PRADHAN MANTRI GRAM SADAK YOJANA

OPERATIONS MANUAL

National Rural Roads Development Agency


Ministry of Rural Development
Government of India

FEBRUARY, 2005
FOREWORD

Over the last 4 years, the Pradhan Mantri Gram Sadak Yojana (PMGSY) has made a place for itself
as a programme characterised by detailed planning, methodical execution, careful management
and high quality consciousness. This has been possible due to the close interaction between the
Ministry of Rural Development and the State executing agencies as well as involvement of the
Principal and State Technical Agencies and senior Engineers of the State and Central Governments
including retired Engineers working as National Quality Monitors. Clear and detailed documentation
on the construction standards in the form of the Book of Specifications, Rural Roads Manual and
Standard Data Book published by the Indian Roads Congress (IRC) supported by the Quality Control
Handbook for quality management have contributed significantly in the process.
At the operational level, the establishment of PMGSY on a firm foundation has come through a
series of operational guidelines issued by the Ministry of Rural Development and the National Rural
Roads Development Agency (NRRDA) from time to time, mainly the result of Regional Review
meetings with the State agencies, on such matters as District Rural Roads Planning, Quality
Monitoring, Online Monitoring & Management System, Fund Flow & Accounting procedures, etc.
Indeed the overall volume of such guidelines has become extensive enough for a need to put them
all down systematically in the form of one comprehensive ‘Operations Manual’. Hence this publication.
The Operations Manual is intended for day-to-day use as a comprehensive supplement to the PMGSY
Guidelines on procedural aspects. On technical aspects the IRC publications will of course need to
be consulted. In the process of drafting the Operations Manual, efforts, have been made to address
the need particularly of the Programme Implementation Units (PIUs) and much of the Manual is
consciously targeted at them, since ultimately the success of the programme depends on the degree
to which the PIU understands and complies with the letter and spirit of the PMGSY Guidelines.
Rural Roads being a State subject, the Operations Manual has rightly left sufficient flexibility and
scope for the State Government and the SRRDA to be able to issue detailed guidelines in keeping
with the procedures and requirements of the individual States. There is also a realisation that micro-
managing the programme centrally might neither be desirable nor feasible. At the same time, there
is an expectation that guidelines of the nature envisaged in the Operations Manual will facilitate to
the systematic implementation of PMGSY, and in fact State Governments may find it advantageous
to adopt many of the principles and practices mentioned in the Manual in rural roads Programmes
other than the PMGSY.
The draft of the Manual was extensively circulated and discussed and then finalised in a workshop
with representatives of State Governments and other stake-holders on 29th December 2004.
Nevertheless there is always scope for improvement, and comments and feedback on the Manual
are accordingly most welcome.

(S Vijay Kumar)
Director-General
National Rural Roads Development Agency

February, 2005

iii
ACKNOWLEDGEMENTS

Preparation of base document leading to the present shape was undertaken by Dr. L.R.Kadiyali of

M/s. Kadiyali & Associates. Based on interaction with States and other stakeholders, many of the

guidelines issued earlier underwent a few modifications in the meantime. These were woven into

the base document and amplified by the Divisional Heads of NRRDA under the active guidance of

the Director General, NRRDA. Comments on the draft document received from various stakeholders

such as Executing Agencies, PTAs&STAs, NQMs, CRRI, IRC, World Bank, ADB etc. enabled a

very useful critical review during the workshop organized for this purpose on 29th December 2004.

This enabled the finalization of the document in a short time. Very useful inputs were provided by

the Technical and support staff of NRRDA in bringing the Operations Manual into its present shape.

Guidance and inputs of all those who contributed is gratefully acknowledged.

v
ABBREVIATIONS & ACRONYMS

ACR Annual Confidential Report DRDA District Rural Development Agency


AADT Average Annual Daily Traffic DRRP District Rural Road Plan
ADB Asian Development Bank DRRSO District Rural Road Safety Officer
ADT Average Daily Traffic DS Deputy Secretary
ADV Animal Drawn Vehicle EC End of Circular Curve
AEE Assistant Executive Engineer ECOP Environmental Code of Practice
AIV Aggregate Impact Value EE Executive Engineer
AMC Annual Maintenance Contract ESMC Equilibrium Subgrade Moisture Content
AR Audit Report ESMF Environment and Social Management
ATR Action Taken Report Framework

AWR All Weather Road FC Forest Clearance

BBM Bitumen Bound Macadam FDR Fixed Deposit Receipt

BC Beginning of Circular Curve FM Financial Management

BM Bituminous Macadam FMR Financial Monitoring Report

BOQ Bill of Quantity FMS Financial Management System

BS Beginning of Transition FWR Fair Weather Road

BT Black Topped GAD General Arrangement Drawings

CAG Comptroller and Auditor General of India GCC General Conditions of Contract

CAO Chief Accounts Officer GIS Geographical Information System

CBF Cash Book Folio GoI Government of India

CD Cross Drainage GPS Geographical Positioning System

CEO Chief Executive Officer GWT Ground Water Table

C/J Car/Jeep HCV Heavy Commercial Vehicle

CN Core Network HQ Headquarters

CNCPL Comprehensive New Connectivity Priority List IPAI Institute of Public Auditors of India

CPWA Central Public Works Accounts IRC Indian Roads Congress

CS Cross Section ISDN Integrated Services Digital Network

CUPL Comprehensive Upgradation Priority List IT Information Technology

CVPD Commercial Vehicle Per Day ITB Instruction to Bidders

CW Carriage Way ITO Income Tax Officer

DPC District Planning Committee LAN Local Area Network

DPIU District Programme Implementation Unit LCV Light Commercial Vehicle

DPR Detailed Project Report LFBM Lime-Flyash Bound Macadam


LL Liquid Limit

vii
LS Longitudinal Section RCC Reinforced Cement Concrete
LWE Left Wing Extremists RCCP Roller Compacted Cement Concrete
MCW Maternity and Child Welfare Pavement

MDR Major District Roads RDD Rural Development Department

M&E Monitoring & Evaluation REO Rural Engineering Organization

MF Maintenance Funding RES Rural Engineering Services

MHA Ministry of Home Affairs RHA Rice Husk Ash

MIS Management Information System RLW Road Land Width

MoRD Ministry of Rural Development RMPL Routine Maintenance Priority List

MOU Memorandum Of Understanding RMS Road Management System

MRL Main Rural Links ROB Railway Over Bridge

MSS Mixed Seal Surface RRM Rural Roads Manual

NBF Non (World/Asian Development) Bank RW Road Way


Financed SBD Standard Bidding Document
NCB National Competitive Bidding SDB Standard Data Book
NCR Non-Conformance Report SE Superintending Engineer
NH National Highway SH State Highway
NIC National Informatics Centre SHO Station House Officer (Sub-divisional police
NIT Notice Inviting Tender officer)

NQM National Quality Monitor SLSC State Level Standing Committee

NRRDA National Rural Roads Development Agency SOR Schedule of Rates

OM Operations Manual SQC State Quality Coordinator

OMMS On-line Monitoring & Management System SLQC State Level Quality Control

ODR Other District Road SQM State Quality Monitor

PCI Pavement Condition Index SRRDA State Rural Roads Development Agency

PHC Primary Health Centre SSR State Schedule of Rates

PIC Project Implementation Consultant STA State Technical Agency

PIU Programme Implementation Unit TE Technical Examiner

PI Plasticity Index TQM Total Quality Management

PL Plastic Limit TR Through Road

PMC Project Management Consultant TW Motorised Two Wheeler

PMGSY Pradhan Mantri Gram Sadak Yojana UC Utilisation Certificates

POT Point of Transit UCM Unsatisfactory Contract Management

PRI Panchayat Raj Institution UMS Unsatisfactory Management Standard

PTA Principal Technical Agency UQW Unsatisfactory Quality of Work

PW Part Work VR Village Road

PWD Public Works Department WBM Water Bound Macadam

QI Qualification Information WP Work in Progress

RBH Rural Business Hubs XEN Executive Engineer

viii
Chapter No. Description Page No..

Foreword iii

Acknowledgements v

Abbreviations vii

1. Introduction 1

2. State Level Institutional Structures 6

3. Planning 11

4. Annual Proposals and their Clearances 36

5. Design 55

6. Project Preparation 86

7. Scrutiny of Detailed Project Reports 96

8. Procurement 115

9. Project Implementation and Contract Management 135

10. Principal and State Technical Agencies 145

11. Quality Management 148

12. Monitoring 167

13. Finance & Accounting System 189

14. Maintenance 220

15. Road Safety 239

16. Implementation Responsibility 242


ANNEXURES

Annexure Description Page No.


No.
3.1 Code for Habitation ................................................................................................................... 24
3.2 Habitation Data : Format-I and Instructions for Filling Format-I ................................................ 25
3.3 Inventory of Rural Roads : Format-II and Instructions for filling Format-II ................................ 27
3.4 Record of Primary & Secondary Roads (Format for District-Level Master Plan) ...................... 29
3.5 Proformae for Core Network ..................................................................................................... 30
3.6 Rural Road Condition Survey : Inspection Forms I and II ......................................................... 34
4.1 Forms for Proposals Received from MPs ................................................................................. 43
4.2 Memorandum of Understanding ................................................................................................ 45
4.3 Affidavit for Land Donation ........................................................................................................ 46
4.4 Brief for Empowered Committee ............................................................................................... 47
4.5 Check list for date for EC .......................................................................................................... 53
5.1 Supplementary Guidance on Soil Survey and Materials ........................................................... 63
5.2 Nomograph for computing soaked CBR values from Sieve Analysis Data ............................... 74
5.3(a) Proforma for Traffic Survey........................................................................................................ 75
5.3(b) Summary of 3-day Counts. ........................................................................................................ 76
5.4 Guidelines on Use of Local Materials ........................................................................................ 77
5.5 Guidelines for Drainage of Rural Roads ................................................................................... 80
5.6 Nomograph for Equilibrium Subgrade Moisture Content ......................................................... 85
7.1 Forms F-1 to F-9 Accompanying DPRs ................................................................................... 101
7.2 Districtwise Summary of Proposals – Proforma A ................................................................... 108
Package Summary – Proforma B ............................................................................................ 109
Check list for PIU & STAs – Proforma C ................................................................................. 110
7.3 Report of the STA on the Project Proposals ............................................................................ 114
8.1 Instructions and check list for preparing the Bidding Documents ........................................... 123
8.2 Input Format-I for Publishing Tender Notice ............................................................................ 130
8.3 Package wise Input Format-II .................................................................................................. 131
8.4 ITB and Contract Data Input Format III ................................................................................... 132
8.5 List of certificates required in submission of bid ...................................................................... 134
9.1 Provisions regarding Disputes in some of the World Bank Funded PMGSY Projects ............ 144

x
Annexures

11.1 Forms for monthly return of the tests conducted ..................................................................... 158
11.2 Monthly return of the tests not meeting the standards ............................................................ 159
11.3 Format for abstract of report of State Quality Monitors ........................................................... 160
11.4 Guidelines to State Quality Monitors ....................................................................................... 161
11.5 Form for dealing with complaints ............................................................................................. 162
11.6 Monthly Statements showing the visits of NQMs .................................................................... 163
11.7 Format for Grading of Work ..................................................................................................... 164
11.8 Action taken statement on the pending report of NQMs ......................................................... 166
12.1 Progress of PMGSY works – Format PW ............................................................................... 175
12.2 Analysis of per kilometre cost of PMGSY works-Format CP .................................................. 175
12.3 Projected completion plan of PMGSY works- Format WP ...................................................... 176
12.4 List of Completed PMGSY works- Format CW ....................................................................... 176
12.5 Monthly return for delay in Award of Contract for PMGSY works ........................................... 177
12.6 Packages not awarded for more than 90 days ........................................................................ 178
12.7 Monthly return of delay in execution of PMGSY packages ..................................................... 179
12.8 Quarterly return for Forest clearances .................................................................................... 180
12.9 Quarterly abstract of award of contracts under PMGSY ......................................................... 178
12.10 Physical and Financial progress under PMGSY ..................................................................... 181
12.11 Quarterly abstract for delay in execution of PMGSY works .................................................... 182
12.12 Quarterly abstract for delay beyond 90 days in completion of packages ................................ 182
12.13 Statement showing details of disposal of final payment cases of road works ......................... 183
12.14 Institutional capacity issues under PMGSY ............................................................................. 184
12.15 Monthly report on Unspent Balances of PMGSY funds .......................................................... 188
14.1 Periodicity of Routine Maintenance Activities .......................................................................... 226
14.2 Special problems of road maintenance in heavy rainfall/snowfall areas ................................. 227
14.3 Maintenance of shoulders, drainage structures and causeways ............................................ 228
14.4 Norms for Routine Maintenance Activities during the Contract period of 5 years ................... 231
14.5 Guidelines for Inspection of Rural Roads as part of maintenance activity .............................. 233
14.6 Routine Inspection Card (Recording format) ........................................................................... 235
14.7 Methodology for Determining the Pavement Condition Index (PCI) ....................................... 236
14.8 Proforma of Output of PCI Data for Each Road on OMMS ..................................................... 238

xi
National Rural Roads Development Agency

CHAPTER 1
INTRODUCTION

1.1 VILLAGE CONNECTIVITY IN INDIA


India has essentially a rural-oriented economy with 74 per cent of its population living in its villages. At the
commencement of PMGSY in 2000, it was estimated that about 330,000 out of its 825,000 villages and habitations
were without any all-weather road access. A majority of the poorly connected rural communities lie in ten States
(Assam, Bihar, Chattisgarh, Himachal Pradesh, Jharkhand, Madhya Pradesh, Orissa, Rajasthan, Uttar Pradesh
and West Bengal).

1.2 CURRENT PLANS FOR RURAL CONNECTIVITY: PMGSY


1.2.1 PMGSY: Programme Goals
Rural Road connectivity is a key component of rural development by promoting access to economic and social
services and thereby generating increased agricultural incomes and productive employment opportunities. It is
also a key ingredient in ensuring poverty reduction.
It was against this background of poor connectivity that the Prime Minister announced in 2000, a massive rural
roads programme. The Prime Minister’s Rural Road Programme (Pradhan Mantri Gram Sadak Yojana, PMGSY)
set a target of:
 Achieving all-weather road access to every village/habitation with a population greater than 1000 by 2003
 Providing all-weather road access to all villages/habitations of population greater than 500 people [250 in
case of hill States (North-Eastern states, Sikkim, Himachal Pradesh, Jammu & Kashmir and Uttaranchal),
the desert areas and tribal areas] by the end of the Tenth Five Year Plan, i.e., 2007
1.2.2 Noteworthy Features of the PMGSY
The Ministry of Rural Development (MoRD) has been entrusted with the task of organising the programme.
Some of the noteworthy features of the programme are:
 Full Central funding, with 50% of the cess on High Speed Diesel being earmarked for this programme.
 Preparation of Master Plans and Core Network for Rural Roads for all the Districts and Blocks, identifying
the unconnected habitations and proposing the most cost-effective routes for the purpose.
 Design and Specifications as contained in the Rural Roads Manual (RRM, IRC SP:20), published by the
Indian Roads Congress (IRC).
 Appointment of a dedicated State Level Agency in all States with overall responsibility for rural road planning,
programme execution and management.
 Appointment of programme implementing agencies, by all States, typically Public Works Departments
(PWDs) or Rural Engineering Organisations (REOs).
 Independent State Technical Agencies (STA) commissioned by MoRD to vet designs and estimates.
 Use of competitive tendering by the implementing agencies of all works on the basis of a Standard Bidding
Document (SBD).
 Execution of the works within a period of 9-12 months.
 A Defects Liability and maintenance period of 5 years specified in the Contracts for the roads constructed
under the programme, with funds for maintenance being provided by the States.

Operations Manual for Rural Roads


1
National Rural Roads Development Agency

 A central on-line web-based financial and project monitoring system.


 A 3-tier Quality Management System.
 Operational management at Central level by the National Rural Roads Development Agency (NRRDA).

1.3 RESOURCES FOR IMPLEMENTING PMGSY


It is estimated that the total investment required to meet the new connectivity targets is of the order of
Rs 79,000 crores with another Rs. 53,000 crore required to upgrade existing rural roads to prescribed standards.
In 1999, a one-rupee cess on every litre of diesel and petrol sold was imposed by the Government of India
(GoI), and in 2000, a Central Road Fund Act was promulgated to direct the resources obtained through this
cess to the improvement of National and State Highways as well as Rural Roads. By law, 50% of the diesel
cess is required to be directed towards rural road development. This amounts to about Rs 2,500 crores (US $
500 million) per year. An additional cess of 50 paise per litre of diesel sold, provided in the Budget for 2003-04,
is likely to yield another Rs. 1,250 crores/year. Additional fund requirements are likely to be met through both
internal and external borrowings.

1.4 NEED FOR THE OPERATIONS MANUAL


The Indian Roads Congress (IRC) have brought out a Rural Roads Manual (RRM) (IRC: SP: 20-2002), which
provides technical guidance on various aspects of rural road development. The requirements of PMGSY were
specially kept in view when drafting this document. The NRRDA and MoRD have also issued several guidelines
and instructions to the implementing agencies. It was, therefore, considered appropriate to bring out an Operations
Manual (OM) in respect of PMGSY, to provide a systematic, comprehensive easily accessible set of operational
instructions on the programme. Provisions of the Manual may be used by States for other rural roads also, with
suitable adaptations. It is hoped that the OM will bring about clarity on various aspects of the programme,
ensuring its timely and successful implementation. The contents of the Manual will be reviewed and revised
according to the experiences gained during implementation.
The OM fully covers the PMGSY programme. It will be mandatory on the part of the State implementing agencies
to follow the OM in every respect. Under the PMGSY, District Programme Implementation Units (DPIUs) have
been set up. The OM is specifically targeted to these DPIUs. Since the OM embodies various instructions
issued earlier, it supersedes such instructions. Where the OM refers to certain clauses of the IRC Rural Roads
Manual, such clauses shall prevail. The Accounts Code and Works Manual of the States shall continue to be
used, and if provisions in the OM are at variance with these, the attention of the NRRDA must be drawn and
specific directions obtained.

1.5 KEY DEFINITIONS


 Rural Roads
Rural Roads cover the categories earlier known as “Other District Roads” (ODRs) and “Village Roads” (VRs).
Other District Roads are roads serving the rural areas of production and providing them with outlet to market
centres, Block, taluka/ tehsil headquarters or main roads. Village Roads are roads connecting villages and
group of villages with each other or to the market centres and with the nearest road of higher category.
 All-Weather Roads
An all-weather road is one which is negotiable during all weathers, with some permitted interruptions. Essentially
this means that at cross-drainage structures, the duration of overflow or interruption at one stretch shall not
exceed 12 hours for ODRs and 24 hours for VRs in hilly terrain, and 3 days in the case of roads in plain terrain.
The total period of interruption during the year should not exceed 10 days for ODRs and 15 days for VRs.
The pavement should be negotiable during all-weathers, but this does not necessarily imply that it should be
paved or sealed or blacktopped.

2 Operations Manual for Rural Roads


Introduction

 Fair-Weather Roads
Fair-weather Roads are those not satisfying the minimum requirements specified for all-weather roads. These
roads could be taken to be in a stage of development to be upgraded to all-weather type.
 Unpaved and Paved Roads
Unpaved or Unsealed roads vary from ‘clay’ roads, which can only serve dry-season light traffic to heavy-duty
crushed rock industrial roads which can serve heavy traffic. Typically, such roads are used for providing rural
access, carrying an average of 20 to 100 vehicles per day. The base course of such roads is made from local
materials e.g., natural gravels and generally using well-tried traditional methods of construction. In sustained
wet weather, the unsealed roads may develop deficiencies such as rutting and potholing. On the other hand, in
dry seasons, such unsealed roads can become dusty and develop corrugations. Paved or Sealed Roads are
those which are rendered waterproof and dust-proof by a surfacing or base-cum-surfacing of bituminous materials
or cement concrete.
 Village/ Habitation
The unit for this Programme is a habitation and not a revenue village or Panchayat. A habitation is a cluster of
dwellings, in an area, the location of which does not change over time. Desam, Dhanis, Tolas, Majras, Hamlets
etc. are commonly used terminology to describe the habitations. The population of all habitations within a
radius of 500m (1.5 km of path distance in case of hills) may be clubbed together for the purpose of determining
the population size. This cluster approach would enable provision of connectivity to a large number of
habitations, particularly in the hill/ mountainous areas.
The population size of the habitation shall be based on the population as recorded in Census 2001. The District
Rural Road Plans and Core Network shall be drawn up/ revised on this basis.
 Accessibility Criterion
The criterion of accessibility when any village/ habitation is deemed to have been connected by a rural road is
generally the permissible maximum distance of the habitation from an existing all-weather road facility or from
an already connected habitation. This permissible maximum distance has been kept at 500m for the plain
areas and 1.5km of path distance in case of hills for the PMGSY. The unconnected habitations are to be
connected to nearby habitations already connected by an all-weather road or to another existing all-weather
road so that services (educational, health, marketing facilities etc.) which are not available in the unconnected
habitation become available to the residents.
 District Rural Roads Plan (DRRP)
The DRRP is long-term plan of road network in a district, showing the existing road network, the habitations of
various population size and roads proposed for connecting the yet unconnected habitations to already connected
habitations/ all-weather roads in an economic and efficient way in terms of cost and utility. It is also known as
the Master Plan for Rural Roads for the district.
 Core Network
The rural road network required for providing the ‘basic access’ to all villages/ habitations is termed as the Core
Network. Basic access is defined as one all-weather road access from each village/ habitation to the nearby
Market Centre or Rural Business Hub (RBH) and essential social and economic services.
A Core Network comprises of Through Routes and Link Routes. Through routes are the ones which collect
traffic from several link roads or a long chain of habitations and lead it to a market centre or a higher category
road, i.e. the District Roads or the State or National Highways. Link Routes are the roads connecting a single
habitation or a group of habitations to Through Roads or District Roads leading to Market Centres. Link Routes
generally have dead ends terminating on habitations, while Through Routes arise from the confluence of two or
more Link Routes and emerge on to a major road or to a Market Centre.

Operations Manual for Rural Roads


3
National Rural Roads Development Agency

The Core Network may not represent the most convenient or economic route for all purposes. However, since
studies show 85-90% of rural trips are to market centres, the Core Network is likely to be a cost-effective
conceptual frame work for investment and management purposes, particularly in the context of scarce resources.
 Market Centres/Rural Business Hubs (RBH)
Market Centres or Rural Business Hubs (RBH) are centres of activities for marketing of agricultural produce
and inputs, servicing of agricultural implements, health, higher education, postal, banking services etc. They
are generally habitations with a large population, located on higher category of roads or at the confluence of
roads emanating from a number of habitations. They can be identified from data available from published
census records, information available from Marketing Boards and local enquiry. The villagers should be able to
go to the nearby Market Centre and come back the same day. The maximum distance between a village and a
Market Centre would normally not be more than 15-20 km. In some cases, a Market Centre may not be fully
developed at present, but a big village may have potential for developing into a Market Centre or Rural Business
Hub (RBH). Such villages also need to be identified as potential Market Centres or Rural Business Hubs
(RBH).

1.6 PROGRAMME OBJECTIVES


1.6.1 New Connectivity
The primary objective of the PMGSY is to provide connectivity, by way of an all-weather road (defined in para
1.5 earlier) to the eligible unconnected habitations in rural areas generally so as to enable access to the
nearest market centre, in such a way that:
 habitations with a population of 1000 persons and above are covered in the Ist Stage.
 all habitations with a population of 500 persons and above are covered in the next stage. In respect of the
hill States (North-East, Sikkim, Himachal Pradesh, Jammu & Kashmir, Uttaranchal) and the desert areas
(as identified in the Desert Development Programme) as well as Tribal (Schedule V) areas, the objective
would be to connect habitations with a population of 250 persons and above.
The spirit and objective of PMGSY is to provide good all-weather road connectivity to the unconnected habitations.
It must be ensured that the provision of New Connectivity (i.e. connecting unconnected habitations) should be
given precedence over upgradation works in keeping with the objectives of the Programme.
1.6.2 Upgradation
Upgradation of existing rural roads is not central to the programme. However, the programme will permit
upgradation of existing rural roads to the prescribed standards in those Districts where all habitations of the
designated population size (para 1.6.1 above) have been provided all-weather connectivity. The provision for
upgradation cannot exceed 20% of the State’s allocation as long as unconnected habitations still exist in the
State. In other words, District-wise allocation is to be done on considerations of equity, but in such a way that
new connectivity still gets priority by keeping a ceiling of 20 percent at the State level for upgradation works.
Upgradation shall also be permitted in cases where the new link connects to a fair-weather road, which leads
to the Market Centre. Only those rural roads are eligible for upgradation, which form part of the Core Network.
Upgradation shall cover the following types of works:
 Improving surface drainage and constructing all missing cross-drainage works to make the road all-weather.
 Improving the road pavement to standards required for the traffic, subject to a condition survey (see
Chapter 3).
 Improving road geometrics to prescribed standards and improving road safety.
1.6.3 Integrated Development of Rural Road Network
Provision of all weather connectivity from habitation to the market centre is the basic feature of PMGSY. Thus,
to provide assured and sustained all weather connectivity from habitation to the market centre, construction of

4 Operations Manual for Rural Roads


Introduction

new links wherever necessary and upgrading existing eligible through route, upto the market centre, would
form the basic feature of project proposals under the PMGSY.
1.6.4 Works not Covered by PMGSY
The following works are not covered by PMGSY:
 PMGSY envisages only single connectivity to be provided. If a habitation is already connected to another
habitation (or to an existing all-weather road) by way of an all-weather road, then no further work can be
taken up under PMGSY at that habitation.
 PMGSY does not permit repairs to black-topped or cement-concrete roads, even if the surface condition
is bad.
 No urban roads can be constructed under the PMGSY.
 PMGSY does not permit any road to be constructed or upgraded that is not part of the Core Network.
 PMGSY does not fund RoB costs for Railway crossings, nor does it fund maintenance of manned/unmanned
railway crossings.

Operations Manual for Rural Roads


5
National Rural Roads Development Agency

CHAPTER-2
STATE LEVEL INSTITUTIONAL STRUCTURES

2.1 In order to ensure efficient and streamlined execution of works under PMGSY, various capacity
enhancement measures have been suggested as an adjunct to the programme. These are required to be put
in place for effective management. Generally, even though PMGSY is primarily aimed at providing new
connectivity, at the sectoral level it seeks the development and strengthening of the rural roads sector through
systematic planning and management of the entire network, and the institutional strengthening and capacity
enhancement is in furtherance of these broader sectoral objectives as well.

2.2 STATE LEVEL AGENCIES


Setting up and operationalisation of an effective state level agency with responsibility to PMGSY specifically,
and for the rural roads network generally is a key component to institutional development.
2.2.1 As per para 7 of PMGSY guidelines, each State Government would identify a suitable agency (or in case
of large States, even two suitable agencies) having a presence in all the districts and having established
competence in executing time-bound road construction work. These agencies shall be designated as Executing
Agencies. These could be the Public Works Department/Rural Engineering Services/Rural Engineering
Organisation/Rural Works Department/ Zilla Parishads/ Panchayati Raj Institutions, which have been in existence
for some time and have the necessary experience, expertise and manpower. In States where more than one
Executing Agency has been identified by the State Government, the distribution of work would be done with the
district as a unit.
2.2.2 Each State Government shall nominate a Department as the Nodal Department. The Nodal Department
shall have overall responsibility for the implementation of PMGSY in the State. All communication between the
MoRD and the State Government would be with and through the Nodal Department/State level Agency. The
Nodal Department shall normally be the State Department responsible for rural roads.
2.2.3 The Nodal Department will set up a State level autonomous Agency, to be called the State Rural Roads
Development Agency (SRRDA), with distinct legal status under the Registration of Societies Act. Preferably
this Agency should have a nodal or coordinating role for the entire Rural Road Sector in the State. This Agency
shall receive the funds from MoRD for the PMGSY programme. Where such a agency already exists, such as
Marketing Boards in Haryana and Punjab, the State can entrust the work to it, provided the necessary PMGSY
provisions are brought into force. All the proposals shall be vetted by the Agency before they are put up before
the State-level Standing Committee (SLSC) and are sent to the NRRDA for clearance by the Ministry of Rural
Development.
The General Body of the Agency may include professionals and retired senior officials / academicians with long
association with the road sector, in order to pool experiences and help develop a comprehensive approach.
The Executive Committee of the Agency may include the stakeholders at the operational (Directorate) level to
enable informed decision making and implementation.
2.2.4 The functions of the Agency in relation to PMGSY would include:
 Rural Road Planning and Sectoral Coordination.
 Management of Funds.
 Preparation and submission of annual proposals.

6 Operations Manual for Rural Roads


State Level Institutional Structures

 Works Management.
 Contract Management.
 Financial Management.
 Quality Management.
 Maintenance Management.
It is expected that the Agency would, over time, be responsible for these activities not only in respect of PMGSY,
but the entire rural roads sector.
A suggested set-up for the Agency is as under

2.2.5 The Chief Executive Officer of the Agency would need to be a Senior Officer of the Nodal/ Executing
Department preferably with a presence in the State Secretariat hierarchy.
2.2.6 The Agency shall appoint a Financial Controller, to oversee the operationalisation of the rural roads
accounting system. The Agency shall maintain centralized accounts, which will be accessed by the Programme
Implementing Units (PIU) and the Financial Controller’s primary responsibility would be the enforcement of
accounting standards and arranging the auditing thereof. The Financial Controller would need to be a professional
with adequate knowledge and experience of Works Accounting.
2.2.7 The Agency would also appoint an Empowered Officer (distinct from the Financial Controller). The
officer would be responsible for operational management of the project funds and would need to be a senior
officer (generally of the rank of Chief Engineer), familiar with Project Management of PMGSY. Since all the

Operations Manual for Rural Roads


7
National Rural Roads Development Agency

implementing units would be operating on the SRRDA account simultaneously, the Empowered officers should
have the necessary ability to ensure efficient management of the finances.
2.2.8 The Accounting system prescribed by the NRRDA, which is largely based on the well-established
Accounting system of the Works Departments, would be utilized for this Programme. The Online Management
and Monitoring System (OMMS) software supports the Accounting System and would be enabled so that PIUs,
SRRDAs and Bank branch concerned can make data entry on-line for their respective transactions. The
Empowered Officer and Financial Controller should have the capability of exploiting the features of the on-line
system. Refer to Chapter 13 for more details.
2.2.9 The Agency would identify a State IT Nodal officer in order to oversee the regularity and accuracy of the
data being furnished by the Programme Implementation Units (PIU) and will be responsible to oversee the
upkeep of the hardware and software as well as the IT training requirements of the personnel dealing with the
PMGSY. The IT Nodal officer should have a background of statistical data computation for the sector, particularly
computer based systems. A qualification in IT would be an added advantage.
2.2.10 The Agency will appoint a senior Engineer (not below the rank of Superintending Engineer) to function
as State Quality Coordinator (SQC) at the state level. His function will be to oversee the satisfactory functioning
of Quality Management mechanism within the State. This would also involve overseeing the follow up action on
the reports of the NQMs. Detailed description of the SQC’s functions is available in Chapter 11 on Quality
Management.

2.3 PROGRAMME IMPLEMENTATION UNIT (PIU)


The Programme Implementation Units (PIU) are the basic units for project planning, execution and accounting.
A PIU may consist of one or more Engineering Divisions, appropriately headed by an Executive Engineer or
Superintending Engineer. The PIU would be directly responsible for contracting implementation and Quality
Management of PMGSY works. The PIU would also be the financial and accounting centre at the field level.
Since PMGSY has high management, quality and accounting standards, PIUs should be set up and
operationalised keeping the following in view:
 PIU should be adequately dedicated to PMGSY in terms of personnel deployment. As such it is necessary
that where the PMGSY workload in a Division is upto Rs 1 Crore, 1JE should be exclusively in charge. For
Rs. 1-5 Crores, 1 AE/AEE should be exclusively in charge with supporting dedicated JEs, and where the
work load is Rs 5 Crore or more an XEN/EE should be Incharge and the Division should be exclusively
devoted to PMGSY work.
 PMGSY personnel of the PIU should be deputed for regular training in Technical, Accounting Contract
Management and Quality aspects of the programme and the SRRDA should arrange for the training in
coordination with the STAs and NRRDA.
 PMGSY personnel of the PIU should normally have a tenure of atleast 3 years. Frequent transfers particularly
of trained and experienced staff adversely affect a fine-tuned programme like PMGSY and will have a
negative impact on funding of the programme in that State.
 The supervisory structure of the PIU should be adequately dovetailed with the departmental segments
and PMGSY requirements. As such, adequate technical and financial powers need to be delegated to the
XEN/EE and SE in terms of the Departmental Works Manual and Financial Code.
 The PIU should be directly accountable to the SRRDA. Not only must the XEN/EE be declared an officer
of the SRRDA (to enable him to access the SRRDA account) but his supervisory officers, the SE and CE
should also be accountable to the SRRDA. For this purpose the CE Incharge of PMGSY should be a
senior officer of the SRRDA and both he and CEO should be empowered to make entries as reporting or
reviewing officers, for the ACRs of the XEN/EEs and SEs involved in the programme.

8 Operations Manual for Rural Roads


State Level Institutional Structures

2.4 STATE LEVEL STANDING COMMITTEE


A State Level Standing Committee (SLSC) set up preferably under the chairmanship of the Chief Secretary
will be responsible for close and effective monitoring of the programme and to oversee the timely and proper
execution of works .The SLSC needs to comprise all the main stakeholders in the programme, including:
 Secretaries of the Programme Departments (Rural Development and PWD).
 Secretaries of the Transport, Finance, Forests & Environment and IT Departments.
 State Informatics Officer (NIC) and
 State Technical Agencies (STAs).
The Secretary of the Nodal Department shall be the Member-Secretary
The Committee shall vet the Core Network, the CNCPL and CUPL (see Chapter-3) and shall clear the annual
project proposals. In addition to this, the Committee shall also review quarterly, the following:
 Progress of ongoing works.
 Quality Control (2nd tier at State level).
 Capacity enhancement and training of executing agency.
 Computerized online project and accounts management.
 Budgeting of maintenance funds.
 Land width availability for roads; and Forests and environmental clearance.
 Provision of public transport on PMGSY roads created.
 Road safety issues.
 Convergence with rural development and poverty alleviation programmes etc.
 Issues impinging on rural road sectoral policy.
Since the primary purpose of PMGSY (and indeed of rural connectivity) is to enable basic access to the rural
hinterland and thus increase the tempo of economic activity and reach of social services, the SLSC’s role is
crucial to exploiting the development potential created by the new assets.

2.5 STATE TECHNICAL AGENCIES


While States are primarily responsible for the programme, in view of the need to enhance technical inputs for
design and techno-economic innovation, State Technical Agencies have been appointed by NRRDA to assist
the States. The main functions of the Agencies are:
 Verification of the District Rural Roads Plan prepared by the district Programme Implementation Unit
(PIU).
 Post-Scrutiny of Core Network.
 Scrutiny of the Detailed Project Reports for road works prepared by the District PIU.
 Providing requisite technical support to the PIUs in design, particularly in CD works.
 Undertaking normal tests of parameters for road design and Quality Control tests for District Programme
Implementation Units and State Quality Control Mechanism.
 Training and R&D Monitoring.
 The Agencies will be selected for appointment on the basis of recommendation of the State Government.
In order to qualify.

Operations Manual for Rural Roads


9
National Rural Roads Development Agency

 Members of STA should have a Civil engineering background and qualifications including one or more
with specialization in Traffic/ Transportation/Highway Engineering.
 The Agency should have a well established laboratory with adequate testing facilities; and
 The Agency should have the infrastructure/facility necessary for organising training programmes.

2.6 MANAGEMENT AND MONITORING SYSTEM


Because PMGSY depends on clear and detailed procedures, with inbuilt time and quality parameters, monitoring
and management of the programme is not only systematic but also highly amenable to computerization.
An on-line (internet based) computerized software has been operationalised by C-DAC, an Agency of Ministry
of Information Technology, with the intention of –
 Creating a database of rural roads.
 Tracking annual proposals from preparation of projects to completion of works.
 Making available a simple and transparent accounting system.
 Ensuring maintenance management.
The basic principles of this On-line Monitoring and Management System (OMMS) are that:
 Data is entered at point of origin, i.e. at PIU level.
 The same data is available in processed form at SRRDA and NRRDA levels; with facility to drill down to
basic units i.e. ‘road’ and ‘habitation’.
 MIS outputs can be tailor-made to suit PIU, SRRDA and NRRDA needs and thus eliminate paper reporting.
The OMMS has been created as a transparent (to citizen) website based information system with access to all
stakeholders: PIUs, SRRDA, STA, SQC, NRRDA, NQM etc. to enable pooling of data emanating from a variety
of sources. The effective working of the institutional structure implementing PMGSY and the successful and
continued operationalisation of the OMMS are very closely bound in a symbiotic relationship.

10 Operations Manual for Rural Roads


Planning

CHAPTER 3
PLANNING

3.1 PREPARATION OF MASTER PLAN


3.1.1 The Need for a Master Plan
Connecting rural habitations through good quality all weather roads, which provide access to services and also
opportunities for the rural population to increase their income, is an important part of the socio-economic
development process. For sustainable development through rural roads, it is necessary that a proper Master
Plan is prepared in order that all activities relating to rural roads such as Construction, Upgradation and
Maintenance can be taken up systematically within the frame work of this Master Plan.
3.1.2 District Rural Roads Plan (DRRP)
The District Rural Roads Plan is a compendium of the existing and proposed road network system in the
District which clearly identifies the proposed roads for connecting the yet Unconnected Habitations to already
connected Habitations/ All-weather roads, in an economic and efficient way.
The District Rural Roads Plan shall be prepared at two levels – the Block and the District. Keeping in view the
convenience from the point of view of Map preparation and Data collection, the work would primarily be done at
the Block level. Block-wise Road Plans would be prepared in accordance with the directions contained in this
Manual and the priorities spelt out by the District Panchayat. After the Block-wise Master Plan has been approved
by the Intermediate level (Block) Panchayat, it would be forwarded to the District Planning Committee (DPC),
where the Block Road Plans would be integrated into the District level Master Plan, called the District Rural
Roads Plan. This would be placed before the District Panchayat (or the District Rural Development Agency -
DRDA where the District Panchayats do not exist) for consideration and approval. Then Plan would be forwarded
by the PIU to the Nodal Department/ SRRDA for the approval of the State level Standing Committee. After
approval, it would become the final District Rural Roads Plan, and would form the basis for selection of road
works under PMGSY, through the Core Network (see para 3.2.).
Errors and deficiencies may exist in the DRRP and Core Network, due to factual inaccuracies such as population
data. These may be detected at a later stage by the PIU, or the affected people may represent against the error.
All detected errors and deficiencies or representations regarding them shall be carefully examined by the PIU
and action shall be taken to amend or correct the DRRP wherever required. The approval of the State Level
Standing Committee shall be obtained through the SRRDA for all changes Concurrence os the NRRDA shall be
obtained and thereafter changes should be made in the OMMS.
3.1.3 Programme Implementation Unit (PIU)
As per PMGSY Guidelines and as detailed in Chapter 2, every State is to identify an Executing Agency for the
execution of the Programme. The Executing Agency is expected to set up the Programme Implementation Unit
(PIU) in each District. In most States, the Public Works Department (PWD)/ Rural Engineering Service (RES)
has been identified as the Executing Agency by the State Government. The PIU at the District Level is usually
headed by a Superintending Engineer/ Executive Engineer of the Division of the PWD/ RES. The Preparation
of the Master Plan for each Block is the responsibility of the PIU, who must ensure that it has the approval of the
Panchayati Raj Institution. Care must also be taken to see that the proposals of the MPs and MLAs, who have
an intimate knowledge of their areas, are fully taken into consideration while preparing/ finalising the Plans.
3.1.4 The Ten Steps in Preparation of DRRP
The Ten Major Steps in the preparation and finalisation of the District Rural Roads Plans are as under:

Operations Manual for Rural Roads


11
National Rural Roads Development Agency

 Constitution of the Team.


 Preparation of Data base.
 Map preparation.
 Preparation of a list of Unconnected Habitations and the selection of the optimal road links.
 Consideration and approval by the Intermediate Level Panchayat.
 Submission of the Block Level Rural Roads Plan to the District Planning Committee.
 Scrutiny by the District Planning Committee.
 Consideration and approval by the District Panchayat.
 Forwarding of the District Rural Roads Plan to the State Level Standing Committee.
 Vetting of the District Rural Roads Plan by the State Level Standing Committee.
3.1.5 Step-I: Constitution of the Team
The first step in the preparation of the Rural Roads Plan is the identification of the team who will perform the
work at the Block level. The Team, for this purpose, should ideally include the Sub Divisional Magistrate (SDM),
the Sub-divisional Police Officer or S.H.O, a Revenue Officer of suitable rank, the Block Development Officer
(BDO), local officers of the Transport and Agricultural Marketing Departments and Secretary of the Intermediate
level Panchayat. The Assistant Engineer of the PIU would be the member-Secretary. In areas with special
characteristics, local officials of the Department concerned should be included, if these characteristics impinge
on rural transportation. The senior most officer (the Sub-divisional Magistrate if possible) should be designated
to lead the Team. The Chief Executive officer (Secretary) of the District Planning Committee/ Chief Executive
Officer, Zilla Panchayat/ District Collector would select the team for this purpose.
The Team should arrange to collect data on all items required for the preparation of the Block-wise Road Plans.
These are as follows:
 An authentic map of the Block on 1: 50,000 scale based on Survey of India Topo-sheets.
 2001 Census Data.
 Existing road maps and road inventory details.
 Block/ District level Statistical Handbook.
3.1.6 Step-II: Preparation of Database
The Team should thereafter undertake the task of tabulation of Data, derived from secondary sources, relating
to Habitation and Rural Road inventory.
 Habitation Level Data
Although Habitations with population of more than 500 persons only [more than 250 in hill states (North-Eastern
States, Sikkim, Himachal Pradesh, Jammu & Kashmir and Uttaranchal), desert areas and tribal areas] are to be
taken up under the PMGSY, for the purpose of preparation of the District Rural Roads Plan, all Habitations
having a population of 100 or more persons and which are more than 500 metres (half-a-kilometre) away from
each other, should be listed and separately identified on the map. This will enable the plan to have the depth
necessary for long term and broad based use.
Each habitation has to be given a specific code number. This code shall contain a combined identification of
state, District, Block and habitation code to make a unique alphanumeric code (see annexure-3.1).
The name and code number for State, District and Block along with the habitations are to be tabulated in
Format-I (Annexure-3.2). This Format gives the reference of the block and demographic and infrastructure
data of habitations under that block. The explanation of abbreviations and instructions for filling the Format-I is

12 Operations Manual for Rural Roads


Planning

also given in Annexure-3.2 as “Instructions for filling Format-I”. The last two columns of Format-I (annexure-
3.2) shall be filled up after completing Format-II (Annexure-3.3).
 Road Inventory
A comprehensive inventory of all Rural Roads including Other Districts Roads (ODR) and Village Roads (VR)
and any other existing earthen roads having a Land Width of 5m or more is to be prepared at block level. The
inventory details are to be filled up in format-II (Annexure-3.3). The annexure also provides the instructions for
filling the Format-II as “Instructions for filling Format-II”.
 Primary and Secondary Road Data
The National Highways (NH), State Highways (SH) and Major District Roads (MDR), which form the primary
and secondary road network in a region, will also be required for analysing connectivity of habitations. Therefore
a record of all such roads passing through the Block shall be prepared as indicated in Format-III
(Annexure-3.4).
It may happen that the data available through the secondary sources may not be accurate or up-to-date. These
would, therefore, have to be physically verified through field visits. The most important activity in preparation of
Database is the actual field visit. This must be undertaken with great care as the accuracy of maps and the data
collected and tabulated in FORMATS I, II & III would depend on the rigour and discipline exercised during the
field visit.
 Condition Survey of Existing Rural Road Network
The inventory of the road network prepared as above gives an overall assessment of each road link. It does not
give a detailed account of each km of the road, in terms of its present condition. Such data is needed for
selecting projects for upgradation or maintenance. A reference may be made to Chapter 14 for using the data
for maintenance management. To prioritise upgradation and maintenance operations, a condition survey of all
the Rural Roads in the Core Network shall be carried out periodically, the first survey results being incorporated
into the District Rural Road Plan itself. The first condition survey and the field verification of the road inventory
can be usefully done at the same time.
 Pavement Condition Index
A Simple Pavement Condition Index (PCI) based on Visual Inspection or Driving Speed or riding comfort,
already in use in many States, would be used and prioritisation methodologies applied for determining Upgradation
as well as maintenance priorities. Details of the procedure for determination of the Pavement Condition Index
(PCI) are given in Para 14.9 and Annexure 14.7.
The PCI data is an integral part of the Online Management & Monitoring System (OMMS) and the data will be
included in the ‘Road Master’ for each kilometre. The PCI data after collection in the manner described in
Annexure-14.7 will be entered into the OMMS database by the PIU and a District-wise output generated, copy
of which will be furnished to the State Rural Roads Development Agency. Another copy will be supplied to the
STAs for record. The Proforma is given in Annexure 14.8.
3.1.7 Step-III: Map Preparation
After the database has been prepared from secondary sources and verified through exhaustive field surveys,
the Team would commence the task of Map preparation. The exercise should be closely supervised by the
Head of the Programme Implementation Unit. Mapping should be done by trained draftsmen, who are normally
available with all Engineering Organisations/ Revenue Departments.
The map should also show the latitudes and longitudes. This will facilitate the sequential arrangement of the
Block Maps and in the preparation of the District map. The basic Rural road map shall be prepared at the Block
level. The scale to be adopted is 1: 50,000. For convenience, Survey of India topo-sheets available on this
scale can be used as the base. On this map, the data collected on the Habitations and the Road Inventory shall
be incorporated. The map shall be drawn indicating the following details: -

Operations Manual for Rural Roads


13
National Rural Roads Development Agency

 Boundaries
All the administrative boundaries should be shown as below:
State and National, if any
District Boundary
Block Boundary
 Road Network
The Road Network map should show the existing alignment (location) of National Highways, State Highways,
Major District Roads, Other District Roads, Village Roads and cart tracks etc, which have land width of 5 meters
or more, accurately using the information compiled in FORMAT-II. The legend to be used for denoting these
features (also railways, if any) on the map are as under:
 Roads/ Railways
Railways

National Highways

State Highways/ MDRs

All-weather Rural Road

Fair-weather Rural Road

(all existing cart-tracks, kutcha roads etc having land width 5m or more)

The Core Network (see para 3.2 below) should be


coloured Red, above the all-weather/ fair-weather
Rural Road Line

Cross-drainage Structure

Rivers & Canals

Lake

Places of Tourist Interest ⊗

Quarry Site QS

Market Centre

14 Operations Manual for Rural Roads


Planning

Health Services

Tehsil Headquarter

Educational Service

Sub Divisional Headquarter

 Location of Habitations
The habitations shall be shown as under Connected in Unconnected in
Black Red

Population > 1000

Population 500 – 999

Population < 500


The three digit Habitation Code should also be indicated beside shape code of each habitation. While numbering
the Habitations, it should be remembered that this will be a three digit code and would basically be the serial
number of the Habitation in the Block after the habitations are arranged alphabetically.
 Link Route and Through Route Identification
Link Routes are the roads connecting a single Habitation or a group of Habitations to Through Routes or
District Roads leading to Market Centres. Through Routes are the roads which collect traffic from several link
roads or a long chain of Habitations and lead it to Marketing centres either directly or through the higher
category roads i.e., the District Roads or the State or National Highway. Link routes generally have dead ends
terminating on a Habitation, while Through Routes arise from the confluence of two or more Link Routes and
emerge on to a major Road or to a Market Centre.

It is possible that some of the Through Routes (sometimes even Link Routes) may cut across Block boundaries.
While integrating the Block Plans into the District Rural Roads Plan, it should be ensured that the continuity is
maintained. Link Routes and Through routes will be distinguished on the Map by use of the Letter L and T
respectively followed by the relevant road code.

Operations Manual for Rural Roads


15
National Rural Roads Development Agency

 Colour Scheme of Map


The use of too many colours makes the presentation and interpretation of the maps difficult. Accordingly the
existing roads should be shown in black, while the ultimate “Core Network” (see para 3.2) should be shown in
Red. The proposed roads for linking the unconnected habitations shall be shown dotted in red. The legend for
the habitations of various population sizes is also indicated therein. All habitations should be code numbered in
the map.
All the Block level maps should then be integrated into a District level map, taking care to match all roads,
railway lines, rivers, canals etc. The District level map shall be to the same scale as the Block level maps.
The maps should in due course be got digitised so that it becomes easy to put them all on a computer-based
system, preferably on a GIS platform. Separate detailed instructions will be issued by NRRDA in this regard in
order to facilitate a web-based GIS which can be used for monitoring and decision support.
3.1.8 Step-IV: Preparation of the list of unconnected habitations and the selection of optimal road links
Next, the Team has to undertake the task of using the available data and the information available from the Map
to prepare the Rural Roads Plan of the Block. The Team should make two separate lists of Unconnected
Habitations : (i) those which are connected only by a fair weather road which needs to be upgraded to the
prescribed specifications and (ii) those which have no connection at all, not even by a fair-weather road. Both
the lists should be in descending order of their population. A Habitation with higher population will rank higher
in the list.
Once the lists have been prepared, the next task is to find out the most efficient and economic route, in terms
of cost and utility, for providing access from an eligible unconnected habitation to an existing All-weather road
or to an already connected habitation. Studies have revealed that upto 95% of the trips made by villagers are to
Market, Health, Education and Administrative centres. Consequently, while selecting the road link, the Team
would have to take into account the requirements of the residents of the Unconnected Habitation and also see
as to which connection best serves their needs. The views of the Village Panchayat or the Gram Sabha may
also be ascertained for this purpose.
Quite often, an Unconnected Habitation can be connected in more than one way. Often the Market Centre is in
a different direction from say, the Taluka Headquarters. In case a consensus is not easily reached, the choice
from various alternative links may need to be made on the basis of weightages accorded to different Socio-
economic services. Since PMGSY envisages only single connectivity, it is necessary to choose the most efficient
road link in terms of utility. The District Panchayat shall be the competent authority to select the set of Socio-
economic/infrastructure variables best suited for the District, categorise them and accord relative weightage to
them. This would be communicated to all concerned before commencing the preparation of the District Rural
Roads Plan. Numbers of people benefited per unit cost, number of persons having all weather access to a
hospital/school etc are a few examples of services/factors.
The proposals of the MPs and MLAs would be taken into account by the Team preparing the Draft Rural Roads
Plan for the Block. A specific list would be made of the roads suggested by the MPs and MLAs and remarks
indicated whether they are included or not; if not, the reasons thereof should be recorded. The Team would
then prepare the Draft Rural Roads Plan for the Block.
3.1.9 Step-V: Consideration and Approval by the Intermediate Panchayat
This Draft plan would be presented before the Intermediate Panchayat by the Leader or the Member- Secretary
of the Team preparing the Draft Rural Roads Plan for the Block. In this meeting, Officers of appropriate level,
who have knowledge of the area, may also be called. The Plan should be finalised by the Intermediate Panchayat.
Any changes made by the Intermediate Panchayat should be separately mentioned and causes thereof should
be indicated.
3.1.10 Step-VI: Submission of the Block Rural Roads Plan to the District Planning Committee
The Team will, after obtaining the approval of the Intermediate Panchayat, submit the Block Rural Roads Plan

16 Operations Manual for Rural Roads


Planning

to the District Planning Committee where these have been constituted, along with original map and all the
Formats and Tables. In its absence, the Plan would be submitted to the Chief Executive Officer/ District Collector.
The Team would record its views in case it feels that the Intermediate Panchayat has deviated from the Guidelines
in this regard.
3.1.11 Step-VII: Scrutiny by the District Planning Committee
The District Planning Committee is the body created in the District for ensuring proper preparation of Plans for
the development of the District. The District Rural Roads Plan is one which would have a tremendous bearing
on the all round socio-economic development of the District. Therefore, it is appropriate that all the Block Rural
Roads Plans are scrutinised by the District Planning Committee.
After the Rural Road Plans have been received from all the Blocks, these would be scrutinised by the Chief
Executive of the District Planning Committee/ Chief Executive Officer/ District Collector. He would be assisted
by a Committee comprising of the Head of the District Programme Implementation Unit (Member Secretary);
Superintending Engineer/ Executive Engineer PWD; Executive Engineer, Rural Engineering Service and senior
officers of the Revenue, Rural Development, Transport and other concerned Departments, as Members. They
should look into the deviations, if any, made by the Intermediate Panchayat and the justifications therefore.
They must ensure that the Road Plan is according to the criteria given by the District Panchayat with respect to
the Socio- Economic/ Infrastructure variables and also that the proposals of the MPs and MLAs have been duly
considered. If any provision made by Intermediate Panchayat or the Team preparing the original plan is not as
per the Guidelines, such provisions should be changed. The reasons thereof should be mentioned clearly.
The Committee, after collating all the Block Rural Road Plans will prepare the draft District Rural Roads Plan as
per the format shown in Annexure 3.4. It would also contain the priority list of road works to be taken up under
the Pradhan Mantri Gram Sadak Yojana, in line with the principles enunciated in Para 3.3.
3.1.12 Step-VIII: Consultation with the District Panchayat and Elected Representatives and Approval of
the DRRP
The Draft District Rural Roads Plan would then be presented to the District Panchayat by the Chief Executive
of the District Planning Committee. MPs should be specially invited to this Meeting. Members of the Committee
who prepared the District Rural Roads Plan should be present in the Meeting. It should be discussed and
adopted by the District Panchayat, with such changes as may be considered appropriate, but strictly within the
framework of the PMGSY Guidelines.
3.1.13 Step-IX: Forwarding of the District Rural Roads Plan to the State Level Standing Committee
After approval by the District Panchayat, the District Rural Roads Plan, along with the District Priority list, would
be forwarded through the SRRDA to the State Level Standing Committee.
3.1.14 Step-X: Vetting of the District Rural Roads Plan by the State Level Standing Committee
The District Rural Roads Plan would be vetted by the State level Standing Committee, headed by the Chief
Secretary/ Additional Chief Secretary, as the case may be. The Committee could call the Chief Executive
Officer/ District Collector to present the Plan before the Committee. This Committee should go into the details
of the Plan and priorities and links decided by the District Panchayat. The changes made by the District Panchayat
and reservations, if any, of the District Planning Committee, can also be discussed. The State level Standing
Committee should ensure that priorities decided by the District Panchayat, as well as direction of the Government
of India, have been followed in preparing the District Rural Road Plans in totality and the proposals of the MPs
have been duly considered. The Plan, after it has been vetted by this Committee, would be the final District
Rural Roads Plan. A copy of the District Rural Roads Plan would be sent to NRRDA for record.
The District Rural Roads Plan would, henceforth, constitute the basis of preparation of projects under the
Pradhan Mantri Gram Sadak Yojana as far as that particular District is concerned. The State Governments
would be required to attach the approved the Core Network along with project proposals under Pradhan Mantri
Gram Sadak Yojana.

Operations Manual for Rural Roads


17
National Rural Roads Development Agency

3.2 IDENTIFICATION OF CORE NETWORK


3.2.1 Core Network-Definition
The Core Network is the network of all the Rural Roads that are necessary to provide basic access to all the
Habitations. Basic access is defined as single all-weather road connectivity to each Habitation. As already
indicated, the effort under the PMGSY is to provide single all-weather road connectivity to each eligible Habitation
by way of connecting it to another Habitation having all-weather connectivity or to an all-weather road, in such
a way that there is access to, inter alia, Market Centres.
A Core Network is extracted out of the total Network mentioned in the DRRP and consists of existing roads as
well as the roads required to be constructed to the as yet unconnected Habitations. However, it will not consist
of all the existing roads of the DRRP since the objective is to establish ‘basic access’ i.e., one all-weather road
connectivity to each habitation.
3.2.2 Why Core Network
The Core Network has the following advantages:
 It will help in optimising the requirements of fresh construction and upgradation, for ensuring connectivity
to all the Habitations.
 It is primarily intended to mark out the essential network that is required to be maintained in good condition
at all times.
 It would optimise the resource allocation in respect of the network management within the District.
3.2.3 Steps Involved in Establishing the Core Network
The following four major steps are involved in establishing the Core Network.
 Prepare Block Maps as part of the District Rural Road Plan process.
 Identify the Market Centres.
 Identify the Network of roads to provide single access to the eligible habitations.
 Catalogue the roads by giving them code numbers.
These steps are explained below:
3.2.4 Preparation of Block Maps
The preparation of the Block Maps using topographical Maps at 1:50,000 scale has already been explained in
Para 3.1.7 for preparation of the district Rural Roads Plan. It may be ensured that the Block Maps show the
following:
 All Habitations upto a population of 100.
 All roads viz., NH, SH, MDR and Rural Roads, constructed by different agencies including the roads under
construction as well as cart tracks and paths (in hilly areas especially).
 Major Rivers/ Streams.
 Administrative office location like Block & Tehsil headquarters.
 Gram Panchayat Headquarters, Patwari office etc.
 Health Service facilities (including veterinary facilities).
 Educational Service Facilities.
 Market Centres and Rural business hubs.
 Places notified by State govt. as being of tourist interest.

18 Operations Manual for Rural Roads


Planning

 Quarry Sites.
 Market Centres, Administrative Centres like sub divisional headquarters and main roads which are outside
the Block boundary but serve the Habitations in the Block must also be marked, outside the Block boundary.
3.2.5 Identification of Market Centres and Rural Business Hubs
Before preparing the Core Network, one needs to identify all the Market Centres in the Block. This is because
an analysis of the transport patterns in the rural areas reveals that most of the travel is to the Market centres.
These are generally located either on bigger roads or at the confluence of roads leading from a number of
Habitations. Because they are easily accessible from the rural hinterland and are linked to the main road
network, they function as Rural Business Hubs and generally have facilities for marketing of agricultural surpluses,
Banking and telecommunication facilities, large stores for agricultural inputs as well as consumer items (durables
and consumables). Facilities like agricultural equipment repair shops may also exist. Consequently they are
likely to have developed public transport, Higher Education and Health care facilities. The Market Centres
should be identified using the data available from published Census records/information available from Marketing
Board/ local enquiries. For purposes of inclusion in the Core Network, market centres need to be identified to
the extent that the local villagers should be able to go to the Market centre and come back within the same day.
The maximum distance between a village and a Market centre would thus normally not be more than 15-20 km.
In some areas, the Market centres may not be fully developed. In such cases the big villages having potential
for developing into suitable Market Centres because of road connectivity etc should be identified. All the Marketing
Centres should be marked on the Block Map.
3.2.6 Identification of the Core Network
There are three types of habitations in the Block Map – those which are connected, having all-weather roads,
(ii) those which are not connected at all, (iii) those which are connected only by a fair-weather road. In the case
of connected Habitations, it is possible that there are more than one road connections. In such a case, one road
should be selected using Socio- Economic infrastructural parameter criteria. If, for any reason, an alternative
road is the preferred choice of the local people, that road may be chosen, but, in any case, only one road should
be selected for the Core Network, as the intention is to provide Basic access. In case of unconnected habitations,
a suitable road connection should be identified, which would generally follow the alignment of an existing track.
If there is more than one track, selection has to be made on the basis of the parameters, as already explained
in 3.1.8.
The Core Network Plan shall thus be prepared for the entire Block. It should be checked again that all the
Habitations are connected or will be connected to the nearby Market Centres, either directly or indirectly through
other all-weather roads. It is not necessary that each Habitation is directly connected to the Market centre in a
hub-and-spoke configuration.
Going by the definition of an all-weather road given in Chapter-1, it is not necessary to provide a road to a
Habitation that is within 500 metres of an already connected habitation or an all-weather road. All such habitations
should be treated as falling on the concerned road.
Suggestions/ proposals received from elected representatives including MLAs and MPs, Panchayats, and
local population must be properly examined as these ca0n provide very useful information about the missing
bridges, missing links and other priority demands of the local community. The existing road Network, location of
major Market Centres, topographical features, and local travel pattern should be kept in mind. While deciding
the Core Network, the fact that it will be used primarily by the local people must be uppermost in the mind.
3.2.7 Numbering of Core Network Roads and Tabulation of Data
Once the Core Network is identified, the details of all these roads should be listed in the Proformae CN 1 to CN
6. The Proforma are given at Annexure 3.5. The data in the Proforma should be uploaded or entered in the
DRRP Module of the Online Management and Monitoring System (OMMS). For purpose of numbering, it is
always better to start with the North-East corner of the Block and workout clock-wise giving progressively
higher numbers.

Operations Manual for Rural Roads


19
National Rural Roads Development Agency

3.2.8 Miscellaneous
In some areas, even the Network of higher order roads like Major District Roads (MDR) and State Highways
(SH) may not be fully developed. Many of the major bridges may be missing. The investment in Rural Roads
will not show expected results unless these major roads and bridges are constructed. The requirements of
such roads and bridges may be identified even though these are not to be included under the Pradhan Mantri
Gram Sadak Yojana. Such information should be provided to the State PWD to incorporate these in their plans.
3.2.9 Approval of Core Network
The procedure to be adopted for the approval of the Core Network shall be the same as that for the Master Plan
(Para 3.1).

3.3 IMPLEMENTING THE CORE NETWORK PLAN


3.3.1 Comprehensive New Connectivity Priority List (CNCPL)
The Core Network is the only basis for selection of works under PMGSY. Once the Core Network is ready, the
States are required to prepare Comprehensive New Connectivity Priority List (CNCPL), at Block and District
level, of all proposed road links under PMGSY (with road code, names of habitations being connected with
habitations code, population served and length), grouping them in the following Order of Priority:

Priority No. Population Size Category

I 1000+ New Connectivity

II 500-999 -do-

III 250-499 New Connectivity [where eligible in respect of Hill States (North-East,
Sikkim, Himachal Pradesh, Jammu & Kashmir, Uttaranchal) and the
Desert Areas (as identified in the Desert Development Programme)
as well as the Tribal (Schedule V) area].

The CNCPL list will be prepared with the following format:


S.No. Name TR/ Code Length Population Habs to be Present Name &
of road LR in CN served connected status no. of TR
(earthen associated
track etc.)

(CN – Core Network / TR – Through route / LR - Link Route)

The priortisation may be done in one of several ways, but whatever methodology is selected has to be uniformly
applied in the State. The basic features of the prioritisation methodology would have to be as follows:
 The proposed links would need to be categorized in the Order of Priority at the outset.
 Further prioritisation within the Order of Priority may be done with the State, District or Block as the
planning unit, as convenient.
 For a given Order of Priority and a given planning unit, the listing can be on basis of total population
benefited.
 Further refinements in terms of population per Km. benefited, etc may be adopted if found useful.

