HANDBOOK OF
CONSTRUCTION
ESTIMATE
Simplified with Technical Data
Rheno A. Velasco
LOACAN PUBLISHING HOUSE
PUBLISHER / DISTRIBUTORPhilippine Copyright C 1997
all rights reserved
Amount of.Water Per Bag: os Coden! |
Approximate Quantity of Surface Water Carried by
Average Aggregates
Fuller's Formula
Copyright c 1997 by :
LOACAN PUBLISHING &
RHENO A. VELASCO
Bibliography:
e Simplified Design of Reinforced Concrete
by : Parker
e Design Concrete Structures - Winter
Construction Planning - Peurifoy
AUDELS
CHB Finish Per Sq. Meter
Mortar ...
Volume of Cement ‘Per ‘CHB
Varying Thickness of Mortar and Quantity ...
Requirements for Mortar.
Concrete Pipe Joint Collars .
Concrete Footing for CHB.
Adobe Plaster.............-..+.
Plaster Mixture Per Cubic Meter.
CHB Mortar Per Sq. M. .....-.
CHB Footing Per Linear Meter.
Quantity of Stone, Cement and Sand
Plastering Per Square Meter
ISBN 971-911-150-XPer 100 CHB Mortar .. aoe
a
7
g
QZ SRRFRLSSS
8
£Be
Placa Romana.
Tencor Corr. Sheets .
2agee
{Quantity of Roof Accesseries in Kilo .
Sample Problesm...csss--ser-reeeeeetePrecast Terrazo and Granulithic Tiles
Vinyl and Rubber Tiles
- Sample Problem
STAIRCASE OR STAIRWAY
Definition of Terms ..
Design of Stairway ...
PAINTING
Painting Works
Spreading Rate of Paint .
Kinds of Paint.
Paint Coverage
LABOR ESTIMATE
Construction Work Capacities in Man Hour:
Capabilities of Manual Labor/Hour
Capabilities of Equipment........... . 87-88
Important Features of Septic Vaults 89-90
Rough Estimates . 90
Checklist of Items to be Considered 90-91
Ceneral Checklist for Estimate. 91-98
Site Visit Report. 99-101
Unit Man Hours.
Concrete Foundation and Elevated Conc.
Unit Man Hours...
Miscelianeous Labor Output .
DEFINITION OF TERMS
AUXILIARY TOPICS ..
Code of Ethics for Construction Contractots
101-103
103-105
106-116
117-119
120-129
etercae LOO
131- 136CONCRETE
History of Concrete
Concrete as we know it today, had its beginning in 1824,
when Joseph Aspdin took out.a patent in England or “Portland”.
cement. Concrete became widely used in Europe during the late
1800's and was brought to the United States late in that century
and in all over the world. It used continued to spread rapidly as
knowledge about it and experienced with it grew.
Concrete — is a stonelike material obtained by permitting a
carefully proportioned mixture of cement, gravel and sand or the
other inert materials, and water to harden in forms of the shape
and dimension of the desired structures.
Estimate — is a project study of determining the quality,
quantity and cost of every materials used in a mass, or in every -
finished work.
There are different types of coment used for construction
1. Ordinary portland cement :
2. Rapid hardening portland cement is specified when high
early strength is required
3. Portland blast furnace or sulphate is used to resist chemi-
cal attack
4. Lowheat portland cement is preferred for amassive section
to reduce the heat of hydration.
5. Portland pozzolan cement is a slow hardening concrete
6. High alumina cement
These are the main compogition of cement:
+ 60 to 65% lime
18 - 25% silica
3— 8% alummina
-5 — 5% ironoxide
2 - 5% ma
1.- 5% sulfur trioxide
1
2.
3.
4
5.
6.2s
Lime — mortar made of mortar cement, lime putty or hydrated
lime, and sand in proportions by vol. Normally of-one part 9f
cement. One or two lime, and five or six sand; suited for all kinds
of masonry.
Silica — a mortar used with silica cement; it is a refactory
material. i
‘Alumina - a cement made with Bauxite and containing a high
percentage of aluminate, having the property of setting to high
strength in 24 hours.
Ironoxide — a mixture of small iron pieces with ammonium
chloride, used to join iron or steel surface. i
Magnesia — magnesium oxychloride cement. ,
Sulfur Trioxide — cement used for connecting iron parts; made
of equal parts of sulfur and pitch.
EXCAVATION AND BACKFILL
SAMPLE PROBLEM:
Find the total volume of excavation and backfill. Assume
the soil to be moitordinary earth. The slope of this kind of soil
varies from 1:1-1:1.
SOLUTION: Assume 1/2 slope:
For the vol. of excavation:
Vexcavation = Veurtoine + Vamp
Solve first for the volume of building and ramp
Vauipine = (1/2 pop + Aporron)! X peorn
= 0.5 (96) (46) + (93) (43) (3)
= 14, 249.16 cu. m.
Veaur = (0-5) (25.5) (3) (7)
= 299.5
+ Vexcavanton® 14,548.66 cu. m.
Vaackri, = 1-25 [14,548.66 — 1.5(90) (40)]
= 11,435.82 cu. m. w/ 25% allowance
ANGLE OF REPOSE
TABLE 1-1
Approximate
90 to 110
100 to 110
110 to 120 |
80 to 100
1/2.8 to 1/1.0
1/2.1 to 1/1.0 ‘80 to 100
10C to 135
100 to. 115.= 5
ght aaa Sy
CONCRETE PROPORTIONING CONCRETE MIXTURE
TABLE 1-2 TABLE 1-3
QUANTITY FOR 1 CU. M. CONCRETE Type of Construction
Side Walk 4” thick
Floor Slab 4” thick
USING 94 LBS PORTLAND CEMENT
Class | Proportion Cement Sand Gravel Wall
Foott
AA 1:2:3 10.50 0.42 84 ne
Post
A 1:2:4 7.84 0.44 0.88 Manhuncry Raindalion
B 1:2.5:5 6.48 0.44 0.88 Reinforced Concrete
c 1:3:6 5.48 0.44 0.88 Foundations
tence, Top Dressing on Wearing Surp.
D 1: 3.5:7 5.00 | 0.45 0.90 Wo eee
USING 88 LBS PORTLAND CEMENT
OTE: Keep te wet 7d t Z
A 2:4 8,20 0.44 0.88 al conerete ce: days ond peoece rom ein
B 1:2.5: 6.80 0.46 0.88
: APPROXIMATE TIME LIMIT BEFORE
0S tose 530 0.47 0.88 | THE REMOVAL OF FORMS AND SUPPORTS:
D 1:3.5:7 5.32 0.48 | 0.90 | miare ie
NOTE: Arch Centers
Centering Under Beams
* Class A = Shall be used for beams, slabs columns, and for all
members which are subjected to bending stress.
* Class B= Shall be used for all members not reinforced for
bending'stress.
* Class C = Used for footing not under water.
Floor Slabs
Walls
Columns, Sides of Beams and Girders.FULLER'S FORMULA
Let’ C = No. of Part Cement, S = Sand
AMOUNT OF WATER G = Gravel'or Stone, Then:
PER BAG OF CEMENT
TABLE 1-5 aT _ ho, of barrel portand cement
“C4S+G__ required for one cu. yd. of concrete
Gallon of Water/Bag Mix
Dry Mix |Moist Mix Wet Mix
75 6.0
5.5 4.5
P_, = 32.2875 P_. = no of barrel portland cement
Mix ‘Type of Const.
required for one cu.m. of concrete
1:3: 5 | Figs., Reinf. Wall
1:2:3 | Side Walk, Step
i
PL xSx3.8 no of cubic meter sand for one
32.2875 ~ cubicmeterofconcrete __
: 2 | Fence Post 45 3.75
P_xGx3.8 no of cubie meter gravel for one
TER CEMENT RATIO 1
ea 32.2875 ~ cubic meter of concrete
US Gzl./94 Lis Bag Cem. | Assumed Comp. Stress at 28 Days
2000 PSI NOTE: i barrel = 4 bags of 96 Lbs. Portland cement
75 = 3.76 Cu. Ft.
