Professional Documents
Culture Documents
S U M M A R Y
prepared by
ITEM MATERIAL
DESCRIPTION QUANTITY UNIT LABOR TOTAL
NO. UNIT COST AMOUNT
I. GENERAL REQUIREMENT
1.1) Temporary Facilities & Const'n. of Bunkhouse 1.00 lot - - - 50,000.00
1.2) Mobilization and Demobilization 1.00 lot - - - 40,000.00
1.3) Layout and Staking 1.00 lot - - - 15,000.00
1.4) Cleaning and Hauling of Construction Debris 1.00 lot - - - 21,000.00
1.5) Board - up 1.00 lot - - - 15,000.00
1.6) Permit & Licenses 1.00 lot - 90,000.00
1.7) Others
1.7.1) As Built Plans 1.00 lot - 45,000.00
1.7.2) Supervision 1.00 lot - 160,000.00
1.7.3) Electrical & Water Consumptions 1.00 lot - 40,000.00
1.7.4) Performance / Warranty Bond / CARI 1.00 lot - 122,000.00
1.7.5) Materials testing 1.00 lot - 65,000.00
sub-total - - 663,000.00
ITEM MATERIAL
DESCRIPTION QUANTITY UNIT LABOR TOTAL
NO. UNIT COST AMOUNT
3.1.7) Area Drain / Catch Basin -
12mm x 6m deform bar 184.00 pcs 220.00 40,480.00 12,144.00 52,624.00
# 16 G.I. Tie Wire 3.00 kgs 52.00 156.00 46.80 202.80
1/4" x 1" x 1" Angle Bar 12.27 pcs 410.00 5,029.33 1,508.80 6,538.13
3.1.8) Footing Tie Beam -
16mm x 6m deform bar 238.33 pcs 400.00 95,333.33 28,600.00 123,933.33
10mm x 6m deform bar 238.33 pcs 154.00 36,703.33 11,011.00 47,714.33
# 16 G.I. Tie Wire 10.00 kgs 52.00 520.00 156.00 676.00
3.1.9) Slab -
a) Lower Ground Floor -
10mm x 6m deform bar 256.00 pcs 154.00 39,424.00 11,827.20 51,251.20
# 16 G.I. Tie Wire 20.00 kgs 52.00 1,040.00 312.00 1,352.00
b) Upper Ground Floor -
10mm x 6m deform bar 144.00 pcs 154.00 22,176.00 6,652.80 28,828.80
# 16 G.I. Tie Wire 14.00 kgs 52.00 728.00 218.40 946.40
c) Second Floor -
10mm x 6m deform bar 800.00 pcs 154.00 123,200.00 36,960.00 160,160.00
# 16 G.I. Tie Wire 30.00 kgs 52.00 1,560.00 468.00 2,028.00
d) Entrance Canopy -
10mm x 6m deform bar 64.00 pcs 154.00 9,856.00 2,956.80 12,812.80
# 16 G.I. Tie Wire 2.00 kgs 52.00 104.00 31.20 135.20
e) Roof Slabv -
10mm x 6m deform bar 1,200.00 pcs 154.00 184,800.00 55,440.00 240,240.00
# 16 G.I. Tie Wire 25.00 kgs 52.00 1,300.00 390.00 1,690.00
3.1.10) Electric Post -
16mm x 6m deform bar 2.00 pcs 400.00 -
12mm x 6m deform bar 4.00 pcs 220.00 880.00 264.00 1,144.00
10mm x 6m deform bar 5.00 pcs 154.00 770.00 231.00 1,001.00
# 16 G.I. Tie Wire 2.00 kgs 52.00 104.00 31.20 135.20
3.1.11) Driveway -
10mm x 6m deform bar 320.00 pcs 154.00 49,280.00 14,784.00 64,064.00
# 16 G.I. Tie Wire 10.00 kgs 52.00 520.00 156.00 676.00
3.1.12) Pump / Filter Room -
10mm x 6m deform bar 100.00 pcs 154.00 15,400.00 4,620.00 20,020.00
# 16 G.I. Tie Wire 10.00 kgs 52.00 520.00 156.00 676.00
3.1.13 Rc beams -
20mm x 6m deform bar 409.50 pcs 610.00 -
10mm x 6m deform bar 357.00 pcs 154.00 54,978.00 16,493.40 71,471.40
# 16 G.I. Tie Wire 1.00 kgs 52.00 52.00 15.60 67.60
3.1.14) Pump Roof Slab -
10mm x 6m deform bar 50.00 pcs 154.00 7,700.00 2,310.00 10,010.00
