You are on page 1of 8

RECOMMENDED PRACTICE

FOR GROUTING OF
POST-TENSIONED
PRESTRESSED CONCRETE

Prepared by PCI Committee on Post-Tensioning

Peter Reinhardt
Chairman

Ted Brown H. Kent Preston


Ned H. Burns Charles Relcha
Brian Carter Morris Schupack
Eugene E. Dabney William Slater
Loris Gerber Mario G. Suarez
Robert L. Koons David Swanson
James R. Libby Adolph Walser
Robert J. McLean

18
These recommendations cover the grouting of
post-tensioning tendons of prestressed concrete
members. The purpose of grouting is to provide
permanent protection to the post-tensioning steel
and to develop bond between prestressing steel
and the surrounding concrete. These procedures
also apply to grouting of rock and soil anchors.
However, more detailed consideration must be
given to grout strength and injection procedures.
The contents of this report include definitions
materials, ducts, equipment, mixing of the grout,
grouting, and temperature considerations. The
Appendix includes a reprint of U.S. Corps of
Engineers Method CRD-C79-58, "Method of Test
for Flow of Grout Mixtures (Flow-Cone
Method)." After most sections, there is an appro-
priate commentary (in italics) to guide specifiers
using this recommended practice.
This document was originally developed and
subsequently revised by a joint committee of the
Prestressed Concrete Manufacturers Association of
California (PCMAC) and Western Concrete
Reinforcing Steel Institute. The original recom-
mended practice, "Guide Specification on Grouting
of Post-Tensioning Tendons," was published by the
PCMAC and unfortunately received limited
distribution. It was the intent of the PCI Com-
mittee on Post-Tensioning to revise this document
and have it published as a PCI specification in
order to get broader distribution and acceptance
by the industry.

PCI Journal/November-December 1972 19


1. General imparts prestressing forces to the con-
crete.
1.1 Scope and purpose 1.2.7 Prestressing steel—That ele-
ment of a post-tensioning tendon which
These procedures also apply to
is elongated and anchored to provide
grouting of rock and soil anchors. How-
the necessary permanent prestressing
ever, since the hardened grout in rock
force.
and soil anchor applications sustain the
full post-tensioning force, more detailed
consideration must be given to grout 2. Materials
strength and injection procedures. 2.1 Portland cement
1.1.1 These recommendations Portland cement should conform
cover the grouting of post-tensioning to one of the following:
tendons of prestressed concrete mem- Specifications for portland cement-
bers. ASTM C 150, Types I, II or III. Ce-
1.1.2 The purpose of grouting is ment used for grouting should be fresh
to provide permanent protection to the and should not contain any lumps or
post-tensioning steel and to develop other indication or hydration or "pack
bond between the prestressing steel and set."
the surrounding concrete. Normally, Type III Cement is
only used for cold weather grouting.
1.2 Definition of terms
Trial mixes are necessary to determine
All terms and symbols are as de- an appropriate mix design using Type
fined in "Guide Specification for Post- III Cement.
Tensioning Materials" published by the
Prestressed Concrete Institute. 2.2 Water
1.2.1 Admixture—Any material The water used in the grout
added to the grout other than portland should be potable, clean and free of in-
cement and water. jurious quantities of substances known
1.2.2 Duct—The hole or void pro- to be harmful to portland cement, or
vided in the concrete for the post-ten- prestressing steel.
sioning tendon. Known harmful substances are
1.2.3 Grout—A mixture of cement chlorides, florides, sulphites and ni-
and water with or without admixtures. trates.
Although sand has not been 2.3 Admixtures
used in grouting practices in the United Admixtures, if used, should im-
States, it may have advantages in ten- part the properties of low water con-
dons with large void areas. Fly ash and tent, good flowability, minimum bleed
pozzolans are occasionally used as filler and expansion if desired. Its formula-
materials in the United States. tion should contain no chemicals in
1.2.4 Grout opening or vent—An quantities that may have harmful effect
inlet, outlet, or vent in the duct for on the prestressing steel or cement. Ad-
grout, water, or air. mixtures containing chlorides (as C1- in
1.2.5 Post-tensioning—The meth- excess of 0.5 percent by weight of ad-
od of prestressing concrete in which the mixture, assuming 1 lb of admixture per
tendon is stressed after the concrete has sack (94 lb) of cement), florides, sul-
reached a specified strength. phites and nitrates should not be used.
1.2.6 Post-tensioning tendons— Aluminum powder of the proper
The complete assembly consisting of fineness and quantity or other approved
anchorage and prestressing steel with gas evolving material which is well dis-
sheathing when required. The tendon persed through the other admixture

