Salient Features

‰ Material required per meter square for various thickness of plaster

The notes attached herewith are for information only.


The Rates of the DSR have no bearing on the notes
enclosed herewith.
In case of any dispute regarding interpretation of
item it’s specifications etc. the reference to original
specifications shall be made.

245
MATERIALS REQUIRED PER MI FOR VARIOUS THICKNESS OF PLASTER

Mix Material Thickness, mm


5 10 20 30 40 50

1:1 C 5.1 10.1 20.3 30.5 40.6 50.8


FA 3.5 7.1 14.2 21.3 28.4 35.5
1:1 ½ C 4.1 8.2 16.3 24.5 32.6 40.8
FA 4.3 8.6 17.1 25.6 34.2 42.7
1:2 C 3.4 6.9 13.7 20.6 27.5 34.4
FA 4.8 9.6 19.3 28.9 38.5 48.1
1:2 ½ C 2.9 5.9 11.7 17.5 23.4 29.2
FA 5.1 10.2 20.5 30.7 41.0 51.2
1:3 C 2.5 5.1 10.1 15.2 20.2 25.3
FA 5.3 10.6 21.2 31.8 42.4 53.0
1:4 C 2.0 4.0 7.9 11.9 15.8 19.7
FA 5.5 11.1 22.1 33.2 44.2 55.3
1:6 C 1.4 2.9 5.7 8.6 11.4 14.3
FA 6.0 12.0 23.9 35.9 47.9 59.9
1:8 C 1.1 2.2 4.4 6.6 8.8 11.0
FA 6.2 12.3 24.6 37.0 49.3 61.6

C = Cement in Kilograms FA = fine aggregate (sand) in litres

NOTE : No allowance has been made in table for bulking and wastage