June 4, 2020
Table of Contents
1. INITIATING A PROJECT 1
2. PLANNING A PROJECT 7
4. REFERENCES 36
1. Initiating a Project
Business case
The name of the project is ‘Self-Registration Kiosk’ and it is about the development
of an online system that will assist patients in booking appointments for check-ups
or follow up appointments at the Cresta Healthworx Centre. The main aim of the
project is to address the issue of the frustratingly long queues that patients have to
succumb to when they go to the centre, seeking for medical attention with a
medical professional. Additional to this, it is sometimes difficult for some of patients
to even fulfil or recall any check-up appointments made with the Health Centre,
due to the reality of busy schedules that people sometimes have. In looking at this
problem, the proposed solution for this issue, is to develop an online system for
booking appointments for consultations with their specified Doctor. This system
can be accessible on their computers or mobile phones which makes it more
convenient for any patient to make an appointment on the fly. With this system in
place, patients that have made an online appointment are also then provided with
reminder notifications the day before they are due to see the Dr and on arrival at
the centre, are given a receipt once they provide their patient ID and head straight
to the Dr’s rooms without having to wait in long queues. The proposed system will
be developed using current and modern technology namely, C# and Microsoft SQL
Server Studio Database.
Goal and objectives statement
The key goal of the project is to complete the system development within budget
($50,000) and timeline (5-months) specified. The project is mainly taken into the
consideration to enhance the service provided at the Cresta Healthworx Centre
and improving its operations and transactions by using the online self-registration
system. The technology behind the development of the system are the
programming languages Asp.net/C# as well as Microsoft SQL Server Studio
Database MySQL for the database or backend. Both these languages were
considered and with research, have found that they both can reduce processing
time. As a result, they will also improve the facilitation of the services in the Health-
Centre creating a benefit to the Health-Centre staff as well as the clients of the
Health-Centre.
Stakeholder engagement
INFLUENCE ON
VH
Health- Hospital
Centre IT Financial
Manager Manager
H
Project
Manager
M
AGAINST PROJECT
FOR PROJECT
VH H M L L M H VH
M
Tester,
System
Designer
Database H
Hospital
Staff VH
INFLUENCED BY
1.3.3 Stakeholder
management
Project title
Stakeholder Assessment of impact
Stakeholder interest(s) in the (attitude to and influence Potential actions
project on or influenced by)
and every stage of the Ally (High for the Finance Manager and
Project
project and ensure all project and high Health-Centre staff to gain
Manager
stakeholders are on influence on) as much information as
common understanding is
Health-Centre IT Manager
Heath-Centre Has a big influence on Ally (High for the
to discuss what can will be
Finance the funding for the project and very high
in scope and what will be
Manager project to take place influence on)
out of scope for the project
the project.
Has a huge say in the Must meet with the Project
Health- Ally (Very high for the
existence of a new Manager to gain a system
Centre IT project and very high
system to take over walk-through and what the
Manager influence on)
the current system new system should do
Must assist and
to it
Must sit with the Heath-
system
Database Will look at the Supporter (Low for the Will develop the back-end
Admin current system and project and High and the database for the
adequate
addition of a new
system or to
system
Communication plan
The interface is the main part or component of the Self-Registration Kiosk which
enables the users to interact with the system. Without interface no one can interact
with the system. The interface is basically known as front-end of the system in
which control of the system are provide to the users i.e. patients, doctors and
hospital staff.
This component allows the Cresta Healthworx Centre to store the data and
information about the patient for the long-term and retrieve or update that info
when required. However, this component would be mainly integrated with the
interface of the system.
Component allow the users to get the access and to use the system. Each user
has its own unique account which can help to prevent the unauthorized access to
the system. Also, system allow the users to make the payment for their follow-up
or check-up at the hospital and they can make payment using the system on their
mobile and laptop. Moreover, they can add their credit or debit card in the system
and payment made will be secure with end-to-end encryption
This component or module allow the users to maintain their profile and view their
medical records and history as well as enable them to book the appointment and
follow-up or check-up at the hospital.
.
