You are on page 1of 4

FOR APPROVAL

A 14.05.2020 L.C.Hai Y.H.Lee J.T.Seo For Approval


Rev Date Prepared Checked Approved Details of Revision
Owner

Owner’s Engineer

Contractor

DOOSAN HEAVY INDUSTRIES VIETNAM

Sub-Supplier

BAC MIEN TRUNG CONSULTANCY INVESTMENT


CONSTRUCTION AND TRADING JOINT STOCK COMPANY

Project

NGHI SON 2 BOT THERMAL POWER PLANT PROJECT


(2 X 600 MW)
Title

[Housing Complex]
Inspection and Test Plan for Painting Works

Document No. Rev. Page No.

NS2-DH01-P0UYK-770014 A 04 Pages
ID No: NS2-DH01-P0UYK-770014
NGHI SON 2 BOT THERMAL POWER PLANT Rev: A
(2x600 MW) Date: 14.05.2020
TITLE: INSPECTION AND TEST PLAN FOR PAINTING WORKS
Participation by
Drawing, Codes & Standards
No. Description of Inspection/Test Process Acceptance Criteria Reporting Format Sampling Frequency Remarks
and Check method
Sub-Con Contractor Owner

I Material receiving inspection

Drawing NS2-VD00-P0UYK-770001
The CO/CQ and delivery report of
Certificate of Origin/Certificate of Quantity (CO/CQ) materials must be available and in
1 Standard QCVN 16:2017/BXD NS2-DH01-P0UYK-770014-01 R R R
- Emulsion Paint according to approved NS2-DE00-
P0UYK-770005 MAR for KOVA Paint
Check method Report Review

Drawing NS2-VD00-P0UYK-770001 - The Code, Batch numbers, and


Production dates shall be specified on
the product package and complied to
The paint materials will be
Painting Procedure NS2-YR01-
Packing, Code, Color, Transportation and Storage P0UYK-770001; take the sample for testing
2 TCVN 8652-2012, Item 4; Manufacture’s NS2-DH01-P0UYK-770014-01 P W W before construction.
Standard - The color must be in according to
- Emulsion Paint Recommendations
Color Scheme NS2-VD00-P0UYK-
770001;
- Transportation, storage shall be
Check method Visual complied manufacturer's instructions;

Drawing NS2-YR01-P0UYK-770001
II General preparation work
Check method Visual, Moisture meter

1 Surface Preparation

- All dirt, dust efflorescence, oil,


NS2-YR01-P0UYK-770001 Painting grease and stains shall be removed;
1.1 Concrete Surface Standard NS2-DH01-P0UYK-770014-01 P W W
Procedure, Item 3.1.1 - All hole shall be properly filled with
proper material;

- The substrate must be sound, clean,


NS2-YR01-P0UYK-770001 Painting dry, free from dust, oil, grease;
1.2 Plastering Surface Standard NS2-DH01-P0UYK-770014-01 P W W
Procedure, Item 3.1.2 - Surface defects must be repaired,
smooth, no crack

NS2-YR01-P0UYK-770001 Painting All instruments and tools must be full


2 Instruments and Tools NS2-DH01-P0UYK-770014-01 P S S
Procedure, Item 3.2 suitable and ready for construction

NS2-YR01-P0UYK-770001; NS2-
Drawing
VD00-P0UYK-770001
III Construction and Workmanship
Visual, Moisture meter, Dry Film
Check method
Thickness Gauge

NS2-YR01-P0UYK-770001 Painting
III.1 Emulsion Paint Standard
Procedure, Item 6

A Application of Interior Surface

- Relative humidity of concrete and


plastering surface: <16%;
1 Condition during application Manufacture’s Instruction - Relative humidity of gypsum surface NS2-DH01-P0UYK-770014-01 P W W
: 25% - 30%;
- Relative humidity of air: <85%

Page 1 of 3
ID No: NS2-DH01-P0UYK-770014
NGHI SON 2 BOT THERMAL POWER PLANT Rev: A
(2x600 MW) Date: 14.05.2020
TITLE: INSPECTION AND TEST PLAN FOR PAINTING WORKS
Drawing, Codes & Standards
No. Description of Inspection/Test Process Acceptance Criteria Reporting Format Participation by Sampling Frequency Remarks
and Check method

- Mixing Ratio: Ratio of water (weight)


NS2-YR01-P0UYK-770001 Painting is 40% - 50%;
2 Application for Putty layer NS2-DH01-P0UYK-770014-01 P W S
Procedure, Appendix 1 - Application: 02 layer, film thickness
1000 µm - 1300 µm / 01 layer;

