You are on page 1of 8

SME Annual Meeting

March 1-3, 1999, Denver, Colorado

Preprint 99-130
CASE STUDY OF EFFORTS TO REDUCE COSTS AND INCREASE
PRODUCTION AT A MID-SIZED INTERNATIONAL MINING COMPANY

J. C. Harrison
M. V. T. Da Silva
Eldorado Gold Corp.
Nogales, AZ

ABSTRACT 5. Shaft hoisting capacity increase.


Eldorado Gold Corporation of Vancouver, 6. Increase process capacity in the recovery
B.C. owns and operates three gold mines. The plant.
São Bento underground gold mine in Minas
Gerais State, Brazil produced 105,907 ounces in The organization structure at São Bento was
1997. The La Colorada and La Trinidad open pit, reviewed. It was decided to incorporate
heap leach mines in Mexico produced over 83,000 maintenance into the operational areas and to
ounces in 1997. With a deteriorating gold market integrate the human resources department. As
plaguing the industry throughout 1997 Eldorado well the number of departments was reduced from
had to take critical measures at each mine to 6 to 4, bringing a new management style that was
enhance gold production while lowering cash more participative.
operating costs. Each mine had its own unique
problems to confront. This case study will discuss Mining , Diamond Drilling and Productivity
three distinct courses of action taken at the three
mine sites. Since the São Bento Mine began operating
over 1,000,000 ounces of gold have been
extracted using manual shrinkage and cut and fill
THE SÃO BENTO MINE stoping methods. The manual stoping costs were
The São Bento mine is located in Minas US$ 20.00/tonne and the safety record was very
Gerais State of Brazil and is ranked fourth in poor. The mine needed to implement a more cost
Brazil in annual gold production. Gold effective mining method. Eldorado undertook a
production in 1997 came to 105,907 ounces. With detailed engineering review of the underground
operating costs as high as $360/oz in 1996 the operation. It was determined that a Long hole
mine set out to increase gold production while Sub-level mining method using mechanized
reducing costs. To achieve these goals mining equipment had the potential of increasing
management would have to make major changes production and lowering mining costs. A total of
within the operations. The following challenges 15 million dollars were allocated to converting
were established and completed in 1997 and 1998: São Bento to a mechanized Long Hole Sub-Level
mining operation. This program included the
1. Modernize and mechanize the underground purchase of mechanized underground equipment,
operations. extensive diamond drilling and development
2. Implement a geological exploration that will required to sustain the increased mine production
increase the reserve base and improve ore rate. To take advantage of the geological
grade continuity. structure, development headings are excavated on
3. Improve safety conditions at the mine and dip with the ore vein. This increases ground
plant. stability and reduces dilution. The new Sub-level
4. Restructure the management organization. mining method consists of removing ore in 30-ft