Component analysis
WBS Inclusions Activities Exclusions Assumption Risks Actions after risk analysis
Number (Deliverables) s
1.3.1 Requirements Users Input Project Users and Poor users’ Prepare the stakeholder list
Document, Charter health-care inputs and users and arrange the meeting
Business staff input are not interest to and interview with them and
Case would be give their input. everything will be noted
taken and down that discussed in the
their meeting.
requirements
are collected
and analysed.
1.3.5 Software Layout Design Project Layout of the Poor design and Design approach and model
Requirement Charter, system is not be accepted. is taken into the
Specification Business designed consideration during design
Case following the phase.
modern
approach and
model of
design.
1.3.5 Software Front-End Project Design meet Stakeholders are Design approach and
Requirement Design Charter, the needs not happy with principles are adopted to
Specification Business and the design meet the stakeholder need
Case expectations and expectations.
of
stakeholders
1.3.5 Project Plan Prototype Project Prototype is Project prototype Stakeholders should be
Charter prepared is not approved constantly involved and
within the prototype will be reviewed.
deadline.
1.3.5 Project Plan Finalize Cost plan Stakeholders Not getting the Resources and cost rough
Prototype agreed with funding and estimate is prepared and
the prototype. resources benefits are defined to the
required for the top management.
project.
WBS Inclusions Activities Exclusions Assumption Risks Actions after risk analysis
Number (Deliverables) s
1.3.2. Project Purchase Online Business Server Crashing of Testing is performed and
Management Server case purchase and server server is configure properly
Plan successfully before the use.
configured.
1.3.5 Project Develop login Feasibility Module Module cannot Quality Assurance is
Management module study developed be integrated performed during each
Plan successful with other phase of the project so that
modules. all issues and defects will
be overcome.
1.3.7. Project Creation of Feasibility Users System would be Two-factor authentication is
Management users account study accounted access used to prevent and avoid
Plan created. unauthorizedly. any kind of unauthorized
access
1.3.5. Project Integration of the Feasibility Integration Cannot meet the Schedule and cost
Management project modules study performed budget and management is prepared in
Plan successfully timeline which consistently tracking
constraints. and monitoring is performed
and if cost and schedule
variance is negative then
corrective actions are made
or both schedule and cost is
revised.
1.3.9. Project Testing Feasibility Testing is Testing results Maximum internal testing is
Management study completed as failed. performed during the
Plan per plan develop to prevent any type
of failure.
1.3.8. Project Training Feasibility All users are High training cost Online training is provide
Management study trained and user-manuals are
Plan successfully. prepared.
10
8
Impact
2.3.4 Risk actions
the system. So, that all of the errors are reduced and Monitor & Control
latest trends.
R3 Cost is reviewed and burn-down chart is prepared to track Planning and
or budget is revised
R4 Schedule is reviewed throughout the completion of the All components
project and when there is delay then burn-out mode is ON would be taken into
in which team is asked to work for extra hours to meet the the consideration
schedule.
R5 Back-up of every team member is generated if anyone All components
leave then that person is replaced is with other one. would be taken into
the consideration
Statement of work document (SOW)
2.4.1 Background
The project mainly aimed meet the needs of the Cresta Healthworx Centre and to
automate the process for the patient to book an appointment to the hospital using
their mobile phone and laptop whenever they want to and with their suitable timing.
The current or existing process at the hospital is very in-adequate and everything
is manual and the patient has to wait for long-time for their number to come-up for
their check-up. So, with the implementation of the system name “Self-Registration
Kiosk” this process can be automated and patients can book their appointment in
hospital for their follow-up and the can manage the medical history and records in
the single application or system as well as they can made the payment for their
follow-up online.
2.4.2 Component by
component discussion of inclusions
The project is categorized into the five components in simple words we can say the
overall project is divided into five phases (Initiation, Planning, Execution, Monitor &
Control and Closing). All of these phases are involved different activities and some
of the key activities are discussed above in the component analyse and the
complete activities list of the project are given below in the WBS.
