STATUS OF PIPING WORKS OF PPU BY M/S JPL AS ON 23/12/11

  
Total scope of fabrication as per SOR 76,555.00 ID
  
Revised scope of fabrication as per ISO 51,137.00 ID
  
MIV Issued 35,923.00 ID
  
Workable Front 24,490.00 ID
  
Fabrication completed as on 23/12/2011 19,526.00 ID
    
Balance work 4,964.00 ID
        
Mismatch 937.00 ID
     
  
Erection completed 10,374.00 IM
     
Total no. of equipments 201 Nos.
No. of equipments arrived at site 141 Nos.
Equipments erected 23 Nos.
Ready for erection 7 Nos.