1 Copyright © 1999 by SME


lifts and 60-ft panels along strike. A rib pillar is conditions, that resulted in significant cost
left between each stope panel. The ore panels are reduction of US$5.00/oz.
extracted from the extremities of the ore zone
retreating towards the center. Back-filling is The following equipment was purchased for the
conducted after the stope panel has been mucked mechanization of the São Bento Mine:
out. This new mining method has resulted in
reducing the stoping costs to US$ 10.00/tonne. 1. 9-LHD Scooptrams, 6-3 yard, 1-6.5 yard, 1-
Increased production targets have been achieved 3.5 yard, and 1-2.2 yard.
and the safety record has improved. 2. 4-Hydraulic Single Boom Jumbos.
3. 5-Long hole drill machines, 4-Pneumatic, 1-
A comprehensive understanding of the ore Hydraulic.
reserve was required for the new mining method. 4. 3-16 tonne trucks.
In 1997 Eldorado purchased a hydraulic diamond 5. Various support equipment and vehicles.
drill machine as well as contracting a Brazilian
company to undertake an extensive drill program. The actual equipment productivity is:
This program provided 17,000 meters of drill
information, giving a better understanding of 1. LHD's produce 65,000 tonnes/month.
geological behavior of the ore deposit and 2. Development Jumbos produce 45,000 meters
allowing accurate mine planning and drilled/month.
development. The current geological resources 3. Long hole drill machines produce 20,000
are 5.2 M Tons @ 10.95 g Au/tonne and meters drilled/month.
geological reserves are 3.3 M Tons @ 9.01 g 4. Haul trucks produce 40,000 tonnes/month.
Au/tonne.
The planned production for next year is 47,000
The mining method involved the utilization of tonnes ore/month and 500 m development/month.
expensive and technically complicated machinery.
To ensure success São Bento undertook an Safety
extensive training program. Rather than rely on
salesman and engineering technicians for the Improving safety and working conditions at
training, São Bento contracted miners from São Bento was also an important objective for
Canada who made their living from operating Eldorado Gold Corp. The São Bento Mine
these machines. The success of this program can implemented the following changes to ensure a
be demonstrated by the fact that currently most of safe and productive mine:
São Bento underground operations achieve a
productivity rate equal to that of mines in North 1. Implementation of the “Neil George” 5 point
America. safety system.
2. Establishment of a stench gas warning
Mechanization of the underground resulted in system.
a reduction of the required labor force and an 3. Construction of underground safety stations
increase in the skills and responsibility of the throughout the mine that are supplied with
miner. This had the intrinsic value of allowing potable water and pressurized air in case of an
São Bento the opportunity to increase salaries, emergency or underground fire.
establish a bonus system and raise the 4. Personal self rescuer masks are carried by all
commitment, dedication and productivity of the underground workers.
work force. Underground productivity has 5. New miners lamps with 50% more light
increased from 2.5 tonnes/man/shift to 5.5 intensity output, high intensity hand held spot
tonnes/man/shift. The ore production has lights.
increased from 30,000 tpm to 47,000 tpm. The 6. Improved personnel safety equipment, which
underground labor force has been reduced from included work clothes equipped with
900 workers and 300 contractors in January 1996 reflective strips, steel toe boots, ear
to a total of 670 workers and 120 contractors at protection, belts with back support protection
the end of 1998. Operation mine costs have been 7. Aluminum scaling bars were introduced to
reduced from $35 per tonne to $25 per tonne. The allow higher back areas to be scaled more
Mine reviewed significant contracts with drilling efficiently.
materials and explosives, negotiating terms and

2 Copyright © 1999 by SME


A bus and train transport system was
established to transport workers to their work 1. Increase production to 43,000 tonnes per
areas both on surface and underground. This month.
reduced worker fatigue and increased productivity 2. Reduce operating cost by $20 per ounce.
by maximizing the available work time at the 3. Improve safety.
work areas. These changes helped São Bento to 4. Improve environmental conditions.
achieve the best safety record in the mine history
and reduced the LTIF (lost time accident A budget of $12.9 million was allocated for
frequency) to less than 10% of the level previous the expansion from 32,000 tonnes per month to
to the changes. 43,000 tonnes. This sum of money would be
required to install a third autoclave and a fourth
In 1998, São Bento Mine made an expansion bio-oxidation reactor. After thorough testing and
of the ventilation main system of underground examination it was determined that by increasing
workings. The investment included the acquisition the oxidation capacity by 34% the installation of
of two axial fans, with a nominal rate of 65 m3/s the third autoclave would not be necessary.
of air and a static pressure of 18 in Hg. The total Operating pressures for the two autoclave vessels
investment in the new ventilation system was were increased from 1,600 Kpa to 1,700 Kpa and
US330,000.00. The actual volume of air is 176 the additional oxidation capacity was achieved.
m3/s, which means an increment of 120% of fresh Minor changes down stream were needed to
air to underground workings. achieve the efficiency throughout the recovery
circuit. Two pumps were added to the
Increase Shaft Hoisting Capacity classification circuit and the CIL circuit was
expanded to handle 10,000 ton/month of oxide
The São Bento Mine hoist was rated at 38,000 product from the oxidation section . A total of $3
tonnes of waste and ore per month. The shaft million dollars was spent on expansion and a
contained a double drum hoist using a 9.5 ton saving of $9.9 million was achieved. After this
capacity skip. A cage used for hoisting workers investment the Milling area reached a production
and supplies was located in the same shaft of 47,000 tpm and exceeded 10,000 ounces per
compartment. Laws require that hoisting be month. São Bento reviewed all the significant
halted while miners are moved within the contracts with suppliers and negotiated terms and
production shaft compartment. This resulted in a conditions, emphasizing partnerships that resulted
loss of productivity. A new design configuration in significant cost reductions. Major benefits were
was approved that would add an additional skip realized with the oxygen costs reducing
and double drum hoist allowing a single drum approximately US$12.00/oz.
hoist to move supplies and workers within a
separate shaft compartment. The shaft expansion SUMMARY
was completed in January 1998 and increased The actions taken at São Bento improved
production from 38,000 tons per month to underground production, lowered costs and
100,000 tons per month. The expansion was increased throughput in the plant. The main
completed for $4 million which was $1.6 million achievements were: Mining Method Change,
under budget. Purchase of Underground Equipment,
Implementation of a Bonus System, Improve
Expansion of the Recovery Plant Working Conditions, Expansion of Shaft Hoisting
Capacity, Improve Safety, Engineering and
The São Bento mine has a complex plant for Planning and Optimizing of the Plant. The most
processing and recovering gold from refractory important results are: Complete Modernization
ore. The plant consists of an autogenous mill, a and Mechanization of the mine, Participative
gravity recovery stage, flotation of sulfides Management Philosophy, Geological exploration
followed by pressure oxidation and bio-oxidation. of Lower Levels, Optimization of Safety and Plant
The original mill processed 20,000 tonnes of expansion. The Operating costs were decreased
refractory ore per month. A second bio-oxidation from $360 an ounce in 1996 to $266 in the first
reactor was installed in 1993, which increased quarter of 1997. These costs are expected to
throughput to 32,000 tonnes per month. reduce to $250 in 1998 and $235 in 1999.