20 Operations Manual for Rural Roads


Planning

Depending on whether State or District is the unit, the SRRDA or PIU will prepare the CNCPL (and CUPL, See
para 3.3.3).
3.3.2 Prioritisation of New Connectivity Road Works in Annual Proposals
The issue of criteria for selection of roads to be taken up has figured several times in Parliament and its
Committees and it is apparent that the District Panchayats in the States need to adopt a uniform and objective
methodology in a transparent manner, and to also enable full consultation with lower level Panchayati institutions
and elected representatives.
Since the Core Network is now the basis for making Annual Proposals, and as given in Para 3.3.1 above, a
Block/ District-wise Comprehensive New Connectivity Priority List (CNCP List) has been prescribed, all
consultations for new connectivity will be based on such lists, and Panchayati Raj Institutions and Elected
representatives may be furnished a copy of the relevant up-to-date CNCP List in order for them to indicate their
choice of road works. Where road works of a higher Order of Priority still remain to be taken up, road works of
a lower Order of Priority will not be taken up in the same District except when it is not feasible to execute the
road work for reasons of non-availability of land etc. While finalising the District proposal, the District Panchayat
shall record reason for such cases.
3.3.3 Upgradation Works
Upgradation works will be proposed in a district only if no new connectivity remains to be taken up. The selection
of roads for upgradation will be done on the basis of a Road Condition Survey (Annexure 3.6) of the Core
Network of the District which will establish a Pavement Condition Index (PCI) on a rating scale of 1 to 5 (see
Chapter 14, and Annexure 14.7). After the Road Condition Survey is completed, a Comprehensive Upgradation
Priority List (CUPL) for the District shall be prepared.
The only exception is if the Through Routes in the District are in such poor condition that the new connectivity
link does not give all-weather farm to market access. In such cases, from the CNCPL, it is possible to identify
such Through Routes (called associated Through Routes) and conduct a Road Condition Survey for such
roads only, in order to be able to decide whether or not they need to be upgraded along with the new connectivity
of the attached link road.
The Road Condition Survey results will first be entered into the PCI register and the Road Master under OMMS
in all cased. In cases where no new connectivity is involved, the PIU will then prepare the Comprehensive
Upgradation Priority List (CUPL) for the District based on the following:-
(i) The roads to be included in the CUPL will necessarily be Through Routes already included in the Core
Network. Presently sealed-surface all-weather roads with PCI more than 2 and sealed-surface all-weather
roads which are less than 10 years old (even if PCI is less than 2) will not be taken up for upgradation.
(ii) Priority-I will be Through Routes which are presently WBM roads. In such cases, upgradation will comprise
of bringing the existing profile to good condition (along with improvement in geometrics, necessary drainage
works and road signages) and providing the appropriate crust and surface as per design requirement.
(iii) Priority II are other fair weather through routes or gravel through routes or through routes with missing
links or lacking cross drainage. In such a case upgradation will consist of converting the road into an all-
weather one with appropriate geometrics and all necessary provisions.
(iv) Priority III will be other through routes which are at the end of their design life, whose PCI is 2 or less, i.e.,
are ‘poor’ or ‘very poor’. In such road width, surfacing, etc., as per normal projected traffic requirements.
(v) Within each priority class, qualifying roads will be arranged in order of population served (directly and
through population served in link routes), as a rough indication of traffic expected. However, States are
advised to conduct an Average Daily Traffic (ADT) Survey at the earliest. Based on the time at which the
traffic survey is carried out (such as Peak or Lean Seasons) the same is to be adjusted for seasonality in
order to arrive at the Annual Average Daily Traffic (AADT) count, which is the basis for the prioritisation as
well as the design. (An axle load survey may also be carried out, on selective basis, on the roads where

Operations Manual for Rural Roads


21
National Rural Roads Development Agency

heavy traffic is expected with wide variations in the Axle Load Spectrum. Proposals for this purpose approved
by NRRDA will be eligible for reimbursement of expenses).
(vi) In case, in any District, the Through Roads defined in the Core Network do not belong to the Rural Roads
category, the main rural links (emanating from the Through Route) will be considered for upgradation on
similar lines indicated above. The basis for Prioritisation will be, in addition to PCI, the population served
by the link in each category. In such cases the selection will be validated by the STAs and data entry made
in OMMS Road Master accordingly after categorising them as main rural links (MRL).
Preparation of CUPL
The work of preparing the CUPL will be taken up only in those districts which are likely to complete new
connectivity to eligible habitations within the next 1 year. The list will be prepared District-wise for each Priority
class on the following proforma (where only a truncated portion of the road is to be taken under upgradation,
only that portion needs to be mentioned by chainage):-

District Priority Class


Block Road Name of Year of Year of Present PCI Total AADT
code in through construction last surface Population of
CN route / periodic type the habitations
MRL* renewal served by the road

* where TR is not a Rural Road

Verification of CUPL
The CUPL will be got verified on the ground on sample basis through the STAs and the NQM system before it
is processed for further approvals. The STAs will do 100% verification on the basis of the PCI data given by the
District and sample ground checking.
Approval
After the CUPL is prepared and verified, it shall be placed before the District Panchayat for approval thereafter
it shall be vetted by the State level Standing Committee (SLSC). After the District is eligible to take up upgradation
works, annual proposals will be made for upgradation in the same manner out of the CUPL, as new connectivity
proposals are made out of the Comprehensive New Connectivity Priority List (CNCPL).
3.3.4 Consultation with the Members of Parliament
The Comprehensive New-Connectivity Priority List (CNCP List) identified to connect unconnected habitations
(along with names of habitations and population served and length) or the Comprehensive Upgradation Priority
List (CUPL) as the case may be, should be sent to the Members of Parliament, to facilitate the Members of
Parliament in making their suggestions. It will be incumbent upon the District Panchayat to ensure that full
consideration is given to the proposals received from the Members of Parliament.
While Lok Sabha Members will be consulted in respect of their constituencies, Rajya Sabha Members will be
consulted in respect of that District of the State they represent for which they have been nominated as Vice-
Chairman of the District Vigilance & Monitoring Committee of the Ministry of Rural Development.
 The proposals received from the Members of Parliament by the stipulated date should be given the full
consideration in the District Panchayat which should record the reason in each case of non-inclusion and
the Members of Parliament should be informed of the inclusion/ non-inclusion of their proposals along with
the reasons in each case in the event of non-inclusion. It would be preferable if the communication is
issued from the Nodal Department at a senior level.

22 Operations Manual for Rural Roads


Planning

 The State Government should also arrange to supply to each Member of Parliament, an annual list of road
works taken up under the Programme for the period ending 31st March. State Governments have already
been advised to print such lists annually, in English and local language. Copies of these may be conveniently
supplied to elected representatives and Panchayati Institution and 10 copies of the English version and
5 copies in the local language version should be sent to NRRDA by 31st May of each year.
 The Programme Implementation Units (PIU) at the District Level should facilitate Members of Parliament
in knowing the status of implementation of the road works in their areas in case they visit their District. The
website (omms.nic.in) may also be kept updated for this purpose.
3.4 DATA ENTRY IN OMMS
3.4.1 As soon as the DRRP is finalised, the PIU shall enter the data in the OMMS after logging in. Unless
already entered, Master Data for the district has to be entered first followed by the details of habitations (as per
2001 census) and roads connecting them. Unless this data is entered, further data entry relating to the Annual
Proposals, Execution of projects and Expenditure cannot be entered, since for all these purposes, the road will
have to be selected out of the DRRP (and infact the Core-Network).
3.4.2 Once the Core-Network roads are identified in the OMMS, the OMMS is enabled to produce the CNCPL
for the district and also, once the Pavement Condition Index has been entered, the CUPL.

Operations Manual for Rural Roads


23
National Rural Roads Development Agency

Annexure 3.1
(See Para 3.1.6)
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
CODE FOR HABITATION

R J 0 9 1 5 0 2 3

This is the serial number of the habitation in


the Block. There can be maximum of 999
habitations in the block as three digits are
allocated.

This is the serial number of the Block in a


district. This shows that a maximum of 99
Blocks can be identified in a District.

This is the serial number of the District in the


state. There can be maximum of 99 districts
in the state as two digits are provided.

This is two-letter code for the State and this is


to be same as that indicated for the package
prepared under PMGSY as listed below:

STATE/ UNION TERRITORY CODES


Name of State Code Name of State Code
Andhra Pradesh AP Nagaland NG
Arunachal Pradesh AR Orissa OR
Assam AS Punjab PB
Bihar BR Rajasthan RJ
Chattisgarh CG Sikkim SK
Goa GA Tamilnadu TN
Gujarat GJ Tripura TR
Haryana HR Uttaranchal UT
Himachal Pradesh HP Uttar Pradesh UP
Jammu & Kashmir JK West Bengal WB
Jharkhand JH Name of Union Territory
Karnataka KN Andaman & Nicobar Islands AN
Kerala KR Chandigarh CH
Madhya Pradesh MP Dadra & Nagar Haveli DN
Maharashtra MH Daman & Diu DD
Manipur MN Delhi DL
Meghalaya MG Lakshadweep LK
Mizoram MZ Pondicherry PD

24 Operations Manual for Rural Roads


Annexure-3.2
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY) (See Para 3.1.6)

HABITATION DATA FORMAT-I


A : REFERENCE DATA
STATE : CODE DISTRICT : CODE BLOCK : CODE:
B : DEMOGRAPHIC & INFRASTRUCTURE DATA (FOR ALL HABITATIONS) :
Provide the following information for each Habitation in the block (Available facilities may be indicated by number of units)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

PHCs
Office
(H/C/P)

Villages
Name of
Habitation
(Plus Two)
(give code)

Dispensary
Habitations
(AWR/FWR)

in the Block
Name of the
Commercial

High School
Constituency
List of Roads

MCW Centres
held per week

Middle School
Establishment

Health Service
Plain Areas (P)
Connecting the

Primary School
Post, Telegraph
Electrified (Y/N)

Degree College/

Total Population
Type of the Road

Telephone Booth
Name of MLA/MP

SC/ST Population

Revenue/Census
Vocational School
Bus Services (Y/N)

No. of days Market

Veterinary Hospital
Panchayat HQ (Y/N)
Hilly (H)/ Coastal(C)/

Railway Station (Y/N)

Intermediate Schools

Sl. No. of Habitations


MLA : L1 :
MP : L2 :
L3 :
MLA : L1 :

Operations Manual for Rural Roads


MP : L2 :
L3 :
MLA : L1 :
MP : L2 :
L3 :
MLA : L1 :
MP : L2 :
L3 :
MLA : L1 :
MP : L2 :
L3 :
Note: Please see the instruction sheet for detail

Certification: certified that the above information is correct : Name: Designation: Signature:

25
Planning (Annexures)
National Rural Roads Development Agency

INSTRUCTION-I
REF: ANNEXURE 3.2

INSTRUCTIONS FOR FILLING FORMAT-I

The form has three parts as explained below: -


A. Reference data: It contains the name and code number for State, District and Blocks. The two-letter
code for various States/ Union Territories, are given in Annexure 3.3. The State administration will first list
all the Districts (preferably alphabetically) and number them serially for use as the District code. The
District administration will list all the Blocks (preferably alphabetically) and number them serially for use
as the Block code.
B. Demographic and Infrastructure data: This data can be provided for each Habitation, as defined earlier.
One revenue village may have one or more Habitations. Therefore, for all such Habitations, suitable
codes should be provided. For code number, all Habitations within a Block may be alphabetically arranged
and then serially numbered, while Habitation within a village should be alphabetically arranged and then
serially numbered. The instructions to fill up each column are given below :
Col 1 Write the name of revenue village and code number.
Col 2 Write the code number of Habitation (this is a serial number only from the list of all Habitations
in the Block).
Col 3 Write the name of Habitation.
Col 4 Give the current population of Habitation based on 2001 Census.
Col 5 Give the current SC/ST population based on 2001 Census.
Col 6 Write the number of units of each facilities available in Habitation under.
to 19 relevant column. If not available write zero.
Col 20 Write Yes, if the Habitation is connected with bus facility, otherwise write No.
Col 21 Write Yes, if the Habitation is connected with railway station, otherwise No.
Col 22 If the Habitation is electrified write Yes, otherwise, write No.
Col 23 Write Yes, if the Habitation is the Panchayat Headquarter, otherwise No.
Col 24 Write (H) if the Habitation is in a Hilly area (C) for Coastal area and (P) Plain.
Col 25 Give the name of MLA and MP constituency.
Col 26 The Habitation may have one or more roads coming from different direction. One or more of
them may be All-weather road. On the other hand none of these may be All-weather road. They
may be fair-weather road e.g. earth road, track, bridle path, etc. Give the list (code number and
type only) of all such roads. If the numbers of such roads are more than the rows specified in
the format, then additional rows of the table should be used. These roads will be required to be
inventorised in FORMAT-II with the same code numbers. Fill the code number of road from
inventory FORMAT-II (after it is prepared) here also.
Col 27 The type of the road i.e. AWR for All-weather Road or FWR for Fair-weather Road.
Certificate: Give the certificate and sign it.

26 Operations Manual for Rural Roads


Annexure-3.3
(See Para 3.1.6)
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)

INVENTORY OF RURAL ROADS FORMAT-II

A : REFERENCE DATA

STATE : CODE DISTRICT : CODE BLOCK : CODE

B : Provide the following details of all types of Rural Roads in the Block
List of
Width (m) Length (Km) with Existing CD Works Habitations on
Surface Type) the Road

(FWR)

Sl. No.
BT

Road Code
Terrain Type
Type

Name of Road
Gravel
Number

Earthen

(ODR/VR/Others)
Width (m)

Category of Road
Fair-weather road

WBM/ Metal
Total Length

Condition Rating (PCI)

Predominant Soil Type


Habitation Code

(waterway span)

Length (Km) (Ex. 12.935)


Formation Width

Road Land Width


Carriageway Width
All-weather Road (AWR) or
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
CD1 H1
CD2 H2

Operations Manual for Rural Roads


CD3 H3
CD1 H1
CD2 H2
CD3 H3
CD1 H1
CD2 H2
CD3 H3
CD1 H1
CD2 H2
CD3 H3
Note: Please see the instruction sheet for detail

Certification: certified that the above information is correct : Name: Designation: Signature:

27
Planning (Annexures)
National Rural Roads Development Agency

INSTRUCTION – II
REF: ANNEXURE 3.3

INSTRUCTIONS FOR FILLING FORMAT-II

A comprehensive inventory of all types of Rural Roads has to be prepared and all these roads should also be
marked on the map. The code number of all such roads should be given in the map.
A. Reference data: Provide the name and code numbers for State, District and Block.
B. Road Inventory:
Col 1 Serial number.
Col 2 Name of road may be formed by giving the names of starting and/ or ending Habitation. The road
may have a normal name for it.
Col 3 Give the code number for each road which may be the serial number of road added to the Block
code, number may be L1. L2. L3 and so on.
Col 4 Specify the category of road (ODR/ VR/ Other category).
Col 5 Give the total length of the road accurately. For example, 12.935 km indicates it to be 12 km and
935 metres long.
Col 6 Give the major type of soil of the road such as Black Cotton (BC), Silty (SL), Sandy (S), Gravel
(G) etc.
Col 7 Terrain type may be classified into Plain (P), Rolling (R) and Hilly (H).
Col 8 Give the three parameters of the road geometry. The land-width
to 10 formation-width and carriage-way are to be recorded.
Col 11 Surface condition: Give the lengths of the road sections having different
to 14 surface type in different parts of the road.
Col 15 Give whether the road is All-weather (AW) or Fair-weather (FW).
Col 16 Give the condition rating (Present Condition Index) in a scale of 1-5 (1 : Very Poor, 5 : Very
Good).
Col 17 Cross Drainage (CD) works: Give the details for all existing CD works
to 20 along the road. If more than three CD works are there, use additional rows of the Format. For
each CD show the waterway span (metres) and carriageway width (metres) of the CD.
Col 21 Give the list of all Habitations within 500 metres from the centre of the
to 22 road. Details of all these Habitations are given in FORMAT-I.

28 Operations Manual for Rural Roads


Annexure: 3.4
(See Para 3.1.6)
Format-III
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
RECORD OF PRIMARY AND SECONDARY ROADS

State: Code: District: Code:


Block: Code:
Sl. Name of Road Identification Kilometer Length Carriage- Surface type Remarks AW/FW
No. code (eg NH- (KM) way width (BT/WBM/Gravel/
33) Starting Ending (m) Earth)
(eg.24.750) (eg. 29.770)

1 2 3 4 5 6 7 8 9

Operations Manual for Rural Roads


29
Planning (Annexures)
30
ANNEXURE : 3.5
(See Para 3.2.7)
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
PROFORMA -CN-1
DETAILS OF CORE NETWORK ROADS
State: Block: District:
District:
National Rural Roads Development Agency

Population
Existing Surface Type
Sl. Road From To Total served indirectly
Miss- Habitation Served Directly Total Owner
No. No. Length by
BT WBM GRAVEL TRACK ing Population ship of
in link routes
CDs served the road
Km L Con L Con L Con L Con Name Code Population C / Link Popul-
Km Km Km Km UC routes ation

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)

Operations Manual for Rural Roads


PROFORMA CN-2 (a)
BLOCK WISE DETAILS OF CORE NETWORK
State: District:
No of conneted habitations
Name No of 1000+ 500-999 250-999 <250
Sl.No. of Habit
Total
Block ations BT WBM GR Total BT WBM GR Total BT WBM GR Total BT WBM GR Total

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Total
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
PROFORMA CN-2 (b)
BLOCK WISE DETAILS OF CORE NETWORK

District:
Block:
No of unconnected habitations

1000+ 500-999 250-499 <250 Total

21 22 23 24 24

Operations Manual for Rural Roads


PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
PROFORMA CN-2 ( C )
BLOCK WISE DETAILS OF CORE NETWORK

District:

Length of roads for connected habitations of core network (In KM)


1000+ Balance 500-999 Balance 250-499 Balance <250 Total
BT WBM GR BT WBM GR BT WBM GR BT WBM GR BT WBM GR
26 27 28 29 30 31 32 33 34 35 36 37 38 39 40

31
Planning (Annexures)
32
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
PROFORMA CN-3
BLOCK WISE DETAILS OF CORE NETWORK
State: District:

Total Road Length in the Block (in Km) Total Road Length in Block for Identified Core Net Work (In Km)
Sl. Name of
No. Block BT WBM Gravel Track Total BT WBM Gravel Track Total
National Rural Roads Development Agency

1 2 3 4 5 6 7 8 9 10 11 12

Total

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)


PROFORMA CN-4(a)
BLOCK WISE DETAILS OF CORE NETWORK

Operations Manual for Rural Roads


State: District:

Sl. Name of Total Road Length in Core Net Work in Km Total Length of NH & SH in Core Net Work in Km Total Length of MDR in Core Network in Km
No Block BT WBM Gravel Track Total BT WBM Gravel Track Total BT WBM Gravel Track Total
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

Total
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
PROFORMA CN-4(b)
Pradhan Mantri Gram Sadak Yojana-Block wise Details of Core Network

State: District:

Total Length of Through routes in Core Network in Km Total Length of Link routes in Core Network in Km Total Length of
Sl. Name of (excluding NH,SH & MDR. ie. Rural Roads) (excluding NH,SH & MDR. ie. Rural Roads) Roads in
No Block core network
BT WBM Gravel Track Total BT WBM Gravel Track Total (Rural Roads)
1 2 18 19 20 21 22 23 24 25 26 27 28

Total

Operations Manual for Rural Roads


PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
PROFORMA CN-6

State: Block: District:

Name of proposed road Habitations being connected


Sl. Unconnected Name of Population subserved by Link
Link
No habitation unconnected Population Number Population Route (col 4+10)
From To Length route
No. habitation
(in Km) Number

1 2 3 4 5 6 7 8 9 10 11

33
Planning (Annexures)
34
Annexure-3.6
(See Para 3.3.3)
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
RURAL ROAD INSPECTION FORM - I

Name of Rater : ............................................. Date of Inspection : .............................................

District : ............................................. Block : .............................................

Name of Road : .................................................................................... Functional Class : ODR / VR Code No. ..........

Topography : ....................... Plain / Rolling / Hilly From : ................................. Km to .....................................Km.


National Rural Roads Development Agency

Traffic Volume(ADT) : ....................... Traffic Composition : ...............................................................................

Approx.Percentage of : HCV : ...................... LCV : ..................................... AT/T : .........................................

C/J : ...................... TW : ...................................... ADV : .........................................

esign Speed : ……… Kmph. Pavement Thickness & Composition :..................................................................................

Pavement Surface Type : ................................................................ Pavement Width : ....................................m .

Shoulder Surface Type : ................................................................ Shoulder Width : ....................................m .

GWT Depth : ...............m . Indicate Waterlogging ............................................. Km to ......................Km.

Soil Type : ..................... Indicate Problematic Soils : Type ............................. Km to ......................Km.

Operations Manual for Rural Roads


Year of Construction ................................. Construction Agency ..........................................................................

Year of last Renewal ................................. Maintenance Agency ..........................................................................

Approx.No.of CD Structures Per Km Pipe Culverts ................ Box Culverts .....................................


and their condition :
Causeways ................ Vented Causeways .....................................

Minor Bridges ................ Other .....................................

Remarks : ......................................................................................................................................................................
......................................................................................................................................................................
......................................................................................................................................................................
Note :
ADT : Average Daily Traffic HCV : Heavy Commercial Vehicles (including buses)
LCV : Light Commercial Vehicles (including Mini Buses) AT/T : Agricultural Tractor/ Trailer
C/J : Cars/ Jeeps TW : Motorised Two-wheelers
ADV : Animal Drawn Vehicles
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
RURAL ROAD INSPECTION FORM - II

Kilometerage

A. Distress Type & Severity 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15


Slight < 10 mm
Rutting Moderate 10 - 20 mm
Severe > 20 mm
Slight < 6 mm
Cracking Moderate 6 - 15 mm
width Severe >15 mm

B . Distress Type & Density 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15


< 15 Slight
Rutting 15 - 30 Moderate
(% Area)
> 30 Severe
< 15 Slight
Cracking
15 - 30 Moderate
(% Area)
> 30 Severe
Depressions < 15 Slight
& Potholes 15 - 30 Moderate
(% Area) > 30 Severe
Slight
Shoulders Moderate
Severe

Operations Manual for Rural Roads


Slight
Roadside Ditches/ Moderate
Drains Severe
Slight
Cross-Drainage Moderate
Structures Severe
Slight
Safety Features Moderate
Severe
40 - 50
30 - 40
Safe Travel Speed
20 - 30
(Km/hr)
10 - 20
0 - 10
Smooth
Comfortable
Riding Comfort Uncomfortable
at 50km /hr Very Rough
and Bumpy
Dangerous

35
Planning (Annexures)
National Rural Roads Development Agency

CHAPTER 4
ANNUAL PROPOSALS AND THEIR CLEARANCES

4.1 FUNDING AND ALLOCATION


4.1.1 Once the Core Network is prepared, it is possible to estimate the length of roads for New Connectivity
from the CNCP List. Similarly, after the Condition Survey in districts having no new connectivity remaining, it is
possible to estimate the length of roads required to be upgraded. States may, each year, distribute the State’s
Allocation among the Districts distributing atleast 80% to New connectivity Districts on the basis of ratios of
road length required for providing connectivity to Unconnected Habitations and not more than 20% to districts
with no new connectivity on the basis of ratio of road length requiring Upgradation under the PMGSY. The
District-wise allocation of funds would also be communicated by the SRRDA to the Ministry/ NRRDA and to the
State Technical Agency, in order to enable the STA to scrutinize the DPRs of the District. Depending on the
extent of new connectivity backlog, absorption capacity, position of the ongoing works etc, the State will be
asked to prepare DPRs for upto twice the PMGSY allocation.
4.1.2 To ensure due primacy to new connectivity, in case only a few Districts have achieved full connectivity, it
is not necessary to distribute the entire 20% among them. A smaller percentage would suffice, based on a
simple arithmetical average of what the Districts share would be.

4.2 PROPOSALS
4.2.1 Annual proposals consisting of list of roads eligible under PMGSY are to be finalized by the District
Panchayat. As mentioned in Para 3.3.1, based on the DRRP and Core Network, a CNCP List or a CUPL is to
be prepared by the PIU/ SRRDA prioritising the list of eligible road works and the annual proposal will be
prepared on the basis of the List as follows:
 In States where existing rural through routes are in reasonably good condition (i.e. PCI is generally above
3) the prioritisation of new links will be taken up for construction in the order of the CNCPL. Based on the
likely value of proposals required to be submitted, the PIU will mark off the eligible road works in the Order
of Priority to the required total value of the District allocations, applying the per km cost based on previous
years cost for similar type of work (new connectivity/ Upgradation etc).
 In States where the existing rural through routes are in very poor condition (PCI is generally 3 or less)
because of neglect of maintenance, upgradation / renewal of through routes may be taken up as an
adjunct to new connectivity and the procedure will be as follows:-
Step 1: Select the New Connectivity Link as per CNCPL in order of priority.
Step 2: Identify the rural Through Routes (called associated Through Route) from which the new link is
taken off till such road reaches the nearest market centre/ higher category road.
Step 3: Find out the Pavement Condition of the associated rural Through routes identified in Step 2 (from
the PCI register, See Para 14.9).
Step 4: Decide the type of intervention required based on the PCI. This implies a decision whether the
roads leading to the market centre require Upgradation or Surface Renewal or routine Maintenance.
Associated Through Routes having PCI 3 and below and 6 years or more old can be taken up for
Upgradation/ Renewal. For the roads with PCI above 3, or whose age is less than 6 years, Routine
Maintenance or, if due, Renewal will be adequate, unless there are structural / geometrical/ drainage
deficiencies which need to be improved through Upgradation.

36 Operations Manual for Rural Roads


Annual Proposals and their Clearances

Step 5: Include all other eligible new links as per Comprehensive New Connectivity Priority List (CNCPL)
coming on to the Through Routes identified in Step 3 even if such links are lower in the Order of the
Priority. These eligible new links would be the subsidiary link routes.
Step 6: Each project will thus comprise of a sub-network of a primary new connectivity link, the associated
Through Route (s) and subsidiary new connectivity links (falling on the associated Through Routes). The
project proposal will include new construction for the new links and Upgradation/ renewal of the Through
Routes based on age and PCI. Generally each such project would form a package for tendering purposes
(all the packages of a particular year would form a Batch for future maintenance purposes).
Step 7: Make a rough estimate of the project cost based on per km construction/ upgradation cost. Through
Routes and subsidiary Link routes required to be considered, are also be included while calculating the
total value. Take up additional links from the CNCP list and repeat steps 1 to 5 till the total cost of the
selected projects cover the District allocation.
 In case of Districts where no new connectivity remains, only the existing rural Through Routes may need
Upgradation. In such cases the Comprehensive Upgradation Priority List (CUPL) will apply and road
works will be selected out of the CUPL in order of priority, to the extent of the District allocation.
 In drawing up the annual list of the road works, it shall be ensured that the Order of Priority for New
Connectivity/ Upgradation is strictly followed. The only exception (in new connectivity links) from the order
of priority is in respect of those routes of the Core Network that include the Village Panchayat Headquarters
or Market Centres or other educational or medical essential services or those which stand notified by the
State Government as places of tourist interest. In such cases, new connectivity may be taken up irrespective
of the population size.
 A Preliminary Survey should be done by the PIU in all cases to ascertain from the Local Panchayat that
land is likely to be available for the road work.
4.2.2 A copy of the CNCPL/ CUPL is sent by the PIU to the Member of Parliament concerned seeking his
suggestions for the annual proposals. At least 15 days time may be given. In order to ensure that the prioritisation
has some reference to the funding available, the size of proposals expected may also be indicated to the
Members of Parliament while forwarding them the List. Para 4.1 gives the basis of District-wise allocation of
fund. All States should allocate the amounts accordingly and also further distribute it Block-wise to enable lower
level Panchayati Institutions and elected representatives to indicate their choice with the requisite geographical
spread. It is expected that such proposals of Members of Parliament which adhere to the order of priority given
in Paras 3.3.1 and 3.3.3 would be invariably accepted subject to consideration of equitable allocation of funds
as per Para 4.1. (See 4.2.4 below)
4.2.3 The list of proposed road works based on the above will be submitted to the District Panchayat by the
PIU. The List will clearly indicate the suggestions received from MPs and the status of eligibility. Along with the
estimated cost of construction based on line estimate, the 5 year routine maintenance estimate will also be
depicted by the PIU.
The District Panchayat will be requested to indicate its approval, and in case any changes are proposed, the
reasons for such changes. The District Panchayat may hold internal consultations or take further suggestions
from lower level Panchayat institutions. A time frame may be indicated, generally about 15 days, to enable full
consultation. Any suggestions received in the meanwhile from the Members of Parliament shall also be forwarded
to the District Panchayat for taking into consideration.
4.2.4 After obtaining the approval of the District Panchayat, the PIU will prepare the MP I and MP II statements
and forward them along with the approved list to the SRRDA. While filling up the MP I and MP II formats
(Formats at Annexure 4.1), the PIU will ensure that
 All MPs have been duly consulted.
 Proposals of MPs qualifying under the guidelines have been included in the annual proposal list. In case,

Operations Manual for Rural Roads


37
National Rural Roads Development Agency

for reasons of budgetary constraints, lack of land availability or forest clearance, the District Panchayat
has not been able to approve the road work, the specific reason shall be clearly stated in MP II, as to why
it is not feasible to take up the work at the present stage.
 Where the road work is relatively low in the Order of Priority, it shall specifically be mentioned as to what
the present population level of coverage is, and what the population benefited by the proposed work is, in
relation to that.
 In all cases where the proposed road work is not eligible because it is not a rural road; is not the part of
Core Network, it connects an already connected habitation; it is being covered under some other programme
etc, the specific reason shall be clearly stated in MP II.
4.2.5 Since the State annual allocation is known in general terms, in the interest of speeding up the matter
without curtailing the consultative element, even before the communication of the actual allocation from the
State Government, the SRRDA may initiate the process in such a way that the District Level Lists are ready by
June each year, and the consolidated State list is ready for submission after scrutiny by SRRDA by July.
4.2.6 On receipt of the District proposals list, the SRRDA will scrutinize the list to ensure that
 The road works have been approved by the District Panchayat.
 All the road works are part of the Core Network, follow the order of the CNCPL/CUPL as the case may be,
except where the road work is not feasible for specific and justified reasons.
 In case Associated Through Route has been taken up along with a Primary New Connectivity, that all
subsidiary New Connectivities as per Core Network has been included.
 The proposals of MPs have been given due consideration and MP I and MP II have been correctly filled in.
 The total value of the proposal (based on the line estimate) is as per requirement.
After proposals from all the districts have been scrutinized and found to be in order, the list along with MP I &
MP II will be placed before the State Level Standing Committee. This may be done as soon as District Level
allocation is available. At that time the SRRDA shall compile and submit the MP III format. The SRRDA will also
compile the likely 5 Year routine maintenance estimate and submit the estimated amount annually required.
4.2.7 The State Level Standing Committee shall normally consider the complete proposal for the State, except
that where there is more than one Executing Agency; the matter may be taken up Agency wise. Clearance by
the Committee, which is chaired by the Chief Secretary/ Additional Chief Secretary and includes Finance Secretary
as a Member is in the nature of Administrative Approval for the works and annual maintenance (based on the
line estimate) enabling the preparation of DPRs required for obtaining project funds from the PMGSY. As such
the Committee shall
 Review the progress of ongoing works and ensure that the Executing Agency is progressing well in terms
of speed and quality.
 Ensure that adequate contracting capacity will be available for the proposed road works.
 Ensure that the proposed road works are fully in accordance with the PMGSY Guidelines.
 Satisfy itself that all necessary clearances can be obtained and policy, funding and procedural issues
impeding execution are identified and resolved. In particular, the Committee shall ensure that maintenance
of the rural Core Network in general and PMGSY roads in particular are fully catered to.
 Approve the budgeting of the 5 year routine maintenance fund requirement.
 The Committee shall then accord its approval to the proposal. The minutes of the meeting shall be drawn,
and copy endorsed to NRRDA as well as SRRDA.
4.2.8 On receipt of the approval of the SLSC, the SRRDA shall communicate the approval to the PIUs and
coordinate the process of preparation of DPRs. It shall then:-

38 Operations Manual for Rural Roads


Annual Proposals and their Clearances

 Hold a coordination meeting with STAs and PIUs to determine the schedule for scrutiny of DPRs of the
various PIUs. At this meeting issues of Design and DPR preparation can also be usefully discussed (See
Chapter 6).
 Determine the funding limits to be allowed to PIUs for preparation of DPRs/ trace cutting and communicate
the details to the Bank branches.
 Monitor the progress of preparation of DPRs and ensure that necessary data on DPRs prepared is entered
by the PIU in the OMMS data base.

4.3 PREPARATION OF DPRS


4.3.1 The PIU will bear in mind the following Guidelines in preparing the Detailed Project reports in accordance
with Chapter 5 ‘Design’ of this Manual :
 Rural Roads constructed under the Pradhan Mantri Gram Sadak Yojana must meet the technical
specifications and geometric design standards given in the Rural Roads Manual of the IRC (IRC:SP20:2002)
and also, where required, the Hill Roads Manual (IRC:SP:48)
 The choice of design and surface for the road would be determined, inter alia, by factors like traffic density,
soil type and rainfall, following the technical specifications laid down in the Rural Roads Manual
(IRC:SP:20:2002). Normally rural roads would need to be designed to carry upto a limit of 45 commercial
vehicles per day (CVPD) only. All cases of design for new construction where a higher traffic is projected
need detailed justification. In the case of new construction for eligible Habitations of population below
1000 where traffic expected is likely to remain low (below 15 CVPD), in the interest of economy, the road
would generally be designed for a gravel or other unsealed surface as provided in the Rural Roads Manual,
subject to considerations of rainfall. In case of new construction to connect Habitations with population
below 500 where the projected traffic growth is likely to be very low, the carriageway may further be
restricted to 3.0 m.
 Where the road passes through a Habitation, the road in the built-up area and for 50 metres on either side
may be appropriately designed preferably as a Cement Concrete Black Pavement Road or Paved with
Stones, besides being provided with side drains. Appropriate side drains and cross drainage will be provided,
so that improper drainage does not damage the road or the dwellings alongside.
 Wherever locally available materials, including products like Fly Ash are available, they should be prescribed
subject to adherence to technical norms and relevant Codes of Practice.
 The Rural Roads constructed under PMGSY must have proper embankment/ drainage. Adequate number
of Cross Drainage (CD) works, including cause-ways where appropriate, must be provided based on site
requirement ascertained through investigation. Minor bridges may be provided where necessary. In case
the length of the bridge exceeds 15m, a separate DPR will be prepared after site inspection jointly by the
Superintending Engineer and the State Technical Agency. In case the length of the bridge exceeds 25m,
the project will be separately executed by the engineering division of the State Government having jurisdiction
and the pro rata costs beyond 25 m and agency charges, if any, will be borne by the State Government.
 In the case of Hill States, the estimates for new construction works may be prepared in 2 parts wherever
circumstances so require as under:
 The first stage will consist of formation cutting, slope stabilization, protection works and drainage
works. The second stage will include the WBM layers and bituminous surface course. The second
stage may be taken up after two rainy seasons have elapsed to ensure adequate stabilization of the
side slopes. The habitations concerned will not be counted as ‘connected’ till the second stage is
taken up.
 Where ‘unsealed’ surfaces are adequate in certain conditions like low traffic, the formation cutting,
slope stabilization and protection works, complete drainage works and appropriate surface course
treatment (to ensure all weather connectivity) will all be included in the first stage and work executed.

Operations Manual for Rural Roads


39
National Rural Roads Development Agency

In such cases, the habitations will be counted as ‘connected’ on completion of the first stage itself, as
there will be no second stage.
4.3.2 The maintenance component to be funded by the State Government out of its resources will also be
provided in the DPR. Annual Lump sum estimate will be made for the routine maintenance items specified in
the Rural Roads Manual. As such:-
 In case of link routes (new construction) the component shall comprise of 5 year routine maintenance.
 In case of associated rural Through Routes not requiring upgradation, the component shall include 5-year
routine maintenance including one renewal as per cycle.
 In case of Through Routes taken up for upgradation, 5-year routine maintenance and a renewal at the end
of the period.
The maintenance component is to be contracted out along with the new construction / upgradation, to the same
contractor. In case the Through Route is not a rural road, the same provision will apply to the Main Rural Links
(MRL) identified in the Core Network.
In respect of Hill roads, if construction is in 2 stages, the initial 5-year maintenance contracting will be done at
the time of contracting the work for the 2nd stage. Interim maintenance, clearance of slips etc., in the period
between the 1st and 2nd stage may be done departmentally.
4.3.3 The cost of preparing DPR, including investigation, survey and testing and trace cutting (in case of hill
areas) will form part of the project cost, and may be met from the funds in hand with the SRRDA subject to
future book adjustment on clearance of the proposal at such rates as may be prescribed by the Ministry /
NRRDA from time to time.
4.3.4 The detailed estimates will be based on the State Schedule of Rates (SSR) prepared using the Book of
Specifications and Standard Data Book published by IRC and prescribed by the NRRDA.
The State Schedule of Rates (SSR) shall be published annually and used for all rural roads. The Schedule may
be District or Circle specific.
4.3.5 As work commences on preparation of DPRs, the PIUs will conduct the Transect Walk (See Chapter 5),
and prepare necessary papers to obtain land, forest clearance etc. so that before road work is put to tender, the
land for the road is available.
It is the responsibility of the State Government/ District Panchayat to oversee that lands are available for taking
up the proposed road works. A certificate that Land is available must accompany the proposal for each road
work. It must be noted that the PMGSY does not provide funds for Land Acquisition. However, this does not
mean that acquisition cannot be done by the State Government at its own cost. The State Government may
also lay down guidelines for voluntary donation, exchange or other mechanisms to ensure availability of land.
The process of making land available for the road works should sub-serve the common good and also be just
and equitable. The details of land made available should be reflected in the local land records to avoid dispute.
As far as possible, voluntary donations should be documented through agreements, copy of which should be
forwarded to the local revenue officials for making necessary changes in the ownership/ possession record of
the land. Specimen of such an agreement is at Annexure 4.2 and 4.3. The States may adopt the appropriate
format.

4.4 ENTRY OF DPR DATA ON OMMS


After DPR has been prepared (See Chapter 5) based on soil survey to estimate CBR, and traffic expected (to
estimate Annual Average Daily Traffic or AADT), the essential data of the DPR is to be entered by the PIU after
logging into the Proposals module of OMMS. The following essential data has to be entered:
 Name of the road (selected from DRRP/Core Network) along with road and habitation data.
 The CBR, AADT values and the design curve being used as per Rural Roads Manual.

40 Operations Manual for Rural Roads


Annual Proposals and their Clearances

 The type of pavement, pavement and CD Costs.


 Year- wise 5 -year routine maintenance cost estimate etc.
 Road construction history and PCI values in case of upgradation of Through Routes.
The STA will scrutinize only such DPRs whose data have been correctly and completely entered in OMMS.
(See Chapter 7).

4.5 SCRUTINY BY STATE TECHNICAL AGENCY


The STA will scrutinize each DPR after checking that it has been entered in the proposals module of OMMS.
Detailed procedure for scrutiny is given in Chapter 7. After scrutiny, the STA will clear the DPR, make confirmatory
entries in the OMMS data for the DPRs and return the DPR documents duly certified and countersigned. In
case OMMS data is incomplete or changes are required as a result of the scrutiny, the STA will ask the PIU to
make the changes and verify that they have been made before countersigning the DPRs. The PIU will forward
the DPRs to the SRRDA after ensuring that the STA has made the confirmatory entry in the OMMS.
4.6 FORWARDING OF ANNUAL PROPOSALS
After scrutiny is complete, the SRRDA will intimate the NRRDA of its readiness to forward the proposals for
clearance of the Ministry under PMGSY.
The SRRDA shall send to NRRDA the following information along with the check list (Annex. 4.5) for the
purpose:
 Status of Core Network.
 Certificate for Maintenance by State Government.
 Status of Connectivity (District-wise).
 Status of ongoing PMGSY projects.
 Status of Quality Control Monitoring.
 Status of OMMS.
 Details of proposals for the current year.
 Cost of projects (Construction and Maintenance).
 Proceedings of the State Level Standing Committee clearing the proposals.
 Capacity and institutional readiness for the projects.
Annexure 4.4 gives the prescribed formats.

4.7 UPLOADING OF TENDER DOCUMENTS


After compilation of DPRs by PIU, the PIU will prepare the bidding document for every package as detailed in
Para 8.6. The above details will be filled up into the Draft Tender Document module of OMMS and draft bidding
document will be generated. As soon as the Ministry of Rural Development clearance is received and technical
sanction is accorded by the competent authority, the necessary input regarding dates and modifications in
respect of other items will be carried out by the PIU in the draft bidding document and the final bidding document
will be published on the website.
4.8 The NRRDA will review the status of readiness of the State Government and at the appropriate time shall
obtain the date and time from the Ministry for holding of a meeting of the Empowered Committee for the
purpose. For this purpose NRRDA shall forward the checklist (Annexure 4.5) with its Comments/
Recommendations regarding completion of the requisite formalities to the Ministry. The NRRDA will communicate
the schedule of meeting of the Empowered Committee to the State Government, at least 7 days in advance.

Operations Manual for Rural Roads


41
National Rural Roads Development Agency

The NRRDA shall at the same time prepare:


(i) A Technical brief for the Empowered Committee on the Proposals (covering design, estimates for
construction and maintenance and their reasonability).
(ii) A quality brief on, the Quality of on-going works.
(iii) An IT brief giving details of data on OMMS and their adequacy.
(iv) Financial Management brief, giving details of status of audit and accounts and use of accounting software
and
(v) Project brief giving status of ADB/World Bank related activities.
These briefs shall be submitted along with the proposals of the State for scrutiny in a Pre-Empowered Committee
Meeting chaired by the Director General, NRRDA and attended by representatives of the State Government.
4.9 In case all required documents are complete and there is no major capacity or institutional deficiency, and
data in OMMS has been found to be satisfactory, the proposal is placed before the Empowered Committee.
The Empowered Committee may recommend clearance of the proposals in accordance with the requirements
of the PMGSY guidelines.
The Ministry will communicate the clearance of the Proposals to the State Government with a copy to NRRDA
as well as to the STAs. The clearance letter will enclose package wise details of proposals cleared with details
of cost, length, habitations benefited etc. Clearance by the Ministry does not imply Administrative or Technical
sanction of the proposals. The well-established procedures of the Executing Agency/ies in this regard would
continue to be followed.
4.10 CLEARANCE OF PROJECT ON OMMS
Based on the clearance letter, NRRDA will log into the proposals module and make confirmatory entry clearing
the proposals into Project Mode, so that further data entry for tendering can be done by the PIU.

42 Operations Manual for Rural Roads


Annual Proposals and their Clearances (Annexures)

Annexure - 4.1
(See Para 4.2.4)
MP-I
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
Proposals received from MPs
(to be filled by PIUs on receipt)

Name of District: Year:

Name of MP: Constituency:

S. Name of Whether included Order of


No. Road Proposed in Core Network Priority

Total no of roads:
Total number of roads included in Core Network:

MP-II
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
Action on Proposals of MPs included in Core Network
(to be filled up by PIU after consideration by District Panchayat)

Name of District: Year:

Whether
# Name of MP Name of Road* Road Code Order of Priority Cost (Rs approved by Reasons,
Lakhs) District if not
Panchayat approved

* Extracted from MP-I in respect of roads in Core Network

Operations Manual for Rural Roads


43
44
MP-III

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)


Abstract of MP Proposals for year
(To be filled by SRRDA from MP-I & MP-II)
National Rural Roads Development Agency

No. of
Value of No. of No. in Core Value of Works Value Col (9) as Col (9) as
# Name of MP Name of District Proposals Proposals Network Work in approved approved percentage percentage
for District made by MP Col (6) (as in MP of Col (4) of Col (7)
(as in MP-I) II)

1 2 3 4 5 6 7 8 9 10 11

Operations Manual for Rural Roads


Total for MP :
Annual Proposals and their Clearances (Annexures)

Annexure 4.2
(See Para 4.3.5)

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)


MEMORANDUM OF UNDERSTANDING

This memorandum of understanding is made on day of


between Sri son of resident of
(hereinafter referred to as “the first party”)
and the Governor of (State) through Sri (designation)
(hereinafter referred to as “second party”).

THESE PRESENTS WITNESS AS FOLLOWS:


1. That the first party is landowner with transferable right acre of land
bearing khasra No. in village Block
, tehsil , district
.
2. That the first party hereby grants to the second party above said land for the construction and development
of PMGSY road in the village for the benefit of the villagers and the
public at large.
3. That the first party would not claim any compensation against the above said grant of land.
4. That the second party agrees to accept the above grant of land for the purposes mentioned in clause 2.
5. That the second party shall construct and develop the PMGSY road and take all possible precautions to
avoid damage to land adjacent to PMGSY road.
6. That the first party also assures the second party that the first party will not indulge in any willful act of
damaging it or obstructing the movement of public and vehicles on the PMGSY road.
7. That both the parties hereto agree that the PMGSY road so constructed/developed shall be public premises.
8. That the provisions of the MEMORANDUM OF UNDERSTANDING will come into force from the date of
signing of this deed.
IN WITNESS WHEREOF the parties hereto have signed this deed on the day and the year first above written.

Signature of the first party Signature for and on behalf of the second party
Witness:- Witnesses:-

1. 1.

2. 2.
(Signature, name and address) (Signature, name and address)

Operations Manual for Rural Roads


45
National Rural Roads Development Agency

Annexure 4.3
(See Para 4.3.5)

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)


Affidavit for land donation

I, wife / son / daughter of Sh. , resident of do


hereby solemnly affirm and declare as under:-

1. I am the landowner with transferable right of acre of land bearing khasra


No. in village block ,
tehsil , and district .
2. That under the PRADHAN MANTRI GRAM SADAK YOJANA a road is to be constructed, which will be of
benefit to all residents of the area. Accordingly, I hereby agree to donate a portion of land, … m long for a
width of ….. m (as delineated in the sketch appended to this affidavit by the letters ABCDEF) absolutely
and forever.
3. I hereby grant the above said portion of the land for the construction and development of PRADHAN
MANTRI GRAM SADAK YOJANA road in the village for the
benefit of the villagers and the public at large to Government of (State).
4. I/my successors would not claim any compensation against the above said portion of land.
5. I hereto agree that the PRADHAN MANTRI GRAM SADAK YOJANA road so constructed/developed shall
be public premises.
6. I hereby commit that this affidavit shall be valid strictly only to the extent of land specified in the affidavit
and shall not spillover into the residual holding. In the event of any violation of the same or any damages
to structure/assets outside the said portion during the project implementation, the liability towards payment
for damages shall be of the DoRD, Government of (State).

PLACE : DEPONENT
DATED :

I affirm that the contents of the above affidavit are true and correct to the best of my knowledge and belief and
nothing has been concealed therein.

PLACE : DEPONENT
DATED :

46 Operations Manual for Rural Roads


Annual Proposals and their Clearances (Annexures)

Annexure: 4.4
(See Para 4.6)

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)


BRIEF FOR THE EMPOWERED COMMITTEE

Name of the State :


Part I - Institutional

1 Name of the Nodal Department :

2. Name of the Executing Agency(ies):

3. a) Name of the State Level Autonomous


Agency & Date of Registration

b) Name & Designation of CEO

4. Name & Designation of main SRRDA


functionaries

a) Chief Engineer

b) Financial Controller

c) Empowered Officer

d) State Quality Coordinator

e) IT Nodal Officer

5 Bank Account with

a) Program Account A / C No

b) Administrative Account A / C No

c) Maintenance Account A / C No

Year UC AR
d) Status of Utilization Certificates (UC)
e) Audit Report (AR)
6 a) Date of approval of Core network

b) whether DRRP entered in OMMS

Maintenance

a) Mechanism for overseeing maintenance

Year Budget Exp Of which


Exp. On
PMGSY
b) Maintenance budget & expenditure for Roads
Rural Roads

Operations Manual for Rural Roads


47
National Rural Roads Development Agency

Part II – Progress under PMGSY

1. Status of Connectivity
1000+ 500-999 250-499 Less Total
than 250
Total number of Habitations
Total number of Connected
Habitations (as on 25-12-2000)
Total number of Unconnected
Habitations (as on 25-12-2000)
Coverage of Habitations
2000-01 (Phase I)
2001-03 (Phase II)
2003-04 (Phase III)
2004-05 (Phase IV)
Under other Programs
Balance Unconnected Habitations

2. PMGSY 2000-01 & Subseqent Years:

2000-01 2001-03 2003-04 2004-05 2005-06


Allocation (Rs. in crore)
Value of projects cleared (Rs. in crore)
Amount released (Rs. in crore)
BMS Works (Rs. in crore)
Total No. of road works
Total length of road works
Total No. of Habitations benefited
Cost (Rs. in crore)
No. of road works
New Length (km)
Connectivity Number of Habitations
covered
Cost (Rs. in crore)
No. of road works
Upgradation Length (km)
Number of Habitations
covered
Progress
Total Expenditure upto (Date)
Total No. of road works completed
Total Length of roadworks completed
Total No. of Habitations benefited
Likely date of completion
Expenditure upto
(Rs. in crore)
No. of road works completed
New
Length of road works
Connectivity
completed (km)
Number of Habitations
benefited
Expenditure upto
(Rs. in crore)
No. of road works completed
Upgradation
Length of road works
completed (km)
Number of Habitations benefited

48 Operations Manual for Rural Roads


Annual Proposals and their Clearances (Annexures)

 It may be ensured that the information given in the website tallies with the information above at Sl.No. 1 & 2.
3.a) Quality Control Monitoring by 2nd tier State Level Quality Control Agency (SQC):

Sl. Name of Total No. of Total No. (& Quality Grading No & (%)
No. District road works %) of Road Complete In Progress
in the district works
inspected by P A G VG Total P A G VG Total
SQC

Total

Note: P – Poor. A – Average. G – Good. VG – Very Good.

ii) Details of State level Quality Control Mechanism


iii) Status of District Labs
iv) Action on NQM Reports
- No. of reports received
- No. of reports on which action taken
- No of cases of action pending with Contractor (with details of penalty)

4. OMMS Data entry (as on )

Item Actual As entered in OMMS

5. Training:

Year No of Trained Contractor


JE AE EE / SE Personnel

Operations Manual for Rural Roads


49
National Rural Roads Development Agency

Part III Current Proposals

1. Details of Proposals :
Year ( )
Allocation (Rs. in crore)
Value of projects proposed (Rs. in crore)
Total No. of road works
Total length of road works
Total No. of Habitations benefited
Cost (Rs. in crore)
No. of road works
New Connectivity
Length (km)
Works
Number of Habitations covered
Average cost per km
Cost (Rs. in crore)
No. of road works
Upgradation Length (km)
Number of Habitations covered
Average cost per km
Year Estimated Cost (Rs. in Lakhs) % of Construction Cost
st
1 Year
2nd Year
Maintenance 3rd Year
4th Year
5th Year
Total

2. Special Cases [Roadworks included in S No. 1 above] :

a) Cement Concrete Roads :

Sl. Name of No. of road Length of Cost (Rs. Average cost


No. District works road works in lakh) (per km)
(in km)

Total

b) Modified Bitumen Roads:

Sl. Name of No. of road Length of Cost (Rs. Average cost


No. District works road works in lakh) (per km)
(in km)

Total

50 Operations Manual for Rural Roads


Annual Proposals and their Clearances (Annexures)

c) Gravel Roads :

Sl. Name of No. of road Length of Cost (Rs. Average cost


No. District works road works in lakh) (per km)
(in km)

Total

d) Lime / Cement Stabilized Roads :

Sl. Name of No. of road Length of Cost (Rs. Average cost


No. District works road works in lakh) (per km)
(in km)

Total

e) Fly Ash Stabilized Roads :

Sl. Name of No. of road Length of Cost (Rs. Average cost


No. District works road works in lakh) (per km)
(in km)

Total

f) Any others (please specify) :

Sl. Name of No. of road Length of Cost (Rs. Average cost


No. District works road works in lakh) (per km)
(in km)

Total

Operations Manual for Rural Roads


51
National Rural Roads Development Agency

3. District-wise summary of proposals attached (Format enclosed - Annexure 7.2)

4. Details of MPs Proposals: (MP-I and MP-II enclosed)

Based on MP-III Totals :

Name of MP Road works taken % of value to


on recommendation total Value
No Value

Total :

Signature
Secretary
Nodal Department

52 Operations Manual for Rural Roads


Annual Proposals and their Clearances (Annexures)

Annexure 4.5
(See Para 4.6 & 4.8)

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)


CHECK LIST FOR DATE FOR EMPOWERED COMMITTEE

State Phase

Annual Allocation Value of proposals

1. Core Network ready Yes No

2. Whether DRRP data entered in OMMS Yes No

3. CNCP/CUP list used Yes No

4. (a) Whether proposals approved by District Panchayat Yes No

(b) Whether proceedings of SLSC attached Yes No

5 DPRs scrutinised and entered in OMMS Yes No

6 If upgradation included, whether PCI register Completed Yes No

7 Whether designed for unsealed surface for roads Yes No


below 1000 population

8 MP I, II and III received Yes No

9 5-year maintenance lump sum estimates given year-wise Yes No

10 (a) Whether estimates prepared using latest SSR for Rural Roads Yes No
(b) Date of SSR:

11 DPR clearance Okayed in OMMS by STA Yes No

12 Whether Draft Tender Document uploaded in proposals module Yes No

13 Whether capacity currently exists to take up the works Yes No


(Please give status of on-going works)

14 Whether IPAI Accounts system adopted Yes No

15 For Border /LWE areas: Whether recommended by MHA Yes No

Operations Manual for Rural Roads


53
National Rural Roads Development Agency

16 In case of ADB/WB proposals

(a) Value of proposals in relation to approved size of batch Yes No

(b) Whether ECoP etc. applied Yes No

(c) Whether sub-projects cleared by TE/PIC &STA Yes No

17. Remarks:

CE, SRRDA

18. Comments/Recommendation of Director (Technical) NRRDA

54 Operations Manual for Rural Roads


Design

CHAPTER 5
DESIGN

5.1 ROUTE SELECTION AND ALIGNMENT


The District Rural Roads Plan gives guidance on the general topology of the network of rural roads required to
connect all eligible rural habitations. This will have to be translated on to the ground in the form of properly
aligned road links.
The IRC: SP 20:2002, Rural Roads Manual gives detailed guidance on selection of the alignment. The following
supplementary points need to be kept in mind at the time of alignment definition: -
 In order to minimise/ avoid land acquisition, the alignment should follow existing cart tracks and footpaths
to the maximum extent possible, subject to considerations of geometrics and hydrology.
 It is always useful to consider 2 or 3 possible route alignments and evaluate each alternative for the
construction costs to be incurred and related benefits accrued, before finalising an alignment. By adopting
such an approach, many unfavourable features can be avoided like long length covered by problematic
soils (e.g., Black Cotton soils), too many cross-drainage works, high cost bridges, landslide susceptible
slopes on hill roads etc. Similarly, the ease with which the desired geometric design standards can be
attained may vary from one alternative to another alternative.

5.2 GEOMETRIC DESIGN STANDARDS


The IRC Rural Roads Manual gives the geometric design standards to be followed. Particular attention is
required in adopting the Carriageway Width (CW) based on traffic volume considerations. Once the CW is
fixed, compatible Roadway (RW) and Road Land Width (RLW) will have to be provided. Where traffic is likely to
be very low as in short roads terminating in dead ends, and is not likely to increase substantially in future, a
carriage way of 3.0 m may be designed instead of the normal 3.75 m.

5.3 TOPOGRAPHICAL AND RELATED GROUND SURVEYS


The recommended ground survey technique comprises of three sequential stages viz (i) Reconnaissance (ii)
Preliminary Survey and (iii) Final Location Surveys.
5.3.1 Reconnaissance starts with a field inspection by walking, riding on ponies (in hills) or driving in jeeps. All
information of value, either in design, construction, maintenance or operation of the facility should be collected,
which may include, inter alia, the following:
 Details of route vis-à-vis topography of the area – plain, rolling or hilly.
 Requirements of cross-drainage works – type, number and length.
 Gradients that are feasible, specifying the extent of deviations needed.
 Curves and hair-pin bends etc.
 Existing means of communication – mule tracks, jeep tracks, cart tracks etc.
 Constraints on account of built-up areas, monuments and other structures.
 Road length passing through different terrains, areas subjected to inundation and flooding, areas of poor
drainage conditions, unstable slopes etc.

Operations Manual for Rural Roads


55
National Rural Roads Development Agency

 Climatic conditions – temperature, rainfall, water table and its fluctuations etc.
 Facilities/ Resources available e.g., availability of local labour, contractors etc.
 Access points indicating possibility of induction of equipment.
 Period required for construction.
 Villages, hamlets and market centres connected.
 Economic factors – population served, agricultural and economic potential of the area.
 Crossing with railway lines and other existing roads.
 Position of ancient monuments, burial grounds, cremation grounds, religious structures, hospitals and
schools etc.
 Ecology or environmental factors.
Only simple instruments like Compass, Abney level, Altimeter, Clinometer, Ghat tracer etc are required in the
Reconnaissance survey.
5.3.2 Preliminary survey is a relatively large-scale investigation of the alternative(s) thrown up as a result of
the Reconnaissance survey. The survey consists in establishing a base-line traverse. For hill roads, it may be
necessary to cut a trace of 1.0-1.2m wide to enable the traverse survey to be carried out. A theodolite or
compass is used for traversing and levels are taken along the traverse and across it. The distances are measured
continuously along the traverse line with a metallic tape. Bench marks should be established at intervals of 250
m to 500 m and the level should be connected to the GTS datum. Physical features such as buildings, trees,
burial grounds, monuments, railway lines, canals, drainage channels etc should be located by means of offsets.
The width to be covered for such detailing should be about the land width proposed to be acquired. Information
on highest flood level, rainfall intensity, catchment areas of streams etc should be collected. The survey enables
the preparation of a map including the plan and longitudinal section. The scales generally recommended are:
 Built-up areas and hilly terrain : 1:1000 for horizontal scale
1:100 for vertical scale
 Plain and rolling terrain : 1:2500 for horizontal scale
1:250 for vertical scale
It is desirable to mark the contour intervals at an interval of 1 to 3m. The map should show all the physical
features surveyed.
5.3.3 At the end of the preliminary survey, it is useful to involve the local community in the process of deciding
on the alignment since several social issues are also involved. As such the JE/AE must conduct a Transect
walk along the alignment /trace together with the Panchayat Pradhan/ Ward Panch, local revenue and forest
officials. For the purpose, the following steps are suggested:-
 The AE/JE may intimate the Gram Panchayat Secretary as soon as the preliminary survey operations
start so that the Panchayat gives it due publicity.
 Date and time for the transect walk may be decided by the AE in consultation with the Pradhan of the
Panchayat/Ward Panch and may be put up by the Panchayat as a public notice. The AE will intimate the
local revenue official (Patwari) and local forest official (Ranger) and the Secretary of the Panchayat.
 The Transect Walk will be conducted by the AE/JE along with the contour map of the proposed
alignment (s). The Patwari will identify all the plot numbers (Khasra No) and distinguish between Government
/Public land and Private land. All lands likely to involve Forest (Conservation) Act and other regulatory
forest enactments shall be identified in consultation with the Ranger. Where Private land is required, it
shall be procured in a manner that is just and equitable and best subserves the common good. The local
Panchayat may be involved in the process.

56 Operations Manual for Rural Roads


Design

 If possible, borrow areas and areas likely to require protection/treatment shall be identified. Areas suitable
for road side plantation by the Panchayat may also be similarly identified.
 Local people including those likely to be affected by the proposed alignment may be given opportunity to
put forth their views. Issues relating to cattle crossings, irrigation field channels, integration of inter-village
and field paths with the alignment, road safety, drainage measures to prevent damage to agricultural fields
and dwellings will all be discussed.
 The proceedings of the Transect Walk reflecting all of the above will be drawn up by the AE/JE and
countersigned by the Panchayat Secretary. A list of Plot Numbers involved along with area and ownership/
possession status shall be provided by the Patwari and appended to the proceedings.
5.3.4 Final Location Survey: - After the preliminary survey and Transect Walk, the final alignment is to be
determined. The purpose of the final location survey is to fix the centreline of the selected alignment in the field
and to collect additional data for the preparation of the drawings. The centreline is translated on the ground by
continuous transverse survey and pegging the same. The points of transit (POT) should be clearly marked on
the ground by a nail in the existing pavement or a hub in concrete on a new alignment. Suitable references (at
least two) should be marked permanently on the ground. The horizontal intersection points (HIP) should be
similarly marked on the ground and referenced. All curve points viz beginning of transition (BS), beginning of
circular curve (BC), end of circular curve (EC) and end of transition (ES) should be marked and referenced. The
centreline should be staked at 50 m intervals in plain terrain and 20m intervals in hilly terrain. Bench marks
should be left permanently at 250 m intervals. The cross-sections taken during the preliminary survey should
be supplemented by additional cross-sections at the curve points. Generally, cross-sections should be available
at intervals of 50-100m in plain terrain, 50-75m in rolling and 20 m in hilly terrain. Survey can be accomplished
these days by a Total Station, with assistance from GPS (Geographic Positioning System) which determines
the location of survey points by satellite. But in the absence of these instruments, an ordinary theodolite,
levelling instrument and compass would be acceptable.

5.4 SOIL SURVEY AND MATERIALS


The IRC Rural Roads Manual SP: 20 contains instructions on Soil Survey and materials for the road projects.
Supplementary guidance on these subjects is given in Annexure 5.1.
The identification of the soil type in the field and the quick determination of its properties , including CBR are the
basic requirement for an economical pavement design. The grain-size (wet sieve) analysis leading to the soil
classification is a simple test and must be carried out to have an idea of the CBR value with a reasonable level
of accuracy, the nomograph given in Annexure 5.2 can be used. This would minimise the need for CBR
determination in lab. The determination of CBR by a rigorous CBR apparatus on a large number of samples
may not be possible unless properly planned, and hence the Nomograph given in Annexure 5.2 may be used.

5.5 CROSS-DRAINAGE STRUCTURES


The Rural Roads Manual contains instructions on the suitability of various types of cross-drainage structures.
Generally, the provisions of the Rural Roads Manual are adequate for CD Structures for Rural Roads. However,
when special CD Works are needed due to location specific conditions, such CD Structures are to be designed
after appropriate exploratory investigations. In such cases, a separate DPR is to be prepared for the CD Works
as a part of the main DPR for the sub project proposal.

5.6 TRAFFIC SURVEY


A traffic survey is needed for existing roads that are proposed for upgradation in order to estimate the extent of
pavement strengthening. Such surveys may also be useful in prioritising maintenance activities The purpose of
the traffic survey is to establish the Average Annual Daily Traffic (AADT). Traffic is likely to be the highest in the
post-harvest season. But the survey cannot always wait till the post-harvest season, and has to be taken up
immediately after a particular project is identified for being included in that year’s programme. If the traffic
survey is done in a lean season, local enquiry should be done to ascertain the post-harvest traffic, particularly

Operations Manual for Rural Roads


57
National Rural Roads Development Agency

of agricultural tractor-trailers, LCVs and trucks, and necessary adjustments for traffic are to be made for seasonal
variation.
Since rural roads have hardly any traffic during night time, a 16-hour (say 5 AM to 9 PM) 3-day classified
volume count is sufficient. Hourly count is not of importance and a daily total is adequate. The standard proforma
is given in Annexure 5.3(a&b). The output of this survey is the base year traffic.
Based on the historical data or by elasticity method, the Growth rate is arrived at and using this Growth rate, the
base year traffic is projected to obtain the design traffic for the horizon year. Normally a 10 year design life is
considered for Traffic Projections.
For new roads, which give access to unconnected villages, it is not possible to carry out an actual traffic survey
for the road. But, the traffic likely to use the facility can be taken from the traffic counts on newly constructed
roads of similar conditions. As an approximation, the following categories may be generally adopted:
Traffic (Average Annual Daily Traffic-AADT) projected over 10 years
 New link roads taking off from existing roads. Less than 150
 New through roads directly leading to Market centres. 150-500
The AADT above signifies the Average Annual Daily Traffic consisting of all motorised and non-motorised
vehicles, including two-wheelers. For pavement design, only commercial vehicles need to be considered. These
form generally 10-15 percent of the ADT. Accordingly, the link roads proposed for new connectivity shall be
designed for A Curve (0-15 CVPD) and in certain cases B Curve (15-45 CVPD). In case of new through routes,
the design will be normally done with B Curve (15-45 CVPD). Only in exceptional cases would the design traffic
be of Curve C (45-150 CVPD). Each such case needs to be substantiated with reasons. In estimating the base
year traffic due care is to be taken in adjusting the traffic for seasonal variations with the use of suitable
adjustment factors.
As part of the database for each rural road, a traffic count needs to be carried out atleast once in 2 years and
the traffic data updated for each road in the OMMS.

