Professional Documents
Culture Documents
HCA 1333/2011
B IN THE HIGH COURT OF THE B
E E
BETWEEN
F 383HK LIMITED Plaintiff F
G G
and
H H
THE INCORPORATED OWNERS OF Defendant
TAK BO BUILDING
I I
J J
K K
Before: Deputy High Court Judge Burrell in Court
L Dates of Hearing:6 – 10 and 14 March 2017 L
N N
JUDGMENT
O O
P P
15 of the shops (including number 17) have frontages on the streets around
T T
U U
V V
A A
the building. The remainder are in the corridors which form a T-shaped
B arcade inside the ground floor. B
C C
2. The central issue in this case concerns the supply of fresh
D water and drainage facilities to the ground floor. The occupation permit D
for the building was issued in 1979 and 30 years later, in 2009, the plaintiff
E E
purchased Unit 17, with vacant possession. The sole witness as to factual
F matters for the plaintiff has been its director, referred to as “Mrs Chan”. F
J its chairman at the material time (2010 – 11) Mr Chan Kit Yan who has J
been a resident in the building since it was built and is now 75 years of
K K
age. Mr Ambrose Ho SC, leading Ms Becky Wong, were the IO’s counsel
L at trial. L
M 4. When the building was designed and built in the late 1970s, M
there were no provisions or facilities included for fresh water and drainage
N N
pipes to the individual shop premises on the ground floor. If shop owners
O required water they went to the toilets which formed part of the ground O
P
floor. There are approximately 10 toilet units in one particular area inside P
the arcade. The toilets are connected to the building’s main fresh water
Q Q
pipe and drainage pipe.
R R
5. The general nature of the type of small commercial premises
S S
which have done business in the Tak Bo shopping arcade since the early
T
1980s is, no doubt, partly due to the fact that the units are not connected to T
U U
V V
A A
the building’s water and drainage main pipes. A survey done in 2013
B describes about 50% of the shops as “printing” shops, others include car B
shop would increase its rental value. At that time she had no particular
H H
tenant lined up. The evidence, in fact, showed that 4 of the 35 shops had
I some such piping. One of the 4 was a hairdressing shop so it may be I
assumed that the water was actually used. Whether it was used in the other
J J
3 was not clear. Two of them were described as “printing shops”, the other
K “car accessories”. In any event, these pipings were not recent installations K
(even in 2010) but had been there some time. It was the IO’s case that
L L
none of them had resulted from consent being sought from the IO, none of
M them had been approved and none of them were legal. The plaintiff on the M
other hand submitted that the IO’s inaction in regard to these particular
N N
pipes provided weight to its argument that the IO’s refusal to consent to
O Mrs Chan’s request for fresh water and drainage was unreasonable. O
P P
7. On becoming the registered owner Mrs Chan asked the IO for
Q its consent to such an application. The IO considered the request but Q
refused it stating:
R R
“ The members unanimously agreed that shops can use the water
supply in toilet and that the installation of independent water
S meters would involve too many issues on the unified S
management of the building. Therefore, the Incorporated
Owners rejects the application from your company for
T T
U U
V V
A A
installation of independent water meter. We hope you can
respect our decision.”
B B
H H
9. Thus, the plaintiff’s request had become a notification that the
I work would proceed regardless. Further, the plaintiff had, in fact, not I
O
11. By February 2010 the matter was in the hands of solicitors. O
By a letter of 8 March 2010 the IO’s position was stated as follows:
P P
“ We are instructed that a water tap has been installed in the
Q lavatory on the Ground Floor for supplying water to the owners Q
and/or their occupiers. Having considered that the water tap at
Ground Floor has been installed for supplying water to owners
R and/or their occupier of Ground Floor and your client is allowed R
to reasonable use for the water tap installed in the lavatory on the
Ground Floor without interruption, out client does not accept
S S
your client’s application for installing water pipe(s) and/or its
ancillary at the common parts of the Building.