20
may be used to obtain 5 to 10 percent of grout. All coring materials should be
unrestrained expansion of the grout. removed.
All admixtures should be used in Materials commonly used for
accordance with the instructions of the formed ducts are 22 to 28 gage galva-
manufacturer. nized or bright spirally wound or longi-
Admixtures commonly used to tudinally seamed steel strip with flexi-
provide expansion of the grout may also ble or semirigid seams.
reduce the water requirement, or im- 3.2 Grout openings or vents
prove flowability at a given water con- All ducts should have grout
tent, and retard set. Such admixtures openings at both ends. For draped ca-
aide normally used. However, research bles all high points should have a grout
in progress for basically horizontal ten- vent except where cable curvature is
dons in rigid ducts suggest that satis- small, such as in continuous slabs.
factory grout quality may be achieved Grout vents or drain holes should be
without admixtures. provided at low points if the tendon is
Current international standards to be placed, stressed and grouted in a
suggest that bleeding may be measured freezing climate. All grout openings or
in a metal or glass cylinder with an in- vents should include provisions for pre-
ternal diameter of approximately 4 in., venting grout leakage.
with a height of grout of approximately Research in progress suggests
4 in. However, recent research in the that high point grout vents may be
United States indicates that more rep- eliminated for bridge tendons up to 400
resentative test results may be achieved ft long in rigid conduit. However, cur-
using a grout specimen of approximate- rent practice does utilize high point
ly 20 in. height and 1% in. diameter. grout vents.
During the test, the container should be Material used for grout vents or
covered to prevent evaporation. It is drain holes may be either plastic or fer-
suggested that the following approxi- rous metal.
mate limits on bleeding be used to Grout vent details for rock and
evaluate the acceptability of the grout: soil anchors require special considera-
2 percent of the volume 3 hours after tions particular to the applications.
mixing; a maximum of 4 percent. In
3.3 Duct size
addition, the separated water should be
For tendons made up of a plu-
absorbed after 24 hours. rality of wires, bars, or strands, duct
area should be at least twice the net
3. Ducts area of the prestressing steel.
3.1 Forming For tendons made up of a single
(a) Formed ducts—Ducts wire, bar or strand, the duct diameter
formed by sheath left in place should should be at least 114 in. larger than the
be of a type that would not permit the nominal diameter of the wire, bar or
entrance of cement paste. They should strand.
transfer bond stresses as required and 3.4 Placement of ducts
should retain shape under the weight of After placing of ducts, rein-
the concrete. Metallic sheaths should forcement and forming is complete, an
be of a ferrous metal, and they may be inspection should be made to locate
galvanized. possible duct damage. Ducts should be
(b) Cored ducts—Cored ducts securely fastened at close enough inter-
should be formed with no constrictions vals to avoid displacement during con-
which would tend to block the passage creting.