6.75 2500 PSI
6.0 3000: PSI
SAMPLE PROBLEM FOR PAVEMENT CONCRETE:
5.0 3750 PSI
Area = 6.70 x 1,000 = 6,700 Sq.m.
Vol.’ = 6,700 x 0.23 = 1,541 cum.
Using 88 Lbs Portland Cement:
(Use Class “A‘)
APPROXIMATE QUANTITY OF
SURFACE WATER CARRIED BY
AVERAGE AGGREGATES
TABLE 1-6
Gal. Cu. Ft.
3/4 to 1/0
1/2
SOLUTION:
Aggregate Classification
Very Wet Sand
Moderately Wet Sand
-| Motst Sand
"Moist Gravel, Crushed Rocks
a) Cement: 1,541 x 2.20 = 12,636.20 Say 12,640 Bags
b) Sand: 1,541 x 0.54 = 678.04 Say 679 Cu.m.
co) Gravel: 1,541 x 0.88 = 1,356.08 Say 1357 Cu.m.Yo RADIUS
HARDWARE MATERIALS
a)
b)
Total length of the bars = 1 334 x 0.60 = 800 m
Dowel Bars, use 3/4" @ x 0.50 m x 0.50 m. O.C.
int for every 75 m.
Assume one const. jo!
Therefore no. of coust. joints =
joints
The are also 6.70 _13.4 Say 14 pcs. of dowel
0.5 bard for each const.
Total no. of dowels fore the whole length
Where: 14 x 14 = 196 pes. ~3/4'@x 0.5 m or = to
98 pes. of 3/4” x1.0m.
Use the standard size reinforcing steel bars is 6 m.
Therefore:
RSB = 98/6 = 16.33 Say 17 pes. - 3/4. 3 20 ft.
The bars use 1/2" @ x 0,60 in spaced c 0.75 m.O.C.
No, of pes. = ae 1,333.33 Say 1,334 pes.
RSB='133.5 Say 134
.000 13.33 Say 14 const.
PLAIN CONCRETE
SAMPLE PROBLEM WITH SOLUTION:
CONCRETING:
Find the quantity of cement
in bags, sand and
oe o needed for a plain conc. slab on fill 0.10 m eu
.0 m in dimension. .
SOLUTION:
1. ‘Find the volume:
V =0.10x9x6
= 5.40 cu.m.
2. ene on table 1-2 class “B”
or cement: 5.4 x 6.48 = 34.99 bags
.99 say 35.
Sand: 5.4 x 0.44 = 2.37 say 2.5 cu.m.
Gravel: 5.4 x 0.88 = 4.75 say 5.0 cu.m.
Aconcrete pavement with a thickne:
SS O!
a dimensions of 18 x 28 m. Using class “C” Meee toe
Compute for the quantity of:
in cubic meters Lip eee Gees pa in bags and10
SOLUTION:
1. | 4 inches = 0.1016 meter
2. Area of the pavement
deo ee eee
3. Volume = 0.1016 x SORT hOURy
4. Referring to table - using Class “C” mixture
Cement; 51.21 x 5.5 = 281.65 say 282 bags
Sand: 51.21 x.44 = 22.52 say 23 cu.m.
Gravel; 51.21 x .88 45.06 say 45 cu.m.
MASONRY
is name for walls, pillars, arches, and other
thie nate ae bricks, stone blocks, and other one
like materials, such as concrete blocks, in a cementing mate-
i Long ago, primitive man discovered that he could nay
occurring stones together to make a rough wall. Later, Hue ms
upon the idea of trimming the stones so that they wot ole
together. Better this made a firmilr and more solid wall. Atal
the same time, people in regions where stone was scarce discov:
ered how to run clay into artificial stones — Bricks. Bricks were
easy to handle. The final step in the evolution of masonry was
taken when builders learned that they could use various mate-
rials to ceraent bricks or stone blocks together. In this way they
could build rigid walls and more complicated structures such as
arches and vaults.
BRICK MASONRY
; : laid
To make a rigid wall of brick, individual bricks are
together in horizontal layers, or coarses. ‘The bricks are bound
together by a cementing material, or mortar.
tetae spreadsa layerof mortar with a wide, flat trowel.
He then sets the bricks on the mortar pressing them down lightly.
Ifa brick is out of line, he tay s i: gently into place with the handle
EL
of his trowel. Mortar ts also placed between cach bricks in a
coarse. When the first coarse is laid. The mason spreads mortar
on top of It and lays the second course on the mortar. He repeats
this process untfl the wall is built. y
itis important that each coarse should be level and that the
wall should be straight. An uneven wail Is not only unsightly but
itis weak. As he work the mason uses a spirit level to make sure
that the bricks are set level in the mortar.
HISTORY OF MASONRY
The ‘iistory of mansonry goes back as far as that of ctvili-
zation. Bricks.were apparently first used around 3500 B.C. by
the people who lived in the flat, low-laying plain between the tigris
and eupharates. Rivers in what is now Iraq. Wood and stone fit
for building were scarce in that region, but there was plenty of
clay, which the people made into sun-dried. They used these
oddly shaped bricks to build their great cities.
The next great civilization to use bricks was that of Egypt.
where brick making began about 3100 B.C. Although the
Egyptians had vast supplies of fine building stone. It took 90
much laber to quarry the stone?
From Egypt and the near east brick making spread over the
mediterranean world. The Romans became the master brick
makers of atiquity and they were made in a variety of different
shapes: rectangular, square, triangular, and semicircular.
One of the worst problems faced by builders in the Ancient
World was the lack of a strong mortar to bind their brick and
stones together. Yet in spite of their poor mortar ancient builders,
constructed some remarkable brick temples and palaces, with
walls 10 to 20 feet thick. The builders depended mainly on the
weight of the walls to hold the bricks in place.
Mansory construction was revolutionized by the Roman
discovery of concrete.in the 2nd century B.C. with the strong
commenting material builders no longer needed to make their
wails enormously thick to keep them from toppling over. Perhaps
the most famous examples of ancient stone masonry are the
pyramiés of Egypt.12
Otheranctent civilizations besides the Egyptians developed
great skill in handling very large blocks of stone.
There are different kinds of sizes and patterns of locally
available materials classified under masonry. Three kinds are as
follows:
: 0 Block 2) Brick 3) «Tile
13 CHB Per Sq.M of Wall,Area
Sand Approx. 1/10/Bag Cement
TABLE 2-2
CHB LAID PER BAG CEMENT:
4° x8" x16"
8" x8" x16"
NOTE:
1 Bag of Cement
equal = one cubic ft.
Plaster Vol. Per Sq. M. = 0.012 Cu. M.
CHB FINISH PER SQUARE METER
8" x8°x 16"
VOLUME OF CEMENT PER CHB
4" x8" x 16"
6" x 8" x 16"
0.001 Cu. M. |
0.003 Cu. M.
0.004 Cu. M.14
MATERIALS REQUIRED FOR 1000 SQUASE FT.
1
1
1
12” @ Non Reinf. Cone. Pipe 1:2 0.10B/JT 0.005 CM/JT
15” @ Reinf. Conc. Pipe 1:2 O15 B/JT 0.006 CM/JT
18° @ Reinf. Cone. Pipe 1:2 020B/UT 0.011 CM/JT.
1
a
1
1
1
24° @ Reinf. Cone. Pipe :2.0.35B/JT 0.019 CM/JT
30° @ Reinf, Conc. Pipe :2 O50B/JT 0.027 CM/JT
936" @ Reinf. Conc. Pipe :20.70B/JT 0.038 CM/JT
42° o Reinf. Conc. Pipe :2 O95B/JT 0.051 CM/JT
48° @ Reinf. Conc. Pipe :2 0.20B/JT — 0.065 CM/JT
QUANTITY OF MORTAR FER 1000 BRICKS
RET ROMM ODP
TABLE 2-5
MORTAR 1 CM THICK FOR ADOBE STONE
js 8 cubic feet
Joints S12 FACTOR PER ADOBE STONE
Joints 5/16 12 cubic feet
Joints 1/4 12 cubic feet
15 cubic feet
1, Cross Footing........... +. 0.00065 cu. one side’
2. ‘Buttress and Stairs......... 0.001575 cu. two sides
Joints 3/816
MORTAR 1 CM. THICK FOR ADOBE STONE
TABLE 2-6
("Sioa sue [able weerStone | Na ofan /60 0
ereniee aoa fae
peritein [ar emer pl eT |
CONCRETE FOOTING FOR CHB
(JACKBILTS SPECIFICATION)
TABLE 2-7
Thickness
17
Stock Size
2" x 4" x 10".