T T
U U
V V
A A
Apart from that, we would like to draw your attention to
section 34I of the Building Management Ordinance (Cap. 344)
B that no owner is allowed to convert the common part into his B
own use without the prior consent of the management committee
of our client. Hence, our client has a right to refuse your client’s
C C
application.
J 13. This work involved drilling two holes (one 40 mm in diameter J
for the drainage and one 25 mm in diameter for the fresh water and about
K K
15 mm apart) through the concrete canopy which ran around the outside of
L the building at the ceiling level of the ground floor shops. The plan was L
then to run the pipes along the surface of the canopy to the main pipes
M M
across the common areas of the building.
N N
the time, consent and approval by the BD was a requirement. It was also
Q Q
contrary to a circular which had been sent to all the owners in the building
R on 20 January 2010 which, inter alia, stated: R
U U
V V
A A
and faced the risk of legal proceedings referred to in the earlier solicitor’s
B letter. B
C C
15. Unfortunately, the licensed plumber’s work was not
D completed because he inadvertently, in the course of his work, shut down D
all the water supply to the commercial premises in the upper floors. This
E E
caused immediate complaints and even the police were called. The work
F stopped, the plumber left the site and, later, Mrs Chan apologized for the F
installed through the drill holes in the canopy above the plaintiff’s shop
I I
having sealed them up.
J J
enjoyed a fresh water supply since July 2011 but still has no provision for
N N
drainage.
O O
U U
V V
A A
Statement of Claim also seeks an order directing the IO to give its written
B consent to the works and an injunction preventing the IO from interfering B
Clause 3 (c):
F F
“ 3. Each owner shall hold his part of the said building and the
said premises subject to and with the benefit of the
G following rights privileges and obligations namely:- G
…
H (c) The free and uninterrupted passage and running of water H
sewage gas and electricity from and to his part of the
I
said building through the sewers, drains, watercourses, I
cables, pipes, pumps, tanks and wires which now are or
may at any time hereinafter be in under or passing
J through the said premises and building or any part or J
parts thereof.”
K K
Clause 4 (t) (ii):
U U
V V
A A
building or do anything whereby the structural strength
thereof may be affected.
B … B
(e) Not to use his part of the said building for any illegal or
C immoral purposes nor do or permit anything therein or C
thereupon which may create unnecessary noise or may
be a nuisance or annoyance to or may cause damage or
D inconvenience to the other occupiers of the said D
building.”
E E
unreasonably).
H H
I The issues I
Building.
Q Q
Issue 3 — If the piping has to go through or utilize the common part
R of the Building and the consent of the defendant is R
U U
V V
A A
Issue 4 — Whether in the event that transpired prior to the
B commencement of the action, the defendant had in all the B
Q
in contravention of clauses 10 (a), (b) and (c) of the DMC; did Q
cause damage to the building; were commenced without
R approval or consent and were illegal; R
S
(iv) if carried out today the work would not be “minor works” S
and/or “designated exempted works”; and
T T
22. in any event the plaintiff suffered no loss.
U U
V V
A A
Issue 1: Whether the terms of the DMC and/or the implied term conferred
even a conditional entitlement on the plaintiff?
B B
constructed with no water or drainage supply to the shop owners) its true
E E
and unambiguous meaning can be derived by summarizing the clause in
F the following way: F
K K
24. In my judgment the expression “may at any time hereinafter”
L can only refer to the possibility that in the future the owners of the building L
(or the IO) decides to put in new piping, for whatever reason, anywhere in
M M
the building. Only then might the ground floor have the “benefit of
N N
running water” through pipes etc. Absent such new piping there are no
O
pipes etc from which the plaintiff can “benefit” to access a new water O
supply.