PCI Journal/November-December 1972 21


All unintentional holes or open- grout line between the pump outlet and
ings in the duct must be repaired prior the duct inlet.
to concrete placing. It is suggested that standby wa-
Grout openings and vents must ter flushing equipment should be avail-
be securely anchored to the duct and to able where difficult grouting conditions
either the forms or to reinforcing steel exist. This equipment should be in ad-
to prevent displacement during con- dition to the grouting equipment. The
crete placing operations. standby water flushing equipment
There are two methods of plac- should utilize a different power source
ing tendons. First, preassembled ten- than the grouting equipment, have suf-
dons may be placed as a unit prior to ficient capacity to flush out any partial-
placing concrete. Second, bearing ly grouted enclosures if necessary due
plates and duct sheathing may be in- to blockage or breakdown of grouting
stalled prior to placing the concrete, equipment, and should be capable of
and then after concreting, the prestress- developing a pressure of at least 300
ing steel and anchorages are installed. prig.
Supports for preplaced tendons must 4.5 The grouting equipment should
be adequate to resist the tendon contain a screen having clear openings
weight. When only the duct is placed of 0.125 in. maximum size to screen the
prior to concreting, supports must re- grout prior to its introduction into the
sist buoyancy forces. grout pump. If a grout with a thixo-
tropic additive is used, a screen opening
4. Equipment of 8A6 in. is satisfactory. This screen
4.1 The grouting equipment should should be easily accessible for inspec-
include a mixer capable of continuous tion and cleaning.
mechanical mixing which will produce A thixotropic grout undergoes
a grout free of lumps and undispersed marked changes in fluidity depending
cement. The equipment should be able on whether the grout is in motion or
to pump the mixed grout in a manner quiescent. This property is produced
which will comply with all provisions by additives.
of this recommended practice. 4.6 The grouting equipment should
Commercially available plaster utilize gravity feed to the pump inlet
and concrete mixers are not suitable for from a hopper attached to and directly
mixing grout. over it. The hopper must be kept at
least partially full of grout at all times
4.2 Accessory equipment which will
during the pumping operation to pre-
provide for accurate solid and liquid
vent air from being drawn into the
measures should be provided to batch
post-tensioning duct.
all materials.
4.7 Under normal conditions, the
4.3 The pump should be a positive grouting equipment should be capable
displacement type and be able to pro- of continuously grouting the largest
duce an outlet pressure of at least 150 tendon on the project in no more than
prig. The pump should have seals ade- 20 minutes.
quate to prevent introduction of oil, air
or other foreign substance into the
grout, and to prevent loss of grout or 5. Mixing of grout
water. 5.1 Water should be added to the
4.4 A pressure gauge having a full mixer first, followed by portland ce-
scale reading of no greater than 300 psi ment and admixture, or as required by
should be placed at some point in the the admixture manufacturer.

22
5.2 Mixing should be of such dura- 6. Grouting
tion as to obtain a uniform thoroughly 6.1 Preparation of duct
blended grout, without excessive tem-
perature increase or loss of expansive 6.1.1 Flushing of metal ducts
properties of the admixture. The grout should be optional with the post-ten-
should be continuously agitated until it sioning contractor.
is pumped. Historically, flushing has been
used to clear the duct of foreign materi-
Equipment currently in use nor-
als, and to wet the duct and tendon
mally requires 1 %/z to 3 minutes to sat-
surfaces to improve the groutability.
actorily mix the grout.
isfactorily
When tendons are flushed, the water
5.3 Water should not be added to may be removed by oil-free air, or it
increase grout flowability which has may be displaced by the grout. In re-
been decreased by delayed use of the cent years, grouting experiences with
grout. rigid conduit and prestressing steel
placed after concreting indicate that
5.4 Proportions of materials should flushing is not necessary and may be
be based on tests made on the grout be- undesirable for large tendons since it is
fore grouting is begun, or may be se- difficult to remove the water from the
lected based on prior documented ex- duct.
perience with similar materials and
equipment and under comparable field 6.1.2 Ducts with concrete walls
conditions (weather, temperature, etc.). (cored ducts) should be flushed to en-
The water content shall be the mini- sure that the concrete is thoroughly
wetted.
mum necessary for proper placement,
and when Type I or II cement is used 6.1.3 Water used for flushing
should not exceed a water--cement ratio ducts may contain slack lime (calcium
of 0.45 or approximately 5 gallons of hydroxide) or quicklime (calcium oxide)
water per sack (94 lb) of cement. in the amount of 0.1 lb per gallon.
6.2 Injection of grout
The water content required for
Type III cement should be established 6.2.1 All grout and high point
for a particular' brand based on tests. vent openings should be open when
grouting starts. Grout should be al-
The pumpability of the grout lowed to flow from the first vent after
may be determined by the Engineer in the inlet pipe until any residual flush-
accordance with the U.S. Corps of En- ing water or entrapped air has been re-
gineers Method CRD-C79 (see Appen- moved, at which time the vent should
dix). When this method is used, the be capped or otherwise closed. Remain-
efflux time of the grout sample immedi- ing vents should be closed in sequence
ately after mixing should not be less in the same manner.
than 11 seconds. The flow cone test 6.2.2 The pumping pressure at the
does not apply to grout which incorpo- tendon inlet should not exceed 250
rates a thixotropic additive. psig.
Hardened grout made in accor- When pumping grout, pres-
dance with this specification at a tem- sures in excess of 250 psi result in a
perature of 65 F and a relative humid- separation of water and cement, which
ity of approximately 70 percent will may cause a blockage. Excessive pres-
produce 28-day compressive strengths sures could also result in cracking or
of about 4000 psi when cured under damage to the structural element. It is
confined conditions. therefore advisable to keep grout