# 16 G.I. Tie Wire 5.00 kgs 52.00 260.00 78.00 338.00
sub-total 1,395,942.50 418,782.75 1,814,725.25
ITEM MATERIAL
DESCRIPTION QUANTITY UNIT LABOR TOTAL
NO. UNIT COST AMOUNT
4.6) Cistern -
1/2" thk. Ordinary Plywood 4.00 pcs 1,200.00 4,800.00 1,680.00 6,480.00
2" x 3" x 10' Good Lumber 50.00 pcs 160.00 8,000.00 2,800.00 10,800.00
Asst'd. CWN 5.00 kgs 63.00 315.00 110.25 425.25
4.7) Column -
1/2" thk. Ordinary Plywood 40.00 pcs 1,200.00 48,000.00 16,800.00 64,800.00
Gauge 20 Plain G.I. Sheets 5.00 pcs 160.00 800.00 280.00 1,080.00
2" x 3" x 10' Good Lumber 100.00 pcs 63.00 6,300.00 2,205.00 8,505.00
Asst'd. CWN 10.00 kgs 63.00 630.00 220.50 850.50
4.8) Beam -
1/2" thk. Ordinary Plywood 50.00 pcs 1,200.00 60,000.00 21,000.00 81,000.00
2" x 3" x 10' Good Lumber 150.00 pcs 160.00 24,000.00 8,400.00 32,400.00
Asst'd. CWN 20.00 kgs 63.00 1,260.00 441.00 1,701.00
4.9) Retaining Wall -
1/2" thk. Ordinary Plywood 15.00 pcs 1,200.00 18,000.00 6,300.00 24,300.00
2" x 3" x 10' Good Lumber 150.00 pcs 160.00 24,000.00 8,400.00 32,400.00
Asst'd. CWN 5.00 kgs 63.00 315.00 110.25 425.25
4.10) Slab -
1/2" thk. Ordinary Plywood 120.00 pcs 1,200.00 144,000.00 50,400.00 194,400.00
2" x 3" x 10' Good Lumber 200.00 pcs 160.00 32,000.00 11,200.00 43,200.00
Asst'd. CWN 20.00 kgs 63.00 1,260.00 441.00 1,701.00
4.11) Roof Slab - -
1/2" thk. Ordinary Plywood 60.00 pcs 1,200.00 72,000.00 25,200.00 97,200.00
2" x 3" x 10' Good Lumber 300.00 pcs 160.00 48,000.00 16,800.00 64,800.00
Asst'd. CWN 10.00 kgs 63.00 630.00 220.50 850.50
4.12) Pump / Filter Roof Slab -
1/2" thk. Ordinary Plywood 10.00 pcs 1,200.00 12,000.00 4,200.00 16,200.00
2" x 3" x 10' Good Lumber 50.00 pcs 160.00 8,000.00 2,800.00 10,800.00
Asst'd. CWN 5.00 kgs 63.00 315.00 110.25 425.25
4.13) Electric Post -
1/2" thk. Ordinary Plywood 4.00 pcs 1,200.00 4,800.00 1,680.00 6,480.00
2" x 3" x 10' Good Lumber 30.00 pcs 160.00 4,800.00 1,680.00 6,480.00
Asst'd. CWN 5.00 kgs 63.00 315.00 126.00 441.00
sub-total 663,752.00 232,328.95 896,080.95
V. CONCRETE WORKS
5.1) Column Footing 22.65
Portland Cement 158.58 bags 235.00 37,267.42 11,180.23 48,447.65
Gravel 126.87 cu.m. 1,800.00 228,362.09 68,508.63 296,870.72
Sand 53.28 cu.m. 2,000.00 106,568.98 31,970.69 138,539.67
5.2) Concrete Column 26.88 -
Portland Cement 188.16 bags 248.00 46,663.68 13,999.10 60,662.78
Gravel 150.53 cu.m. 1,800.00 270,950.40 81,285.12 352,235.52
Sand 63.22 cu.m. 2,000.00 126,443.52 37,933.06 164,376.58
5.3) Footing Tie Beam 6.86 -
Portland Cement 48.05 bags 248.00 11,915.90 3,574.77 15,490.68
Gravel 38.44 cu.m. 1,800.00 69,189.12 20,756.74 89,945.86
Sand 16.14 cu.m. 2,000.00 32,288.26 9,686.48 41,974.73
5.4) Septic Tank 2.60 -
Portland Cement 18.20 bags 248.00 4,513.60 1,354.08 5,867.68
Gravel 14.56 cu.m. 1,800.00 26,208.00 7,862.40 34,070.40
