Professional Documents
Culture Documents
Page
8474L 000 JSD 2220 001 2 2 / 51
CONTENTS
TABLES 3
1. SCOPE 4
2. REFERENCES 4
3. DESIGN - GENERAL 6
5. DESIGN - EQUIPMENT 8
6. MATERIALS - GENERAL 20
13. APPLICATION VERTICAL VESSELS AND PIPE GREATER THAN 900MM (36") OD
29
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 3 / 51
TABLES
FIGURES
FIGURE 1: PIPING 33 to 37
FIGURE 2: REMOVABLE COVERS FOR FLANGED VALVES 38 to 39
FIGURE 3: REMOVABLE COVERS FOR FLANGED JOINTS 40 to 41
FIGURE 4: VERTICAL EQUIPMENT 42 to 45
FIGURE 5: HORIZONTAL EQUIPMENT 46 to 48
FIGURE 6: ACCOUSTIC INSULATION 49 to 50
FIGURE 7: PERSONNEL PROTECTION 51
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 4 / 51
1. SCOPE
1.1 This Job specification is developed from FEED document 6960-8440-SP-0003Rev D2.
1.2 This Job specification covers the use of thermal insulation for above ground, external insulation of
piping and equipment in cold service between minus 100°C and plus 35°C for the purpose of
reducing heat gain, process stabilisation and the prevention of condensate accumulation.
1.3 The insulation requirements of this Job Specification are suitable for use in both indoor and
outdoor service with normal process plant atmospheres. Alternative designs and materials shall be
considered if necessary for highly corrosive atmospheres or potential leaks and spills of chemicals.
1.4 This Job specification does not cover hot service insulation. For hot service insulation
requirements, refer to Job specification 8474L-000-JSD-2210-001.
1.5 This Job specification shall be read in conjunction with Licensor and Vietnamese mandatory
Project Standards, codes and regulations that also apply. In the event of any conflict between this
Project Standard, those documents and industry codes and Project Standards, Contractor shall seek
clarification from PetroVietnam before proceeding.
2. REFERENCES
The following documentation is referenced within the text of this Project Standard
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 5 / 51
ASTM C177 Standard test method for Steady-State heat Flux measurements and
Thermal transmission Properties by Means of the Guarded Hot-
Plate Apparatus
ASTM D696 Standard test Method for Coefficient of Thermal expansion of
Plastics between -30°C and 30°C with a Vitreous Silica
Dilatometer
ASTM D1621 Standard Test Method for Compressive Properties of Rigid
Cellular Plastics
ASTM D1622 Standard Test Method for Apparent Density of Rigid Cellular
Plastics
ASTM D1623 Standard Test Method for Tensile and Tensile Adhesion Properties
of Rigid Cellular Plastics
ASTM D2865 Standard Test Method for Open-Cell Content of Rigid Cellular
Plastics by the Air Pycnometer
ASTM E96 Test Method for Water Vapour Transmission of Materials
EEMUA 142 Acoustic Insulation of Pipes, Valves and Flanges
BS EN 10025 Hot rolled products of non-alloy structural steels. Technical
delivery conditions
BS EN 10215 Continuously hot dip zinc-aluminium coated steel strip and sheet.
Technical delivery conditions
BS 476, Pt. 7 Method of test to determine the classification of the surface spread
of flame of products
BS EN 10147 Specification for continuously hot-dip zinc coated structural steel
sheet and strip. Technical delivery conditions
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 6 / 51
3. DESIGN - GENERAL
3.1 In this Project Standard, insulation for reducing heat gain is designed to provide thicknesses that
limit the heat gain to 25W/m2 and that result in hot face surface temperatures that minimise the
formation of condensation in ambient air temperature of 35°C.
3.2 Contractor shall install personnel protection for unlined equipment and piping with exposed surface
temperatures of minus 10°C and below.
3.3 Contractor shall identify equipment and piping requiring acoustic attenuation insulation in
accordance with Project Standard 8474L-000-JSD-6000-001.
3.4 Contractor shall identify Items requiring low level vapour relief load and systems required to
operate during a fire, for fire protection insulation.
3.5 Equipment, vessels and piping shall be insulated with the thickness of insulation appropriate to the
insulation classification and operating temperature.
3.7 Contractor shall ensure that the design of the insulation system, including the selection of
adhesives, weather coatings, vapour seals and joint sealers takes into account that piping and
equipment may be subject to elevated temperatures during purging, cleaning and flushing
operations.
3.8 Each line shall be insulated as a single unit. A minimum clearance of 50mm shall be maintained
between the outer surface of insulation and any obstruction such as structural steel, electrical
conduit, piping or other insulated lines.
3.9 Instruments and associated piping subject to operating flow and/or temperature conditions
approximating those in the piping or equipment to which they are connected, shall be insulated to
the same requirements as that piping or equipment in accordance with Table 1.
3.10 Contractor shall identify all equipment and piping where differential thermal movements exceed
15mm. For all such equipment and piping, insulation contraction joints shall be provided and shall
be positioned under insulation layer support rings, clips and lugs when they are used. Contraction
joints shall be constructed as stated in Section 17.
3.11 Insulation for vessels and similar equipment shall be adequately supported by clips and supports
lugs, welded around the equipment item. Contractor shall submit details of support lugs for
PetroVietnam review and approval.
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 7 / 51
3.12 On vertical pipe lines or lines inclined more than 45° from horizontal where straight runs are in
excess of 3m length, a bolted insulation support shall be installed at the bottom and every 3m
thereafter.
3.13 The width of support rings shall be such that the inner layer(s) and one-half of the outer layer of the
insulation shall be supported.
3.14 Pipe supports and hangers shall be attached to the outside of the insulation and shall not be in
contact with the pipe.