Eldorado Gold set the following goals:

3 Copyright © 1999 by SME


THE LA COLORADA MINE stripping ratios their percentage of the total costs
continued to increase. It was this area that
The La Colorada Mine is located in the state of provided the single largest opportunity for cost
Sonora, Mexico 45 kilometers southeast of the reduction.
capital city of Hermosillo. The mine is a
conventional cyanide heap leach operation A Sonoran-based contractor had performed the
processing approximately 9,000 tonnes of ore mining since the beginning of operations in 1993.
daily and utilizing a Merrill-Crowe recovery As production rates increased the mine contractor
circuit. Approximately 30 % of the ore is treated continued to add equipment and build the mining
as run-of-mine and dumped directly onto pads fleet. Over a three year period they had worked
with the majority being crushed in a two-stage under one-year contracts as the size of the deposit
crushing plant to a size of -3/4". Combined ore continued to be defined. The uncertainty of future
and waste production of 10-12 million tonnes per work was reflected in higher unit pricing. After
year are mined with a fleet of Cat 992 loaders and Eldorado completed the drilling of the Gran
Cat 777/773 trucks operated by a mining Central and La Colorada deposits, a long-term
contractor. Currently the work force stands at 110 plan was prepared. The plan was used for bidding
employees. Mining, blasting and security are a more cost effective long-term contract.
performed by contractors with a combined
manpower of 125. Annual gold production has A four-year mine life contract was bid on by 5
increased steadily with 20,000 ounces produced in companies. All bidders were provided an estimate
1994, 31,000 in 1995, 47,000 in 1996 and 53,000 of the annual mining requirement including
in 1997. tonnage movements and average annual haulage
profiles. The next step was to select the three
The mine produced approximately 60,000 most qualified bidders and further refine their
ounces of gold in 1998 at a cash operating cost of estimates. For this final round, Eldorado had a
$240/ounce. This is the result of efforts in 1997 more refined plan and had asked the contractors to
and 1998 to re-design pits and reduce unit- provide a range of unit prices depending on
operating costs with the goal of being profitable at average haulage distances. On a competitive
gold prices at or slightly below $300 per ounce. basis, Eldorado’s current contractor still proved to
be the best option. Mining costs were based on
A review began in mid-1997 of all facets of total yearly metric tons mined versus haul
the operation including long range planning, distances.
current operating practices, and mine costs. Some
of the resulting changes were minor but many The La Colorada contractor had previously
resulted in significant improvements in the effort indicated a willingness to share in the risk and
to contain costs. Although no extra impetus was success of the La Colorada mining operation and
needed to proceed with these changes, the had voluntarily indexed the price per tonne they
precipitous drop in gold prices from $360/ounce charged to the gold price during the last five
in June 1997 to the $300 range in 1997 and 1998 months of 1997. Building on the concept that
added the survival instinct to these efforts. The both the company and the contractor should share
following changes were made in 1997 and 1998 to in the success or downside of the gold mining
improve productivity while reducing costs: business, a pricing table was developed for several
ranges of gold prices where the price per tonne
1. “Partnering” with the mining contractor. paid increased with increasing gold price. There
2. Reduced drilling and blasting costs. are 4 ranges starting with <$300/ounce and
3. Improved mine productivity by better ore increasing to >$375/ounce.
control.
4. Improved land use and waste dump planning. Two other factors were incorporated into this
5. Implemented changes in cost accounting and pricing table: haulage distances and projected
purchasing. annual mining rates. Haulage distances were
6. Reduced manpower indexed at 500 meter increments ranging from 0
to >2,500 meters. Finally, recognizing the
"Partnering" with the Mining Contractor relationship of economies of scale and the
contractor's overhead, the pricing table was also
Mining costs have historically been the largest indexed to variable annual production rates. This
cost component for the mine. With higher provided Eldorado the flexibility of adjusting