Sand 6.12 cu.m. 2,000.00 12,230.40 3,669.12 15,899.52
5.5) Reinforced Concrete Stair 48.80 -
Portland Cement 341.60 bags 248.00 84,716.80 25,415.04 110,131.84
Gravel 273.28 cu.m. 1,800.00 491,904.00 147,571.20 639,475.20
Sand 114.78 cu.m. 2,000.00 229,555.20 68,866.56 298,421.76
5.6) Rain Water Storage 19.20 -
Portland Cement 134.40 bags 248.00 33,331.20 9,999.36 43,330.56
Gravel 107.52 cu.m. 1,800.00 193,536.00 58,060.80 251,596.80
Sand 45.16 cu.m. 2,000.00 90,316.80 27,095.04 117,411.84
5.7) Slabs -
a) Lower Ground Floor 11.80 -
Portland Cement 82.60 bags 248.00 20,484.80 6,145.44 26,630.24
Gravel 66.08 cu.m. 1,800.00 118,944.00 35,683.20 154,627.20
Sand 26.43 cu.m. 2,000.00 52,864.00 15,859.20 68,723.20
b) Upper Ground Floor 24.40 -
Portland Cement 170.80 bags 248.00 42,358.40 12,707.52 55,065.92
Gravel 136.64 cu.m. 1,800.00 245,952.00 73,785.60 319,737.60
Sand 54.66 cu.m. 2,000.00 109,312.00 32,793.60 142,105.60
Date: February 19, 2018
Project: Proposed Two - Storey Residence with Swimming Pool
Location: Lot 3 Brgy. Alimanguan, San Vicente, Palawan Roughing-in Works
Owner: Jose Mari Picazo
Subject: Bill of Materials
ITEM MATERIAL
DESCRIPTION QUANTITY UNIT LABOR TOTAL
NO. UNIT COST AMOUNT
c) Second Floor -
Portland Cement 270.00 bags 248.00 66,960.00 20,088.00 87,048.00
Gravel 216.00 cu.m. 1,800.00 388,800.00 116,640.00 505,440.00
Sand 86.40 cu.m. 2,000.00 172,800.00 51,840.00 224,640.00
5.8) Retaining Wall & Retaining Wall Footing 7.44 -
Portland Cement 52.08 bags 248.00 12,915.84 3,874.75 16,790.59
Gravel 41.66 cu.m. 1,800.00 74,995.20 22,498.56 97,493.76
Sand 17.50 cu.m. 2,000.00 34,997.76 10,499.33 45,497.09
5.9) Area Drain / Catch Basin 7.07 -
Portland Cement 49.46 bags 248.00 12,265.88 3,679.76 15,945.65
Gravel 39.57 cu.m. 1,800.00 71,221.25 21,366.37 92,587.62
Sand 16.62 cu.m. 2,000.00 33,236.58 9,970.97 43,207.56
5.10) Driveway - -
Portland Cement - bags 248.00 - - -
Gravel - cu.m. 1,800.00 - - -
Sand - cu.m. 2,000.00 - - -
5.11) Concrete Beam 17.14 -
Portland Cement 119.95 bags 248.00 29,748.10 8,924.43 38,672.52
Gravel 95.96 cu.m. 1,800.00 172,730.88 51,819.26 224,550.14
Sand 40.30 cu.m. 2,000.00 80,607.74 24,182.32 104,790.07
5.12) Electric Post 0.24 - -
Portland Cement 1.65 bags 248.00 407.96 122.39 530.35
Gravel 1.32 cu.m. 1,800.00 2,368.80 710.64 3,079.44
Sand 0.55 cu.m. 2,000.00 1,105.44 331.63 1,437.07
sub-total 3,841,038.00 1,152,311.40 4,993,349.40
ITEM MATERIAL
DESCRIPTION QUANTITY UNIT LABOR TOTAL
NO. UNIT COST AMOUNT
Sand 37.44 cu.m. 2,000.00 74,880.00 26,208.00 101,088.00
Fibrem bags - - -
6.2.5) Rain Water Storage 14.80 -
Portland Cement 2.84 bags 248.00 704.72 246.65 951.37
Sand 2.37 cu.m. 2,000.00 4,736.00 1,657.60 6,393.60
Fibrem bags - - -
6.2.6) Septic Tank 23.00 -
Portland Cement 4.42 bags 248.00 1,095.17 383.31 1,478.48
Sand 3.68 cu.m. 1,800.00 6,624.00 2,318.40 8,942.40
Fibrem bags - - -