5.7 USE OF LOCAL MATERIALS


Recognising that the low volume rural roads are essentially low cost roads, the specifications for pavement
materials in various layers should be as economical as possible, consistent with the traffic expected to use the
road, the climatic conditions etc. From this angle, local materials which are cheaper to extract and involve
minimum haulage cost should be used to the maximum extent feasible. A variety of local materials can be
used which may be grouped under the following categories.
 Better granular soil for use on improved subgrade/ sub-base or as surfacing for earth roads.
 Mechanical stabilisation of local soil with blending of different materials; stabilisation with lime, cement,
lime and flyash, as appropriate.
 Naturally occurring low grade marginal materials like moorum, kankar, gravel etc.
 Brick and over burnt brick metal.
 Hard stone aggregates.
Past experience gained from long-term performance of test tracks in India on the use of local materials shows
that for the same pavement thickness, the use of local materials in lieu of the conventional hard stone aggregates
can bring about savings to the tune of 25% of conventional construction costs. In situations where hard stone
aggregates have to be carted from long distances of the order of 200 km, the maximised use of local materials
can bring about savings in material costs to the extent of even 40% of the conventional material costs. Some of
the more important points in the use of these materials are discussed in Annexure 5.4.
In most of the regions where black-cotton soil is predominant (parts of Karnataka, Andhra Pradesh, Maharastra,
Gujarat, Madhya Pradesh and Chhattisgarh), it is very economical to stabilise the soil by adding lime, and such

58 Operations Manual for Rural Roads


Design

layers can be used as sub-base courses. For base courses, further addition of a small quantity of cement/ fly
ash could be beneficial. The same treatment can be applied to areas with clayey soil in the delta regions of
Orissa and West Bengal. For the silty soils of the Gangetic plains, cement stabilisation can be a good alternative
to the costly stone aggregates courses in the sub-base and base courses.
Flyash can replace upto 50 percent of cement in concrete roads, which then become viable alternative to
flexible pavement, particularly in areas where stone aggregates are costly and soils are poor. Fly-ash shall also
be used in the body of the embankment provided it is possible to provide a cover of soil at least 1000 mm thick
on the slopes and 500mm below the bottom layer of pavement. Lime-flyash stabilised courses can be used as
subgrade and sub-bases.
5.8 ROADSIDE SHOULDERS
Adequately designed shoulders should be provided on rural roads. In case soft soils are used for embankment,
hard shoulders of 1 m width shall be provided on either side. Where availability of land is not a constraint, extra
width of shoulders can be provided near bus stops and to provide platforms for storing material during
maintenance.
5.9 DRAINAGE
One of the very important reasons for a very rapid loss in the level of serviceability of most of the rural roads in
the country is the lack of attention to appropriate drainage. It is basically due to the lack of proper drainage that
the maintenance requirements of a rural road rise rapidly even during the early years of its service life. The
modern trend is to incorporate maintenance considerations at the design stage itself. Ensuring proper drainage
during the design life is considered one of the most essential pre-requisites for a satisfactory performance of
the road during its service life.
Provision of adequate drainage should be considered more of an investment than an expenditure, since it
yields benefits by way of more economical designs and much reduced subsequent maintenance costs.
It is mandatory under PMGSY to have a drainage plan prepared for each rural road project. Annexure 5.5 gives
guidelines for achieving good drainage of Rural Roads. The following points must be taken into the design of
Rural Roads:
 Provide the specified camber both for the carriageway and the shoulder. Shoulders should never be
allowed to be higher than the pavement.
 Roadside drains, with proper longitudinal slopes leading the water to cross drains and hence to a natural
water course, must be provided.
 When the road passes through a village, keep the road level high, with side drains on both sides to ensure
proper drainage and to prevent water from entering dwellings. The drains should be open L Shaped drains
or U shaped depending upon site conditions.
 In hill roads, provide lined (dry stone lining) side drains to avoid scour, as well as interceptor drains (catch
water drains).
 Integration of cross-drainage and longitudinal drainage is essential in the project.
 Hydrological design of waterway considering afflux, scour due to restricted water way is essential. High
afflux causes flooding of up-stream and excessive scour on the downstream.
 Water balancing culverts (average 2 Km per Km) needs to be provided in areas which do not have a well
defined water channel to drain out rain water.
5.10 PAVEMENT CRUST DESIGN
5.10.1 Design Methodology for New Connectivity Roads: The design of the crust thickness for new
connectivity roads is as suggested in the Rural Roads Manual IRC SP:20:2002. Special care is to be taken
while assessing the design parameters, namely the CBR of subgrade soil and projected traffic for the design
life period in terms of CVPD.

Operations Manual for Rural Roads


59
National Rural Roads Development Agency

When Local materials are used with or without stabilization, material characterization is required for determining
the thickness of the layers used in the design.
The choice of surface for the road would be determined by traffic density and rainfall, as per the Rural Roads
Manual. In the case of new construction for eligible habitations of population below 1000, where traffic expected
is likely to remain low, in the interest of economy the road would generally be designed as Gravel road or other
Unsealed surfaces provided in Rural Roads Manual subject to considerations of rainfall. In case of roads
leading to habitations below 500 (where eligible) where the projected traffic is likely to be very low, the carriageway
may further be restricted to 3 m.
5.10.2 Design methodology for Upgradation roads: The Upgradation of the existing roads include
strengthening the crust with an overlay, Geometric improvements and improvements in surface drainage or
additions of CD Works, where necessary. The data needed on an existing road proposed to be upgraded
should include:
 Pavement condition as explained in the Chapter 14 dealing with Rural Roads Maintenance.
 Shoulder condition and Shoulder width or combined pavement and shoulder condition, as explained in the
Section dealing with Rural Road Maintenance.
 Pavement design of the existing road.
 Geometric design of existing road.
 Existing surface and cross drainage.
 Materials and soil properties.
 Climatic conditions.
 Traffic studies.
 Safety considerations.
 Age of the road with records of routine maintenance and periodic surface renewals.
5.10.3 Pavement Design: The suggested methodology for design of Pavements for Upgradation is as given
below:
(i) Determine the field moisture content and the field density, after the rains, at a distance of 0.6m to 1 m from
the pavement edge, below the pavement crust. Collect a representative subgrade soil sample for laboratory
tests.
(ii) The field moisture content and field density determinations as at (i) above must be carried out at a number
of locations, not less than 3 per Km length of the road if the same type of soil and drainage conditions
prevail. For different types of soils and for different sets of drainage conditions, the number of field tests
must be suitably increased.
(iii) Prepare laboratory CBR samples of subgrade soil conforming to the density and moisture content
determined from field tests as described at (i) and (ii) above, for each of the locations selected for the
tests.
(iv) Determine the CBR value of subgrade soil for each location selected for field tests as at (i) and (ii) above.
(v) Evaluate the Traffic parameter by carrying out 24 hour field traffic counts during the lean season and
during the harvesting seasons, finally arriving at the Commercial Vehicles per Day (CVPD). A suitable rate
of growth of traffic can be selected depending on the economic potential of the area but bearing in mind
that in most cases traffic levels would have plateaued.
(vi) For each of the subgrade CBR values at (iv) above, determine the pavement thickness requirement
corresponding to the traffic parameter evaluated as at (v) above. Let the pavement thickness requirements
at each of the locations 1,2,3…….(at different chainages) applicable in the corresponding lengths be T1,
T2, T3——

60 Operations Manual for Rural Roads


Design

(vii) Determine the thickness of the pavement in the existing road at each of the above locations of the field
tests 1,2,3…….Let these be t1, t2, t3 ———. Also examine the thickness and quality of subbase and base
materials in the existing pavement.
(viii) The amount of strengthening / overlay thickness required is thus T1-t1; T2-t2; T3-t3; ——. The type of material
in the layers for the overlay will depend on the residual subbase and base materials used in the existing
pavement and will be adopted in the corresponding lengths of the road.
5.10.4 Geometric Design: There may be geometric deficiencies in the alignment, either horizontally or vertically.
These would have to be seen on a case-by-case basis depending on the severity of the problem, road safety
implications, availability of land etc.
Upgradation may require widening of the carriageway to 3.75 m in case the earlier width was less. This will also
require corresponding road way width of 7.5 m and land width of 11-12 m. While formation width may not
always be available it must be ensured that in all upgradation cases roadway width of 7.5 m is available (except
in habitation portion). The design of the pavement must take into account the difference in the over lay crust
thickness over the existing pavement and in the widened portion. Due to changes in centre line etc. appropriate
changes in the surface profile and camber will also have to be designed, where necessary.
5.10.5 Drainage: It is possible that the road to be upgraded may suffer from inadequate side drains or lack of
integration of the drains with the cross drainage. In adequate cross drainage (in terms of number of CDs, their
proper siting or their capacity) may also need to be addressed. Inspection of the road will generally reveal the
nature of the deficiency and necessary hydrological investigations may be made in the case of CD Works.

5.11 SOME IMPORTANT ISSUES IN THE DESIGN


5.11.1 Geometric Design-
It has been indicated that the geometric standards for Rural Roads are to be as given in IRC SP 20:2002.
However, practical difficulties sometimes normally arise in providing the recommended geometrics due to non-
availability of land, with no scope even for acquisition. In such cases, efforts must be made to provide the
geometrics within the land available by shifting the centre line to the extent possible. If even after this, Standard
Geometrics like Radius of Curvature, gradient etc. cannot be provided for the normal design speed, the geometrics
are to be designed as per the ground conditions and the corresponding safe speed determined. Appropriate
signboards must be erected on either side indicating the safe speed at which the vehicles can travel in such
stretches. In addition at accident prone locations, speed reducing devices such as rumble strip should be
provided.
5.11.2 Pavement Design-
 The estimation of design parameters is the most important issue in the design of pavement. It has been
noticed quite often that there is a tendency to estimate the design CBR on the conservative side and also
to inflate the amount of traffic expected. The combined effect of this is over design of the pavement, which
in turn is reflected in higher costs of construction. This engineering skill of the PIU lies in ensuring quality
with economy. Not only must CBR be estimated properly, the conditions in which it is to be estimated also
need to be consciously determined. It is always not necessary to adopt 4 day soaked CBR for design,
since this represents the worst condition of design. Depending upon the pattern of conditions prevailing at
the site, the CBR may be determined at the equilibrium moisture content (Annexure 5.6) in cases where
the sub grade is not likely to come in contact with water either due to capillarity or through percolation from
the top. Similarly, the estimation of base year traffic should be done judiciously taking guidance from the
recently constructed roads in similar conditions. The traffic must have some correlation with the agricultural
surplus of the area and its expected growth rate.
 When marginal aggregates and locally available material are used, special care should be taken in material
characterization. While adopting a particular method of stabilization, the efficacy of use of the most suitable
stabilizing agent is to be established and accordingly used in the design. Detailed specifications are available
for various methods of stabilization in the publication ‘Specification for Rural Roads’ published by the IRC.

Operations Manual for Rural Roads


61
National Rural Roads Development Agency

 In the conditions where the lead distance for bringing the aggregates is high, alternative methods of
aggregate free construction or limited use of aggregates shall be explored.
5.11.3 Design of CD Structures-
 The proper location of the CD works and their design with proper estimation of expected discharge from
the catchments is extremely important. The type of CD Structure is to be decided based on the site
conditions. Type designs sometimes may lead to problems at a later stage. Therefore, care must be taken
in the location of CD Works, estimation of discharge and designing appropriate CD Structure.
 The possibilities of adopting causeways need to be fully explored where minor /major bridges are proposed,
for cost effectiveness.

62 Operations Manual for Rural Roads


Design (Annexures)

Annexure 5.1
(See para 5.4)

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)

SOIL SURVEY

1. The Need
For the construction and maintenance of low cost rural roads catering to relatively low volumes of traffic, local
soil is not only the cheapest but also the highly versatile road material which can be used directly or after
suitable processing or by modification or stabilisation by additives. It is, therefore, necessary that the needed
field and laboratory investigations are carried out to scientifically evaluate the engineering properties of the
various types of soils encountered adjacent to the centreline of the alignment. These investigations are needed
for the evaluation of the strength of subgrade soil(s) for pavement design and to determine the type of processing
that may be necessary for its use in a pavement layer. It is to be recognised that the procedures for both the
field and laboratory investigations should be simple enough as would be practicable within the available resources
and skills in rural areas. Available information on soil types of an area in the form of soil maps (Refer Map given
in IRC : SP-20 : 2002) is often helpful.
2. Field Investigations
In order to evaluate the types of subgrade soils, field investigations should be carried out along the alignment
so as to collect representative soil samples wherever there is a visible change in the soil type. Even if the same
soil type continues, at least 2 representative samples should be collected from each kilometre length of road
alignment. In its simplest form, the method of collecting soil samples consists in digging a pit about 1mx1mx1m.
Within this pit, it should be possible to determine the depth of topsoil and the soil type(s) underneath. Generally,
it is possible to get acceptable quality of soils within about 0.6m depth below the ground level, which can be
used in the subgrade and even in subbase/base courses. It is necessary to collect representative soil samples
for the different soil strata as visible from the test pit. Ordinarily, the depth of the pit should not be more than 1m
and must not exceed 1.5m since the depth of borrow pits normally would be limited to 1.5m. It is often expedient
to use a post hole/helical auger (Fig. 1) with or without the digging of pit to a certain depth. It must be ensured
that the samples collected are representative of soils to be evaluated. Samples of adequate size (2 to 5kg for
gradation and plasticity tests; 20kg where detailed strength tests like CBR are to be carried out). All samples
should be collected in sample bags on which the location, depth of strata etc should be tagged.

Fig. 1: Hand-Operated Augers (A) Helical Auger (B) Post-Hole Auger

Operations Manual for Rural Roads


63
National Rural Roads Development Agency

3. Visual Classification
In order to identify the broad soil types in the field without any laboratory testing, a visual classification is
recommended. The following are the categories of soils visually categorized (Fig. 2).
Gravels : These are coarse materials with particle size over 2.36 mm. These may have little or
no fines contributing to cohesion of the material.
Moorums : These are distinctly different materials from gravels and are products of decomposition
and weathering of the parent rock. The properties of these materials naturally depend
on the parent rock and the process of weathering and decomposition. Visually they
look like gravels except for the difference that the percent fines is relatively much
higher.
Sands : These vary in texture from coarse to fine but exhibit no cohesion. They allow water to
permeate readily through them.
Silts : These are finer than sands in texture; lighter in colour compared to clays and exhibit
little cohesion. Dilatancy is a specific property of silts. When a lump of silty soil mixed
with water is alternatively squeezed and tapped, a shiny surface makes its appearance
(Fig. 3).
Clays : These are finer than silts and are the ultimate product of weathering and decomposition
of parent rock. Clay and clayey soils exhibit stickiness, high strength when dry and
show no dilatancy. Black cotton soils and other expansive types of clays exhibit swelling
and shrinkage and are characterised by a typical shrinkage pattern. A paste of clay
with water when rubbed in between fingers leaves a stain which is not observed for
silts (Fig. 4).

FIG. 2 : VISUAL CLASSIFICATION OF SOILS AND GRAVELS (TOP-LEFT TO RIGHT) CLAY, SILT AND SAND.
(BOTTOM-LEFT TO RIGHT) MOORUM WITH EXCESSIVE FINES, MOORUM AND GRAVEL

64 Operations Manual for Rural Roads


Design (Annexures)

FIG. 3 : DILATANCY TEST FOR SILTY SOILS

FIG. 4 : HAND-FEEL ‘STAIN’ METHOD FOR TESTING CLAYEY SOILS

The field procedure for visually identifying the soils as per the Unified Soil Classification System developed in
the USA and adopted in India with slight modifications, is outlined in Table 1. The various symbols in this
classification system are :
G : Gravels; S : Sands; M : Silts; C : Clays; O : Organic Soils; Pt : Peat; W : Well-graded; P : Poorly Graded; L
: Low Compressibility; H : High Compressibility.
The three field identification procedures for fine grained soils or fractions are described below. Before carrying
out any of these tests, remove by hand the coarse particles that interfere with the tests.
(1) Dilatancy (Reaction to shaking):
After removing particles larger than 380 mm sieve size, prepare a pat of moist soil with a volume of about
8000mm3. Add enough water if necessary to make the soil soft but not sticky.
Place the pat in the open palm of one hand and shake horizontally, striking vigorously against the other
hand several times. A positive reaction consists of the appearance of water on the surface of the pat which
changes to a livery consistency and becomes glossy. When the sample is squeezed between the fingers,
the water and gloss disappear from the surface, the pat stiffens and finally it cracks or crumbles. The
rapidity of appearance assists in identifying the character of the fines in a soil.
Very fine clean sands give the quickest and most distinct reaction whereas a plastic clay has no reaction.
Inorganic silts, such as a typical rock flour, show a moderately quick reaction.

Operations Manual for Rural Roads


65
National Rural Roads Development Agency

(2) Dry Strength (Crushing characteristics):


After removing particles larger than 380 mm sieve size, mould a pat of soil to the consistency of putty,
adding water if necessary. Allow the pat to dry completely by oven, sun or air drying, and then test its
strength by breaking and crumbling between the fingers. This strength is a measure of the character and
quantity of the colloidal fraction contained in the soil. The dry strength increases with increasing plasticity.
High dry strength is characteristic for clays of the CH group. A typical inorganic silt possesses only very
slight dry strength. Silty fine sands and silts have about the same slight dry strength, but can be distinguished
by the feel when powdering the dried specimen. Fine sand feels gritty whereas a typical silt has the
smooth feel of flour.
(3) Toughness (Consistency near plastic limit):
After removing particles larger than the 380m m sieve size, a specimen of soil about 12mm cube in size,
is moulded to the consistency of putty. If too dry, water must be added and if sticky, the specimen should
be spread out in a thin layer and allowed to lose some moisture by evaporation. Then the specimen is
rolled out by hand on a smooth surface or between the palms into a thread about 3mm in diameter. The
thread is then folded and re-rolled repeatedly. During this manipulation the moisture content is gradually
reduced and the specimen stiffens, finally loses its plasticity, and crumbles when the plastic limit is reached.
After the thread crumbles, the pieces should be lumped together and a slight kneading action continued
until the lump crumbles. The tougher the thread near the plastic limit and the stiffer the lump when it finally
crumbles, the more potent is the colloidal clay fraction in the soil. Weakness of the thread at the plastic
limit and quick loss of coherence of the lump below the plastic limit indicate either inorganic clay of low
plasticity, or materials such as kaolin-type clays and organic clays which occur below the A-line.
Highly organic clays have a very weak and spongy feel at the plastic limit.
4. Laboratory Classification
The two simple tests to be carried out for laboratory classification as per Indian Standard classification
system are:
(i) Sieve Analysis (Particle size distribution).
(ii) Plasticity Index (PI).
These simple tests are briefly outlined below:
(i) Sieve Analysis
The particle size distribution is by far the simplest way of broadly classifying a soil in terms of its being
granular (gravelly soils), medium grained (sandy soils) and fine grained (silts and clays). The sieve analysis
consists simply in taking a weighed quantity of the sample, soaking it in water overnight and washing out
the finer fraction through 75 micron IS Sieve. The fraction retained is dried and then passed through a
series of sieves (12 in number as specified by Indian Standards). However, for the rural road works, a set
of 7 sieves (ISS 40mm, 20mm, 10mm, 4.75mm, 2.36mm, 425 micron and 75 micron) is recommended. To
be able to broadly evaluate the particle size distribution of a soil even three sieves namely 2.36mm, 425
micron and 75 micron may suffice. While a mechanical shaker is generally used in well-equipped
laboratories, manual shaking of sieves is considered sufficient if carried out for a period not less than three
minutes.
(ii) Plasticity Index
(a) Liquid Limit: The test is carried out in a standard Casagrande liquid limit (LL) device in which a cup
containing a grooved specimen is made to fall on a rubber plate. The number of blows to close the
groove to a length of about 12.5mm is determined for different moisture contents. The liquid limit i.e.,
the moisture content corresponding to 25 blows is determined from a plot between the number of
blows and moisture content.

66 Operations Manual for Rural Roads


Table 1
Field Identification Procedures : Unified Soil Classification System
Field Identification Procedures Group Typical Names Information Required for Describing
(Excluding particles larger than 75µm and basing fractions on estimated weights Symbols Soils
Wide range in grain size and substantial amounts of GW Well graded gravels, gravel-sand Give typical name; indicate approximate
all intermediate particle sizes mixtures, little or no fines percentages of sand and gravel;
Predominantly one size or a range of sizes with some GP Poorly graded gravels, gravel-sand maximum size; angularity, surface
conditions, and hardness

fines)
intermediate sizes missing mixtures, little or no fines

(little or no
Clean gravels
Non-plastic fines (for identification procedures, see GM Silty gravels, poorly graded-sand-silt

size.
ML below mixtures
Plastic fines (for identification procedures, see CL GC Clayey gravels, poorly graded For undisturbed soils add information on
below) gravel-sand-clay mixtures stratification, degree of compactness,
cementation, moisture conditions and
drainage characteristics.

(appreciable
amount of fines

Gravels with fines

Gravels More than half of coarse


Example:

fraction is larger than 4 mm sieve


Silty sand, gravely; about 20% hard,
angular gravel particles 12 mm maximum

than 75 µm sieve size


Wide range in grain sizes and substantial amounts of SW Well graded sands, gravely sands,
all intermediate particle sizes. little or no fines size; rounded and subangular sand
grains coarse to fine, about 15% non-
Predominantly one size or range SP Poorly graded sands, gravely sands,

Clean
gravels
(little or
no fines)
plastic fines with low dry strength; well
little or no fines
compacted and moist in place; alluvial
Non-plastic fines (for identification procedures, see SM Silty sands, poorly graded sand-silt sand; (SM).
ML below) mixtures

Coarse-grained soils More than half of material is larger


Plastic fines (for identification procedures, see CL SC Clayey sands, poorly graded sand-

Gravels
with
fines
(appre-
ciable
amount

Sands More than


half of coarse
fraction is smaller
below) clay mixtures

Operations Manual for Rural Roads


Dry Strength Dilatancy Toughness
(crushing (reaction to (consistency
characteristics) shaking) near plastic limit)
None to slight Quick to slow None ML Inorganic silts and very fine sands, Give typical name; indicate degree and
rock flour, silty or clayey fine sands character of plasticity, amount and
with slight plasticity. maximum size of coarse grains; colour in
Medium to None to very Medium CL Inorganic clays of low to medium wet condition, odour if any, local or
high Slow plasticity, gravely clays, sandy clays, geologic name, and other pertinent
descriptive information, and symbol in
silty clays, lean clays. parentheses.

(The 75 sieve size is about the smallest particle visible to naked eye)

smaller
Slight to Slow Slight OL Organic silts and organic lilt-clays of

Silts and clays liquid limit less


than 50
medium low plasticity. For undistributed soils add information on
structure, stratification, consistency in
Inorganic silts, micaceous or

than 75 µm sieve size.


Slight to Slow to none Slight to medium MH undisturbed and remoulded states,
medium diatomaceous fine sandy or silty moisture and drainage conditions
soils, elastic silts.
High to very None High CH Inorganic clays of high plasticity, fat
high clays. Example:

Fine-grained soils More than half of material is


Medium to None to very Slight to medium OH Organic clays of medium to high Clayey silt, brown; slightly plastic; small

Silts and clays


liquid limit
greater than 50
high slow plasticity. percentage of fine sand; numerous
vertical root holes; firm and dry in place;
Highly Organic Soils Readily identified by colour, odour, spongy feel and Pt Peat and other highly organic soils loess; (ML)
frequently by fibrous texture.

67
Design (Annexures)
National Rural Roads Development Agency

(b) Plastic Limit: The moisture content at which a soil water mix, when rolled into a thread on a glass
plate, starts crumbling at 3mm diameter gives the plastic limit (PL) of the soil.
The numerical difference between liquid limit and plastic limit is the plasticity index (PI). Thus, it is
determined from the liquid limit and plastic limit values of soil. A rough estimate of this can also be
made using Uppal’s Syringe. A soil paste is made by adding water to soil such that water is above the
plastic limit of soil. This paste is put into the syringe and pushed out through the holes in the cap.
Depending upon the texture of the thread, the PI can be estimated as under: -
 Shiny surface and continuous thread: PI>11.
 Rough surface and broken threads PI 5 to 11.
 No thread formed PI > 5.
The Indian Soil Classification System (IS : 1498) is essentially the same as the Unified Soil Classification
System except with a slight modification in the classification of fine-grained soils (Fig. 5).

FIG. 5: PLASTICITY CHART FOR LABORATORY CLASSIFICATION OF FINE-GRAINED SOILS.

68 Operations Manual for Rural Roads


Design (Annexures)

Table 2
Unified Soil Classification System
Description Group Laboratory Criteria
Symbols Fines
(%) Grading Plasticity Notes

Coarse Gravels Well graded gravels, GW 0-5 Cu>4 Dual


grained (more with little or no fines I<CC<3 symbols if
(more than 5-12%
Poorly graded GP 0-5 Not satisfying
than 50% of fines. Dual
gravels, sandy GW
50% coarse symbols if
gravels, with little or requirements
larger fraction above A-
no fines line and
than 63 of gravel
mm BS size) Silty gravels, silty GM >12 Below A- 4< PI<7
or No. sandy gravels line or
200 US PI<4
sieve Clayey gravels, clayey GC >12 Above A-
size) sandy gravels line and
PI>7
Sands Well graded sands, SW 0-5 Cu>6
(more gravelly sands, with I<CC<3
than little or no fines
50% of Poorly graded sands, SP 0-5 Not satisfying
coarse
gravelly sands, with SW
fraction
little or no fines requirements
of sand
size) Silty sands SM >12 Below A-
line or
PI<4
Clayey Sands SC >12 Above A-
line and
PI>7
While describing a soil type, the group symbols given in Tables 1 and 2 should be used and the use
of non-engineering terms like red soil, hard soil, black soil, weak soil etc. should be avoided.
The broad classification of soils (as per IS) into Gravels, Sands, Silts and Clays based on particle
seizes is as under:

SAND
CLAY SILT Fine Sand Medium Sand Coarse GRAVEL
Sand
0.002mm 0.075mm 0.425mm 2.0 mm 4.75 mm
(2 micron) (75 micron) (425 micron)

Operations Manual for Rural Roads


69
National Rural Roads Development Agency

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)

MATERIAL SURVEY

1. General
All-India surveys carried out for different types of soils and low grade materials in different parts of the country
reveal that there is a wide variety of soil types as well as gravels, moorums and naturally occurring soft aggregates
which can be used to advantage in rural road construction. The distribution of a wide variety of naturally occurring
low grade materials/ soft aggregates is shown at Fig. 8. Traditionally, hard stone has been and is still being
used as a road material for all categories of roads including the low-volume rural roads. In general, hard stone
has all the attributes of a good construction material, both in regard to strength and durability, but its sources
are fast depleting. Moreover, in many parts of the country the leads involved are so long that they make the
material costs prohibitive. It is, therefore, necessary to go in for locally available low grade materials especially
for rural roads where the construction costs are to be kept low so as to enable full connectivity to all rural
habitations within a reasonable time frame. In the class of low grade materials are included various types of
soils encountered; sands from streams/ river beds and other sources; moorums which may even be available
at shallow depths below the ground level or from other quarries; gravels, well spoils, soft aggregate like laterite,
kankar, dhandla, river sand-gravel mixes etc. To this list can also be added the local availability of waste
materials like flyash etc.
2. Field Surveys
While locations of the PWD/Zilla Parishad approved quarries of stone metal can be obtained from the district
headquarters, the quarries for locally available low grade materials like the ones mentioned in para 4.5.1 are
generally not known but local enquiries from villagers etc can help a great deal in this regard. Samples of other
locally available materials like lime, that could possibly be used as soil stabiliser should also be collected. It is
necessary to ensure that the samples collected from quarries of low grade materials are truly representative of
the material(s) being evaluated. The samples would have to be subjected to strength tests like CBR besides
the classification tests and, therefore, should be about 20 kg in weight. The location and depth of the strata from
where the sample has been collected must be tagged on to the sample bag. Besides the quality, it is also
essential to assess the quantity of material that would be available from the quarry. In general, the locally
available low grade materials can be quite variable in their engineering characteristics. This aspect, naturally
has significant implications in the construction and performance of roads. The site quality control of materials
can be exercised meaningfully only if sampling and testing of these locally available materials has been carefully
done and the design values arrived at judiciously based on laboratory strength values.
3. Material Testing
The samples of locally available low grade materials should be subjected to the following laboratory tests:
(i) Sieve Analysis (Particle Size Distribution).
(ii) Plasticity Index.
(iii) Proctor Compaction.
(iv) CBR.
(v) Aggregate Impact Value.
(vi) Deleterious Material : In areas infested with harmful salts and containing organic matter, special tests to
determine their approximate content need to be carried out, in addition to the above tests.
The laboratory tests at (i) and (ii) have been briefly outlined in Section 4.3. The remaining four are described
below:
(iii) Proctor Compaction

70 Operations Manual for Rural Roads


Design (Annexures)

This test is conducted to determine the achievable density in the field and the optimum moisture required
for compaction. It is conducted in a standard Proctor apparatus. The soil sample (passing through 20 mm)
is compacted in three layers giving 25 blows on each by a standard rammer (weight 2.5 kg, fall 30 cm) at
five different moisture contents. From the plot between moisture content and dry density (Fig. 6), the
optimum moisture content and maximum dry density are determined.
It may be pointed out here that for rural road works, the Standard Proctor Compaction (light compaction)
test is relevant (as per IS : 2720 Part 7) and there is no need to go in for Modified AASHTO or heavy
compaction test as per IS : 2720 Part 8, which is recommended for heavily trafficked/ highway works.
(iv) CBR
CBR as a parameter is extensively used for the design of flexible pavements in India. The test is carried
out on a sample compacted at optimum moisture content to maximum dry density and soaked for 4 days.
In case of stabilised soil specimen (with lime/cement), the specimen is cured for 7 days prior to 4 day
soaking. The CBR of the specimen is computed from the load needed for 2.5 mm/ 5 mm penetration of a
standard plunger determined from the graph between penetration and load. If required, the zero correction
is applied for penetration while computing the load for 2.5 mm/ 5mm penetration (Fig. 7).

FIG. 6: MOISTURE-DENSITY RELATIONSHIP

FIG. 7: TYPICAL LOAD-PENETRATION CURVE FOR A CBR TEST

Operations Manual for Rural Roads


71
National Rural Roads Development Agency

(v) Aggregate Impact Value


The test is done on the coarse fraction in soil-gravel or on stone and soft aggregates. The crushing
produced in an AIV test apparatus by a rammer (13.5 kg) when it falls 15 times through 375 mm on the
sample (Passing 12.5 mm and retained on 10 mm ISS) is determined by sieving the sample through 2.36
mm IS Sieve. The AIV of sample is expressed as percentage of the material passing through 2.36 mm IS
Sieve to the weight of sample taken. A rough estimate of AIV can also be made from the moisture absorption
by aggregates in 66 hrs.

Moisture Absorption Approximate AIV


less than : Less than

1.5% 30%

3.0% 40%

6.0% 50%

(vi) Deleterious Material


The presence of organic matter and harmful salts like sulphates also need to be evaluated. Presence of
organic matter can be detected by its smell and dark colour, in case of fibrous materials. The organic
content can be determined by burning a weighed quantity of soil and noting the loss on ignition. The
presence of sulphates can be detected by adding a few crystals of barium chloride to the filtrate of soil
suspension in water. If a white precipitate is formed, this gives an indication of the presence of sulphates.
From the extent of milkiness of the solution, an approximate evaluation of sulphate content can also be
made.
Sodic soils can be easily detected by dipping an inexpensive pH determining strip into a solution of the soil
sample in water and comparing the changed colour of the strip with a standard colour chart. If pH value is
estimated to be over 8.5 from the colour chart, the soil is sodic in nature and unsuitable for use (i) as an
embankment material (ii) as filler in WBM and (iii) in roadside earthen shoulder.
4. Suitability Criteria for Materials
The samples of soils/ soil-gravel/ aggregates collected during the material survey are tested in the laboratory to
confirm their suitability for use in the different pavement layers. The criteria regarding the suitability of these
materials for gradation, plasticity and strength requirements have been outlined in the Rural Roads Manual.
However, considering the constraints in rural areas, these have been simplified and are given at Table 3.
In case the available materials meet the requirements as outlined at Table 3, these can be used as such.
Otherwise, the local materials have to be processed with a view to improve their engineering properties so that
these can be incorporated in the lower layers of road pavements. The various methods which can be adopted
to improve the local soils and inferior aggregates are shown in Fig. 8.
Table 3
Gradation & PI Requirement for Sub-base, Base and Wearing Courses (Ref. 5)

Sl. No. Fraction Percent (by Weight)

1. Sub-base/base courses
(a) Gradation requirements
(i) Passing 40 mm and retained 2.36 mm IS Sieve 45-65
(ii) Passing 2.36 mm and retained 75 micron IS Sieve 30-40

72 Operations Manual for Rural Roads


Design (Annexures)

(iii) Passing 75 micron IS Sieve 5-15


(b) The Plasticity Index of the fine fraction (passing 425 micron IS Sieve) should be less than 6.

2. Wearing Course
(a) Gradation requirements
(i) Passing 40 mm and retained 2.36 mm IS Sieve 30-60
(ii) Passing 2.36 mm and retained 75 micron IS Sieve 30-50
(iii) Passing 75 micron IS Sieve 10-25
(b) PI Requirement :

Climate Liquid Limit Plasticity


not to exceed Index
(Range)
(i) Moist temperature and wet tropical 35% 6-9
(ii) Seasonal wet tropical 40% 6-15
(iii) Arid 55% 15-30

FIG. 8: SOIL STABILISATION TECHNIQUES

Operations Manual for Rural Roads


73
National Rural Roads Development Agency

Annexure 5.2
(See Para 5.4)
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
NOMOGRAPH FOR COMPUTING “SOAKED CBR”
VALUE FROM SIEVE ANALYSIS DATA

74 Operations Manual for Rural Roads


Annexure 5.3(a)
(See Para 5.6)
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
FIELD DATA SHEET FOR TRAFFIC CENSUS
Name of Road :

Location on Road : Km

District :

State :

Vehicle Class
Animal Cycle Motorised Cars, Jeeps, Agricultural Light Remarks
Hour Drawn Cycles Rickshaws two-wheelers Vans, Three- Tractors/ Commercial Trucks Buses Season : Post Harvest
Vehicles wheelers Trailers Vehicles Monsoon) Weather :

From Hrs.
To Hrs.

From Hrs.

Operations Manual for Rural Roads


To Hrs.

From Hrs.
To Hrs.

From Hrs.
To Hrs.

Total for day

Record traffic volume by tally marks [four vertical strokes followed by a diagonal stroke for the 5th vehicle (IIII IIII II)]

75
Design (Annexures)
76
Annexure 5.3(b)
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
SUMMARY OF 3-DAY COUNTS
National Rural Roads Development Agency

Name of Road :
Location on Road : Km
District :
State :
Vehicle Class
Day Cars, Jeeps, Motorised Light Agricultural Cycle Animal Drawn Total
Vans, Three- two-wheelers Commercial Trucks Tractors/ Buses Cycles Rickshaws Vehicles
wheelers Vehicles Trailers

Day 1 (Date)
Day 2 (Date)
Day 3 (Date)

Operations Manual for Rural Roads


Total
Average Daily
Traffic
PCU Factor 1.0 0.50 1.5 3.0 1.5 3.0 0.5 2.0 4.0 for Horse Drawn
6.0 for Bullock
drawn
Average Daily
Traffic PCUs
Design (Annexures)

Annexure 5.4
(See Para 5.7)

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)

GUIDELINES ON USE OF LOCAL MATERIALS

1. Use of Better Granular Soil


Well-graded soils with low plasticity index values have better engineering properties and should be reserved
for use as improved subgrade/ sub-base or surfacing in the case of earth roads. Such soils can be identified by
their high Proctor density and low PI values.
2. Stabilisation of Local Soils
A variety of techniques are available for stabilising local soils for improving their engineering properties, but not
all the techniques are applicable to all types of soils. A brief description of the stabilisation mechanism and
applicability of the individual techniques are given in Table 1. This may be referred to for choosing the most
appropriate technique for stabilising the soil at site. The mix proportions are generally worked out in the laboratory
based on soaked CBR value.

Table 1
Mechanism and Requirements of Soil Stabilisation Techniques

Sl. Technique Mechanism Application


No.
1. Mechanical Blending missing fractions (e.g., clay with Sands, moorum/ gravel having missing
stabilisation sand and sand with clay) so as to produce a fractions and clayey soils can be stabilised by
mass of maximum possible density with this technique.
plasticity within limits. A smooth grading
similar to that given by Fuller’s grading rule*
is adopted to work out the proportion of the
missing fractions to be blended.

2. Lime Lime in hydrated form reacts with the clay Medium and heavy clays having a PI of at least
stabilisation minerals in the soil to cause (i) immediate 10 and containing at least 15% of materials
reduction in plasticity and increase in CBR finer than 425 micron are suitable. However,
because of cationic exchange, flocculation some soils though containing clay fractions
and agglomeration, which may be reversible may not produce the long-term chemical
under certain conditions, and (ii) long term reaction because of the presence of organic
chemical reaction with the clay minerals to matter (> 2%), or soluble sulphate/carbonate
produce cementitious products which bind (> 0.2%) etc. For lime stabilisation to be
the soil for increased strength and stability. successful, it will be desirable to test the soil
for lime reactivity. A soil whose 7-day
unconfined compression strength increases by
at least 3 kg/cm2 with lime treatment can be
considered lime reactive.

3. Cement The hydrated products of cement binds the Generally, granular soils free of high
stabilisation soil particles, the strength developed concentration of organic matter 2% deleterious
depending on the concentration of cement salts (sulphate and carbonate <0.2%) are
and the intimacy with which the soil particles suitable. A useful rule for soil selection is
are mixed with cement. A high cement that the plasticity modulus (product

Operations Manual for Rural Roads


77
National Rural Roads Development Agency

Sl. Technique Mechanism Application


No.
content of the order of 7-10% can produce a of PI and fraction passing 425 micron sieve)
hard mass having a 7-day compressive should be less than 250 and that the uniformity
strength of 20 kg/cm2 or more, and this coefficient should be greater than 5.
usually goes by the term soil-cement.
However, a smaller proportion of 2-3%
cement can improve the CBR value to more
than 25, and the material going by the term
“cement-modified soil” can be
advantageously used as sub-base/base for
rural roads.
4. Lime-flyash Lime chemically reacts with the silica and Soils of medium plasticity (PI 5-20) and clayey
stabilisation aluminium in flyash to form cementitious soils not reactive to lime can be stabilised with
compounds, which bind the soil. lime and flyash.

* Fuller’s grading rule is given by :

Percent passing sieve = 100 x

3. Use of Naturally Occurring Low-grade Marginal Materials


Low grade marginal materials like moorum, kankar, dhandla, laterite etc where available within economic
leads, should be made use of in pavement construction to the maximum extent feasible. The material may
occur in a graded form or as discrete blocks or admixtured with soil. Water Bound Macadam (WBM) is one of
the most common specifications being adopted for construction of sub-base, base and surfacing courses.
Broken stone, crushed slag, overburnt brick metal, laterite or kankar of acceptable quality can be used as the
coarse aggregate for WBM. The manner of using these is indicated in Table 2.
Table 2
Manner of Using Soft Aggregates in Pavement Construction
Sl. State of Occurrence of Manner of using in pavement Test/ Quality Requirements
No. Material Construction
1. In block or large discrete As water bound macadam without Wet aggregate impact value (IS : 5640)
particles screenings/ filler in accordance with not to exceed 50, 40 and 30 when used in
IRC : 19, after breaking the material sub-base, base and surfacing respectively.
into required sizes.
2. Graded form without Directly as a granular layer for sub- PI should be 4-9 when used as surfacing
appreciable amount of soil base/ base or surfacing. and should not exceed 6 when used in
lower courses. Evaluated for strength by
soaked CBR.
3. As discrete particles mixed Directly as soil-gravel mix for sub- The material should be well graded and
with appreciable amount of base, base or surfacing. the PI restricted as for Sl. No. 2. Evaluated
soil such as soil-gravel by soaked CBR.
mixtures.
Notes on Improving the engineering properties:
(i) Improving gradation – Sieving out sizes not required and blending with missing fractions.
(ii) Reducing plasticity – Stabilisation with lime
(iii) Improving strength – Materials with appreciable soil fraction can be stabilised with lime (where PI is high), lime-
flyash or cement.

78 Operations Manual for Rural Roads


Design (Annexures)

4. Use of Bricks and Overburnt Brick Metal


In alluvial plains where hard stone aggregates are normally not available within economical leads, the general
specification adopted for sub-base and base courses is to provide brick soling. Either flat bricks or bricks on
edge or broken brick ballast can be used depending on the thickness requirements. The bricks should be of
good quality and well burnt. Before laying flat bricks or brick-on-edge, it is desirable to provide a cushion of
sand above the earth subgrade.
5. Other Waste Materials
Many other waste materials like quarry waste, marble slurry dust, other metallic slags are available in many
parts of the country. Laboratory and field studies conducted on some of these materials have indicated that
such materials can be utilised for construction of lower layers of pavement and/ or embankment. However,
before embarking on use of such materials, detailed characterisation and design of mix through a reputed
laboratory would be needed.

Operations Manual for Rural Roads


79
National Rural Roads Development Agency

Annexure 5.5
(See Para 5.9)

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)


GUIDELINES FOR DRAINAGE OF RURAL ROADS

QUALITY OF DRAINAGE
Like any other design parameter, it is necessary to define the level of drainage to be provided which will
eventually reflect in the time taken for the water to be removed from the pavement structure. AASHTO definition
of the quality of drainage is given in Table 1.
Table 1
Quality of Drainage
Quality of Drainage Water Removed Within
Excellent 2 hours
Good 1 day
Fair 1 week
Poor 1 month
Very Poor Water will not drain

Even though low volume rural roads are essentially low-cost roads, the funds invested on aiming at “Good”
quality of drainage will eventually pay handsome dividends both by way of more economical pavement designs
and more importantly, by way of significantly reduced maintenance costs. Only in certain conditions, where the
cost of providing “good” drainage becomes prohibitive, could the “Fair” quality of drainage be acceptable.
Principles of Good Drainage
Some of the basic principles of drainage design are briefly outlined below:
 The surface runoff over the pavement surface and the shoulders should be drained away as quickly as
possible, preventing the water from finding entry into the pavement layers from the top and into the subgrade
from the top and the sides.
 Precipitation over the open land adjoining the road should be led away from the pavement structure
through natural drainage channels or artificial drains. Suitable cross-drainage channels should be provided
to lead the water across the road embankment which may be cutting across to the natural drainage
courses.
 Consideration should be given to deal with the precipitation on the embankment and cut slopes so that
erosion is not caused.
 Seepage and subsurface water is detrimental to the stability of cut slopes and bearing capacity of subgrades.
An effective system of subsurface drainage is a guarantee against such failures.
 Landslide-prone zones deserve special investigations for improving drainage.
 Relatively poor embankment soils can perform satisfactorily if drainage is considered in the design.
 Water-logged and flood-prone zones demand detailed consideration for improving the overall drainage
pattern of the area through which the road is aligned.

80 Operations Manual for Rural Roads


Design (Annexures)

Provision of Surface Drainage


For an effective surface drainage system, it must be ensured that the following measures are taken on all
PMGSY roads:
(a) Cross-slope or camber on the carriageway must be ensured by means of a Camber Board (Fig. 1) at all
times to conform to the standards laid down in the Rural Roads Manual. The cross-slope of the shoulder
should be 1% steeper than the cross-slope of the carriageway, subject to a minimum of 4%.
(b) Longitudinal drainage should also be ensured, despite the provision of adequate cross-slopes, for better
internal drainage of pavement layers, especially granular materials and in cut sections. Similarly along
vertical curves, the drainage considerations are of great importance and in some cases, the length of the
vertical curve may have to be adjusted to satisfy drainage requirements. For most conditions, a minimum
0.3% longitudinal gradient is considered adequate.
(c) It is absolutely essential to provide roadside drains/ ditches to collect the surface water from the roadway
(and lead it to an identified outlet) and also to drain the base of the roadway to prevent saturation and loss
of support for traffic.
Roadside drains/ ditches should be constructed and maintained in accordance with the following :
 provide enough area to accommodate storm flow and depth enough to drain the base course.
 protect the surface of ditches from erosion with turf cover or other suitable lining.
 keep velocities low enough to prevent erosion but great enough to prevent deposition or silting.
 maintain a continuous and unobstructed waterway.
 provide stable outlets to natural channels or drainage ditches.
The design of the roadside drains/ ditches can be done in the following step-by-step manner (the
needed formulae, design tables and charts etc are available in the Rural Roads Manual) (Ref. 3) :
(i) From the known soil type, arrive at the value of Manning’s Rugosity coefficient, side slopes and
the maximum permissible velocity.
(ii) Determine the slope from the topography.
(iii) For the given discharge, calculate the hydraulic mean depth from Manning’s formula.
(iv) Find out the cross-sectional area from the given discharge and the maximum permissible velocity.

Operations Manual for Rural Roads


81
National Rural Roads Development Agency

FIG. 1 : (a) and (b) TWO DESIGNS OF CAMBER BOARD


(v) From the results of steps (iii) and (iv), solve the simultaneous equations to obtain the bottom
width and depth.
(vi) Calculate the critical depth and determine whether the flow is tranquil or turbulent. If it is tranquil,
add a freeboard to the depth and finalise the cross-section. If the flow is turbulent, it may be
necessary to line the channel or decrease the longitudinal slope.
In the absence of any data, the salient design features are given in the Rural Roads Manual,
reproduced below
Location : 300 mm deeper than the bottom of road crust
Minimum width at bottom : 450 mm
Minimum longitudinal grade : 0.5 percent
Discharge : 0.50 cum per sec.
Shape : Triangular, Rectangular and Trapezoidal
Side slope : Generally not exceeding 1 in 4
(d) Lining : Grass lining is more economical than other linings to establish and with proper maintenance, will
indefinitely provide adequate protection against erosion for most of the site situations. A key factor to the
success of grass lining is that it must form a firm, dense turf. For a rapid establishment of vegetal lining in
ditches, the same principles must be followed as adopted for providing vegetal protection cover on slopes.
The roadside drain/ ditch can also be lined with sod freshly cut, to a depth of about 20 mm from a well
established dense turf. Sod strips should be placed across the ditch rather than lengthwise. The joints
should be staggered and strips pressed firmly against one another. After the sod is in place, it is tamped or
rolled to produce a smooth continuous surface. It should be watered for several weeks after placing, as
conditions may warrant.
(e) Outlets : At points of outlet to natural waterways or drainage channels, ditch erosion can occur unless
appropriate steps are taken to avoid it. It is necessary, therefore, to provide a well-protected sluice or
chute to carry water from the ditch level to the stream or to build an outlet structure. A sluice is generally
more suitable and economical to construct than an outlet structure. The grade should be as flat as possible
(less than 10 percent). Generally, there is substantial drop from the ditch to collecting channel and it is
necessary to divert the sluice sufficiently away from the road as it drops to the stream to meet the grade
requirement.
From one side of the road where there is no natural outlet, cross-overs of concrete or metal pipe may be
installed to drain water to the other side with a natural outlet. It must be ensured at all times that the outlet
while discharging water into the natural stream is always kept higher than the free water level in the
natural water course or, in other words, the outlet must never be submerged.

82 Operations Manual for Rural Roads


Design (Annexures)

Slope Protection Against Erosion


The following principles need to be followed for providing slope protection against surface erosion.
 Keep slopes flat and edges well rounded to reduce erosion potential to a minimum.
 Establish a healthy, vegetal cover as quickly as possible.
 Intercept water from higher ground before it reaches slopes susceptible to erosion.
 Provide safe outlets for water collected in intercepting drains and gutters.
 Protect slopes from freely flowing underground water.
 Take special precautions around structures which protrude above slope surfaces.
Interceptor ditches (drains) are constructed in hill areas to protect the road bench and hill side slope from
erosion due to heavy rainfall and run off. These are very effective in the areas of high intensity of rainfall and
where slopes do not have any vegetative cover. These are the structures designed to intercept and carry
surface run off away from erodible areas and slopes with reduced velocity resulting in potential of surface
erosion. The rain water from these interceptor drains is then brought down in manageable quantities through
chutes without damage. The Chutes on stable supports and may be located at 10 to 15 m intervals depending
upon intensity of rainfall and length of the hill slope. Stepped outfall which is a simple energy dissipation may be
used in place of Chutes if site condition so warrant. The discharge should be led to the nearest natural channel.
The layout and siting of ditches shall be in accordance with guidelines on Road Drainage IRC: SP – 42.
Intercepting/Catch-water Drain on a Hill slope is shown in Fig. 2

FIG. 2: INTERCEPTING/ CATCH-WATER DRAIN ON A HILL SLOPE


Subsurface Drains
Sub surface water in the granular layers or in the subgrade of a pavement may harm the road in various ways
such as :
 By way of reduction of subgrade strength which in turn, affects the performance of top granular layers
also.
 Heavy wheel loads may create pulsating water pressure resulting in internal erosion and ejection of materials
through cracks and joints. This, coupled with movement of subsoil water, changes the arrangement of fine
to coarse material and aggregates in the structure resulting in weakened granular bases, cement treated
bases and stabilized layers.
 Absorption of water in the filler material, which may not be fully non-plastic, may seriously undermine the
load support characteristics of the layer.
 Free water in bituminous pavements results in stripping of the binder leading to faster cracking and
deterioration.

Operations Manual for Rural Roads


83
National Rural Roads Development Agency

Condition of subsurface water accumulation arises due to one or more of the following:
 Top, i.e., surface infiltration of precipitation through paved or unpaved areas, shoulders, higher adjoining
grounds/hills seeps down. Collection of water in pot holes, undulations, cracks, defects, joints also seeps
down.
 Lateral seepage through shoulders, adjoining hill slopes etc.
 Free water from a high water table or capillary action from a water table.
Best way of drainage of pavement course is to provide and extend a specially designed subbase layer, called
drainage layer, upto the embankment slope face. The drainage layer also helps in draining away the water from
a high water table and also acts as a capillary cut off and thus prevents damage to subgrade and subbase
layers. In addition, proper cross fall to the drainage layer is required to be provided to guard against sluggish
flow.
In cases where it is not possible to take the drainage layer upto the embankment slope face provision of
subbase drainage is achieved through sub surface drain pipes encased in drainage media. Guidance for
design of subsurface drains may be taken from Para 8 (Sub Surface Drainage) of IRC SP:50-1999-Guidelines
on Urban Drainage. Sub surface drains are also required where quantity of subsurface water is very high which
can not be drained off fully using economical thickness of drainage layer.
A typical subsurface drain intercepting free water in a slope before it reaches to a point as would render the
slope unstable, is shown in Fig. 3.

FIG. 3: DRAINAGE LAYER AND TYPICAL SUBSURFACE DRAIN

84 Operations Manual for Rural Roads


Design (Annexures)

Annexure 5.6
See Para (5.11.2)

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)


NOMOGRAPH FOR EQUILIBRIUM SUBGRADE MOISTURE CONTENT

Operations Manual for Rural Roads


85
National Rural Roads Development Agency

CHAPTER 6
PROJECT PREPARATION

6.1 STEPS INVOLVED


The various steps involved and the agency responsible for the Project Preparation are given below:

Sl. No. Activity Agency Responsible

(i) Estimate Length of Roads for New connectivity SRRDA


and/or Upgradation
(ii) Distribution of State’s Allocation among Districts State Nodal Department
(iii) Selection of list of proposals in each district District Panchayats, with assistance of PIU
(iv) Vetting of list of proposals for each year & State-level Standing Committee with
Administrative approval assistance of SRRDA
(v) Preparation of DPRs PIU
(vi) Scrutiny of DPRs PIU/STA/PTA
(vii) Technical Sanction Nodal Department/SRRDA

6.2 DETAILED PROJECT REPORT (DPR)


Each Rural Road Project (whether a new link or upgradation of an existing road) should have a separate
Detailed Project Report (DPR).
The DPR should be based on detailed survey and investigations, design and technology choice and should be
of such detail that the quantities and costs are accurate, and no cost over-run takes place due to changes
in scope of work or quantities at the time or execution. Guidance may be taken from IRC: SP: 19 for preparing
the DPR.
Before the commencement of the preparation of the DPRs, a joint meeting of all concerned Engineers of PIUs
and STA(s)/ PTA shall be convened by the SQC under the Chairmanship of the Chief Engineer (PMGSY) to
discuss the issues and the data requirements for the preparation of DPR. At this stage STA/ PTA shall take
initiative in guiding Executing Agencies for adopting designs with New Materials where it is possible. If needed,
they will associate in the investigations of special nature. The Engineers also will be appraised of the need for
appropriate Designs with respect to Geometrics, Pavement Crust, Surface Drainage, CD Works as well as the
measures for Environmental Conservation.
The steps involved in the preparation are as under:
1. Selection of alignment : The suitability of the existing track as the final alignment is examined, and
need for avoiding sharp kinks and dwellings is explored.
2. Topographical survey : The topographical survey is carried out with a plane table/ compass/
theodolite, designing the horizontal curves. A line of levels is run along the
centre line and cross-sections are taken.
3. Soil survey : Samples of local soils are collected and tests like grain-size analysis,
moisture-density relationships and CBR are carried out.

86 Operations Manual for Rural Roads


Project Preparation

4. Material survey : The source of materials for forming the embankment, pavement layers
and cross-drainage structures are identified and their leads established.
5. Hydrological survey : The sites for bridges are selected and hydrological survey to determine
the discharge and HFL is carried out.
6. Traffic Estimation : On existing roads, traffic survey is done. On new roads, the traffic likely to
ply is estimated. The growth rate is determined.
7. Pavement Design : Considering the soil strength, traffic and design life, pavement thickness
is determined. Its composition is selected after exploring the ways to
maximise the use of local materials.
8. Drainage Plan : A drainage plan is made for the road giving a scheme for the effective
drainage of water into natural channels, supported by levels.
9. Design of cross- : The type of culverts, bridges and causeways is selected and design of
drainage works the various elements like foundations, substructure and superstructure is
done.
10. Preparation of Land Plans : Plans showing the land holdings and the selected alignment are made to
a scale of 1:8000 to 1:2000, depending upon the availability of maps. The
existing village plans available with the revenue authorities are generally
used.
11. Preparation of road drawings : Alignment Plans, Longitudinal Sections and Cross-sections are prepared.
12. Preparation of drawings : Drawings of culverts, causeways and bridges are prepared.
of C.D works
13. Selection of specifications : The specifications for various items of work are selected, keeping in view
need to adopt intermediate technology.
14. Estimation of quantities : Detailed quantities of each item of work are worked out.
of items of work
15. Analysis of Rates : The rates for each item of work are analysed.
16. Estimate : The estimated cost is arrived.
17. Preparation of : The DPR documents are prepared.
DPR documents
The Junior Engineer shall prepare the DPR as per the provisions of the relevant IRC Codes of Practice and
bring out the document along with all data supported by necessary investigations and the maps/ drawings. It is
emphasized, in this context, that the Senior Engineers of the Department shall make a reconnaissance of the
proposed link, prior to the investigation and preparation of DPR. Even when the preparation of DPRs is
outsourced, the Senior Engineers of the Executing Agency will do the reconnaissance.
Having prepared the DPR the Engineer concerned shall cross check that the data used in the Designs is
correct and the Estimations are accordingly made.
The DPR shall be submitted in two volumes:
Volume I : Report and Estimate in A4 size.
Volume II : Drawings in A3 Size.
Volume I (Report and Estimate) shall have the following contents:

Operations Manual for Rural Roads


87
National Rural Roads Development Agency

Chapter Title Coverage


No.
1. Introduction Name of work, its status vis-à-vis Master Plan, Core Network, priority,
terrain, geography, climatic conditions, habitations served
2. Alignment Obligatory points, existing tracks
3. Land Acquisition Present and proposed right-of-way, Need for new land, Status of
Land Acquisition
4. Geometric Design Standards Roadway width, carriageway width, shoulders, design speed,
horizontal curves, vertical gradient, cross slopes etc.
5. Topographical Surveys Surveys carried out
6. Soil and Materials Survey Borrow Area, Quarry Charts, availability of local materials, test results
7. Traffic Survey Different types of rural vehicles plying per day.
8. Pavement Design Type of pavement, thickness design, use of local materials, type of
and Surfacing surfacing adopted
9. Hydrological Survey Data required for hydraulic design of cross-drainage works.
10. Design of Cross-Drainage Types of culverts, submersible bridges, paved dips, High Level
Structures and Integration of Bridges, and justification for selection.
Drainage System
11. Protective Works Retaining walls, breast walls, check walls
12. Specifications Choice of technology, specifications adopted
13. Environmental Issues and Re-instatement of borrow areas, erosion control etc.
Mitigation Measures
14. Analysis of Rates Rates of different items of rural road pavement construction.
15. Estimate Provision for contingencies, Quality Control, Supervision
16. Construction Programme Bar chart showing activities and time frame
17. Undertaking for State’s commitment of funds needed for maintenance and adoption
Future Maintenance of maintenance management system.

A Detailed Project Report (DPR) is to be prepared for each proposal after collecting necessary base data. The
DPR essentially should contain the following:
 Population of the habitation(s) connected.
 Population (Direct + Indirect) served by the proposed road.
 A drawing (Not to scale) showing the nature of connection and the habitation(s) connected/ served by the
proposed road.
 Type and condition of the existing road/track.
 Road Land Width (RLW) available both in built up area as well as open area.
 Data from Engineering Surveys such as alignment, Longitudinal Section (LS) and Cross Section (CS).
 Processed data of LS & CS.
 Geometric design particulars.

88 Operations Manual for Rural Roads


Project Preparation

 Soil Investigation results for the sub grade such as Gradation, OMC, CBR etc.
 Hydraulic data for the design of Cross Drainage (CD) works.
 Base year Traffic data of Motorised and Non-motorised vehicles.
 Growth rate adopted and projected traffic for the horizon year based on the design life.
 Layer wise design of the pavement along with a sketch of dimensioned cross section indicating the Pavement
Layers, Carriageway (CW), Roadway (RW) and Road Land Width (RLW).
 Design details of CD works/ Protection works and associated working drawings.
 Estimation of BOQs.
 Estimation of cost as per standard data analysis based on SDB and State Schedule of Rates (SSR).
 Provision for Logo and other road furniture.
 Total cost of the proposed road and cost/ km for the same.
It is to be ensured that the data is complete in all respects in Formats F1 to F9 which forms an integral part of
the DPR and the design of Geometrics, Pavement and CD works should be strictly in accordance with the
provisions of the Rural Roads Manual (RRM) (IRC : SP 20 : 2002).

6.3 DRAWINGS
The following drawings should accompany the DPR as Volume II:
1. Key Map, showing the State in relation to India, District in relation to State, and a district map showing all
the Blocks, with the names of each Block marked.
2. A Block road map showing the Master Plan and the Core network and the proposed road.
3. An Index Map of the road showing the full road to a suitable scale, topographical features like rivers,
canals, streams, railway lines, villages, Market Centres, other roads and Legend.
4. Plan and Longitudinal Sections of the road, showing 1 km in each sheet.
5. Typical cross-sections.
6. Detailed cross-sections.
7. Drawings of culverts, submersible bridges, paved dips and High Level Bridges, giving General Arrangement
Drawings (GAD), structural details.
8. Drawings of protective works like retaining walls, breast walls, check walls, drains.
9. Miscellaneous Drawings like kilometre stones, Traffic signs.

6.4 CHOICE OF TECHNOLOGY


Since there is readily available labour in most rural areas of the country, and Rural Road construction and
maintenance can be efficiently implemented by labour-oriented or appropriate technology, the DPR should be
prepared keeping this important consideration in view. Simple agricultural tractor-based equipment is very
easily manufactured and serviced in the rural areas, and can produce roads of acceptable quality for the
PMGSY. The use of modern highway construction equipment like large capacity Hot Mix Plants, Paver Finishers,
Wet Mix Macadam Plants, Vibratory Rollers, Earthmoving and excavating equipment may not be insisted upon
where it is not cost and/or time-effective.

6.5 SPECIFICATIONS
The MoRTH Specifications for Road and Bridge Works are intended for highway facilities like National Highways
and State Highways. These are not in conformity with specification prescribed in RRM. Therefore, a separate
book of Rural Road Specifications has been drawn up by the IRC. The specifications in the DPR for PMGSY

Operations Manual for Rural Roads


89
National Rural Roads Development Agency

road works will be based on the specifications contained in the above document brought out by IRC as
‘Specifications for Rural Roads’ for MoRD in 2004 for adoption to all Rural Roads.

6.6 STANDARD NOMENCLATURE OF ITEMS OF WORK


The items of work involved in Rural Road works are not large in number and therefore, it would be advantageous
if the nomenclature of these items is standardised. Adoption of information data analysis for the standardised
times and rate analysis will also facilitate comparison of rates across the country. Accordingly the estimates
and BOQ should be based on the standard items, and the Standard Rate analysis for Rural Roads published by
the IRC as ‘Standard Data Book: Analysis of Rates for Rural Roads – 2004’.

6.7 ANALYSIS OF RATES


While preparing schedule of Rates using MoRD, Standard Data Book (SDB) for Analysis of Rates for Rural
Roads the following principles should be kept in view:
 The Schedule of Rates (SOR) shall be prepared by the competent authority of the State Government as
per the prevalent practice of the State either at State level, Revenue Division or Circle level or District level
as the case may be. States may, at their option switch over to district-wise Schedule of Rates with the help
of the software made available.
 The nomenclature of all the items of works will be strictly as given in “Ministry of Rural Development -
Standard Data Book for Analysis of Rates for Rural Roads” September 2004 (SDB).
 The coefficients given in the Standard Data Book Analysis shall be used together with the adopted basic
rates for material, labour and machinery to compute the rate of the complete items of work as per Schedule
of Rates.
 Complete items of work include cost of labour, material, machinery and transportation/ carriage. General
Conditions in the Standard Data Book provide that complete item of work includes the rate of material at
source and also the carriage to site of work including loading, unloading and stacking. Various States
have different practices. In some States the component of loading, carriage, unloading and stacking are
added separately to the basic rate at source, while others follow the all inclusive rate particularly for items
like select soil, coarse and fine aggregates, bricks, stone etc. In order that the cost of each component is
easily distinguishable and verifiable that each element has been properly accounted for, it is recommended
that cost of material at source and the carriage element using analysis given in Chapter 1 of SDB are
shown separately in the analysis of rates.
 If any item is used which is not covered in the SDB, the analysis will be approved by the competent
authority under intimation to the NRRDA and STAs in the State.
 The Schedule of Rates may be updated annually and updated Schedule used at the time of estimation/
technical sanction for the annual proposals under PMGSY. A copy of the Schedule of Rates may invariably
be endorsed to the STAs.