P P
S S
T T
U U
V V
A A
26. Both counsel referred the court to a number of authorities on
B this issue, including: B
Ltd CACV 40/2003;
E E
Cogi Enterprises Ltd v The Incorporated Owners of Malahon
F Apartments HCA 816/2004 and CACV 108/2010; F
27. Mr Ho relied on, inter alia, the Success case above in which
I I
Zervos J was dealing with a situation concerning, in similar circumstances
J to the present case, the supply of natural gas to an entire building which at J
the time had no such supply. Mr Chiu sought to distinguish that case on
K K
the ground that in our case the building already had a water supply,
L whereas in Success there was no (gas) supply at all. I agree with Mr Ho L
that this is not a valid distinction. The proper comparison is between the
M M
whole building (in Success) and the whole of the ground floor (in the
N present case). The plaintiff in our case is seeking a construction of the N
O
DMC which would confer the same right (albeit, as Mr Chiu carefully O
emphasised, which could be conditional) on the whole of the ground floor.
P P
Thus, it is the general principle in Success which is important and therefore
Q
useful to cite herein a lengthy extract: Q
U U
V V
A A
provided through the existing pipes or pipes which are
subsequently installed on the Land or Building. I interpret this
B provision to mean that an owner will be guaranteed the free and B
uninterrupted passage of essential services through the existing
or subsequent system in place for the supply or passage of the
C C
service. It is required, therefore, that the system in place should
provide the owner free and uninterrupted supply or passage of
D the service whether existing or subsequently installed. Where D
there is no system in place, it still requires the incorporated
owners to decide on a system to be installed in accordance with
E the decision making process as provided under the DMC. Once E
a system of pipes for the supply of gas has been decided to be
F and is installed, the plaintiffs are [then] entitled to the free and F
uninterrupted connection of gas under the system in place
whether now or in the future, but this still requires the
G incorporated owners to agree a system for the connection of gas G
to the units of the Building. It does not entitle an individual unit
owner to connect gas to his unit, unless a decision of the
H H
incorporated owners has been made for that to happen in
accordance with the provisions of the DMC. It entitles an
I individual unit owner the guarantee of free and uninterrupted I
passage of gas through the system put in place whether now or in
the future. It does not in my view guarantee as of right an
J J
individual unit owner the supply of gas through his own and
exclusive system of pipes on or over common areas of the
K Building, unless it is in accordance with the provisions of the K
DMC.
R R
S S
T T
U U
V V
A A
28. The “Clause 3” referred to was effectively the same as
B clause 3 (c) in the current case. An almost identical clause was also in B
issue in the Cogi case (above). In that case the parties were reversed as it
C C
was the IO making the application. Nonetheless the same principles were
D adopted. The Court of Appeal cited Sakhrani J’s remarks with approval: D
U U
V V
A A
Shop 17 in 2010 was illegal and (iv) any such piping would inevitably
B encroach on the common areas of the building) must lead to the same B
conclusion.
C C
K K
31. Thus the BMO does not contemplate a situation where a
L plaintiff acquires a right to encroach on the common part of the building. L
M M
32. To conclude on this issue the plaintiff has failed to establish
N that on a proper analysis the DMC provides for or entitles the plaintiff to N
P Issues 2 and 3 P
Q 33. Mr Chiu has largely abandoned issue 2 but I shall deal with it Q
briefly (as it retains some relevance with regard to issue 4) in the context
R R
of the implied term issue.
S S
34. The plaintiff submits that a term should be implied into the
T T
DMC that a shop owner such as the plaintiff has the ‘right’ contended for,
U U
V V
A A
namely, a right to water, drainage and the installation of pipes for the same,
B with the consent of the IO not being unreasonably withheld. B
C C
35. As a starting point, the fact that the DMC does not
D specifically provide for or entitle the plaintiff to a water and drainage D
supply does not, of itself, preclude or prevent the IO from agreeing to such
E E
an arrangement if it considers it to be consistent with the good
F management of the building. F
G G
36. In the pleadings both parties argue for an implied term: the
H plaintiff for a term that the consent to an application for water and drainage H
K K
37. In my judgment the appropriate way of resolving these
L competing submissions is to deal with the last point first; namely, was the L
O O
38. Issue 2 (estoppel) can be first disposed of briefly by reference
P to Mr Chiu’s concession as follows: P
U U
V V
A A
Accordingly we will not make further submission under this
head.”