6.2.7) Cistern 14.80 -
Portland Cement 2.84 bags 248.00 704.72 246.65 951.37
Sand 2.37 cu.m. 2,000.00 4,736.00 1,657.60 6,393.60
Fibrem bags - - -
6.2.8) Retaining Wall 84.00 -
Portland Cement 16.13 bags 248.00 3,999.74 1,399.91 5,399.65
Sand 13.44 cu.m. 2,000.00 26,880.00 9,408.00 36,288.00
Fibrem bags - - -
sub-total 479,664.59 167,882.61 647,547.19
ITEM MATERIAL
DESCRIPTION QUANTITY UNIT LABOR TOTAL
NO. UNIT COST AMOUNT
o
UPVC sanitary elbow 3 inch x 90 23.00 pcs 52.00 1,196.00 837.20 2,033.20
o
UPVC sanitary elbow 3 inch x 45 23.00 pcs 72.22 1,661.11 1,162.78 2,823.89
UPVC sanitary wye reducer 3 x 2 inch 17.00 pcs 64.00 1,088.00 761.60 1,849.60
UPVC sanitary p-trap 2 inch 14.00 pcs 94.00 1,316.00 921.20 2,237.20
o
UPVC sanitary elbow 4 inch x 90 14.00 pcs 79.17 1,108.33 775.83 1,884.17
o
UPVC sanitary elbow 4 inch x 45 14.00 pcs 95.00 1,330.00 931.00 2,261.00
UPVC sanitary wye 4 inch 12.00 pcs 96.00 1,152.00 806.40 1,958.40
UPVC sanitary tee 4 inch 12.00 pcs 80.00 960.00 672.00 1,632.00
Atlanta Solvent 400grams 14.00 pcs 185.00 2,590.00 1,813.00 4,403.00
UPVC sanitary clean out 2 inch 14.00 pcs 29.17 408.33 285.83 694.17
UPVC sanitary clean out 3 inch 14.00 pcs 70.00 980.00 686.00 1,666.00
UPVC sanitary clean out 4 inch 12.00 pcs 45.00 540.00 378.00 918.00
81,939.62 198,996.22
X. ELECTRICAL WORKS
Materials
24 Holes PWSCPB 1 Center Main Bolt On Koten Panel Board 1.00 pc 13,680.00 13,680.00 5,472.00 19,152.00
10 Holes PWSCPB 1 Center Main Bolt On Koten Panel Board 1.00 pc 7,320.00 7,320.00 2,928.00 10,248.00
MTS for PWSD Koten C.B. 1.00 pc 20,340.00 20,340.00 8,136.00 28,476.00
250 Amperes PWSP 2 pole Koten C.B. 3.00 pcs 7,680.00 23,040.00 9,216.00 32,256.00
150 Amperes PWSP 2 pole Koten C.B. 1.00 pcs 6,600.00 6,600.00 2,640.00 9,240.00
100 Amperes PWSP 2 pole Koten C.B. 1.00 pc 1,200.00 1,200.00 480.00 1,680.00
40 Amperes PWSP 2 pole Koten C.B. 3.00 pcs 342.00 1,026.00 410.40 1,436.40
30 Amperes PWSP 2 pole Koten C.B. 12.00 pcs 342.00 4,104.00 1,641.60 5,745.60
20 Amperes PWSP 2 pole Koten C.B. 15.00 pcs 342.00 5,130.00 2,052.00 7,182.00
NEMA 3R Box with 30 amperes 2 pole bolt on C.B. Set 5.00 pcs 822.00 4,110.00 1,644.00 5,754.00
2
3.5 mm THHN wire: 10 box red, 10 box black, 6 box green 26.00 boxes 3,588.00 93,288.00 37,315.20 130,603.20
2
5.5 mm THHN wire: 3 box red, 3 box black 6.00 boxes 5,568.00 33,408.00 13,363.20 46,771.20
2
8.0 mm THHN wire: 10 box red, 10 box black, 10 box green 2.00 boxes 10,080.00 20,160.00 8,064.00 28,224.00
2
50 mm THHN wire 60.00 mtrs 360.00 21,600.00 8,640.00 30,240.00
2
14 mm THHN wire 30.00 mtrs 114.00 3,420.00 1,368.00 4,788.00
2
125 mm THHN wire 120.00 mtrs 900.00 108,000.00 43,200.00 151,200.00
2
30 mm THHN wire 30.00 mtrs 216.00 6,480.00 2,592.00 9,072.00
1/2 inch UPVC pipe thick wall 350.00 pcs 84.00 29,400.00 11,760.00 41,160.00
