibulatkan 94,500.00
10 1 BUAH PASANG GRENDEL / SLOOT PINTU
a Grendel / sloot pintu 1.00 bh 32,500.00 32,500.00
b Pembantu tukang 0.05 org 40,000.00 2,000.00
c Tukang kayu 0.50 org 55,000.00 27,500.00
Jumlah 62,000.00
Dibulatkan 62,000.00
11 1 BUAH PASANG GRENDEL / SLOOT JENDELA
a Grendel / sloot jendela 1.00 bh 19,500.00 19,500.00
b Pembantu tukang 0.05 org 40,000.00 2,000.00
c Tukang kayu 0.50 org 55,000.00 27,500.00
Jumlah 49,000.00
Dibulatkan 49,000.00
12 1 BUAH PASANG TARIKAN JENDELA
a Tarikan jendela 1.00 bh 17,600.00 17,600.00
b Pembantu tukang 0.05 org 40,000.00 2,000.00
c Tukang kayu 0.50 org 55,000.00 27,500.00
Jumlah 47,100.00
Dibulatkan 47,100.00
13 1 M2 PASANG KACA POLOS, TEBAL 3 MM
a Kaca polos 1.10 m2 63,000.00 69,300.00
b Pembantu tukang 0.02 org 40,000.00 600.00
c Tukang kayu 0.15 org 55,000.00 8,250.00
Jumlah 78,150.00
Dibulatkan 78,150.00
14 1 M2 PASANG KACA POLOS, TEBAL 5 MM
a Kaca polos 1.10 m2 85,000.00 93,500.00
b Pembantu tukang 0.02 org 40,000.00 600.00
c Tukang kayu 0.15 org 55,000.00 8,250.00
Jumlah 102,350.00
Dibulatkan 102,350.00
15 1 M2 PASANG KACA RAY BAND, TEBAL 5 MM
a Kaca 1.10 m2 155,000.00 170,500.00
b Pembantu tukang 0.02 org 40,000.00 600.00
c Tukang kayu 0.15 org 55,000.00 8,250.00
Jumlah 179,350.00
Dibulatkan 179,350.00