PCI Journal/November-December 1972 23


pumping pressures under this level. Vertical or nearly vertical
This can be done by visually monitor- tendons made up of strands, which tend
ing the pressure gage, or by equipment to act as filters for the grout, require
which includes automatic or manual special consideration. Because of exag-
bypasses. gerated bleed, special grouting tech-
niques should be used to ensure com-
6.2.3 If the actual grouting pres-
plete filling of the top portion of the
sure exceeds the maximum recommend-
tendon. This may be achieved by two
ed pumping pressure, grout may be in-
stages of grouting, free expansion of
jected at any vent which has been, or is
grout pushing the bleed water out at
ready to be, capped as long as a one-
the high points, or admixtures which
way flow of grout is maintained. If this
increase the water retentivity so that
procedure is used, then the vent which
bleed is controlled.
is to be used for injection should be
fitted with a positive shutoff.
6.2.4 When one-way flow of grout 7. Temperature considerations
cannot be maintained as outlined in 7.1 In temperatures below 32 F,
Section 6.2.3, the grout should be im- ducts should be kept free of water to
mediately flushed out of the duct with avoid damage due to freezing.
water. This is normally accomplished
6.2.5 Grout should be pumped with low point drains.
through the duct and continuously
7.2 Concrete temperature—The
wasted at the outlet pipe until no visi-
temperature of the concrete should be
ble slugs of water or air are ejected and
35 F or higher from the time of grout-
the efflux time of the ejected grout
ing until job cured 2 in. cubes of grout
should not be less than the injected
reach a minimum compressive strength
grout. To insure that the tendon re-
of 800 psi.
mains filled with grout, the outlet and
/or inlet should be closed. Plugs, caps At 35 F grout may be expected
or valves thus required should not be to reach 800 psi cube strength in about
removed or opened until the grout has 5 days.
set. 7.3 Grout temperature—Grout should
Current research indicates not be above 90 F during mixing or
that use of standpipes at high points of pumping. If necessary, the mixing
grouted tendons is a satisfactory sub- water should be cooled.
stitute for a positive means of shutoff. Difficulties in pumping grout
Standpipes permit free expansion may occur when the grout temperature
which tends to push out any bleed wa- in the mixer exceeds 90 F.
ter that may occur at high points. (See p. 25 for Appendix)

Discussion of this committee report is invited.


Please forward your discussion to PCI Headquarters by March 1, 1973,
to permit publication in the March-April 1973 issue of the PCI JOURNAL.

24
ҟ

APPENDIX

(Issued 1 Sept. 1958)


CRD-C 79-58
METHOD OF TEST FOR FLOW OF GROUT MIXTURES
(Flow-Cone Method)

Scope top will be level and the cone free


from vibration. The discharge tube
1. This method of test covers the shall be closed by placing the finger
procedure to be used both in the over the lower end. A quantity of
laboratory and in the field for deter- water equal to 1725± 1 ml shall be
mining the flow of grout mixtures by introduced into the cone. The point
measuring the time of efflux of a gage shall be adjusted to indicate the
specified volume of grout from a level of the water surface.
standardized flow cone.
Sample
Apparatus
4. The test sample shall consist of
2. (a) Flow Cone. — The flow 1725± 1 ml of gout.
cone shall conform to the dimensions
and other requirements indicated in Procedure
Fig. 1.
CJ N.O E. E O
5. Moisten the inside surface of
I the flow cone (Note). Place the finger
over the outlet of the discharge tube.
Introduce grout into the cone until
the grout surface rises into contact
with the point gage. Start the stop
watch and remove the finger simul-
taneously. Stop the stop watch at the
first break in the continuous flow of
grout from the discharge tube. The
time indicated by the stop watch is

Ij
the time of efflux of the grout. At
least two tests shall be made for any
\\ // CAST ALO 1- grout mixtures.
Note. — A recommended procedure for insuring
that the interior of the cone is properly wetted is
to fill the cone with water and, one minute before
beginning to add the grout sample, allow the water
to drain from the cone.

Report
6. The report shall include:
Fig. 1. Cross section of flow cone
(a) Average time of efflux to the
nearest 0.2 sec,
(b) Stop Watch. — A stop watch (b) Temperature of the sample at
having a least reading of not more than the time of test,
0.2 sec. (c) Ambient temperature at the
time of test,
Calibration of Apparatus
(d) Composition of the sample, and
3. The flow cone shall be firmly (e) Information on the physical
mounted in such . a manner that the characterisitics of the sample.

PCI Journal/November-December 1972 25

You might also like