3/4 inch UPVC pipe thick wall 100.00 pcs 108.00 10,800.00 4,320.00 15,120.00
1-1/4 inch UPVC pipe thick wall 30.00 pcs 192.00 5,760.00 2,304.00 8,064.00
1 inch UPVC pipe thick wall 20.00 pcs 144.00 2,880.00 1,152.00 4,032.00
2-1/2 inch UPVC pipe thick wall 25.00 pcs 384.00 9,600.00 3,840.00 13,440.00
2-1/2 inch UPVC long elbow 3.00 pcs 204.00 612.00 244.80 856.80
1-1/4 inch UPVC long elbow 6.00 pcs 54.00 324.00 129.60 453.60
1/2 inch UPVC flexible hose 4.00 rolls 816.00 3,264.00 1,305.60 4,569.60
1/2 inch UPVC flexible hose connector 6.00 packs 480.00 2,880.00 1,152.00 4,032.00
1/2 inch UPVC clamp 6.00 packs 240.00 1,440.00 576.00 2,016.00
2x4 inch UPVC utility box poly 140.00 packs 24.00 3,360.00 1,344.00 4,704.00
UPVC junction box poly 100.00 pcs 36.00 3,600.00 1,440.00 5,040.00
4x4 inch UPVC square box poly 20.00 pcs 84.00 1,680.00 672.00 2,352.00
12x12 inch metal pull box 1.00 pc 864.00 864.00 345.60 1,209.60
10x10 inch metal pull box 4.00 pcs 648.00 2,592.00 1,036.80 3,628.80
8x8 inch metal pull box 2.00 pcs 504.00 1,008.00 403.20 1,411.20
1 Gang switch set wide series panasonic 10.00 pcs 150.00 1,500.00 600.00 2,100.00
2 Gang switch set wide series panasonic 3.00 pcs 228.00 684.00 273.60 957.60
3 Gang switch set wide series panasonic 8.00 pcs 312.00 2,496.00 998.40 3,494.40
2 Gang 3way switch set wide series panasonic 6.00 pcs 372.00 2,232.00 892.80 3,124.80
1 Gang 3way switch set wide series panasonic 2.00 pcs 216.00 432.00 172.80 604.80
2 Gang 3 prong universal outlet set wide series panasonic 14.00 pcs 150.00 2,100.00 840.00 2,940.00
1 Gang 3 prong universal outlet set wide series panasonic 46.00 pcs 372.00 17,112.00 6,844.80 23,956.80
2 Gang 3 prong weather proof outlet set 5.00 pcs 576.00 2,880.00 1,152.00 4,032.00
1 Gang 3 prong water heater outlet set wide series panasonic 3.00 pcs 550.00 1,650.00 660.00 2,310.00
Ground fault circuit interrupter outlet set 250V/20a, GMA sensitivity 14.00 pcs 3,360.00 47,040.00 18,816.00 65,856.00
3 mtrs x 5/8 inch ground rod 2.00 pcs 480.00 960.00 384.00 1,344.00
5/8 inch ground rod heavy duty ground clamp 2.00 pcs 228.00 456.00 182.40 638.40
3/8 inch mica tube 16.00 mtrs 28.80 460.80 184.32 645.12
Butane gas 12.00 pcs 84.00 1,008.00 403.20 1,411.20
Electrical tape 40.00 pcs 30.00 1,200.00 480.00 1,680.00
400 grams solvent cement 6.00 pcs 456.00 2,736.00 1,094.40 3,830.40
#16 Tie wire 6.00 kg 90.00 540.00 216.00 756.00
215,382.72 753,839.52
Date: February 19, 2018
Project: Proposed Two - Storey Residence with Swimming Pool
Location: Lot 3 Brgy. Alimanguan, San Vicente, Palawan Roughing-in Works
Owner: Jose Mari Picazo
Subject: Bill of Materials
ITEM MATERIAL
DESCRIPTION QUANTITY UNIT LABOR TOTAL
NO. UNIT COST AMOUNT
I. OTHERS
1.1) Gate lot included -
1.2) Swimming Pool & Deck 1.00 lot 973,503.00 included 973,503.00
1.4) Landscaping lot included -
sub-total 973,503.00