3"x4"x10
Width Meter
4” (0.10) 12° (0.39} 0.03 Cu. M.
4” (0.10) 0.03 Cu. M-
e158 | _14°(0.35)_| 0.0525.cu. m.
[sea9 | 16040
ADOBE STONE FOR ZOCALO WALL AND FOUNDATION
(BASED ON 0.15 M X 0.35 M X 0.45 M BLOCKS)
|
TABLE 2-8
4°x4"x 10"
3”x 10" x 10"
MISCELLANEOUS BRICKS AND STONE
TABLE 2-11
2°x4"
2° x6"
2°x 8"” 19
ADOBE BUTTRESS QUANTITY OF CEMENT AND SAND FOR
CHB MORT.,
TABLE 2-12 ‘AR PER SQ. M.
Finished Cross Section No. of Stones Per cone
MKS FPS Course Meter Height
0.35 x 0.50 14" x20" 2 12
0.50 x 0.50 20° = 20" 3 18
0.50 x 0.65 20" x 26" 4 24 12.5 .525 .994 328 .416 .308 .263 .04375
eo anS 20" x 32° . 30 12.5 1.013 .789 633 .802 .801 .606 .08438,
0.80x0.95 | 20°x38" 6 36 12.5 1,500 1,125 .998 1.188 .875 .750 .12500
NOTE: When wall is supported by buttress then. QUANTITY OF CEMENT, SAND AND GRAVEL
1. Estimate first for the buttress stone. FOR CHB FOOTING PER LINEAR METER
2. Estimate stone for wall.
3. — Cross footing estimated as continuous. TABLE 2-15
QUANTITY OF CEMENT AND SAND FOR MORTAR
AND PLASTER MIXTURE PER CUBIC METER
°
=
i}
TABLE 2-13
CEMENT in BAGS
40 kg. 50 kg.
ge $e
8B 88
&
8388 2238
18.0 14.5
12.0 9.5
~ 9.0 7.0
75 6.0
{888 88
882 2
225
-263
300
380
450
506 ‘
563
675
600
730
200
B5821
QUANTITY OF CEMENT AND SAND FOR
PLASTERING PER SQUARE
TABLE 2-18
QUANTITY OF CEMENT AND. SAND
PER 100 CHB MORTAR
TABLE 2-19
AND FOOTINGS
QUANTITY OF STONE, CEMENT AND SAND
FOR
15x 20x40| 8.104 6.072 5.064| 6.416 4.728 4.048 |0.675
TABLE 2-17 20 x 20x 40/12.000 9.000 7.504] 9.504 7.000 6.020 | 1.000
(CEMENT MORTAR PER STONE
ce ee QUANTITY OF CEMENT AND SAND
PER 100 CHB PLASTER
TABLE 2-20MASONRY
SAMPLE PROBLEM:
with 6"x8*
Construct a fence 2 meters high 52 meters long
x 16" CHB using Class “B” mortar and plaster mixture.
Be
¢
rt
9
Find the area of the wall:
‘A= 2m x52 = 104 9q. m.
Referring to table 2-14
104x 12.5 = 1,300 pcs.
ind the volume of mortar Tabl- 2
0.0008 x 1,300 = 1,04 cu. m.
Mortar for 4 cells Table 2-1
,300 = 3.9 cu. m.
Oo Calman ae wit ecm,
Referring to table mortar
12.04 x 4.94 = 59,48 cement
0.97 x 4.94 = 4.79 cu. m. sand
h. Find the volume of plaster
Two faces: 0.002 x 1,300 = 2.6 cu. m,
1 Referring to table _—_ using Class "B"
Cement: 2.60 x 5.5 = 14.30
Lime: 2.60 x 5.5 = 14.30
Sand: 2.60 x 0.90 = 2:34
Summary of Computation for Materials:
Cement: 59.48 + 14.30 = 73.78
Lime: = 14.30
Sand: 2.34 + 4.94 =7.28
POST AND FOOTING:
EXAMPLE PROBLEM:
Aconcrete post 4.00 m. high with a cross sectional dimen-
sion of a 10 x 12 in. is resting on a concrete footing 8 in. Thick
by 32" sq. if class B mixture is specified, find the quantity of
cement sand and gravel.
GIVEN FIGURE:24
REQUIRED: The quantity of cement, gravel and sand.
SOLUTION:
A Convert first the measurement from meters.
8" =.20m
32° = .80m
12° = .30m
10° =.25m
B. Find the volume of the footing
-20 x .80 x .90 = .128 cu. m.
Cc. Volume of Post
-25 x .30 x 4.00 = .30 cu. m.
D. Total volume 2 and 3 = .428
E. Referring to Table 1-2
Cement: .428 x 6.48 = 2.77 say 3 bags
428 x .44 = 0.188 cu. m.
-428 x .88 = .38 cu. m.
MASONRY:
PROBLEM:
‘The net area of a certain masonry wall is 100 sq. m. Find
the no. of 9* x 6*x 8 CBH. Bag of cement and lime, and cu. m.
of land. The wall is to be tooled finished on one side. Use 13
mixture for plaster and mortar.
SOLUTION:
1)-_ Pes. of CHB = 100 x 13 = 1300 pes.
2) Mortar Volume: Referring on Table 2-1 and Table 2-4.
Filler Volume = 1300 x 0.0026 = 3.64 cu. m.
Volume of mortar = 100(3.28)?
Sq.Ft x6Cu. Ft. Cu. m.
25
«. Volume of mortar = 1.83 cu. m.
Total volume of mortar = 3: 1,83 = 5.47.cu. m.
Referring on Table 2-3, using Class “B" mixture
Cement: 5.47 x 12.07 = 66.02 say 66 bags
Sand: 5.47 x 0.97 = 5.31 say 5.5 cu. m.
3) ~~ Plaster volume referring on Table 2-3
V = 100x 0,012 = 12 cu. m.
Cement: 1.2 x 5.5 = 6.6 bags
Lime: 1.2 x 5.5 = 6.6 bags
Sand; 1.2 x 0.90 = 1.1 cu. m.
SAMPLE PROBLEM:
Compute the quantity of cement in bags sand in cu. m. and.
poe 0.45 adobe stones for a wall supported by buttress'as
8 2
FIGURE:SOLUTION:
1, Buttress:
Total height = 2x 3 = 6.0 m.
No. of stones = 6(12) = 72 pes.
Mortar Volume %
V = 72 (0.001575) = 0.1134 cu, m.
on i:3 mixture:
Cement: 0.1134 (12.04) = 2 bags
Sand: 0.1134 (0.92) = 0.11 cu. m.
Wall:
Area = [10 — 3(0.35)] (2) = 17.90 sq. m.
No. of stones = 17.9(13) = 233 pcs.
For class “A” plaster on two faces
Cement: 233(0.0304) = 7 bags
Sand: 233(0.0017) = 0.5 cu. m.
3. Cross-footing:
No. of stones = 10(6) = 60 pes.
Mortar volume §_V = 60{0.0065) = 0.39 cu. m.
Referring on Table 2-3 using 1:3 mixture:
Cement: 0.39 (12.04) = 5 bags
Sand: 0.39(0.97) = 0.5 cu. m.
SAMPLE PROBLEM FOR MASONRY:
From the figure prepare the bill of materials using class “5”
mixtures.
28.0
VS
27
SOLUTION:
A. For conc. hollow blocks:
Compute for the total perimeter of the fence
P=20+20+20+15
=75m
Subtract the space occupied by the posts:
75 - (20 posts x 20)
=75-4
= 71 m. total length
Solve for the area of the fence
A=240x71m
A=170.4 sq! m.
Multiply:
CHB: 170.4 x 12.5 = 2,130 pes.