6.8 ESTIMATES
The estimates shall reflect the true scope, quantum and cost of works, based on detailed surveys and
investigations. The following points may be kept in view while framing the estimates:
 The borrow areas must be located accurately. It is not advisable to borrow earth from the road land.
Temporary earth from adjacent fields may be borrowed with the consent of the farmers. Otherwise, fallow
land, and non-agricultural land, near to the project may be identified. The lead and lift involved may be
accurately assessed and accounted for. The haulage method should also be identified.
 The sources of gravel, sand, stone aggregates, bricks and marginal materials should be accurately identified,
and the availability of the required quantity and quality of materials established. The leads involved, and
the condition of roads leading to the sources shall be determined.

90 Operations Manual for Rural Roads


Project Preparation

 The rates shall be based on the State’s updated Schedule of Rates based on Standard Data Book: Analysis
of Rates for Rural Roads 2004 (See para 6.8).
 No provision for escalation shall be allowed.
 For externally funded projects, contingencies supervision charges may be allowed as agreed upon.
Several roads in a Block or in adjacent Blocks can be combined into packages of a value of Rs 1-5 crores. The
abstract of the cost shall be given in Forms F-1, F-2A and F-2B (Annexure 7.1).
The total proposal for the State shall be submitted in District wise volumes to the NRRDA.
A package will be identified by a unique number given to it. The package number shall be designated as RJ 03
07, as an example, shown below:

6.9 ENVIRONMENTAL MANAGEMENT


6.9.1 Introduction
It is very important that the impact of road schemes on the environment be considered at the planning and
design stage itself. It is also necessary that adequate safeguards are taken to prevent environmental degradation
during the construction phase.
6.9.2 Selection of Alignment
Most of the Rural Roads are aligned along tracks or footpaths, which are already in existence. Utilising the
existing facility to the maximum possible extent will minimise the hardships caused by land acquisition and also
minimise incremental environmental impact. Ecologically sensitive areas like national parks, wildlife and bird
sanctuaries, and reserve forests should be avoided. In general, drainage and hydrology should be given due
consideration. An alignment, which balances the cuts and fills is not only economical, but also avoids the
problems of disposal of excess material from cuts and locating fresh borrow areas. The balancing of cuts and
fills should, ofcourse, not sacrifice geometric standards.
6.9.3 Borrow Areas
It is observed that in most of the Rural Roads being constructed now, the borrow areas are located just by the
side of the road embankment. This may be economical to the contractor, but it is an environmental hazard,
because of the following:
 The location of deep borrow pits at the toe of the embankment undermines the stability of the embankment.
 The borrow pits are cut at varying depths, with the result that water stagnates and is not drained effectively.
The stagnant water breeds mosquitoes and is a health hazard.
 It is accident prone.
As such, borrow pits should not be dug close to the road embankment. Earth may be taken from the adjoining

Operations Manual for Rural Roads


91
National Rural Roads Development Agency

fields by obtaining consent of the farmers. Earth may also be borrowed from areas not cultivated, though this
may involve some lead. The tender documents should clearly indicate the borrow areas identified, and the
tender items must specify the lead and lift involved, so that the contractor knows the scope of the work and
quotes accordingly. The borrow areas must be either filled up or landscaped with vegetation such that they do
not present ugly scars.
6.9.4 Turfing
In most of the Rural Roads, erosion of the slopes of the embankments, rain cuts and erosion of the earth in the
shoulder are commonly observed defects. The erosion of the slopes causes the loss of the roadway width,
besides leading to sedimentation of the adjoining water bodies and natural drainage channels. This must be
arrested by turfing the embankment slopes and earthen shoulders. Provision must be made in the estimates
for this item, wherever found essential.
6.9.5 Road Drainage
At the edges of the road land, shallow roadside drains should be provided to drain away the water from the
road. These drains must have a designed longitudinal gradient, so that the water is led to a natural drainage
channel. Where two roads intersect, there should be culverts to continue the drainage if the slope of the terrain
demands it. If the levels permit, and the intersection is on higher ground, the side drains may have longitudinal
slopes away from the high ground.
To prevent erosion of the side drains, they must have sufficient cross-section so as to promote a non-silting and
non-scouring velocity. It is always preferable to turf the sides of the drain to prevent erosion, which can lead to
sedimentation and reduction in carrying capacity.
Inadequate waterway across the road can cause flooding of the land upstream; such situations must be avoided.
The road construction should not adversely impact on fisheries, pond, aquatic ecology and other beneficial
uses of water by the community.
6.9.6 Roadside Plantations
To improve the landscape, suitable species of trees and shrubs should be planted along the road, away from
the road embankment. They should preferably be at the land boundary, so that the future encroachment of road
land is avoided. The community must be encouraged to take up tree plantation activities and look after them.
The choice of species should be made in consultation with the local community.
6.9.7 Roads Through Villages
When roads pass through villages, care shall be taken to ensure that there are side drains on either side to
drain away the water from the road and the discharge from the abutting houses. The road level shall be
sufficiently above to ensure that the road itself does not act as a drain. Provision of a concrete pavement
provides a dust-proof and low maintenance road, which suffers less damage during occasional overtopping.
6.9.8 Use of Cut-Back
It is the normal tendency on the part of the contractors and the engineers to dilute the bitumen by adding
diluents like kerosene. The kerosene and other diluents will ultimately find their way to water-bodies and
contaminate them. The use of cut-backs should be prohibited. If liquid bitumen is needed for spraying and
premix work, an emulsion should be preferred. Cut-backs shall be permitted only in extremely cold temperatures.
6.9.9 Conservation of Stone Materials
Though stone sources are abundant in India, the use of stone should be restricted to the barest minimum.
Wherever possible, low cost marginal materials like soil, gravel, moorum and kankar should be used, if necessary
by processing them by stabilisation.
6.9.10 Use of Flyash
In areas near to thermal power plants, flyash is available in plenty, almost at a throw-away price. Flyash should
be used in rural road construction (also refer Annexure 5.4):

92 Operations Manual for Rural Roads


Project Preparation

 as an embankment fill material (for high embankments above 3m height, and with a minimum cover of
ordinary soil 1000 mm thick on sides and 500mm below the bottom layer of the pavement).
 as a partial replacement for cement in cement concrete pavements.
 as a stabilising agent in conjunction with lime, for soil stabilisation and lime-flyash-concrete.
Since the use of fly-ash wherever possible within a radius of 100 Km of thermal plants is mandatory, the PIU
shall ensure that the possibility of its use is fully investigated.
6.9.11 Historical/ Cultural/ Religious Monuments
The road alignment should not cause impact on or damages to historical, cultural and religious monuments.
6.9.12 Environmental Measures in Hill Roads
The construction of roads in hilly region disturbs the ecosystem in many ways. The main ecological problems
associated with hill road construction are:
 Geological disturbances and stability of slopes is a major concern in hill roads. During DPR preparation
proper geological investigation need to be carried out. The rock profile and geologically critical sections in
many States have been mapped based on satellite imaginary and should be made use of for carrying our
detailed investigations. Slope stability analysis for retaining wall/breast walls of height greater than 5m
shall be carried out as per IRC:SP-48 and incorporated in DPR.
In addition to stability analysis the alignment should be such that steep as well as heavy cuts are avoided.
Rock fall can be controlled through use of geogrids or rock bolts.
 Soil erosion is a consequence of high runoff on hill slopes. Construction of interceptor ditches/catch water
drains to protect the road formation and hill side slope are effective in areas of high intensity rainfall and
where slopes are exposed.
 On side slopes in hill, immediately after cutting is complete and debris is removed, fast growing
species of grass should be planted. This would prevent high velocities of runoff. Sodding and turfing,
vegetation or pitching, asphalt mulch treatment, use of jute or coir netting are some of the measures
of preventing erosion on hill slopes.
 Sheet and gully erosion on gentler slopes can be prevented effectively through construction of check
dams (maximum height 0.6m). These can be constructed using locally available material such as
riprap, logs, sandbags and or straw bales. If the length of hill slopes is long multiple check dams can
be provided.
 Loss of tree cover
Any felling of trees during the construction of hill roads should be minimised. If some trees are unavoidably cut,
additional compensatory tree plantation is required to be carried out as per Forest Department instructions.
 Aesthetics degradation.
When hill faces with vegetation cover are cut, the cut faces present a scar on the general landscape. Visual
appearance should be restored through fresh vegetation cover, which may be hastened through asphalt mulch
technique or jute/coir/geofabric / geogrid matting.
 Waste Management.
Waste and debris generated through construction activities can be reused and if cannot, it needs to disposed
off in a manner that they do not damage water bodies and cause siltation to ponds and channels. In this
respect, tipping of wastes into stream channels, water bodies, forests and vegetated slopes should be avoided.
Some of the measures of waste disposal are:-
 Construction of gabion walls – these are constructed on valley side at ridge locations to form a trough
for waste disposal. These walls can withstand large deformation without cracking and are flexible.

Operations Manual for Rural Roads


93
National Rural Roads Development Agency

Further due to open nature of the structures they allow free drainage of water. After filling up of the
disposal site, it shall be grassed and suitably vegetated to prevent erosion of the disposed soil.
 Silt fencing – it is a sediment barrier provided to prevent sediment carried by sheet flow from leaving
the site and entering to natural drainage or any other water body located near the construction site.
 Bally benching – These are provided in order to arrest the shallow movement of top mantle slide
mass at the construction location.
 If the wastes generated during construction cannot be reused, the following precautions should be
adopted
 In case of bituminous wastes, dumping will be carried out over a 60mm thick layer of rammed
clay so as to eliminate any chances of leaching.
 In case of filling of low lying areas with wastes, it needs to be ensured that the level is matched
with the surrounding areas. In this case, care should be taken that these low laying areas are
not used for rain water storage.
 Quarry Area.
The excavating of material from quarry area should be done with minimum adverse impacts on environment. It
should be ensured that adequate drainage system has been provided to prevent the flooding of the excavated
area. At the stock piling locations, sediment barriers (brush barriers) shall be constructed to prevent the erosion
of excavated material during runoff.
 Water for Construction.
In water scarce regions and in winter season when water availability is not sufficient, the various construction
activities need to be rescheduled to reduce the drawl of water from community sources. Various modern
techniques like Water harvesting/Ground water recharging are needed to be explored to avoid water extraction
from the community sources.
6.9.13 Measures Needed in Desert Roads
The construction of roads in arid region disturbs the ecosystem in many ways. The main ecological problems
associated with desert road construction are:
 In case of roads in arid areas, the embankment made up of silty and cohesion less sandy soils are
subjected to erosion due to high wind velocities. Also, when the slopes are steep (more than 20 degrees),
the erosion of embankment is more predominant. As a result there is reduction in road formation width
(erosion of shoulders/berms). Moreover, the sand gets deposited over or near the road surface, which is
not desirable. In order to avoid the deposit of sand, hardy variety of shrubs and plants are planted at
appropriate distance from the formation. There should be a clear gap between the roadway and shrubs to
allow the wind to pick up its velocity and carry along with it any sand that is deposited.
 Desert roads passing through shifting sand dunes require special design considerations. Some of the
proven techniques are:
 Avoidance of partial cut and partial fill sections:- Partial cut and partial fill sections should be avoided
as they will provide loose sand to be carried away by high wind velocities which in turn will be deposited
over the road and nearby areas.
 Avoidance of high embankments:- High embankment should be avoided in desert areas as they are
subjected to more erosion in the absence of vegetative cover.
 Top soils with humus, wherever encountered while opening up the site for construction, shall be stripped,
stockpiled and used for restoration of borrow areas to maintain its fertility.

94 Operations Manual for Rural Roads


Project Preparation

 Water for construction-


In water scarce regions construction activities need to be rescheduled to reduce drawl of water from community
sources to a minimum. Assessment of water requirement for each stage should be made. Earthwork for
embankment can be carried out just before monsoon so that subsequent works of granular sub-base and WBM
can be carried out during monsoon when water is readily available.
 Water harvesting structure (water tanks for collection of rain/stream water) may be constructed where
feasible to provide water for construction.
6.9.14 Environmental Considerations during Maintenance
The following guidelines may be noted:
 For making up the eroded slopes and shoulders, earth should not be borrowed from roadside land. This
leads to formation of deep side channels, endangering the stability of the road embankment and creating
pools of stagnant water where mosquitoes breeding can take place. Earth should be borrowed from
nearby fields after obtaining consent of the farmers.
 The turf on embankment slopes, shoulders and drainage ditches must be trimmed periodically.
 The culverts and bridges, and the channels around them, should be desilted periodically so that water
flows away quickly without stagnation.

6.10 ECONOMIC ANALYSIS


While providing new links to unconnected habitations is a social responsibility, the investments on upgradation
of existing roads should result in economic benefits. Proposals for upgradation should be subjected to economic
analysis. The specifications for upgradation and maintenance interventions should be so selected that the IRR
is at least 12 percent. The benefits that may be considered for the analysis may include (i) agricultural producer
surplus (ii) savings in vehicle operating costs and (iii) savings in travel time of passengers.

6.11 USE OF CONSULTANTS FOR PREPARATION OF DPR


The task of survey, investigations, design and preparation of DPRs is laborious and requires skill and experience.
Since PMGSY is a time-bound programme, State Governments need to build up capacity to prepare DPRs of
acceptable quality. For this purpose, they may outsource this service where adequate in-house capacity is not
available, to Consultants with adequate expertise and capacity. This may be done after inviting expression of
interest and short-listing prospective consultants meeting the requirements including previous experience of
preparing DPRs of road works equal to at least 50% of the value of the proposed DPRs.
The work of design Consultants should be periodically evaluated by assessing:
(i) Whether any serious excess has occurred between the estimated and as executed quantities.
(ii) Whether any design deficiency has come to the notice of the Department in the execution of the work.
The Consultants whose work has not been wholly satisfactory should not be awarded further consultancies.

Operations Manual for Rural Roads


95
National Rural Roads Development Agency

CHAPTER 7
SCRUTINY OF DETAILED PROJECT REPORTS

DPRs for Rural Roads are usually prepared by JE/AE level staff. Though Rural Roads are generally small low
volume roads, the technical inputs required may actually be quite high because of the need to cater to the
sensitivities of the local community directly affected by the road. As such, scrutiny of DPRs by senior officers is
essential to ensure that the road is not only technically well engineered, but also well integrated with community
requirements. This requires intervention at Executive Engineer and Superintending Engineer levels on key
parameters based on local knowledge and long field experience.
7.1 STEPS INVOLVED
The following steps are involved in the scrutiny of the DPRs :

1. Completion of Forms F1-F9 by PIUs and submission to the SE


2. Scrutiny of DPRs by SEs
3. Scrutiny of DPRs by STAs
4. Preparation of Summary of Proposals by SRRDA.
5. Submission of Proposals to NRRDA and test scrutiny of 15% cases by NRRDA.

7.2 PREPARATION OF DPRS SUMMARY BY PIUS


7.2.1 Once the DPRs have been prepared for each road work, the details have to be filled in Forms F1-F9.
These Forms (except F-3& F-5) are enclosed in Annexure 7.1
The information in the Forms are as under:
F1 : Package-wise Summary Sheet.
F2 A : Road-wise Summary of Cost of Pavement.
F2 B : Road-wise Summary of Cost of CD Works.
F3 : Typical cross-section of Road for New Construction.
F4 : Details of Existing Roads Proposed for Upgradation.
F4A : Association of Routes.
F5 : Typical cross-sections of Road for Upgradation.
F6 : Detailed Estimate for Pavement.
F7 : Detailed Estimate for CD Works.
F8 : Rate Analysis.
F9 -A : Summary of on-site verification of DPRs by Executive Engineer.
F9-B : List of DPRs verified on ground.
7.2.2 The PIU shall enter the details of each DPR in the proposals on-line in the www.omms.nic.in website
under “Proposals Mode” giving road-wise details of the length, cost and habitations connected etc. Scrutiny of
the proposals will not be done by the STAs, if the details are not available on the website.

96 Operations Manual for Rural Roads


Scrutiny of Detailed Project Reports

7.2.3 The responsibility for proper preparation of the DPRs rests with the Executing Agency and in particular,
the PIU. It is essential therefore that the DPRs be thoroughly checked at various levels.

7.3 SCRUTINY AT DPIU LEVEL


 The Assistant Engineer (Deputy Executive Engineer)will check and certify at least 30% of the DPRs at site
in respect of accuracy of data and ground realities as well as correctness of the design and estimation.
‘Design’ covers Geometric Design, Structural Design (Pavement Crust), CD Works and Protection Works.
In this process, he has to identify the issues where deficiencies are found and get them corrected uniformly
in all the proposals.
 The Executive Engineer shall check and certify at least another 20% of the DPRs at site in order to make
sure that the investigations are adequate and design and estimation is as per the requirements. If any
deficiencies are found, he will point out the same and get the DPRs corrected accordingly.
 The DPRs should be personally checked and signed by the Head of the DPIU and scrutinised by the
SE(Also see para 7.3.3).In case of CD Works with length exceeding 15 m, the SE will visit the site. DPRs
which have been checked on site by SE shall be so certified.
 The AE/EE shall record a certificate in form F9-B to the effect that they have checked the required percentage
of DPRs at site and are satisfied with the content and quality, before sending the DPR to the STA (s). The
certificate will be sent alongwith the DPRs.
7.3.1 The primary responsibility for the accuracy of the provisions in the DPR shall rest with the Executive
Engineer. The Executive Engineer shall check at least 20% of the DPRs on site. He shall personally himself
satisfy that:
 the proposed road links form part of the Core Network and the priority criteria laid down by MORD from
time to time.
 adequate road land is available.
 all surveys and investigations have been done with due diligence.
 the Transect Walk has been conducted by Junior Engineer/Assistant Engineer and issues arising have
been resolved.
 leads of materials have been assessed correctly.
 rates of work items are reasonable.
 all designs have been done correctly.
 the overall cost of the project is reasonable; and
 safety requirements have been incorporated.
7.3.2 The estimates for each work under the PMGSY shall be made in two parts, viz,
 first part comprising of the estimate for the construction of the road, and
 the second part comprising of the estimate of year-wise routine maintenance for 5 years with details of
BOQ items to be included.
7.3.3 Scrutiny by SEs
The Superintending Engineers (SEs) are required to conduct a scrutiny of the proposals prepared by the PIUs,
in regard to conformance to guidelines, design standards, specifications, safety requirements, cost etc. The
SEs are expected to examine the proposals personally, on a random basis and do a detailed check of at least
10 percent of the proposals.
Cross-drainage structures having a length of 15m or more should be inspected at site by the SEs or higher
officers, who shall confirm the need for the structures and approve the design.

Operations Manual for Rural Roads


97
National Rural Roads Development Agency

7.4 SCRUTINY BY STAs


Ministry of Rural Development has identified in consultation with each State Government, reputed Technical
Institutions to scrutinise the project proposals prepared by the State Governments, provide requisite technical
support to the State Governments, and undertake Quality Control tests upon specific request. These are being
referred to as the State Technical Agencies (STA). The coordination of jurisdiction of the STAs would be performed
by the NRRDA, who may add to or delete from the list of institutions, as well as to entrust specific tasks from
time to time. The Ministry of Rural Development/ NRRDA may from time to time identify additional technically
qualified agencies to provide these services to the State Governments and to perform such other functions as
may be necessary in the interest of the Scheme.
The PIU will forward the proposals alongwith the Detailed Project Reports to the State Technical Agencies for
scrutiny of the design and estimates. The Proformae F-1 to F-9 will form part of the DPR. These will be forwarded
at the level of the Superintending Engineer or the supervising officer of the PIU along with road-wise checklist
in the Proforma ‘C’ of Annexure 7.2. A summary of the road works will be prepared in Proformae ‘B’
(Annexure 7.2).
The DPRs are to be scrutinised by the State Technical Agency (STA) in the light of the PMGSY Guidelines, IRC
Specifications as contained in the Rural Roads Manual IRC SP 20: 2002 the specification for Rural Roads and
the applicable Schedule of Rates based on the analysis of Rates for Rural Roads.
Before commencing with the scrutiny of DPRs the STA will check that certificate in Form 9-B has been recorded
and informed to tally with the certificates on the DPRs.The STA will then log into the OMMS with their password
and check that the proposals for which the DPRs have been sent have been entered in the ‘Proposals Module’.
Only such DPRs will be checked whose data has been entered.
The STA will check all the DPRs for their correctness. If minor shortcomings are noticed, they will be brought to
the notice of Engineers of the Executing Agency to get them corrected on the spot. However, if major mistakes/
errors are noticed in a DPR, it will be returned with a signed endorsement giving the nature of the change
required. Further investigations, if required, will be suggested to the Executing Agencies in order to rectify
deficiencies. Difference of opinion on any issue are to be sorted out among STA, PIU and Senior Engineers.
Such discussions will be coordinated by the SQC. If a consensus is not possible, the matter will be referred to
NRRDA through the Chief Engineer for necessary clarification/ decision.
The STAs may, while scrutinising the DPRs
 Ensure that the proposals are for new connectivity as long as unconnected eligible habitations remain.
Upgradation is to be considered only after all unconnected habitations 500/250 (as applicable) are connected
in the District and a certificate is given by the PIU to this effect.
 Check that the proposals are part of the Core Network.
 Verify that Associated through Routes if taken are appropriate for upgradation/renewal as per PCI and age
and all subsidiary links as per CNCPL have been taken.
 Check that Land Availability Certificate and Transect Walk proceedings are attached.
 Check that the pavement design is as per the provisions in Rural Roads Manual (RRM) IRC SP: 20: 2002
for all the layers. In particular, they will examine the data of the traffic and ensure that all cases of traffic
exceeding 45 CVPD are adequately justified. They will also analyse the CBR values. In all cases where
CBR is below 3, it shall be ensured that soil stabilization measures are included. Link Roads to habitations
with population below 1000 should be designed as unsealed roads of appropriate design in view of the
likelihood of traffic being below 15 CVPD. Where the target habitation is below population 500, the
carriageway width may be kept as 3.0 m instead of 3.75 m.
 Check whether the soil tests have been carried out and traffic has been estimated properly.
 Investigate economies in use of materials, including soil stabilization and use of alternative/ local material.
 Check the geometric design parameters and make sure that they are as per RRM/Guidelines.
 Ensure that a proper drainage plan has been worked out.

98 Operations Manual for Rural Roads


Scrutiny of Detailed Project Reports

 Verify that the method of flood and waterway computations is satisfactory and check the design of CD
works for suitability as per the guidelines and given site conditions.
 Check whether the CD works require additional protection works based on the site conditions.
 Check the items and estimation of BOQs and the cost as per Standard Rate Analysis and SSR.
 Verify whether suitable and adequate provisions are made for PMGSY logo, signs, Km & Hm stones and
guard stones as required.
 Check that lump sum provision for each year of the 5 years of routine maintenance has been adequately
provided in the BoQ, as per NRRDA guidelines.
 Visit the site if so requested by the PIU for advice, or where it is felt that the design needs site inspection.
 Point out the short-comings and offer suggestions for their rectification (major defects shall be intimated in
writing).
At the end of the scrutiny, the STA will complete and countersign the checklist filled and signed by PIU Engineers
in Proforma C and certify to the effect that the Design and Estimation are as per the data and SSR provided by
the PIU and may be cleared. The check list in Proforma C signed by the Engineers and STA shall be in
quadruplicate. Two copies will be sent to SRRDA, one will remain with STA and the fourth will be retained with
the PIU along with DPR. A consolidated summary report will be sent on format given in Annexure 7.3 by the STA
to the NRRDA and to the Executing Agency.
The State Technical Agencies, after completion of the scrutiny of all DPRs of the Executing Agency shall also
send a detailed note on the experiences on the scrutiny of the project proposals and communicate to the
Executing Agency as well as NRRDA. The Executing Agency shall study the observations of the STA, ensure
necessary corrections in the current proposals, and use them for future guidance of PIUs.
7.5 COMPILATION BY PIUs
The scrutinized copy of the DPR will be retained with the PIU. The DPR corrected on the basis of scrutiny by
STA shall be forwarded to the SRRDA along with Forms F1 to F9 (duly updated) and MP-I and MP-II containing
details of proposals made by MPs and proposals accepted/ not accepted along with specific reasons.
7.6 UPLOADING OF TENDER DOCUMENTS
After compilation of DPRs by PIU, the PIU will prepare the bidding document for every package as detailed in
Para 8.6. The above details will be filled up into the Draft Tender Document module of OMMS and draft bidding
document will be generated. As soon as the Ministry of Rural Development clearance is received and technical
sanction is accorded by the competent authority, the necessary input regarding dates and modifications in
respect of other items will be carried out by the PIU in the draft bidding document and the final bidding document
will be published on the website.
7.7 SUMMARY OF PROPOSALS
The SRRDA will consolidate the proposals from each PIU, after verifying that they have been duly scrutinised
by the respective STAs and Tender Documents have been uploaded in the Project module. They will then
prepare the State Abstract and send all the Project proposals to the NRRDA alongwith the Proformae MP-I and
MP-II of each District, the compiled MP-III for the State as well as the proformae prescribed by NRRDA as brief
for the Empowered Committee.
Proformae A and B (Annexure 7.2) give the forms for summarising the district-wise proposals and package-
wise proposals. Form A will be signed by the State Secretary of the Nodal Department on the basis of Form B
of all the districts.

7.8 SUBMISSION OF PROPOSALS TO NRRDA


The clearance for the estimates for construction of road and related works shall be provided by the MoRD, but
the clearance for the estimate for routine maintenance shall be provided by the State Government. The provision
for the funds related to maintenance shall be done by the State Government. Before submitting the proposals

Operations Manual for Rural Roads


99
National Rural Roads Development Agency

for the construction of roads and related works for clearance to the Empowered Committee, the State Government
shall give administrative approval to the estimate for routine maintenance if already not done as described in
para 4.2.7, and furnish a certificate to the effect that provision of funds for maintenance of PMGSY roads will be
made annually in the State Budget. Each year’s proposals will be cleared by the MoRD only if adequate provision
has been made for the maintenance of PMGSY roads already constructed.
All the summaries (Forms A and B) and Checklists (Form C, Annexure-7.2) are to be bound together for each
State and are to be submitted to the NRRDA.

7.9 APPROVAL OF PROPOSALS


The NRRDA will scrutinize 15% of DPRs on a representative basis as well as all proposals falling on C-curve,
listing the scrutinized DPRs and shall record a technical note on that basis. The NRRDa will also check that the
Tender Document have been uploaded in the Project module. Thereafter, NRRDA will process the proposals
and submit them to the Empowered Committee for clearance as given in Chapter 4.

7.10 ADMINISTRATIVE APPROVAL AND TECHNICAL SANCTION


The Administrative Approval and Technical Sanction to the works cleared by the MoRD shall be accorded by
the competent authority as per the State’s rules.

7.11 SCHEDULE OF ACTIVITIES


Table 7.1 gives the illustrative schedule of activities and the time allotted.

Table 7.1
Schedule of Activities in Connection with Proposals
Sl. Activity Start Finish No. of
No. Days
1 Distribution of amount district-wise 30th June
2 Preparation of list of proposals at district level by the District 1st July 15th Aug. 45 days
Panchayat (including obtaining suggestions from MPs etc).
3 Clearance by State level Standing Committee of district 1st Aug. 31st Aug 30 days
proposals (clearance may be State or Agency wise).
4 Preparation of DPRs by PIU’s (preparation may be phased 15th Aug 30th Sept 45 days
out as per clearance).
5 Scrutiny of DPRs by STAs (scrutiny may be phased out in 30th Aug 30th Oct 60 days
consultation with STAs so that batches of DPRs are sent to
STAs for scrutiny and clearance within 1 month period).
6 Forwarding of proposals to NRRDA (Consolidated 1st Nov
for entire State)
7 Clearance by Empowered Committee 5th Nov 15th Nov 10 days
8 Administrative Approval and Technical Sanction 15th Nov 22nd Nov 7 days
th th
9 Tendering 15 Nov 30 Nov 15 days
th
10 Contracting By 15 Feb.

For Hill Roads, the above activities (Items 1-5) may be rescheduled to give adequate time for survey, investigations
and project preparation, but adhering to the overall dates for scrutiny of DPR. The Schedule suggested above
is illustrative and the States may workout similar schedules maximizing the duration of working period in the
respective State.

100 Operations Manual for Rural Roads


ANNEXURE-7.1
FORMAT F-1
(See Para 7.2)
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
SUMMARY SHEET

Name of the Code Total No. of Unconnected habitations


Block Habitations
>1000 500-999 250-499 <250 Total Eligible
Habitations
Total Eligible

Type of No. of Total Length of No. of New CD Estimated Cost (Rs Lakhs) No. of Unconnected
Proposal Roads Roads (km) Structures Habitations connected /
Pavement from CD Structure Total [(5)+(6)] Connected habitations

Operations Manual for Rural Roads


Format-F5 from Format-F6 benefited

1 2 3 4 5 6 7 8

New
Connectivity

Associated
Through Route

Upgradation

Other
Upgradation

Total

101
Scrutiny of Detailed Project Reports (Annexures)
102
FORMAT F-2A
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
ROADS PROPOSED IN PMGSY FOR RURAL CONNECTIVITY (PAVEMENTS LAYERS)

District Block
National Rural Roads Development Agency

Details of Thickness & Cost for Pavement Layers (Rs. In Lacs)


Name of Name of New Facility Road Existing
Surfacing Dressing
Block Habitations construction accessed Length Surface
Connected / (N)/ Associated (Km) Type Details Clearing Earth- Subgrade Sub-Base WBM WBM B.O.E K.C. PRIMER Road Total
Benifited Through Route Grubbing work Preparation G.S.B. G2 G3 EDGING DR- & TACK P.C. Seal Furniture Cost for
(A)/ upgradation G.S.B.I G.R II AIN/ COAT Coat Pavement
(U) CUT- Rs. lakhs

Sl.No.
STONES
Form To N A U
1 2 3 4 5 5A 5B 6 7 8
Thickness (mm)

Cost (Rs) in Lacs

Thickness (mm)

Cost (Rs) in Lacs

Thickness (mm)

Cost (Rs) in Lacs

Thickness (mm)
Cost (Rs) in Lacs

Thickness (mm)

Operations Manual for Rural Roads


Cost (Rs) in Lacs

Thickness (mm)

Cost (Rs) in Lacs

Thickness (mm)

Cost (Rs) in Lacs

Thickness (mm)

Cost (Rs) in Lacs

Thickness (mm)

Cost (Rs) in Lacs

Thickness (mm)

Cost (Rs) in Lacs

Cost (Rs) in Lacs


FORMAT F-2B
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
ROADS PROPOSED IN PMGSY FOR RURAL CONNECTIVITY (CROSS DRAINAGE STRUCTURES)

District Package No.

Existing CD Structure by Type Details of Proposed CD Structure by Type


Total Total
Name Block Habitations Road Hume Pipe Box/ Arch. Cost Cost of
Hume Pipe Box/ Arch. Minor Bridge
of Code Name of Road Connected Population Length Culvert Culvert Minor Bridge of Pavement Total Cost
of Culvert Culvert
Proposed from of ROAD

Sl.No.
Block / Benifited (Km)
CD Format [(18+19)]
Structures F-5
No. Dia No. Length No Length
No. Dia No. Length No Length
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
1 Cost (Rs)
2 Cost (Rs)
3 Cost (Rs)
4
Cost (Rs)
5
Cost (Rs)
6 Cost (Rs)

Operations Manual for Rural Roads


7
Cost (Rs)
8
Cost (Rs)
9
Cost (Rs)
10
Cost (Rs)
Total
Cost (Rs)

Junior Engineer Assistant Engineer Executive Engineer

103
Scrutiny of Detailed Project Reports (Annexures)
104
FORMAT F-4
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
DETAILS OF EXISTING ROADS (FOR UPGRADATION)
PACKAGE NO.
DISTRICT:
BLOCK(S):

Traffic per day*** Existing Road Details


Sl.No. Name of the Road Road Road Facilities
National Rural Roads Development Agency

Length connecting to accessed Total


Land Road Embankment WBM Layer Bituminous Layer
(in km) * (Use Total LCV/Truck/Bus
Motorised Agricultural Width Width Height Width Width Thickness Type**** Width Thickness
A/B/C/D)**
Tractor/Trailer (m) (m) (m) (m) (m) (mm) (m) (mm)

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

*Road Connecting to NH/SH/MDR/ODR/VR


**Use A = Market, B = Education facilities, C = Health Centre and D = Combination of previous
***Where actual figure is not available, Estimated figure may be included
****Type BM/MSS/DMC
Format F- 4A
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
Association of Routes

Operations Manual for Rural Roads


Package Primary Associated PCI Age Whether Other Non- Whether Habitation served with
No. Network Through proposed for conformance includes in Population
Route (ATR) Upgradation (U) subsidiary to the package
No. Habitation or Renewal(R) ATR Y/N
served
(with
popn.)
FORMAT F-6
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
COST ESTIMATE FOR ROADS CONSTRUCTION

Package No.
District:
Road From:
Length of the Road (km): Block:

Sl. No. Description of Item No. L B D/H Quantity Unit Rate Amount
(m) (m) (m) (Rs) (Rs)

1 2 3 4 5 6 7 8 9 10

FORMAT F-7

Operations Manual for Rural Roads


PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
COST ESTIMATE FOR ROADS CONSTRUCTION OF CROSS DRAINAGE WORKS

Package No.__________
District: ______________
Road From: _____________
Type of cross Drainage Works : ________________________ Block: ________________

Sl. No. Description of Item No. L B D Quantity Unit Rate Amount


(m) (m) (m) (Rs) (Rs)

1 2 3 4 5 6 7 8 9 10

105
Scrutiny of Detailed Project Reports (Annexures)
106
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
RATE ANALYSIS
FORMAT F-8

State: District: Package No.:


Road from to

Material Source Lead(in Km)


National Rural Roads Development Agency

Stone
Bituminous
Cement
Hume Pipes
Any Other

Analysis Of Rates:

Sl. No. Sl No. as per MoRD Description Units Qty. Rate


SDB for Rural Roads (Rs) Amount (Rs)

A. Construction Activities

Operations Manual for Rural Roads


Total
B. Maintenance
Activities(Year wise)

Total

Note:
1. Rate Analysis shall cover all the items such as Site Clearance, Earth Work, Drainage, Granular Sub Base, & Surface Course, CD works, Traffic Signs, PMGSY
Board & Logo& Maintenance activities
2. Where local material is used at site and the specifications & rate analysis are not found in BOS &SDB, for Rural Roads ,the analysis &nomenclature of the item can
be suitably used based on other standards such as PWD Schedule or Rate or assessment based on field observation.
3. Completed items rates including lead for carriage of materials should be shown
Scrutiny of Detailed Project Reports (Annexures)

FORMAT F-9A

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)


CERTIFICATE OF GROUND VERIFICATION FROM EXECUTIVE ENGINEER / HEAD PIU

1. a) Certified that the Land width for the Road is available and that no additional land is required; or
b) Certified that land width for the Road is likely to be available as certified by the Panchayats.

2. a) Certified that no forest land is involved along the entire road way; or
b) Certified that the case for permission under Forest conservation Act has been moved to the Forest
Department on (Date).

3. Certified that the DPR has been checked at site by

AE EE SE
On date ……………………..
( DPR wise summary in Format F9-B)

Executive Engineer,
Head of PIU.

FORMAT F-9B

LIST OF DPRS VERIFIED ON GROUND:

# DPRs seen on ground by DPR Nos % of total number

1 AE

2 EE

3 SE

Head of PIU

Operations Manual for Rural Roads


107
National Rural Roads Development Agency

Annexure-7.2
(See Para 7.4 & 7.6)

PROFORMA-A

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)

DISTRICT WISE SUMMARY OF THE PROPOSALS FOR THE YEAR

Sl.No. District Package No. of Length Value Rs AV. Cost/ Km


No. Habitations Km (Lakh) Rs (Lakh)
covered

Const. Maint. Const. Maint.

1 3

Total

2 3

Total

5
etc.

No. of Total Habitations Length Value AV. Cost/ Km


State Dists. Packages Covered Km Rs (Lakh) Rs (Lakh)
Summary

Signature :
Name :
State Secretary :

108 Operations Manual for Rural Roads


PROFORMA-B
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
PACKAGE SUMMARY

Package Number :
District :
State :
Sl. No. Name of Block Name of the Road Type of Proposed Cost of No. of CD Cost of CD Total estimated Average Cost
Proposal length Pavement works Works Cost per Km
From To *N/U Km Rs. Nos Rs. Rs. Rs.
Const. Maint. Const. Maint.

Operations Manual for Rural Roads


Total Estimated cost of the Package: Rs. Lakh
* N-New Connectivity U-Up gradation
Prepared By: Signature:
Name:
Designation:
Checked By: Signature:
Name:
Scrutinized By: Signature:
Name:
Technical Scrutiny
done By: Signature:
Name:
Coordinator
STA: Signature:
Name:

109
Scrutiny of Detailed Project Reports (Annexures)
National Rural Roads Development Agency

PROFORMA-C

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)


CHECK LIST FOR P.I.U & S.T.A
(FOR INDIVIDUAL ROAD WORKS)

To be filled by PIU

1. Location:- State:- District:- Block:-

2. Package No.:-

3. Name of the Road: From: To:

4. Length (Km) Total Km In Built up area: Km In Open Area: Km

5. Estimated Cost Rs: Lakhs Cost Per Km Rs. Lakhs

6. Type of Proposal: New connectivity/ Up gradation

 If the proposed road is a New connectivity


- Is the road a part of core network YES/NO

- Name of the unconnected Habitation (s) (to be crosschecked with CN-6)

- Does the Proposed Road lead up to the Habitation for which it is Supposed to provide
connectivity (In other words are you sure that the road is not being made partially?) YES/NO

- Does the Proposed Road connect the unconnected Habitation to


(a) Another Habitation having All-weather road. (a) (b)
(b) Directly to an all weather road.
If (b), indicate the nature of road to which the proposed road leads. RR MDR SH NH

 If the proposal is for upgradation


- Is the road a part of the core network YES/NO
- Is it associated Through Route or not YES/NO
(In case if it is not associated TR)
Whether
PCI, has been done YES/NO
Age of Road given YES/NO

- Is it certified that there are no other Unconnected Habitation in the district. YES/NO

- Population sub served by the proposed road

7. a) Whether the Proposed Road has the desired carriageway width, YES/NO
Roadway width and Road Land Width (RLW).
In the Built Up In the open
b) Indicate the actual widths of the following for the Proposed road. Area (m) Area (m)
a) Carriageway
b) Roadway
c) Road Land Width

110 Operations Manual for Rural Roads


Scrutiny of Detailed Project Reports (Annexures)

INDEX MAP (Not to scale)


R
O H1 CD1 H2 CD2 H3
A
D
X 0.9 1.5 2.1 2.8 3.2 km
Y
H1, H2, H3 – Habitations
CD1, CD2 – Cross Drainage Works
8. Base year traffic volume

Total
Bus/Truck LCV/ Cars/ Three Two Cycle Cycles Bullock Motorized Non-
Mini Bus Vans/ wheelers wheelers Rickshaw Carts motorized
Jeeps

9. Growth rate adopted (%): Projected Traffic: CVPD

10. Sub grade CBR

Chainage

Design CBR (%)

11. Cost Details


A. Clearing and Grubbing Cost in Rs.

B. Pavement Components

For Black Top For Unsealed

Item Thickness Cost Item Thickness Cost (Rs.)


(Rs.) (mm)

Earth work Earth Work

Subgrade Preparation Subgrade Preparation


(GSB)

WBM-1 Wearing Surface

WBM-2

WBM-3

C. Bituminous Layers

Prime Coat

BM/ BBM

Tack Coat

MSS

PMC with Seal Coat

Operations Manual for Rural Roads


111
National Rural Roads Development Agency

D. CD Works No. of Existing CD Works:

Do they require any improvement YES/ NO

If Yes, cost of improvement Rs.

No. of proposed CD Works

Cost of Proposed CD Works

E. Protection Works Length: Cost:

F. Side Drains (if provided) Length: Cost:

G. Road Logo, other Road Furniture Cost:

H. Five Year Routine Maintenance Yr 1 Cost % of Const. Cost


Yr 2
Yr 3
Yr 4
Yr 5

12. Whether the road has Geometrics as YES/ NO


per Rural Roads Manual (RRM)

13. Whether CD works/ Protection works are YES/ NO


provided as per RRM

14. Whether the Cost estimates are as per standard YES/ NO


data analysis and S.S.R

Certified that information provided is true

Prepared By: Checked By: Scrutinized By:


A.E. E.E. S.E.

To be filled by S.T.A

Name of the STA:


15. If the proposal is for new connectivity
 Have you satisfied yourself that the proposed Road is a part Yes/ No
of the Core Network.
 Is the unconnected habitation(s) part of list of Yes/ No
unconnected Habitations as per CN-6.
 Does the Proposal ensure full connectivity. Yes/ No
16. Are you satisfied with the following
 Engineering Surveys. Yes/ No
 Soil/ Material Investigation Yes/ No

112 Operations Manual for Rural Roads


Scrutiny of Detailed Project Reports (Annexures)

 Traffic Surveys/ Estimation Yes/ No


 Hydraulic Studies Yes/ No
17. Is the design of the following elements as per Rural Roads Manual:
 Alignment & Geometric Yes/ No
 Pavement Design Yes/ No
 CD works and protection Measures Yes/ No
 Side drains Yes/ No
 Drainage Layer Yes/ No
18. Does the Estimation conform to Standard rate analysis and SSR Yes/ No
19. Does the Proposal have provision for
 PMGSY Logo Sign Boards Yes/ No
 Km/ Hm Stones Yes/ No
 Guard Stones (where necessary) Yes/ No
 Traffic Sign Boards (as necessary) Yes/ No
 5 year routine maintenance, estimated on lump-sum basis
20. Specific remarks, if any, by STA

Certified that the Design and Estimation for the Proposed Roads works are based on the data and SSR
provided by Engineers. The Proposal may be cleared.

Technical Scrutiny: Coordinator:


Done by S.T.A

Signature Signature
Name Name

Operations Manual for Rural Roads


113
National Rural Roads Development Agency

Annexure 7.3
(See Para 7.4)
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
Format for Consolidated Report of the STA
On the Project Proposals under PMGSY.

1. State: Phase: Year:

2. Names of the Members of the STA involved in the Technical Scrutiny.

3. Whether Pre-DPR meeting was held with SRRDA and DPIUs.

4. Summary of the Project Proposals scrutinized indicating district wise and road wise details of length and
cost. The summary includes the No. of Packages and total value.

5. Whether schedule for scrutiny was fixed in advance (give details) and difficulty in adhering to schedule.

6. Actual scrutiny process and time taken for scrutiny (Please indicate the dates).

7. Interaction of the Engineers of the Executing Agencies with the STAs.

8. Major deficiencies observed during scrutiny with details.

9. Reliability of data obtained through investigations and used in the design/ estimation.

10. Compliance of the provisions/ instructions given in the guidelines/ circulars/ operations manual/ IRC
codes etc. in the preparation of DPRs including Environmental/RR/ Road safety aspects etc.

11. Levels of response from the Senior Engineers of the Executing Agencies for the suggestions given by
the STAs for revision/ modifications in the DPRs.

12. If DPRs outsourced, perceived level of competence of outsourced consultants and suggestions.

13. Overall comments and impressions of the STAs, if any, on the process of the preparation of DPRs and
their technical scrutiny.

Signature and
Name of the Coordinator STA

114 Operations Manual for Rural Roads


Procurement

CHAPTER 8
PROCUREMENT

8.1 STANDARD BIDDING PROCESS


8.1.1 After the project proposals have been cleared and Technical Sanction has been accorded, the Executing
Agency will invite tenders. The well-established procedure for tendering, through competitive bidding, will be
followed for all works under the Programme.
As provided in the guidelines of the programme, the Executing Agencies will follow the Standard Bidding Document
(SBD) for Construction and Maintenance of Roads under Pradhan Mantri Gram Sadak Yojana prescribed by
the NRRDA. The SBD is available on PMGSY and OMMS websites. The SBD will be made State specific based
on 36 parametric values to be provided at State level. The response on these parameters will first be cleared by
NRRDA and then applied to the SBD. The instructions and 36 point checklist for preparing the State-specific
Bidding documents for PMGSY Works are given in Annexure 8.1. Change in any provisions of the bidding
document except those provisions which have been indicated in the list of 36 parameters by the State Government
is not permissible. In case it is proposed to change the response to any of the 36 parameters after clearance of
NRRDA, prior concurrence of NRRDA will need to be obtained.
8.1.2 All the States shall follow the State specific Standard Bidding Document, prescribed by the NRRDA, for
all the tenders. The Standard Bidding Document, inter alia, provides for:
 A two envelope tendering process consisting of the Technical Bid and Financial Bid (except in the case of
some World Bank works). The Technical bids to be opened first and evaluated and the financial bids of
only those bidders to be opened whose technical bids are found responsive after evaluation.
 Time frame for various activities in the tendering process.
 Clear qualifications for the contractor to qualify for Bidding.
 Evaluation of Bidding Capacity in each case.
The time frame for various activities in the tendering process is given below:
Particulars of Action Days Cumulative
Total Days
Advertising the Press Notice Time Count Starts 7
Sale of Bidding Documents 15 Days
Pre-bid meeting, at least ten days before the last date for submission of bids
Issue of corrections/clarifications at least six days before the last
date of bid submission
Last Date for submission of bids and opening of Tenders (Opening of 21 28
outer envelope and technical Bids)
Evaluation of Technical Bids and notification of Results 10 38
Opening of Financial Bids 1 39
Evaluation and Approval of Financial Bids 10 49
Communication of Approval 7 56
Submission of Performance Security, Agreement and Work-order 15 71
Commencement of Work 15 86

Operations Manual for Rural Roads


115
National Rural Roads Development Agency

All State level formalities relating to the issue of tender notice, finalisation of tender and award of works shall be
completed within 71 days (120 days in case of re-tendering).
8.1.3 As a result of adoption of the Book of Specifications entitled as Ministry of Rural Development –
Specifications for Rural Roads, August 2004 published by Indian Roads Congress, the Section 5 of the bidding
document has been modified to define the above publication as ‘Specifications’ for the purposes of bidding
under PMGSY. NRRDA has also issued the first amendment to the SBD effective for all tendering w.e.f. 15th
February 2005. Brief description is given below:
 The provisions to obtain address and the contact details of the contractor at the time of Technical offer and
submission of bid form have been modified.
 Provisions of communication through fax and other electronic means have been incorporated.
 Provision for deployment of machinery and establishment of field laboratory required to ensure the quality
of works as has been made in Contract Data as well as in GCC. Failure to deploy machinery and equipments
has been specifically included as a fundamental breach.
 Provision of part possession of the work site has been made but at the starting of the work, the Engineer
will be required to handover possession of at least 75% of the site.
 Provision has been made for refund of 50% of retention amount and additional performance security for
unbalanced bids after the completion of construction work.
 Provisions of issue of completion of construction works as well as maintenance work have been modified.
 Provision of final account and final payment of construction work and routine maintenance has been
modified.
 The activities of routine maintenance and their frequency have been modified as per Ministry of Rural
Development Specifications for Rural Roads, August 2004.

8.2 SCOPE OF WORK TENDERED


All the projects scrutinized by the STA and cleared by the Ministry shall be accorded Technical Sanction by the
competent State Authority before issue of Tender Notice. In case of variations of upto 10% in a DPR, the State
may continue with the tendering process, after informing NRRDA and making changes in the OMMS. Variations
will be adjusted within the overall District allocation and failing that, within the overall State allocation. In cases
where variation exceeds 10%, prior approval of NRRDA will be sought before tendering. Such packages may
be excluded and tendering process continued with the other packages. After Technical sanction works will be
tendered as such, and no changes shall be made in the work without the prior approval of the NRRDA. The
complete items of work (construction and maintenance) will be put to tender since issue of any materials to the
Contractors is not allowed, and the executing agencies are not allowed the separate procurement of the material
like Hume pipes, cement, steel and bitumen etc. for issue to the Contractor.

8.3 SPECIFICATIONS, RATES AND BILL OF QUANTITIES


The Book “Specifications for Rural Roads IRC-August, 2004” shall be adopted as specifications for the works
of rural roads under PMGSY. The rates and / or standard nomenclature of items of work contained in Bill of
Quantities for the purposes of road works under the PMGSY will be taken from the “Schedule of Rates for Rural
Roads” of the respective State Governments which will be prepared from the “Standard Data Book for analysis
of rates IRC-September, 2004” published by Indian Roads Congress for the Ministry of Rural Development.

8.4 CALLING OF TENDERS BY SRRDA AND BID CAPACITY


8.4.1 Two envelope system the Standard Bidding Document envisages submission of bids in two envelopes
marked respectively, “Technical Bid” and “Financial Bid”. On the basis of the eligibility criteria laid down in the
Instructions to Bidders (ITB), the Technical Bids will be evaluated, and a list will be drawn up of the responsive
bids whose Financial Bids are eligible for consideration.

116 Operations Manual for Rural Roads


Procurement

8.4.2 Assessing Bid Capacity: The Standard Bidding Document as per Clause 4.6 provides for calculation of
‘Assessed Available Bid Capacity’. The bidders who meet the minimum qualification criteria will be qualified
only if their available bid capacity for construction work is equal to or more than the bid value under consideration.
As per Clause 29 of ITB, the employer will award the contract to the bidder whose bid has been determined to
be within the available bid capacity adjusted to account for his bid price which is evaluated the lowest in any of
the packages opened earlier than the one under consideration. The assessment of ‘Assessed Available Bid
Capacity’ is carried out during evaluation of technical bids. The purpose of the Assessed Available Bid Capacity
(AABC) is to ensure that the works being awarded to the contractor do not exceed what he can reasonably be
expected to complete, given his earlier performance as well as ongoing commitment. Since in PMGSY proposals
of the entire State are generally cleared at one go and a contractor can bid for a number of packages, it may
happen that he is the lowest bidder for more works then he has the capacity to complete within the stipulated
period. Accordingly, it is necessary to ensure that the sum total of works awarded to him does not exceed the
AABC. This may be done by centralizing the process and sequencing it through an objective rule, so that at the
time of award of each sequenced package, any work awarded previously in the sequence to the same contractor
is deducted from his AABC, in order to work out the net AABC, and then award the package to the contractor
only if the net AABC exceeds the bid value. The centralization for purposes of working one net AABC may be
done at the level of the SRRDA, and any one of the following sequencing rules uniformly applied for determining
the award. An alternative procedure which meets the expected standards of fairness and transparency may
also be used, under intimation to the NRRDA. In the interest of transparent procurement, it is necessary that
the sequencing rule be explicitly mentioned in the Notice Inviting Tenders.
8.4.3 Sequencing Option:
Option 1: Bidders may be asked to indicate in each technical bid the order of opening of their bids, so that the
financial offers corresponding to the qualifying technical bids are opened in that order the his AABC is exhausted.
Remaining financial offers of the bidder will be kept unopened.
Option 2: Financial bids of all qualifying bidders may be opened and bids arranged in order with that package
where the difference between potential L-1 and potential L-2 is the greatest followed by the one in which it is
next greatest and so on. L-1 will be awarded packages till his bid capacity is exhausted. The process will be
repeated for the remaining packages based on difference between earlier potential L-2 (now potential L-1) and
earlier potential L-3 (now potential L-2) values etc.
It may be noted that negotiation with bidder other than L-1 is not permitted. The determination of L-1 needs to
be done carefully, and the lowest bidder whose net bid capacity is lower then his bid value would not be
qualified to be declared L-1 for obvious reasons.
In case tenders are invited independently at PIU level, due to differences in dates and the inability of Bidders to
indicate order of opening in case of option 1 the Bid capacity may not be applied properly. As such, it is
preferable that, to facilitate proper bid capacity evaluation, tendering should be done centrally at SRRDA level.

8.5 PREPARATION OF BIDDING DOCUMENT


Bidding Documents for each package will be prepared by completing the following:
a. Section 1: List of important Dates of Bids – The list of important Dates of Bids will be completed by
filling-up the prescribed spaces.
b. Notice Inviting Tenders (NIT): The NIT will be completed by filling-up the prescribed spaces and Press
Notice will also be generated.
c. Press Notice: The notice for publication in the News papers will be completed by filling-up the prescribed
spaces.
d. Appendix to ITB: The basic information regarding requirement of equipments, technical personnel and
other details required for the bidder to understand the work shall be filled up in ITB. The information in this
Section is very important and the PIU is expected to fill up the information regarding requirement of machinery

Operations Manual for Rural Roads


117
National Rural Roads Development Agency

and equipments on the basis of the type of and quantities of items of work, similarly the information
regarding the equipments for the field laboratory will also depend upon the type and quantity of items of
work.
e. Contract data: The basic contract data shall be filled up in the prescribed format.
f. Special Conditions of Contract: If there are any special conditions of contract, these are to be shown in
Section-4.
g. Specifications: The specifications to be adopted for the construction and maintenance work have to be
clearly shown in this section.
h. Drawings: The list of drawings has been given in the SBD. All the drawings have to be attached in this
section.
i. Bill of Quantities: There are two formats for Bill of Quantities. If item rate type of tendering is allowed by
the State, the format for BOQ will be filled up by giving full and clear description of items and quantities.
The contractor is required to fill up rates in figures and words. In case percentage rate bids are allowed,
the BOQ should be filled up completely wherein the description of item, its reference to Schedule of Rate,
quantity, unit, rate and amount columns will be filled up. However, the contractor is required to fill up the
form of bid wherein the rates, percent above, below or at par will be indicated.
In both the cases the routine maintenance item for every year upto five years (the lump-sum amount per km.)
shall be mentioned in the estimate and the contractor is required to fill up his per km. lump-sum amount.
8.6 GENERATING BIDDING DOCUMENT FROM OMMS
The State Specific Bidding Document is available on OMMS website which is based on the State’s response on
36 action points. After the clearance of the DPRs from the STA, the PIU will prepare the package-wise bidding
document by filling up the details in draft tender document module of proposals as given below:
 For entering the Press NIT details Input Format I (Publish tender notice) will be filled up.
 For generating the List of Important Dates etc. Input Format II (Package wise details) will be filled up.
 For generating ITB and Contract Data, Input Format III (ITB and Contract Data Format) will be filled up.
 The BOQ will be attached as MS-Excel or MS-Word file.
While scrutinizing the DPRs, the NRRDA will also scrutinize the tender document with a view to see that the
tender document has been prepared in accordance with the requirement of the work. As soon as the clearance
of the package is communicated by the Ministry of Rural Development and technical sanction has been accorded
by the competent authority of the State Government, the PIU will make necessary entries regarding the dates
or any modifications in other items. After the above modifications are affected, the tender will be published on
OMMS website. The tender notice can be printed out and issued for the press advertisement.

8.7 PRESS ADVERTISEMENT OF NIT


In order to give wide publicity to the tendering process and generate adequate competition, the tenders shall be
published in reputed news papers of the State in local language or English as well as in one national newspaper
in English.
The tender notice for the press advertisement will generally be in the format given in the SBD. Both the
construction and routine maintenance estimate shall be published. In the interest of economy, it is preferable
that the entire or circle wise lot of cleared packages are advertised centrally by the SRRDA in one go. Since
PMGSY places high emphasis on time and quality, States shall take steps to increase competition. As such the
SRRDA may register contractors to whom Notice Inviting Tenders may be sent. They may also be asked to
register online under OMMS so that SMS or E-mail notices can be sent to them. SRRDA may also make
available the Bidding documents at Division, Circle as well as SRRDA level. States shall ensure that all Tender
notices are put out on the Internet under the OMMS in such manner as may be prescribed in the Standard

118 Operations Manual for Rural Roads


Procurement

Bidding Document and associated guidelines of NRRDA. To facilitate response, the Tender notice should
mention that Bid documents are downloadable from the Internet, and necessary steps should be taken to
enable this to be done.
The SRRDA shall at all times update the OMMS tendering module to enable downloading of complete and
up-to-date tender documents including corrigendum’s and amendments.
8.8 SALE OF BIDDING DOCUMENT AND PRE BID MEETING
The sale of bidding documents will be effected as per the schedule. Sale of Tender documents may also be
arranged at Division, Circle and SRRDA levels. In order to allow adequate access to bid document, these
documents may be made available at SRRDA, also on line. (In such cases cost of Bid Documents may be
taken at the time of submission of the Bid).
A Pre-Bid Meeting will be organised on the specified date, place and time (after close of sale of tender documents
and before last date for submission of bids). The meeting may be held at SRRDA in case the number of
packages is not large, or at circle level in other cases. The meeting will be chaired by the officer inviting tender
or an officer at-least of the rank of Executive Engineer. Clarifications given in response to queries may be
circulated by fax/e-mail to all bidders whether or not they attended the pre bid meeting. As such, minutes of the
Meeting will be drawn and circulated to all the bidders as per provisions of clause 9 of ITB.
8.9 RECEIVING OF BIDS
The officers responsible for receiving the bids shall place an appropriate sealed box with a provision of adequate
size of slit to facilitate the insertion of sealed bid envelope which will be termed as ‘Tender Box for receiving
tenders vide notice no………dated …………’ right from the day on which tender forms are issued. Last date
and time for receipt of tenders will also be mentioned prominently. Before the box is sealed by the officer in-
charge, the empty box should be shown to at-least three independent persons and the sealing should be done
in their presence and recorded. It will be responsibility of the said officer to ensure safe custody of the box in
such a way that during office hours the tender box is accessible to the bidders who want to put their bid, but
cannot be tampered with in any manner.
The bidders will be required to put their sealed bids in the tender box. The bids will be received at the specified
places up to the specified date and time. As soon as the time of receipt of bids expires, the officer responsible
shall seal the slit, affixing his signature on the seal, and keep the box in his safe custody till time for opening of
the bids.
8.10 OPENING OF BIDS
The bids shall be opened at the specified place, date and time by the officer authorised, in presence of bidders
or their authorised representatives and will be recorded. The signatures of bidders present (including
representatives) and officers present in the bid opening will also be obtained on the record of bid opening
maintained in the prescribed register (To be prescribed by the State Government). At the designated time, the
meeting to open bids will be held in which the authorised representatives of the bidders and other officers as
decided by the officer in-charge will be present. Late bids will not be allowed and will be returned unopened as
per provisions Clause 19.3 of ITB.
As per clause 19 of ITB, the two separate envelopes marked ‘Technical Bids’ and ‘Financial Bids’ are required
to be placed in one outer envelope and before opening the bids. It will be checked by the officer in-charge that
whether the sealing and marking is as per the provisions.
The outer envelope will be opened first then in case of submission of downloaded bidding documents, the
envelope containing the ‘cost of bidding document downloaded from internet’ will be opened and if the cost of
bidding document is not there, or incomplete, the remaining bid documents or envelopes will not be opened
and bid will be rejected. After this, the envelope containing the ‘Earnest money’ and the ‘Technical Bids’ will be
opened. The envelope containing the ‘Financial Bids’ will not be opened at this time. As a measure of abundant
precaution, the sealed envelopes of financial bid may be got signed from present bidders or their representatives
and this fact may be recorded.

Operations Manual for Rural Roads


119
National Rural Roads Development Agency

In all cases the amount of earnest money, forms and validity shall be announced and after this the bidder’s
name and such other details as the employer may consider appropriate, will be announced in the meeting of
bid opening. The officer in-charge will prepare the minutes of the Bid Opening which will include the information
disclosed to those present in the meeting.
The list of certificates required in submission of bids is at Annexure 8.5.

8.11 TECHNICAL BIDS AND THEIR EVALUATION


8.11.1 The Technical Bid shall comprise of the following:
(i) Earnest Money in a separate cover marked as ‘Earnest Money’.
(ii) If the bid has been prepared in downloaded bidding document from internet, the Demand Draft for the cost
of bidding document in a separate cover marked as ‘Cost of bidding document downloaded from internet’.
(iii) Qualification Information with supporting documents, certificates, affidavits and undertakings as specified
in clause 4 of ITB.
(iv) Undertaking regarding validity of bid as per clause 15.1 of ITB.
(v) Any other information/documents.
(vi) An Affidavit affirming that information submitted in the Bidding Document is correct.
8.11.2 The technical evaluation shall be taken up and completed within five working days of the date of opening
of bids. The officer responsible for evaluation of technical bid may follow the following steps for the evaluation:
(i) Cost of Bidding Document: If downloaded Bidding Document has been submitted without the cost of
tender form, the bid will be rejected.
(ii) Earnest Money: The Earnest Money has to be as per clause 16 of ITB. If Earnest Money is not there or is
not as per the provisions no further evaluation will be required and the bid will be declared non-responsive
and rejected.
(iii) Qualification Information: After the above two points have been disposed off, the examination of qualification
information will be started. The officer in charge will see that all the information prescribed in Section 3
Qualification Information has been duly completed and supported by the prescribed certificates. If the
information furnished in the above section is not supported by desired authentic certificates, that particular
information will not be considered valid. The evaluation of the Technical Bid in respect of Qualification
Information will be based on provisions of Clause 4 of ITB. The evaluation of Bid based on Qualification
Information (QI) may be carried out in the following manner.
 Eligibility of bidder: As per Clause 3 of ITB, the examination of the Constitution and Legal Status of
the Bidder as presented by the contractor in Para 1.1 of QI on the basis of copies of relevant papers
shall be carried out.
 Qualification: As per Clause 4.4 A of ITB, the examination of monetary value of civil construction
work performed in last five years and experience of similar works as presented by the contractor in
Para 1.2 and 1.3.1 of QI on the basis of copies of relevant papers shall be carried out.
 Demonstration of availability of equipments and personnel: As per Clause 4.4 B (b) of ITB, the
bidder is required to demonstrate the availability of owned or hired key equipments, technical personnel
and liquid assets and/or credit facilities as specified in Appendix to ITB. The examination of availability
of owned or hired construction equipments, technical personnel and liquid assets and/or credit facilities
as presented by the contractor in Para 1.4, 1.5, 1.7 and 1.8 of QI on the basis of copies of relevant
papers shall be carried out.
 Production of Certificates: As per Clause 4.4 B (a), the bidder is required to produce an affidavit to
the effect that the information furnished in the bid document is correct, current income tax clearance

120 Operations Manual for Rural Roads


Procurement

certificates and such other certificates defined in Appendix to ITB. The above aspects will be examined
and failure to produce the certificates shall make the bid non-responsive.
 For assessment of bid capacity as per clause 4.6 of ITB the Contractor is required to give the information
regarding maximum value of civil engineering works executed in any one year of the last five years
and value of existing commitments and on-going works. The first information will be available from
para 1.2 of Qualification Information and will be verified from the certificates of Chartered Accountant
and other relevant papers and the second information will be available from para 1.3.2 (A) of
Qualification Information.
 Sub-contracting: As per clause 4.2 (k), the Bidder is required to propose for sub-contracting the
components of work upto a maximum of 25% of the contract price. The Bidders proposal in this
regard as presented by the contractor in Para 1.6 of QI on the basis of copies of relevant papers shall
be examined from the point of view of its approval in case his bid is finally accepted, however, the
Bidder is not authorised to propose for sub-contracting of component of works aggregating to more
than 25% of the contract price.
 Methodology and Work Programme: As per clause 4.2 (l) of the ITB, the Bidder is required to
furnish proposed methodology and programme of construction and quality management plan. The
above information shall be examined for justification of the capacity of the Bidder regarding execution
and timely completion as per specifications within stipulated period.
 Disqualification: Even if the Bidder meets the above qualification criterion, the bids are subject to
be disqualified if the Bidder has made misleading or false representations, has a record of poor
performance and the Bidder participated in previous bidding for the same work and has quoted
unreasonably high or low bids and could not furnish rational justification.
8.11.3 After the detailed evaluation of the bids the employer will determine whether each bid meets the
qualification criterion defined in clause 3 and 4 of ITB, whether the bid is properly signed at designated places,
whether the bid is accompanied by required securities and each bid is substantially responsive to the requirements
of the Bidding Document.
The bid capacity of every bidder will also be calculated on the basis of information furnished by the bidders
during the evaluation of technical bids.
A list of responsive bids will be drawn up whose financial bids are eligible for consideration. The employer shall
inform the bidders whose technical bids are found responsive the date, time and place of opening of financial
bids by telegram or facsimile.
8.12 OPENING AND EVALUATION OF FINANCIAL BIDS
8.12.1 The Financial Bids will be opened at specified place, date and time in presence of bidders or their
authorised representatives and will be recorded. At the designated time, the meeting to open bids will be held
in which the authorised representatives of the bidders and other officers as decided by the officer in-charge will
be present. At the time of opening of financial bid the names of the bidders whose technical bids were found
responsive will be announced. The financial bids of only these bidders will be opened. The financial offers will
be opened following the procedure given in Option 1 or Option 2 of Para 8.4.3, whichever was stated in the NIT.
For the purpose, if Option 1 is being followed, the AABC of all responsive bidders will be announced before
financial bids are opened. In all cases, the rates quoted by the bidder, total bid price and conditions, if any, and
such other details as employer may consider appropriate shall be announced in the meeting of bid opening.
The signatures of bidders present (including representatives) and officers present in the bid opening will also
be obtained on the record of bid opening. The officer in-charge will prepare the minutes of the Financial Bid
Opening which will include the information disclosed to those present in the meeting. The financial Bids of non-
responsive bidders will be returned unopened to the bidders.
8.12.2 The evaluation of financial bids will be carried out to determine the responsiveness of the bid with
respect to remaining bid conditions i.e. the rates quoted by bidder and the priced bill of quantities, technical
specifications and drawings (if provided by bidder). The evaluation of the bid, correction of errors and comparison
of bids will be done as per provisions in Clause 25.2, 25.3, 26 and 27 of ITB.