3.15 For fire hazard protection stainless steel sheeting of 0.5mm thk shall be used for piping up to
200mm (8 ins) NPS and 0.8mm thk for piping 200mm (8 ins) NPS and greater, including
equipment.
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 8 / 51
4.1 Piping systems requiring insulation shall be fully insulated, including all piping fittings and
components together with supports, piping and tubing of insulated instruments, drains, valves and
flanged joints. Valves shall be insulated up to the packing gland.
4.2 Insulation shall not be applied to piping and piping components which become cold intermittently
(i.e. blowdown or pumpout systems, drain or filling systems etc) unless required for acoustic
attenuation, personnel protection or as otherwise specified by PetroVietnam. If this piping is
connected to an insulated cold source, it shall be treated as a projection and insulated in accordance
with paragraph 4.3.
4.3 All metal protrusions through the insulation shall be insulated in accordance with Table 3.
Protruding metal parts include, but are not limited to, pipe trunnion supports, pipe support clips,
pipe hangers and uninsulated piping connections such as vents, sample connections and uninsulated
instrumentation.
5. DESIGN - EQUIPMENT
5.1 Equipment items requiring insulation shall be fully insulated including all nozzles, manways,
bolted flanges, stiffener rings, exchanger channels and bonnet flanges.
5.2 Insulation shall not be applied to pumps, fans, compressors, blowers or other rotating or
reciprocating equipment unless required for acoustic attenuation, personnel protection or as
otherwise specified by PetroVietnam.
5.3 Vessels and their skirts or saddles shall be thermally isolated from their holding down bolts.
Hardwood blocks or other suitable material shall be used for this purpose.
5.4 Where equipment is supported on metal saddles, the insulation shall be carried down the saddle to
the junction of the saddle and the thermal isolation material. The vapour barrier shall continue
down over the isolation material.
5.5 Where equipment is supported through the use of attached support lugs resting on unattached
structural steel members, the insulation shall be extended not less than four times, the insulation
thickness in each direction, measured from junction of equipment with insulated support lug.
Thickness of insulation over structural steel members shall be one-half that specified for body of
equipment. Thickness of insulation over support lugs shall be the same as the body insulation.
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 9 / 51
5.6 Equipment support legs shall be insulated with insulation blocks as part of equipment area.
Insulation is to extend down legs a distance of four times, insulation thickness, measured from
leg/equipment junction. Thickness shall be as specified for body of equipment. The body
insulation shall be brought up to and butted firmly against the leg flange. Spaces between flange
and webs of structural members shall be filled with block cemented in place with specified
insulation adhesive.
5.7 Skirts supporting vertical equipment shall be insulated inside and outside. Insulation shall extend
downward from junction of skirt with bottom head for a distance of not less than four times the
thickness of insulation, but in no case less than 300mm. Thickness shall be specified for body of
equipment. Insulation shall be secured to inside of skirt with specified insulation adhesive.
Insulation inside skirt shall be supported on angle or plate support.
5.8 All metal such as insulation support rings or stiffeners except vacuum stiffening rings, which are an
integral part of the vessel, shall be insulated with two thirds the total of multi-layer insulation
thickness with thicknesses rounded up to the nearest 10mm. Full thickness insulation is required
for single layer application.
5.9 For metal projections not provided with insulation for the entire length, vapour weather barrier
material shall be continued along the uninsulated metal for a minimum of 150mm to ensure a tight
joint. A low operating temperature valve bonnet extension through the insulation represents a
specialised case of metal projection. A mastic seal shall be provided between the bonnet and the
insulation around it, as well as providing a continuance of the vapour barrier along the metal.
5.10 The insulation shall be taken over any nameplate without a break. The position of the nameplate
shall be marked on the outer covering and where warning notices occur, these shall be copied on
the outside of the insulation finish. A duplicate nameplate shall be installed over the outside
surface of the insulation system. The method of attachment used shall not puncture the vapour seal.
Before insulation work is commenced, Contractor shall make a certified copy or rubbing of the
nameplate and submit to PetroVietnam.
5.11 The pre-insulation of vertical vessels in the horizontal position prior to erection is not permitted.
Prevention of heat gain Table No. 3A or Normal operating temp of Each defined section of Equipment
(process lines) where 3B process fluid and nominal operating at different temps. may be
normal operating pipe size. insulated to suit its individual temp.
temps. are below 35°C. For shell and tube exchanger shells and
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 10 / 51
Personnel protection Refer to Table 3A Refer to Figure 7 Over piping and equipment provide
(Stood-off metal guard) open mesh metal guards over
surfaces which would normally be
left uninsulated and which may be
accessible. See Note 1.
Acoustic attenuation for Table 4 Acoustic Category Mineral fibre insulation applied under
noise control at various Attenuation subject to cold service insulation system to
level of requirement. calculated insertion loss achieve attenuation.
requirements.
Fire protection required Table 3B Normal operating temp of Insulation to be applied in two
in addition to process fluid and nominal layers and checked against
prevention of heat gain pipe size. required fire rating.
-
Not insulated - -
Note: 1. Exposed surfaces below minus 10°C and located within 600mm horizontally or 2100mm vertically of a normal access,
walkway, or work area. Pipe and equipment designated for personnel protection shall be fully painted in accordance with
Project Standard 8474L-000-JSD-2310-001.
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 11 / 51
Straight Pipe 150mm (6") Pre-formed pipe sections 12mm wide stainless steel
band.
NPS and below
Welded valves and All sizes Oversized sections and lags As for "straight pipe"
butt-weld tees and as per "straight" pipe cut and
reducers shaped to fit.
Bends and Elbows All sizes As for "straight pipe" cut and As for "straight pipe"
shaped to fit.
Flanged Valves All sizes Oversized sections and lags As for "straight pipe"
and Joints as per "straight pipe" cut and
shaped to fit.
Equipment Heads Up to 900mm Flat blocks shaped to fit. 20mm wide stainless steel
bands.