B. Cement mortar for-block laying and cell filler
Referring to Table 2+4 using class “B”
mixture 40 kg. cement
Cement: 170.4x .525 = 89.46 say 90 bags
Sand: 170.4x.0437=7.45 say 7.5cu. m.
Plastering of the fence to ground line only (2:0 m)
Solve for the area:
A= Ht. x Perimeter
A=2,00x71 m.
‘= 142 m. one face
Two faces: 142 x 2 = 284,sq. m.
Using Class B mixture
Cement: 284x .192 = 54.5 say 55 bags
Sand: 284x .016=4.54 say 5cu. m.28
Footing of posts = .60 x .60 eq.
Compute for the volume of footing Plastering of the Post:
vetxwxl o i i
vy =.15x.60 x .60 x 20 posts Take the guriace area of the
v= 1,08 cu. m. the CHB (0.20 x 2.60) Post lezs the area occupied by
9.89 x 2.00 ht. x 20 posts
Using class “B” = 24 sq. m.
F.
mixture
‘Cement: L08 x 7.5 = 8.1 bags
Sand: 1.08x.50=.5cu.m.
Gravel: 1.08 x 1.0 = 1.08
Using class “B" ruixture.
Cement: 24 x 0.192 = 4.6 bags
Sand: 24 x 0.016 = 0384 cu. m.
CHB Footing:
Summary:
‘Total length of the fence less the space occupied by the post
footings (.60 x .60 m.) ie i
75 m ~ (.60.x 19 posts) men
= a 11.40 Sand
= 83.6 m. Gravel
Instead of 20 posts we used 19 pes. only. Where the two Specify the use of 15 cm.
post at the gate entrance where in only one half footing having a dimension of 30 perm Sate cf fire wall
occupies by the CHB footing. mixture of mortar, Prepare 4 bill of mai high with class “B*
reinfercement for the same phase, clals for both CHB and
Using 40 kg. cement class “B" i
Mixture 10 x40 cm, footing.
Cement: 83.6 x .30 = 25 bags.
Sand: 83.6 x .02 = 1:67 cu. m.
Gravel: 83.6 x .04 = 3.34 cu. m.
Cencrete Post:
Solve for the volume
0.20 x 0.20 x 2.40 x 20 posts
= 1.92 cu. m.
Using class “B” mixture 40 kg. cement
Cement: 192 x 7.5 = 14.4 bags
Sand: 1.92 x 0.50 = 0.96 cu. m.
Gravel: 1.92 x 1.0 = 1.92 cu. m.
FOOTING LIME3} For Cement Plaster:
a) Referring tc table using Class “C* mixture
For Cement:.34.51 x -144 = 4.97 bags
Sand: 34.51 x .016 = 0.55 cu. m.
4) Footings:
a) ‘Total length of wall = 3.50 + 5.50 = 9.0m
b) Referring to table for a (15 x 40) footing using Class “A”
concrete mixture
For Cement: 9.0 x .450 = 4.05 bags
Sand: 9.0 x .030 = 0.27 cu. m.
Gravel: 9.0 x .060 = 0.54 cu. m. ,
cost analysis between a reinforced concrete wall
and a concrete hollow block wall:
This question is ordinary wherein some of the consultants
are confident enough when asked by a client which Is cheaper to
construct. A reinforced concrete wali or a concrete hollow block
wall? Usually their answer Is the concrete hollow block wall.
Then the client asked how sure are you thai a CHB wallis cheaper
than a reinforced concrete wail? ‘The consultant answered, I'm
certain and sure for it is already a proven fact sir. The client with
a laymen view believe whatever the consultant says: The
recommendaticn is approved, construct the fire wall with a 15
em. Concreie hollow blocks.
PROBLEM:
A Ore wall Kas a dimension of 35 meters long and
meters high specify the use of 15 cm. Concrete hollow
blocks with Clase “B" concrete mortar mixture. Prepare a
bill of materials for both CHB and a reinforced for
same wall.
_
|
SOLUTION:
1) Fora 15x20 x 40 cm. CHB wall:
a) Find the area of the wall
A=35%x7.0
A= 275 sq. m.
b} Referring to table:
275 x 12.5 = 3,437.5 pes.
For Cement Mortar:
8) Referring to table using Class “B” mixture 40 kg. cement
For Cement : 275 x 1.013 = 278.56 say 279 bags
Sand: 275 x .08438 = 23.20 say 24 cu. m.
For Cement Mortar:
4) Total area to be plastered
275 x 2 faces = 550 sq. m.
») Referring to table using Class “B* mixture 40 kg. cement
For Cement: 550 x .192 = 105.6 say 106 bags
Sand: 550 x .016 = 8.8 say 9 cu. m.34
Summary:
Concrete hollow block 15cm = 3,438 pcs.
Cement = 385 bags
Sand = 33 cu. m.
METAL REINFORCEMENT
STEEL REINFORCEMENT:
Steel is widely used reinforcing material for almost all
types of concrete construction. It ts an excellent partner of
concrete in resisting both tension and compression load and
Jhundred times stronger in tensile stresses:
Concrete design assumes that concrete and steel reinforce-
ment act together in resisting load and likewise to be in the state
of simultaneous deformation, otherwise, the steel bars might slip
from the concrete in the absence of sufficient bond due to
excessive load.
Types of Deformed-Bars__
STANDARD WEIGHT OF PLAN OR DEFORMED
ROUND STEEL BARS
TABLE 3-1
| 32 mm @ [31.57 | 37.88 [47.36 [56.82 [66.29 | 75.76 | 85.25 |
[71.92 [83.91 | 95.89 |107.88
96 mm @ [0.96
Max. Value
Summation
of Gaps of
Lugs
Nominal
Diameter
Max, Average
Spacing of LugsLength of Bars in Meter
Per
Per
Sq. M.
and
the determine the number of 10 cm. CHB
the wien recta bars apaced at 80 cm On center
including the horizontal bars at every three layers
verb. Reirg. Bo.8ou. Oc.
HORIZON TAL
RBINF. @ EVERY
S LAYERS
SOLUTION:
Solve for the Area of Fence:
A = length x height
A =4.00 x 3.00
A= 12 sq.m.
For vertical reinforcement of 80 cm. 0.C.
Referring to table by square meter or area method.
MULTIPLY:
12X 1.60 = 19.2 meters
Convert this value to commercial length of steel bars
ranging from 5.00 to 13.50 meters. Select the moat economical
length avo!ding extra cut.
Select 4 pes. 10 mm. x 5.00 m. long
Horizontal bars at every after 3 layers from table; multiply
12 x 2.15 = 25.8 meters
Adopt: 4 pes. @ 5.00 m and 1 — @ 600 m long.
Order: 8 pes. 10 mm, x 5.00 m. steel bars
1-10 mm x 6.00 m. steel bars
ANOTHER SOLUTION:
First: Solve for the area of fence:
A=4x3,00
A= 12.00 sq. m.
Determine the number of CHB
12 x 12.5 = 150 pes.
Referring to table:
Vertical reinforcement per block @ 80 m : O.C.
Multiply:
150 x 0.128 = 19.2 meters
Select: 4 pcs 10 mm x 5.00 m. longb) Horizontal bars for every after 3 layers
Referring to table mul!
150 x 0.172 = 25.8 m.
Convert to commercial length
Adopt:
4 pes. 10 mm x 5.00 and 1 @ 6.00 m. long
Order: 8 pes. {0 mm x 5.00 m. and
: oe tam x 6.00 m. steel bars
c)
PROBLEM:
12 mm steel bars and the tle wire
Independent square footing with
5 meters.
Determine the Ee ‘of
kilogram if there are 20 pcs.
pate dimension of 15 x 1d
(2 MM STEEL BAR’
FIGURE:
Lag
SOLUTION:
1. Determine the net length of one reinforcing cut bar
* 1.00 m. + .20 m. = 1.20 m.
389
2. Total cut-bars in one footing
6x2 = 12 pes.
3. Total cut-bars for 20 footings
12 x 20 = 240 pcs.
4. — Total length of all the bars
240 x 1420 « 288 meters
5. Divide the above result by the length one steel bar say 6.00
meters.