XVII PEKERJAAN PENGECATAN


1 1 M2 MENGIKIS / MENGEROK / MENGELUPAS PERMUKAAN CAT TEMBOK LAMA
a Soda api 0.05 kg 45,000.00 2,250.00
b Pembantu tukang 0.05 org 40,000.00 2,000.00
c Tukang cat 0.02 org 55,000.00 1,100.00
Jumlah 5,350.00
Dibulatkan 5,350.00
2 1 M2 MENDEMPUL DAN MENGGOSOK KAYU
a Dempul jadi 0.10 kg 24,500.00 2,450.00
b Minyak cat 0.03 kg 20,000.00 600.00
c Ampelas kasar 0.30 lbr 2,500.00 750.00
d Pembantu tukang 0.04 org 40,000.00 1,600.00
e Tukang cat 0.05 org 55,000.00 2,750.00
Jumlah 8,150.00
Dibulatkan 8,150.00
3 1 M2 PENGECATAN KAYU LAMA
a Cat meni 0.25 kg 19,000.00 4,750.00
b Plamir 0.15 kg 22,500.00 3,375.00
c Ampelas 1.00 lbr 2,500.00 2,500.00
d Cat dasar 0.15 kg 40,000.00 6,000.00
e Cat penutup kwalitas baik 0.60 kg 40,000.00 24,000.00
f Pembantu tukang 0.05 org 40,000.00 2,000.00
g Tukang cat 0.15 org 55,000.00 8,250.00
Jumlah 50,875.00
Dibulatkan 50,870.00
4 1 M2 PENGECATAN KAYU BARU
a Cat meni 0.50 kg 19,000.00 9,500.00
b Plamir 0.15 kg 22,500.00 3,375.00
c Ampelas 1.00 lbr 2,500.00 2,500.00
d Cat dasar 0.15 kg 40,000.00 6,000.00
e Cat penutup kwalitas baik 0.35 kg 40,000.00 14,000.00
f Pembantu tukang 0.05 org 40,000.00 2,000.00
g Tukang cat 0.15 org 55,000.00 8,250.00
Jumlah 45,625.00
Dibulatkan 45,620.00
5 1 M2 PENGECATAN KAYU DENGAN POLITUR
a Politur 0.15 Ltr 35,000.00 5,250.00
b Dempul jadi 0.25 kg 24,500.00 6,125.00
c Ampelas 2.00 lbr 2,500.00 5,000.00
d Pembantu tukang 0.05 org 40,000.00 2,000.00
e Tukang cat 0.15 org 55,000.00 8,250.00
Jumlah 26,625.00
Dibulatkan 26,620.00
6 1 M2 PENGECATAN KAYU DENGAN MELAMIK
a Melamik 0.15 Ltr 32,200.00 4,830.00
b Dempul jadi 0.25 kg 24,500.00 6,125.00
c Ampelas 2.00 lbr 2,500.00 5,000.00
d Pembantu tukang 0.05 org 40,000.00 2,000.00
e Tukang cat 0.15 org 55,000.00 8,250.00
Jumlah 26,205.00
Dibulatkan 26,200.00
7 1 M2 PENGECATAN KAYU DENGAN CAT RESIDU/TER
a Residu atau ter 0.35 Ltr 4,300.00 1,505.00
b Pembantu tukang 0.15 org 40,000.00 6,000.00
c Tukang cat 0.02 org 55,000.00 1,100.00
Jumlah 8,605.00
Dibulatkan 8,600.00
8 1 M2 PENGECATAN TEMBOK/Plafon BARU KWALITAS SEDANG
a Plamir 0.10 kg 27,000.00 2,700.00
b Rol cat 0.01 bh 27,400.00 274.00
c Cat penutup kwalitas sedang 0.45 kg 15,000.00 6,750.00
d Steger ( perancah kerja ) 0.01 Ls 70,000.00 700.00
e Ampelas 0.50 lbr 2,500.00 1,250.00
f Pembantu tukang 0.06 org 40,000.00 2,400.00
g Tukang cat 0.20 org 55,000.00 11,000.00
Jumlah 25,074.00
Dibulatkan 25,070.00
9 1 M2 PENGECATAN TEMBOK/Plafon BARU KWALITAS BAIK
a Plamir 0.10 kg 27,000.00 2,700.00
b Rol cat 0.01 bh 27,400.00 274.00
c Cat penutup kwalitas baik 0.50 kg 44,000.00 22,000.00
d Steger ( perancah kerja ) 0.01 Ls 70,000.00 700.00
e Ampelas 0.50 lbr 2,500.00 1,250.00
f Pembantu tukang 0.06 org 40,000.00 2,400.00
g Tukang cat 0.20 org 55,000.00 11,000.00
Jumlah 40,324.00
Dibulatkan 40,320.00
10 1 M2 PENGECATAN TEMBOK LAMA
a Cat penutup kwalitas baik 0.40 kg 28,250.00 11,300.00
b Rol cat 0.01 bh 27,400.00 274.00
c Steger ( perancah kerja ) 0.01 Ls 70,000.00 700.00
d Ampelas 0.50 lbr 2,500.00 1,250.00
e Pembantu tukang 0.06 org 40,000.00 2,400.00
f Tukang cat 0.20 org 55,000.00 11,000.00
Jumlah 26,924.00
Dibulatkan 26,920.00
11 1 M2 PENGECATAN EXTERIOR
a Cat tembok 0.36 kg 78,000.00 28,080.00
b Plamir tembok 0.16 kg 27,000.00 4,320.00
c Rol cat 0.01 bh 27,400.00 274.00
d Steger ( perancah kerja ) 0.01 Ls 70,000.00 700.00
e Ampelas 0.50 lbr 2,500.00 1,250.00
f Pembantu tukang 0.20 org 40,000.00 8,000.00
g Tukang cat 0.30 org 55,000.00 16,500.00
Jumlah 59,124.00
Dibulatkan 59,120.00
12 1 M2 MEMASANG WALLPAPER
a Wallpaper 1.20 m2 17,600.00 21,120.00
b Lem Perekat 0.20 kg 35,000.00 7,000.00
c Pembantu tukang 0.02 org 40,000.00 800.00
d Tukang cat 0.15 org 55,000.00 8,250.00
Jumlah 37,170.00
Dibulatkan 37,170.00
13 1 M2 PENGECATAN PERMUKAAN BAJA DENGAN MENI BESI
a Meni besi 0.10 kg 19,000.00 1,900.00
b Kuas 0.01 bh 14,000.00 140.00
c Pembantu tukang 0.02 org 40,000.00 800.00
d Tukang cat 0.20 org 55,000.00 11,000.00
Jumlah 13,840.00
Dibulatkan 13,840.00
14 1 M2 PENGECATAN PERMUKAAN BAJA DENGAN MENI BESI DAN CAT
a Meni besi 0.10 kg 19,000.00 1,900.00
b Cat besi 0.13 kg 38,500.00 5,005.00
c Kuas 0.01 bh 14,000.00 140.00
d Ampelas 0.50 lbr 2,500.00 1,250.00
e Perancah kayu 0.01 m3 70,000.00 700.00
f Pembantu tukang 0.20 org 40,000.00 8,000.00
g Tukang cat 0.20 org 55,000.00 11,000.00
Jumlah 27,995.00
Dibulatkan 27,990.00

