You are on page 1of 2

Date ………/……/2020

Project Manager : Mr Cheang Makara


Site Manager : Mr. Thach San
Project : BOREY TESCHOR
BILL OF QUANTITIES FOR VO (CASTING CONCRETE ROOF FLOOR)
STRUCTURE WORK SINGLE VILLA(12x10m)
Materials Cost Labor Cost
No Description Unit Amount Total
Unit Cost Total Cost Unit cost Total
A Option 01 ចាក់ខាងក្នុង (ពីរផ្ទះ) $ 2,573.94 $ 871.06 $ 3,444.99
I Beam
Form work sq.m 15.71 $ 7.00 $ 109.96 $ 4.00 $ 62.83 $ 172.79
Rebar Ton 0.25 $ 690.00 $ 174.76 $ 110.00 $ 27.86 $ 202.62
Concrete (28PMa ) cu.m 1.12 $ 72.00 $ 80.78 $ 15.00 $ 16.83 $ 97.61
Sub Total $ 365.50 $ 107.52 $ 473.03
II Slab
Form work sq.m 129.42 $ 7.00 $ 905.96 $ 4.00 $ 517.69 $ 1,423.65
Rebar Ton 0.76 $ 690.00 $ 521.50 $ 110.00 $ 83.14 $ 604.63
Concrete (28PMa ) cu.m 10.85 $ 72.00 $ 780.98 $ 15.00 $ 162.70 $ 943.68
Sub Total $ 2,208.43 $ 763.53 $ 2,971.96
B Option 02 ចាក់ខាងក្នុង (មួយផ្ទះ) $ 1,286.97 $ 435.53 $ 1,722.50
I Beam
Form work sq.m 7.85 $ 7.00 $ 54.98 $ 4.00 $ 31.42 $ 86.39
Rebar Ton 0.13 $ 690.00 $ 87.38 $ 110.00 $ 13.93 $ 101.31
Concrete (28PMa ) cu.m 0.56 $ 72.00 $ 40.39 $ 15.00 $ 8.42 $ 48.81
Sub Total $ 182.75 $ 53.76 $ 236.51
II Slab
Form work sq.m 64.71 $ 7.00 $ 452.98 $ 4.00 $ 258.85 $ 711.83
Rebar Ton 0.38 $ 690.00 $ 260.75 $ 110.00 $ 41.57 $ 302.32
Concrete (28PMa ) cu.m 5.42 $ 72.00 $ 390.49 $ 15.00 $ 81.35 $ 471.84
Sub Total $ 1,104.22 $ 381.77 $ 1,485.98
C Option 03 ចាក់ស្លា បខាងក្រៅ (ពីរផ្ទះ) $ 4,067.98 $ 1,356.07 $ 5,424.05
I Beam
Form work sq.m 49.59 $ 7.00 $ 347.12 $ 4.00 $ 198.35 $ 545.47
Rebar Ton 0.63 $ 690.00 $ 437.48 $ 110.00 $ 69.74 $ 507.23
Concrete (28PMa ) cu.m 3.54 $ 72.00 $ 255.02 $ 15.00 $ 53.13 $ 308.15
Sub Total $ 1,039.62 $ 321.23 $ 1,360.85
II Slab
Form work sq.m 173.65 $ 7.00 $ 1,215.54 $ 4.00 $ 694.60 $ 1,910.14
Rebar Ton 1.11 $ 690.00 $ 764.96 $ 110.00 $ 121.95 $ 886.91
Concrete (28PMa ) cu.m 14.55 $ 72.00 $ 1,047.85 $ 15.00 $ 218.30 $ 1,266.15
Sub Total $ 3,028.35 $ 1,034.85 $ 4,063.20

សៀមរាប , ថ្ងៃទី....... ​ខែ....... ឆ្នា ំ ២០២០


ឯកភាពដោយ ប្រធានគំរោង ត្រួតពិនិត្យដោយ ប្រធានការដ្ឋា ន ត្រួតពិនិត្យដោយអនុប្រធានការដ្ឋា ន Inspector វស្វ
ិ ករប្លុក ក្រុមម៉ៅ KHTC
និង ប្រធានបច្ចេកទេស