(See Note 1) (36") O/D
Equipment Shells 750mm (30") As for "straight pipe" in sets. 20mm wide stainless steel
bands.
O/D and below
Radiused and bevelled lags
in sets. 20mm wide stainless steel
Above 750mm (30") O/D up
bands.
to 3600mm (140") O/D
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 12 / 51
Casings of Pumps, All sizes Flat blocks cut and shaped to Adhesive tape as necessary
Manholes and fit. to secure.
Handholes,
Exchanger
Channels
Note: 1. Bottom heads enclosed with weather protective support skirt shall not require metal cover finish. . For fire hazard protection
stainless steel sheeting 0.5 mm thk. shall be used for piping up to 200mm (8ins) NPS and 0.8 mm thk for piping 200mm (8 ins)
and greater, including equipment.
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 13 / 51
TABLE 2: INSULATION, VAPOUR BARRIER AND METAL COVER, FORM AND SECUREMENT
METHOD (cont.)
Straight Pipe Two coats of Up to 150mm (6") 0.8mm thick 12mm wide stainless
continuous membrane steel bands.
reinforced vapour
barrier mastic 150mm (6") up to 1.0mm thick
450mm (18")
Welded valves and As for "straight pipe" All sizes As for "straight pipe" As for "straight pipe"
butt-weld tees and
reducers
Bends and Elbows As for "straight pipe" All sizes As for "straight pipe" As for "straight pipe"
Flanged Valves and As for "straight pipe" All sizes 1.2mm thick As for "straight pipe"
Joints
Equipment Heads Two coats of All sizes 1.2mm thick 20mm wide stainless
continuous membrane steel bands.
(See Note 1)
reinforced vapour
barrier mastic.
Equipment Shells Two coats of All sizes 1.2mm thick 20mm wide stainless
continuous membrane steel bands.
reinforced vapour
barrier mastic.
Casings of Pumps, As for "Equipment As for "Equipment 1.2mm thick 20mm wide stainless
Manholes and Heads". Heads" steel bands.
Handholes,
Exchanger Channels
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 14 / 51
Note 1: Bottom heads enclosed with weather protective support skirt shall not require metal cover finish. For fire hazard
protection stainless steel sheeting of 0.5mm thk shall be used for piping up to 200mm (8 ins) NPS and 0.8mm thk for
piping 200mm (8 ins) NPS and greater, including equipment.
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 15 / 51
Nominal Pipe
Size
+35 to +1 0 to -20 -21 to -40 -41 to -60 -61 to -80 -81 to -100
0.5 25 30 40 50 60 70
0.75 25 40 50 60 60 70
1 25 40 50 60 70 80
1.5 25 40 50 60 70 80
2 30 40 50 70 80 90
3 30 50 60 70 80 100
4 30 50 60 80 90 100
6 40 50 70 80 100 110
8 40 50 70 90 100 120
10 40 60 70 90 110 120
12 40 60 80 90 110 130
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 16 / 51
Design Basis:
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 17 / 51
Nominal Pipe
Size
+35 to +1 0 to -20 -21 to -40 -41 to -60 -61 to -80 -81 to -100
(inches)
1” & smaller 40 50 60 70 80 90
1½” 40 50 70 80 90 100
2” 40 60 70 80 90 100
3” 40 60 70 90 100 110
4” 50 60 80 90 100 110
6” 50 70 80 100 110 120
8” 50 70 90 100 120 130
Design Basis:
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 18 / 51
70 30/40
80 40/40
90 50/40
100 50/50
110 50/60
120 30/40/50
130 30/50/50
140 40/50/50
150 50/50/50
160 50/60/50
180 50/80/50
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 19 / 51
A 50 0.70 Aluminium or
Stainless Steel
Stainless Steel only
B 100 0.70
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 20 / 51
6. MATERIALS - GENERAL
6.1 All materials covered by this Project Standard shall be of high quality, good appearance, and shall
not have any deleterious action on the surface to be insulated.
6.2 Insulation materials shall be chemically inert, non-sulphurous, water-repellent, rot proof, vermin
proof, impervious to hot water and steam, non-injurious to health and non-corrosive to equipment
or piping materials, (even if soaked with water at ambient temperatures for extended periods).
6.3 Pre-formed insulating materials shall be manufactured at the manufacturers works and transported
to the application site in properly constructed packaging cartons or crates. Contractor shall ensure
that all insulation materials are properly stored at the application site in suitably weatherproofed
storage areas.
6.4 The use of insulation materials containing ASBESTOS in any form is not permitted.
6.5 Insulation and jacketing materials backed with paper or other flammable material is not acceptable.
6.6 Precautions shall be taken against liquid metal embrittlement as specified in Project Standard
8474L-000-CN-0008-005.
7.1 Insulation material shall be either Polyisocynurate (PIR) or Cellular Glass and shall conform to the
requirement detailed in the following paragraphs.
7.2 The cellular glass shall be of a glass thermal insulation material composed of numerous
hermetically sealed cells. The material shall be made by expanding molten glass to approximately
15 times in volume. The cellular glass shall be totally inorganic and contain no binders.
7.3 The insulation material shall be supplied plain faced in manufacturer's standard sizes. Single or
multi layer insulation shall be supplied as defined by Contractor.
7.4 In addition to the above, the Cellular Glass insulation shall have the following physical properties:-
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 21 / 51
-10 0.036
0 0.039
+10 0.0378
7.6 The bun stock shall be foamed and cured at manufacturer’s factory. Only cutting and fabrication
from bun stock can be performed at site.
7.7 The insulation material shall be supplied in manufacturer’s standard sizes. Single or multi layer
insulation shall be supplied as defined by Contractor.