XVIII PEKERJAAN LISTRIK


1 PASANG 1 TITIK STOP KONTAK
a Stop kontak 1.00 bh 21,200.00 21,200.00
b Kabel listrik NYM 3 x 2,5 mm 0.25 rol 445,000.00 111,250.00
c Aksesoris ( 20 % material ) 1.00 ls 22,250.00 22,250.00
d Pembantu tukang 0.20 org 40,000.00 8,000.00
e Tukang listrik 0.60 org 55,000.00 33,000.00
Jumlah 195,700.00
Dibulatkan 195,700.00
2 PASANG 1 TITIK LAMPU
a Saklar 1.00 bh 21,200.00 21,200.00
b Kabel Listrik NYM 2 x 2,5 mm 0.25 rol 425,000.00 106,250.00
c Aksesoris ( 20 % material ) 1.00 ls 21,250.00 21,250.00
d Pembantu tukang 0.20 org 40,000.00 8,000.00
e Tukang listrik 0.60 org 55,000.00 33,000.00
Jumlah 189,700.00
Dibulatkan 189,700.00
3 PASANG 1 BUAH LAMPU SL
a Lampu SL 1.00 bh 58,000.00 58,000.00
b Aksesoris ( 1 % alat ) 1.00 ls 580.00 580.00
c Tukang listrik 0.10 org 55,000.00 5,500.00
Jumlah 64,080.00
Dibulatkan 64,080.00
4 PASANG 1 BUAH LAMPU TL
a Lampu TL 1.00 bh 58,000.00 58,000.00
b Aksesoris ( 1 % alat ) 1.00 ls 580.00 580.00
c Tukang listrik 0.12 org 55,000.00 6,600.00
Jumlah 65,180.00
Dibulatkan 65,180.00
5 PASANG 1 BUAH LAMPU BARET
a Lampu Baret 1.00 bh 90,000.00 90,000.00
b Aksesoris ( 1 % alat ) 1.00 ls 900.00 900.00
c Tukang listrik 0.15 org 55,000.00 8,250.00
Jumlah 99,150.00
Dibulatkan 99,150.00
6 PASANG 1 BUAH LAMPU PIJAR
a Lampu Pijar 1.00 bh 6,000.00 6,000.00
b Aksesoris ( 1 % alat ) 1.00 ls 60.00 60.00
c Tukang listrik 0.10 org 55,000.00 5,500.00
Jumlah 11,560.00
Dibulatkan 11,560.00
7 PASANG 1 BUAH LAMPU TAMAN
a Lampu Taman 1.00 bh 186,000.00 186,000.00
b Aksesoris ( 1 % alat ) 1.00 ls 1,860.00 1,860.00
c Tukang listrik 0.35 org 55,000.00 19,250.00
Jumlah 207,110.00
Dibulatkan 207,110.00
8 PASANG 1 BUAH PANEL
a Panel Listrik standart untuk Rumah 1.00 bh 300,000.00 300,000.00
b Aksesoris ( 10 % alat ) 1.00 ls 30,000.00 30,000.00
c Tukang listrik 1.00 org 55,000.00 55,000.00
Jumlah 385,000.00
Dibulatkan 385,000.00

XIX PEKERJAAN WATERPROOFING


1 PASANG 1 M2 WATERPROOFING MEMBRAN
a Material Primer 2.50 kg 2,450.00 6,125.00
b Waterproofing Membrane 1.10 m2 70,000.00 77,000.00
c Pengetesan ( 10 % material ) 1.00 ls 7,700.00 7,700.00
d Pembantu tukang 0.20 org 40,000.00 8,000.00
e Tukang batu 0.60 org 55,000.00 33,000.00
Jumlah 131,825.00
Dibulatkan 131,820.00
2 PASANG 1 M2 WATERPROOFING COATING
a Pre treatment / Cleaning ( 10 % material ) 1.00 m2 4,500.00 4,500.00
b Bahan Waterproofing Coating 1.00 kg 45,000.00 45,000.00
c Kuas 3 " 0.25 bh 14,000.00 3,500.00
d Pembantu tukang 0.20 org 40,000.00 8,000.00
e Tukang batu 0.60 org 55,000.00 33,000.00
Jumlah 94,000.00
Dibulatkan 94,000.00
3 PASANG 1 M2 FLOOR HARDERNER
a Material Natural non Metalic 1.10 kg 45,000.00 49,500.00
b Aksesoris ( 10 % alat ) 1.00 ls 495.00 495.00
c Pembantu tukang 0.20 org 40,000.00 8,000.00
d Tukang batu 0.60 org 55,000.00 33,000.00
Jumlah 90,995.00
Dibulatkan 90,990.00