Operations Manual for Rural Roads


121
National Rural Roads Development Agency

8.12.3 After the evaluation of financial bid in respect of bid conditions the bids will be evaluated in respect of
award criteria as per Clause 29 of the ITB. The substantial responsive bid is the bid which has offered the
lowest bidding price and if the bidders available bid capacity for construction work is equal to or more than the
bid value under evaluation.

8.13 ACCEPTANCE OF BID AND PERFORMANCE SECURITY


8.13.1 After the evaluation, the complete case will be put up to the competent authority for approval. It is
desirable that the Chief Engineer (PMGSY) or CEO of the SRRDA be empowered to decide Tenders so that
long and complicated procedures are avoided in the interests of speedy decision. This will also ensure that
validity period does not expire. The bidders whose bids have been accepted will be notified of the award by the
PIU/SRRDA prior to expiration of the Bid validity period by cable, telex or facsimile confirmed by registered
letter (Letter of Acceptance – on format given in the SBD). This letter will state the sum that the employer will
pay to the contractor in consideration of the execution, completion and maintenance of the Works, and the
routine maintenance of the works for five years, by the contractor as prescribed by the contract. The Letter of
Acceptance will constitute the formation of the contract, subject only to the furnishing of a performance security
in accordance with the provisions of Clause 32. The agreement will incorporate all agreements between the
employer and the successful bidder. It will be signed by the XEN in case of PIU and an authorised officer in
case of SRRDA, and the successful bidder after the performance security is furnished. Upon the furnishing by
the successful bidder of the performance security, the employer will promptly notify the other bidders that their
bids have been unsuccessful.
8.13.2 Within 10 days after receipt of the letter of acceptance, the successful bidder shall deliver to the employer
a performance security of 5% of the contract price, for the period of 5 years plus the time for completion of
works. Additional security for unbalanced bids will also be delivered in accordance with Clause 27.3 and 27.4
of ITB and Clause 46 Part I General Conditions of Contract.
8.13.3 The performance security shall be either in the form of a Bank Guarantee or Fixed Deposit Receipts, in
the name of the employer, from a Scheduled Commercial Bank. Failure of the successful bidder to comply with
the requirements of Clause 32.1 shall constitute sufficient grounds for cancellation of the award and forfeiture
of the Earnest Money. He will also be debarred from participating in bids under PMGSY for one year.

8.14 CONTRACT AND WORK ORDER


On completion of prerequisites, the Contract (Agreement – format given in SBD) shall be signed and Work
Order (Notice to proceed with work – format given in SBD) shall be issued to the successful Bidder (Contractor).
Within 15 days of the date of Work Order, signboards along with the Logo of the PMGSY should be erected at
the side of road works. The Signboards should indicate the name of the Programme (PMGSY), name of the
road, its length, contracted cost of construction and cost of maintenance, date of commencement and due date
of completion of construction and name of the executing contractor. It is desirable that after completion of
construction, this is in the form of a permanent brick-masonry/ concrete structure at both ends of the road.

8.15 RE-TENDERING WORKS


If no bids have been received or in the opinion of the employer adequate competition has not been generated,
if the technical evaluation indicates that no party has been qualified or an inadequate number have been
qualified (say, single tender or inadequate number for generating competition), or if after the financial evaluation,
it is found that there are no responsive bids, the tendering process shall be repeated. The same condition shall
also apply to cases where the Performance Security is not furnished.
In such cases, if deemed appropriate, the duration of opening the bids from the date of NIT can be reduced
from 28 days to 15days in the second and 7 days in subsequent calls and the duration of sale of bidding
document will also be reduced correspondingly for cutting down the delays.
If the bidder who is awarded the work does not start the work within the time stipulated, the contract may be
terminated as per the Condition of Contract and the entire bidding process repeated.

122 Operations Manual for Rural Roads


Procurement (Annexures)

Annexure 8.1
(See Para 8.1)

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)

36 POINT CHECK LIST FOR PREPARING THE BIDDING


DOCUMENTS FOR PMGSY WORKS

(i) The Ministry of Rural Development has prescribed standard bidding document for Pradhan Mantri Gram
Sadak Yojana.
(ii) The following instructions check list are issued to help in the preparation of individual bidding document
for each work, or a number of works for which bids are invited in one tender.
(iii) The State Government has to decide on the following aspects and inform the authorities inviting bids
about its decision so that the bidding documents are prepared in line with its decisions.
The important points are:
1. On whose behalf are the tenders to be invited? Designation of the Employer on whose behalf, the bid is
invited. Also decide who is his authorized representative?
2. Who is the tender inviting authority?
3. What is the percentage of the estimated cost of works for the Earnest money? (Usually it is two percent,
rounded off to the nearest thousand.)
4. Whether down loading of the bidding documents from the internet is allowed?
5. Whether the bidding documents will be placed on the internet for viewing?
6. What will be the period of bid validity?
7. Whether pre-bid meetings will be held?
8. Who are eligible contractors?
9. Who are exempted from submitting earnest money?
10. Whether percentage rate or item rate tender will be invited?
The name of the Schedule of rates to be adopted for the percentage rate tenders.
11. Price of tender documents.
12. Extra charges for sending the bidding documents by mail.
13. Whether any of the sub-clauses of Clause 4.2 of the Instructions to Bidders is to be amended? If so,
what is the amended version?
14. What is the percentage of the contract price the successful bidder is expected to invest in cash?
15. The bidding document requires a bidder to have completed satisfactorily one work equal to one-third of
the estimated cost of works. Does the State want to increase this percentage? If yes, then what would be
the new percentage?

Operations Manual for Rural Roads


123
National Rural Roads Development Agency

16. What other certificates the contractor should submit under clause 4.4 B (a) (iii) of the Instructions to
Bidders?
17. What key equipment the contractor must possess or have access to? The equipment must be listed and
not left blank in the bidding document. It is to be related to the nature of road work and the specifications.
Some examples of equipment are:

Tar Boiler Water Tanker with Sprinkler


Mini Hot Mix Plant Road Rollers (8-ton)
Hot Mix Plant (Drum Type) Vibratory Road Roller
Pave Finisher Smooth wheeled Tandem Tired Rollers
Bull dozer Truck
Excavator Tractor
Air Compressor Loader (5 Cum capacity)
Concrete Mixers Tippers
Water tanker Vehicle Mounted Mechanical Spray

18. How many degree and diploma holders in civil engineering the bidder must have in his employment?
19. What should be the qualification of the person for the field laboratory?
20. What is the minimum amount of liquid assets and/or credit facilities net of other contractual commit-
ments of the successful bidder must have.
[Note: Usually it is the equivalent of estimated payments flow over 2 months at the average (straight line
distribution) construction rate.]
21. What are the designations of the departmental officers whose relations must not be in the contractor’s
employment?
22. What are the names of departments whose retired officers must not be in the employment of the con-
tractor?
23. Should M be more than 2 for judging the available bidding capacity of the bidder? Refer Clause 4.6 of
Instructions to Bidders. It cannot be more than 3. Higher the value, greater is the chance of failure of the
contractor.
What is to be the language of the bid?
24 Clause 12.1 Part I (V) of Instructions to the Bidders. What are the other documents required from the
bidders?
25. What are the deductibles, if any, for insurance? (Refer clause 13.1 of Part I General Conditions of
Contract.
26. What are the powers of the Superintending Engineer and the Chief Engineer for settlement of disputes?
(Refer clause 24.1 of Part I General Conditions of Contract).
27. What is the period within which the contractor must submit the programme for approval of the Engineer?
(Refer clause 26.1 of Part I General Conditions of Contract).
28. What is the period of interval within which the contractor must submit the up dated programme to the
Engineer? (Refer to clause 26.3 of Part I General Conditions of Contract).
29. What is the amount to be withheld if the up dated programme is not submitted? (Refer to clause 26.3 of
Part I General Conditions of Contract).

124 Operations Manual for Rural Roads


Procurement (Annexures)

30. What is the percentage of variation which calls for revision of rates? (Refer to clause 36.1 of Part I
General Conditions of Contract).
31. What is the designation of the authorized person to make payment in case consultants are appointed?
(Refer to clause 39.2 of Part I General Conditions of Contract).
32. Prescribe the State Government’s form for unconditional bank guarantee.
33. What is the number of days within which the field laboratory must be set up after the notice to start work
is issued? Refer to clause 52.2(i) of Part I General Conditions of Contract).
34. What is the percentage to apply to the value of work not completed. (It is usually 20 percent.) Refer to
clause 53.1 of Part I General Conditions of Contract).
35. If the State Government wants to include any Special Conditions of Contract, it must take prior approval,
in writing, of the National Rural Roads Development Agency.
36. The following is the schedule of time to be taken to complete the entire bid process.
(Time frame for various activities shall be same as given at the end of Para 8.1)

Check List for preparing Standard Bidding Document

Name of the Work........................................................................................................

Identification Number of the Work...............................................................................

Name of the person preparing the bidding papers......................................................

Name of person checking the bidding papers.............................................................

Section 1 List of Important Dates

Item Date Initials of person


Preparing Checking

Name of the Work

Completion Period

Date of Issue of Notice Inviting Bids

Period and Places of Sale of Bidding Documents

Time, Date and Place of Pre-bid Meeting

Deadline for Receiving Bids

Time and Date for opening Technical Bids/Bids

Time and Date of opening Financial Bids

Place of opening bids

Last Date of Bid Validity

Designation and Address of Officer inviting Bids

Operations Manual for Rural Roads


125
National Rural Roads Development Agency

Section 1 Press Notice

Designation of Authority Inviting Bids Initials of person


Preparing Checking
tender tender
document document
Designation of authority on whose behalf bids are invited
Contractors registered with
Deadline for receiving bids (Time and Date )
Fill in the columns of the table
demand draft-fill in details of designation in whose name
DD is drawn, where payable and the amount
Write the name of the office where tender documents
can be inspected and the dates when available for inspection
State whether the tender documents are available on the
internet site www.omms.nic.in
State where the tender document can be downloaded
from the internet
Write the designation and the address of the authority inviting tenders

Section 1 Notice Inviting Tenders

Item Initials of person


Preparing Checking
tender tender
document document

Paragraph no. 1. Designation of authority inviting tenders


on whose behalf tenders are invited
Percentage Rate or Item rate tenders (Delete whatever is not applicable)
Fill in the columns of the table
Paragraph No. 4 Write the name of the office where tender documents
can be inspected and the dates when available for inspection
Price of tender documents
demand draft-fill in details of designation in whose name DD is drawn,
where payable and the amount
State if the bidding documents are available for viewing on the internet
site www.omms.nic.in
Paragraph 5. Extra amount for sending tender documents by mail
Paragraph 6. Deadline for receiving bids (designation, Time and Date )
Time, Date and place of bid opening
Write the designation and the address of the authority inviting tenders
Write the designation of authority on whose behalf bids are invited

126 Operations Manual for Rural Roads


Procurement (Annexures)

Section 2 Instructions to Bidders


Note: Any change in any clause of the Instructions to bidders is not allowed.

Section 2 Appendix to ITB

Item Initials of person


Preparing Checking
tender tender
document document
Clause 1.1 Write the designation of the Employer
Write the name and summary description of the Works
Write the Identification No. of the works
Clause 2.1 Write the name of the State
Clause 3.1 Write details of the eeligible bidders
Clause 4.2 Check if the information required from bidders in Clause 4.2 is
to be modified. If yes, write its details sub-clause wise.
Otherwise write ‘none’
Clause 4.2 (g) Fill in the percentage of contract price the bidder will be
able to invest if successful.
Clause (4.4 A) (b). _____________[insert the amount if the cost of
successful completed works is more than one-third of the estimated cost of
proposed works
Clause (4.4 B) (a) (iii). Write what other certificates are required with the bid
Clause (4.4. B) (b)(i). Write carefully the details of key equipments for road
works and field testing laboratory Road Works.
Clause (4.4 B) (b)(ii). Write details of the number of technical personnel,
their qualifications and experience.
Clause (4.4 B) (b)(iii). Write the minimum amount of liquid assets and/or
credit facilities net of other contractual commitments of the successful
Bidder.
[Note: Usually it is the equivalent of estimated payments flow over 2
months at the average (straight line distribution) construction rate.]
Clause (4.4 B) (c) (i). Write the designations of the departmental officers
whose relations must not be in the contractor’s employment.
Clause (4.4 B) (c) (ii). Write the names of departments whose retired
officers must not be in the employment of the contractor.
Clause 4.6. Write the value of M if it more than 2 and up to 3.
Clause 71. Write the contact person’s designation, address,
and telephone no.
Clause (9. 2.1). Write Place, Time and Date for pre-bid meeting
Clause (11.1) Write the language of the bid.
Clause (12.1) Part I (V) Write the details of other documents required

Operations Manual for Rural Roads


127
National Rural Roads Development Agency

Clause (13.2.). Select only one option, namely percentage rate or item rate.
Delete the other option.
Clause (13.2). Write the schedule of rate if percentage rate has been
selected. Otherwise, leave it blank.
Clause (16.2) Write the amount of the earnest money.
It is usually two percent of estimated value of the Works, rounded off to
the nearest thousand.
Clause (16.2). Write the designation of the authority in whose favour the
fixed deposit receipt should be drawn for the earnest money.
Clause (16.3). Write categories of contractors exempted from submitting
the earnest money.
Clause (20.1). Write the Employer’s address for the purpose of
Bid submission
Clause (20.1). Write the deadline for bid submission, hour and date.
Clause (22.1). Write the date, time and place for opening of the
Technical Bids and Financial Bids
Clause (32.1) Write the amount of the performance guarantee.

Section 3 Qualification Information


Note: No action is required.

Section 4 Conditions of Contract


Part I General Conditions of Contract.
Note. Any change in any clause is not allowed.

Section 4 Contract Data to Part I General Conditions of Contract

Clause Item Initials of person


Preparing Checking
tender tender
document document
1.1 Write the designation and address of the Employer, and his
authorized representative
1.1 Write the designation and address of the Engineer
1.1, Write the intended completion date of the works.
17 and 28
1.1 Write details of location of the Site
1.1 Write the number of days to count the Start Date from the date
of issue of notice to start work.
1.1 Write identification number of the contract and the details of
works.
2.2 Write what is section completion, if any
2.3 (11) Write names of other documents if they are part of contract

128 Operations Manual for Rural Roads


Procurement (Annexures)

3.1 Write the name of the language of the contract


8.1 Attach the schedule of other contractors, if any
9.1 Write the number of technical persons required, degree and
diploma holders in civil engineering; also write qualification of
the persons for the field laboratory
13.1 Write deductibles for insurance, if any
14.1 Write brief details of Site Investigation Report
24.1 Write the powers of the Superintending Engineer and the
Chief Engineer for settlement of disputes
26.1 Write the period within which the contractor must submit the
programme for approval of the Engineer
26.3 Write the period of interval within which the contractor must
submit the up dated programme to the Engineer
26.3 Write the amount to be withheld if the up dated programme
is not submitted
36.1 Write the percentage of variation which call for revision of rates
39.2 What is the designation of the authorized person to make
payment in case consultants are appointed? Otherwise,
leave it blank
46.1 Enclose the State Government’s prescribed form for
unconditional bank guarantee
51.1 (a) Write the dates by which in-built drawings are to be supplied.
52.2(i) Write the number of days within which the field laboratory must
be set up after the notice to start work is issued
53.1 Write the percentage to apply to the value of work not
completed. (It is usually 20 percent.)

Section 4 Part II Special Conditions of Contract


Note: Special conditions of contract to modify Part I General Conditions of Contract may be added with the
approval of the National Rural Roads Development Agency.
Section 5 Specifications and Drawings.
Write the specifications and details of drawings in the light of the notes given. Then delete the notes. The notes
are not published. The notes are not part of the bidding document.
Section 6 Form of Bid
Note: No action on the part of the authority inviting tenders
Section 7 Bill of Quantities
Note: Select the form bill of quantities for item rate tenders or the bill of quantities for percentage tenders.
If the Bill of Quantities for Item Rate Tenders is selected, leave the columns of rates blank. The tenderer will fill
it in. Fill in the column of description of works with brief specifications and reference to the book of specifications.
If the Bill of Quantities for Percentage Rate Tenders is selected, do not leave any column blank. Fill in all the
columns.
Section 8 are standard forms for use.

Operations Manual for Rural Roads


129
National Rural Roads Development Agency

Annexure 8.2
(See Para 8.6)

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)

OMMS Input Format I (Publish New Tender Notice)

130 Operations Manual for Rural Roads


Procurement (Annexures)

Annexure 8.3
(See Para 8.6)

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)

OMMS Input Format II (Package Wise Details)

Operations Manual for Rural Roads


131
National Rural Roads Development Agency

Annexure 8.4
(See Para 8.6)

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)


OMMS Input Format – III (ITB and Contract Data Format)

1. Add Equipments For Construction

2. Add Equipments For Field Laboratory

3. Technical Personnel Requirement For Construction and Up gradation

132 Operations Manual for Rural Roads


Procurement (Annexures)

4. Technical Personnel Requirement For Maintenance

5. Technical Personnel Requirement For Field Laboratory

Operations Manual for Rural Roads


133
National Rural Roads Development Agency

Annexure 8.5
(See Para 8.10)

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)


List of Certificates required in submission of bid under PMGSY

1. Proof of eligibility of Contractor as per clause 3 of ITB.


2. Copy of constitution or legal status of bidder.
3. Power of attorney of signatory of bid.
4. Certificates of Charted Accountant regarding annual volume of civil engineering construction works executed
and payments received in last five years.
5. Certificates from employers regarding experience of construction of similar nature of work as detailed in
para 1.3.1 of Qualification Information.
6. Certificate from Engineer in-charge regarding on-going works.
7. Evidence of submission of bids (bids not approved/ accepted) by bidders at other places.
8. Evidence of availability of owned key equipments or leased key equipments.
9. Certificate giving the availability of key technical personnel stated in Appendix to ITB.
10. Financial reports of last five years: balance sheets, profit and loss statement and auditor’s report.
11. Bank certificate or other evidence of access to financial resources, cash in hand and lines of credit.
12. Undertaking that Bidder will be able to invest a maximum of cash upto the percentage of contract price as
specified in the Appendix to ITB.
13. Affidavit to the effect that information furnished with the bid document is correct in all respects as per
clause 4.4 B (a) of ITB.
14. Income tax clearance certificate.
15. Undertaking of the Bidder to the effect that near relatives and retired Gazetted officers are not and will not
be in his employment.
16. Any other certificates as provided in Appendix to ITB.

134 Operations Manual for Rural Roads


Project Implementation and Contract Management

CHAPTER - 9
PROJECT IMPLEMENTATION AND CONTRACT MANAGEMENT

9.1 INTRODUCTION
PMGSY requires that all works should be executed by Contractors with the capability of executing the work
within the given time and with the requisite quality. PMGSY places high emphasis on both time and quality.
Contracting out the work makes it possible to achieve both objectives of speedy execution and good quality by
emphasizing requirements of adequate execution capacity (in terms of engineering personnel and necessary
equipment and machinery) and adequate Quality Testing. The Standard Bidding Document developed for PMGSY
not only sets down the well established procedures of competitive bidding to ensure selection of qualified
Contractors with the necessary expertise and ability, it also ensures that the Contract terms and conditions are
commensurate with the need to make both time and quality assurance the essence of the Contract.
Every work under the Programme is required to be contracted as per the provisions of Standard Bidding Document
prescribed by NRRDA. The successful bidder, after furnishing the required Performance Security as per clause
32 of Instruction to Bidders (ITB), executes the Agreement, after which a notice to proceed with the work, often
termed as ‘Work Order’ is issued by the Employer. For purposes of PMGSY, ‘Employer’ means the State
Government or the SRRDA. The performance of the Contract will start from the date of issue of the notice to
proceed with the work. The execution of work and management of the Contract is required to be done strictly as
per the conditions of Contract.

9.2 CONTRACT DOCUMENTS


To properly manage the Contract, it is necessary to understand the Contract documents and their order of
priority. As given in the Agreement constituting the Contract, the following documents shall form part of the
Contract, interpreted in the following order of priority:
(a) Agreement.
(b) Notice to Proceed with the Work (Work Order).
(c) Letter of Acceptance.
(d) Contractor’s Bid.
(e) Contract Data.
(f) Special Conditions of Contract (SCC).
(g) General Conditions of Contract (GCC).
(h) Specifications.
(i) Drawings.
(j) Bill of Quantities (BOQ), and.
(k) Any other document listed in the Contract Data.
The obligations arising out of these documents, generally in the naturally occurring sequence is given in the
following paragraphs.

Operations Manual for Rural Roads


135
National Rural Roads Development Agency

9.3 PRE-MOBILIZATION
9.3.1 Insurance: The Contractor is required to provide insurance cover from the start date to the date of
completion as per clause 13 of the GCC. Insurance policies and certificates shall be delivered by the Contractor
to the engineer for the approval before the start date. The Contractor and Employer should note that as per
clause 52 of GCC, it is a fundamental breach of the Contract if the Contractor fails to provide insurance cover.
9.3.2 Subcontracting: After the issue of Work Order, the engineer (i.e. the Executive Engineer who would be
the ‘engineer’ as defined in the Contract) would first ascertain whether there is any sub-contracting allowed
within the Contract. As per clause 4.2(k) of ITB, if the Contractor has proposed to sub-contract the work and the
proposal has been accepted by the competent authority, the sub-contracting will be allowed. The conditions of
sub-contract will be governed by clause 7 of General Conditions of Contract (GCC).
9.3.3 Mobilization Advance: As per clause 45 of the GCC, the Contractor is entitled to get mobilization
advance upto 5% of the Contract price (excluding routine maintenance). The advance shall be paid by the
Employer against submission by the Contractor of an unconditional Bank Guarantee in the prescribed format
by a commercial bank acceptable to the Employer in an amount equal to advance payment. The Bank Guarantee
shall remain effective until the advance payment has been repaid. The amount of the Bank Guarantee shall be
progressively reduced by the amounts repaid by the Contractor. The Employer is entitled to ensure that the
advance payment has been used by the Contractor for the purpose it has been released. The Employer is
entitled to ask for copies of invoices or other documents as may be determined by him. The repayment of
advance will be effected by the engineer by deducting proportionate amounts from the payments due or otherwise
falling due.

9.4 MOBILIZATION
The Contractor is required to mobilize men, material and machinery within 10 days after the date of issue of the
Work Order. The duration between the date of issue of the work order and the date of actual commencement of
the work is termed as ‘Mobilization Time’ which is very important for the Contractor as well as the ‘engineer’.
During this period, the complete planning of the work and mobilization of resources i.e. men, material and
machinery is carried out for ensuring not only completion of the work, but also timely completion of various
items of work so as to ultimately achieve the target of timely completion of whole work with requisite quality.
The following activities are required to be completed, generally in the suggested order, by the ‘engineer’ and
the Contractor during the Mobilization Time:-
(a) Deployment of Contractor’s personnel: As per clause 9 of the GCC, the Contractor is required to
employ the technical personnel enumerated in the Contract data. At the start of the Mobilization Time,
technical and administrative instructions will be passed on to the Contractor by the engineer and therefore,
to fully understand the instructions and before any further activity is allowed, the Contractor will be required
to employ his key technical personnel who will interact with the Engineer. At the mobilization stage, at-
least one graduate Engineer and required number of diploma Engineers should be deployed to attend to
the work programme, working drawings and recording of pre-commencement level. After the mobilization
activities completed, the requirement of technical personnel will depend on the items of work being executed
but soon after the commencement of the work the technical personnel required for field laboratory should
be in place till the completion of the work.
(b) Listing of Requirements by Engineer: As per the Bill of Quantities, the requirement of material, labour
and machinery during the construction period divided suitably in the defined durations is required to be
listed by the ‘engineer’. The ‘engineer’ will also prepare the list of the equipments required to establish the
field laboratory. These will be based on the data entered in Appendix to ITB with reference to clause 4.4 B
(b) (iii) of the ITB and the list of equipments given in Contract Data to GCC.
(c) Work Programme: Based on the BOQ and the list of requirements of men, material and machinery, the
‘engineer’ is required to guide the Contractor for the preparation of work programme. The Work Programme
is the programme showing the general methods, arrangements, order and timing of all the activities in the

136 Operations Manual for Rural Roads


Project Implementation and Contract Management

works along with monthly cash flow forecasts for the construction of the works. Based on the guidance of
the ‘engineer’ and availability of resources, the Contractor is required to prepare his work programme and
assess the requirement of additional men, material and machinery. The work programme should be detailed
in such a way that the date of start and date of completion of every item of work is clearly laid down; the
details of requirements for completion of various items of works including cash flow forecasts should also
be captured. It is desirable that a sample PERT-chart of complete activity of construction should be drawn
up wherein the details of every large or small activity should be clearly shown. It is also desirable that in
the work programme, the Contractor should clearly indicate the tentative periods during which the presence
of the engineer or his representatives will be required at site.
(d) Handing over of Site to Contractor: The ‘engineer’ is required to handover the full possession or part
possession (at least 75%) of the work site to the Contractor. As far as possible, the ‘engineer’ should
handover the possession of the full work site.
(e) Working Drawings & Designs: While the ‘engineer’ is handing over the possession of the work site,
complete set of working drawings should be handed over to the Contractor which, inter-alia, will include L-
Section, Cross-Section and Plan of road alignment, drawings of CD works and designs as decided by the
‘engineer’.
(f) Specifications & Drawings of Temporary Works: The Contractor has to submit the specifications in
drawings of proposed temporary works for the approval of the engineer as per clause 18 of the GCC. The
Contractor shall be responsible for temporary works as well as for the safety of all the activities on the site.
(g) Approval of Work Programme: Once the above activities are complete, the work programme will be
submitted by the Contractor for approval of the ‘engineer’ and the ‘engineer’ after checking that the work
programme is realistic (keeping in view seasonal factors) shall accord his approval. It is important that the
time period given for completion of different portions of the work are properly checked with reference to
availability of machinery and if necessary the ‘engineer’ should advise the contractor to redraw the work
programme before according his approval. It is to be stressed that as per Clause 26.2 of GCC (“An update
of the Programme shall be a programme showing the actual progress achieved on each activity and the
effect of the progress achieved on the timing of the remaining Works, including any changes to the sequence
of the activities”), not deploying requisite key personnel or equipment is a fundamental breach of the
contract as per clause 52.2 k which is worded as “if the Contractor fails to deploy machinery and equipment
or personnel as specified in the Contract Data at the appropriate time”.
(h) Establishment of Field laboratory: The Contractor will establish the field laboratory at a convenient
location as approved by the engineer. It will be ensured by the Contractor that the laboratory has all the
equipments as required by the engineer. It should be noted that the Contractor will not be allowed to
commence the work if the field laboratory is not established in the stipulated time frame. Non-establishment
of the Laboratory within the time given is a fundamental breach of the Contract. The Contractor shall have
some area available for holding meetings with PIU. It is suggested that the Contractor should provide a
temporary site office along with the field laboratory. Such an office would serve as a meeting place between
PIU Engineers and the Contractor’s Engineer’s. Also the works programme and other day-to-day required
information can be kept in such office.
(i) Pre-Commencement Levels: Recording of pre-commencement levels is the first activity of the Work
Programme. After the handing over of the possession of the work site, actual measurements of pre-
commencement levels will be recorded by the representative of the ‘engineer’ in the presence of authorized
representative of the Contractor in the Measurement Book. The acceptance signature of the representative
of the Contractor will invariably be recorded.

9.5 INTIMATION OF MOBILIZATION


As soon as the above mentioned activities are complete, and in particular the men and machinery are in
position and site Quality Control Laboratory has been established, the PIU shall inform the SQC so that the
Empowered Officer can operationalise the financial limits for the Contract package (See para 13.1.4).

Operations Manual for Rural Roads


137
National Rural Roads Development Agency

9.6 MANAGEMENT MEETINGS


As per clause 29 of GCC, there is a provision for Management Meetings to review plans and progress of work.
The ‘engineer’ may require the Contractor to attend the management meetings. It is highly desirable that the
‘engineer’ should organize the first Management Meeting within 3 days of issue of the Work Order and the
items listed above under the head of mobilization should be attended to in this Management Meeting. It is also
desirable that the ‘engineer’ works out a schedule of Management Meetings in relation to the Work Programme.
A communication listing the Schedule should be sent to the Contractor well in advance so that the business of
review of progress of works is well understood and appreciated by the all concerned. The management meeting
should be an integral part of the Contract management process to ensure that there are no deficiencies or
delays on part of the Contractor or the Employer/ Engineer. As such it would be useful to maintain a clear record
of such meetings. A copy would be given to the Contractor, and a copy would be given to the AE/JE, with the
office copy being filed in the relevant Management Meeting file for the Package.

9.7 COMMENCEMENT OF WORK, PROGRESS AND TIME CONTROL


The Contractor will commence the work as per the Work Programme. The ‘engineer’ is required to monitor the
progress of execution of work in relation to the work programme and as per clause 26 of GCC, in case, the
Contractor is not in a position to carry out the work as per the work programme, the updated/revised work
programme shall be invariably submitted by the Contractor, without affecting the total stipulated duration of the
Contract. In case of initial delay in activities, the Contractor may adjust the activities of the further work within
the stipulated duration and furnish the revised work programme, within the duration prescribed in the Contract
data, for approval as per provisions of the Contract. If the Contractor fails to submit revised work programme,
there is a provision of withholding the amount as per the Contract data. The ‘engineer’ is empowered to withhold
from the next due payment and continue to withhold this payment until the next payment after the date on which
overdue programme is submitted. The ‘engineer’s approval of the programme shall not alter the Contractors
obligations.

9.8 UPDATING WORK PROGRAMME


The revised/updated work programme shall be a programme showing the actual progress achieved for each
of the activity and the effect of the progress achieved on the timing of remaining works including any changes
to the sequence of the activities. The Contractor is free to revise the programme and to submit it to the ‘engineer’
again at any time. The revised/updated work programme must show the effect of variations if any and
compensation events (if any).

9.9 SUBCONTRACTING DURING CONSTRUCTION


The Contractor may propose sub-contracting any part of the work during execution, beyond what has been
stated in clauses 7.1 and 7.2 of GCC generally to make up for unexpected delays which cannot be made up in
the normal course. To enable the Contractor to complete the work as per terms of the Contract, the Employer
will consider the following before according approval.
(a) The Contractor shall not sub-contract the whole of the works.
(b) The Contractor shall not sub-contract any part of the work without prior consent of the Employer. Any such
consent shall not relieve the Contractor from any liability or obligation under the Contract and he shall be
responsible for the acts, defaults and neglects of any of his sub-contractor, agents and workmen.
The Engineer should satisfy himself before recommending to the Employer whether
(a) the circumstances warrant such sub-contracting; and
(b) the sub-contractor so proposed for the work possess the experience, qualifications and equipment necessary
for the job proposed to be entrusted to him in proportion to the quantum of works to be subcontracted.

138 Operations Manual for Rural Roads


Project Implementation and Contract Management

9.10 LIQUIDATED DAMAGES


In case the following milestones are not achieved by the Contractor, he shall be liable for payment of liquidated
damages for the period that the completion date is later than the intended completion date as per clause 44 of
the GCC:
i) if 1/8th of the value of entire Contract work has not been completed upto 1/4th of the period allowed for the
completion.
ii) If 3/8th of the value of entire work has not been completed upto ½ of the period allowed for completion.
iii) If 3/4th of the value of entire Contract work has not been completed upto 3/4th of the period allowed for
completion.
1% of the initial Contract price, rounded off to the nearest thousand, per week, is the amount of liquidated
damages for delay in completion subjected to maximum of 10% of initial Contract price.
The engineer is empowered to withhold the amount of liquidated damages if Contractor fails to achieve the
above milestones. However, if the Contractor achieves the subsequent milestone in time, the withheld amounts
would be restored.
The engineer should note that the quality and time are the essence of the Contract, as such, the delay in
completion of the work constitutes a fundamental breach of the Contract as per clause 52. The provision
in this respect is given below:
(a) The Contractor stops the work for 28 days when no stoppage of work is shown on the current programme
and the stoppage has not been authorized by the engineer.
(b) The Contractor has delayed the completion of the work by the number of days for which maximum amount
of liquidated damages can be paid, as defined in clause 44.1
(c) If the Contractor has not completed at least 30% of the value of work required to be completed after ½ of
the completion period has elapsed.
As soon as a delay occurs, is essential for the engineer/Employer to issue appropriate notices/ letters giving
clear reference of the specific clauses of Contract. Since a legal Contract is involved, unofficial/oral warnings to
Contractors should not be resorted to as a substitute for a formal notice. The Employer is empowered
to terminate the Contract if the fundamental breach of the Contract occurs in respect to delay in completion of
the work.

9.11 QUALITY CONTROL


As per Clause 16 of the GCC, the Contractor has to construct and install and maintain the works in accordance
with specifications and drawings. Section 5 ‘Specifications’ of the Contract Document forms the part of Contract
and all the works shall be carried out by the Contractor strictly as per specifications prescribed in Section 5. As
per clause 31 of GCC the Contractor is solely responsible for carrying out mandatory tests prescribed in Rural
Roads Manual and for correctness of test results whether performed in his field laboratory or elsewhere. For
ensuring effective quality control the Employer/ engineer will be required to ensure the following:
(a) The Contractor will be required to furnish a Quality Management Plan along with the work programme.
The Engineer will prepare the schedule of those tests which will be carried out in presence of JE, AE or EE
as per the provisions given in Quality Control Register/Handbook.
(b) The Contractor is required to establish field laboratory as per provisions of clause 31.1 of the GCC read
with clause 4.4 B (h) of ITB. The engineer will ensure that the field level quality control laboratory required
for mandatory tests is established by the Contractor during the mobilization time.
(c) No material will be used on the work unless the mandatory tests have been conducted and the material
has qualified the tests parameters. No work will be accepted unless the mandatory tests for workmanship
have been conducted and the workmanship has qualified the tests parameters. In case the Contractor

Operations Manual for Rural Roads


139
National Rural Roads Development Agency

has failed to comply with the above the Engineer will take cognizance of this under clause 30 of the GCC
and will issue a written notice to the Contractor for rectification of the defect.
(d) Quality Control Register Part I will be maintained by the designated personnel of the Contractor at the field
laboratory and this register will be made available for inspecting officers as prescribed in the conditions of
the contract. For this the Contractor will be required to furnish clear authorization because the responsibility
of maintenance of Quality Control Register will be of the Contractor. Every week, the abstract of the
register will be communicated by the personnel of the Contractor to the Assistant Engineer in-charge of
work in the format ‘Abstract of Tests Conducted’ given in Quality Control Register Part II.
(e) The personnel of the Contractor responsible for laboratory will inform the AE the cases of non-conformance
within the duration (generally within next two days of conducting tests) prescribed by the Engineer in the
form prescribed by PIU which will include the test no., name of test, date of test, results and its comparison
with standard values.
(f) The AE will maintain Quality Control Register Part II which is abstract of the mandatory tests conducted
and record of non-conformance reports. The AE will ensure that non-conformance report is issued to the
Contractor immediately on occurrence. The Contractor will take immediate steps for rectification. In case
the Contractor fails to comply with the above the Engineer will take cognizance of this under clause 30 of
the GCC and will issue a written notice to the Contractor for rectification of the defect.
(g) As per clause 22 of GCC, the Contractor has to allow the access to the site to the Engineer and other
authorized persons. The supervising officer in the department, the State Quality Monitors and National
Quality Monitors will be carrying out inspections of the work and subject to guidelines issued separately for
the purpose, the instructions given by the above persons will be the instructions to the Engineer. The
Engineer/ Employer will ensure the compliance of the instructions of the inspecting officers through the
Contractor.
(h) As per clause 30 of the GCC, without affecting the Contractor’s responsibility, the Engineer shall check the
work and notify the Contractor if any defects are found. The Engineer is also empowered to instruct the
Contractor to search for a defect and to uncover and test any item of work that the Engineer considers
may have a defect.
(i) As per clause 32, even after the completion of work but before the end of the defect liability period the
Contractor has to correct the defects within the specified duration of time.
The engineer should note that the time and quality are the essence of the Contract, and failure to ensure
quality of the work constitutes a fundamental breach of the Contract as per clause 52 of the GCC, provision
of which include:
(i) Clause 52.2 (i):- If the Contractor fails to set up a field laboratory with the prescribed equipment, within the
period specified in the Contract Data.
(ii) Clause 52.2 (c):- The Engineer gives Notice that failure to correct a particular Defect is a fundamental
breach of Contract and the Contractor fails to correct it within a reasonable period of time determined by
the Engineer.
(iii) Clause 52.2 (k): If the Contractor fails to deploy machinery and equipment or personnel as specified in the
Contract Data at the appropriate time.
It is very essential for the engineer to issue appropriate written notices/ letters giving clear reference of the
specific clauses of Contract, if the instances of unacceptable quality are detected. The Employer is empowered
to terminate the Contract if a fundamental breach of the Contract occurs.

9.12 COST CONTROL AND VARIATIONS


The execution of work is required to be done as per the items and quantities detailed in the Bill of Quantities.
The Contractor is paid for the quantity of work done at the rate approved for the purpose either on the basis of

140 Operations Manual for Rural Roads


Project Implementation and Contract Management

Schedule of Rates in case of percentage rate tenders or on the basis of approved rates given in Bill of Quantities
for each item of work in case of item rate tenders.
Having regard to the scope of works and sanctioned estimated cost, the Engineer has the power to order in
writing, variations within the scope of works he considers necessary or advisable during the progress of work.
The Contractor shall carry out such works and such variations shall form the part of the Contract. If the
Engineer gives oral order for variations, these orders will have to be confirmed by written directions.
If rates for variation items are specified in the Bill of Quantities, the Contractor shall carry out such work at the
same rate. This shall apply for variations only upto the limit prescribed in the Contract Data. If the variation
exceeds this limit, the rate shall be derived under the provisions of clause 36.3 of GCC for quantities (higher or
lower) exceeding the deviation limit.

9.13 EXTENSION OF INTENDED COMPLETION DATE


The Engineer is empowered to extend intended completion date in the following events:
 If a compensation event occurs.
 If it is impossible for completion to be achieved by intended completion date because of a variation order
issued by the Engineer.
The Engineer shall decide within 21 days of the request of the Contractor whether, and by how much time, the
extension is to be granted. The Contractor is required to give full and detailed proposal for extension of time
along with supporting information. It should be noted that as per para 27.2 of GCC, if the Contractor fails to
cooperate in dealing with a delay, the delay because of the failure shall not be considered in assessing the new
intended completion date. The Engineer as per clause 28 of the GCC is empowered to instruct the Contractor
to delay the start or progress of any activity within the works. However, the Engineer will have to obtain a written
approval of the Employer for ordering delay totaling more than 30 days.

9.14 PAYMENTS AND DEPOSITS


As per clause 38 of the GCC, the Contractor is required to submit fortnightly/ monthly statements of value of the
work done including variations and compensation events, if any, supported with detailed measurement of each
item. The Engineer within 14 days is required to check the Contractor’s statement and certify the amount. It is
to be noted that the value of work executed shall be determined on the basis of measurements by the Engineer.
Payments shall be adjusted for various deductions and the Engineer shall pay the Contractor amounts certified
within 15 days of date of each certification.
The rates quoted by the Contractor shall be deemed to be inclusive of the sales and other levies, duties,
royalties, cess, toll, taxes of Central and State Governments, local bodies and authorities that the Contractor
will have to pay for the performance of this Contract.
The Engineer shall deduct a security deposit of 5% from each running payment due to the Contractor. The
security deposit and performance security, aggregating to 10%, of the Contract price shall be released to the
Contractor, after completion of defect liability period provided that the Contractor has corrected defects notified
to him during the period of performance guarantee and the Contractor has satisfactorily completed the routine
maintenance of roads as per the conditions of Contract. The Engineer would convert security deposits for the
defect liability period into interest bearing securities of a scheduled commercial bank in the name of Employer
if so desired by the Contractor.
The amendment to SBD applicable for the tenders invited after 15th February, 2005 provides for release of 50%
of the retention amount and performance security for unbalanced bids just after completion of the construction
work. However, the release of rest of the retention amount and performance security shall be done only after
the routine maintenance period.

Operations Manual for Rural Roads


141
National Rural Roads Development Agency

9.15 COMPENSATION EVENTS


The Contractor is entitled for compensation for the following events, if these events have not been caused by
the Contractor:
 The Engineer orders a delay or delays exceeding a total of 30 days.
 The effects on the Contractor of any of the Employer’s Risks.
 If a compensation event prevents or is likely to prevent the works being completed by the intended completion
date, the intended completion date shall be extended in writing by the Engineer. The Engineer shall decide
whether and by how much the intended completion date shall be extended.

9.16 DEFECT LIABILITY PERIOD AND ROUTINE MAINTENANCE


All the contracts under PMGSY will not only be a construction Contract but will also include the routine
maintenance for five years. Description of items to be attended during the routine maintenance has been
clearly laid down in the Contract data. As per clause 32 of GCC, the Contractor will be required to attend to the
defects during the defect liability period. The Contractor is also required to carry out routine maintenance of the
work executed by him, in such a way that road surface and structures are kept in defect free condition during
the entire maintenance period of five years. To fulfill the above objectives the Contractor is required to fulfill the
requirements stipulated in para 32.2.2, 32.2.3 and 32.2.4 of GCC.
The Engineer is required to issue written notices to correct the defects noticed during the defect liability period.
In case the defect is not satisfactorily rectified within the given time period the Engineer shall deduct the cost
and get the defect corrected under clause 33 of the GCC.

9.17 DISPUTE RESOLUTION


The Standard Bidding Document of PMGSY provides for simplified and effective dispute redress mechanism,
governed by clause 24 of GCC. Any dispute or difference of any kind arising in connection with the execution
of the Contract whether before its commencement, during the progress of work, after the termination or
abandonment or breach of Contract, in the first instance is required to be referred for settlement to the competent
authority specified in Contract data. Generally, the States have empowered Superintending Engineers and
Chief Engineers of the executing department for the above purpose. Either party have right of appeal against
the decision of competent authority to the Standing Empowered Committee, in case the amount appealed
against exceeds Rupees one Lakh. The composition of Standing Empowered Committee (SEC) shall be as per
clause 24.3 of GCC.
In States where mandatory provisions of arbitration are applicable the provisions of Clause 24 and 25 of the
General Conditions of Contract under the Standard Bidding Document for Pradhan Mantri Gram Sadak Yojana
will not be applicable. Such State Governments will propose modifications in the provisions of Clause 24 and
25 of the General Conditions of Contract under the Standard Bidding Document for Pradhan Mantri Gram
Sadak Yojana. States may keep in view the provisions in this respect applicable to World Bank funded PMGSY
works. The details are given in Annexure 9.1.

9.18 COMPLETION
The Contractor shall request the Engineer to issue a certificate of completion of the construction of the works,
and the Engineer will do so upon deciding that the works is completed. In case of Routine Maintenance the
Contractor shall request the Engineer to issue the certificate of completion of the Routine Maintenance and the
Engineer will do so upon deciding that the Routine Maintenance is completed.

9.19 FINAL ACCOUNT


The Contractor shall supply the Engineer with a detailed account of the total amount that the Contractor considers
payable for works under the contract within 21 days of issue of certificate of completion of construction of
works. The Engineer shall issue a defect liability certificate and certify any payment that is due to the Contractor

142 Operations Manual for Rural Roads


Project Implementation and Contract Management

for works within 42 days of receiving the Contractor’s account if it is correct and complete. If the account is not
correct or complete, the Engineer shall issue within 42 days a schedule that states the scope of the corrections
or additions that are necessary. If the Account is still unsatisfactory after it has been resubmitted, the
Engineer shall decide on the amount payable to the Contractor and issue a payment certificate within 28 days
of receiving the Contractor’s revised account. The payment of final bill for construction of works will be made
within 14 days thereafter.
In case the account is not received within 21 days of issue of Certificate of Completion as provided in clause
50.1 above, the Engineer shall proceed to finalise the account and issue a payment certificate within 28 days.
The payment of final bill for construction of works will be made within 14 days thereafter.
In case of Routine Maintenance, the Contractor shall supply the Engineer with a detailed account of the total
amount that the Contractor considers payable under the contract 21 days before the end of the Routine
Maintenance Period. The Engineer shall issue a Routine Maintenance Completion Certificate and certify any
final payment that is due to the Contractor within 42 days of receiving the Contractor’s account if it is correct
and complete. If it is not, the Engineer shall issue within 42 days a schedule that states the scope of the
corrections or additions that are necessary. If the Final Account is still unsatisfactory after it has been resubmitted,
the Engineer shall decide on the amount payable to the Contractor and issue a payment certificate within 28
days of receiving the Contractor’s revised account. The payment of final bills for routine maintenance will be
made within 14 days thereafter.
In case the account is not received within 21 days of issue of Certificate of Completion as provided in clause
50.3 above, the Engineer shall proceed to finalise the account and issue a payment certificate within 28 days.
The payment of final bill for routine maintenance will be made within 14 days thereafter
9.20 TERMINATION
As per clause 52 of the GCC, the employer is empowered to terminate the contract if the Contractor causes a
fundamental breach of the contract. Some of the main conditions of fundamental breach are:
 The contractor stops the work for 28 days without authorization of Engineer.
 Contractor fails to correct the defect within the time determined by Engineer.
 Contractor delays the completion of work by the number of days for which maximum amount of liquidated
damages can be paid.
 Contractor has not completed 30% of the value of work after half of the completion period.
 Contractor fails to establish field laboratory.
 Contractor fails to deploy required machinery and equipment for construction and personnel as prescribed
in the contract.
If the Contract is terminated, the Engineer shall issue the certificate for value of work and if the total amount due
to Employer exceeds any payment due to the Contractor, the difference shall be recovered from the deposits
available with the Employer, if amount is still left un-recovered it will be a debt payable to employer.
As per the clause 54 of GCC, if the Contract is terminated because of Contractor’s default the property as
mentioned in the said clause shall be deemed to be the property of the Employer and credit of the same will be
given to the Contractor.

Operations Manual for Rural Roads


143
National Rural Roads Development Agency

Annexure 9.1
(See Para 9.17)

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)


Provisions Regarding Disputes
in some of the World Bank Funded PMGSY Projects

Disputes
If the Contractor believes that a decision taken by the Engineer was either outside the authority given to the
Engineer by the Contractor or that the decision was wrongly taken, the decision shall be referred to the Adjudicator
within 14 days of notification of the Engineer’s decision. Performance under the Contract shall continue
notwithstanding the reference to the Adjudicator, and payments by the Employer to the Contractor will not be
withheld unless they are the subject matter of dispute.
Procedure for Resolution of Disputes
The Adjudicator shall give a decision in writing within 28 days of receipt of a notification of a dispute.
The Adjudicator shall be paid daily at the rate specified in the Contract Data together with reimbursable expenses
to the types specified in the Contract Data and the cost shall be divided equally between the Employer and the
Contractor, whatever decision is reached by the Adjudicator. Either party may refer a decision of the Adjudicator
to Arbitration within 28 days of the Adjudicator’s written decision. Arbitration shall be under the Arbitration and
Conciliation Act 1996. If neither party refers the dispute to Arbitration within the above 28 days, the Adjudicator’s
decision will be final and binding.
Where the Initial Contract Price as mentioned in the Acceptance Letter is Rs.5 Crore and below, disputes or
differences in which an Adjudicator has given a decision shall be referred to a sole Arbitrator. The Sole Arbitrator
would be appointed by the agreement between the parties; failing such agreement within 15 days of the reference
to arbitration, by the appointing authority, namely the Chairman of the Executive Committee of the Indian
Roads Congress.
Arbitration proceedings shall be held in India, and the language of the arbitration proceedings and that of all
documents and communications between the parties shall be English.
Performance under the Contract shall continue even after reference to the arbitration and payments due to the
Contractor by the Employer shall not be withheld, unless they are the subject matter of the arbitration proceedings.
Replacement of Adjudicator
Should the Adjudicator resign or die or be incapable, or should the Employer and the Contractor agree that the
Adjudicator is not fulfilling his functions in accordance with the provisions of the Contract; a new Adjudicator will
be jointly appointed by the Employer and the Contractor. In case of disagreement between the Employer and
the Contractor, within 30 days, the Adjudicator shall be designated by the appointing authority designated in the
Contract Data, at the request of either party within 14 days of receipt of such request.

144 Operations Manual for Rural Roads


Principal and State Technical Agencies

CHAPTER 10
PRINCIPAL AND STATE TECHNICAL AGENCIES

10.1 BACKGROUND
The PMGSY is a programme involving huge investments and represents a major step-up in Rural Road
Construction activity. It is no longer either desirable or even practicable that the requisite technical and engineering
inputs should be managed in-house. Need based outsourcing will not only be more economical, it will also
ensure access to a better range and quality of services and enable R&D and innovations to enter into the
mainstream of rural road construction. Over the years, many Engineering Colleges and Technical Institutes
have grown into centres of excellence imparting quality education, and at the same time taking up R&D studies.
Recognising the vast reservoir of knowledge in these bodies, the MoRD has devised a scheme to utilise the
potential of a Government -academia partnership for the benefit of PMGSY. Partnership with State Technical
Agencies (STAs) is oriented more towards outsourcing of technical functions, while partnership with Principal
Technical Agencies (PTAs) will have a higher R&D and academic content.

10.2 STAs AND PTAs


The STAs are Engineering Colleges/ Technical Institutes which have been identified in various States (in
consultation with the States) for acting as catalyzing agents in the State level Rural Road programme. These
agencies are expected to improve the project quality at the design and conceptual level and function as a 2nd
tier of quality management at the Project preparation level.
PTAs are premier technical institutions having in-depth knowledge of the technology of road design and
construction and therefore, able to provide additional R&D and training inputs.

10.3 ROLE AND RESPONSIBILITY OF STATE TECHNICAL AGENCIES (STAs)


State Technical Agencies are envisaged as catalysing agents in the State Level rural road programme. Their
functions include:
 Verification of the District Rural Roads Plan prepared by the district Programme Implementation
Unit
The verification will include:
 Checking of correctness of existing links.
 Checking of new proposed links in terms of the parameters laid down by the District Panchayat.
 Ensuring that all necessary coding and indexing has been done to enable extraction of the Core
Network.
 Post-Scrutiny of the Core Network
The State Technical Agency will, after finalisation of the Core Network by the District Panchayats, conduct
a 100% review (suitably phased) in consultation with the DPIUs in order to help locate deficiencies, if any,
in the Core Network with the objective of achieving a standard suitable for a GIS application.
 Scrutiny of the Detailed Project Reports for road works prepared by the District Programme
Implementation Units
The scrutiny by STAs of project reports shall be a thorough and detailed one in order to ensure that

Operations Manual for Rural Roads


145
National Rural Roads Development Agency

geometric and physical design is appropriate and economic, that the specifications are adequate and
based on site conditions and that the estimation of quantities is accurate and reasonable. PMGSY roads
are to be of the highest quality and it is the STAs that will have to provide the new inputs into the system to
ensure the paradigm shift in terms of proper designing of roads for excellence with economy.
As such STAs while scrutinising DPRs must
 Ensure that mere time constraint does not interfere with proper scrutiny. They should liaise with
DPIUs to ensure a proper phasing out of the process.
 Ensure that each DPR is made on the basis of thorough field investigation. If necessary additional
data may be asked for.
 Check that the basic parameters viz, traffic and CBR are properly estimated.
 Determine that the design is really appropriate and there is no over-designing.
 Investigate that all possible economies on use of materials, including soil stabilisation measures, use
of alternate material like flyash/ industrial waste etc have been fully explored and used appropriately
wherever possible.
 Provision of requisite technical support to the State/ District Units
The District Programme Implementation Unit (DPIU), if required may take the advice of the STA in design
of works involving special problems. The DPIU will associate the STA in all cross drainage design works
where the proposed structure involves a span exceeding 15 metres.
The STA would normally not be involved in routine monitoring of execution of works. However in case of
works involving new or innovative features or with R&D components, the DPIU may take the technical
services of the STA in studying the benefits of such innovations and to make general recommendations on
their utility.
 Undertaking normal tests of parameters for road design and Quality Control tests for PIUs and QC
The STA laboratories would be available for conducting tests necessary for design and quality control. The
DPIU and the SQM would liaise with the STAs for the tests. Samples may also be sent by NQMs for testing
through the DPIUs.
The STA will also liaise with other engineering institutions in the area in order to maintain information
regarding whether testing facilities in such institutions are available so that routine testing for design and
estimation could be done at such locations as well.
 Training
The training modules designed by Principal Technical Agencies (PTAs) will be operationalised by STAs
who will draw resource personnel from their own as well as other suitable technical institutions. The STAs
will conduct training, evaluate feedback and suggest future training needs. The training may include both
routine and refresher programmes as well as specific technical programmes of local or special relevance.
The STAs may also prepare audio-visual training material for dissemination and use under the overall
specifications and guidance of Principal Technical Agencies.
 R&D Monitoring
Research & Development activities will be carried out by STAs with the involvement direction of PTAs.
STAs may be associated with specific projects in terms of implementation, monitoring and feedback, and
in terms of general evaluation on behalf of the PTA.
STAs are most welcome to identify active research projects after consultation with the DPIUs. Such projects
should be aimed as using locally available materials or locally relevant designs with a view to effecting
economy. NRRDA will give 100% funding support to such proposals. Research work will be executed

146 Operations Manual for Rural Roads


Principal and State Technical Agencies

through DPIUs as a part of the PMGSY and the STA will monitor/ advise the DPIU and document and
report the research project.
 Technical Advice
STAs may be associated by State Governments with all activities concerning the rural road sector. The
nodal Department as well as the SRRDA should maintain close liaison with STAs and use their resources
to provide valuable policy level and technical inputs into the State Government decision making process.
The STAs will be associated with the State Level Standing Committee for the purpose.
State Governments may also, if required, commission studies through STAs on issues such as traffic
patterns, road designs, quality control, maintenance etc. STAs may however not be associated with day to
day operational issues.
PTAs would utilise STA inputs for determining R&D activities, training requirements etc.

10.4 THE ROLE AND RESPONSIBILITIES OF THE PRINCIPAL TECHNICAL AGENCIES


Principal Technical Agencies are premier institutions with in-depth knowledge of the technology of road
design and construction. As agencies helping manage technical change in rural road programmes, PTAs are
expected to:
 Oversee the activities of the State Technical Agencies (STAs) in the region and advise/ assist in resolving
issues that may arise at the time of the scrutiny of Project Proposals of the States.
 Carry out random ex-post facto checks of the Proposals scrutinised by STAs to identify systemic issues
 Organise Orientation/ Refresher Programmes for the STA Personnel for Proper Scrutiny of Project Proposals.
 Identify at SRRDA’s request the type of strengthening required for the Laboratories in the Districts (PIUs)
and also at STAs.
 Advise Programme Implementing Units (PIUs) on the basis of SRRDA request on any region specific
issues that will have a bearing on the Design, Construction and Performance of Rural Roads.
 Design and manage Regional Training Programmes for the Engineers of PIUs and Contractors by
developing course material for different training modules and acting as Resource persons/ Institutions.
 Manage Regional Quality Control System and assist NRRDA with the analysis of Quality Monitoring Reports
of State Quality Monitors (SQMs) and National Quality Monitors (NQMs). Also, help identify and resolve
the issues arising out of the Quality Monitoring System.
 Evaluate specifications, practices and the use of locally available materials for making the proposals Cost
Effective.
 Formulate design specifications for new and innovative technologies.
 Study the gaps in the existing practices in Rural Roads Construction and to identify areas for R&D. The
PTAs will also assists NRRDA in processing the R&D proposals and entrusting the same to reputed
organisations.

Operations Manual for Rural Roads


147
National Rural Roads Development Agency

CHAPTER 11
QUALITY MANAGEMENT

11.1 INTRODUCTION
In order to achieve the aim of building safe and durable roads economically, the road structure should meet
certain requirements. The characteristics that such a structure should posses should be specified through
codes of practices and enforced through contract documents. Laying down not only the technical specifications
but the workmanship and the testing and acceptance criteria, Quality Control comprises the operational
techniques of controlling quality. A Quality Assurance Standard is set when the Quality Control system is
operationalised using human resources, trained to a particular standard. Quality Management includes quality
planning to maintain a Quality Assurance Standard, as well as Quality Control. Quality Management which
includes an external mechanism providing Quality Assurance and an internal mechanism to constantly improve
the quality system is termed Total Quality Management (TQM) and PMGSY Quality Management is intended to
evolve in that direction. PMGSY aims at Quality Assurance through procedures prescribed in the PMGSY
Quality Control Handbook and enforced through the contracts framed under the Standard Bidding Document
process. Quality Control operational procedures described below need to be supported by the requisite training
and HRD measures in the SRRDAs, PIUs and contracting personnel to generate the requisite Quality Assurance.

11.2 QUALITY STANDARDS


Road works under PMGSY are designed and constructed to standards prescribed in the Rural Roads Manual
and Book of Specifications for Rural Roads of Ministry of Rural Development published by Indian Road Congress,
August, 2004. In order to provide guidance to the officers implementing the PMGSY, the NRRDA has brought
out a Quality Control Handbook at the work level, which provides the information regarding equipment for tests,
procedures for quality control tests, process of recording the test results in prescribed registers of tests and
details about the drainage aspects and third party inspections.
Proper quality testing and recording is an essential feature of PMGSY which believes that relentless testing and
meticulous quality control is the only way to build good roads.

11.3 THREE-TIER SET UP FOR QUALITY MANAGEMENT


Ensuring the quality of the road works is the responsibility of the State Governments, who are implementing the
Programme. To this end, all works must be effectively supervised. The Quality Control Register prescribed by
the NRRDA to operationalise the provisions of the mandatory testing prescribed under the specifications shall
invariably be maintained for each of the road works. Payment shall not be made to the Contractor unless the
tests have been conducted as per the prescribed procedure and the results have been found to be satisfactory.
A three-tier Quality Management mechanism is envisaged under the Pradhan Mantri Gram Sadak Yojana. The
first tier of quality management mechanism is in-house quality control system of the Executing Agency whereas,
the second tier of quality management mechanism will be independent quality assurance system operationalised
by the State Government. Therefore, the State Governments would be responsible for the first two-tiers of the
Quality Management Structure. The third tier is envisaged as independent quality management mechanism
operationalised by the NRRDA, as such, this tier would be enforced by NRRDA through the National Quality
Monitor (NQM).

11.4 FIRST TIER


11.4.1 The in-house quality control system to ensure the implementation of quality standards by way of carrying

148 Operations Manual for Rural Roads


Quality Management

out mandatory tests shall be termed as first tier of quality management mechanism. The supervision of works
by the officers of implementing agency will also form the part of this system. The PIUs as the first-tier of quality
management have the crucial responsibility in the Quality Assurance system which determines the quality
standard delivered by the Contractor. The PIU’s quality management functions shall include:
 Preparation of quality DPRs with adequate attention to aspects impinging on quality, including geometrics,
drainage and correct estimation of items and scope of work. The quality standards will be as prescribed
in the Rural Roads Manual.
 Effective selection process for contracting of execution of works, based on proven capacity and ability of
the Contractors, including access to funds, equipment and engineering resources. Even where contracting
is centralised, PIUs will be preparing the bid documents and the NITs, which are crucial in the selection of
competent contractors. The quality standards will be as prescribed in the Rural Roads Manual and specified
in the Standard Bidding Document.
 Ensuring that the Contractor brings adequate resources to bear for the proper execution of the contracted
work including
 Necessary equipment
 Qualified key engineering personnel
 Field laboratory properly equipped for testing quality
As per PMGSY guidelines, payment cannot be made to contractor unless these conditions are satisfactorily
fulfilled and work programme approved. The quality standards will be as prescribed in the Standard Bidding
Document and Quality Control Handbook.
 Supervising Site Quality Control arrangements including materials and workmanship, primarily through
testing as per provisions of the Quality Handbook.
 Taking action to ensure replacement of defective material and rectification of defective workmanship.
11.4.2 Where in-house capacity in a PIU is limited, a Project Implementation Consultant (PIC) may be outsourced
for carrying out all or any of the PIU functions including actual operation of the first level of the quality control.
The PIC will be recruited on the basis of NRRDA’s PIC procurement procedure which is quality- cum -cost
based. The PIU, as employer/principal for the PIC will continue to have overall responsibility for the first level
of quality control.
11.4.3 To ensure quality control on materials and work management at site, the PIU shall ensure that: -
(i) All the tests are conducted by the designated staff of the Contractor and the test results are recorded in the
Quality Control Registers prescribed, maintained separately for each of the road work. The registers shall
be in two parts, viz,
Part I : Quality Control Register – Record of Tests
Part II : Record of Abstract of Tests and Non-Conformance Report Register
Part 1 Register is the register of all Quality Control Tests conducted by the person who is responsible for
the basic Quality Control Testing. It is, therefore, maintained by the person who is responsible for the basic
QC tests. If the Contract provides for Quality Control by Contactor, the Part 1 Register will be issued to the
Contractor for each road work; but if the responsibility of basic QC tests is with Department (for agreements
entered into prior to adoption of SBD), the register will be issued to the site-in-charge officer of basic
quality control testing, not below the rank of Junior Engineer/Sub-Engineer.
The Part 1 Register will always be available at the work site. If some tests are required to be conducted in
a laboratory situated away from the work, the prescribed format of the test conducted will be duly filled up
on a separate sheet and this sheet will be pasted on the space prescribed for the test but the register will
not be taken away from the site in any case.

