Professional Documents
Culture Documents
Program Actors
Both MSP and the PMI Standard define a number of program stakeholders. I have
extracted eight roles from these standards. These correspond to roles that I and my
colleagues encountered in our practice. Table 5.1 overleaf defines these roles.
Whereas most roles are similarly described in both standards, albeit with different
designations, the PMI attributes the responsibility of ensuring that program goals
are achieved to the Program Governance Board, whereas the MSP attributes it
to the Senior Responsible Owner (SRO). The reality of practice shows that both
are applied and that the choice of one or the other depends on the delegation of
authority in the organization and the seniority of the SRO/Director. In MSP, the
Programme Board is appointed by the SRO who has full authority over it. I separated
the BCM and customer although they would play similar roles. MSP seems to
consider the BCM’s role mainly as that of an internal customer, whereas PMI sees
the customer more as external, having only a needs definition and an acceptance of
Thiry, Michel. Program Management, Ashgate Publishing, Limited, 2010. ProQuest Ebook Central,
the program’s outcome function; for PMI, the transition is seen as formal contract-
http://ebookcentral.proquest.com/lib/liverpool/detail.action?docID=564132.
Created from liverpool on 2020-03-27 08:15:47.
84 Program Management
Thiry, Michel. Program Management, Ashgate Publishing, Limited, 2010. ProQuest Ebook Central,
http://ebookcentral.proquest.com/lib/liverpool/detail.action?docID=564132.
Created from liverpool on 2020-03-27 08:15:47.
Program Actors 85
based activities. The project managers are described as stakeholders only in the
PMI Standard. MSP attributes the responsibility of appointing the project managers
and the authority over them to the Program Manager, which is more effective from
a program point of view; if this authority is not clearly defined, it becomes very
difficult to run the program. I will elaborate on the role of the project manager in
Chapter 9: Deployment.
In the rest of the book, I will primarily use the PMI terms as they seem more
generic and more pertinent for a worldwide application. However, I will use the
term and the role of the Business Change Manager (BCM) as there is no equivalent
in the PMI Standard and, in my opinion, it is an essential role in the success of a
program.
Table 5-2 presents some more specific responsibilities for each of the roles
previously described within a number of program functions. The customer’s role,
as described by PMI, is essentially subjected to contractual arrangements and
therefore fairly standard. One group of actors that do not appear in MSP is the
Project Managers; I will not cover it either as it is well described in standards like
the PMBOK® Guide (PMI, 2008).
Manager Office
Outcomes Define Own the vision Deliver Realize, Administer
direction of (champion) capability embed and support
business benefits
Governance Endorse, Accountable Define Compatibility Quality
advise governance governance of new control
director arrangements framework capability
Investment Provide Secure Manage Financial
investment investment program accounting
decision budget
Formulation/ Program Program Plan and Prepare Set up
Organization mandate charter/brief, design organization monitoring
business case program for change and reporting
Deployment Approve vs Maintain Ensure Monitor Tracking and
strategic alignment overall outcomes vs configuration
objectives integrity and predicted management
coherence
Risks and Manage Manage Manage Risk and
Issues strategic risks programme operational issue
risks risks tracking
Thiry, Michel. Program Management, Ashgate Publishing, Limited, 2010. ProQuest Ebook Central,
http://ebookcentral.proquest.com/lib/liverpool/detail.action?docID=564132.
Created from liverpool on 2020-03-27 08:15:47.
86 Program Management
Accomplished program managers will also improve their team’s career development
opportunities by ensuring that the core team members gain satisfaction from their
role, recognising their contribution and allowing them to gain valuable experience.
