Professional Documents
Culture Documents
Question 1
Production:
Monthly Production Monthly Unit Shipments
Valves 7,500 7,500
Pumps 12,500 12,500
Flow Controllers 4,000 4,000
Materials:
Material Costs Total Costs
Valves $ 16.00 $ 120,000.00
Pumps $ 20.00 $ 250,000.00
Flow Controllers $ 22.00 $ 88,000.00
$ 458,000.00
Run Labor:
Dollars per hour $ 16.00
Machine Hours:
Machine Hours Total Machine Hours
Valves 0.5 3750
Pumps 0.5 6250
Flow Controllers 0.2 800
10800
Overhead:
Setup hours Monthly Runs
Valves 8 1
Pumps 8 5
Flow Controllers 12 10
Manufacturing Overhead:
Receiving $ 20,000.00
Materials Handling $ 200,000.00
Engineering $ 100,000.00
Packing & Shipping $ 60,000.00
Maintenance $ 30,000.00
Machine Depreciation $ 270,000.00
Total $ 680,000.00
Total Overhead:
Total Setup Overhead $ 2,688.00
Total Manufacturing Overhead $ 680,000.00
Total $ 682,688.00
Valves Pumps
Overhead $ 131,623.65 $ 438,745.50
Direct Labor $ 30,000.00 $ 100,000.00
Total Material $ 120,000.00 $ 250,000.00
Total Cost $ 281,623.65 $ 788,745.50
Total Units 7,500 12,500
Unit Cost $ 37.55 $ 63.10
Shipments
1
7
22
Contribution Margin:
Valves Pumps Flow Controllers
Revenues $ 433,350.00 $ 1,015,750.00 $ 388,280.00
Variable Costs $ 150,000.00 $ 350,000.00 $ 113,600.00
Total Contribution Margin $ 283,350.00 $ 665,750.00 $ 274,680.00
To find the contribution margin you must calculate the total revenue and
subtract it by the variable cost. To find the revenue I took the actual selling
price of each of the components and multiplied it by the monthly production.
Then I found the variable costs by adding the direct labor cost and the total
material cost of each unit. Then by subtracting these two I found the
contribution margin.
Question 3
Production:
Monthly Production
Valves 7500
Pumps 12500
Flow Controllers 4000
Materials Overhead:
Receiving $ 20,000.00
Materials Handling $ 200,000.00
$ 220,000.00
Materials:
Material Cost Total Material Costs Percentage
Valves $ 16.00 $ 120,000.00 26%
Pumps $ 20.00 $ 250,000.00 55%
Flow Controllers $ 22.00 $ 88,000.00 19%
$ 458,000.00
Labor:
Total cost for run Total Cost for setup
Valves $ 30,000.00 $ 128.00
Pumps $ 100,000.00 $ 640.00
Flow Controllers $ 25,600.00 $ 1,920.00
$ 155,600.00 $ 2,688.00
Machine Hours:
Machine Hours Total Machine Hours Percentage
Valves 0.5 3750 35%
Pumps 0.5 6250 58%
Flow 0.2 800 7%
10800
Overhead:
Engineering $ 100,000.00
Packing & Shipping $ 60,000.00
Maintenance $ 30,000.00
Machine Depreciation $ 270,000.00
Total $ 460,000.00
Predetermined OH 4259%
ABC Method:
Valves Pumps Flow Controllers
Receiving $ 600.00 $ 3,800.00 $ 15,600.00
Materials Handling
Once per receipt (60%) $ 3,600.00 $ 22,800.00 $ 93,600.00
Once per run (40%) $ 2,400.00 $ 15,200.00 $ 62,400.00
Packing & Shipping $ 2,400.00 $ 13,800.00 $ 43,800.00
Engineering $ 20,000.00 $ 30,000.00 $ 50,000.00
Depreciation & Maintenance $ 105,000.00 $ 174,000.00 $ 21,000.00
Direct Labor $ 30,000.00 $ 100,000.00 $ 25,600.00
Setup Labor $ 128.00 $ 640.00 $ 1,920.00
Total Material $ 120,000.00 $ 250,000.00 $ 88,000.00
Total Cost $ 284,128.00 $ 610,240.00 $ 401,920.00
Total Units 7500 12500 4000
Unit Cost $ 37.88 $ 48.82 $ 100.48
Question 5
Net Income:
Valves Pumps Flow Controllers
Revenue $ 433,350.00 $ 1,015,750.00 $ 388,280.00
Variable Costs $ 150,000.00 $ 350,000.00 $ 113,600.00
Contribution Margin $ 283,350.00 $ 665,750.00 $ 274,680.00
Fixed Costs $ 131,623.65 $ 438,745.50 $ 112,318.85
Net Income $ 151,726.35 $ 227,004.50 $ 162,361.15
Current System:
Valves Pumps Flow Controllers
Total Units 7,500 12,500 4,000
Unit Cost $ 37.55 $ 63.10 $ 56.48
Selling Price $ 57.78 $ 81.26 $ 97.07
Gross Margin per unit $ 20.23 $ 18.16 $ 40.59
Gross Margin % per unit 0.005% 0.002% 0.010%
ABC Method:
Total Units 7500 12500 4000
Unit Cost $ 37.88 $ 48.82 $ 100.48
Selling Price $ 57.78 $ 81.26 $ 97.07
Gross Margin per unit $ 19.90 $ 32.44 $ (3.41)
Gross Margin % per unit 0.005% 0.003% -0.001%
Original Flow Controllers ABC Information Flow Controllers Price Increase 10%
Flow Controllers
Units 4,000 4000
Unit Cost $ 100.48 $ 100.48
Selling Price $ 97.07 $ 106.78