Method Statement submitted for eaxcavation at Bambalapitiya Pump Station deviate with designers recomendation in note 5 mentioned in
accepted working drawing no LE150572-C-WW-SW-GA-BAM-3023

LE150572-C-WW-SW-GA-BAM-3023 LTCD/GCRW-WET/WW/MSD/BAM/1036
Maximum
Excavation Level Supporting System Excavation Stage Level Supporting System
Level
Up to Lvl 1 +2.3 MSL With support at +3.90 MSL Excavation Stage 01 +4.25 MSL to -0.10 MSL After reaching -0.10 MSL
Bracing provided at +3.90 MSL
& +0.90MSL
Lvl 1 to Lvl 2 +2.3 MSL to -0.1 MSL With support at +3.90 MSL & +0.90 MSL Excavation Stage 02 -0.10 MSL to -4.282 MSL After reaching -4.282 MSL
Bracing provided at -2.10MSL
Lvl 2to Lvl 3 -0.10 MSL to -4.282 MSL With support at +3.90 MSL, +0.90 MSL Excavation Stage 03 -4.282 MSL to -7.563 MSL After reaching -7.563 MSL
& -2.10 MSL Bracing provided at -5.10MSL
Lvl 3 to Lvl 4 -4.282 MSL to -6.164 MSL With support at +3.90 MSL, +0.90 MSL,
-2.10 MSL & -5.10 MSL
Lvl 4 to Lvl 5 -6.164 MSL to -7.563 MSL With support at +3.90 MSL, +0.90 MSL,
-2.10 MSL & -5.10 MSL
Immediately after reaching the
excavation level to -6.164 MSL, the
support at -5.10 MSL shall be installed

2. Not mentioned any mechanism to monitor the horizontal deflection of secant pile and ground settlement & Water fluctuation level outside the
excavation area.