B B
E
19 and 21 are believed to have installed a water pipe (when is not known) E
and Shops 30 and 31 have connected water and drainage pipes through the
F F
wall of the shops to the toilets. The only shop which it can be safely
G
inferred has used its water supply is Shop 31 which is (or at least was in G
2013) a hairdressing salon. There is no factual evidence that any of these
H H
pipes are connected to the building’s main pipes. It is also a fact that the
evidence that they were ever asked. Finally, it is agreed that the
J J
uncompleted works carried out by the plaintiff in August 2010 were illegal
K works. K
L L
Issue 4: Unreasonableness?
M M
40. The parties agree that the burden is on the plaintiff to show
N that the IO’s refusal to consent to the plaintiff’s request was unreasonable. N
The authority for this proposition is BG Global Energy Ltd v Talisman
O O
Sinopec Energy UK Ltd [2015] EWHC 110 (Comm).
P P
41. As to the correct test to be applied Mr Chiu refers the court to
Q Q
Ashworth Frazer Ltd v Gloucester City Council [2001] 1 WLR 2180 as an
R authority for the proposition that the IO’s reasonableness or otherwise must R
be measured in the light of what was stated at the time of refusal and that
S S
the IO is not permitted to rely on grounds which surface subsequently. In
T particular, in the present case, Mr Chiu submits that the IO cannot rely on T
U U
V V
A A
the fact that the 2010 works in fact required the BD’s consent and were
B therefore illegal, because this came to light later and was relied on by the B
the illegality of the 2010 works cannot be relied on, I do not agree. The
E E
Ashworth case concerned a dispute under the Landlord and Tenant Act
F 1988 in the UK, where consent or refusal was governed by the terms of the F
statute. Moreover, even within that strict statutory regime (which does not
G G
apply to the facts of the present case) the judgment recognized the need for
H some latitude saying: H
43. The judgment had earlier set out the overriding principles
P P
including:
Q “ … in any case where the requirements of the first principle are Q
met, the question whether the landlord'’ conduct was reasonable
or unreasonable will be one of fact to be decided by the tribunal
R R
of fact.”
and
S S
“ … the landlord’s obligation is to show that his conduct was
reasonable, not that it was right or justifiable. …. one ‘should
T T
read reasonableness in the general sense’. There are few
U U
V V
A A
expressions more routinely used by British lawyers than
‘reasonable’, and the expression should be given a broad,
B common sense meaning in this context as in others.” B
C C
44. Accordingly, the legality of the proposal must be a crucial
D
factor. I reject Mr Chiu’s submission that if the works are later found to be D
illegal the remedy is the repudiation of the consent by reason of mistake of
E E
law and the subsequent removal of the offending works. In my judgment
F the plaintiff fails to discharge the burden on it to prove that the IO was F
unreasonable when the request was for an illegal installation and was
G G
supported by an inaccurate plan. The only plan submitted at the time was
H prepared by the licensed plumber which showed the proposed pipes joining H
the building main pipes whereas, in evidence at trial, it was said that the
I I
new pipes went directly and independently into the gutter next to the main
J drainage pipe. J
K K
45. Also, as earlier stated, the application contained more
L inaccuracies than merely in the proposed plan. The plaintiff had stated that L
an application to the WSD had been made when it had not and, later, that
M M
the WSD had approved, when it had not.
N N
T T
U U
V V
A A
(2) The IO was concerned about the safety of the canopy. Any
B layman would be concerned about the drilling of holes in B
N
IO in its letter dated 12 July 2010 in which it reminded the N
plaintiff of clause 10 (b) of the DMC (not to make alterations
O which may cause damage) and clause 10 (e) (not to use the O
(7) The plaintiff’s second witness of fact, Mr Wu Kun Wa, gave
R R
evidence of the Committee’s discussions through the minutes
S of its meetings. It is clear that any holes in the canopy would S
U U
V V
A A
scheme which lacked detail, which was not ‘in keeping’ with
B the established nature of the arcade’s business, which was a B
I 47. The plaintiff has asked the court to make a ruling on this I
BD and ask the question “do we need your consent for these works or do
L L
they fall within the ‘minor works’ regime or ‘designated exempted
M works’”. In this case I have heard expert evidence from two helpful and M
the effect would be to usurp the function of the BD. In any event such a
R R
ruling would only be pertinent to the exact works which were in fact
S carried out in 2010. Thus, the ruling which would not bind the BD in any S
event is confined to the drilling of two holes, one 40 mm in diameter and
T T
one 25 mm, in the canopy above the plaintiff’s shop.
