REKAPITULASI
RENCANA ANGGARAN BIAYA (RAB)
JUMLAH HARGA
NO URAIAN PEKERJAAN PEKERJAAN
(Rp)
I. PEKERJAAN PERSIAPAN (UMUM) 190.000,00
II. PEKERJAAN BETON BADAN JALAN 1.852.106,39
III. PERKERASAN LAPISAN ASPAL 80.572,80
(A) JUMLAH HARGA PEKERJAAN (I + II + III) 2.122.679,19
(B) PAJAK PERTAMBAHAN NILAI (PPN) = 10 % X ( A ) 212.267,92
(C) OPERASIONAL TPK 72.000,00
(D) JUMLAH TOTAL HARGA PEKERJAAN ( A + B + C) 2.406.947,11
(E) PEMBULATAN 2.400.000,00