2.88
raaoy 7 28 Poe
Urder: 48 pcs. of 12 mm x 6:00 m. steel bars
ANOTHER SOLUTION:
1, Net length of one reinforcing bar = 1.20 m.
2. Total bars in one footing:
6x2 =12 pes.
3. Total for 20 footings
12 x 20 = 240 pcs.
4. Divide one steel bar by the length of one cut bar
6.00 _
$20!
This means that 5 pcs. at 1.20 meter long reinforcing bar
could be taken from a 6.00 meters long steel bar then.
5. Divide the total cut bars for 20 footings by 5
sn 48 pieces
LATERAL TIES:
The spacing of the ties shall not exceed:
16 x the Longitudinal bar diameter
48 x lateral tie bar diameter or
at least dimensicon of the column
eres40
SAMPLE PROBLEM:
termine the lateral tie for a tied column as Stirrups ~ the structural reinforcing member that holds or bind:
“ apaiah together the main reinforcement of a beam orgirder toadesigned
shown. oe
FIGURE:
epr
STIKRUPS FOR BEAMS AND GIRDERS:
There are two types of stirrups that is commonly used
a. Closed stirruns. b. open st
Te RAL TIED
we ER
COLUMN REINF
OPEN
ne
SAMPLE PROBLEM:
Aconcrete beam with a cross sectional dimension of 25x 40
em. required 10 mm open stirrups spaced as shown. Prepare the
order of 10 mm. steel bars for stirrups of § beams with the same
category.
Diameter of the main longitudinal bar = 20 mm.
Diameter of lateral ties = 10 mm
Multiply:
16 x 20 = 320 mm.
48 x 10 = 480 mm.
Shoriest side of the column = 300 mm.
Adopt 300 mm OK 30 em. spacing.
JONM. STIRRUPS,SOLUTION: 6
A. Bydirect counting there are 24 stirrups at 96 cm. say 1.00,
long.
B. Total number of stirrups ia
24 x 8 beams = 192 pes.
C. Using a 5.00 m long steel bars for a 1.00 m long stirrups.
Divide:
122 «38.4 pes. 10 mm x 5.00.m.
orusinga6.0 mm. long steel bars
Divide:
192. _ 32.0 pes.
6
D. Order: 32 pcs. of 1O mm x 6.00 m steel bars
10 mm x 6,00 m.
Aspiral column with a cross sectional diameter of 50 cm.
Requires 10 mm spiral reinforcement as shown in Figure.
Ifthere are 14 columnsat 7.00 meters high each, find the number
Col. Reinf.
of 10 mm Steel bars needed for a 5.00 cm. pitch.
Spiral ties
fe
a
td 5.0 cm. pitch
SPIRAL COLUMN:
(oe
til
SOLUTION:
A.
Spiral reinforcement
1. Find the total length of the 14 columns
7x 14 = 98 meters
2. From Table —_ for'a 50 cm. column diameter
5.00 cm. pitch
Multiply:
98 x 3.223 = 315.8 say 316 pcs.
3. Order: 316 pcs. 10 mm x 9.00 m. steel bars
The Wire
1. Find the number of vertical bars per column = 12
2. Referring to Table 3-7 for a 5 cm. pitch
Multiply:
12 x 21 tums per meter = 252 ties
3. Total tle wire for 14 column bar intersections at
7.00 m. ht. B
252x7,00mx14= 24,696 pcs.
4. Total length of the wire'at .30 m. long per tie wire
254,696 x .30 = 7,409 m.
5. Convert tc kilogram at 53 m. long/kilo
Divide:
7409
53
= 139.8 say 140 kilos44
AND HOOK ALLOWANCE OF ROD
REINFORCEMENT WEIGHTS au
wailable lengths of commercial bars: ee
, oon Gam aak (7.5 m) 30 ft. (9.0) pn email
OF ROD:
WEIGHTS AND HOOK ALLOWANCE | on 3 cabagens TiS
TABLE 3-3 ( |
- 6 0.222
u 10 0.616
d - 12 0.888
: 16 1.579
; S ey 2.466
: 5 25 3.854
; ? 28 4.833
a) 32 6.313
\ q 5 631 |
ii 8
2 te 40 . 9.864
z a 50 15.413
No. of pes, of lateral tie in one 6.0 m. bar
NOTE:
Kg. x 0,001102 = ton
Lb x 0.453 =kg
Tie Wire: é
No. 16G I. tie wire = 20 kg./ton of rebar
“= 0.02 x total weight of rebar
= $5 kgs. per rollCONCRETE SLAB REINFORCEMENT
| TABLE 3-7
| Bar | One Way Slab ‘Two Way Slab
20 Bar | Tie Wire 20Bar | Tie Wire
Kg./Sq.M. | Per Sq. M. 1Kg./Sq. M.
CHB - REINFORCEMENT
TABLE 3-7
Spacing of Vertical
Length of Bars in Meter Per
NOTE: Rebars for spiral column, slab and “CHB” indicated in
the tables ticlude the allowance for bending splicing and
end hook.
CHB REBAR
(JACKBILT SPECIFICATION)
TABLE 3-8
VERTICAL BAR SPACING50
HORIZONTAL BAR SPACING
Block Every Third Every Fourth Every Fifth
Thickness Course or 0.60 Course or 0.60 Course 0.0
a 3/8" 3/8O 3/8"
e 1/2° 1/2°8 1/2°@
a 1/z “SO 1/2” @ 1/278
ELECTRICAL ESTIMATES
Class of Work Unit Labor - Hour
Electrician Helper
Install thin-wali conduit.
with outlet boxes 1/2 and 3/4 in
100 L.F. 4-6 4-6
1.0 in. 100 LF. 4.3-7 4.3-7
1.25 in. 100 LF. 45-7.5 4.5-7.5
1.50 100 LF. 5.5-9 5.5-9
Install flexible conduit
with outlet boxes
1/2 and3/4in. 100LF. 3-5 3-5
1 and 1.25 in 100 LF. 4-6 4-
Class of Work. Unit Labour - Hour
Install Service Entrance Electrician Helper
Cap and conduit Each 05-10 05-1.0
‘Install conduit and
fuse panel Each 05-10 05-1.0
Install heavy rigid conduit
with outlet boxes
1/2 and 3/4 in. 100 in. ‘ft. 5.0-10 5.0-10 |
1 and 1.25 in. 100 in. ft. 50-11 6.0-11
11/2 in 100 in. ft. 3:0-13 3.0-13
2 in 100 in. ft. 12-17 12-17
21/2 in: 100 in. ft, 15-21 15-21
3 in 100 jn. ft. 20-28.’ -20-28
4 in 100 in. ft. 25-35 25-35
woop
Wood is that fibrous substance which compose the trunk
and branches of the tree that les between the pith and the bark.
The versatility of using wood in the construction has lifted it to
its present importance and high demand in almost all types of
construction
Even with the introduction and acceptance of new materi-
als and methods of construction, wood is evidently much in use
wood because of its strength, light in weight, durability and ease
of fastening has become one of the most important building
material.
DEFINITION OF TERMS
Lumber ~ is the term applied to wood after it is sawed or sliged
into boards, planks, timber etc.
Rough Lumber — is the term applied to unplaned or undressed
lumber.
Surface or Dressed Lumber - is a planed lumber having at least
one smooth side.
82s; $49 — are dressed lumber wherein in the number connotes
the number of smooth side such as s2s means smooth on two
sides and s4s for four sides.
Slab — {s a kind of rough lumber which js cut tangent to the
annual rings running the full length of the log and containing at
least one flat surface.
Timber — is a plece of lumber five inches or 13 cm. or larger {n its
smallest dimension.
Plank - is a wide piece of lumber from 4 to 13 cm. thick.
Board - is a piece of lumber less than 4 cm thick with at least 10
em. wide.
Flitch - is a thick piece of lumber.
Fine Grained - when the annual rings are small the grain or
marking which separates the adjacerft rings is said to be fine
grained. When large, it is called coarse grained.52
Straight Grained ~ when the direction of the fibers are nearly
parallel with the side and edges of the board, it is said to be
straight grained.
Crooked or Cross-Grained - is a lumber taken from a crooked.
tree.