7.8 In addit ion to the above, the Polyisocyanurate insulation shall have the following physical
properties:
Water Vapour Permanence at 38°C & 100% RH. 5ug/Ns max. to ASTM E96
Flame Spread Less than 25 to ASTM E84
Class 1 to BS476 Part 7.
Coefficient of Thermal Expansion and Contraction 40-70 × 10-6mm/mmK to ASTM D696
Compressive strength minimum value of all directions. 200kPa min. value to ASTM D1621
Tensile strength minimum value of all directions. 300 kPa min. value to ASTM D1623
Leachable halide content 60 ppm maximum
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 22 / 51
7.9 Low density mineral fibre slabs or blanket (unfaced) for application at contraction joints, also
valves and flange joints as in-fill material shall have the following minimum properties:
7.10 Semi-rigid mineral fibre for acoustic attenuation requirements shall meet the following
requirements:
8.1 The selection of Aluminium material in both coil and flat sheeting form for use as the thermal
insulation protective metal cover shall take precedent over other metallic coverings with the
exception of fire hazard protection and acoustic insulation Classes B&C, where stainless steel
covering shall be used.
8.2 Aluminium jacketing shall be flat mill finished commercial grade of alloy AlMn in accordance
with ASTM B209 Alloy 3003 - H14 or H16. Stainless steel jacketing required for fireproofing
purposes and acoustic insulation classes B&C shall be flat mill finished grade 2B of steel to comply
with ASTM A167, A40, Type 304 or 316.
8.3 Aluminium metal jacketing shall be supplied with factory applied reflective and protective barrier
coating of polyethylene and aluminium foil which shall comply with BS 476 Part 7, Class 1. The
backing shall be directly laminated to the aluminium without use of adhesives or glue. Thicknesses
shall be as indicated in Table 2.
8.4 Coated mild steels may be selected by Contractor subject to prior PetroVietnam review and
approval. If permitted, either flat aluzinc, flat galvanised or flat aluminised mild steels shall be in
accordance with the following qualities:
• Aluzinc - Alloyed Carbon Steel. Quality to meet BS EN 10215. The weight of aluzinc alloy shall
not be less than 185 g/m2 including both sides of sheeting.
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 23 / 51
• Galvanised Carbon Steel. Quality to meet BS EN 10147 with coating finish 'M' and surface quality
'M' and chemically passivated.
• Aluminised Carbon Steel. Quality to meet ASTM A463-88 T2 100 C. The weight of aluminium
coating shall not be less than 305gr/m2 including both sides.
• The thickness of mild steel weatherproof jacket shall be as specified for Aluminium and
exclusive of coating thickness.
9.1 The outer layer vapour barrier used to seal all piping and equipment insulation against the ingress
of moisture, shall be a fire resistant mastic possessing good flexibility and based on a solution of
copolymer of vinyl chloride and vinyl isobutyl ether in blend with high boiling aromatic solvent
and cyclohexanone; and pigmented with neutral pigments and aluminium paste. Vapour barrier
mastic shall be applied to a total nominal dry film thickness of 3mm.
9.3 The joint sealant used to seal all insulation joints on pipework and equipment shall be based on
marine oil (blend of fish oils) pigmented with neutral fillers and alumin ium paste, dissolved in a
small quantity of xylol. The material shall have the following properties:
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 24 / 51
9.4 The fabrication adhesive used for bonding together pieces of prefabricated cellular glass insulation
for fittings, flange covers and valves, also for joint bonding at contraction joints in vertical
pipework shall be a fire resistant one pack grey paste of trowelling consistency composed of
medium oil le ngth alkyd resin solution in xylol, pigmented with neutral fillers, and having the
following properties:
9.5 The metal sealant suitable for gun extrusion at all metal overlays shall be a tough, durable sealant
consisting of a metallic and mineral pigment filled co-polymer resin solution with the following
properties:
9.6 The heat resistant sealant for use in flashing of protrusions shall be a grey, high solids content
flexible compound, based on selected oils and of a soft paste consistency of an approved type, with
the following properties:
9.7 To reduce abrasion from vibration, expansion and contraction of vessels and piping, an anti-
abrasion compound shall be applied which is non-flammable and fire resistant to the inner surfaces
of cellular glass.
9.8 Adhesive for securing ins ulation to metal surfaces shall be a two part adhesive compound of
polyurethane modified bitumen.
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 25 / 51
10.1 Adhesive tape used to secure all inner layers of insulation where applied to pipework and
equipment in two layers, shall be a pressure-sensitive glass fibre reinforced tape 19mm wide.
10.2 Bands and seals for securing pipework and equipment insulation and jacketing shall be Type 304
stainless steel, soft annealed temper. Bands shall be in handable coils 0.5mm thick ready to be cut
as required in width sizes as shown in Table 2.
10.3 Reinforcing membrane for embedding between coats of the vapour barrier mastic shall be open
weave glass cloth No. 10 having 18 x 12 threads per 25mm and with a weave lock finish.
10.4 Toggle fasteners to secure removable boxes shall be of quick release, spring shackle lock type and
shall be sized commensurate with the weight of the box concerned. All fasteners shall be
constructed from stainless steel.
10.5 Rivets required for metal jacket fabrication shall be the expanding Monel 'pop' blind eye type,
9.5mm long x 5mm diameter.
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 26 / 51
11.1 Piping and equipment shall have all welding completed and shall be hydrostatically or
pneumatically tested prior to application of insulation. Surfaces to be insulated shall be free of all
oil, grease, loose scale and foreign matter and shall be dry.
11.2 All lines and equipment scheduled for cold insulation shall be coated in accordance with Project
Standard 8474L-000-JSD-2310-001.
11.3 Site touch-up of the shop coating including preparation and painting at field welds shall be
completed prior to commencement of insulation.
11.4 Insulation for fittings, flanges and valves shall be the same thickness as the insulation of the pipe.
11.5 Stiffener rings where provided on vacuum equipment and/or piping shall be insulated with the
same thickness of insulation as specified for that piece of equipment or piping. The rings shall be
fully insulated independent of the equipment or piping.