The risk associated with the project are identified in the above section of risk
management but the major risks of the project are:
Turnover of team member during the project.
Project cannot meet the deadline
Project cost exceeded to its limit
2.4.5 Exclusions
Immediately preceding
Activities Duration
activities
A 25 -
B 5 A
C 20 A
D 30 B, C
E 25 D
F 18 D, E
G 20 D
H 60 D, E, F, G
I 45 H
J 80 H, I
K 30 H, I
L 30 C, D
M 22 C, D
M 35 J
O 20 H
P 45 H, I, J, L, M
Q 120 J, K, N, O, P
2.6.2 Network diagram
Project scheduling: Gantt chart
Cost estimation
The total cost assigned for the development of system is $50,000 the cost includes all associated cost i.e. development cost,
maintenance cost. The analogous estimation method is used for the cost estimation in which the cost or budget is used for the
project which is completed in the future or past. Here below is below is the budget of the project is defined using the key items of
WBS.
Determine budget
In our project, the main source of funding is the Finance Department of University. The project can cost us approx. $ 50,000 and
during the first year there will be no profit, the investment will be recovering after 3 years. Cost $ 90,000 will be estimated as a
benefit, ROI is 73% and NPV is $ 72,250.
2.9.2 Project baseline
Earned Value Management can play an important role to control the performance of the project by performing the comparison
between time and cost initially. EVM below provides schedule and cost performance and project assessment. EVM is used to
measure the performance of the project, identify a problem in different scenarios related to the project as well as a forecast or
estimate the cost and time required for completion of the project.
3.
As from now the project activities are completed within the time and on the track as
the project manager is consistently monitoring the project timeline and referring to
the Gantt Chart. If delay occurs then project manager can revise the schedule and
asked team member to work for an extra hour to meet the deadline of the project
and at the end they would be rewarded as rewards and incentives. Also, the cost is
tracked and monitored by comparing the actual value and estimate value (date).
As from the Gantt Chart given above till the date everything is completed
according to the time
3.1.2 Cost summary report on
activity level for Time Now
Here below the EVM is given which elaborates the overall progress of the project
in term of cost and timeline.
The graph given above can show three values PV, AC, EV. The point of BAC in a
graph is projected to total budget and this was shown only when project total
budget is spent that we have. EAC point mean project needs the extra budget or
cost and maybe it takes the extra days as planned. The budget for "Self-
Registration Kiosk" will be less than 70K and from the probability of project we
can get the idea, there is a need for the extra cost than estimated to successfully
complete the project
Earned value management
Item Data
Budget at completion (BAC) 50,000
Budgeted cost of work scheduled (BCWS) 45,000
Budgeted cost of work performed (BCWP) 50,000
Actual cost of work performed (ACWP) 52,000
Schedule performance index (SPI) or 0.9
schedule variance (SV %)
Cost performance index (CPI) or cost 0.86
variance (CV %)
Budget to completion (BTC) 52,000
Estimate to completion (ETC) 57,090
Estimate to completion (ETC) 13.3 months
Variance at completion (VAC) 7,090
Project Report:
The project performance is not good in term of cost and budget as the SPI and CPI
from the above result is less than 1. So the project manager need to identify that
where the delay is occurring and where cost is spent maximum. During the project,
the risk may occur to interrupt the overall project performance and progress as
every thing has associated risks. So, to overcome the risk, the project risk
management is performed in which each risk associated with the project are
identified and contingencies and mitigation strategies are proposed for each risk to
overcome its impact and effect on the project cost, timeline and quality. However,
the variance is calculated throughout out the project life-cycle and in each phase of
the project and variance is calculate by comparing the actual cost or time with
estimated cost and time. If variance is negative then corrective actions are made
and schedule and cost is revised and minor variance is neglected and acceptable
but if the variance is high then it is the point of indication to make the corrections
with schedule and cost. However, to deal with different issues in the project the
contingency strategies proposed are:
To overcome the project delay in the project schedule, project tracking is
at the end when the software is delivered that will be an error or defect-free
and no extra time is required because of no fixing or error and at the same
Mcgraw-Hill Education.