U U
V V
A A
49. The plaintiff’s expert was Mr Paul Kong Ming of Paul Kong
B & Partners Ltd, Design and Planning Consultant Engineers. He wrote 2 B
reports totalling 40 pages with 110 pages of exhibits. The defendant called
C C
Professor Fan Siu Kay, a registered structural engineer and Authorised
D Person, whose report was 43 pages with 150 pages of exhibits. They also D
G G
50. At the beginning of 2011 a new statutory regime came into
H operation in which certain building works were exempted from the H
necessity of BD consent. Mr Chiu has helpfully set out the two areas of
I I
disagreement under the new regime, between the experts as follows:
J J
(1) Whether the drilling of the holes in the canopy above Shop 17
K meet the conditions set out in Part 2, item 1 in Schedule 2 to K
U U
V V
A A
so that it is “Designated Exempted Works” (“DEW”) and
B thereby exempted from consent under section 41 (3B) of the B
E
(2) Whether the drainage pipe work would meet the conditions E
set out in Part 3, item 3.23 of Schedule 1 to the Building
F (Minor Work) Regulation so that it is a Class III Minor Works F
N
51. Guidance as to the proper approach to deciding whether an N
exemption applies in this context is found in Mariner International Hotels
O O
Ltd v Atlas Ltd (2007) 10 HKCFAR 1 per Bokhary PJ at p 26:
P
“ …. Mr Sumption submits that the exemption has to be construed P
narrowly in a manner consistent with the statutory scheme of
which it forms a part. I accept that submission. A purpose, if not
Q the purpose, of the approval scheme of our building legislation is Q
to protect the public by subjecting the matter of structural
acceptability to the scrutiny of the Building Authority. To widen
R R
the exemption would be to reduce such scrutiny. In my view,
Mr Sumption is right in his submission, on the first requirement,
S that building works added to a building involves its structure if S
they serve a structural function or are capable for some reason of
affecting the integrity of the structure. That is to be derived from
T purpose. And it is also to be derived from linguistic T
U U
V V
A A
consideration, for I think that Mr Sumption is right in
characterizing the word ‘involving’ as one of the broadest words
B of association known to the English language. Perhaps only B
phrases like ‘in relation to’, ‘relating to’ and ‘with respect to’ are
wider.”
C C
52. Professor Fan’s starting point was that the exemptions could
E E
never apply to a cantilevered slab. His reasoning being that it was
F impossible not to affect the “load” on a cantilevered slab if a hole is drilled F
through it. He said quite simply that this legislation does not apply to
G G
cantilevered slabs. There is some logic to this opinion on the basis that it
H is unlikely that the BD intended to permit the drilling of holes in concrete H
I
slabs which protrude over busy pavements without their approval. On the I
other hand there is some force in Mr Chiu’s submissions that
J J
“cantilevered” slabs are not excluded. He points out that if, for the
K
purposes of the legislation, the definition of “slab” meant all slabs other K
than cantilevered slabs, then it would have been easy for the legislature to
L L
say so in the definition section. Also, what 1 (a), above, must mean is that
O 53. The experts also disagreed on how the word “load” should be O
construed. Both experts gave detailed consideration to this and many other
P P
issues. In my judgment it would serve no useful purpose in setting them
Q out at length. The question posed to the court is a narrow one. A decision Q
being made through the concrete. I accept that a reduction in the structural
T T
strength of the canopy must follow as a result of holes being drilled
U U
V V
A A
through it and that, in turn, redistributes and increases the “stress” or
B “load” on the canopy. B
C C
54. Thus, I am not satisfied that the plaintiff can safely say that
D 1 (a), above, in the Minor Works regime has been satisfied. If 1 (a) is not D
satisfied, then neither is 1 (b). Mr Kong agreed with this. However, even if
E E
the plaintiff’s submissions as to the meaning of “slab” and “load” are right
F the matter does not end there. F
G G
55. 1 (c) and 1 (d) deal with restrictions on drilling holes in slabs.