11.6 Initial layers of insulation shall be applied with all joints tightly butted and staggered relative to
each other.
11.7 Additional layers of insulation, where required, shall be applied in the same manner as the first
layer with side and end joints staggered between joints of preceding layers, so that no two joints
coincide.
11.8 All joints of single layer or outermost layers of multi-layer insulation, with the exception of
contraction joint locations, shall be buttered with specified joint sealer before installation. In multi-
layer constructions, the first la yer shall be applied without sealant. The joints shall be tightly
drawn together when insulation is applied so that only a very thin joint seal remains.
11.9 Insulation shall be applied with all joints fitted to eliminate voids. Large voids shall not be fille d
with vapour seal coating, but eliminated by refitting or replacing insulation.
11.10 Each line shall be insulated as a single unit. Adjacent lines shall not be enclosed within a common
insulating cover.
11.11 The face of the insulation in contact with the steel surfaces shall be given a coat of anti-abrasion
compound prior to erection.
11.12 Whenever the application of mastic is referred to in this Project Standard, it shall be applied in two
coats (with reinforcing fabric as specified) to obtain a total dry thickness as recommended by the
manufacturer, but not less than 2.4mm. The mastic shall be applied as a continuous moisture
vapour mastic covering.
11.13 All insulation materials listed in this Project Standard shall be kept dry and shall be applied only to
thoroughly dry, frost free surfaces.
11.14 All insulation material applied in one day shall have at least one coat of the vapour barrier applied
the same day. If impractical to apply the first coat of the vapour barrier, exposed insulation shall be
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 27 / 51
temporarily protected with a moisture barrier, such as an appropriate polyethylene film, and sealed
to the pipe of equipment surface. All exposed ends shall be protected before work stoppage.
11.15 Vapour stops shall be installed at all directly attached pipe support locations and at locations
requiring potential maintenance, such as valves, flanges and instrumentation connections to piping
or equipment. If specified by PetroVietnam, that certain valves and flanges are required to be left
uninsulated until after plant start-up, temporary vapour stops shall be installed.
11.16 No holes, thin spots or open joints in the vapour barrier shall be allowed. The vapour barrier shall
be installed in such a manner than no area of the insulation is exposed to the atmosphere.
11.17 Metal jacketing fabrication shall not result in the mastic vapour barrier being punctured.
11.18 Wire shall not be used to secure the insulating system. During construction, glass fibre filament
tape shall be used to secure the inner layer(s) of the insulation and stainless steel bands for the outer
layer. The sheet metal jacketing shall be secured with stainless steel bands. The type and method
of securing insulation and jacketing is summarised in Table 2.
11.19 Insulation for vessel manways, exchanger channels and bonnet flanges shall be equal in thickness
and type to that applied to the main equipment. The insulation shall be applied similar to the
equipment with all voids kept to a minimum and packed with glass fibre insulation where
unavoidable. All joints shall be tightly fitted together and staggered where possible. Metal jacket
is required in the form of removable boxes after the application of the vapour barrier.
12.1 Insulation to the specified thickness shall be applied by the use of pre-formed two (2) half pipe
sections wherever possible. For diameters where half sections are not available, multi-segments or
radiused and bevelled lags shall be used.
12.2 Insulation shall be applied starting with a full length piece and a half length piece so as to stagger
the circumferential joints. When more than one layer is employed, the joints in the second layer
shall not match the joints of the previous layer.
12.3 When applying Cellular Glass the bore of the inner layer shall be coated with a thin application (to
fill surface cells only) of anti-abrasion compound and allowed to dry before application of
insulation to the surface.
12.4 All joints of single or outermost layers of insulation, with the exception of contraction joints, shall
be buttered with the specified joint sealer before installation and then firmly butted together.
12.5 Inner insulation layers applied in two half sections, shall be secured with 19mm wide
pressure-sensitive filament tape bands spaced at 220mm maximum centres applied with a 50%
overlap. Single or outer layers and where inner layers are applied in radiused and bevelled
segments, securing shall be by 12mm wide x 0.5mm thick stainless steel bands at 220mm
maximum centres, machine tensioned and sealed.
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 28 / 51
12.6 Insulation on be nt pipe shall be neatly cut and mitred to suit the contour of the bend. All the
external surfaces of the insulation shall be rasped smooth to facilitate the vapour barrier.
12.7 Insulation of flanges, flanged fittings and valves shall consist of prefabricated fitting covers of the
same material and thickness and applied in the same manner as specified for pipe insulation. The
insulation shall stop short of studs and/or nuts to permit easy removal without damage to the
insulation. Voids created by stopping short at studs and/or nuts shall be packed with glass fibre in-
fill material. Securing bands shall be so located that maximum strength and security is obtained.
12.8 The installed insulation shall be vapour sealed with a vapour barrier as follows:
A thin coat of mastic shall be sprayed or trowelled on to a minimum thickness. While the mastic is
still tacky, an open weave reinforcing fabric shall be laid smoothly and thoroughly embedded in the
coating. Care shall be exercised that the weave does not rupture and, the fabric shall be overlapped a
minimum of 80mm at joints to provide strength equal to that maintained elsewhere. Before the first
coat becomes dry to the touch a second coat of mastic shall be sprayed or trowelled over the
reinforcing fabric with a smooth unbroken surface and allowed to dry. The total thickness of barrier
material shall be 3mm (nominal).
12.9 Insulation on cylindrical straight sections of piping shall be covered with an additional protective
sheet metal jacketing to the requirements of Table 2 rolled to conform to the pipe diameter and
applied in 1.0 metre lengths. The jacketing shall be applied with minimum 50mm overlaps at both
longitudinal circumferential overlaps
12.10 All longitudinal overlaps on horizontal pipes shall be arranged weatherside down to shed water
and shall be located along the lower half at approximately 135° or 225° positions. Longitudinal
overlaps on vertical pipes shall be arranged away from the prevailing site weather conditions.