- Mixing Ratio: not exceed 5% with


NS2-YR01-P0UYK-770001 Painting water (If thinning is required);
3 Application of Primer Coating NS2-DH01-P0UYK-770014-01 P W S
Procedure, Appendix 2 - Application : 01 layer, dry film
thickness 35µm - 40 µm;

- Mixing Ratio: not exceed 5% with


NS2-YR01-P0UYK-770001 Painting water (If thinning is required);
4 Application of Top Coating NS2-DH01-P0UYK-770014-01 P W S
Procedure, Appendix 4 - Application : 02 layer, dry film
thickness 40µm - 60 µm each layer;

Evenly colored, constant thickness, no


5 Finished Surface TCVN 8652-2012 Item 3, Table 1 NS2-DH01-P0UYK-770014-01 P W W
drops, run bubbles chips, etc.

B Application of Exterior Surface

- Relative humidity of concrete and


1 Condition during application Manufacture’s Instruction plastering surface: <16%; NS2-DH01-P0UYK-770014-01 P W W
- Relative humidity of air: <85%
- Mixing Ratio: Ratio of water (weight)
NS2-YR01-P0UYK-770001 Painting is 40% - 50%;
2 Application for Putty layer NS2-DH01-P0UYK-770014-01 P W S
Procedure, Appendix 1 - Application: 02 layer, film thickness
1000 µm - 1300 µm / 01 layer;
- Mixing Ratio: not exceed 5% with
NS2-YR01-P0UYK-770001 Painting water (If thinning is required);
3 Application of Primer Coating NS2-DH01-P0UYK-770014-01 P W S
Procedure, Appendix 3 - Application : 01 layer, dry film
thickness 35µm - 40 µm;
- Mixing Ratio: not exceed 5% with
NS2-YR01-P0UYK-770001 Painting water (If thinning is required);
4 Application of Top Coating NS2-DH01-P0UYK-770014-01 P W S
Procedure, Appendix 5 - Application : 02 layer, dry film
thickness 40µm - 60 µm each layer;

Evenly colored, constant thickness, no


5 Finished Surface TCVN 8652-2012 Item 3, Table 1 NS2-DH01-P0UYK-770014-01 P W W
drops, run bubbles chips, etc.

Abbreviation P: Performance R: Report Review W: Witness Inspection H: Hold Inspection S: Surveillance Inspection Acc: Accept Rej: Reject N/A: Not Applicable

Page 2 of 3
Code: NS2-DH01-P0UYK-770014-01
NGHI SON 2 BOT THERMAL POWER PLANT PROJECT Rev: A
Date: 14.05.2020

Date:
Sub-Contractor:
Start:
Finish:
Work title:

Area No:
Inspected Item:

Inspection Report for Painting Work


Applicated Paint System: Emulsion Paint Epoxy Paint Chemical Resistant Paint

Approved shop drawing No.:

Assessed by
Inspected Item Description Check method
Acc Rej N/A
I Check Receiving Inspection
Certificate of Origin / Certificate of Quality The CO/ CQ shall be available and in
1 Report Review
(CO/CQ) according to Painting Procedure
Certificate of Origin / Certificate of Quality The Code and Color in according to Painting
2 Visual
(CO/CQ) Procedure, Color Scheme
II General preparation work
1 Surface Preparation
- All dirt, dust efflorescence, oil, grease and
stains shall be removed; Visual/
1.1 Concrete Surface
- All hole shall be properly filled with proper Moisture Meter
material
- The substrate must be sound, clean, dry,
free from dust, oil, grease; Visual/
1.2 Plaster Surface
- Surface defects must be repaired, smooth, Moisture Meter
no crack
All instruments and tools must be full and
2 Instruments and Tools Visual
ready for construction
III Construction and workmanship
Relative humidity of surface and the air before
Visual/Moisture
1 Condition during application apply shall be complied to Manufacturer's
Meter
Instructions

Mixing ratio, Applicated layers and Film Visual/Moisture


2 Application for Putty Layer thickness must be complied approved Meter /Dry Film
Painting Procedure Thickness Gauge

Mixing ratio, Applicated layers, and Typical Visual/Moisture


3 Application of Primer Coating dry film thickness / layer must be complied Meter /Dry Film
Approved Painting Procedure Thickness Gauge

Mixing ratio, Applicated layers, and Typical Visual/Moisture


4 Application of Top Coating dry film thickness / layer must be complied Meter /Dry Film
Approved Painting Procedure Thickness Gauge
Evenly colored, constant thickness, no drops,
5 Finished surface Visual
run bubbles chips, etc.
CONCLUSION

Approved Not approved


…………………………………………………………………………………………………………………………………………………………………

…………………………………………………………………………………………………………………………………………………………………

Signature
Description Full Name

Owner

Contractor

Subcontractor

Page 3 of 3