H In support for his opinion Professor Fan, inter alia, referred to the H
T 1 T
Practice Notes for Authorized Persons, Registered Structural Engineers and Registered
Geotechnical Engineers
U U
V V
A A
repair work as soon as possible in order to ensure that the canopy
is safe and there is no unauthorized structure erected on it.”
B B
57. The two holes drilled in the slab have a space of 15 mm
C C
between them. 1 (d), above, states that there should be a gap of 450 mm
D between a drilled hole and a hole which is already there. Professor Fan, D
E
construing this provision narrowly, was of the opinion that once a hole is E
drilled in the slab a second hole must be 450 mm away. The second hole
F F
in the present case was a mere 15 mm away. Or, if measured from the
G
outside edge of each hole it is still only 80 mm. G
H H
58. Mr Kong’s opinion was that when two holes are drilled at the
I
same time they should constitute a single hole and they must be at least I
450 mm away from any hole drilled on a previous occasion. A flaw in this
J J
approach is what if a third, fourth or fifth hole is drilled on the same
L L
59. Construing 1 (d) strictly, I think Professor Fan’s opinion
M
should prevail. Condition 1 (d) is not satisfied. M
N N
(2) The drainage pipe
O 60. As stated earlier, the plaintiff connected her shop to the public O
water supply in Nelson Street in 2012. We are only concerned now with
P P
the drainage pipe which ran from the opening in the canopy along the
Q Q
surface of the canopy to the main drainage pipe at the rear of the building.
R R
61. Mr Ho, for the defendant, submits that the proposed works do
S not satisfy 3.23 (b), above, namely that “the works do not involve any main S
U U
V V
A A
Mr Kong accepted that if the proposed drainage pipe was to be connected
B to the main drain it could not be an exempted work. The original plan B
D 62. In the event this academic point became even more academic D
M 63. The bulk of the expert evidence centred on whether (3C) (a) M
applied to the present case. Opinions differed. Mr Chiu does not concede
N N
that (3C) (a) is fatal to his case, he submits that the drainage pipes once
O secured to the building would not “affect its structure”. However, he very O
fairly acknowledges that (3C) (b) would apply to the plaintiff’s proposed
P P
works.
Q Q
U U
V V
A A
canopy. Mr Kong had not noticed it beforehand. The competing opinions
B as to its cause were that, according to Mr Kong, it was likely to be a B
that can be said is that given its location it would be risky to exclude
E E
Professor Fan’s opinion.
F F
their respective opinions, much of which has not been touched on in this
I I
judgment.
J J
Issue 6: Damages
M M
was the plaintiff’s expert and Mr Keith L H Siu the defendant’s. Again,
R R
the report and exhibits were voluminous and again, there was only sparse
S areas of agreement. S
T T
U U
V V
A A
69. The basic facts were that the plaintiff became the owner of a
B vacant unit in September 2009. (I shall use round figures throughout the B
following assessments.) The previous tenant had been paying $72,000 per
C C
month. The property remained vacant until 2012 when it was rented out at
D $82,000 per month (apart from a period of 10 months when Mrs Chan’s D
husband used the unit for storage in connection with his business and paid
E E
$30,000 a month). In 2014 the property was let again for $98,000.
F Mrs Chan had connected up to the public water supply in Nelson Street in F
August 2011. For all practical purposes therefore the lettings were with
G G
water but without drainage.
H H
(a) What rent might have been achieved when the property was
J J
empty had it had water and drainage?
K (b) For how much of the vacant period should the defendant be K
liable in damages?