Operations Manual for Rural Roads


149
National Rural Roads Development Agency

The Part 1 Register contains forms for tests sufficient to accommodate quantities given in Para 12.2 of the
Rural Roads Manual for a length of road up to 3km.If the quantities of the items in the work exceed this,
additional forms required as per prescribed frequency may be added at the end of the register and the
corresponding entries should be done in the abstract. In case the quantities or the items in the work are
less, the remaining forms may be left blank and a corresponding note recorded in the abstract. If the
length of the road is more than 3km, additional Register(s) should be maintained. The Part I Register will
have the following three sections:
Section 1 : Earthwork
Section 2 : Granular Construction
Section 3 : Bituminous Construction
For effective Quality Control, the following percentages of various categories of tests will be done in the
presence of the JE/AE/EE:-
(ii) 50 percent of the tests are conducted in the presence of the in-charge JE of the work. The JE should
record his observations in the Quality Control Register, Part I.
(iii) 20 percent of the tests are conducted in the presence of the AE in charge of the work recorded in the
quality Control Register, Part I.
(iv) 5 per cent of the tests shall be conducted in the presence of the EE in charge of the work, and the EE
should record his observations in the Quality Control Register, Part I. The EE will also see that the Non-
Conformance Reports are issued in time and timely action is taken by the Contractor.
Register Part II is the Record of abstract of the tests conducted and Non-Conformance Reports. It will be
maintained by the site-in-charge officer not below the rank of Assistant Engineer. If the test results do not
conform to the prescribed limits, a Non-Conformance Report (NCR) in the format prescribed in the Register will
be issued to the Contractor.
11.4.4 A monthly return of the tests shall be submitted in the prescribed Profoma (Annexure 11.1) by the AE to
the EE in the first week of every month. The EE will review this return regularly to see that the Quality Control
tests are being performed at the desired frequency and with the desired accuracy. The EE will also verify that
the Non-Conformance Reports are being issued by the AE whenever non-conformance occurs and the Contractor
is taking action promptly on the Non-Conformance Reports. Payment to the Contractor shall be regulated by
the EE as per the returns of the Quality Control tests. Any deviation will be the personal responsibility of the EE.
11.4.5 The SE in charge of the circle and the Chief Engineer having jurisdiction are responsible for the proper
functioning of the PIU as part of their normal administrative duties. Their inspection and quality testing supervision
will therefore be counted as part of effective supervision of the 1st tier of quality management (and not as a 2nd
tier of quality management). The SE/ CE shall
i) During his visits to the work, oversee the operation of the Quality Control Testing procedure and record his
observation in the Quality Control Register, Part I. The SE and CE will also verify that the Non-Conformance
Reports are issued in time and action is being taken by the Contractor promptly.
ii) Prepare Inspection Reports in the prescribed formats which shall be sent to the PIU for taking remedial
action. A copy of all such reports will be endorsed to the State Quality Coordinator in the SRRDA. The
report shall be detailed and precise and shall cover all aspects of the work inspected, including: -
 Design and estimation
 DPR
 Contract Management by PIU
 Contractor performance
 Quality testing
 On line data entry status

150 Operations Manual for Rural Roads


Quality Management

11.5 SECOND TIER


11.5.1 While the 1st tier of Quality Management has the primary function of quality control through enforcement
of technical standards, the function of the 2nd tier of independent quality management is to improve the quality
and effectiveness of the enforcement process. This includes
 Checks to ensure that the 1st tier is properly functional
 Independent quality tests to verify that the quality control system is achieving its intended objective
 Detection of systemic flaws in the quality control process and action to improve the process
 Independent supervision of deterrent and punitive measures in respect of the 1st tier and the Contractor
In order to be able to take an independent, impartial and dispassionate view of quality control, it is essential that
the 2nd tier should have no stake in the outcome. In other words it should have nothing to do with the day-to –
day or supervisory management or administration of contracts so that issues of legal action against the contractor,
disciplinary proceeding against PIU officials, answerability to audit etc do not colour its judgement or actions.
11.5.2 The 2nd tier of Quality Management will function from the SRRDA, utilising upto 0.5% of the project funds
provided for the PMGSY. The 2nd tier will be headed by the State Quality Coordinator (SQC), an officer of the
SRRDA. Quality management function may be provided by a combination of
 Independent Quality Management Division of the Executing agency
 State Quality Monitor, mainly retired senior engineers of the State with adequate experience in road project
management and suitable for the assignment.
 Outsourced Consultancy organisations with proven capabilities selected on quality-cum-cost criteria based
on NRRDA’s Project Management Consultant (PMC) procurement document.
All functionaries in the system will be designated by the generic term ‘State Quality Monitor’.
11.5.3 The SRRDA will nominate/appoint State Quality Coordinator with the following minimum qualifications:
a He/She should be a graduate Civil Engineer not below the rank of Superintending Engineer.
b He/She must possess field experience of working for construction of roads for at-least five years in last ten
years. Also in the last five years he/she should have worked for at-least two years in the field of construction/
maintenance of road works.
In some cases it has been noticed that officers having the experience in the field of construction of Irrigation
structures or Water Supply schemes and now deployed for rural roads are being designated as SQCs. Appointing
an Engineer with inadequate knowledge and experience as the Head of Quality Control will defeat the very
purpose. Officers not possessing the laid down experience should not be designated to work as SQC. States
will ensure that the State Quality Coordinator appointed by the State Government possesses the above
qualifications, in case the present SQC does not possess the above qualifications State will take appropriate
steps to appoint an officer who fulfils the qualification criteria.
11.5.4 The main function of the State Quality Coordinator will be the following-
 Supervise the first tier Quality Management arrangement.
 Liaise with the STAs who function as the 2nd tier of Quality Control for Design and DPR.
 Coordinate and control the activities of State Quality Monitoring arrangement (the 2nd tier), and ensure
compilation by PIUs of action on the reports of State Quality Monitors. (SQM)
 Facilitate and coordinate the activities of the National Quality Monitoring arrangement (the 3rd tier) and
ensure compilation by PIUs of action on the reports of National Quality Monitors.
 Prepare monthly abstracts of SQM visits and an Annual Quality Report based on the Reports of SQMs and
NQMs, Identifying systemic and procedural deficiencies in the Quality Management System and submit
the Report for the consideration of the SRRDA and the State Level Standing Committee.

Operations Manual for Rural Roads


151
National Rural Roads Development Agency

 To assess training requirements at PIU level and to arrange for and coordinate training programmes
in coordination with STAs.
 To act as nodal point for request of public complaints and for taking action thereon.
11.5.5 Supervision of the 1st tier of Quality Management shall include
 Obtaining a certificate from PIUs at the time of commencement of the contract that
 Contractors have brought the necessary machinery and equipment
 Field laboratory has been established
 Key engineering personnel have been deployed by the contractor
 The work programme has been approved
After the certificate is received, the State Quality Coordinator shall intimate the Empowered Officer of
the SRRDA to allocate the credit limits for the contract and operationalise the accounting system in
order to enable payments to be made and accounted for.
 Obtaining monthly return of the tests (Annexure 11.2) conducted by the PIU, and the action taken on
non-conformance reports (see para 11.4.4). The SQC shall test check to see that payments to
contractors have not been made in the absence of satisfactory tests.
11.5.6 Liaison with the State Technical Agencies to ensure quality in Design and DPR including: -
 Holding of initial coordination meeting with STAs and PIUs (see para 6.2) to sort out issues of design,
investigation and data collection, so that DPR is of acceptable standard.
 Coordination of the scrutiny process so that STAs get adequate time to scrutinise DPRs.
 Sorting out issues raised by STAs during scrutiny of DPRs, and making references to NRRDA for
clarifications where required, through the Chief Engineer (PMGSY), (see para 7.4)
11.5.7 To coordinate and control the activities of the State Quality Monitors and operationalise the 2nd tier of
Quality Management, the SQC will proceed as follows: -
 Draw up programmes for SQM inspections in such a way that every work is inspected at-least three times.
The first two inspection of every work should be carried out during the execution of work spaced at least 3
months apart and the last inspection should be carried out on the completion of every work, within one
month of its completion.
 The schedule should be drawn up monthly, specifying the Block and preferably the road, so as to ensure
systematic coverage. Effort may be made to get those road works in the package inspected first by SQM,
which have not been inspected by the NQMs. This may include other roads in package, one road of which
was inspected by an NQM recently.
 The SQM should be asked to give his inspection report, covering all the following aspects.
(i) Design of pavement and CD woks.
(ii) Provisions made in estimates.
(iii) Management of the contract, deployment of qualified staff by the contractor and establishment of Quality
Control Laboratory by the contractor.
(iv) Work Programme and progress of work.
(v) Execution methodology and adherence to specifications.
(vi) Arrangement at Quality Testing Laboratories.
(vii) Record of Tests – Quality Control Registers and their upto date maintenance.

152 Operations Manual for Rural Roads


Quality Management

(viii) Accuracy of Quality Tests, issuance of non-conformance reports (NCR) and action of contractor on NCRs.
(ix) Inspection by departmental officer/ SQMs or NQMs and compliance of the instructions.
(x) Provision and execution of CD works and side drains.
(xi) Road furniture, Logo and Signboards.
(xii) Timely payment to the contractors.
(xiii) Other issues including the technical knowledge of the staff of the executing agency and the contractor.
 The SQC should examine the reports with regard to their adequacy and counsel SQMs in case of deficiency.
The State Quality Coordinator should send the Monitor’s reports to the Project Implementing Unit with a
copy to the SE. Compliance reports to the SQC should be routed through the CE/SE. All cases of delay in
reporting compliance and major cases of deviation from acceptable quality standards should be taken
seriously. The SRRDA may adopt a two level classification for quality Unsatisfactory and Satisfactory. The
earlier NQM formats can be used for inspection of works by the State Quality Monitors. For grading the
works as ‘Satisfactory’ and ‘Un-satisfactory’, the corresponding changes shall be made in the format.
 Each month, the SQC will compile an abstract of the SQM visits giving the District-wise grading and send
copies to the DPIU, CE, Nodal Department and NRRDA in the prescribed Format (Annexure 11.3).
 The State Quality Control Coordinator should send an Annual Report to NRRDA through the State Nodal
Agency comprising the analysed performance of the State Quality Monitoring System in a prescribed
format. The analysis should include the SQM reports, NQM reports, Action taken in individual cases and
systemic deficiencies detected and remedied.
 The Annual Quality Report will be forwarded to the NRRDA, the STAs concerned and the PTA for the
State. The PTA shall analyse the Report and after such further study and field visits as may be necessary,
with the approval of NRRDA, shall make recommendations on action to be taken at systemic and
organisational level to improve quality of constructed roads and the programme performance in general.
11.5.8 The suggested guidelines to SQM are attached as Annexure 11.4.
11.5.9 As part of the Quality Management process, the SQC shall also look after the training needs of the
PMGSY staff and contractor’s personnel, drawing up an annual programme of training at various institutions
such as the NITHE, CRRI, State Training Institutes, and Engineering Institutes etc. He shall operationalise a
management system for training programmes and ensure that training inputs are optimised.
11.5.10 The State Quality Coordinator/Head of PIU shall be the authority to receive and inquire into complaints/
representations in respect of quality of works and they would be responsible for sending a reply, after proper
investigation, to the complaint within 30 days. The SRRDA, for this purpose, shall ensure the following:
 The name, address and other details of the State Quality Coordinator will be given adequate publicity in
the State (including tender notices, websites, etc.) as the authority empowered to receive complaints.
 The State Quality Coordinator shall register all complaints and will get them enquired into by the PIU or if
circumstances so require, by deputing a State Quality Monitor.
 All complaints shall be acknowledged on receipt (giving registration number) and likely date of reply shall
be indicated. On receipt of the report, the complainant shall be informed of the outcome and the action
taken/proposed.
 Action on anonymous/pseudonymous complaints will be taken as per extant instructions of the State
Government.
 Complaints received through the Ministry of Rural Development/NRRDA will normally be sent to the State
Quality Coordinator for enquiry and necessary action. In case report from an SQM is desired, this shall be
furnished within the time specified. In case an adequate response is not received within the stated time
schedule, the NRRDA may depute an NQM and further processing will be done only on the basis of
NQM report.

Operations Manual for Rural Roads


153
National Rural Roads Development Agency

The SQC shall make a monthly report to the State Nodal Department/ SRRDA in the prescribed format (Annexure
11.5). The status of action taken on complaints shall be discussed as an Agenda item of the State Level
Standing Committee, a copy of the proceedings of which shall be sent to the MORD.
11.5.11Supplementary guidelines on quality control will be issued from time to time by the NRRDA. However,
the Nodal Agency in the State should ensure that adequate quality consciousness is created among the PIUs
Also, adequate number of SQMs should be made available under the SQC to undertake the tasks assigned to
the 2nd tier, with the designated frequency.

11.6 THIRD TIER


Whereas the State Government is responsible for Quality Management, the NRRDA arranges for external
Quality Assurance by deploying National Quality Monitors, whose responsibility is to verify that the State’s
Quality Management is adequate. Their role is to guide the Quality Management team and to give feedback on
the quality management shortcomings to enable systematic improvements.
11.6.1 As the third tier of the Quality Management Structure, the NRRDA engages independent National Quality
Monitors (NQM), mostly retired Senior Engineers from State/ Central Organisations. The detailed guidelines for
the third tier of quality management shall be issued by NRRDA from time to time. As per the present guidelines,
the NQMs are given the programme of inspection once in two months for carrying out inspection as per the
programme for the forthcoming two months, indicating the Districts (and Blocks) to be visited. The inspection
schedule of NQMs is also displayed on PMGSY web site. Guidelines for the Third Tier Independent Quality
Monitoring are available on the OMMS website. The present guidelines provide for:
 Arrangements for Inspection by NQM: The NQMs will be sent a letter of request once in two months
covering the 2 months period. The details of schedule of visit will also be available on PMGSY web site in
the last week of the preceding month to enable SQC and PIUs to make necessary arrangements:
 It will be the responsibility of the SQC to ensure adequate arrangement for inspection by the NQM,
including local stay and transport.
 The NQM is required to inspect these districts in a single visit in one State in each two months (the
total districts inspected during one visit shall not exceed three). He should finalise a suitable programme
to spend not more than 3 days in each district inspecting normally between 2-4 works on each day
and one old road work of PMGSY completed at-least 1 year back to assess the maintenance in each
district (2 works in progress or 1 work in progress and 2 completed works or 4 completed works but
in both cases 1 work of earlier phases completed at-least 1 year back to be inspected to assess the
routine maintenance). The format for inspection of work for assessment of routine maintenance shall
be prescribed by NRRDA.
 The programme of inspection is valid for the month mentioned in the letter of request only, and in no
case should the inspection spill over to the next month, since it will not be counted in a valid inspection.
Prioritisation of Works for Inspection: The NQM will prioritise the selection of roads as per guidelines
of NRRDA from time to time.
 Information and Details to be furnished to the NQM by the PIU:
 Phase wise list of all works according to the priority with details of dates of previous inspection, for the
Block of the district due to be visited.
 A road map showing location of roads to enable planning of itinerary and selection of works to be
inspected.
 Necessary work information in respect of the road selected by NQM for inspection in part-1 of the
inspection report format (formC1 and C2) for ongoing and completed works respectively.
 Any previous inspection report of the selected road and Action Taken Report thereon.

154 Operations Manual for Rural Roads


Quality Management

 Guidelines to NQMs for filling up the Inspection Formats: -


 Before filling in part-2(forms D1 and D2) respectively for ongoing and completed works, NQMs should
traverse the entire road upto the end habitation.
 NQM should focus on project management by the PIU and make his observations on
 DPR quality.
 Contract management.
 Quality management.
 Post-inspection discussion
 The NQM should hold informal meeting with the PIU officers to discuss the results of inspection and
to suggest improvements necessary in order to obtain better quality.
 Submission of Inspection Report by NQM and action by PIU/SQC
 Copy of part II of reporting format will be handed over by NQM to the PIU before leaving the district.
The NQM should also forward a copy of the completed report to the SQC and NRRDA within 10 days
of the date of completion of inspection.
 The PIU will immediately inform the SQC in case the NQM Report is not received before he leaves
the district and the SQC shall inform NRRDA.
 The SQC shall at the end of each month submit a report to NRRDA on NQM visits to the State during
the month in format given in Annexure 11.6.
 The PIU will not wait for the grading of the work to be communicated by NRRDA or SQC but will start
taking action based on inspection reports furnished by NQM immediately after inspection, unless it
disagrees with a recommendation. In all such cases, the matter should be immediately referred to
the SQC.
 SQC should ensure that the PIU takes immediate steps to implement the observation of NQM. In
case PIU proposes not to implement a recommendation the SQC should give suitable advice or if
required, seek further clarification from the NRRDA.
 The reports of the NQM will be examined in NRRDA and internal grading of works will be done as
‘Satisfactory’ or ‘Unsatisfactory’.
11.6.2 The grading of works will be done by National Quality Graders (NQG) based on the report of NQM and
the following guidelines:-
 The NQG will carefully read the observations of the NQM given in the Part II of the Inspection Report and
summarize them in the prescribed format (Annexure 11.7). Every sub-item in format F(Annexure 11.7) will
be graded as ‘Satisfactory’ (S) or ‘Unsatisfactory’ (U). Grading of sub-item will be done as per details
given in column ‘How to grade’. Based on the grading of sub-items, the main items will be graded. If, the
grading of any of the sub-items is U, the complete item will be graded as U.
 Based on the grading of the items, the grading of the work will be done on the basis of the overall grading
of the individual issues. The overall grading will be coded based on the issue(s) graded unsatisfactory in
the following manner:
 Management Standard: In this issue items about information in format C-1 /D-1 and inspections will
be incorporated and if any of the two items are graded U; the overall grading of the institutional issues
will be U, which will be graded as UMS.
 Contract Management: If any of the sub-items is graded U, the overall grading of the contract
management issues will be U, which will be graded as UCM.
 Quality of Work: The grading of quality issues will be based on grading of items pertaining to design,

Operations Manual for Rural Roads


155
National Rural Roads Development Agency

quality control arrangements and quality of works. If any of the sub-items in the items of quality
control arrangements and quality of works is graded as U, the overall quality of this issue will be U,
which will be graded as UQW.
 Works found ‘Satisfactory’ will be graded simply as ‘S’.
11.6.3 Action Taken Report
 The Following Action will be taken on the grading of works by NQG:-
 The overall grading will be communicated to the State Quality Coordinator. The action in respect of
institutional issues i.e. UMS will be taken by the SRRDA and ATR will be communicated to NRRDA.
 The action in respect of UCM i.e. contract management issues will be taken by PIU and the ATR will
be communicated to NRRDA through the SQC. If the work is graded as UCM the ATR is expected to
include details of action taken against the Contractor and/or PIU.
 The action in respect of UQW i.e. work quality issues will be taken by PIU and the ATR will be
communicated to NRRDA through the SQC. If the work is graded as UQW the ATR is expected to
include details of action taken against the Contractor and/or the staff of PIU in addition to rectification
of work. The work or any of its items graded as unsatisfactory will be required to be re-done unless
in-situ rectification is possible. While furnishing the ATR, the head of PIU will clearly mention that
whether the item of work graded as unsatisfactory has been removed and re-done and if in-situ
rectification has been done, the process of rectification will be explained in sufficient details.
 The following action will be taken by SQC in respect of Action Taken Reports:
 Whether the grading has been communicated by NRRDA or not, it will be basic duty of the SQC to
take Action Taken Report from the PIU after the lapse of one month of inspection i.e. if, inspection is
done in January the SQC must have ATR from PIU positively in the first week of March.
 As soon as the grading of particular work is communicated to SQC, the compilation of ATRs will be
carried out by him and ATR will be sent to NRRDA in format given as Annexure 11.8 within one month
of receipt of grading of the work. It is quite possible that some time will be required to complete the
action on the observations of NQM, still when the action is started it will be reported in column 5 of the
format and in column 6 word ‘Yes’ will be used if the action is complete, but word ‘No’ will be used if
action is not complete and in column 7, probable date will be shown when action is likely to be
completed. The ATR will be treated interim, if the action is not complete and the ATR will be treated
final, if the action is complete. The monitoring of Action Taken Reports will be done accordingly in
NRRDA.
11.7 QUALITY CONTROL LABORATORIES
The States are required to establish (or cause the Contractor to establish) the Field Level Quality Control
Laboratories and district Level Laboratories as per the provisions of the Rural Road Manual. The laboratories
are required to be provided with the equipments and trained staff. The Laboratories of Engineering Colleges
and other institutions can also be used for higher level of Quality Control Testing. For meeting the requirements
of testing, the SRRDA may empanel the laboratories of such institutions and may also fix the rates for conducting
different tests. The training and staffing of the Laboratories under its control should be done by the State
Governments.
Taking cognisance of the views put forward by State Executing Agencies that for conducting accurate surveys
and soil and materials tests, laboratory testing facilities need to be properly provided, it has been decided to
provide a one-time assistance for the replacement/ upgradation of District level and central level labs, acquisition
of Mobile Laboratories where ever considered necessary can also be provided. (See also para 11.4). For the
purpose:-
 The State Executing Agency will forward a consolidated proposal after joint assessment with the State
Technical Agency (STA).

156 Operations Manual for Rural Roads


Quality Management

 The requirement of equipment shall be worked out, in accordance with the Rural Roads Manual and
Quality Control Handbook issued by NRRDA.
In case of mobile laboratory equipment, the operating costs will be borne by the State Government. It is expected
that PIUs will posses survey equipments such as Dumpy level, Abney level, Theodolite, Chain, Steel and
metallic tapes, Plane table etc., in order to ensure acceptable DPR quality.
Regular training Programmes should be organised for the staff of laboratories also to ensure effectiveness of
testing process and accuracy of results.

11.8 ENTRY IN OMMS


11.8.1 In respect of NQM visits, Quality Management Division of NRRDA will place inspection data on the
website by selecting the name of the NQM and the road visited, and entering the date and grading.
11.8.2 The SQC is required to similarly enter data of SQM visit in the website on the Quality Monitoring database.
11.8.3 PIUs will check the data in the database and supply the print out of PMGSY roads in the District showing
status of previous inspection by NQM/SQM, to enable NQM to decide on the road to be inspected on a visit.

Operations Manual for Rural Roads


157
158
Annexure-11.1
(See Para 11.4.4)
National Rural Roads Development Agency

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)


Monthly Return of the Tests conducted (Return from AE/AEE to EE/Head DPIU)

Name of District: ...............................................................................Name of Block .............................................................


S.No. Name of Total No. Total No. Tests Conducted During the Month CumulativeTests Conducted Action Taken Report
Work of of Nos. Nos. Nos. Not Nos. Nos. Nos. Not Nos for. Nos. Nos. Nos.
mandatory mandatory Conducted Qualified Qualified Conducted Qualified Qualified which NCR Action Contractor’s DPIU’s Remark
QC Tests QC Tests issued taken by Action Action
required required contractor Pending Pending

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

Instructions to fill up the format


1. Sl. No. 1 & 2 are self explantory.
2. Sl. No. 3-Total No. of Mandatory tests required as per estimate to be shown.

Operations Manual for Rural Roads


3. Sl. No. 4-Total No. of Mandatory tests required during the month as per the work done.
4. In column No. 5,6 & 7 - No. of tests conducted, out of which No. of Tests which have qualified and No. of Tests which have not qualified should be mentioned.
5. In column No. 8,9 &10 - Total cumulative No. of tests conducted since the starting of the work out of which No. of Tests which have qualified and No. of Tests which
have not qualified should be mentioned.
6. In column No.11,12,13 & 14 the details of Action Taken is to be given. In column No. 11, No. of Tests for which Non-Conformance Report (NCR) has been issued
should be mentioned. Similarly for column No. 12 No. of Tests for which action has been taken by the Contractor should be mentioned and in column No. 13, No. of
tests for which action is pending at Contractor level should be mentiond. In Column No. 14, No. of tests for which DPIU’s action is pending should be mentioned.
Annexure- 11.2
(See Para 11.5.5)

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)


Monthly Return of the Tests not meeting the Standards and Action taken thereon*
(Returen from EE/PIU to SQC)

Name of District: .……………………………………………….. Name of Block ….............................…………………………

S.No. Name of Tests Conducted During CumulativeTests Action Taken Report


Work & the Month Conducted
Contract Nos. of tests Nos. not Nos. Nos. not Nos. for Nos. where Nos. where Nos. action Remark
Package No. conducted Qualified Conducted Qualified which NCR material/work work rejected pending
issued replaced/rectified

1 2 3 4 5 6 7 8 9 10 11

Operations Manual for Rural Roads


Instructions to fill up the format
1. Sl. No. 1 & 2 are self explantory.
2. In column No. 3 & 4- Nos. of tests conducted, out of which, No. of tests which have not qualified should be mentioned.
3. In column No. 5 & 6 - Total cumulative No. of test conducted since the starting of the work, out of which No. of tests which have not qualified should be mentioned.
4. In column No. 7,8,9 & 10, the details of Action taken is to be given. In column No. 7 tests for which Non Conformance Report (NCR) has been issued should be
mentioned. In column No. 8, No. of tests where the material or the work has been replaced or rectified should be mentioned and in column No. 10, No. of tests for
which Action is pending should be mentioned.
* Copy of Annexure 11.1 received form AE shall be sent to SQC along with Annexure 11.2

159
Quality Management (Annexures)
160
Annexure 11.3
(See Para 11.5.7)
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
Abstract of Report of State Quality Monitors for the month of ……………………………….

Name of State
National Rural Roads Development Agency

Grading
Sl. No. District Month of Visit No. of Works Visited Completed In Progress

C I T U S T U S T
1 2 3 4 5 6 7 8 9 10 11 12

Total District Wise

Operations Manual for Rural Roads


Total for the Month
Instructions to fill up the format
1 This format will be filled up District wise and month wise
2 Column No. 1 & 2 are self explanatory
3 In this Format C, I, T, U and S stands for Completed work, Incomplete work, Total works, Unsatisfactory and Satisfactory respectively.
4 In column No. 4, 5 & 6 No. of works visited should be mentioned.
5 In column No. 7 to 12 the works graded as Unsatisfactory and satisfactory as graded by State Quality Monitor should be mentioned.
6 The total of every District should be done and grand total should also be done.
Quality Management (Annexures)

Annexure-11.4
(See Para 11.5.8)

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)


Guidelines for Second tier of Quality Mechanism

The First tier of quality mechanism is an in-house Quality Control and supervision of not only quality of works
but also the other aspects of execution. The Second tier is envisaged as an independent monitoring mechanism
for quality control at State Level.
The State Quality Monitors will be identified by the State Government and sent for inspection of works in such
a way that each work is inspected at least three times.
In order to have uniformity in reporting and for better analysis, the format prescribed by NRRDA for Third tier of
quality monitoring issued in the month of August, 2002 can be used.

GRADING OF THE WORKS


The works will be graded in the following manner:
A. Each layer of the work will be graded separately for Material used as well as for Workmanship. The
Grading will be indicated as ‘Satisfactory’ or ‘Unsatisfactory’.
B. The overall Grading of the work will be the lesser of the two Grades (for Material used and Workmanship).
For example if Material used is ‘satisfactory’ but the workmanship is ‘Unsatisfactory’, the overall Grading
of the work will be ‘Unsatisfactory’. Only if the Average Grading of both materials used and workmanship
is ‘satisfactory’, then the overall Grading be treated as ‘satisfactory’.
In short it shall be:
1. Each layer or item of work will be graded for Material and Workmanship.
2. In case of incomplete works, only the Overall Grading will be worked out. These will be only ‘satisfactory’
or ‘Unsatisfactory’.
3. FINAL GRADING will be worked out only in case of Completed works. The Grading in these cases will
also be ‘satisfactory’ or ‘Unsatisfactory’.
It will be the responsibility of all Executing Agencies that all completed works of PMGSY are ‘satisfactory’.

Operations Manual for Rural Roads


161
National Rural Roads Development Agency

Annexure 11.5
(See Para 11.5.10)

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)

Report for the month , 2003


State

Part A: Monthly abstract of complaints with reference to quality of PMGSY works

# of pending # received # disposed off


complaints at during month Balance
start of month
less than 1 1-3 months over 3 months
month

Part B: Details of pending complaints over 1 month old

Regn # Date of From Subject Sent to Status


complaint

Part C: Action taken against contractor / official during the month


District Road name Contractor name Nature of Action taken
complaint proved against
contractor /
official

162 Operations Manual for Rural Roads


Annexure 11.6
(See Para 11.6.1)
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
Monthly Statement Showing the Visits of NQMs
(to be submitted by the SQC to NRRDA)

STATE:
Month of Inspection:

S. Name of NQM District Visited No. of No. of on- No. of Date of handing over Remark (Mention if
No. completed going works maintenance Dates of Inspection of inspection report inspection report not
works inspected works by NQM to PIU handed over
inspected inspected Start Date End Date by NQM to PIU)
1 2 3 4 5 6 7 8 9 10

Operations Manual for Rural Roads


163
Quality Management (Annexures)
National Rural Roads Development Agency

Annexure 11.7
(See Para 11.6.2)

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)


Format for Grading the Work

State: District and Block: Month of Inspection:


Name of Work:
Complete/On-going: Package No.
Date of Receipt of NQM Report:
Name of NQM:
Grading done by (NQG code) on date:

S. Issue Item Sub-Item Individual


No. Grading

1 Information in Format C-1/ D-1 1.1. General

1.2. Contract Details

1.3. *Physical Progress and Work Programme

1.4. Contract Management Information


Management Issues

1.5. QC tests

1.6. Inspections

1.7. Quality Control Monitoring

1.8 $ Maintenance

Item Grading

2 Inspections (As per item 2.1 Inspection by Departmental Officer


7 of D-1 and 5 of D-2).
2.2 Inspection by SQMs

2.3 Inspection by NQMs


Item Grading

Overall Grading

3 Contract Management (As 3.1. Delays and Action


Management

per item 1 of D-1 and 1 of


Contract

D-2 and item 10 of D-1


and item 9 of D-2). 3.2. *Work Programme

Item Grading

Overall Grading

164 Operations Manual for Rural Roads


Quality Management (Annexures)

S. Issue Item Sub-Item Individual


No. Grading

Overall Grading

4 Design of Pavements, Drainage 4.1 Pavement


and Geometrics (As per item 2
and 3 of D-1 and 2 and 3 of D- 4.2 Cross Drainage
2).
4.3 Side Drains

4.4 Geometrics

Item Grading

5 Quality Control Arrangements 5.1 Arrangements


(As per Item 5 and 6 of D-1 and
Item 4 of D-2.) 5.2 Attention to quality and QC Registers

5.3 *Plant & Machinery

5.4 *Deployment of Technical Staff

Item Grading

5 Quality of Works 6.1.1 *Preparatory work


Quality Issues

6.1. Pavements (As per Item 6.1.2 Earth Work


No.9 of D-1 and Item No.7 and 8
of D-2) 6.1.3 Sub-base

6.1.4 Base Course

6.1.5 Bitimunous Courses

6.1.6 CC Pavements

6.1.7 Shoulders

6.1.8 $ Maintenance
6.2 Drainage
6.2.1 Side Drains and catch water drains

6.2.2. CD works
6.3 Road Furniture and Markings 6.3.1 Board and Logos

6.3.2. Road Stones

6.3.3. Signages

Item Grading
Overall:

Summary of Overall Grading: Management Issues

Contract Management

Quality of Work

* Not applicable for Completed works, $ Not applicable for on-going works

Operations Manual for Rural Roads


165
166
Annexure 11.8
(See Para 11.6.3)

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)


Action Taken Statement on the Pending Reports of NQMs of the
………………… District for the month of……………………..

Name of National Quality Monitor:………………………………………………………. Date of Inspection………………….


S. Name of Block Paragraph of Report on Parawise Action Taken. Whether Action If ‘No’ in col 6, Remarks/
No. & Name of which action required. is complete specify the Date Reasons for
National Rural Roads Development Agency

Work S. No. Action Required ( Yes/No) when the Action delay if any
of Para. will be completed
1 2 3 4 5 6 7 8

(Name and Signature of Executive Engineer/ DPIU)

Remarks of SQC

Operations Manual for Rural Roads


(Name and Signature of SQC)

Guidelines to fill up the format

1. In case of works, if the overall grading of work “Unsatisfactory” or some action point is suggeste by the NQM, the action taken report is to be prepared.
2. Separate format shall be filled up for each District.
3. Column 1 & 2 are self explanatory.
4. In Column No. 3 & 4, the serial No. of paragraphs of Report of National Quality Monitor and in short the action warranted is required to be mentioned.
5. In Column No. 5, short descriptions of the action taken should be mentioned.
6. In Column No. 6, it should be mentioned that whether the action taken is complete or not.
7. If the reply in the Column No.6 is No then in Column No. 7, the date is to be mentioned on which the action will be completed.
8. Column No. 8 may be used for remarks and reasons for delay in taking action should be mentioned.
9. The Format will be filled up by the EE/DPIU and sent to SQC. The SQC will fill up the Remark Column and forward the Report to the NRRDA.
CHAPTER 12
MONITORING

12.1 ONLINE MONITORING


Computerisation of data has the advantage of reliable storage, easy retrieval, immediate processing and
complicated calculation ability useful in generating high level abstracted information for use in management.
The advantage of a Centralised database is that the range of comparison is not only vertical in terms of the time
period but also horizontal in terms of geographic spread across Districts and States. If to this is added the
facility of being able to access the data anywhere/anytime through a web-based system, the utility and
transparency is multiplied manifold, enabling an extremely high level of project management and monitoring.
The OMMS software is designed especially for PMGSY as an online web-based system with centralised database
and the principles underlying the operational management of the software are the following: -
 Data entry should be done at the point where data will be generated i.e. at the PIU level for project data
and at the STA/SRRDA and NRRDA level where their intervention contributes value addition to the data.
 The data entry should be near real-time, to enable outputs to be useful for management as well as
monitoring. This implies that the data entry should closely parallel the actual work process and to ensure
this, system checks must be in place to ensure that the data precedent is on-line before processing for the
next step is done.
 Since data entry may involve some extra effort, it must be seen to be sufficiently advantageous. This
involves building in the ability to generate MIS outputs closely resembling or better than existing manually
generated outputs and dispensing with manually generated outputs and attendant labour.
 The full power of the software is to be brought to bear to generate outputs useful at all levels – monitoring
and management output at PIU levels, progress management and management-by-exception outputs at
SRRDA level MoRD and NRRDA level and abstracted and analysed information policy and overall
management information for use in NRRDA.
 Transparency must be inbuilt in the system enabling abstracted data to be drilled down to the basic data,
generally ‘road’ or ‘Habitation’.

12.2 ONLINE MONITORING RESPONSIBILITIES


Effective monitoring of the Programme being critical, the State Nodal Departments must ensure that all aspects
of the PMGSY programme in the State are systematically monitored and feedback used for correcting deficiencies.
The Online Management & Monitoring System developed for the PMGSY is the chief mechanism for monitoring
the Programme. Officials managing the various aspects of the programme are required to furnish online all the
data in respect of road details and transactions carried out by them in the relevant module of the Online
Management & Monitoring System.
The OMMS consists of the following main modules: -
 Master data Module: - Master data includes the following
 Area master which contains data regarding the villages/Habitations and details of facilities available
at habitation level (To be entered at PIU level).
 Roads master which includes details regarding the name of the road, surface type etc. (To be entered
at PIU level).

Operations Manual for Rural Roads


167
National Rural Roads Development Agency

 Contractor master (To be entered at SRRDA level).


 MP/MLA Constituency (To be entered at SRRDA level).
 Contractor details (To be entered at SRRDA level).
 Standard bidding document (including check-list) in order to generate bidding document (to be entered
at SRRDA level).
 Rural Road Plan Module
 DRRP road data categorising it as NH/SH/MDR/ Rural Road. Further categorisation of rural roads
into Link Routes and Through Routes and also into existing routes and proposed routes. (entered at
PIU level).
 Core network data – selecting links from DRRP for inclusion in Core Network (entered at PIU level
from CN.I).
 Proposal Module: -
 Entry of annual proposals based on selection of road links from the Core Network (to be entered at
PIU level).
 Data entry of proposal details based on DPRs prepared and packaged for tendering purposes. (Initial
physical and financial data to be entered by PIUs with further entry by STA and cleared by NRRDA.)
 Tendering Module
 Tendering data and NIT. (PIU level).
 Contractor award details.(PIU level).
 Execution & Monitoring Module
 Entry of progress against each work in physical and financial terms (PIU level).
 Completion of road works (PIU level).
 Payment and fund flow Module Accounting data with regard to classified expenditure against each road
work (entered by PIU level).
 Maintenance Module: - Physical and financial data regarding 5 years contract-based maintenance (entered
by PIU level).
 Security and Administration: - Management of procedures etc (at SRRDA level).
 Quality Monitoring – Data Regarding QC inspection carried out by NQMs is entered. The monthly schedule
of inspection of NQM is entered on website.
Details of procedure for making data entry are given in the PMGSY Online Management and Monitoring System
Users Manual prepared by Centre for Development of Advanced Computing (C-DAC) on behalf of the NRRDA
(Brief mention of the procedure is also made in this Operations Manual in the relevant Chapters).

12.3 OPERATING THE ON-LINE MONITORING AND MANAGEMENT SYSTEM (OMMS)


12.3.1 The SRRDA will appoint one officer of sufficient seniority and having adequate knowledge of Information
Technology to function as the State IT Nodal Officer. His function will be to oversee the regularity and accuracy
of the data being furnished by the District PIUs. The IT Nodal Officer shall also be responsible to oversee the
upkeep of the Hardware and Software as well as the training requirements of the personnel dealing with
PMGSY. He shall maintain close liaison with C-DAC (the software developers), NIC State Unit/District Units
and the IT Division of NRRDA.
The SRRDA will ensure provision of necessary manpower, space and facilities to set up the Computer Hardware
at the District and State Level apart from ensuring regular and timely feeding of data. Since most of the data

168 Operations Manual for Rural Roads


Monitoring

would reside on the State Servers, the IT Nodal Officer must ensure that the State server is functional all
24 hours of the day.
12.3.2 The main function of the IT Nodal officers will accordingly include the following: -
 Ensuring proper management of the State server, including its functioning, maintenance, data backup,
and connectivity.
 Overseeing the proper management of the computer system at PIU level, including their functioning,
maintenance, connectivity etc.
 Monitoring the progress of data entry at PIU level and apprising the CEO of the SRRDA of persistent
delays/failure to update data.
 Supervising bulk data entry, management of data entry operator deployment etc.
 Monitoring effectiveness of online connectivity status of PIU computers, devising and implementing solutions
for better and more secure connectivity.
 Coordination with the Financial Controller for the continued and accurate operation of the payment and
fund flow module. Coordination with the SQC for ensuring updating of SQM inspection data on the OMMS.
 Liaising with the NIC officers at State and District levels, and ensuring integration of data and applications
with similar or complementary applications in State.
 Managing the PMGSY e-mail system for the State and District level functionaries and liaising with C-DAC
and NRRDA’s IT Division for the purpose.
 Developing and keeping updated, State level PMGSY website.
 Printing out monthly/quarterly MIS outputs and submitting them to the CEO of the SRRDA along with his
comments.
 Training needs assessment.
12.3.3 It shall be the responsibility of Executive Engineer/ Head of the PIU to ensure at District level, effective
up-time of the Hardware and also the Internet connectivity, with the State Server and the Central Server. He
shall be responsible for the constant updating and accuracy of data relating to the progress of road works,
record of Quality Control tests as well as the payments made. The data shall be updated as warranted but at
least once a week.
The Executive Engineer/Head of PIU is pivotal to the successful operation of the OMMS and the CEO of the
SRRDA must hold him personally responsible in case of persistent failure to keep the OMMS data updated,
since the programme funding in the District can be affected adversely. The Executive Engineer/Head of PIU
shall be responsible for:-
 Ensuring proper management of the DPIU computers and peripherals including the software, data backup
etc.
 Enforcing an Annual Maintenance Contract (AMC) for the computer system.
 Ensuring internet connectivity.
 Managing the offline software and uploading of data in case of poor internet connectivity.
 Supervising data entry in all modules of the OMMS and ensuring in particular that the payment and fund
flow module is working satisfactorily.
 Using the PMGSY email system at PIU level and liaising with the NIC’s DIO and the IT Nodal Officer on all
aspects.
 Printing monthly quarterly MIS outputs and forwarding them to the IT Nodal officer along with his comments
on the reliability of the data.

Operations Manual for Rural Roads


169
National Rural Roads Development Agency

12.4 SEQUENCING PROTOCOL UNDER OMMS


12.4.1 The PMGSY Guidelines in Para 19.3 states that the release of the second Instalment for PMGSY
projects is subject inter-alia to submission of the outputs of the relevant modules of the OMMS, duly certified by
SRRDA as being correct. These outputs relate to physical and financial progress and accounts. In order to
ensure accuracy of information at all times, system checks have been placed in the software and it is necessary
therefore that PIUs and SRRDAs ensure that data entry is accurately, systematically and regularly done into
the system, since release of instalment may otherwise get held up.
12.4.2 The following main points are therefore to be kept in view:-
 Annual Proposal cannot be placed online unless the relevant road is already entered in the Core Network,
since the roads are to be selected online from the Core Network for the purpose of annual proposals.
 The annual proposals will not be considered by the Empowered Committee until the DPR data has been
correctly entered online and verified by STA. Since this data is checked by the State Technical Agency
while scrutinising DPRs, it is essential that the data entry be made before the DPRs are forwarded to the
STA.
 Instalments are released to the SRRDA on the basis of financial and physical progress as recorded in the
OMMS .As such completion data of road works need to be entered online since the second instalment can
be released only if at least 80% to 100% of the road works of earlier years are completed and recorded as
such in the website. The completion data of the road work can be entered only if the tendering and
contractor details of the road works had been previously entered by the PIU.
 The release of instalment is also subject to 60% expenditure of the earlier released funds. The expenditure
details in OMMS are taken from the payment & fund flow module which includes an accounting system
where the package is selected from the proposals cleared and tendered, and classified payment details
are entered against each road of the package. It is necessary therefore that the accounting system should
be updated promptly by the PIU and SRRDA to avoid delays in release of funds. Needless to add, the
accounts for the PIU and SRRDA will be generated as part of this process.

12.5 M.I.S OUTPUTS AND ANALYSIS


12.5.1 Progress of Works Sanctioned During Each Year
The States shall report the progress achieved for PMGSY works sanctioned during each year as under:
 Works sanctioned during 2000-01 (Form PW-1).
 Works sanctioned during 2001-02 (Form PW-2).
 Works sanctioned during 2002-03 (Form PW-3) and so on.
The forms are given in Annexure 12.1. It may be noted that in case the OMMS data is complete and accurate,
the information is available as an output from the system.
12.5.2 Analysis of Cost per Km of PMGSY Works
The States shall submit an analysis of the cost per Km of PMGSY sanctioned during various years. Forms
CP-1, CP-2 and CP-3 etc shall be used (Annexure 12.2).
The analysis shall be done once a year.
12.5.3 Report on Projected Completion Plan
The States shall send progress reports on the projected completion plan among the works sanctioned during
the various years. Forms WP-1, WP-2, WP-3 etc shall be used (Annexure 12.3).
12.5.4 Report on Projects Completed
The States shall send progress reports on the projects completed among the works sanctioned during various

170 Operations Manual for Rural Roads


Monitoring

years. Forms CW-1, CW-2 etc shall be used (Annexure 12.4). In case data entry on OMMS is complete, these
formats are available as outputs of the system.

12.6 MONITORING AT DPIU LEVEL


The DPIU is overall responsible for all aspects of operational level monitoring of PMGSY, from preparation of
proposals and DPRs to recording the work completion for constructed road works. Project Management of
contracted road works however is the one aspect, which requires not only day to day management but also
monitoring of key indicators on periodic basis, and submission of data (paper as well as on-line) to the SRRDA
monitoring cell. If, all the transactional data is entered by PIU in OMMS, the required outputs will be available
not only to the PIU for monitoring at PIU level but also to State level for overall management and monitoring.
The monitoring at PIU level shall be carried out on the following items:
 Preparation of proposals.
 Monitoring of Survey and DPR Preparation.
 Monitoring of Works:
 Procurement.
 Physical and Financial Progress.
 Monitoring of Contract:
 Time Control.
 Quality Control.
 Advances, Payment of Works and Recoveries.
 Other Aspects of Contract.
 Final Accounts of the Contract.
 Monitoring of Routine Maintenance.
 Monitoring of Handing over of Works to PRIs after Completion of Routine Maintenance Period.
12.6.1 Preparation of Proposals: The PIU will need to monitor the process of preparation of proposals of the
road works, including the approval by District Panchayats, and ensure that the consultation process is conducted
smoothly and efficiently.
12.6.2 Monitoring of Survey and DPR Preparation: Based on the proposals cleared by the SLSC, PIUs are
to conduct survey and prepare DPRs. The head of the DPIU needs to monitor the progress on a weekly basis,
particularly the conduct of the Transect Walk.
12.6.3 Monitoring of Procurement: Once the project is cleared by the Government of India, the works are
required to be tendered in time. The State will devise suitable mechanism for monitoring of procurement of
works. However, based on the reports required in the NRRDA for monitoring of procurement, the PIU will be
required to submit report in the format shown as Annexure 12.5 to the SRRDA. The information regarding
delays in contracting for more than 90 days will be furnished by PIU to the SRRDA in the format shown in as
Annexure 12.6.
12.6.4 Monitoring of Progress of Work: For monitoring the physical and financial progress of the works at
PIU level the State will devise suitable mechanisms. However, the formats for monitoring of the progress
should be so prescribed by the State that the quarterly and monthly information required at NRRDA could be
easily extracted out of the information, furnished by PIUs to SRRDA.
12.6.5 Monitoring Implementation of Contracts: Monitoring of work under the contracts shall form an important
element of the contract management. Time and quality is the essence of the Contract and therefore, these
items should be monitored by the PIU on a regular basis. To enable monitoring the delays at SRRDA level, the

Operations Manual for Rural Roads


171
National Rural Roads Development Agency

PIUs will also furnish a report in the format prescribed as Annexure 12.7 which shall form the basis of
communication of further information to the NRRDA. These aspects need to be monitored closely not only by
SRRDA level but also by Supervisory level Engineers like Superintending Engineers. The SRRDA shall devise
a suitable mechanism for monitoring of the following aspects of the Contract at PIU/SRRDA levels:-
(a) Time Control: Suitable formats has been prescribed, however the SRRDA will be free to prescribe such
a format which will cover the aspects given in Annexure 12.7 but will also provide desired additional
information to the SRRDA.
(b) Quality Control: The responsibility of establishment of field laboratory is of the contractor and he is
supposed to maintain Quality Control Register Part-I. The SRRDA should devise suitable mechanism to
monitor this aspect including monitoring of maintenance of Quality Control Register Part-II and non-
conformance reports.
(c) Advances, Payment of Works and Recoveries: The contract allows mobilization advance and machine
advance to the contractor. It is also prescribed in the SBD that the PIU should make monthly payments to
the contractor. The SRRDA is required to devise a suitable mechanism for monitoring of this aspect.
(d) Other Aspects of Contract: Monitoring of other aspects like compliance to existing law, rules and
regulations, etc. is required to be done by the SRRDA/Nodal Department.
(e) Final Accounts of the Contract: The contract cannot be termed complete unless the Final Accounts are
settled. The aspect of timely final payment and closing of accounts requires greater attention of the senior
officers, therefore, the SRRDA should devise the mechanism for monitoring of this aspects.

12.7 MONITORING AT STATE LEVEL


The SRRDA shall closely monitor the PMGSY works on a regular basis. The items of monitoring in respect of
PIUs will need to be monitored at the State level from an overall management point of view:-
 Preparation of proposals: The SRRDA will need to monitor the process of preparation of district wise
proposals.
 Monitoring of Survey, DPR Preparation and Clearance: The process of survey, DPR preparation and
clearance of DPRs by the STA will need to be monitored on a weekly basis at the SRRDA level. The road
works needing clearance from Forest Department is to be monitored at State level. The Quarterly inspection
on Forest clearance will be furnished to NRRDA in Annexure 12.8.
 Monitoring of Procurement: Once the project is cleared by the Government of India, the works are
required to be tendered in time. The SRRDA will devise suitable mechanism for monitoring of procurement
of works. The quarterly information regarding award of contract will be furnished to NRRDA in Annexure
12.9.
 Monitoring of Proposals dropped: Sometimes, after a proposal has been cleared by MoRD, a few of the
roads, which can not be taken-up due to various reasons, are proposed by the State to be dropped. In
such cases, the details of road dropped by State along with corresponding values of road works dropped
total length of road works, number of affected habitation and name of the block should be clearly mentioned
by the State. The reason behind dropping a proposal is also to be intimated to MoRD for acceptance.
Once approved by MoRD, the corrected position should be reflected in the web as well as in the subsequent
progress reports to NRRDA.
 Monitoring of Progress of Work: For monitoring the physical and financial progress of the works the
SRRDA would be well advised to hold monthly meetings with PIU heads. The formats for monitoring of the
progress should be so prescribed by the SRRDA that the quarterly and monthly information required at
NRRDA could be easily extracted out of the information which is being furnished by PIUs to SRRDA. The
monthly and quarterly information regarding progress and its monitoring will be submitted to NRRDA by
the State in the formats given below:

172 Operations Manual for Rural Roads


Monitoring

 Format for Monthly Physical and Financial Progress – Format in Annexure 12.10.
 The following formats will be submitted by the State to NRRDA on quarterly basis.
 Format for quarterly Physical and Financial Progress – Phase-wise Format PW given in Annexure
12.1 (referred earlier).
 Format for quarterly work plan – Phase-wise Format WP given in Annexure 12.3 (referred earlier).
 The information regarding works completed during the quarter will be furnished in Phase-wise Format
CW given in Annexure 12.4 (referred earlier).
 Monitoring of Contract: As the monitoring of contract is an important element of the contract management,
the SRRDA is required to closely monitor the contract management work of the PIUs. Time and quality are
the essence of the Contract, and the PIUs are required to furnish the report in the format prescribed as
Annexure 12.7 which shall form the basis of communication of further information to the NRRDA. The
SRRDA shall devise a suitable mechanism for monitoring of the following aspects of the Contract at State
level.
 Time Control: Suitable formats have been prescribed. However the SRRDA will be free to prescribe
such a format which will cover the aspects given in Annexure 12.7 and will also provide desired
additional information to the State. The SRRDA will be required to furnish phase-wise information
regarding delay in execution of works to NRRDA in format given in Annexure 12.11. To monitor the
action taken in respect of works delayed beyond 90 days the SRRDA will be required to furnish
information in format given in Annexure 12.12.
 Quality Control: The responsibility of establishment of field laboratory is of the contractor and he is
required to maintain Quality Control Register Part-I. The SRRDA should devise a suitable mechanism
to monitor this aspect as well as monitoring of maintenance of Quality Control Register Part-II and
action regarding non-conformance reports. The SRRDA is to furnish quarterly report regarding the
second tier of quality mechanism in the format given in Annexure 11.3. The action taken statement
on pending reports of NQMs shall be furnished by the SRRDA on monthly basis in the format given at
Annexure 11.8.
 Advances, Payment of Works and Recoveries: The SRRDA is required to devise a suitable
mechanism for monitoring of mobilization advance and equipment advance to the contractor. The
monthly payments to the contractor will need to be closely monitored by the Empowered Officer of
the SRRDA, to ensure that limits are set or reset keeping in view the field situation and fund demand
forecasting can be reliably done.
The aspect of timely final payment and closing of accounts for each contract requires greater attention
of the senior officers, and the SRRDA should devise suitable mechanisms for monitoring the finalization
of final bills and completion of contracts. The SRRDA will send to NRRDA quarterly reports regarding
final payments in the prescribed format given in Annexure 12.13.

12.8 MONITORING OF PROGRESS AT MoRD/ NRRDA LEVEL


12.8.1 The progress reports and analysis data received from the States shall be analysed in the NRRDA on the
respective State files and put up to the Head of the respective Project Division. Cases of poor performance or
deviation from procedures will be brought to the notice of the Director-General on file.
12.8.2 The monitoring of ongoing works is also being done through Regional Review meetings held periodically
with SRRDAs. The items of review meeting shall include:
 Review of Institutional and capacity issues as per Annexure 12.14.
 DRRP and Core Network.
 Progress of works for Phase-I, II, III & IV etc.

Operations Manual for Rural Roads


173
National Rural Roads Development Agency

 Progress in respect of World Bank/ADB Projects where applicable.


 Quality Management.
 Maintenance.
 OMMS and Data entry status.
 Accounting Systems.
 Training and HRD.
 Unspent Balances as per Annexure-12.15.
 Forest cases.
 Delay in Final payment cases.
12.8.3 Regional Review would generally be held in May-June to take stock of progress up-to the Monsoon.
Another series of Regional Review would be held in January-February to enable assessment of final fund
requirement during the financial year, and status of preparation of proposals for the next year. These would be
supplemented with State-level discussions with SRRDAs and PIUs, particularly in the 10 Core States.

174 Operations Manual for Rural Roads


Annexure 12.1
(See Para 12.5.1)
Format- PW-…..

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)


Progress of PMGSY Works Sanctioned During Phase ...…... (for the year ……..)
Name of State

Reporting for the quarter ending............................. Length in Km and Amount in Rs.Lakh


Road Works * Physical Progress of Road Works
Upgradation
New of through Other Amount Estimated Completed Works On going Works
Connectivity Routes Upgradation as Cost after Tendered Upgradation %
# District Upgradation
cleared Technical Cost New of through Other New of through Other Physical Expenditure Remarks
by GoI Sanction Connectivity Routes Upgradation Connectivity Routes Upgradation Progress (if any)
Nos. Length Nos. Length Nos. Length
Nos. Length Nos. Length Nos. Length Nos. Length Nos. Length Nos. Length
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

This Format to be Filled-up Phase-wise and to be termed as PW-1, PW-2, PW-3 and so on.

Annexure - 12.2
(See Para 12.5.2)
Format- CP-..............

Operations Manual for Rural Roads


PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
Analysis of Per Kilometer Cost PMGSY Works Sanctioned During Phase ….. (for the year …..)
Name of State
Reporting as on ………….. Length in Km and Amount in Rs.Lakh
Road Works Sanctioned Per Kilometer Cost as per Technical Scrutiny

Upgradation Upgradation
New of through Other New of through Other Cross
Connectivity Routes Upgradation Amount Connectivity Routes Upgradation Drainage
Total as Estimated Rema-
# District length cleared Cost rks
Cost per Cost per Cost per Cost per (if
by GoI after TS Pave Pave Pave CD
Km. Km. Km. Km. any)
ment Pavement ment Pavement ment Pavement Cost
Nos. Length Nos. Length Nos. Length Cost (Col 10/4) Cost (Col 10/6) Cost (Col 10/8)

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

175
Monitoring (Annexures)
176
Annexure - 12.3
(See Para 12..5.3)
Format-WP.....
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
Projected Completion Plan PMGSY Works Sanctioned During Phase……….(for the year…….)

Upto quarter ending …………. Upto quarter ending ………


Name of State
Reporting for the quarter ending……………. Length in Km and Amount in Rs.Lakh
National Rural Roads Development Agency

Road Works
Sanctioned Estimated Completion Status as Completion Plan
Cost after Tendered on …………………. Remarks if
S. District Technical Cost Upto quarter ending.......... Upto quarter ending.......... Upto quarter ending.......... any
No Nos. Length Sanction Completed Expendit-
Nos Length Expenditure Nos Length Expenditure Nos Length Expenditure
Length ure
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

Annexure-12.4
(See Para 12.5.4)

Operations Manual for Rural Roads


Format-CW……
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
List of Completed PMGSY Works Sanctioned During Phase………. (for the year……...)

Name of State
Reporting for the quarter ending…………... Length in Km and Amount in Rs.Lakh
If Yes in col. If Grading Habitations Connected
New Date of Date of Cost of Whether Inspection
Name Connectivity/ Amount as Estimated Tendered Starting Compl Completed Inspected is not very
S. District Block Pkg. of Road Upgradation Length cleared by Cost after Cost Work etion Work by NQM/ Date of good, Name Population
No. (N/U) STA GoI after TS SQM (Yes/No) Inspection Grading action taken (2001)

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Annexure 12.5
(See Para 12.6.3)

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)


MONTHLY RETURN FOR DELAY IN AWARD OF CONTRACT FOR PMGSY WORKS
(To be submitted by PIU to CE/ SE)

STATE :
REPORTING MONTH :
YEAR OF CLEARANCE FROM GoI :

No. of Un-awarded Packages in Hand at No. of Balance Un-awarded Packages in


No. of No. of Awarded
the Start of Month Hand at the End of Month
S. Packages in Packages During
No. District Hand Awarded <75 Days 75 to 90 Days >90 Days Month <75 Days 75 to 90 Days >90 Days
Old Old Old Old Old Old
1 2 3 4 5 6 7 8 9 10 11

Operations Manual for Rural Roads


Instructions to fill up the format:
1. Row 1 & 2 are self explainatory, this information is to be prepared phase-wise. The works cleared in 2000-01, 2001-02 and 2003-04 will be treated as phase-1,
phase-2 and phase-3 respectively, therefore, in 3rd row phase will be mentioned.
2. In Column no. 3 the total number of packages cleared from GOI for the Phase under reporting should be mentioned.
3. Column no. 4 and 8 are self explainatory.
4. Column no. 5,6,7,9,10 and 11 show the number of packages pending for award of contract, period being counted from the date of clearance by Empowered
Committee.

177
Monitoring (Annexures)
178
Annexure 12.6
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
STATEMENT SHOWING DETAILS FOR PACKAGES CONTRACT NOT AWARDED FOR MORE THAN 90 DAYS (To be submitted by PIU to CE/ SE)

DISTRICT:
REPORTING MONTH:
YEAR OF CLEARANCE FROM GoI :
National Rural Roads Development Agency

S. No. Block Package No. Cost Date of Delay in Days from Reasons for Delay
(Rs. in Lakh) Clearance from Date of Clearance
GoI

1 2 3 4 5 6 7

Annexure 12.9
(See Para 12.7)
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
QUARTERLY ABSTRACT OF AWARD OF CONTRACTS UNDER PMGSY

Operations Manual for Rural Roads


(To be submitted by State to NRRDA)
STATE:
REPORTING QUARTER:
YEAR OF CLEARANCE FROM GOI :
No. of Packages, where Contract not Awarded
Month of No. of No. of
S. No. Clearance from Packages Packages Delayed for Delayed for 75 to
GOI Cleared Contracted <75 Days 90 Days Delayed for >90 Days
1 2 3 4 5 6 7
Annexure 12.7
(See Para 12.6.5)
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
MONTHLY RETURN OF DELAY IN EXECUTION OF PMGSY PACKAGES
(To be submitted by PIU to CE/ SE)
DISTRICT:
REPORTING MONTH:
YEAR OF CLEARANCE FROM GOI :

% of Work % of Work If Liq.


Date of Date of Stipulated to be Completed Delay Action Liq. Damages
S. Block Package Clearance Award Name of Date of Completed During in Reasons Taken Damages not Levied, Remarks
No by GOI of Work Contractor Completion During Month Months for Delay by PIU Levied Reasons
Month

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

Instructions to fill up the format:


1. This information is to be prepared year-wise on separate sheets.

Operations Manual for Rural Roads


2. Column No. 1 to 7 are self explanatory.
3. As per the contract data clause 19 of SBD (in case of use of other bid document for phase-1 and phase-2 works, clause relating to prescription of progress of work
for a defined part of the total period of execution may be referred) milestones are required to be achieved. In column no. 8, the milestone in terms of percentage of
work to be completed during the month should be mentioned and in column no. 9, the progress actually achieved should be mentioned. Delay in achieving the
milestone prescribed for the month in months should be mentioned in column no. 10.
4. Reason for delay should be mentioned in column no.11. Reasons should be specific to each work or the package.
5. As per the contract conditions the notice should be given to the contractor promptly, if delay is expected other appropriate action is also required if the contractor
has failed to achieve milestones.
6. As per provisions in the clause 44 of the SBD an amount equal to the liquidated damages at the rates prescribed in contract data shall be withheld/ levied. In
Column no.13 the liquidated damages as a percent of contract price should be mentioned.
7. In Column no.14 reasons for not levying liquidated damages should be mentioned.

179
Monitoring (Annexures)
180
Annexure 12.8
(See Para 12.7)
Format FC-1

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)


Quarterly Return for Forest Clearances
Quarter ........................ Year........................
National Rural Roads Development Agency

Name of the State:

No. of cases No.of cases referred to No.of cases cleared No. of cases pending at the end of quarter with Forest
S. District pending at start of Forest Department Forest Department Department
No. quarter during quarter during quarter <3 months 3-6 months >6 months Total
1 2 3 4 5 6 7 8 9

Operations Manual for Rural Roads


Monitoring (Annexures)

Annexure -12.10
(See Para 12.7)

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY) Statement showing Physical & Financial progress

Name of State: Reporting month & year : (Length in Km. Amount in Rs. Lakh)

Item Phase I@ Phase II Phase III etc.


Total Value of proposals cleared
Amount released
No. of road works
Length of road works
Value of road works
New >1000
Connectivity 999-500
Details of road No. of Habitations to
499-250 *
works cleared be benefitted
Incidentally
<500**/ <250#
No. of road works
Upgradation Length of road works
Value of road works
No. of road works completed
Length of road works completed
Expenditure
>1000
New 999-500
No. of Habitations
Connectivity
benefitted (for completed 499-250 *
road works) Incidentally
<500**/ <250#
During the % physical progress
Month No. of road works completed
Length of road works completed
Expenditure
>1000
Upgradation No. of Habitations 999-500
benefitted (for completed 499-250 *
road works) Incidentally
Physical <500**/ <250#
and % physical progress
Financial
No. of road works completed
Progress
Length of road works completed
Expenditure
>1000
New No. of Habitations 999-500
Connectivity benefitted (for completed 499-250 *
Cumulative road works) Incidentally
Figures <500**/ <250#
including % physical progress
the current No. of road works completed
month Length of road works completed
Expenditure
>1000
Upgradation No. of Habitations 999-500
benefitted (for completed 499-250 *
road works) Incidentally
<500**/ <250#
% physical progress
No. of road works completed
Length of road works completed
Total (uptodate)
Expenditure
% physical progress
@
Note: Information in this column will be prepared by the States in which only PMGSY works were taken up and
incomplete BMS works were not taken up in the Phase I, i.e. year 2000-01.
* Information to be furnished in case of Hilly, Desert or Tribal Areas only. ** Information regarding incidentally connected
habitations, where eligibility of habitations is 500 or more population. # Information regarding incidentally connected
habitations, where eligibility of habitations is 250 or more population.

