You are on page 1of 1

Rate Analysis of Concrete

Step - 1 Rate of item as per relevant section of this Schedule Rs. A

Step - 2 Add cost of stone aggregate of different grading as per


Consumption required for one cum of concrete.( As per table:T-1)
20mm Nominal Size: ( M-20 to M-40= 0.54M3, 1:2:4=0.66M3 ) Rs. B
10mm Nominal Size: (M-20 to M-40= 0.36M3, 1:2:4=0.22M3)

Step - 3 Add cost of carriage of stone aggregate as per


Consumption required for one cum of concrete.( As per table:T-2)
20mm Nominal Size: Rs. C
10mm Nominal Size:

Step - 4 Add cost for loading and unloading of stone aggregate Rs. D
(As per table: T-3)

Final Rate of Item = [Rs. A +Rs.B + Rs.C + Rs.D] = Rs.

Note:
1. Cost of stone aggregate of different grading to be obtained from Table T-1 by considering rate of
the nearest
2. Cost of carriage of stone aggregate to be obtained from Table: T-2 by considering the actual
distance from the

3. Cost for loading and unloading of stone aggregate to be obtained from Table:T-3

4. ANNEXURE – II is applicable for It. No. 5(a), 6(a)(i) to 6(e)(i), 7(a), 9(A)(a) to 9(A)(e) & 9(B)(a) to 9(B)(e)
of
Chapter – C only.