On the other hand, a mature and well-integrated organization will use all the
flexibility and dynamism that a project and program approach can generate. The
program board will consist of the sponsor, program manager and business managers
Copyright © 2010. Ashgate Publishing, Limited. All rights reserved.
that are concerned by the change that the program brings about. As the members
of the program team will be responsible for the realization of the benefits, they
will ensure a good integration with the operations. The operations users, under
the guidance of the business managers, will prepare the business for the new
capabilities that will be delivered and give constructive feedback to the program
team. In this sense, the program will become like the value chain described on
p. 51. This approach is more effective when using a vision-led approach, but can
also be achieved with an emergent program if there is a firm dedication to the
success of the business and a commitment to an end-to-end process that spans
business units or departments. Figure 5‑2 graphically depicts this situation.
In the next three sections, I will discuss the responsibilities for realizing benefits,
governance and stakeholder management; each of these will be further developed
in Part Three.
In my experience the traditional handover process is not really effective for programs
that deal with organizational change, and the role of the program manager should
extend beyond the delivery of project outputs. The ongoing collaboration of the
program manager and the business manager/customer is essential, but the program
manager should take the responsibility, and be given the authority to realize the
benefits. Only in the case of highly strategic programs would the role of Business
Change Manager be warranted and this role would mainly entail preparing the
Copyright © 2010. Ashgate Publishing, Limited. All rights reserved.
organization for the change, which the program manager cannot always do.
In cases where full program manager authority is not possible, the business manager
should be as involved as possible in all program decisions from the start.
Thiry, Michel. Program Management, Ashgate Publishing, Limited, 2010. ProQuest Ebook Central,
Figure 5‑2 Programs in Integrated Organizations
http://ebookcentral.proquest.com/lib/liverpool/detail.action?docID=564132.
Created from liverpool on 2020-03-27 08:15:47.
Program Actors 89
Both the PMI PgM Standard and MSP recognize that the governance of the
program needs to be embedded within the corporate governance system. The MSP
defines overall program governance responsibilities as the design and approval of,
and compliance with the corporate controls, governance strategies and assurance
reviews. The PMI PgM Standard defines governance activities as controlling the
program investment and monitoring the delivery of benefits. Although MSP has a
program definition phase, in their processes, both of them focus on the compliance
and control aspects of program governance. Only P2M insists on the development
of the program vision as part of the program process. The APM (Association for
Project Management, UK), in their Guide to Governance of Project Management,
identify four components to project governance: a) portfolio direction, b) project
sponsorship, c) project management effectiveness and efficiency, and d) disclosure
and reporting (APM, 2004). Only efficiency, disclosure and reporting concern
control, all the other elements concern leadership and direction. This seems like a
better focus for governance.
Often strategies and strategic objectives are communicated in ways that are not
clear and leave a lot to interpretation. Setting strategic objectives involves that the
person responsible exercises leadership by consulting with the main stakeholders
to identify their needs and expectations to define what constitutes value for them.
This is typically the role of the sponsor, who can delegate it to the program manager
when they have enough seniority. Following this process, the sponsor will need
to formulate and clearly communicate the program strategy in measurable terms;
this is usually done through the program mandate which is clarified in the business
case. When a Program Board is set up, the Program Board may take up this
responsibility.
Management has to commit, not only to clear, measurable objectives, but also
allocate the necessary resources – financial, human, technical and time – to
achieve them. The sponsor and Program Board has a responsibility to use their
expert knowledge to assess the achievability of these objectives and correct
any discrepancies. They bear the responsibility to provide the program with the
necessary resources to deliver the benefits and to authorize changes in the program.
Thiry, Michel. Program Management, Ashgate Publishing, Limited, 2010. ProQuest Ebook Central,
This role is well described in the PMI PgM Standard, but not in MSP.
http://ebookcentral.proquest.com/lib/liverpool/detail.action?docID=564132.
Created from liverpool on 2020-03-27 08:15:47.
90 Program Management
In terms of stakeholder management, the PMI PgM Standard defines the role of
Thiry, Michel. Program Management, Ashgate Publishing, Limited, 2010. ProQuest Ebook Central,
the program manager as communicating a vision of the need for change, specific
http://ebookcentral.proquest.com/lib/liverpool/detail.action?docID=564132.
Created from liverpool on 2020-03-27 08:15:47.