Operations Manual for Rural Roads


181
182
Annexure - 12.11
(See Para 12.7)
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
QUARTERLY ABSTRACT FOR DELAY IN EXECUTION OF PMGSY WORK
(To be submitted by State to NRRDA)
STATE:
REPORTING QUARTER:
YEAR OF CLEARANCE FROM GoI :

No. of No. of Packages not Completed and Delay has already Occurred
Date of Packages Packages Remarks
National Rural Roads Development Agency

S. No. Clearance Cleared Completed


inTime Upto 75 Days Upto 75 to 90 Days More than 90 Days
1 2 3 4 5 6 7 8

Note: In this case, time period will be reckoned from date of clearance, with time period for completion being the time given in the
PMGSY guidelines.

Annexure - 12.12
(See Para 12.7)
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
QUARTERLY ABSTRACT FOR DELAY BEYOND 90 DAYS IN COMPLETION OF PACKAGES

Operations Manual for Rural Roads


(To be submitted by State to NRRDA)
STATE:
REPORTING QUARTER:
YEAR OF CLEARANCE FROM GoI:

Liquidated
Reasons Action Damages If Damages
S. District Package No. Estimated Cost Date of Award Stipulated Date of Name of Physical Progress for Taken Enforced on not
No. of Work Completion Contractor of Work Delay by PIU Contract in Enforced,
Percentage Reasons

1 2 3 4 5 6 7 8 9 10 11 12
Annexure - 12.13
(See Para 12.7)

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)


Statement Showing Details of Disposal of Final Payment Cases of Road Works

Details of Disposal of Final Payment

Total No No. of No. of No of Pkgs No of Pkg Final Brief Reasons


of Packages Pkgs - Final Payment pending for delay beyond Remarks if any
S.No. District Cleared Completed Final Payment for > *6 months 3 months if any
Packages Payment pending for
Made > *3 months

Operations Manual for Rural Roads


Total of
State

Note: Information should be given for PMGSY works of Phase 1 (Excluding BMS works), Phase 2 and Phase 3 Only.
* From Date of Physical Completion of work.

183
Monitoring (Annexures)
National Rural Roads Development Agency

Annexure 12.14
(See Para 12.8)

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)


Institutional and Capacity Issues

State: As on

No. Issues Response


of the State
A Institutional Issues
1 Setting up and operationalization of SRRDA (appointment of SQC,
Empowered Officer, Financial Controller, Nodal IT Officer, etc. )
a SRRDA: Name & Date of Registration, etc.
b Designation and Contact details of Chief Executive Officer
c SQC
d Empowered Officer
e Financial Controller
f I T Nodal Officer
2 Setting up of Programme, Administrative and Maintenance Accounts and
their operations as per Tripartite Agreement with Bank
a Date and details of tripartite agreement
b Programme account details: Bank and Account No.
c Administrative account details: Bank and Account No.
d Maintenance account details: Bank and Account No.
3 Making SRRDA nodal for rural roads and bringing PIUs under administrative
control of SRRDA
a Action taken regarding SRRDA strengthening
b Brief description of constitution of PIUs & their dedication
c Brief description and nature of administrative control of SRRDA on PIUs
4 Making the SRRDA the dedicated agency for all rural road programmes and
for maintenance
a Action taken details
5 Policy & Co-ordination role of the State level Standing Committee
a Constitution of State Level Standing Committee
b Role
c Meetings and issues (copies of minutes to be endorsed and NRRDA
to be invited)

184 Operations Manual for Rural Roads


Monitoring (Annexures)

State: As on

No. Issues Response


of the State
B Programme Issues

1 Status of preparation of Comprehensive New Connectivity Priority List


(CNCP List)

2 Conducting a Pavement Condition Survey

3 Status of preparation of Upgradation Priority Lists based on prioritization


criteria

4 State specific Standard Bidding Document

a Date and reference of order issued by the State Government for adoption
of SBD

b Providing soft copy of 36 points & SBD to NRRDA/ CDAC

5 Action taken on Centralized tendering / evaluation for attracting better


contractors and assessing bid capacity

6 State’s promptness in submission of monthly / quarterly formats prescribed


by NRRDA

a Monthly formats in format IIA and IIB

b Monthly formats in format III B and III C

c Quarterly formats PW, WP and CW, MF and FC

C Accounting Procedures:

1 Status of adoption of new Accounting System (IPAI Report)

2 Adoption of computerised accounting at SRRDA

3 Status of finalization of Audit Reports for 2000-01 / 2001-02 / 2002-03

4 Utilization certificate for 2000-01 / 2001-02 / 2002-03

5 Posting of Accountants in SRRDA

6 Ensure Empowered Officer is setting limits package & work-wise PIU-wise


and PIUs are issuing cheques to Authorized Payees only as per Tripartite
Agreement

a Date from which system of setting limits operationalised. Give reference of the
communication issued to PIUs.

b Briefly describe arrangements at State level for setting limits package wise
and work-wise. Give reference of the communication issued to PIUs.

Operations Manual for Rural Roads


185
National Rural Roads Development Agency

State: As on

No. Issues Response


of the State
c Date from which system of issue of cheques by PIU to authorized payees
operationalised. Give reference of the communication issued to PIUs.

d Arrangements at State level for ensuring that PIUs are issuing cheques to
authorized payees only. Give reference of the communication issued to PIUs.

7 Transferring unspent balances to Agency Account. Give amount transferred,


amount remaining.

D Quality Issues

1 Independent 2nd tier of quality control by identified independent Department


Engineers / retired engineers / consultancy firms.

a What is the system of second tier of quality monitoring.

b What is the frequency of inspection of works through second tier of quality


monitoring.

c What is the mechanism at State level to ensure adequate action on report of


second tier of quality monitoring.

d What are the laboratory facilities available at Circle and Divisional Level.

E Capacity Issues

1 Status of taking action on NQM Reports ensuring rectification of defective


works in every case and action against contractors with defective works

a Status of furnishing ATRs to NRRDA.

b What is the mechanism at State level to ensure adequate action on report of


third tier of quality monitoring.

2 Status of training for PIU engineers through STAs under NRRDA funded
programme.

3 Action taken in respect of inducing project management consultants at State


level and / or design & supervision consultants at PIU level to augment
capacity if required.

F Online Management & Monitoring

1 Results of review of online / offline status of PIUs and action taken to provide
better connectivity (ISDN / LAN).

2 Briefly describe PIU’s level of usage of OMMS for data entry and outputs.

3 Ensure master data entry for roads and habitations (complete DRRP).

186 Operations Manual for Rural Roads


Monitoring (Annexures)

State: As on

No. Issues Response


of the State
a Status of data entry in OMMS

b DRRP

c Annual Proposals

d 2nd level Quality Monitoring

e Maintenance

f Accounts

G Maintenance

Tender

1 Produce Road List out of OMMS and publish annual road list as on 31.3.2004

a Whether road list as on 31st March 2004* published

b Whether the road list has been generated through OMMS

2 Planning and Financing Maintenance

a Briefly explain the methodology of maintenance of works completed in first


and second phase.

b Indicate the Budget provision for maintenance of roads constructed under


PMGSY in the Budget for the year 2004-05*.

c Give methodology for allocation of funds District-wise and within District


Road-wise (Whether PCI is/ will be used).

* Appropriate year to be entered

Operations Manual for Rural Roads


187
National Rural Roads Development Agency

Annexure 12.15
See Para (12.8)

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)


Monthly report on unspent balances of PMGSY funds with the State
Government Implementing agencies

For the Month ending .

NAME OF SRRDA

Name of Account Bank Branch A/c No.

Sl.No. Rs. (In lakhs)

1. Opening balance on 1st of the month (previous month closing balance).

2. Receipts during the month (give sanction no. and date)

3. Accruals during the month


a) Interest.
b) Miscellaneous receipts other than 2 and 3 (a)

4. Expenditure during the month.

5. Unspent balance as on
(Reason for non-transfer in case of DRDA)

Empowered Officer
SRRDA
Telephone No.
Fax No.
E-mail id.

Note: -
 It should include all funds released to SRRDA from the beginning of the Programme.
 Old Amounts lying with DRDAs etc. should be indicated separately, DRDA wise, on the same proforma
till such time as the unspent balance is transferred to SRRDA account. The reason for non-transfer till
date may be indicated.
 Sl. No. 5 (unspent balance) of current report should be Sl.No. 1 of next months report.

188 Operations Manual for Rural Roads


Finance & Accounting System

CHAPTER 13
FINANCE & ACCOUNTING SYSTEM

13.1 FLOW OF FUNDS


13.1.1 SRRDA to receive funds :
The State Level Autonomous Agency, designated as the SRRDA for each State shall receive the funds for the
PMGSY from the MORD / NRRDA. These include the Programme Funds, Administrative Expenses Funds and
Maintenance Funds. The Agency will be responsible for rendering its accounts to the State Nodal Department
and the Ministry of Rural Development.
13.1.2 Bank : The SRRDA shall select a branch of any Public Sector Bank, or Institution based Bank, having a
branch at the State Headquarters and Internet connectivity for operating the PMGSY’s OMMS. Once selected,
the accounts shall not be changed to any other Bank or branch without the concurrence of the NRRDA. There
shall be a written understanding from the Bank that it will follow the Guidelines of the Government of India for
payments from PMGSY Fund. The concerned branch will maintain Internet connectivity and enter the data into
the relevant module of the OMMS. The SRRDA shall communicate to the NRRDA and MORD the details of the
Bank branch and the Account Numbers. There will be separate Account Number for the Programme Fund, for
the Administrative Expenses Fund and the Maintenance Fund.
The Bank shall provide the following facilities to the PIUs by its branches at the Headquarters of PIUs.
(i) To draw self cheque by the PIUs.
(ii) To accept deposit of moneys received by the PIU in the bank account of the SRRDA maintained at State
Level.
(iii) Clear the cheques issued on the account at par, the same day in the designated accounts.
(iv) To furnish bank statement at the close of each month showing the opening balance of bank authorisation
account, details of PIU’s cheques encashed during the month and the balance of bank authorisation
account on the closing day of the month. This statement shall also be furnished to the SRRDA.
(v) For interest paid to SRRDA, the bank statement will show both the gross amount of interest and tax
deducted at source.
13.1.3 PMGSY Programme Fund, Administrative Expenses Fund and Maintenance Fund:
The SRRDA will open with the selected bank and branch one bank account for the PMGSY Programme Funds,
one for Administrative Expenses and one for Maintenance Funds. The MORD will release the funds only to
these accounts, on the recommendations of the NRRDA, who shall satisfy itself that the requirements in the
Guidelines have been met. All payments for work related expenses under the programme will be made from the
programme fund account. No other administrative expenditure (such as purchase of vehicles and office
equipment) shall be debitable to this account. Expenses on administration for items approved by MORD
guidelines will be debitable to Administrative Account.
The Maintenance Fund will be used to manage the funding of the Maintenance contracts, and the State
Government will release funds from the State Budget for the purpose.
13.1.4 Regulation of Programme expenditure:
Expenditure under the PMGSY Programme Fund will be regulated as under: –

Operations Manual for Rural Roads


189
National Rural Roads Development Agency

1. The SRRDA will declare the Executive Engineers of PIUs/Heads of PIUs (who are the drawing and disbursing
officers of the PIU) as its ex-officio members or officers so as to enable them to draw on the funds of the
Agency from the Programme Fund Account. They shall be Authorised Signatories.
2. There will be no separate bank accounts of the PIUs for the PMGSY Programme Fund.
3. The SRRDA shall designate a senior officer as the Financial Controller of this Agency so that he can
oversee the implementation of the accounting system. The Financial Controller would be a Senior Accounts
Officer, with adequate experience in works accounting.
4. The SRRDA will nominate one of its senior officers, normally of the rank of Finance Controller or Chief
Engineer or Superintending Engineer, as the Empowered Officer. It shall be open only to the Empowered
Officer to inform the Bank of the names of the Authorised Signatories, for issuing cheques on the Agency’s
bank account.
5. The Empowered Officer will furnish this list of Authorised signatories along with attested signatures to the
Bank, apart from himself maintaining a record of it. This list will be verified quarterly and updated list
supplied to the Bank each quarter. As soon as there is a change in the name of an Authorised signatory
the Bank will immediately be informed, with instructions on disposal of cheques issued.
6. The Bank will issue Cheque Books to each of the Authorised signatories on the basis of written requisitions
from the Empowered Officer. Cheque Book numbers shall be intimated to the Financial Controller.
7. When a work is awarded, the PIU shall obtain the Bank details and account no. of the contractors and
intimate the Empowered Officer of all Account Payee information for each package, including the total
amount admissible for each account payee. The Empowered Officer will inform the Bank of the names of
Authorised Payees (contractors and suppliers with whom Agreements have been duly entered into, as
well as Statutory Authorities, such as ITO etc) and their designated payee accounts. The Empowered
Officer will authorise the payment of mobilisation and machinery advance admissible. He will authorise
payment of running bills after obtaining a certificate of satisfactory mobilisation from the PIU, which will
certify that the contractor has mobilised the required key personnel and equipment, has set up the site
Quality Control Laboratory, and has got his work programme approved. A list of the authorised payees will
be entered in the Master of the OMMS by the Empowered Officer enabling operations of the Accounting
Module for the package.
8. The Empowered Officer will lay down suitable limits on monthly/quarterly payments in line with the agreed
Works Programme for the respective packages. Standing instructions will be issued to the Bank Branches
by the Empowered Officer in this regard.
9. The Authorised Signatories will make payments, as per the established PWD procedure, by Account
Payee cheque mentioning the designated payee accounts. They will immediately enter the cheque and
payee details in the Payment Module of the OMMS, and also issue an advice to the Bank which may
consist of electronic advice available on the OMMS Accounting Module.
10. On presentation of the cheque, the Bank would satisfy itself after checking the advice from the PIU that the
payment details have been entered in the Payment module, and that the cheque meets with all other
requirements, among others, like signatures agreeing with specimen signatures, the cheque amount being
within the balance authorised limit, and the payee being the authorised payee, payee account details
being fully and correctly specified etc. The Bank will then made payments and confirmatory entries in the
OMMS Accounting Module.
11. Normally, there will not be any self-cheque drawn on the PMGSY Programme Funds Account. However, in
individual cases, the Empowered Officer may make the Executive Engineer/Head of PIU an authorised
payee for a specified amount and also as one time measure only. There will not be any standing directions/
instructions to the Bank for this.
12. The Bank will not allow the funds to be used by any person other than the Authorised Signatories and for
any purpose other than the authorised payment for Works taken up under the PMGSY. Nor will it be open
190 Operations Manual for Rural Roads
Finance & Accounting System

to the SRRDA to invest these funds in any other Bank Branch, whether for short or medium term, including
under Fixed Deposits.
13. The Bank will render monthly account, in respect of PMGSY Funds, to the SRRDA and the National Rural
Roads Development Agency by processing the data on the Receipts and Payment Modules of the OMMS.
It will also inform the concerned PIU of its cheques encashed.
14. A tripartite Memorandum of Understanding will be entered into between the Bank, State-level Agency and
the Ministry of Rural Development wherein the parties would agree to abide by the provisions of the
Guidelines. In particular, the Bank will agree to abide by the instructions issued, from time to time, by the
Ministry of Rural Development/ National Rural Roads Development Agency (NRRDA) regarding the
operation of the Account. The Bank will not make any advance, overdraft or loans to any State Government
or its agency or unit or corporation or any one else out of or against the security of the investments or
funds or PMGSY account under any circumstances.
15. All funds in excess of Rs. 50 (fifty) lakhs will be automatically maintained by the bank as Fixed Deposits, at
an interest rate not below that of Treasury Bill for 91 days. The Bank may encash the Fixed Deposits in
tranches of Rs. 25 lakhs by paying the interest for the days of the FDR without any reduction in the rate of
interest (The Reserve Bank of India follows this procedure for investing in 91-day treasury bill the surplus
funds of the State Government and Union Government).
16. Money accruing as Interest will be added to the same account. The expenditure out of this interest amount
will be guided by the instructions/ guidelines to be issued by the Ministry of Rural Development/ NRRDA
from time to time. The Bank shall intimate to the SRRDA, the interest amount credited by it to the Account
from time to time. The MORD or the NRRDA may, from time to time, issue such directives to the Bank/
SRRDA as necessary for smooth flow of funds and effectiveness of the Programme, and the Bank shall
take note of the advice, and comply with such directives.
13.1.5 Regulation of Administrative Expenditure: Unlike the Programme Fund, the Administrative Fund
may be credited with funds from both PMGSY and the State Grant-in-aid. These are funds necessary for the
administration of the SRRDA and PIUs and for Quality Management. The operation of the Administrative
Account will be as follows:-
1. The SRRDA will declare the Executive Engineers of PIUs/Heads of PIUs (who are the drawing and disbursing
officers of the PIU) as its ex-officio members or officers so as to enable them to draw on the funds of the
Agency from the Programme Fund Account. They shall be Authorised Signatories.
2. There will be no separate bank accounts of the PIUs for the PMGSY Administrative Fund.
3. The Bank will issue Cheque Books to each of the Authorised signatories on the basis of written requisitions
from the Empowered Officer. Cheque Book numbers shall be intimated to the Financial Controller
4. The position of the PMGSY administrative expenses and travel expenses which are meant for PIUs will be
distributed in the form of limits under intimation to the Bank.
5. The 2nd tier quality monitoring expenses shall only be used to the purposes specified in the guidelines.
They shall not be used for defraying administrative and travel expenses except travel expenses of designated
State Quality Monitors.
6. The Authorised Signatories will make payments, as per the established procedure, by Account Payee
cheque mentioning the designated payee accounts. They will immediately enter the cheque and payee
details in the Payment Module of the OMMS, and also issue an advice to the Bank which may consist of
electronic advice available on the OMMS Accounting Module. However, the Empowered Officer may
allow drawal of self cheques by PIUs within an overall limit, to meet petty expenses.
7. On presentation of the cheque, the Bank would satisfy itself after checking the advice from the PIU that the
payment details have been entered in the Payment module, and that the cheque meets with all other
requirements, among others, like signatures agreeing with specimen signatures, the cheque amount being

Operations Manual for Rural Roads


191
National Rural Roads Development Agency

within the balance authorised limit, and the payee being the authorised payee, payee account details
being fully and correctly specified etc. The Bank will then made payments and confirmatory entries in the
OMMS Accounting Module.
8. The Bank will not allow the funds to be used by any person other than the Authorised Signatories and for
any purpose other than the authorised payment for Works taken up under the PMGSY. Nor will it be open
to the SRRDA to invest these funds in any other Bank Branch, whether for short or medium term, including
under Fixed Deposits.
9. The Bank will render monthly account, in respect of PMGSY Funds, to the SRRDA and the National Rural
Roads Development Agency by processing the data on the Receipts and Payment Modules of the OMMS.
It will also inform the concerned PIU of its cheques encashed.
10. A tripartite Memorandum of Understanding will be entered into between the Bank, State-level Agency and
the Ministry of Rural Development wherein the parties would agree to abide by the provisions of the
Guidelines. In particular, the Bank will agree to abide by the instructions issued, from time to time, by the
Ministry of Rural Development/ National Rural Roads Development Agency (NRRDA) regarding the
operation of the Account. The Bank will not make any advance, overdraft or loans to any State Government
or its agency or unit or corporation or any one else out of or against the security of the investments or
funds or PMGSY account under any circumstances.
11. All funds in excess of Rs. 50 (fifty) lakhs will be automatically maintained by the bank as Fixed Deposits, at
an interest rate not below that of Treasury Bill for 91 days. The Bank may encash the Fixed Deposits in
tranches of Rs. 25 lakhs by paying the interest for the days of the FDR without any reduction in the rate of
interest (The Reserve Bank of India follows this procedure for investing in 91-day treasury bill the surplus
funds of the State Government and Union Government).
12. Money accruing as Interest will be added to the same account. The expenditure out of this interest amount
will be guided by the instructions/ guidelines to be issued by the Ministry of Rural Development/ NRRDA
from time to time. The Bank shall intimate to the SRRDA, the interest amount credited by it to the Account
from time to time. The MORD or the NRRDA may, from time to time, issue such directives to the Bank/
SRRDA as necessary for smooth flow of funds and effectiveness of the Programme, and the Bank shall
take note of the advice, and comply with such directives.
13.1.6 Regulation of Maintenance Expenditure:- SRRDA’s are required to have separate maintenance
funds and operate a separate Maintenance Fund Account with the same bank which operates the other two
accounts, namely Programme Fund Account and Administrative Expenses Account. Funds for this account will
primarily flow from the State Government and may also come from other sources. The funds will be used for
payments to contractors for the routine maintenance of rural roads for five year after construction. Guidelines
for the management of this fund will be issued from time to time as required. Similarly, its accounting procedure
will be laid down separately.

13.2 ACCOUNTING SYSTEM


13.2.1 Since the PMGSY funds are now administered by the SRRDA and are, therefore, outside the Government
finances (with no role for the district treasury and the State Accountant General), it is necessary to maintain
accounting system capable of on-line monitoring and management. This system has now been developed by
the Institute of Public Auditors of India (IPAI), and a software for the accounting system has been developed by
the C-DAC. Until the OMMS system becomes fully operational, the accounts will be kept on manual basis on
the procedures and formats prescribed by IPAI
13.2.2. The new system, while retaining the basic structure of the PWD accounting system, incorporates the
following:
a. Bank authorisation account will be opened and operated both in the books of accounts of PIUs and the
SRRDA.
b. SRRDA shall maintain PIU-wise ledger account for the “Programme Fund, Admn. Fund and Maintenance

192 Operations Manual for Rural Roads


Finance & Accounting System

Fund” as well as “Bank Authorisation”. The balances in these accounts kept by SRRDA must agree with
the balances appearing in the monthly accounts of the PIU.
13.2.3 Chart of Accounts:- Transactions under PMGSY works are further sub-divided according to the chart
of accounts. The chart of accounts of PMGSY is like the List of Major and Minor Heads of Accounts for Government
transactions. The prescribed chart of accounts for PMGSY is as follows:

CHART OF ACCOUNTS FOR PMGSY PROGRAMME FUND

Head of Account Credit / Account Entry


Debit Head To be
Balance Number made By

Programme Funds
Programme Funds received by SRRDA from GoI Credit 1.01 SRRDA
Programme funds transferred by SRRDA to PIU Debit 1.02 SRRDA
Programme funds received by PIU from SRRDA Credit 1.03 PIU
Bank Authorization Account (Books of SRRDA) Credit 1.04 SRRDA
Bank Authorization Account (Books of PIU) Debit 1.05 PIU
Incidental funds generated from interest and net Incidental Credit 1.06 SRRDA
Receipts etc. and PIU
Funds transferred from interest income to Administrative Expenses Debit 1.07 SRRDA
Fund on orders of the Ministry of Rural Development
Statutory Deductions from Contractors/suppliers
Income Tax and Surcharge from contractors/ Suppliers Credit 2.01 PIU
Commercial/Sales/Entry tax from contractors / Suppliers Credit 2.02 PIU
Any Other statutory deductions Credit 2.03 PIU
Deposits Repayable
Earnest Money Deposits from Contractors / Suppliers Credit 3.01 PIU
Security Deposit from contractors/ Suppliers Credit 3.02 PIU
Sums due to contractors on closed accounts Credit 3.03 PIU
Miscellaneous Deposits Credit 3.04 PIU
Purchases (Suspense) Credit 4.01 PIU
Spare number for future use
Expenditure on works
Construction of New Roads Debit 11.01 PIU
Up-gradation of existing Roads Debit 11.02 PIU
Expenditure on Plantation Debit 11.03 PIU
Expenditure on Sign Boards Debit 11.04 PIU
Technical Monitors Debit 11.05 PIU
Laboratory and Equipment Debit 11.06 PIU
Detailed Project Report Debit 11.07 PIU

Operations Manual for Rural Roads


193
National Rural Roads Development Agency

Head of Account Credit / Account Entry


Debit Head To be
Balance Number made By

Materials at Site Account (Material issued to Departmental Works)


Construction of New Roads Debit 12.01 PIU
Up-gradation of existing Roads Debit 12.02 PIU
Stores and Stock Debit 13.01 PIU
Misc. Works Advance
Against Contractors Debit 14.01 PIU
Against Staff Debit 14.02 PIU
For DPR Preparation
Cash Balance
Cash in Chest Debit 15.01 PIU
Imprest with Staff Debit 15.02 PIU
Bank Balance
Bank Debit 16.01 SRRDA
Advances
Advance Payment to Contractors Debit 17.01 PIU
Materials issued to contractors Debit 17.02 PIU
Secured Advance against materials Debit 17.03 PIU
Mobilisation Advance Debit 17.04 PIU
Machinery Advance Debit 17.05 PIU
Advances to Suppliers Debit 17.06 PIU
Other Advances Debit 17.07 PIU
Spare No.
Income Tax
Tax deducted at Source on the investments of SRRDA Debit 19.01 SRRDA
Balance Sheet
Balance Sheet Account NIL 20.01 PIU/ SRRDA
Incidental Receipts
Interest received from Bank Account Credit 21.01 SRRDA
Forfeiture of Earnest Money Deposit Credit 21.02 PIU
Fines, Forfeitures, Penalties etc Credit 21.03 PIU
Any Other non refundable Deductions from Contractor / Supplier Bill Credit 21.04 PIU
Miscellaneous Receipts Credit 21.05 PIU / SRRDA
Recoverable Administrative Expenses Debit 22.01 PIU / SRRDA
Spare numbers for future use

194 Operations Manual for Rural Roads


Finance & Accounting System

EXPLANATORY NOTES ON CHART OF ACCOUNTS PROGRAMME FUNDS

ACCOUNT Explanatory Notes


CODE/HEAD

1.01 Funds received by the SRRDA at State level from the Government of India shall be credited.

1.02 Programme funds transferred through Bank Authorisation by SRRDA to PIU shall be accounted for
by Debit to this account code in the Transfer Entry Book of the SRRDA. Moneys if any, received by
the PIU relating to Programme and deposited in the Bank Account of SRRDA by the PIU shall be
accounted for by credit to this account on the receipt side of Cash Book of SRRDA in “Bank Column”.

1.03 Programme funds received through bank Authorisation by PIU from SRRDA shall be accounted for
by Credit to this account code on the receipt side of the Cash Book of PIU in “Bank Authorisation”
column. Moneys, if any, received by PIU relating to programme shall be accounted for on the
receipt side of PIU Cash Book in “Cash column” by credit to related account code. On deposit of
such moneys in the Bank account of SRRDA it shall be accounted for on the “Payment side” of the
cash book in “Cash” column by debit to this account code.

1.02 & 1.03 Account code 1.02 & 1.03 shall be squared up and hence shall not appear in State Level Consolidated
Balance Sheet of PIU and SRRDA.

Programme funds transferred through Bank Authorisation by SRRDA to PIU shall be accounted for
by Credit to this account code in the Transfer Entry Book of the SRRDA.On receipt of the statement
for the cheques drawn by the PIU during the month against Bank authorisation in the prescribed
format the SRRDA shall account for the amount of cheques drawn by the PIU on the payment side
of its cash book in Bank column by debit to this account code.

1.04 Programme funds received through Bank authorisation by PIU from SRRDA shall be accounted for
by the PIU on receipt side of its cash book in Bank Authorisation column.All payments made by the
PIU against Bank authorisation shall be accounted for by the PIU on the payment side of its cash
book in “Bank Authorisation” column.No ledger account of Bank Authorisation account shall be
maintained by the PIU as the Cash Book of PIU with column “Bank Authorisation” on the receipt as
well the payment side will serve the purpose of ledger.

1.05 Account code 1.04 and 1.05 shall be squared up and shall not appear in State Level Consolidated
Balance Sheet.

1.06 At the close of each financial year shall be adjusted by credit to this (1.06) account code.

2.01, 2.02 & Statutory deductions viz. Income tax, Commercial Tax, Sales Tax, surcharge on tax and any other
2.03 Tax etc. made from the payments to Contractors/Suppliers by the PIU shall be credited.The payment
to the concerning authorities by the PIU shall be made by debit resulting in NIL balance.

3.01 Earnest money deposits received from Contractors/Suppliers shall be credited.

3.02 Security Deposits received/recovered from Contractors/Suppliers shall be credited.Refund of Earnest


Money Deposit/Security Deposit shall be Debited resulting in NIL balance.

3.03 Sums due to Contractors on closed accounts shall be credited. The payment to Contractors shall
be made by Debit resulting in NIL balance.

3.04 All other deposits received by PIU shall be credited and refund thereof shall be made by Debit
resulting in NIL balance. Amount with-held and any other refundable deduction from the bill of the
Contractor/Supplier shall also be credited to this account code.

Operations Manual for Rural Roads


195
National Rural Roads Development Agency

ACCOUNT Explanatory Notes


CODE/HEAD
4.01 Materials purchased from Suppliers remaining unpaid during the month shall be accounted for by
debit to the concerned account code and credit to PURCHASES. The payments to suppliers in
subsequent month shall be made by Debit to Purchases resulting in NIL balance. It is a suspense
head to account for the unpaid materials at the close of the month.

11.01 & 11.02 Expenditure on works: The works have been classified as per guidelines of the Government of
India, Ministry of Rural Development (MORD). Expenditure incurred for the execution of works
shall be debited to the works concerned. Account Codes are self-explanatory i.e. Construction of
New Roads and Up-gradation of Existing Roads.

11.03 Expenditure on plantation on both sides of the road shall be debited to this Account Code.

11.04 Expenditure of fixing of Sign Boards on the roadside as per guidelines of MORD shall be debited to
this Account Code.

12.01 & Materials required for the execution of works shall be routed through Stores and Stock Account.
12.02 Materials issued from Stores shall be debited to Material and Site and its account shall be maintained
by the Site Engineer. When the Materials are finally consumed on the works the expenditure shall
be debited to works concerned under major code 11 by Credit to this account code.Unconsumed
Materials/Tools & Plants, if any, left at the site of work shall be returned to Stores and the cost
thereof shall be adjusted by debit to Account Code 13.01 “Stores & Stock” and Credit to this Account
Code. This Account Code shall finally be closed with “NIL” balance. Scrap, if any, shall also be
returned to Stores for auction.

13.01 Value of stores purchased shall be debited to this Account Code and issues thereof from Stores to
site of work/Contractors shall be credited to this Account Code by debit to Account Code of works
concerned under Major Head–12–”Expenditure on Materials directly charged to works (MAS) or
Account Code 17.02-Materials issued to Contractors.Stock account code 013.01 shall be minus
debited/minus credited in the following cases:

1. In the absence of the bill of Supplier approximate value of the unpaid materials received during
the month is adjusted by debit to stock account code 13.01 and credit to purchase. Suspense
account code 04.01. If the actual payment for the supplies is found to be less than the approximate
value, the difference shall be adjusted by minus debit to account code 13.01 and debit to account
code 04.01.

2. There may be some credit balance in stock account “Account Code 13.01” at the time of closing
stores due to issue rates. Such credit balance (profit on stock) shall be adjusted by minus credit
to account code 13.01 and credit to miscellaneous receipt account code 021.07 and stock
account code 13.01 shall be closed with NIL balance.

Scrap in stores, if any, shall be sold by auction and sale proceeds thereof shall be credited to
Account code 021.07 “Miscellaneous receipts”.At the close of scheme the value of stores and
stocks, if any, shall be adjusted as per guidelines issued by Govt. of India, Ministry of Rural
Development.

14.01 & Any expenditure, which can not be debited to any Account Code and require investigation/recovery
14.02 from the Contractor/staff shall be debited to Account Code number 14.01/14.02. Theft/losses shall
also be debited to this account code. It is a suspense head and is to be adjusted by debit to final
Account Code and credit to 14.01/14.02 after investigation. This Account Code is to be finally
closed with NIL balance.

196 Operations Manual for Rural Roads


Finance & Accounting System

ACCOUNT Explanatory Notes


CODE/HEAD
15.01 Account Code-Cash in Chest is self explanatory. Cash balance appearing in Cashbook at the close
of month shall be shown against this Account Code.

15.02 Imprest issued to staff for petty expenses/purchases/labour payment shall be debited to this account
code. On receipt of account this account code shall be adjusted by debit to final head of account
code relating to expenses. This Account Code is to be finally closed with NIL balance.

16.01 Funds received by SRRDA from Govt. of India, Ministry of Rural Development shall be kept in an
account opened in any one of the Scheduled Bank. The funds shall be transferred to PIU through
“Bank Authorisations”. Bank account for the funds received from the State Govt. shall be opened in
another Scheduled Bank, so that the transactions from Central and State funds may not be mixed-
up. Name of the Scheduled Bank in which account is opened shall be incorporated in the Chart of
Account.Funds shall be released on the basis of requisition of PIU. Bank reconciliation statement
shall be prepared at the end of each month by SRRDA as well as PIU to reconcile the difference, if
any, in balance as per Bank and Cash Book.

17.01 Advance Payment if any made to the Contractor against his running bill shall be debited to this
account code. Recovery as and when effected shall also be credited to this account code.

17.02 Materials issued to the Contractors from store shall be debited to this account code. Materials as
per requirements of the work and as per terms and conditions of contract shall be issued and cost
thereof shall be recovered on the basis of its consumption

17.03 Secured advance against imperishable materials brought to site of work shall be debited. Secured
advance shall be limited to 75 per cent of value thereof and for the quantity actually required and
brought to the site of work. Advance shall be given after signing indenture in the prescribed format
and it shall be recovered on the basis of consumption.

17.04 & These advances shall be debited to the concerned Account Code. The advances shall be given
17.05 strictly as per terms and conditions of agreement after ensuring its recovery. Advance shall also be
recovered as per terms and conditions of the Agreement.Interest recovered from the Contractor on
the amount of advance shall be credited to Miscellaneous receipts account code 21.05.

17.06 Advances to Suppliers shall be debited to this account code. Advances shall be given as per
conditions of supply order after ensuring its security and recovery. Recovery of advances shall be
adjusted when supplies are received and accepted.

18.01 All payments relating to repairs and maintenance of the road after the expiry of Defects Liability
Period as per terms and conditions of the contract shall be debited to this account code. Expenditure
on repairs and maintenance of Sign Boards and maintenance of road side plantation shall also be
debited to this account code.Schedule of works expenditure shall be prepared showing the road
wise details of expenditure for the month and to end of the month etc. and the total of the schedule
shall agree with that shown in the account.

19.01 Tax deducted at source by the Bank from the interest shall be debited to this account code. Refund
for the same shall be claimed from Income Tax Department.

20.01 This account code shall be operated to account for the assets and liabilities of the programme if the
SRRDA has been changed. The following adjustment shall be done to account for the assets and
liabilities.

Operations Manual for Rural Roads


197
National Rural Roads Development Agency

ACCOUNT Explanatory Notes


CODE/HEAD
(i) Debit : Balance Sheet Account
Credit : Liabilities
(ii) Debit : Assets
Credit : Balance Sheet Account

This account code shall be closed with NIL Balance.

21.01 Gross amount of interest received on deposits etc. shall be credited to this head of account.

21.02 to These account codes are self-explanatory. Account Code 21.03 will also include deduction on
21.04 account of non-refundable liquidated damages etc. from the bill of Contractor.

21.05 All other receipts shall be credited. Sale proceeds of scrap etc. shall also be credited. Interest
recovered from Contractor against mobilisation/ machinery advance shall also be credited. At the
close of each financial year the total amount of incidental receipts shall be credited to Account
Code 1.06 Incidental Funds generated from interest etc. and account code 21 shall be closed with
NIL balance.

Note: –
1. Account Codes (1.02 and 1.03) and (1.04 and 1.05) while preparing the balance sheet of the state by the
SRRDA will be normally squared up. Monthly meetings of the PIUs shall be arranged by SRRDA so that the
differences if any may be reconciled and adjusted.
2. Balances if any against major code numbers 3, 4, 13, 14, 16 and 17 at the close of the scheme shall be
adjusted as per the guidelines issued by the Govt. of India, Ministry of Rural Development.

198 Operations Manual for Rural Roads


Finance & Accounting System

CHART OF ACCOUNTS FOR PMGSY – ADMINISTRATIVE EXPENSES FUNDS


The Chart of Account for Administrative Expenses Fund is as follows:
Charts of Accounts
PMGSY - Administrative Expenses Fund

Head of Account Credit / Account Entry


Debit Head To be
Balance Number made By
Administrative Funds
Central Administrative Expenses Funds received by SRRDA from GoI Credit 51.01 SRRDA
Central Administrative Expenses Funds transferred by SRRDA to PIU Debit 51.02 SRRDA
Central Administrative Expenses Funds received by PIU from SRRDA Credit 51.03 PIU
State Administrative Expenses Funds received by SRRDA from Credit 51.04 SRRDA
State Government
State Administrative Expenses Funds transferred by SRRDA to PIU Debit 51.05 SRRDA
State Administrative Expenses Fund received by PIU from SRRDA. Credit 51.06 PIU
Bank Authorization Account(Books of SRRDA) Credit 51.07 SRRDA
Bank Authorization Account(Books of PIU) Debit 51.08 PIU
Incidental funds generated from interest and net Incidental Receipts etc. Credit 51.09 SRRDA/PIU
Cash and Bank Balance
Cash in Chest Debit 52.01 PIU/SRRDA
Imprest with Staff Debit 52.02 PIU/SRRDA
Bank Balance Debit 52.03 SRRDA
Fixed Deposits with Bank Debit 52.04 SRRDA
Income Tax ( Receivable)
Tax Deducted at source Debit 53.01 SRRDA
Administrative Expenses
Travelling expenses Debit 54.01 SRRDA/PIU
Telephone Expenses Debit 54.02 SRRDA/PIU
Maintenance of Computers Debit 54.03 SRRDA/PIU
Internet Expenses Debit 54.04 SRRDA/PIU
Data Entry Costs Debit 54.05 SRRDA/PIU
Other Office Expenses Debit 54.06 SRRDA/PIU
Quality Monitoring Expenses Debit 54.07 SRRDA
Bank Charges 54.08 SRRDA
Any other expenses with approval of MoRD 54.09 SRRDA/PIU
Expenses approved by the State Government to be incurred from Debit 54.10 – SRRDA/PIU
Funds it provided. 54.19
Assets expenses allowed by the MoRD (i.e., computers) Debit 54.20-24 SRRDA/PIU
Assets expenses allowed by State Government Debit 54.25-54.30 SRRDA/PIU
Incidental Receipts
Interest received from Bank Credit 55.01 PIU
Miscellaneous Receipts Credit 55.02 PIU

Operations Manual for Rural Roads


199
National Rural Roads Development Agency

EXPLANATORY NOTES ON CHART OF ACCOUNTS FOR PMGSY


ADMINISTRATIVE EXPENSES FUNDS
ACCOUNT Explanatory Notes
CODE/HEAD
51.01 Funds received from Govt. of India by SRRDA shall be credited
51.02 Funds Transferred during the year by SRRDA to PIU shall be debited to this account
51.03 Funds received during the year by PIU from SRRDA shall be credited to this account
51.04 Funds received during the year from State Government by SRRDA shall be credited to this account
51.05 Funds transferred during the year by SRRDA to PIU shall e debited to this account
51.06 Funds received during the year by PIU from SRRDA will be credited to this account
51.07 Administrative Expenses funds transferred through Bank Authorisation by SRRDA to PIU shall be
accounted for by credit to this account in the Transfer entry book of SRRDA
51.08 Administrative Expenses funds received through Bank Authorisation by o PIU from SRRDA shall
be accounted for by the PIU on receipt side of its cash book in the Bank Authorisation column.
51.09 At the close of each financial year all incidental receipts in Major account code 055 shall be adjusted
by credit to this account code.
52.01 Account Code-Cash in Chest is self-explanatory. Cash balance appearing in Cashbook at the
close of month shall be shown against this Account Code.
52.02 Imprest issued to staff for petty expenses/purchases etc. shall be debited to this account code. On
receipt of account this account code shall be adjusted by debit to final head of account code
relating to expenses. This Account code is to be finally closed with NIL balance.
52.03 Funds received from Govt. of India, Ministry of Rural Development and State Government shall be
kept in one account opened in any one Scheduled Bank in accordance with PMGSY guidelines.
Funds shall be transferred to PIU’s through’ Bank Authorisations’
52.04 The tripartite agreement wit the bank provides for automatic investment of surplus funds with the
bank in fixed deposits. This head is for that purpose
53.01 Tax deducted at source from the amount of Interest on Deposits etc. shall be debited to this Head
of Account.
54.01 to These account codes are self explanatory
54.30
55.01 Gross amount of interest received on deposits etc shall be credited to this Head of account.
55.02 This account code is self explanatory.
Note: –
1. Account code number 51.01 and 51.02 for the receipt/transfer of funds shall be operated by the SRRDA only.
2. Account head code 51.03 for the receipt of funds shall be operated by the PIUs only.
3. At the close of each financial year: –
(a) Administrative Expenses shall be adjusted by debit to account code number 54.01 or 54.19
(b) Incidental receipts shall be adjusted by credit to account code 51.02 or 51.04
4. Balance sheet as on 31st March shall show only the unspent amount of the fund on liability side and cash/Bank
balance on asset side.
5. Subsidiary registers for administrative/incidental receipts shall be maintained as laid down by the State Govt.
6. Unspent balance amount of the fund as on 31st March shall be carried forward in the next year.

200 Operations Manual for Rural Roads


Finance & Accounting System

CHART OF ACCOUNTS FOR PMGSY MAINTENANCE FUND

Head of Account Credit / Account Entry


Debit Head To be
Balance Number made By
Maintenance Fund
Central Maintenance Fund (received by SRRDA from GOI) Credit 101.01 SRRDA
Central Maintenance Fund transferred by SRRDA to PIU Debit 101.02 SRRDA
Central Maintenance Fund received by PIU from SRRDA Credit 101.03 PIU
State Maintenance Fund received by SRRDA from State Government Credit 102.01 SRRDA
State Maintenance Fund transferred by SRRDA to PIUs Debit 102.02 SRRDA
State Maintenance Fund received by PIU from SRRDA Credit 102.03 PIU
Maintenance Funds from Other Sources
Source A Credit 103.01 SRRDA
Source B Credit 103.2 SRRDA
Maintenance funds from Other Sources transferred to PIUs Debit 104.01 SRRDA
Maintenance Funds from Other Sources received by PIUs Credit 105.01 PIU
Bank Authorization Account (Books of SRRDA) Credit 106.01 SRRDA
Bank Authorization Account (Books of PIU) Debit 106.02 PIU
Incidental funds generated from interest and net Incidental Credit 107.01 SRRDA/PIU
Receipts etc.
Statutory Deductions from Contractors/suppliers
Income Tax and Surcharge from contractors/ Suppliers Credit 108.01 PIU
Commercial/Sales/Entry tax from contractors / Suppliers Credit 108.02 PIU
Any Other statutory deductions Credit 108.03 PIU
Deposits Repayable
Earnest Money Deposits from Contractors / Suppliers Credit 109..01 PIU
Security Deposit from contractors/ Suppliers Credit 109..02 PIU
Sums due to contractors on closed accounts. Credit 109..031 PIU
Miscellaneous Deposits Credit 109..04 PIU
Purchases (Suspense) Credit
Purchase (Suspense) 110.01 PIU
Spare number for future use
Maintenance of Roads

Maintenance of newly constructed roads

Operations Manual for Rural Roads


201
National Rural Roads Development Agency

Head of Account Credit / Account Entry


Debit Head To be
Balance Number made By
First Year Maintenance Debit 120.01 SRRDA/PIU

Second Year Maintenance Debit 120.02 SRRDA/PIU

Third Year Maintenance Debit 120.03 SRRDA/PIU

Fourth Year Maintenance Debit 120.04 SRRDA/PIU

Fifth Year Maintenance Debit 120.05 SRRDA/PIU

Maintenance of up-graded roads

First Year Maintenance Debit 121.01 SRRDA/PIU

Second Year Maintenance Debit 121.02 SRRDA/PIU

Third Year Maintenance Debit 121.03 SRRDA/PIU

Fourth Year Maintenance Debit 121.04 SRRDA/PIU

Fifth Year Maintenance Debit 121.05 SRRDA/PIU

Spare Numbers

Renewal of Roads

Renewal of PMGSY roads Debit 126.01 SRRDA/PIU

Maintenance of Zonal Roads

First Year Maintenance Debit 127.01 SRRDA/PIU

Second Year Maintenance Debit 127.02 SRRDA/PIU

Third Year Maintenance Debit 127.03 SRRDA/PIU

Fourth Year Maintenance Debit 127.04 SRRDA/PIU

Fifth Year Maintenance Debit 127.05 SRRDA/PIU

Materials at Site Account (Material issued to


Departmental Works)

MAS account Debit 131.01 PIU

Stores and Stock

Stores and Stock Debit 132.01 PIU

Misc. Works Advance

Against Contractors Debit 133.01 PIU

Against Staff Debit 133.02 PIU

Cash Balance

202 Operations Manual for Rural Roads


Finance & Accounting System

Head of Account Credit / Account Entry


Debit Head To be
Balance Number made By
Cash in Chest Debit 134.01 SRRDA/PIU

Imprest with Staff Debit 134.02 SRRDA/PIU

Bank Balance

Bank Debit 135.01 SRRDA

Advances

Advance Payment to Contractors Debit 136.01 PIU

Materials issued to contractors Debit 136.02 PIU

Secured Advance against materials Debit 136.03 PIU

Mobilisation Advance Debit 136.04 PIU

Machinery Advance Debit 136.05 PIU

Advances to Suppliers Debit 136.06 PIU

Other Advances Debit 136.07 PIU

Spare No.

Income Tax

Tax deducted at Source on the investments of SRRDA Debit 139 SRRDA

Incidental Receipts

Interest received from Bank Account Credit 140.01 SRRDA

Forfeiture of Earnest Money Deposit Credit 140.02 PIU

Fines, Forfeitures, Penalties etc Credit 140.03 PIU

Any Other non refundable Deductions from Contractor / Supplier Bill Credit 140.04 PIU

Miscellaneous Receipts Credit 140.05 PIU / SRRDA

Spare numbers for future use

13.2.4 Accounting System for the SRRDA


(i) SRRDA shall maintain a two column cash book – one for cash and another for bank transactions.
(ii) The funds received from Government of India will be accounted for on the receipt side of the cash book in
bank column by showing classification Account Code No.1.01.
(iii) On receipt of requisition of funds from the PIU in the prescribed format, SRRDA’s empowered officer will
issue it a bank authorisation in the prescribed format with endorsement to the bank showing the amount,
names of payees, etc.

Operations Manual for Rural Roads


203
National Rural Roads Development Agency

(iv) One signed copy of the bank authorisation will become the voucher for the entry in the “Bank Authorisation
Transfer Entry Book”. No bank authorisation will be dispatched to a PIU before an entry is made in the
Bank Authorisation Transfer Entry Book. Bank Authorisation authority to PIU will bear the entry number in
the Register. Entry in the Bank Authorisation Transfer Entry Book will be debited to the account head 1.02
Programme Funds Transferred to the PIU; and credited to the head 1.04 Bank Authorisation. The detailed
account of each PIU will be kept in the PIU Programme Funds Transferred and PIU Bank Authorisation
Register.
(v) Each PIU will send to SRRDA monthly account, monthly balance sheet with the prescribed schedules
including a statement of the cheques drawn during the month and bank reconciliation statement. The
statements should reach the SRRDA latest by the 5th day of the next month. On receipt of this monthly
bank reconciliation statement, the SRRDA shall pass an order for its acceptance and make an entry in the
cash book, bank column, payment side, of the amount of the cheques issued during the month. It will treat
the bank reconciliation statement as a voucher. Apart from posting the entry from the cash book to the
Ledger of Credit Balances, Bank Authorisation Account, it will also make an entry in the PIU Bank
Authorisation Register, make an entry of each cheque issued on the payment side of cash book showing
the total amount of cheques drawn during the month by the PIU in bank column by debit to “Bank
Authorisation Account” in the same month. It will post the amount to the PIU Bank Authorisation Register.
Details of the cheques will always be available in the voucher, namely the bank reconciliation statement.
(vi) Net credit balance in the PIU Bank Authorisation Register should agree with the amount shown in the
balance sheet of the PIU. Any difference should be promptly investigated and set right.
(vii) Moneys received by PIUs by cheques/ demand drafts/ pay orders, etc. against the PMGSY programme
shall be deposited by the PIU in the branch of the bank at its Headquarter in the account of SRRDA.
Intimation for such deposit shall be furnished by the PIU to SRRDA in the prescribed form along with
photocopy of bank pay-in-slip. On receipt of such intimation the SRRDA shall pass an transfer entry order
crediting the account head 1.02 Programme Fund transferred to PIU and crediting the head to which the
receipt relates.
(viii) Net debit balance of programme fund of the PIU in the accounts of SRRDA shall be in agreement with the
net credit balance in the accounts of PIU. Any difference should be promptly investigated and set right.
(viii) In order to avoid any difference there shall be no issue of bank authorisation during the last five working
days of the month, to prevent difference, which arise because of delays in transit.
(ix) Gross amount of interest received from bank on the balances shall be taken as receipt in bank column in
the cash book Account Code 21.01. The tax deducted at source by bank shall be shown on payment side
in the bank column “tax deducted at source” Account Code 19.01. Refund for tax deducted at source shall
be claimed from Income Tax Department.
(Note: It would be better for the SRRDA to obtain exemption from payment of income tax.)
(x) Each SRRDA will send monthly consolidated balance sheet to NRRDA by the 15th of the succeeding
month.
(xi) Each SRRDA will send to NRRDA a statement of closing balance in the Programme Account in the prescribed
format by the 5th of the succeeding month.

13.2.5 ACCOUNTING SYSTEM FOR PIUS


13.2.5.1. The PIU entrusted with the task of PMGSY may be a Public Works Division under any Govt. Department
like the Public Works Department, Panchayati Raj Department, Rural Development Department etc. or it may
be an engineering division under DRDA or District Panchayat. It will be declared ex-officio part of the State
SRRDA and it will keep the accounts in the manner described in this sub-section.
13.2.5.2 The PIU will keep three separate sets of books of accounts as follows:
Programme Fund: It will be for the execution of works.

204 Operations Manual for Rural Roads


Finance & Accounting System

Administrative Expenses: It will be for the administrative expenses given by the Ministry of Rural Development
and by State Government.
Maintenance Expenses Account:- It will be for maintenance of roads .Funds for this shall be provided by
State Governments and the accounts shall be maintained as per guidelines issued by Ministry of Rural
Development from time to time
13.2.5.3 Accounting for Programme Funds
1. Since the PIU will work on Bank authorisation from the State SRRDA, its Cash Book would show the
authorisation received and utilised and the balance available. The PIU does not have an independent
Bank Account, therefore, its Cashbook will not have a Bank column. Instead it will have a Bank authorisation
column. Thus, its Cashbook will have two columns on the receipt side, namely, Cash column and Bank
authorisation column to show the cash received or the authorisation received. Similarly, its payment side
will have two columns, namely, cash column and Bank authorisation column to show the cash payments
and the cheques issued against Bank authorisation.
2. The PIU will send to the SRRDA a statement of the cheques drawn by it during the month so as to reach
the SRRDA latest by the 3rd of the next month.
3. Moneys received by PIUs by cheques/demand draft/pay orders, etc. against the PMGSY programme shall
be deposited by the PIU in the branch of the Bank at its Headquarters in the account of SRRDA. Intimation
for such deposit shall be furnished by the PIU to SRRDA in the prescribed form alongwith photocopy of
Bank pay-in-slip. On receipt of such intimation the SRRDA shall make an entry oh the receipt side of cash
book in ‘Bank’ column by credit to Programme Fund transferred by SRRDA. Programme Fund balance of
the PIU shall be reduced. Net debit balance of programme fund of the PIU in the accounts of SRRDA shall
be in agreement with the net credit balance in the accounts of PIU.
4. The PIU shall submit the requisition of funds for the next quarter in the prescribed format to the SRRDA
showing the work-wise details and name of contractors/payees, etc.
5. Contra entry shall be made for the self cheque drawn by PIU on both sides of the Cash Book. On payment
side of Cash Book it shall be shown in “Bank Authorisation” column as cash received from Bank.
6. The advances, if any, to the Contractors would be shown separately as advances. This will mean that that
there is no variation between physical progess and the payments made for work done and measured. The
expenditure on works will show the actual progress of works.
7. The material issued shall be debited to the Material at Site account. Such materials on consumption shall
be debited to the works concerned by contra credit to Material at Site account.
8. General Ledger is the most important record for preparing the monthly account. It is a book of final entry
containing all the accounts. Its purpose is to bring together all the related financial transactions with uniform
account structure. It is the source for monthly account and Balance Sheet.
Accounts opened in the General Ledger shall correspond to the order indicated in chart of accounts to
facilitate preparations of monthly account. Separate ledger folio shall be given for each account code and
work. Posting of the ledger shall be made from the Cash Book and transfer entry book. The Ledger shall
be balanced at the close of each month and the balance of each account code shall be worked out for the
month and to end the month.
9. Schedule of Works Expenditure in Form-53 shall be separately prepared for (a) Construction of New
Roads; (b) Up-gradation of existing roads; (c) Roadside Plantation; (d) Road sign boards. Expenditure for
all the works included in the schedule shall be totalled to work out the total works expenditure for the
monthly account and balance sheet. Expenditure on completed works shall be transferred from the Schedule
in Form-53 to Schedule in Form-54. All the schedule have been provided for in the OMMS and can be
generated online.

Operations Manual for Rural Roads


205
National Rural Roads Development Agency

13.2.6 Initial Account Records, Subsidiary Registers, Monthly Account & Balance Sheet for Programme
Funds:- The PIU and the SRRDA will use the following forms for the Initial Account Records, Subsidiary
Registers, Stores & Stock Account Records, Monthly Account and Balance Sheet. The forms pattern is broadly
that the Central Public Works Account Code, with deviations sometimes for meeting the requirements of the
Programme. Wherever changes have been made in the form of CPWA Code – “R” has been suffixed. The
formats are available in the vol. III of Accounts Manual for Programme Funds.

S. No. Name of Record PMGSY Form No. Relevant


CPWA Code
Form No.
MONTHLY ACCOUNT & BALANCE SHEET
1. Monthly Account (State) PMGSY-F-1 New
2. Monthly Account (SRRDA.) PMGSY-F-1A New
3. Monthly Account (PIU) PMGSY-F-1B Form-80 / R
4 Annual Account (State) PMGSY-F-1 (Annual) New
5 Annual Account (SRRDA) PMGSY-F-1A (Annual) New
6. Balance Sheet Monthly (State) PMGSY-F-2 New
7 Balance Sheet Annual (State) PMGSY-F-2annual New
8 Balance Sheet Monthly(SRRDA) PMGSY-F-2A New
9 Balance Sheet Annual (SRRDA) PMGSY-F-2Aannual New
10 Balance Sheet Monthly (PIU) PMGSY-F-2B New
INITIAL ACCOUNT RECORDS
11 Cash Book of SRRDA PMGSY/IA/F-3 Form-1 / R
12 Cash Book of PIU PMGSY/IA/F-3A Form-1 / R
13 Register of Cheques Received and Adjusted PMGSY/IA/F-3B Form 1A/R
14 Imprest Cash Book PMGSY/IA/F-4 Form-2
15 Money Receipt Book PMGSY/IA/F-5 Form-3 / R
16 Payment Voucher PMGSY/IA/F-6 Form-28/ R
17 Transfer Entry Book PMGSY/IA/F-7 Form-54 / R
18 General Ledger (Debit) PMGSY/IA/F-8 Form-61 / R
19 General Ledger (Credit) PMGSY/IA/F-9 Form-61 / R
20 Ledger for Funds Transferred by E.A./ GOI to PIU PMGSY/IA/F-10 New
21 Running Account Bill PMGSY/IA/F-11 Form-26 / R
22 Account of Secured Advance PMGSY/IA/F-12 Form-26A / R
23 Account of Advance against Machinery PMGSY/IA/F-13 New
24 Indenture for Secured Advance PMGSY/IA/F-14 Form-31 / R
25 Record Measurement Book PMGSY/IA/F-15 Form-23
26 Bill Measurement Book PMGSY/IA/F-16 New
27 Transfer Entry Order PMGSY/IA/F-17 Form-53
28 Contractor’s Ledger PMGSY/IA/F-18 Form-43 / R

206 Operations Manual for Rural Roads


Finance & Accounting System

S. No. Name of Record PMGSY Form No. Relevant


CPWA Code
Form No.
29 Register of Works PMGSY/IA/F-19 Form-40 / R
30 Register of Departmental Works PMGSY/IA/F-19A Form 43A/R
31 Detailed Completion Report PMGSY/IA/F-20 Form-44
SUBSIDIARY REGISTERS
32 Register of Statutory Deductions from Contractors/ Suppliers PMGSY/SR/F-21 Form-67
33 Register of Deposits Repayable PMGSY/SR/F-22 Form-67
34 Register of Miscellaneous Works Advance PMGSY/SR/F-23 Form-67
35 Register of Sale of Tender Forms PMGSY/SR/F-24 New
36 Register of Tenders Received PMGSY/SR/F-25 New
37 Register of Contract Agreements PMGSY/SR/F-26 New
38 Register of Interest Bearing Securities / Bank Guarantees PMGSY/SR/F-27 Form-85 / R
39 Account of Interest Bearing Securities PMGSY/SR/F-27A Form 86
40 Register of Measurement Books PMGSY/SR/F-31 Form-92
41 Register of Cheques/ Receipt Books PMGSY/SR/F-32 Form-52
42 Register of Miscellaneous Recoveries PMGSY/SR/F-32A Form 95
43 Register of Term Deposits PMGSY/SR/F-33 New
44 Ledger of Term Deposits PMGSY/SR/F-34 New
STORE AND STOCK ACCOUNT RECORD FOR DEPARTMENTAL EXECUTION
45 Goods Received Sheet PMGSY/SS/F-35 Form-8A
46 Summary of Stock Receipt PMGSY/SS/F-36 Form-9
47 Stores Indent PMGSY/SS/F-37 Form-7
48 Summary of Indents PMGSY/SS/F-38 Form-10
49 Register of Indents PMGSY/SS/F-38A Form 7A
50 Bin Cards PMGSY/SS/F-39 Form-8
51 Priced Store Ledger PMGSY/SS/F-40 Form-12
52 Register of Goods Received Sheet PMGSY/SS/F-41 Form-12A
53 Register of Bin Cards PMGSY/SS/F-42 Form-12B
54 Sale Account form PMGSY/SS/F-42A Form 19
55 Statement of Receipts, Issues and Balance of Road Metal PMGSY/SS/F-42B
56 Register of Materials at Site Account PMGSY/SS/F-43 Form-35
57 Register of Issues from Material At Site Account PMGSY/SS/F-44 Form-35
58 Register of Materials Issued to Contractors PMGSY/SS/F-44A Form-35A
59 Register of Advances to Suppliers PMGSY/SS/F-45 New
60 Register of Purchases-Suspense PMGSY/SS/F-46 Form-67

Operations Manual for Rural Roads


207
National Rural Roads Development Agency

S. No. Name of Record PMGSY Form No. Relevant


CPWA Code
Form No.
61 First & Final Bill PMGSY/SS/F-47 Form-24
62 Muster Roll PMGSY/SS/F-48 Form-21
63 Register of Unpaid Wages PMGSY/SS/F-49 Form-21A
64 Register of Muster Rolls PMGSY/SS/F-50 New
65 Register of Scrap PMGSY/SS/F-51 New
66 Hand Receipt PMGSY/SS/F-51A Form 28
67 Bill for Refund of Lapsed Deposit PMGSY/SS/F-51B New
SUPPORTING SCHEDULES WITH MONTHLY ACCOUNT/ BALANCE SHEET
68 Bank Reconciliation Statement PMGSY/SCH/F-52 Form-51 / R
69 Schedule of Programme Funds received PMGSY/SCH/F-52A New
70 Schedule of Incidental Funds/Misc. Income PMGSY/SCH/F-52B New
71 Schedule of Deposits Repayable PMGSY/SCH/F-52C
72 Schedule of Current Liabilities PMGSY/SCH/F-52D
73 Schedule of New Roads Constructed PMGSY/SCH/F-53E
74 Schedule of Up-gradation of Roads PMGSY/SCH/F-53E
75 Schedule of Other Expenditure on Roads PMGSY/SCH/F-53F
76 Schedule of Current Assets PMGSY/SCH/F-53G
77 Funds Reconciliation Statement (Funds in Transit) PMGSY/SCH/F-55 New
78 List of Schedules to be Annexed with Balance Sheet of PIU PMGSY/SCH/F-56 Form-83 / R
79 Schedule for Statutory Deductions from Contractors /Suppliers PMGSY/SCH/F-57 New
80 Schedule for Deposits Repayable PMGSY/SCH/F-58 New
81 Schedule for Incidental Receipts PMGSY/SCH/F-59 New
82 Schedule for Cash Balance PMGSY/SCH/F-60 New
83 Schedule for Materials At Site PMGSY/SCH/F-61 New
84 Schedule for Miscellaneous Works Advance PMGSY/SCH/F-62 New
85 Schedule for Advances to Contractors / Suppliers PMGSY/SCH/F-63 New
GENERAL
86 Requisition for Funds PMGSY/GEN/F-64 New
87 Bank Authorisation PMGSY/GEN/F-65 New
88 Monthly Statement of Cheques issued by PIU against PMGSY/GEN/F-66 New
Bank Authorisation
89 Advice for Amounts Deposited by PIU in Bank PMGSY/GEN/F-67 New
Account 97of SRRDA

208 Operations Manual for Rural Roads


Finance & Accounting System

13.2.7 The Monthly Account will be compiled from Cash Book, the Ledger and Schedule for Works Expenditure
in the following format:
Pradhan Mantri Gram Sadak Yojana
Monthly Account (for PIU)
Name of PIU
Month 200 PMGSY/F-1B
Debit balances
Account Head of Account Ledger To end For To end
Code folio of the of
Number Previous Month Month
Month (4+5)
1 2 3 4 5 6
1.05 Bank Authorisation Account
6.01 Cheques/Demand Drafts etc. received by PIU
6.02 Cheques/Demand Drafts etc. transferred by PIU to SRRDA
11.01 Expenditure on construction of New Roads
A – In Progress Sch/F-53
B – Completed Sch/F-54
11.02 Expenditure on Up-gradation of Existing Roads
A – In Progress Sch/F-53
B – Completed Sch/F-54
11.03 Expenditure on Plantation
A – In Progress Sch/F-53
B – Completed Sch/F-54
11.04 Expenditure of Road Sign Boards
A – In Progress Sch/F–53
B – Completed Sch/F–54
12.01 Expenditure on Materials At Site for Construction
of New Roads
12.02 Expenditure on Materials At Site for Up-gradation
of Existing Roads
13.01 Store and Stock
14.01 Miscellaneous Works Advance against Contractors
14.02 Miscellaneous Works advance against Staff
15.01 Cash in Chest CBF*
15.02 Imprest With Staff
17.01 Advance payment to Contractors
17.02 Materials issued to Contractors
17.03 Secured Advance against Materials
17.04 Mobilisation Advance
17.05 Machinery Advance
17.06 Advance to Suppliers
17.07 Other Advances
19.01 Tax deducted at source
TOTAL
*Cash Book Folio
Notes:
1. Cash in chest “to end of the month” shall be the closing balance as shown in the Cashbook. Cash Balance for the month shall
be worked by deducting the balance “to end of the previous month” from the balance “to end of the month” i.e. column 6
minus column 4.
2. Schedule for Works expenditure (Work in progress)/(completed works) shall be enclosed with the monthly/annual account.
3. Vouchers shall be retained by PIU for Audit
4. Completed works shall be transferred from Sch/F–53 to Sch/F–54

Operations Manual for Rural Roads


209
National Rural Roads Development Agency

Pradhan Mantri Gram Sadak Yojana


Monthly/Annual Account (for PIU)

Name of PIU
Month 200 PMGSY/F-1B
Debit balances
Account Head of Account Ledger To end For To end
Code folio of the of
Number Previous Month Month
Month (4+5)
1 2 3 4 5 6
1.03 Programme Funds Account
1.06 Incidental funds generated from interest and net incidental
receipts (under the old system)
21.02 Forfeiture of Earnest Money Deposit
21.03 Fines, Forfeitures, Penalties etc.
21.04 Any Other Non-refundable deduction from Contractors/
Suppliers
21.05 Miscellaneous receipts
2.01 Income tax from Contractors/Suppliers
2.02 Commercial/Sales/Entry Tax from Contractors/Suppliers
2.03 Any other Statutory deduction
3.01 Earnest Money Deposits
3.02 Security Deposit from Contractor/Suppliers
3.03 Sums due to Contractors on closed Accounts
3.04 Miscellaneous Deposits
4.01 Purchases (Suspense)
21.02 Forfeiture of Earnest Money Deposit
21.03 Fines, Forfeitures, Penalties etc.
21.04 Any Other Non-refundable deduction from Contractors/
Suppliers
21.05 Miscellaneous receipts
TOTAL

Notes: Total amount of incidental receipts shall be credited to Incidental Funds generated from interest etc. in the annual account.