12.11 The metal covering shall be secured tightly around the insulated pipe and held in place with
stainless steel bands at a maximum of 220mm centres. One band shall be located on each
circumferential lap and the distance between laps divided at equal band spacing.
12.12 Each section of metal covering on vertical piping with insulation 0.D.'s larger than 250mm shall be
supported from the next lower sections with two 'S' clips fabricated from banding material. The 'S'
clips shall be of sufficient length to allow the minimum overlap of 50mm.
12.13 Insulated bends and elbows on piping 80mm (3") NPS and larger, shall be metalled with 'lobster
back' segments using 10mm minimum ball swage to assist shaping. The metal segments shall be
banded.
12.14 Insulated bends and elbows on piping smaller than 80mm (3") NPS and/where constricted at the
throat bend, shall use fabricated 'stove pipe' elbows.
12.15 Butt-weld, socket-weld and threaded valves, where insulated, shall be clad and secured as pipe.
12.16 Removable covers on flange joints, flange valves etc. shall be fitted with snap fasteners for quick
and easy removal.
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 29 / 51
13. APPLICATION VERTICAL VESSELS AND PIPE GREATER THAN 900MM (36") OD
13.1 Insulation to the specified thickness shall be applied by the use of pre-formed radiused and
bevelled lags for vessel, shells and pipes, and pre-formed sets for vessel heads.
13.2 Insulation shall primarily be supported on rings welded to the steel surfaces. Additional support
and application aid shall be provided by the use of adhesive.
13.3 Insulation shall be applied starting from the bottom with vertical joints staggered. When more than
one layer is employed, the joints in the second layer shall not match the joints of the previous layer.
13.4 When applying Cellular Glass the base of the inner layer shall be coated with a thin application (to
fill cells only) of anti-abrasion compound and allowed to dry before application of insulation to the
surface.
13.5 All joints of single or outermost layers of insulation, with the exception of contraction joints, shall
be buttered with the specified joint sealer before installation and then firmly butted together.
13.6 Insulation shall be held against the metal surface with sta inless steel bands (see Table 2) at 300mm
maximum centres.
13.7 Heads of vessels shall be insulated with pre-formed vessel head insulation sets. Where fabrication
is necessary the material shall be cleanly cut and shaped to closely follow the contour of the head.
The joints shall be buttered in accordance with paragraph 13.5. The insulation shall be secured to
the heads by bands drawn radially from the tan line circumferential body bands attached at 300mm
centres, to a centralised floating ring of 10mm O/D bar. The bands shall be tensioned in suitable
sequence to ensure a positive securing of the insulation material. Adhesive shall be used for initial
support on bottom heads.
13.8 An additional layer of insulation shall be applied over the outside layer where insulation supports
are located.
13.9 The installed insulation shall be vapour sealed in accordance with Paragraph 12.8.
13.10 Insulation shall be covered with an additional protective sheet metal jacketing employing flat
sheeting to the requirements of Table 2.
13.11 The panels shall be applied commencing at the bottom of the vessel. Each circumferential ring of
panels shall be tensioned by means of temporary tensioning bands until the final joint is made. 'S'
clips shall be used as additional sheeting supports at circumferential overlaps.
13.12 The panels shall have a minimum overlap of 80mm on both horizontal and vertical edges. The
overlaps shall be arranged to shed water at all times.
13.13 The panels shall be held tight to the vessel by means of circumferential bands and seals. The bands
shall be positioned on all horizontal overlaps and at 450mm max. centres.
13.14 Over vessel heads the metal sheet shall be fabricated in an orange peel construction with all radial
seams overlapping a minimum of 25mm. Radius direction joints shall be double lap seam joints
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 30 / 51
and circumferential direction joints shall be folded seam joints to ensure the sheeting does not
become loose.
13.15 All equipment projections shall have the jacketing sealed using metal flashing cut to fit the
projections.
13.16 Insulation and vapour barrier on the bottom head of a vessel protected by a closed skirt shall not
require weather protection.
14. APPLICATION - HORIZONTAL VESSELS AND PIPE GREATER THAN 900MM (36")
OD
14.1 Insulation to the specified thickness shall be pre-formed radiused and bevelled lags for vessels
shells and pipes, and pre-formed insulation sets for vessel heads.
14.2 Insulation shall be applied starting with full length and half lengths lags, with all circumferential
joints being staggered. When more than one layer is employed, the joints in the second layer shall
not match the joints in the previous layer.
14.3 When applying Cellular Glass the base of the inner layer shall be coated with a thin application (to
fill cells only) of anti-abrasion compound and allowed to dry before applic ation of insulation to the
surface.
14.4 All joints of single or outermost layers of insulation, with the exception of contraction joints, shall
be buttered with the specific joint sealer before installation and then firmly butted together.
14.5 The applied insulation shall be secured in place with circumferential stainless steel bands (see
Table 2) spaced at 220mm maximum centres.
14.6 Heads of vessels shall be insulated with pre-formed vessel head insulation sets. Where fabrication
is necessary the material shall be cleanly cut and shaped to closely follow the contour of the head.
The joints shall be buttered in accordance with Paragraph 13.4. The insulation shall be secured to
the heads by bands drawn radially from the tan line circumferential body bands to a centralised
floating ring of 10mm, O.D. bar. The radial bands shall be fastened to the body bands at 300mm
centres and when attached to the floating ring shall be tensioned in suitable sequence to ensure a
positive securing of the insulation material.
14.7 The installed insulation shall be vapour sealed in accordance with Paragraph 12.8.
14.8 Horizontal cylindrical equipment shall be finished with flat metal jacket arranged in circumferential
bands with the longer dimension edge applied around the circumference of the equipment
insulation.