CLASSIFICATION OF WOOD
Wood used in building construction are those wood which
grows larger by addition of layer on the oliter surface each year
known to Botanist as exogens.
WOOD ARE CLASSIFIED ACCORDING TO:
1. Mode of Growth
a. Exogeneous - are those outward growing trees which
are most prepared for lumbering
b, Endogeneous — are those inside growing trees which
are not preferred for lumbering because they produced
a soft center core
2. Density - density is either
a. soft
b. hard
3. Leaves — the leaves of the tree is either
a. needle shape
b. broad shape
4. Shade or Color
a, white
b. yellow
C,, 16d
d, brown
e. biack, ete.
5. Grain
a. straight
b. cross
ce fine
d, coarse
Nature of the surface when sawed
a.
b.
Cc
plain
grained
figured or marked
LUMBERING
(BOARD MEASURE = BOARD FT.)
oy
a
| a33_|
Lio —
‘ a
&
ci
® Pie |=|¢
8 3
S/=)18
B18
8
8
-
rePNFrbrs
uaa
y
2
8FLOOR JOISTS
(BOARD FT. OF FLOOR JOIST PER SQUARE METER)
TABLE 4-2
SPACING ON CENTER
10’ (0.25) 12° (0.30) 14" (0.35)
12.26 10.78
18.11 16.10
21.12
2.
3.
Subtract all floor openings from gross floor area.
Round total to 100 bd. ft.
For girts, girders, post, etc. — Estimate by direct counting
0.40 x 0.40
6.410
9.630
12.840
0.40 x 0.60
5.50
8.40
10.903. For components of shorter lengths, compuie according to
their sizes combined together and adjust to commercial
size. fl
Lumber over 24” shall have splicing with 8-1/2 diameter
bolt per splice.
Add 20% for waste and splicing or 15% fer waste alone.
Round to 10 bd. ft. for each truss or rafter.
Truss bolt size = 12 diameter minimum.
Minimum truss bolt requirements:
top joints = 5 bolts
end joints = 2 bolts
intermediate at bottom chord = 1 bolt
intermediate at top chord = < bolts
quantity of nails per 1000. board it.
CEILING JOIST
TABLE 4-6
is
BOARD FT. PER SHEET OF CEILING PANEL
xe
18°x24" 18"
0.c o.c bw.
inx2? |3.85 44
2°x2° 17.70 8.8
27x39" | 11.55 18.20
2° x4" | 15.40 17.60
Stock
Pie
Boop
QUANTITY OF NAILS PER 100C BAD. FY.
CEILING BOARD
TABLE 4-7 ~
Rafters 6kg
il A of Pes. /Sq. M. Purlins 9-10 kg
\ Size | No. of Pes./Sq.M.| Size __| No. of fsa: Floor Joist
12” x 12” 11.30 24" x 24" 263 5 Flooring ea i
¥ 6” 0.65 FS" x 2°
16" x 16" 6.35 3" x6 = 1/2" x 2"
16" x 24" 2.82 4x8" 0.38 "x4"
1"x 6"
CEILING JOIST
as Studs 4kg
TRUSSES AND RAFTE Sidings 8 kg
1. Estimate by direct counting and measuring met? od. Door and Wdw. Frame
2. Make a check list of components: Briding 1° x4"
a. top chord
b. bottom chord
c. collar plate
d. strut or web member
e. brace
f windor sway bracing59
58
SIZE OF POST’ SAMPLE PROBLEM:
TABLE 4-9 Find the total board foot of lumber that could be derived
from a 28 inches diameter log by 20 feet long.
pee 1 by the Department of Engineering of the City of | FIGURE:
Manila (Ipil or Its Equivalent) ;
ite the needéd materials for the floor system shown
using 1” x 6" flooring supported by 2” x 6” joist spaced at 12° on
center.: Puke ROOFINGS
1. For 1°x6".T & G Flooring:
Referring Table 3-3 10.8 bd. ft/eq: m.
Total bf = 10.6 (3 x 6} = 104.4 bd. fo
N-2x67 x 16" +2 = 104; Ne 24 pes.
ROOF PITCH AND PERCENTAGE ADDITION
Percent Addition’ to Flat
Area for Trusses and Rafters
2. For 2” x 6" x 12" Floor Joist
From Table 3-2 16.10 bd. ft./sq. m.
‘Tatal bf = 16.10 (3 x 6) = 289.8 bd. fU
N-2°x6"x 12 + 12 = 289.8, N = 24 pes.
SAMPLE PROBLEM:
te the needed materials for the ceiling frame shown.
Use 3° x 6" joist 18" Lone
SOLUTION:
1. Divide 4 +0.9=5; 10+ 1.8=6
Pes. of Ceiling Panel = 5 x 6 = 90 pcs.
2. For Ceiling Joist:
Referring to Table 3-6 8.8 bd. ft./sht.
No. of pcs. without considering cutting
wastage = (4 x 10) + (9x 1.8 = 25 pes.
Total bf = 25 (8.8) = 220 bd. ft.
N-2°x2°x 12 + 12 =220, N = 55 pes.
Nail from Table 3-8
No. of kis (1 1/2) ewn = 8(334.4) x 10 = 2.7 kis
Formula for Pitch:
Pitch =
$s63
Ga ROOTS 4. Solve for puriin based on Table 5-2 and round up to 10 Bd.
PURLINS FOR STANDARD THAN 3.0 M 2 a -
roofing sheets adn round up to:10 sheets
ROOFING HARDWARES
Roofing Rivets = 180 pcs. per kgs.
6' Corr. G.I. Sheet - 6 Rivets Per Sheet
T Corr. G.I. Sheet - 9 Rivets Per Sheet
8' Corr. G.I. Sheet - 9-12 Rivets Per Sheet
12’ Corr. G.L Sheet - 12 Rivets Per Sheet,
Lead Washers = 96 Pes. Per Kilo
Plate (Washer) = 152 Pcs. Per Kilogram
PLAIN G.I. STRAPS PER SHEET
(36”" X 8” — 0”)
TABLE 5-4
Strap Size
ROOFING NAILS: —
102 Pes. Per Kg. 2 1/2
188 Pres. Per Kg. 2 1/2
NO. OF ROOFING NAILS:~—
6. 7 and 8 Length = 12 Pcs. Per Sticet
9 and 10’ Length = 16 Pcs. Per Shest
12 Length = 18 Pcs. Per SheetNO. OF WASHERS PER SHEET = NO. OF RIVETS FOR
3 PURLINS/G.1. SHEET d
12 Straps
7 Pcs. Rivets Non Engaging
26 Pcs. Rivets Engaging
For 4 Purlins Per G.I. Sheet
16 Straps, 7 Pes. Rivets Non-Engaging
32 Pcs. Rivets Engaging
Non-Engaging Rivets 3/8" x 1/4” = 189 Pcs. Per Kg.
Engaging Rivets 1/2' x 1/4' = 153 Pes. Per Kg.
2 Pcs. Lead Washer
2 Pcs. G.I. Washer
2 Pes. 11/2 Flathead
Nails 0.06 Kg. Per Sheet
2 Pcs. 2 1/2" Roof Nails.
0-082 Kg. Per Sheet
Plain G.I. Gutter, Ridge Roll. Facia Flashing
Standard Length = 8 Ft.
No. of Sheets Req'd. =Total Linear Mtr. x 0.44
Nikolite Soldering Lead:
~@utter ;
No, of Bars = No. of Pes. of Gutter + 4
Downspout
No. of Bars = No. of Pes. of Downspot + 5
Murilatic Acid = 10 cc. Per Bar
KINDS OF ASBESTOS ROOFING:
1, Standard Corrugated Sheets
4-V Corrugated Sheets
2
3. Kanaletas
4. Placa Romana
6. Tencor Corrugated Sheets
TECHNICAL DATA
Standard Corrugated Sheets
_ =4to
End Lapping: Below 20° = 0.30 M rg
Width: Effective ae acre
pean meri aia a General Formula
97ap
98
Sepeoesnoge
GENERAL EXPENSE MAY INCLUDE AMONG OTHER®: a
_ Mobilization and Demobilization
* Job Salaries
Security and Safety
Medical-Dental
Temporary Facilities or Temfacil
‘Transportation, Material, Equipment, Personnel
SSS-Medicare, or Fringes
Insurance, Bonds
Taxes
Home Office Overhead
SET-UP PROFIT INCREMENT OR MARKED-UP AND PROFIT
MAYBE
a)
b)
On-site visit by
Pop
Opportunity cost of money advances
~ Payroll Money
- Equipment Operation Cost ~
~ Materials Purchases
- Prepaid Insurance
Proportionate share on the company’s real property depre~
ciation cost or outstanding loan payment.