210 Operations Manual for Rural Roads


Finance & Accounting System

13.2.8 The monthly balance sheet from 1st April 2002 shall be prepared from the monthly account in the
following format:
Pradhan Mantri Gram Sadak Yojana
Monthly/Annual Account (for PIU)

Name of Unit (PIU)


Month PMGSY/F–2B

Liabilities Amount Assets Amount


1. Programme Fund Control 1. Cash Balance
(i) Cash in Chest
(ii) Imprest with Staff
2. Incidental Funds generated 2. Bank Authorisation
from interest and net account
incidental receipts
3. Payables 3. Cheques/Demand Drafts
(a) Statutory Deductions Received by PIUs
form Contractors/ Suppliers
(b) Deposits repayable
4. Purchases-Suspense 4. Cheques/Demand Drafts
Transferred to NA
5. Deposits with State Govt.
6. Construction of New Roads
A. In Progress (Sch/F-53)
B. Completed (Sch/F-54)
7. Upgradation of existing roads
A. In Progress (Sch/F-53)
B. Completed (Sch/F-54)
8. Roadside Plantation
A. In Progress (Sch/F-53)
B. Completed (Sch/F-54)
9. Roadside Sign Boards
A. In Progress (Sch/F-53)
B. Completed (Sch/F-54)
10. Materials At Site (Sch/F-61)
11. Stores and Stock
12. Miscellaneous Works advance
(Suspense)
13. Advances to Contractors/]
Suppliers

Enclosures: Schedule of Works Expenditure (Sch/F–53 & 54)

Operations Manual for Rural Roads


211
National Rural Roads Development Agency

13.2.9 Accounting for Administrative Expenses Funds:- Accounting for Administrative Expenses Funds is
on the same principles as for the Programme Funds, with minor changes. Its Cash Book will also have a Bank
authorisation column.. Chart of accounts Administrative Expenses Funds is given in 13.2.3. The Empowered
Officer will intimate the Bank whether or not the PIUs will be the Authorised Payees for the amounts/cheques
released by the Autonomous Agency. There is no objection if the other administrative funds of the Autonomous
Agency including miscellaneous receipts and State Government grants are also held in the same account
provided they are subject to the same procedure including computerisation. Other programme and maintenance
funds of the State Govt. handled by the Agency shall not, however, be kept in this account.
13.2.10 Accounts procedure for Expenses:- All the payments for various expenses like travel, stationery
etc., after being recorded in the cash book, shall be posted to the relevant heads of accounts in the Ledger of
Debit Balances. At the end of the year, the amount will be transferred to the Income and Expenditure Account,
to close the balance to a nil amount. This will be done through a transfer entry. The net effect of the transactions
in the Income and Expenditure Account will be transferred to the Central (or State) Administrative Expenses
Fund, which will then appear in the Balance Sheet.
13.2.11 Accounts Procedure for Assets:- The expenditure or purchase of assets will be booked to assets
account and not carried to the Income and Expenditure Account. Assets will be shown in the Balance Sheet.
13.2.12 Ledger of Debit Balances:- All the transactions appearing on the credit side of the Cash Book, or in
the Debit column of the Transfer Entry Book will be posted in the debit column of the relevant head of account
in the General Ledger. All the transactions appearing on the debit side of the Cash Book, or in the credit
column of the Transfer Entry book will be posted in the credit column of the relevant head of account of the
General ledger.
13.2.13 Initial Accounting Records, Subsidiary Registers, Monthly Account & Balance Sheet for
Administrative Expenses Funds:- The PIU and the SRRDA will use the forms for the Initial Account Records
in the form of ledger accounts, and such registers for administrative expenses as are laid down by the State
Government. The PIU will also prepare a Monthly Account and Balance Sheet in the form given overleaf:

212 Operations Manual for Rural Roads


Finance & Accounting System

Pradhan Mantri Gram Sadak Yojana


Monthly Account of Receipts and Payments (for PIU)
Administrative Expenses Fund
Name of Unit (PIU)
Month 200
Debit balances
Account Head of Account Ledger To end For To end
Code folio of the of
Number Previous Month Month
Month (4+5)
1 2 3 4 5 6
51.08 Bank Authorization Accountant
54.01 Travelling expenses
54.02 Telephone Expenses
54.03 Maintenance of Computers
54.04 Internet Expenses
54.05 Data Entry Costs
54.06 Other Office Expenses
54.07 Quality Monitoring Expenses
54.08 Bank Charges
54.09 Any other expenses with approval of MoRD
54.10-54.19 Expenses approved by the State Government
to be incurred from Funds it provided.
54.20-54.24 Assets expenses allowed by the MoRD
( i.e., computers).
54.25-54.30 Assets expenses allowed by the State
Government.
56.02 Miscellaneous Advances
52.01 Cash in chest CBF
52.02 Imprest with Staff
TOTAL

Accountant Officer-in-Charge/PIU

Operations Manual for Rural Roads


213
National Rural Roads Development Agency

Pradhan Mantri Gram Sadak Yojana


Monthly Account of Receipts and Payments (for PIU)
Administrative Expenses Fund

Name of Unit (PIU)


Month 200

Debit balances
Account Head of Account Ledger To end For To end
Code folio of the of
Number Previous Month Month
Month (4+5)
1 2 3 4 5 6

51.03 Central Administrative Expenses Fund received from


SRRDA.

51.08 State Administrative Expenses Fund received by PIU


from SRRDA

51.09 Incidental funds generated from Interest and net


incidental receipts.

55.02 Miscellaneous Receipts

56.03 Unpaid bills

56.04 Deposits Repayable

TOTAL

Accountant Officer-in-Charge/PIU

Note:- Amount of incidental receipts shall be credited to Incidental funds generated from Interest etc. in the annual account.

214 Operations Manual for Rural Roads


Finance & Accounting System

Pradhan Mantri Gram Sadak Yojana


Monthly/Annual Balance Sheet
Administrative Expenses Fund
As on
Name of Unit (PIU)
AS ON

CAPITAL FUND AND LIABILITIES Schedule Amount


Central Administrative Expenses Fund 1
State Administrative Expenses Fund 1
Incidental Funds (from interest and other receipts) 2
Misc. Income 2

CURRENT LIABILITIES

Deposits Repayable 3

Unpaid Bills 4

TOTAL

ASSETS

Miscellaneous Advances 5

Cash in Chest

Bank Authorisation

Imprest with Staff

The same procedure as for Programme Funds will be adopted for preparing the balance sheet as on the 31st
December, 2002 and its incorporation in the accounts.

13.3 REPORTING AND MONITORING


13.3.1 For PMGSY works, it is mandatory to maintain the progress of expenditure on each of the major activity
(called sub-head) of the works.
13.3.2 The C-DAC Pune has already made a provision for this in its software. It requires a public works division
to fill, in the prescribed format, the activity-wise details when entries of payment of the Contractor’s claims are
made in the online cash book. The following format of abstract of activities is recommended. This format should
be part of the Contractor’s claim. Its details are:
(a) Earthwork
(b) WBM and hard shouldering work
(c) B.T. work
(d) Road furnishing work

Operations Manual for Rural Roads


215
National Rural Roads Development Agency

(e) CC Road and Protection wall


(f) Cross Drainage work.
13.3.3 The Balance Sheet of the public works division will show the following information:

Liabilities Amount Assets Amount

1. Programme Fund Control 1. Construction of new roads


Account PIUs (a) In progress (Sch/F-53)
(b) Completed (Sch/F-54)
2. Incidental funds generated from 2. Upgradation of existing roads
interest and net incidental receipts (a) In progress (Sch/F-53)
(b) Completed (Sch/F-54)
3. Payables 3. Roadside Plantation
(a) Statutory Deductions from (a) In Progress (Sch/F-53)
contractors/ Suppliers (b) Completed (Sch/F-54)
(b) Deposits repayable

4. Purchase-Suspense 4. Roadside Sign Boards


(a) In Progress (Sch/F-53)
(b) Completed (Sch/F-54)
5. Advances to Contractors
6. Material Issued to Works
7. Stores and Stock
8. Material Issued to Contractors
9. Deposits with State Govt.
and others (for past balances)
Cash and Bank Balances
10. Cash in hand
11. Cash with Bank
12. Bank Authorisation
13. Impreset with Staff

The Balance Sheet has separate schedules showing the expenditure on each work. The Schedule will also
show, whenever required, activity wise expenditure. Thus, the total expenditure on each work can be known at
the end of each month.
13.3.4 Externally funded projects:- For externally funded projects, the funding agency meets part of the
expenditure. It requires a funds flow statement both for the projects it funds, and other projects. Therefore, the
expenditure on the road construction will need to be divided into two parts: roads funded by the Funding
Agency and other works. The balance sheet will reflect the expenditure on the roads funded by the funding
Agency as separate line expenditure.

216 Operations Manual for Rural Roads


Finance & Accounting System

13.4 AUDIT
13.4.1 Statutory Audit:- The Comptroller and Auditor General of India (CAG) is the auditor for Government
accounts. He also audits the accounts of bodies receiving grant or loan if the amount from Government of India
and State is more than Rs. 25 lakhs and not less than 75 percent of its total expenditure [Section 14 (1) of the
Comptroller and Auditor General (Duties, Powers and condition of Services] Act, 1971. Therefore, all the funds
received by the State level Rural Roads Development Agency will fall in his audit jurisdiction.
The SRRDA will also appoint its own auditors from the panel of Chartered Accountants the CAG maintains for
the audit of Government companies. The auditors may be appointed for not more than 3 years at a time, with
the approval of the Executive of the SRRDA. It may be ensured that the Audited Accounts are approved by the
General Body of the SRRDA by 30th September, and printed along with the Annual Report.
The PIUs will function as ex-officio officers of the SRRDA. Therefore, their accounts will form part of its accounts,
and thus subject to audit by the CAG and the Chartered Accountants.
13.4.2 Internal Audit:- Internal audit can be entrusted to independent auditors. The SRRDA will appoint the
independent internal auditors. The general methodology of the selection will be similar to that of selection of
Statutory Auditors. The selection should be from a panel of auditors obtained from the office of the C&AG of
India and approved by the State Government (Nodal Department).

13.5 ORGANISATIONAL SET-UP


At the central level, the NRRDA shall be responsible for the compilation of activity-wise progress reports of the
PMGSY and the use of the funds.
At the State level, the SRRDA shall maintain the PMGSY accounts, prepare Balance Sheet, maintain ledger
account of each PIU and reconcile each month the Bank account and PMGSY programme account. In order to
install the new accounting system it is essential that each SRRDA have in place a Financial Controller and a
Senior level Accountant having experience in works accounts. Each PIU should also have one Divisional
Accounts Officer / Divisional Accountant.

13.6 PROCEDURE FOR RELEASE OF PROGRAMME FUNDS TO THE SRRDA


13.6.1 Since the PMGSY has adopted a Project approach where road works have to be completed within a
stipulated time-limit, the cost of the projects for a State for each Phase of the PMGSY will be made available to
the SRRDA in two instalments.
13.6.2 The first instalment amounting to 50% of the cleared value of projects, (for annual allocation whichever
is lower) shall be released subject to fulfilment of conditions, if any, stipulated earlier.
13.6.3 Since the cost of only the contracted works have to be paid, the second instalment would be calculated
on this basis, and would be equal to the balance due on the cost of the awarded works. Release would be
subject to utilisation of 60% of the available funds and completion of at least 80% of the road works awarded in
the year previous to the preceding year and 100% of the awarded works of all the years preceding that year,
and fulfilment of other conditions, if any, stipulated while releasing the previous instalment. Works cleared and
not awarded by the time of the 2nd instalment would be deemed as lapsed. Available funds will be the funds
available with the SRRDA on 1st April of the Financial year (including interest accrued) plus the amount of the
instalment released, if any, during the Financial Year.
13.6.4 The release of the second instalment in a year shall be subject to submission of the following documents:-
a. Utilisation Certificate for the funds released earlier, year-wise in the form prescribed.
b. Certificate by the Bank Manager indicating the balance amount on date of issue of the Certificate and the
interest credited.
c. A Certificate regarding the requisite physical completion of works.
d. For all releases after October of a year, production of an audited Statement of Accounts and a Balance

Operations Manual for Rural Roads


217
National Rural Roads Development Agency

Sheet and related Statements, duly certified by the Chartered Accountant for the accounts of the previous
financial year.
e. Outputs of the relevant modules of the OMMS, duly certified by the SRRDA as being correct.
13.6.5 For the purpose of releasing funds, the State would be the Unit.
13.6.6 The estimation of expenditure and of completed road works will be based on data entered in the OMMS.

13.7. PROCEDURE FOR RELEASE OF ADMINISTRATIVE EXPENSES FUNDS


13.7.1 At the District level, the Programme will be co-ordinated, and implemented through a dedicated Programme
Implementation Unit (PIU). All PIUs will be manned by competent technical personnel from amongst the available
staff or through deputationists. In exceptional cases and with the prior approval of NRRD, Consultants may be
engaged to build up or enhance capacity. NRRDA’s Model documents shall be used for the purpose.
13.7.2 All staff costs will be borne by the State Government. The Pradhan Mantri Gram Sadak Yojana does not
provide for any staff costs. However, the administrative and travel expenses of PIUs and SRRDA costs will be
met to the following extent, with the State Government bearing any additional costs:

Item % of funds released


(a) Admin. Expenses for PIUs 1.00%
(b) Travel Expenses of PIUs 0.50%
(c) Admin. & Travel Expenses (SRRDA) 0.25% (Rs. 25 lakh maximum)
nd
(d) Independent Quality Monitoring 2 tier 0.50%
For this purpose:
(i) Administrative expenses shall, in addition to usual office expenses, include all expenses incurred in relation
to the operation of the OMMS computers and their maintenance, including internet charges and data entry
costs. Amounts paid on account of outsourcing of execution and management related functions may also
be paid out of administrative expenses within the limits prescribed. However, expenditure on purchase of
vehicles, payment of salaries & wages and purchase or construction of buildings is not permissible.
(ii) The amounts shall be released to the SRRDA along with programme fund releases. The SRRDA shall
further allocate the amounts (by way of limits set by the Empowered Officer) in respect of sl.no.a) & b) to
PIUs generally in proportion to the funds released to them, also keeping in view the actual pace of work
and requirement in the PIUs.
(iii) In case works lapse or are dropped at a later stage, necessary adjustment will be made while releasing
the next tranche of expenses.
(iv) Funds for the purpose will be kept in a separate account (‘Administrative Account’) operated in a manner
similar to the programme account (see Para 18 of the NRRDA Guidelines Nov. 2004). State Government
funds for administrative expenses and incomes of the Agency used for administrative purposes may also
be kept in the same account, but no other funds shall be credited to the account nor shall the account be
used other than for defraying admissible administrative, travel and quality monitoring expenses.
(v) The releases of administrative and travel expenses shall be dependent on:
 Continued updating of OMMS modules.
 Appropriate dedication of the PIU and its clear linkage to the SRRDA;
 Adequate institutional mechanism at the SRRDA level including nodal IT officer, State Quality
Coordinator, Financial Controller and Empowered Officer.
13.7.3 No Agency charges will be admissible for road works taken up under this Programme. In case Executing

218 Operations Manual for Rural Roads


Finance & Accounting System

Agencies levy charges in any form, such as Centage charges etc., it would have to be borne by the State
Government.

13.8 UTILISATION CERTIFICATE


13.8.1 From 2003-04 onwards, each State will be treated as one Accounting Unit since the funds were released
to single account of the State. As such from 2003-04 onwards the requirements are:-
a. One Utilisation Certificate for the Programme Account and one single Utilisation Certificate for Administrative
Account upto 31st March of each year.
b. An interest accrual Certificate for each of the 2 accounts and.
c. A certificate of closing balance in the accounts as on 31st March each year for each of the two accounts.
d. Audit Report of the year.
The format to be used for submission of the utilisation certificate of the programme and administrative expenses
funds will be as specified from time to time.

Operations Manual for Rural Roads


219
National Rural Roads Development Agency

CHAPTER 14
MAINTENANCE

14.1 INTRODUCTION
Road maintenance is a routine work performed to upkeep pavement, shoulders and other facilities provided for
road users, as nearly as possible in its constructed condition, and at least at an adequate level of serviceability.
Even with the highest possible quality of construction, maintenance is essential to get optimum service from the
pavement structure during its life period. All pavements require maintenance as they are subjected to traffic and
environmental effects. Maintenance helps in preserving the pavement surface, and thus postpones the need
for costly investments in rehabilitation. Unsealed roads deteriorate at a faster rate compared to sealed roads
and hence need greater attention; at the same time maintenance operations on unsealed roads are more
easily done, particularly at community level. Maintenance requirements are dependent on traffic, terrain, soil
type, climate etc. and it is possible therefore to devise management systems which optimise maintenance
costs and maintenance efforts.
14.2 PMGSY PROVISION
As per Para 17 of PMGSY Guidelines, State Governments are required to undertake the maintenance of the
entire Core Network, particularly the road works constructed/upgraded under the PMGSY. State Governments
are required to develop sustainable sources of funding for undertaking the maintenance functions. In respect of
roads constructed / upgraded under the PMGSY, as per the Standard Bidding Document, 5-year routine
maintenance is contracted out along with the construction itself to the same contractor who is constructing the
road. In respect of Through Route subjected to PMGSY investments a further 5-year maintenance on Zonal
contract basis will need to be done as per para 17.3 of the PMGSY guidelines

14.3 SPECIFIC PROVISIONS IN RRM FOR ROUTINE MAINTENANCE


Maintenance operations during the period of 5 years shall be based on Chapter 11 of Rural Roads Manual
(IRC: SP: 20:2002). Its specific provisions are:-
(i) Clause 11.2, which, explains the various types of distress/defects of pavements. For example, cracks,
ravelling, rutting, pot holes etc.
(ii) Clause 11.3, which, defines different maintenance activities. For example, fog seal, bituminous surface
treatment, etc.
(iii) Clause 11.4, which suggests planning of routine maintenance.
(iv) Clause 11.5 and Clause 11.6 (a), which, define preventive and corrective maintenance, and classify activities
of routine maintenance and repairs.
(v) Clause 11.7, which, discusses in detail the assessment of defects and maintenance measures for sealed
roads, roads with rigid / RCCP and Roads with special pavement.
(vi) Appendix 11.1of Rural Roads Manual lays down the periodicity of routine maintenance (attached as
annexure-14.1)
(vii) Appendix 11.3, of Rural Roads Manual, covers the special problems of Road Maintenance in Heavy
Rainfall / Snow fall areas (attached as annexure-14.2)
(viii) Appendix 11.4, of Rural Roads Manual, explains the nature of activities in maintenance of shoulders,
drainage structures and causeways (attached as annexure-14.3)

220 Operations Manual for Rural Roads


Maintenance

14.4 SPECIFIC PROVISIONS IN STANDARD BIDDING DOCUMENT (SBD)


Clause 32: Correction of defects noticed during the Defect Liability Period and Routine Maintenance of
Roads for five years
Clause 32.2.1: The Contractor shall do the routine maintenance of roads, including pavement, road side and
cross drains to the required standards and keep the entire road surface and structure in defect free condition
during the entire maintenance period which begins at completion and ends after five years.
Clause 32.2.2: The routine maintenance standards shall meet the following requirements:-
(i) Potholes on the road surface to be repaired soon after these appear or brought to his notice either during
Contractor’s monthly inspection or by the Engineer.
(ii) Road shoulders to be maintained in proper condition to make them free from excessive edge drop offs,
roughness, scouring or potholes.
(iii) Cleaning of surface drains including reshaping to maintain free flow of water
(iv) Cleaning of culverts and pits for free flow of water.
(v) Any other maintenance operation required to keep the road traffic worthy at all time during the maintenance
period.
Clause 32.2.3: To fulfil the objectives laid down in clauses 32.2.1 & 32.2.2 above, the Contractor shall undertake
detailed inspection along with JE of the roads at least once in a month. The Engineer can reduce this frequency
in case of emergency. The Contractor shall forward to the Engineer the record of inspection and rectification
each month. The Contractor shall pay particular attention on those road sections which are likely to be damaged
or inundated during rainy season.
Clause 32.2.4: The Engineer may issue notice to the Contractor to carry out maintenance of defects, if any,
noticed in his inspection, or brought to his notice. The Contractor shall remove the defects within the period
specified in the notice and submit to the Engineer a compliance report.
Clause 46.1: In case contractors quote low for maintenance activities, performance security for such activity
should be obtained as security towards unbalanced bid.
14.5 ROUTINE MAINTENANCE AND REMEDYING DEFECTS DURING THE CONTRACT PERIOD OF
FIVE YEARS
14.5.1 As per the provisions in the Standard Bidding Document the PMGSY roads shall be maintained by the
contractors for five years from the date of completion of the work. During this period the Contractor shall carry
out all routine maintenance works required to keep the road in good condition. The various work items for
Routine Maintenance are listed below:
(i) Clearing/re-shaping of road side drains.
(ii) Pothole filling (WBM & BT).
(iii) Filling up edges of asphalt surface.
(iv) Dressing of berms, earth work on berms, rain cuts and dressing of earthen embankments, Turfing whenever
necessary.
(v) Refixing displaced guard stones, White washing guard stones, parapets of CD works.
(vi) Fixing disturbed caution board / Village Name board / Speed limit board, etc.
(vii) White washing and Geroo painting of trunks of trees.
(viii) Cutting of branches of trees etc obstructing flow of traffic and line of sight, and cleaning wild growth on
berms.
(ix) Topping of W.B.M. blindage including picking of loose metal.
(x) Maintenance of catch water drains.

Operations Manual for Rural Roads


221
National Rural Roads Development Agency

(xi) Clearance and desilting of cross drains.


(xii) Making up the loss of profile (for gravel roads).
(xiii) Rectifying Corrugated Surface (for gravel and WBM Roads).
(xiv) Filling up local depressions, ruts, potholes and erosion control (for gravel and WBM Roads).
(xv) Regravelling (for gravel roads).
(xvi) Repairing damaged edges (for WBM).
(xvii) Rectifying revelled surface (for WBM).
(xviii) Periodic surface renewal (for WBM).
(xix) Painting of Km & Hecto stones, Logo & Sign Boards
As per PMGSY guidelines, the cost estimation of routine maintenance is required to be done at the time of
preparation of DPRs, as such the estimates of every work shall be prepared in two parts. The first part of the
estimate will cover construction of road, CDs and related works and the second part shall cover the estimates
of routine maintenance for five years calculated separately for each year after the completion of work. Based
on estimation of work to be carried out every year, a lump-sum amount will be worked out for every work every
year and this lump-sum amount will be put into the BOQ at the time of tendering. The contractor will be required
to quote rates in Lump sum only, for every year.
The estimates for routine maintenance shall be based on actual estimated requirements calculated on the
basis of actual experience of routine maintenance of similar types of roads existing in similar conditions in the
State. Norms for working out quantities of various items of maintenance activities shall not be lower than the
norm prescribed in Annexure 14.4. The specifications of items of routine maintenance shall be as per
“Specification of Rural Roads”-IRC, Aug-2004 and analysis of rates shall be based on the Standard Data Book.
14.5.2 Annexure 14.1 lists out these works and their periodicity. Annexure 14.5 gives the Guidelines for inspection
of Rural Roads as part of maintenance activity.
14.5.3 Recognising that the present need for upgrading the Through Routes primarily arises out due to inadequate
investments in planned and systematic routine maintenance and periodic renewal, maintenance of the assets
created under the PMGSY, particularly the Through Routes should be given the priority it requires.
As such, for Through Routes the construction /upgradation part of which was funded out of PMGSY, as addition
to the 5-year contracted routine maintenance at the end of this period, a Zonal Contract will be entered into,
covering all the Through Routes in the District which have received PMGSY investments in that batch. The
batch Zonal Contract would comprise an initial surface renewal on the Through Routes followed by 5- year of
routine maintenance. The funding of the maintenance part will continue to be the responsibility of the State
Governments.

14.6 ROLE OF DPIU DURING THE MAINTENANCE CONTRACT PERIOD


The DPIU is the authority for managing the maintenance contract for five years after completion of the construction
of the road. For facilitating the maintenance operations, each road should be divided into Km stretches, and
each Km should be sub-divided into 200 metres sections. The Junior Engineer shall inspect each Km of the
road at least once in a month. The Assistant Engineer shall inspect the road at least once in three months, and
the Executive Engineer shall inspect the road at least once in six months. One of the inspections of the Executive
Engineer shall be before the monsoons and one after the monsoons.
During the above inspections, the Contractor’s engineer shall be present. All defects such as potholes, berms
needing dressing, clearing of road side drains and weeds, cross-drainage works and repairs for Road furniture
should be identified, recorded and intimated to the Contractor. The supervisory staff shall ensure that the
repairs are carried out as per specifications with due regard to quality control. Painting, whitewashing, colour
washing of road furniture items at the specified periodicity must be got done through the Contractor. All

222 Operations Manual for Rural Roads


Maintenance

maintenance work shall be noted in a checklist in the routine inspection card attached with Annexure 14.6. A
maintenance log book for each road under the Contract package shall be maintained. The date(s) of inspection,
defect and deficiencies noticed during each inspection (recorded in the proforma of Annexure 14.6) and whether
defects have been rectified or not shall also be recorded in the log book. The rectification of defects can be
marked in different colour on to the routine Inspection Card (Annexure 14.6) for easy reference.
The DPIU shall verify every time the Contractor submits his bill whether the defects noted during the inspections
have been rectified. If the Contractor has failed to carry out an item of work ordered, the DPIU shall withhold the
payment of the bill in that month.

14.7 MAINTENANCE AFTER COMPLETION OF PMGSY CONTRACT


14.7.1 PMGSY roads are designed for a 10 year life. If quality of construction, proper maintenance and periodic
renewal is ensured, subject to traffic considerations, PMGSY roads can give continued service provided
maintenance is continued.
Para 17.1 of the PMGSY guidelines require the State Government to build up the capacity in the District
Panchayats to maintain Rural Roads and to devolve funds and functionaries on to the Panchayats in order to
be able to manage maintenance contracts for Rural Roads. To this end, PIUs may function as the technical
agency to operationally manage the contracts, with the District Panchayat approving the contracting out of
maintenance on a Zonal basis by prioritising the road works within the maintenance budget allocation. To
enable this to be done, the PIU may:
(i) Prepare and submit to the SRRDA and the District Panchayat a detailed annual estimate of funds for
proper maintenance of the Rural Core Network;
(ii) Apply a prioritisation criteria developed at SRRDA level Fig. 14.1 for allocation of the budgeted maintenance
funds. The criteria would be based on the Pavement Condition Index (PCI) giving weightage to conditions
like traffic and population. It is expected that Rural Through Routes would secure higher priority for
maintenance funding.

14.8 MAINTENANCE PLANNING


The SRRDA shall implement a simplified Rural Road Maintenance system, which consists of a road condition
survey (based on simple visual inspection), which yields a Pavement Condition Index (PCI). The flow chart for
such a system is shown in Fig. 14.1.

Fig. 14. 1. Flow Chart for Rural Road Maintenance Management System

Operations Manual for Rural Roads


223
National Rural Roads Development Agency

14.9 PAVEMENT CONDITION SURVEY


Annexure 14.7 gives the Methodology for determining the Pavement Condition Index (PCI).
The PCI data is an integral part of the OMMS and the data will be included in the “Road Master” for each
kilometre. The PCI data collected as per Annexure 14.7 will be entered in the OMMS data base by the PIU and
a District wise output generated, copy of which will be furnished to the State Road Development Agency.
Another copy will be supplied to the STAs for record. The proforma is given in Annexure 14.8
The OMMS software will incorporate provisions which enable selection of roads for upgradation from the short-
list on the basis of the PCI.
The States shall get the PCI survey of the Core Network conducted once in 2 years immediately after the rainy
season. Costs not exceeding Rs. 50 per km (except road lengths constructed under PMGSY for which PCI of
5 will be used) will be allowed for getting the PCI survey done and Rs. 10 per road for completing the Road
Master in the OMMS (including surface nature, surface condition, population and facilities linked etc.). The PCI
survey will be repeated every 2 years and prioritisation of roads for upgradation and or maintenance shall be
redrawn accordingly.

14.10 MAINTENANCE PRIORITISATIONS


Given the scarcity of maintenance funds, the basic principle governing the application of routine maintenance
funds is that these should be applied to those roads whose maintenance is in the greater public interest (Core
Network Through Routes which generally have much more traffic) and which are manageable at relatively low
cost i.e., which are presently in good condition. Accordingly, Routine Maintenance Priority List (RMPL) will be
prepared at District level based on the following.
(a) The roads will include all Through Routes (or main Rural links) already included in the Core Network, at a
higher priority.
(b) The roads in each District will be ranked according to the Pavement Condition Index (PCI). Subject to the
overall availability of funds, roads of progressively lower PCI will be uniformly taken up in all Districts for
inclusion in the list. For this purpose abstract of District-wise length of roads of each PCI will be prepared
and fund allotment done generally in ratio of the road lengths of the PCI classes to which maintenance
funding is to be applied. For this purpose, each District may compile and make available to the budgeting
centre the information as follows:-
PCI class Total length of TR/MRL Amount required for routine maintenance

Total
(c) In case it is necessary a further sub-prioritisation will be done as follows on the basis of Average Annual
Daily Traffic (AADT) which will need to be applied only in case if all roads of a particular class cannot be
taken up for maintenance given the scarcity of resources.
PCI class Name of road Length AADT Amount required for routine maintenance

Sub total for PCI


(d) Subject to earmarking of maintenance funds on project basis e.g., World Bank aided projects, PMGSY
maintenance contracts, etc., the divisible pool of maintenance fund will be distributed among the Districts
in ratio of the total length of roads of the priority classes being taken up for maintenance. For example, if
the maintenance funds allow roads upto PCI 3 and above to be taken up (though the funds may not be
adequate to take care of all roads of that PCI value and further categorisation on basis of ADT may need

224 Operations Manual for Rural Roads


Maintenance

to be done) the total length of roads in each District upto value of PCI 3 would be worked out from the Core
Network and maintenance funds would be divided in that ratio.
(e) The District RMPL will be got verified on the ground on sample basis through the STAs and the NQM
system before it is processed for further approvals.
(f) After the District RMPL is prepared and verified, it shall be placed before the District Panchayat for approval;
thereafter it shall be vetted by the State level Standing Committee (SLSC).

14.11 STATE MAINTENANCE FUND


The approved and vetted RMPL would be basis for undertaking routine maintenance. In order to operationalise
the system, routine maintenance funds will need to be placed in a separate ‘Maintenance Fund’ with the State
Autonomous Agency and the PIUs responsible for rural road construction activities would operate the Fund in
a manner identical to the PMGSY programme fund.

14.12 MAINTENANCE OPERATIONS


Routine maintenance operation will be carried out on the basis of maintainance prioritisation and taking into
account the availability of funds with the State. However, it must be ensured that the execution of various
maintenance activities is carried out as per “Specifications for Rural Roads”. States with a comprehensive
Rural Road Maintenance System already in place may continue with the present practice in consultation with
NRRDA.

Operations Manual for Rural Roads


225
National Rural Roads Development Agency

Annexure-14.1
(See Para 14.5.2)
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
Periodicity of Routine Maintenance Activities

S. No. Name of Item/ Activity Frequency of operation in one year


1 Restoration of rain cuts and dressing of berms as per clause Once generally after rains (In case of
1902 of the Specifications. areas having rainfall more than 1500
mm per year, as and when required).
2 Making up of shoulders as per clause 1903 of the As and when required.
Specifications
3 Maintenance of Bituminous surface road and/ or gravel road As and when required.
and/or WBM road including filling pot holes and patch repairs
etc as per clause 1904, 1905 and 1906 of the Specifications.
4 Maintenance of drains as per clause 1907 of the Twice (In case of hill roads as and when
Specifications required).
5 Maintenance of culverts and cause ways as per clause 1908 Twice (In case of hill roads as and when
and 1909 of the Specifications required).
6 Maintenance of road signs as per clause 1910 of the Maintenance as and when required.
Specifications Repainting once in every two years.
7 Maintenance of guard rails and parapet rails as per clause Maintenance as and when required.
1911 of the Specifications Repainting once in a year.
8 Maintenance of 200 m and Kilo Meter stones as per clause Maintenance as and when required.
1912 of the Specifications Repainting once in a year.
9 White washing guard stones Twice
10 Re-fixing displaced guard stones Once
11 Cutting of branches of trees, shrubs and trimming of grass Once generally after rains (In case of
and weeds etc as per clause 1914 of the Specifications areas having rainfall more than 1500
mm per year, as and when required).
12 White washing parapets of C.D. Works Once

226 Operations Manual for Rural Roads


Maintenance (Annexures)

Annexure: 14.2
(See Para 14.3)

Ref: Appendix- 11.3 of the Rural Roads Manual


PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
Special Problems of Road Maintenance in Heavy Rainfall/Snowfall Areas

i) Major problems for maintenance of roads in heavy rainfall areas in hilly terrain include landslides, drainage
failure, soil erosion and damage to pavements. The maintenance regime required for up keep of the roads
will be similar to the type of activities for normal roads, but with higher intensity of effort and monitoring.
ii) Proper drainage of rainwater and snowmelt and protection of land surface should be the focus of activities
for prevention of landslides. Erosion of soil from both above and below the road formation must be controlled.
Prevention of deforestation of hillside, maintenance of slope stability, through turfing, plantation, terrace
benching, catch water drains, avoidance of excessive blasting and protective measures like toe wall,
retaining walls, breast walls, etc. are some of the recommended measures for prevention of soil erosion
and landslides.
iii) Landslides that occur on rural roads will have to be removed manually using minor hand tools as major
earth moving equipment like dozer; shovel, etc. are not likely to be available for rural road maintenance.
Proper care should, however, be taken to ensure that the workers are not exposed to the threat of fresh
slides. A watchman should be posted to constantly monitor the behaviour of the hill above and to warn the
workers of the possibility of a fresh slip coming down.
(iv) Snowfalls in the high altitude areas can also cause landslides, avalanches destruction to protective
structures, pavement damages, etc. besides the blockage to traffic and reduction in worker efficiency. The
main effort in clearance of snows should be to open a minimum track to enable to traffic to move.
(v) The side drains and the CD structures should also be cleared to enable drainage snowmelt. The avalanche
prone areas should be identified and camping of commuters and stoppage of the traffic near such areas
should be prevented.

Operations Manual for Rural Roads


227
National Rural Roads Development Agency

Annexure: 14.3
(See Para 14.3)
Ref: Appendix- 11.4 of the Rural Roads Manual

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)


Maintenance of Shoulders, Drainage Structures and Causeways

1. MAINTENANCE OF SHOULDERS
1.1. Properly built-up and well maintained shoulders provide lateral support to the pavement. The slow moving
vehicles, like, bullock carts or hand driven carts tend to ply over the shoulders. The shoulders are also used for
parking of vehicles.
1.2. The shoulders shall be kept free from obstructions, like, logs, shrubs, deep cuts, boulders, etc. The wild
growth on them shall also be removed from time to time. In hill roads located in high rainfall zones, the overgrowths
on the hillsides and the valley side must be cleared twice a year, at least once before the onset of winter. The
extent of clearance area should be enough to provide six hours of sunshine to the road surface during fair
weather. It must, however, be seen that the roots of the grass are not removed, so that rains hitting on the
exposed surface do cause erosion and induce landsides. The debris of leaves, branches and stems of the cut
trees shall be cleared form the drain, pavement and the shoulder of the road, removed beyond the road edge
on the valley side by at least 2 m. The shoulders should be kept flush with the pavement edge and then
given slightly steeper slopes than the pavement to facilitate effective draining of rainwater flowing across the
pavement. The shoulders shall be maintained by filling moorum or sand and scrapping the heaved-up portion
wherever necessary.
Since the shoulders also form part of the body of the road, they shall be kept free from encroachments.

2. MAINTENANCE OF ROAD FURNITURE


2.1. Traffic signs are the principal means of conveying information about the road to the road users. Signs
which are erected at proper places and which are in good condition free from any obstruction can be properly
understood and they inspire confidence in the minds of the road users. Damaged, missing or obliterated signs
shall be replaced promptly. The signs shall be inspected and cleaned at least twice a year. At the junctions of
two or more roads proper information boards or information pillars giving information about various destinations
would be of immense help. They shall preferably be located at least 200 m ahead of the junctions to guide the
road users.
2.2. Guard rails, guard walls, parapets of bridges, guard stone delineators, etc. shall also be maintained
properly. If they are damaged due to moving vehicles, the same shall be repaired or replaced promptly.
2.3. Kilometre/200-metre/boundary stones shall be painted twice in a year. The wild growth along the kilmetre/
200-metre boundary stones, which obstructs the visibility, shall be removed. Delineators and header stones on
the curves shall be properly painted and kept in good condition to guide the driver properly at these locations.

3. MAINTENANCE OF CROSS DRAINAGE STRUCTURES


3.1. Structures are provided for effective drainage of runoff water etc. It is, therefore, essential that the cross
drainage structures shall be maintained effectively and it shall be ensured those drainage elements, waterways
remain free of obstructions and retain their intended cross-sections and grades. They must function properly so
that surface water and ground water can drain freely and quickly away from the road or under the road. Water
is the worst enemy of every road element. It can erode soil, weaken the pavement and subgrade, and destroy
shoulder and slope, even wash out cross drainage structures or bridges.
3.2. The parapet, railing, guard stone etc, of the CD work should be repaired if broken. These should be
properly painted for improving visibility during night.

228 Operations Manual for Rural Roads


Maintenance (Annexures)

3.3. In the following paragraphs maintenance of mainly culverts and causeways is discussed as these are
usually used as cross drainage structures on rural roads.
3.4. Inspection: Inspection of drainage system and structures shall be a routine task. If it is not possible then
the inspections should be carried out at least on four occasions. Firstly before onset of monsoon, Secondly,
during monsoon particularly after first flash floods, Thirdly after heavy floods, and Fourthly after monsoon.
3.4.1. Inspection before monsoon: Following points shall be inspected:
(i) Waterway is clear and not blocked by debris or silt
(ii) Settlement cracks in foundations or in superstructure
(iii) Cracks or damages in pavement
(iv) Guide stones are properly fixed and pointed
(v) Warning signs are placed on both sides of cross drainage structures giving clear warning that when water
is flowing above the guide stones, vehicle shall not cross the cross drainage structure
(vi) Approaches are in sound condition and there is no erosion
(vii) Debris arrestors if provided are properly fixed.
3.4.2. Inspection after first flash flood: It is generally observed that during first flash flood or during next two,
three spells, there is substantial load of floating debris along with flood water. If the vents are not of sufficient
opening, then waterway is blocked by the debris and water starts flowing on approaches or by breaching the
adjoining road sections. It is, therefore, essential to remove this blocked debris from pipe vents or waterway
immediately so that there will be minimum damages in subsequent floods. In view of this, close and repeated
inspections are essential during rainy season.
3.4.3. Inspection after heavy floods: During heavy floods, causeways are generally over topped. This results in
heavy damages to pavement, approaches as well as scouring on down streamside of structures. In some
cases there is breaching of approaches. All these points shall be closely inspected after every heavy flood, so
that timely protective measures can be taken.
3.4.4. Inspection after monsoon : Once the monsoon season is over, the structures shall be inspected closely
for any damage, any heavy silting or scouring to pavement, damages to guide stones etc. Repairs to these
damages shall be carried out promptly.

4. MAINTENANCE OF CULVERTS
4.1. Defect: Silting, Sanding and Blockage by debris
If a culvert structure is constructed too low, resulting in deposition of silt or sand, vegetation or floating debris
gets blocked in vents of culvert. Blockages of waterway lead to ponding and heading up of floodwater, which
results in over flooding the embankment. This damages the embankment or causes breaching in roadway.
Slopes of bed shall be corrected by Nalla training properly: Debris arrestors shall be provided on upstream side
so that floating debris will not enter the vents and there will be no blockage of vents. It is also comparatively
easy to clear the debris from arrestors.
4.2. Defect: Erosion of Streambed on Downstream Side
Due to flowing water or overtopping of water from culvert, the downstream side bed sometimes gets eroded.
Due to heavy scouring, the foundations of headwalls are also exposed and endangered. Due to steep slope of
bed or vents or due to inadequate waterway, the velocity of flowing water increase on downstream side and
results in erosion below headwall, wing walls or even approaches. This may result in collapse of headwall or
wing walls in due course of time. Protection work to the bed with properly designed apron at downstream side
shall be provided. Also adequate waterway shall be provided.

Operations Manual for Rural Roads


229
National Rural Roads Development Agency

4.3. Defect: Settlement Cracks in Masonry Structure


Settlement of foundations takes place due to weak founding strata. If the settlement is negligible then the
damages can be checked and repaired. But, if the settlement is major in nature, then reconstruction of structure
will be only the remedial measure.

5. MAINTENANCE OF CAUSEWAYS
5.1. Defect: Cracks in Paved Surface
Settlement of fill below pavement, dislocation of stones in stone set pavements, scouring of filler material due
to eddy currents. Damaged area shall be opened, refilled and compacted properly and then pavement shall be
re-Iaid. In case of stone pavements, dislocated stones shall be refixed properly. If there is scouring below fill,
then it shall be sealed properly so that there will be no damage due to eddy current.
5.2. Defect: Blockage of Vents Due to Debris
Floating debris block the vents. Debris arrestors shall be provided on upstream side.
5.3. Defect: Damages Due to Overtopping of Water
Structure is not properly designed or provision of inadequate waterway or inadequate protection measures.
The geometry of the structure shall be properly designed. Water way shall be provided in such a way that it
shall effectively pass at least 20 per cent of high flood discharge. The Road Top Level shall be properly protected
with pitching on upstream and downstream side as well as at top of formation extending upto high flood level.
If possible RCC Wearing Coats must be provided.
5.4. Defect: Damages to guide stones, information boards
Due to flood water or due to vandalism such damages are experienced. Guide stones, information boards, and
kerb stones shall be a replaced promptly. If neglected, when the pavement gets submerged during floods, the
edge of pavement can not be seen, more over if guide stones are missing, the depth of water on road top level
can not be judged. This may result in serious accidents.
6. MAINTENANCE OF DRAINAGE FEATURES
For proper upkeep of drainage features, maintenance should take care of the following:
Camber: A proper camber needs to be maintained for surface water. Whereas it is found improper or inadequate,
corrective measures need to be taken. In case of unsealed roads, blading, grading and shaping may be required.
For sealed roads, a profile corrective courses may be provided on the existing surface.
Shoulder and Side Slope : The shoulder on both sides should have required outward slope starting from the
edge of pavement. Also, side slope is to be maintained at the end of shoulders, especially on high embankments.
Longitudinal Drainage : A lined or unlined longitudinal drain provided in a rural road,as the case may be, shall
be cleared of any accumulated debris. The blockage of the drains by silting also may be cleared regularly.

230 Operations Manual for Rural Roads


Maintenance (Annexures)

Annexure- 14.4
(See Para 14.5.1)

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)


Norms for Routine Maintenance activities during the Contract period of 5 years.
(Refer para 14.5.1)

A) Quantity for the relevant item(s) for filling up of pot holes shall be dependent upon the average
annual rainfall & volume of Commercial Vehicles.

 Factor on the basis of annual average rainfall.


High : More than 1500mm mean rainfall per year and hilly roads.
Medium : Between 500mm to 1500mm mean rainfall per year.
Low : Less than 500mm mean rainfall per year.

Rainfall
High Medium Low
I Year 1% 0.5% -
II Year 2% 1.0% 0.5%
III Year 3% 1.5% 1.0%
IV Year 4% 2.0% 1.5%
V Year 5% 2.5% 2.0%

For I and II Year percentage of the BT surface area only to be taken.


For III, IV and V Year percentage of the BT surface area and WBM top layer to be taken.
 In addition to this Multiplying Factor of Traffic Intensity (TI) shall also be considered in obtaining the quantity.
Low - Multiplying Factor of 1 with TI up to 15 commercial vehicles per day.
Medium – Multiplying Factor of 1.25 with TI between 15 to 45 commercial vehicles per day.
High – Multiplying Factor of 1.5 with TI more than 45 commercial vehicles per day.
B) Making up of Berms/ Shoulders, stripping excess soil from the shoulder surfaces to achieve the
required level etc.:
Rainfall
High Medium Low
I Year 15% 10% 7.5%
II Year 18% 12% 9.0%
III Year 21% 14% 10.5%
IV Year 24% 16% 12.0%
V Year 27% 18% 13.5%
Percentage area of the Berms to be taken and multiplied by the Multiplying Factor considering the Traffic
Intensity (TI) as given in the item of pot holes.

Operations Manual for Rural Roads


231
National Rural Roads Development Agency

C) Restoration of berms, restoration of rain cuts with soil, moorum, gravel etc.
Rainfall
High Medium Low
I Year 7.5% 6.0% 5.0%
II Year 9.0% 7.2% 6.0%
III Year 10.5% 8.4% 7.0%
IV Year 12.0% 9.6% 8.0%
V Year 13.5% 10.8% 9.0%
Percentage area of the berm to be taken with an average depth of 0.30 metre.
The quantity is to be multiplied by the Multiplying Factor considering the Traffic Intensity (TI) as given in the item
of filling up of potholes.
D) For items such as White washing guard stones, Refixing displaces guard stones, Clearance of CD works
and White washing parapets of CD works. Approximate quantity may be accessed as per the DPR.
E) For item such as White washing and Geroo painting of trunks of trees, Cutting of branches of trees,
Clearing of wild seasonal growth on berm etc. The quantity may be accessed as per actual requirement
at site.
F) For remaining item quantities shall be considered based on the basis of actual experience of routine
maintenance of similar type of roads existing in similar locations.

232 Operations Manual for Rural Roads


Maintenance (Annexures)

Annexure-14.5
(See Para 14.5.2)

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)


GUIDELINES ON INSPECTION OF RURAL ROADS FOR MAINTENANCE
1. Frequency
The minimum frequency of inspections for condition of road is suggested in Table 1.
Table 1 : Frequency of inspections

Sl. No. E.E. A.E. J.E.

Routine Special Routine Special Routine Special

1. Twice in a Before Once in Before and Once a month Every week


year (April and after two months after
& October) monsoons Jan. monsoons
March Twice during
May rains
July
Sept.
Nov.

The inspection should be carried out not only to check the conditions of works but also for planning future
strategies. Senior officers should make it a point to note and communicate the instructions to the subordinates.
While on inspection, the senior officer should go through the notes of Junior colleagues and make suitable
suggestions so that inspections are meaningful.

2. DUTIES
The duties of Junior Engineer (JEs), Assistant Engineers and Executive Engineers are as follows :
2.1. Duties of JEs
(i) Inspection and supervision of works as per prescribed norms
(ii) Reporting observations to higher authorities
(iii) Preparing estimates for repairs after conducting condition surveys of road
(iv) Reporting about closure of road/ obstructions due to any of the following reasons :
(a) Over topping/ breach
(b) Landslides
(c) Earthquake
(d) Accident
(e) Any other reason (specify)
(v) Arranging for removal of obstructions, dead animals and other debris lying on the road
(vi) Enumerating safety measures and restoration works in case of flood damages and breaches and
reports on opening of traffic/ completion of restoration.

Operations Manual for Rural Roads


233
National Rural Roads Development Agency

2.2. Duties of Assistant Engineers


(i) Inspection and supervision of works
(ii) Reporting observations with suggestion for remedial action to higher authorities
(iii) Getting estimates prepared and checked after conducting surveys and site investigations
(iv) Reporting about heavy rainfalls in the area and consequent rain damage
(v) Enumerating action on the report of engineering subordinates regarding obstructions, accidents etc.
(vi) Enumerating Safety measures and restoration of (both temporary and permanent) works in case of
flood damages and breaches.
2.3. Duties of Executive Engineers
(i) Inspection and recording of observations
(ii) Planning and finalizations of nature of maintenance activity e.g. surface renewal, repair to CD works
etc.
(iii) Arranging men, materials and machinery in advance as per requirements
(iv) Finalising action on reports of Assistant Engineers and also on safety measures, diversion in case of
breaches and flood damages
(v) Coordination with various agencies like traffic police, local administration, publicity media etc., in
case of emergent repairs, interruption to traffic by road blockage, etc.
(vi) Initiate steps for finalizing permanent restoration work.
3. Identification of Defects
It is important to identify and locate the defects of surface, shoulders, side drains and cross drainage during the
inspection of the road by various officers.

234 Operations Manual for Rural Roads


Annexure-14.6
(See Para 14.6)
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
ROUTINE INSPECTION CARD (RECORDING FORMAT)
Name of District Contract Package No. Road Code No.
RECORDED BY Date:
AE/ JE
KM - 100 KM - 101 KM - 102 KM - 103 KM - 104
Sl.No. PARTICULARS ACTION TO BE TAKEN
.2 .4 .6 .8 .2 .4 .6 .8 .2 .4 .6 .8 .2 .4 .6 .8 .2 .4 .6 .8
1. SIDE DRAIN
R
RESECTION L
R
FILL SCOUR HOLE / 0.5 KM
L
CLEAR SITE

2. SHOULDER & SLOPE 0.5 KM 0.4 KM


R
CORRECT CAMBER
L
R
FILL POT HOLES 0.5 KM
L
R 0.5 KM
FILL EROSION CUTS
L
R
FILL RAIN CUTS
L

3. CARRIAGE WAY
(i) FILL PATCHES 200SQ.M

Operations Manual for Rural Roads


(ii) FILL POT HOLES
(iii) GRIT FOR BLEEDING 100SO.M

(iv) RENEWAL NEEDED


BRIDGE
DECK
4. C.D. WORKS

5. ENCROACHMENTS 2 SHOPS
DETAILS R
L
6. ROAD FURNITURE 2 NOS
(i) MISSING BOARDS
(ii) Km, STONES
(iii) REPAIRABLE BOARDS
(iv) PAVEMENT MARKING

REQUIRING URGENT ACTION REQUIRING RECURRENT ATTENTION

REQUIRING SPECIAL ATTENTION REQUIRING ROUTINE ATTENTION

235
Maintenance (Annexures)
National Rural Roads Development Agency

Annexure-14.7
(See Para 14.9)

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)


Methodology for determining the Pavement Condition Index (PCI)

1. Background
The measurement of the condition rating of Rural Roads can be done by several methods. Automated equipment
like Bump Integrator are perhaps more accurate but given the huge length of the network and the fact that the
condition rating is used as a qualitative and relativistic parameter as rather than as a quantitative parameter in
the context of the investment resource scarcity, simple and low cost methods may be used to initiate a Pavement
Management System. Once the system stabilises and the utility of the condition rating becomes more important,
it may be appropriate to switch over to more intensive and accurate measurement methods. Accordingly 3
simple, low cost methods are suggested for the present, which can be done by the PIU staff without much
equipment.
2. Methods suggested
(i) Measurement based on Visual Inspection only
An experienced engineer can rate the PCI by visual inspection of the pavement for each kilometre, a Pavement
Condition Index (PCI) of 1 to 5 is adopted, as under:
Description of Surface Condition PCI
Very Good 5
Good 4
Fair 3
Poor 2
Very Poor 1
(ii) Based on Riding Comfort
A jeep or car is driven at 50 km/hr. and the riding comfort noted for each kilometre. Based on ‘Riding Comfort’
while driving at the design speed of 50 km/hr, the PCI is assessed as under:

Riding Comfort @ 50 km/hr. PCI


Smooth and Pleasant Ride 5
Comfortable 4
Slightly Uncomfortable 3
Rough and Bumpy 2
-Dangerous 1
(iii) Based on comfortable Driving Speed possible
The driver is instructed to drive at the most comfortable and safe speed possible on the road. The PCI then
assessed for each kilometre based on the Normal Driving Speed, as under

236 Operations Manual for Rural Roads


Maintenance (Annexures)

Normal Driving Speed PCI


Over 40 km/hr 5
30 to 40 km/hr 4
20 to 30 km/hr 3
10 to 20 km/hr 2
Less than 10 km/hr 1

3. Determination of PCI for a Road


In order to get the PCI of the road, the arithmetic mean of the condition assessed for each km is taken if the
kilometre-wise PCI is varying within a small range. However, if the variation of PCI is large from section to
section of the road under consideration, the road is to be divided into homogeneous sections and the arithmetic
mean of PCI is taken for each section.

Operations Manual for Rural Roads


237
238
Annexure 14.8
(See Para 14.9)
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
National Rural Roads Development Agency

Proforma of Output of PCI Data for Each Road on OMMS

Name of TR/LR/ Code# Length Name of the Population Year of Year of last Amount Type of Km# AADT** PCI Date of
Road MRL* in CN habitations served Construction periodic spent on pavement PCI
connected renewal routine
(PR) maintenance
since PR

Operations Manual for Rural Roads


* MRL-Main Rural Link (In case TR is not a rural road)
** If already done(can be done separately)
Road Safety

CHAPTER 15
ROAD SAFETY

15.1 BACKGROUND
The traffic on most existing earthen tracks and substandard existing links consists mainly of bicycles, some
two-wheelers, some animal-drawn vehicles and a few agricultural tractors. The construction of new links to
hitherto unconnected habitations and upgradation of existing links will generate a considerable amount of
motorised traffic on Rural Roads.
The sudden influx of high speed motorised vehicles to the rural roads can severely endanger the safety of road
users, particularly of vulnerable road users like children (going to the schools), women carrying headloads of
agricultural produce, cyclists etc. The problem gets aggravated because all the road users utilise the same
narrow road width of a single lane, where crossing and overtaking becomes very difficult. Moreover, drivers of
agricultural tractors, jeeps, light commercial vehicles, two-wheelers and buses in the rural areas are not always
given to adequate observance of driving rules and traffic signs. It is thus expected that as the rural roads get
constructed and upgraded, road safety will be an issue requiring serious consideration. When accidents do
take place, trauma care and other facilities available in hospitals of towns and cities are not within the easy
reach of the accident victims. Under these circumstances, preventive measures, both engineering and social,
must be taken up to the extent feasible.

15.2 ENGINEERING MEASURES IN THE DESIGN PHASE


Incorporating appropriate safety design standards and features in the rural roads can enhance road safety to a
great extent. In view of the lower levels of education in the rural areas, the engineering of roads to constrain
users to follow safe driving and behavioural standards may be necessary to Supplement Cautionary Sign-
board. Some of the engineering measures that should be in-built into the design of rural roads are enumerated
below. These issues should also be considered at the time of the transect walk (See chapter 5) so that the local
community alerts the engineers at design stage itself to local traffic and pedestrian movement patterns that
may have road safety implications.
 Rural roads have to necessarily have a tortuous path, keeping in view the narrow land width available. All
the same, the horizontal curves should be designed scientifically, conforming to the selected design speed
and terrain. The horizontal curves must be provided with smooth transition curves and super-elevation.
The pavements should be widened at curves.
 The vertical profile of the road should be designed such that the required minimum stopping sight distance
is available. Suitable summit and valley curves should be provided.
 In hill roads, blind curves are a safety hazard. Suitable vision berms may be cut at such locations.
 Passing places must be provided at convenient locations particularly on hill roads.
 The provision of rural connectivity leads to the introduction of bus services. Properly designed bus-bays
must be provided at bus stop to ensure that the buses do not hamper the normal traffic.
 Where the roads pass through habitations and school, it is necessary that the motorized vehicles travel at
low speeds. This can be ensured by providing adequately designed road humps or rumble strips.
 The junction of rural roads with a main road is always a point of conflict and an accident-prone zone. Such
junctions must be designed scientifically by providing minimum turning radii, flaring of the side road with
taper, acceleration/deceleration lanes and adequate sight distances.
 Ramps must be provided where field paths and cattle crossings intersect the road.

Operations Manual for Rural Roads


239
National Rural Roads Development Agency

 Traffic signages, incorporating warning and regulatory signs, can enhance road safety, especially near
habitations and school zones, sharp curves, narrow bridges, junctions, submersible bridges and causeways.
The design must incorporate these.
 Hazard markers like reflectorised delineaters must be provided at dangerous locations.
 Submersible bridges and causeways should be provided with water depth gauges and guide-posts that
shall remain at all times above the highest water level.
 300mm dia ducts should be provided in the embankment to enable cultivators to thread agricultural wise
pipes for irrigating their fields lying on both sides of the road.

15.3 SAFETY DURING CONSTRUCTION OR MAINTENANCE OPERATIONS


Construction zones create an environment where the road user is confronted with sudden obstacles and
unfamiliar conditions. Safety in construction zones must be enhanced by:
(i) Warning the road users (in the appropriate language) clearly and sufficiently in advance
(ii) Providing safe and clearly marked lanes for guiding road users
(iii) Providing safe and clearly marked buffer zones and work zones
 Barricades, drums, traffic cones, cylinders and signs around work zones
 Flagmen with red flags positioned to regulate and warn the road users.
 Using construction machinery carefully and parking such machinery at locations where they are not
traffic hazards.
 Stacking construction materials such that only the quantity needed for one operation is stacked along
the road, and obstruction to road users is minimised.
 Providing well designed temporary diversions as necessary so that the essential traffic moves with
the least hindrance. The Contractor shall be asked to provide these as part of his work. The bidding
document and specifications shall elaborate these requirements.

15.4 ROAD SAFETY DURING USE


The Head of PIU will be the District Rural Roads Safety Officer (DRRSO). To ensure operational safety the
DRRSO shall ensure that
 Routine maintenance of rural roads are regularly carried out.
 All safety issues out of maintenance inspection are properly addressed.
 In all cases of accidents and inquiry/investigation thereof, safety issues are resolved, and a report is
made to the SQC for examination whether standard design features need to be incorporated in other rural
roads.
 All resolutions of Panchayats regarding safety issues are acknowledged and action proposed/taken intimated
to the Panchayat.
 Road safety awareness camps are organised involving Panchayats, School, Rural road users (inhabitants
as well as drivers), in accordance with programmes drawn up by the State Quality Coordinator.
The State Quality Coordinator will be the State Rural Road Safety Officer and shall ensure:
 Adequate coordination with the State Road Safety Council and road safety programmes.
 Formulation of rural road safety awareness programme proposals (for funding under PMGSY).
 Implementation and coordination of rural road safety awareness programmes in the field.
 Hold quarterly meeting with DRRSO and take feedback for improving safety standards.

240 Operations Manual for Rural Roads


Road Safety

15.5 INSTITUTIONAL ARRANGEMENT


In order to enhance road safety, coordination shall be maintained with the Road Safety Mission of the MORT&H.
At the State level, SQCs and DPIUs shall ensure coordination with the State Government’s Road Safety
Programme, in particular through membership of the State Road Safety Council and District Road Safety
Committees, created as per provisions of Section 215 of the Motor Vehicles Act, 1988 (Act No. 59 of 1988). For
this purpose, the SQC may be nominated to the State Road Safety Council. For each district, the Executing
Agency shall designate the Head of the DPIU or a senior engineer as the District Rural Road Safety Officer
(DRRSO). The State Government shall nominate the DRRSO to the District Road Safety Committee. The State
Government shall also nominate the Panchayati Raj Institutions designated to take over maintenance to the
District Road Safety Committee. As part of the Rural Road development and maintenance programmes, the
State Government shall ensure road safety audit of construction and maintenance works along with quality
monitoring.

Operations Manual for Rural Roads


241
National Rural Roads Development Agency

CHAPTER 16
IMPLEMENTATION RESPONSIBILITY

The PMGSY programme encompasses a wide range of activities and its success depends on the clear allocation
of responsibilities at various levels. Table 16.1 lists out some of the key activities and identifies the officers/
organisations responsible for the implementation. The process for each activity has already been detailed out
in each of the respective Chapters.
TABLE-16.1
Activity Officer/ Organisation
Responsible
Data collection, inventorying and condition survey Head of PIU*
Preparation of Master Plan/ Core Network Head of PIU*
Incorporation of suggestions of MPs and MLAs Head of PIU*
Scrutiny of Master Plan/ Core Network 1. District Planning Committee
2. District Panchayat
Approval of Master Plan/ Core Network
 at State Level State Level Standing Committee
 at Central Level NRRDA
Preparation of CNCPL /CUPL Head of PIU*
Preparation of Annual Road List State Nodal Agency
Allocation of funds among States MORD
Distribution of State’s allocation among districts Nodal department in the
State/SRRDA
Preparation of Project Proposals for each year Head of PIU
Approval of Annual proposals Distt. Panchayat

Clearance of Project Proposals


 at State Level SRRDA and State Level
Standing Committee
 at Central Level Empowered Committee, MoRD
Survey, Investigations, Design Head of PIU*
Approval of drainage structures 15-25m S.E.
Preparation of DPR Head of PIU*
Technical Scrutiny of DPR State Technical Agency
 Data Entry on OMMS PIU
Compilation and forwarding of DPRs SRRDA

242 Operations Manual for Rural Roads


Implementation Responsibility

15% Sample Scrutiny and submittal of NRRDA


proposals for clearance of EC

Technical Sanction C.E / Designated Technical


Officer of Executing Agency

Prepare NIT Documents Head of PIU

Sample check of NIT NRRDA

Advertise and Receive Bids Head of PIU /SE/CE/SRRDA

Evaluate Bids and Decide on Award As per State practice

Employer for Contract As per State practice

Engineer for Contract Head of PIU

Contract Management Head of PIU*

Certification of Bills and Payments Head of PIU*

Preparation of Progress Reports and Monitoring Head of PIU*, Nodal Agency

Quality Control

1st Tier Head of PIU*

2nd Tier SQC of SRRDA

3rd Tier NRRDA

Analysis of NQM/SQM Reports NRRDA/ PTA

Overseeing the Quality Monitoring System State Quality Coordinator

On-line Management System IT Nodal Officer of SRRDA /


IT Division of NRRDA
On-line Accounting System Financial Controller SRRDA/
Accounts Officer PIUs

* Head of PIU to allocate responsibilities to his subordinate Technical Officers depending on jurisdiction, with
a fixed time frame for completion of activity.

Operations Manual for Rural Roads


243
244
National Rural Roads Development Agency

Operations Manual for Rural Roads


Notes / Corrections / Slips

Designed by Akhil Chandra Associates, New Delhi & Printed at International Print-O-Pack Ltd., New Delhi, India