RENCANA ANGGARAN BIAYA (RAB)

PEKERJAAN : PEMBUATAN JALAN RABAT BETON


LOKASI : DESA MARGA MULYA KECAMATAN PANGKALAN BANTENG
TAHUN ANGGARAN : 2020

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN KODE SATUAN VOLUME
( Rp ) ( Rp )
I. PEKERJAAN PERSIAPAN (UMUM)
1. Mobilisasi dan Demobilisasi AHSP SDA LA.04.1 Ls 1,00 190.000,00 190.000,00
SUB TOTAL I 190.000,00
II. PEKERJAAN BETON BADAN JALAN
1. Galian biasa manual AHSP SDA T.06.a.1 m3 0,40 63.465,45 25.386,18
2. Pemasangan Bekisting AHSP CK A.4.1.1.24a m2 3,00 85.210,00 255.630,00
3. Plastic sheet Ls m2 4,00 2.000,00 8.000,00
4. Lantai kerja beton f’c = 7,4 Mpa AHSP CK A.A.4.1.1.4 m3 0,40 1.134.328,99 453.731,60
5. Pekerjaan Beton badan jalan,f’c = 21,7 MPa AHSP CK A.4.1.1.8 m3 0,80 1.386.698,26 1.109.358,61
SUB TOTAL II 1.852.106,39
III. PERKERASAN LAPISAN ASPAL
1. Membran/lapis resap pengikat EI-6.1 (1)(a) Liter 1,40 24.178,86 33.850,40
2. Pelaburan Aspal EI-4.2 (6)a Liter 1,40 27.404,00 38.365,60
3. Taburan Pasir Ls m2 4,00 2.089,20 8.356,80
SUB TOTAL III 80.572,80

REKAPITULASI
RENCANA ANGGARAN BIAYA (RAB)

JUMLAH HARGA
NO URAIAN PEKERJAAN PEKERJAAN
(Rp)
I. PEKERJAAN PERSIAPAN (UMUM) 190.000,00
II. PEKERJAAN BETON BADAN JALAN 1.852.106,39
III. PERKERASAN LAPISAN ASPAL 80.572,80
(A) JUMLAH HARGA PEKERJAAN (I + II + III) 2.122.679,19
(B) PAJAK PERTAMBAHAN NILAI (PPN) = 10 % X ( A ) 212.267,92
(C) OPERASIONAL TPK 72.000,00
(D) JUMLAH TOTAL HARGA PEKERJAAN ( A + B + C) 2.406.947,11
(E) PEMBULATAN 2.400.000,00

TERBILANG :### SERATUS DELAPAN PULUH ENAM RUPIAH ####