L L
(c) Since August 2011 how much more rent would the plaintiff
M have received over and above the actual income, had the unit M
R very different. Mr Siu for the defendant used location as the key factor R
whereas Mr Cheung chose comparables on the basis of the dates of the
S S
rental transactions. In other words with Mr Cheung’s comparables the
T leases commenced at the material time but their locations were further T
U U
V V
A A
afield and there was a greater variation in the nature of the businesses
B conducted in the different shops. Each expert then made numerous B
adjustments for a variety of factors including the size of the property, the
C C
age of the building, whether it has street frontage, the location and the
D nature of the business. The percentage adjustments varied from 0% to as D
K K
73. Criticism of Mr Cheung’s method was made, inter alia,
L because of the big differences in rents in some of the properties. One was L
being let at $200,000 a month and was 42 square metres in size, another
M M
was considerably larger but the rental was only $50,000 per month. Even
N after the adjustments were made it was submitted that they provided only N
rent (with water and drainage) for 2009 – 2012 at $95,000 per month and
Q Q
post 2012 at $123,000 per month. Mr Siu’s figures were $65,000 and
R $92,000 respectively. R
S S
T T
U U
V V
A A
75. In cross examination Mr Cheung confirmed the accuracy of a
B different exercise designed to gauge the accuracy of the comparables B
results, as follows.
C C
with water, was the rents that were actually agreed (assuming they were
E E
arm’s length’s transactions) namely $82,000 in 2012 and $98,000 in 2014.
F Using these figures as benchmarks it is then possible to calculate what a F
fair rent would have been at either an earlier date or a later date by
G G
multiplying the benchmark figure by the appropriate multiplier in the
H Government’s “Private Retail — Rental and Price Indices”. The Indices H
for December 2009, August 2012 and May 2014 were 117.3, 154.4 and
I I
173.0 respectively. Thus by way of example if the rent in 2012 was
J $82,000 the rent in 2009 would have been 82,000 ÷ 154.4 × 117.3 = J
$72,000. Going forwards that produces figures of $94,000 for 2012 and
M M
$106,000 for 2014. All these figures would have to be adjusted
N downwards by a small amount to reflect rent free periods at the N
commencement of a lease.
O O
U U
V V
A A
value of the subject premises in 2015 was $876,000 or $73,000 per month
B in rent; a vastly different figure from Mr Cheung’s $123,000 in 2012. B
C C
79. With all these figures, methods, adjustments and calculations
D in mind, it seems to me that the loss of rent due to the property being D
out, albeit without water and drainage, for some of this period but she did
G G
not do so because she chose to wait, optimistically, for the water and
H drainage supply rather than mitigating her loss whilst the issue was being H
received) = $540,000.
K K
ground floor units in the Tak Bo Building who would require water and
M M
drainage, such as a hairdresser or foot massage parlour, would pay more
N than the 30+ tenants in the arcade doing printing business or selling sports N
reduced pool and the maximum pool is likely, on the available evidence,
Q Q
also to be small. Mr Cheung’s figure of $123,000 in 2012 for the unit with
R water and drainage seems unrealistic. The actual rent achieved, with R
S
water, was $82,000. Mr Cheung’s figure represents a 50% increase S
because of additional drainage. Two years later, in 2014, Mrs Chan was
T T
receiving $98,000 a month. This is clearly in the same general range as
U U
V V
A A
Mr Siu calculated to be appropriate. It should nonetheless be recognized
B that the unit with drainage is worth more than without. Thus, a small, B
possibly even token, increase would have been added to reflect this.
C C
D Counterclaim D
counterclaim was pared down from a small sum to a tiny sum. All that is
F F
now claimed is $1,600 for the cost of dismantling the illegal pipework
G installed in 2010. Mr Chan’s evidence (for the IO) concerning this invoice G
I Conclusion I
J
82. There will be judgment for the defendant on the claim with a J
costs order nisi in the defendant’s favour and a certificate for two counsel.
K K
L L
M M
N N
(M P Burrell)
Deputy High Court Judge
O O
S S
T T
U U
V V