លោក ឈាង មករា លោក ថាច់ សាន លោក ឈន


ិ សុ ខខេង លោក ហង់ យ៉ា ងហ៊រ លោក រួត ទិតណាង លោក ............................
Materials Cost Labor Cost
No Description Unit Amount Total
Unit Cost Total Cost Unit cost Total
A House I08 $ 1,474.90 $ 553.96 $ 2,028.86
I Beam
Form work sq.m 6.78 $ 9.00 $ 61.03 $ 6.00 $ 40.69 $ 101.71
Rebar Ton 0.08 $ 800.00 $ 67.39 $ 32.00 $ 2.70 $ 70.09
Tie wire kg 2.11 $ 0.80 $ 1.68 $ 0.08 $ 0.17 $ 1.85
Concrete (28PMa ) cu.m 0.48 $ 81.70 $ 39.22 $ 12.20 $ 5.86 $ 45.07
Sub Total $ 169.32 $ 49.41 $ 218.73
II Slab
Form work sq.m 63.24 $ 9.00 $ 569.16 $ 6.00 $ 379.44 $ 948.60
Rebar Ton 0.39 $ 800.00 $ 315.20 $ 32.00 $ 12.61 $ 327.81
Tie wire kg 9.85 $ 0.80 $ 7.88 $ 0.08 $ 0.79 $ 8.67
Concrete (28PMa ) cu.m 5.06 $ 81.70 $ 413.34 $ 12.20 $ 61.72 $ 475.06
Concrete Pump set 1.00 $ - $ 50.00 $ 50.00 $ 50.00
Sub Total House I08 $ 1,305.58 $ 504.56 $ 1,810.13
B House I21 $ 1,474.90 $ 553.96 $ 2,028.86
I Beam
Form work sq.m 6.78 $ 9.00 $ 61.03 $ 6.00 $ 40.69 $ 101.71
Rebar Ton 0.08 $ 800.00 $ 67.39 $ 32.00 $ 2.70 $ 70.09
Tie wire kg 2.11 $ 0.80 $ 1.68 $ 0.08 $ 0.17 $ 1.85
Concrete (28PMa ) cu.m 0.48 $ 81.70 $ 39.22 $ 12.20 $ 5.86 $ 45.07
Sub Total $ 169.32 $ 49.41 $ 218.73
II Slab
Form work sq.m 63.24 $ 9.00 $ 569.16 $ 6.00 $ 379.44 $ 948.60
Rebar Ton 0.39 $ 800.00 $ 315.20 $ 32.00 $ 12.61 $ 327.81
Tie wire kg 9.85 $ 0.80 $ 7.88 $ 0.08 $ 0.79 $ 8.67
Concrete (28PMa ) cu.m 5.06 $ 81.70 $ 413.34 $ 12.20 $ 61.72 $ 475.06
Concrete Pump set 1.00 $ - $ 50.00 $ 50.00 $ 50.00
Sub Total House I08 $ 1,305.58 $ 504.56 $ 1,810.13
C House I24 $ 2,275.55 $ 829.07 $ 3,104.62
I Beam
Form work sq.m 22.78 $ 9.00 $ 205.03 $ 6.00 $ 136.69 $ 341.71
Rebar Ton 0.15 $ 800.00 $ 123.47 $ 32.00 $ 4.94 $ 128.41
Tie wire kg 3.86 $ 0.80 $ 3.09 $ 0.08 $ 0.31 $ 3.40
Concrete (28PMa ) cu.m 2.08 $ 81.70 $ 169.94 $ 12.20 $ 25.38 $ 195.31
Sub Total $ 501.53 $ 167.31 $ 668.83
II Slab
Form work sq.m 85.00 $ 9.00 $ 765.00 $ 6.00 $ 510.00 $ 1,275.00
Rebar Ton 0.55 $ 800.00 $ 442.40 $ 32.00 $ 17.70 $ 460.10
Tie wire kg 13.83 $ 0.80 $ 11.06 $ 0.08 $ 1.11 $ 12.17
Concrete (28PMa ) cu.m 6.80 $ 81.70 $ 555.56 $ 12.20 $ 82.96 $ 638.52
Concrete Pump set 1.00 $ - $ 50.00 $ 50.00 $ 50.00
Sub Total House I08 $ 1,774.02 $ 661.76 $ 2,435.78
GRAND TOTAL STRUCTURAL WORK $ 5,225.34 $ 1,937.00 $ 7,162.34