14.9 The panels shall have a minimum of 80mm overlap on both longitudinal and circumferential edges,
both overlaps being finished with a 4mm minimum ball swage and rendered water tight with a
4mm bead of metal seam sealer located in the ball swage.
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 31 / 51
14.10 The jacketing shall be held tight to the vessel by means of circumferential bands and seals. The
band sizes and spacing shall be 20mm wide x 0.5mm thick bands on all circumferential laps and at
300mm maximum centres.
14.11 For vessel heads the metal sheet shall be fabricated in an 'orange peel' construction with all radial
seams overlapping a minimum of 25mm. Radius direction joints shall be double lap seam joints
and circumferential direction joints shall be folded seam joints to ensure the sheeting does not
become loose.
14.12 All equipment projections shall have the jacketing sealed using metal flashing cut to fit the
projections.
14.13 Where applicable exchangers shall be insulated, vapour sealed and clad as horizontal vessels, with
the exception that the channel cover and/or bonnet covers shall have removable cladding (see
Paragraph 11.19).
15.1 The acoustic insulation system shall be applied over the cold service insulation system.
15.3 The acoustic insulation material shall be applied in single or double layers as stated in Table 4.
When applied in double layer the joints in individual layers shall be staggered. Fixing shall be by
12mm wide stainless steel bands at 220mm maximum centres. The entire surface of the acoustic
insulation shall be sealed with a reinforced vapour barrier mastic in accordance with paragraph
12.8.
15.4 The specified metallic cover finish (See Table 4) shall be applied over the cold insulation and
vapour barrier in the manner described in Sections 12, 13 and 14.
15.5 Care shall be taken to ensure that there is absolutely no direct contact between the piping and
equipment from which the noise is emitted, and the insulation metallic finish.
15.6 Gaps between the outer metallic cover and protruding metal part shall be sealed with a flexible,
non-setting, impervious seal, of material suitable for operating temperatures.
15.7 Rigid pipe supports shall be insulated down to the concrete or steel base where acoustic insulation
is required for Class B & C.
15.8 Contractor shall install further insulation over steel support structures where vibration isolations
has been omitted.
15.9 Where acoustic insulation of machinery is required, Contractor shall review the machinery
Vendor’s standard noise insulation standard to ensure if meets the requirements of this Project
Standard and also the requirements of Project Standard 8474L-000-JSD-6000-001.
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 32 / 51
16.1 Where fire hazard protection insulation is required Cellular Glass shall be applied. The general
insulation application procedures shall be followed as described for piping and equipment under
Sections 12, 13 and 14 inclusive except that the insulation shall be applied in a minimum of two
layers.
16.2 The inner layer shall be coated with adhesive and allowed to dry prior to the application of the
second layer.
16.3 The metallic insulation finish over insulation used for fire hazard protection shall be stainless steel
of 0.5mm or 0.8mm thk. as indicated in Table 2.
17.1 Contraction joints shall be positioned in sufficient number and at such distance to allow the
contraction of piping and equipment to take place without disturbance or damage occurring within
the insulating system. Contraction joints shall be determined based on the expected movement.
Joints on horizontal piping and equipment shall be installed at 6m max. centres and a minimum of
one mid way between fixed points.
17.2 On vertical piping and equipment contraction joints shall be provided directly below insulation
support rings where practical. The same method described for non-vertical piping shall be
employed, with the added provision that the side of the contraction joint cover adhered to the outer
layer of insulation shall be above the contraction joint.
17.3 Contraction joints on non-vertical piping shall be provided using a 25mm wide break in the
insulation. Contraction joints in multi-layers of insulation shall be positioned approximately
200mm apart. A layer of insulation sealer shall be applied to the mating surfaces between layers in
the area between contraction joints. All joints are to be packed with mineral fibre in-fill material
compressed to 50% of its thickness. Single or outer layer insulation contraction joints shall be
covered with a 150mm by 25mm thick collar of insulation centred over the joint. One side of this
cover layer of insulation shall be fixed using insulation adhesive. The other side is to be liberally
coated with insulation sealer on the inner surface that mates to the outer layer of insulation. A
heavy fillet of insulation sealer shall be applied to the butt end of the sealed side. Bands shall be
used at each end of the contraction joint cover for security. The mastic vapour barrier system shall
be applied over the contraction joint cover.
17.4 Two layers of insulation shall be used in single layer application, with the second layer being the
same thickness as the first. Joints shall be introduced in all layers of multi-layer application.
17.5 Contractor shall submit detailed drawings of contraction joint design for PetroVietnam review and
approval.
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 33 / 51
FIGURE 1: PIPING (1 OF 5)
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 34 / 51
FIGURE 1: PIPING (2 OF 5)
PREFORMED PIPE
SECTIONS
METAL
JACKET
FLASHING SECURING
BAND
VAPOUR
BARRIER
PREFORMED
PIPE SECTION
METAL TEE OR BRANCH
JACKET WELD
JACKET TO BE
FLANGED AND
SEALED WITH BAND
METAL LAP SEALER
VAPOUR BARRIER
NON SETTING
MASTIC METAL METAL LAP SEALER
JACKET
SECURING
BAND METAL SECURING BAND
JACKET
SEALER
FLASHING PACKED
WITH LOOSE
MINERAL METAL
FIBRE JACKET
SEALER NON SETTING
MASTIC
LOOSE
MINERAL FIBRE
VAPOUR
CONCENTRIC BARRIER
REDUCER
ECCENTRIC
REDUCER
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 35 / 51
FIGURE 1: PIPING (3 OF 5)
GLASS MEMBRANE
1st COAT MASTIC
BANDS
REFER TO PAGE 4 OF 5
FOR METAL JACKET
1st MASTIC COAT
GLASS MEMBRANE
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 36 / 51
FIGURE 1: PIPING (4 OF 5)
METAL JACKET
VAPOUR BARRIER
A
PIPE SECTIONS
50mm
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 37 / 51
T/2 T/2
' D'
' D'
BOLT LENGTH
PLUS 25mm
' D'
' D'
T/2
BOLTED CLIP WHEN WELDING NOT
CLIP SPACING PERMITTED
PIPE TEMP ( ºC) SPACING ' D' (mm)
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 38 / 51
PREFORMED
PIPE SECTIONS
1st COAT
FILL VOIDS OF MASTIC
WITH
FIBRE
GLA ND LEFT FREE INSULATION
OF INSULATION
GLASS CLOTH
2nd COA T
MASTIC
BA NDS
SEALER
METAL
CLADDING
ON PIPE
INS.
