BAR CHART

NAME OF WORK : - Construction of Sendurjana Tank


NAME OF AGENCY : - MISA CONSTRUCTION PRIVATE LIMITED
DATE : - 08/04/2019
BALANCE 2019
REMARK
S. No. DESCRIPTION QUANTITY APRIL MAY JUNE
EARTHWORK IN 77190 CUM 20000 CUM 40000 CUM 17190 CUM
1
EMBANKMENT PROG.
184.19 34.19 150
2 CONCRETE WORK
PROG.
1900 800 800 300
3 PITCHING WORK
PROG.
11637.9 5000 6637.87
4 EXCAVATION IN SOIL
PROG.
EXCAVATION IN SOFT 25924.1 10000 10000 5924.14
5
ROCK PROG.
70 30 40
6 900 MM HUME PIPE
PROG.
15 CM SPALL UNDER 1300 200 600 500
7
PITCHING PROG.