SITE VISIT REPORT
Name of Project
Client
Location of Project
Date of Visit
Distance to closest towns or cities |
Highways: Roads:
a) Type and surface condition
b) Capacities of bridges or load restrictions
10.
11.
5 a 99
Hall roade, distance and condition
a), “From barge back facility : «
b) From various materials sources i
Power Connection ;
a) Closest installation and capacity Description
b) Cost of extension or/installation of job
¢) Person to contact for installation sg
Telephone Communications:
a) Person to contact for installation
Land rental, ownership and availability if owners does not
supply ate we area
a) Project:
a es ea | ea
ae availability, adequacy. Location with reference to
Trailer Facilities: location; adequacy: availability
Local sub contractors or suppliers:
a) Adequacy of plant; method of delivery; reputation
Construction material suppliers
Lumber
Aggregate
Rock and riprap materials.
Clearing )
Painting
Mechanical
Electrical
Ready Mix Plants
Rental haul trucks
Grouting
Seeding and Sodding
Bituminous surfacing and road work
Well drillers17.
101
Determine if terrain and working conditions will allow or
12. Visit Clients Office: require specialized equipment.
a. List names and titles: telephone numbers of Persons
ca 18. Emergency Services (ambulance, hospitals etc.)
Title Phone 19, Notes and Comments
Name :
Title Phone Pe anaes es FE
Name ’
Title Phone
b. Discuss general job requirements; UNIT MAN HOURS
Check when completed
13.
14.
15.
16. Investigate ground-water conditions, natural drainage.
oop
¢. Clarifying questioned items in specifications check
when completed
Form Lumber ~ 110-140 bf per cubic meter of concrete
Form Plywood - 0.8 pieces of 4° x 8" plywood form per cubic of
d. Examine special reports, etc. Secure copy if possible; concrete.
otherwise make extracts of pertinent features check Assorted Nails ~ 1 keg. of assorted nails per 2000 bf of nailing
surface
when completed.
Describe site: Take photographs of all borrow areas; plant
area; general construction areas extent of clearing and
grubbing required.
Determine availability of potable water
a. Secure approximate costs of drilling and casing well
Recommend locations of contractor's worksite:
Locate office, shot and sheds
Estimate work required to prepare site
Locate batch plant and aggregate area
1. Estimate site preparation
2. Determine foundation conditions
d. Locate storage areas for materials
e. Recommend temporary roads
f. Is local road surfacing material pit available?
Yes No
aread
45 kilos of nails ~ 1 keg.
1 keg ~ 100 Ibs. - 45 kg.
FORMULAS TO FIND APPROXIMATE NUMBER
OF NAILS REQUIRED (REF. U.S. ARMY
ENGINEER FIELD DATA)
Number of Pounds (12 d+ 60d, framing) = 4.
Number of Pounds (2d to 12d, sheating) = ay a
Where:
d = Size of desired nail in penriies
BF = Total board feet to be nailed
and features which may revised or relocated to assist in main-
taining dewatered operation: J102
a 103
UNIT MAN HOURS ITEM OF WORK CAST IRON PIPE
1. Commen Excavation fstmaual) 6.0 ME gag Sle. 98.g MH LOO LE
Se si ao aati) 300.2 MH/ 100: LE
2 Common Excavation (Machine) 5 oe 8 aie 150.3
. ae CE ss a ae |
MH 10° 300.6
8.0 gC St Ee
3. Hook Excavation (Manual and Machine Ww 12° 317.3
MH 14” @ 367.4
4. Structural Backfill (Manual) 5.0 Fer 16"@ 417.5
MH 18° @ A a
5. Structural Backfill (Machime 2.075
is PVC PIPES
1.0
6. Hauling Spoils 'e 1/2°@ ey), OM LORE
MH 3/4" @ ——__—__ | 20 MH/100 BF
7. Trenching by Hand 6.0 we I" @ 22.5
MH L2G, ee | |
8. Trenching by Machine O25 1-1/2°@ % 2B.
2° 25..
9. Piping Installation Pobsfar Oy 30.
3 @ 33.
ASBESTOS CEMENT PIPE UNIT MAN HOURS ss 8 ae
1/20 20.00 MH/100 BF 4@ 40.
3/470 20.00 MH/100 BF ao 5.
re 20.50 eS 2 is
Lite / ACO ee eee a) ae CONCRETE FOUNDATION AND ELEVATED CONCRETE
Bat See ee eee ec |) UNIT MAN HOURS
oo 25.00 '
2"-1/2°8 30.00 1. GRADE MEMBER
3° 33.00 Forwork 2, MH/M?
1/2 e. ee S600 Concreting _s Ss—() = 1472kn/m?
Taking 1-m strip of the slabs
wh = 24.72 kn/m
For maximum moments:
=M= WL? = 14.7205) = 656knm :
2 eee
design Mu = 16.56 kn-m P
Required Ru: :
Ru = Mu(i
rye
Assume:
Ru + 16.56.10
0.90 (1000) (100)
d = 100mm
Ru = 1.84 MPa
computing Actual P_
P = 1f/m[1-/ 1-2mRu]
} fy
Po = 1/14.72 [1-/1-2(04.72(1.84 ]
j 300
P= 00064 8 >
_ pmax > p> pmin OK
135
As 1.0064 gon crony
= 640 min’ \
RBINPORCEMENT BARS:
Use 12mm@ bars;Ab = 113.1 mm?
S = 113101000) = 176.72mm
640 é
Nb = 1000 =
176.72
5.66 SAY 6 BARS
TEMPERATURE BARS:
Use 10mm @ bars; Ab = 78 mm?
As = 0.002(1000)h; whereh = 100+ cover /
= 100+ 25 = 125mm
= 0.002(1000)(125). = 250mm?
S = 78(1000) = 312 SAY 310mm
250
Nb = 1000 = 3.3 SAY 4 BARS
310
THEREFORE:
Adopt: 125 mm thick slabs with 12 mm 0 minimum reinfor-
cement and 10mm 0 temperature bars.» TERMS IN CONSTRUCTION -
PILIPINO - ENGLISH EQUIVALENTS
POSTE, HALIGE
GUILILAN
SULERAS
SAHIG, SUELO
SEPO
BIGA
BARAKILAN
REOSTRA
SENEPA.
KOSTILYAHE
TABIKE
PILARETE
PABALAGBAG
PASAMANO
SUMBRERO
HAMBA
SI ON
ARDINERA
MADRE (DE ESCALERA)
BAYTANG
TAKIP (SILIPAN)
GABAY
ain
IBE
BOLADA
BALANGKAS
KANAL
ALULOD
aoa ow
on onun tuo wt
| | |
POST
GIRDER
JOIST
FLOORING
GIRT
BEAM
BOTTOM CHORD
PURLIN
FASCIA BOARD
CEILING JOIST
SIDING (EXTERNAL)
STUD (VERTICAL)
STUD (HORIZONTAL)
WINDOW SILL
WINDOW HEAD
WINDOW OR DOOR JAMB
COLLAR PLATE
STRINGER (OPEN)
STRINGER (CLOSED)
TREAD
RISER
HANDRAIL
MOULDING
EAVE
PROJECTION
FRAME WORK
GUTTER
CONDUCTOR
DE BANDEHA
ESCOMBRO
LASTILYAS
LIYABE
HINANG
ESTANYO
SUBAN, SUBUHAL
PIE DE GALLO
PUNSOL
POLEYA
ESPOLON
ononou o rannunou tooo
wnunud
137
‘W.1. STRAP
BOLT
SCAFFOLDING
STAKE
PLASTERED COURSE
STUCCO OR PLASTER
SCRATCH COAT.