PREFORMED
PIPE
SECTIONS
CORNERS
ROUNDED
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 39 / 51
INSULATION
FASTEN WITH
QUICK RELEASE
TOGGLES
SHAPE TO GIVE 12mm CLEARANCE
ALL ROUND PROJECTING PARTS OF
VALVE. ALL CUT-OUTS TO BE
SEALED WITH MASTIC AND ADHESIVE
TAPE
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 40 / 51
PIPE
PIPE
SECTIONS
CORNERS
ROUNDED
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 41 / 51
SEALER
SEALING COLLA R
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 42 / 51
INSULATION SEALED
SUPPORT RINGAT
3660mm CENTRES MAX.
BAND SECURINGJACKET
CONTRACTION JOINT
PACKED WITHFIBROUS
GLASS AT ALL SUPPORT
RINGS CIRCUMFERENTIAL OVERLAPS SUPPORTED ON
'S' CLIPS. ALL OVERLAPS TO BESEALED
WITH SUITABLESEAM SEALER.
VESSEL SHELL
INSULATION SLABS
ERECTED WITH
STAGGERINGJOINTS FLASHINGAROUND NOZZLEBEHIND
JACKET TOBESEALED
WITH SUITABLESEAM SEALER.
FLASHINGSEALED WITH
MASTIC FILLER
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 43 / 51
INSULATION
VESSEL
FINISH
SUPPORT
LUG
THICKNESS 'T'
FOUR'T' MEASURED
FROM JUNCTION OF
VESSEL WITH
INSULATEDSUPPORT
LUG
HEAVY FILLET
CHAULKING MASTIC
SUPPORT BEAM
OUTERLAYERJOINTS SHALL BE
COATEDWITHJOINT SEALER
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 44 / 51
BANDS
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 45 / 51
METAL JACKET
JACKET SECURINGBAND
VESSEL SHELL
LOCATEJACKET SECURINGBAND
ABOVE SUPPORT POINTS
(TYPICAL-INCLUDING'S' CLIPS)
INSULATION
INSULATION ANGLE
WELDED TOSHELL BY
VESSEL FABRICATOR
FLASHING
BOTTOMHEAD
BAND
METAL JACKET
INSULATION
THICKNESS'T'
VESSEL
HEAVYFILLET OF
SECURELEGINSULATION CAULKINGMASTIC
WITHSTRAP AND
APPROVED ADHESIVE
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 46 / 51
80mm
METAL JACKET
OVERLAP
METAL JACKET
SECURINGBANDS
80mm JACKET
OVERLAP.
METAL JACKET SEALER IN OVERLAP
"ORANGEPEEL"
FABRICATION
SEALING
COLLAR
10mm FLOATING
RING
MASTIC VAPOUR
BARRIER VESSEL
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 47 / 51
VAPOUR
MASTIC
LAYER
DOUBLE CIRCUMFERENTIA L
INSULATION
METAL JACKET
SHELL
BA NDS
HEAD BANDS
B
BARRIER
JACKET
METAL
CONSTRUCTION
"ORANGE PEEL"
SEALING CAP
8474L-000-JSD-2220-001- 2.doc
8474L-000-JSD-2220-001- 2.doc
VESSEL HEAD
INSULATION BLOCKS
VAPOUR BARRIER OF
TWO COATES MASTIC
REINFORCED WITH
GLASS MEMBRANE
VESSEL
10 mm FLOATING RING SUPPORT
INSULATION SADDLE
SECURING BAND
METAL JACKET
MASTIC VAPOUR
BARRIER
INSULATION
COLD SERVICE INSULATION
JOINT SEALER
8474L 000
APPLYING INSULATION
JSD
ANTI-VIBRATION SEAL
METAL
SECURING JACKET
BAND
END
CAP
RIVET FIXING
POROUS INSULATION
FABRICATED
METAL JACKET
PROFILE COLLAR
RETAINING BANDS
COLD INSULATION
VAPOUR BARRIER MASTIC
ANTI-VIBRATION
MATERIAL COLD SERVICE
INSULATION
ADHESIVE SEALING
LAYER
PIPE
COLD INSULATION
VAPOUR BARRIER MASTIC
MASTIC SEAL
METAL
SECURING BAND JACKET
END CAP
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 50 / 51
POROUS LAYER.
(INSULATION MATERIAL)
METAL JACKET
METAL JACKET
FABRICATED
MITRES
VIBRATION-ISOLATING
PAD (CLASS C)
8474L-000-JSD-2220-001- 2.doc
Project n° - Unit Doc. type Mat. code Serial n° Rev. Page
8474L 000 JSD 2220 001 2 51 / 51
40 x 2 GALVANISED
MILD STEEL BANDING
6THK. CERAMIC GASKET
7 GALVANISED ' B'
MILD STEEL RIVET
25 x 2 GALVANISED MILD
STEEL BANDING
40 x 2 GALVANISED MILD
25 STEEL BANDING
DIMENSIONS IN mm.
8474L-000-JSD-2220-001- 2.doc