4. As build drawings
5. Construction related documents like Hydro test acceptance reports, NDT reports, Equipment erection
inspection report
FORMAT I
Site Commissioning Team will check the system and issue checklist for deviations
FORMAT II
Check Lists
This is checklist points issued by site Commissioning Team (SCT) to construction Coordinator.
Construction Coordinator (CC) will work for resolving / liquidation checklist points. SCT will perform final
check and final Punch list
FORMAT III
Construction Coordinator Issues the Format 3 which will be approved by Site Commissioning Team.
FORMAT IV
This is initiated by the Site Commissioning Team (SCT) for acceptance by customer’s Commissioning
Coordinator (CCC)
Pre commissioning activities are to be performed by client’s Operation team as per the procedure
provided by the SCT. SCT/CCC will review the commissioning in progress and ensure successful working
of system.
FORMAT V
Upon successful Completion of commissioning FORMAT 5 will be issued by SCT for the acceptance of
customer’s Commissioning Coordinator (CCC)