PICKWORK (ON MASONRY)
VARNISH FINISH
SPACING OF GAP
CONCRETE SLAB (ROUGH)
ALIGNMENT
PLUMB LINE
CEMENT TILE
CEMENT BRICK
DOOR FILLET
GROOVE
GOOD GRAIN
PATTERN OR SCHEDULE
HINGE
PANELED DOOR
EARTHFILL
MASONRY FILL
ADOBE ANCHOR
SOLDER
NICOLITE BAR
TEMPER (METAL WORK)
DIAGONAL BRACE
NAIL SETTER
WIRING KNOB
CABINET HINGE138
EQUIVALENT VALUES
1 CENTIMETER = 03937 IN.
1 METER = 3.281 FT.
1 METER + 39.37 IN.
1 METER = 1.0936 YARDS
1 KILOMETER = 0.54 NAUT. MILE
1 KILOMETER = 0.6214 STATUTE MILB
1NAUTICALMILE = °° 6080 FT.
1 STATUTE MILE =) 5280 FT.
1 LITER = 0.22 BRITISH GALS.
1 LITER + 0.2642 U.S. GALS.
1 GALLON I 4 QUARTS
1 QUART = \ 2PINT
1 QUART = 0.95 LITERS
1:GALLON (US) = 231 CULIN.
1 GALLON (BRITISH) = — 277.42 CU.IN.
1 BRITISH GAL. =~ 1.2U.S. GAIL.
1 POUND — = 16 OUNCES
1 QUART = 32 FLUID OUNCE
1 TON = 2000 POUNDS
1 LONG TON = 2240LB.
1 METRIC TON = 2200 LB.
1ROD =F LSS DS!
4RODS = 1 CHAIN = 22 YRDS.
1 FURLONG = 40 RADS = 220 YRDS.
1MILE = FURLONG = 1760 YRDS.
1 FURLONG = 201.1684 M.
1CU. METER = 1000 LITERS
1 CU: METER = 35.5 CU. FT.
1CU. FT. = 7.48 GALLONS
1 CU. FT. = 28.3 LITERS
1 HECTARE = — 10,0v00M?
1 ACRE =
43,560 SQ.FT.
1SQ. KILOMETER
1SQ.M.
18Q.M
1SQ.M.
1 INCH
1 CABLE LENGTH
1 FATHOM
1 LEAGUE
1 SPAN
1 VARA
1MIL
8
8
8
1 RPM
1 RPM
1BTU
1 WATT
1 WATT
1 ERG
1 JOULE
1 THER.
1HP
1HP
1HP
1Kw
1 BOILER H.P.
1 MECH. HP.
1kw
1 METRIC H.P.
1 NEWTON
1 NEWTON
1 NEWTON
“I NEWTON
iunnnud ao
od ut wt bea oo
uw on od
iunnhunu
139
247.1055 ACRES
10.7639 SQ. YRDS.
1.1960 SQ. YRDS.
0.155 SQ. IN.
2.54 CM.
720 FT.
6 FT.
3. NAU. MILES
9 INCHES
33 1/3 INCHES
0.001 INCH
32.2 Eps”
9.8 mps”
980 cm/sec”
60 RPS
120 TI RAD/SEC.
778.26 FT.LB.
1 JOULE/SEC.
10 7 ERGS/SEC.
1 DYNE-CM.
1 NEWTON-M
100,000 BTU
0.746 KW
33,000 FT-LB/MIN.
550 FT-LB/SEC.
1.34 HP
33479 BTV/HR.
424 BTU/MIN.
56.9.BTU/MIN.
0.986 U.S. HP
100,000 DYNE
102 GRAMS
0.102 KG.
0.2248 LB.140
1 DYNE
1 DYNE
1 DYNE
1 GRAM
1 GRAM
1 GRAM
‘10 KGX9.81
1KG
1KG
1KG
TTB:
1LB
1 1B
1LB
1 GAL/MIN.
1 ACRE
1 ARE
1 CENTARE
1 HECTARE
1SQ. ROD
1 BARREL
1 GANTA
1GANTA .
1 CAVAN"
1 KEROSENE CAN
1 N=m/sec.
" 1 JOULE/SEC.
soe PU eRe eae
u
0.0001 NEWTON
0.0102 GRAMS
2.205 X 10° LB.
9.81 X 10-3 NEWTON
980.67 DYNE
2.205 X 10° LB.
98.1 NEWTON
9.806 NEWTON
9.81 X 10° DYNE
2.205 LB
4,448 NEWTON
4,45 X 10° DYNE
453.6 GRAMS
0.4536 KG.
0.063 LITER/SEC.
0.4047 HECTARE
100 SQ.M.
1SQ. METER
2.471 ACRES
25.29 SQ.M.
4 BAGS CEMENT
8 CHUPAS
3 LITERS
25 GANTAS
5 GALLONS
1 watt
wat
RECTANGLE:
bh
Wee
= 2ie
SECTOR OF A CIRCLE:
a = 1/2RC = 1/2R° 90
ELLIPSE: A = [lab142
ACI
Act
Acst
AGC
AOA
AON
ASTM
Amp
Apt
Arch
Approx
Air Cond.
Asph
Auto
Outta ee ee eee ae
ABBREVIATION
American Concrete Institute
Access Panel
Actual
Acoustic
Addition
Adhesive
Aggregate
Associated General Contractors of America Inc.
Activity On Arrow
Alternating Current
Activity On Node
Aluminum
American Society for Testing and Materials
Ampere
Anchor Bolt
Apartment
Approved
Architectural
Approximate
Air Condition
Area :
Asbestos
Asphalt
At
Automatic
Avenue
Average
Balcony
Basement
Bathroom
Bathtub
Beam
Ctoc
Cube Feet Per Minute
. Construction
Corrugate
Cycle Per Minute
Cycle Per Second
Cubic Foot
Cast Concrete
Cast Iron
Center
Center Line, Closset
Ctoc
Circlewo gee oer yey SEP PRe
Circuit Breaker
Circumference
Clear
Coated
Combination
Common
Composition
Concrete
Conduit
Continue
‘Contractor
‘Courses
‘Cross Section
Cubic Inch
Cubic Yard
Cubic Meter
Damper
Damp Proofing
Bee pepe Rea age FE
145
Electric
Elevation
Enamel
Entrance
Equal
Equipment
Estimate
Excavate
Existing
Exterior
Fabricate
Feet
Feet Board Measure
’ Finish
Fahrenheit Temperature
Gage
Glass, Grade Line146
14
GPM = Gallon Per Minute ipa . ,!
H = Hall = . Program Evaluation Review Technique
Hdw = Hardware P/LE = Pounds Per Linear Foot
Hd = Head PSF = Pounds Per Square Foot
Hp = Horsepower PSI = Pounds Per Square Inch
Hr = Hour Reqd = Required
‘Htr = Heater Rd = Road
Ht = Hetght RPM = Revolution Per Minute
Hor = Horizontal Sec = Second
HB = Hose Bib aoe = Square Foot
HW = How Water Sain = Square Inch
Hse = House Square = = —-100 Square Feet of Area /
Cc = Hundred Sq. M. = Square Meter |
Qin = Inch 4 Sq. Yd = Square Yard |
Int = Interior Std = Standard |
I = Iron f Bs = Truck
Jt & Joint | TPH = Tons Per Hour
Kw = Kilowatt } Wa = Width
Kwh = Kilowatt Hour { cone = Standard Ridge Tile
Kip (10001b) = K wie = Week
Kit = Kitchen {Wk = Per Week
Ki = Rilo Wt. /Pe. = Weight Per Piece
Lbs = Pounds Yd. = Yard
Lam = Laminate > Yr. = Year
Ltr = Liter t
Lin. Ft. = Linear Foot j
M = 1,000 {
M = Meter 4
Me = Cubic Meter i
/M. Ht. = Per Meter Height }
Max = Maximum
MFBM = 1,000 Feet Board Measure of Lumber
Min = Minute
MM = Millimeter
MPH = Miles Per Hour
Op = Operation
Pes. /Kgs. * Pieces Per Kilograms #|
Pes. /Sq.M. = Pieces Per Square Miles #|