4 Copyright © 1999 by SME


mine plans without writing a new contract and plans. The monthly mine plan, including model-
provided the contractor with higher unit prices if predicted ore zones, is distributed at the start of
annual tonnage rates were reduced. each month and is also posted at the pit for
reference.
With a new, life of mine contract in place, a
joint review of the operating efficiencies of the To improve sampling efficiency, through-the-
contractor led to several changes that improved deck ore pipe samplers were installed on the blast
productivity. Time studies to increase hole drills. These samplers were "field-modified"
productivity led to fueling during lunch periods to to ensure a sufficient sample size. These changes
decrease the down time of equipment for fueling resulted in a reduction of manpower of three
during the shift. The mine’s engineering laborers per shift that had been previously
department improved the road and ramp designs assigned sampling responsibilities. Another
for reducing travel distances. change was to designate "no sampling" areas in
the pit to reduce the assay requirements in the lab.
Reduced Drilling & Blasting Costs Waste stripping areas are identified and marked
by ore control personnel and no samples are
Through mid-1997, blast holes were drilled to taken.
develop 5-meter high benches. Normal pattern
spacing was 4 by 4 meters in waste and 3 by 3 In the assay lab insufficient fire assay
meters in ore. Lower explosives costs were capability to assay all blast holes required the use
achieved by increasing the bench height to 10 of a cyanide-shake analysis for determining blast
meters and increasing the distance between drill hole assays. A factor was developed based on
holes. Eldorado continues to experiment but has check assays to convert this assay back to a fire
found that in most areas of the pit they are able to assay equivalent.
drill a hole spacing of 5.5 by 5.5 and even 5.5 by
6 meters without impacting blasting effectiveness. The use of factors to make critical ore-waste
determinations had been an on-going subject of
A comparison of the Eldorado’s in-house discussion and concern. For this reason, two used
blasting costs to the use of a down-the-hole fire assay units were installed in the first quarter
blasting service was made in September 1997. of 1998.
Two quotes were received and one provided
significant savings in manpower costs and Improved Land Use and New Waste Dump
blasting agents with a two-year contract. An Planning
additional benefit was the readily available
technical expertise and blast monitoring In conjunction with reducing costs in the near-
capabilities. term and in obtaining the optimum pit design, a
fresh look at the location of leach pads and waste
Improved Mine Productivity by Better Ore dumps was undertaken. In this exercise, an area
Control closer to the open pit but not permitted as a waste
dump was considered for a future waste dump.
The one area in the mine receiving a staff This area had not been permitted for waste
increase was the geology department. A chief material due to inadequate condemnation drilling
geologist and ore control technician were hired years earlier. In addition there were also concerns
primarily to improve ore control in the pit. regarding continuing rights of usage by the La
Geologists, short range mine planners and Colorada Ejido.
surveyors received training in the use of the
MEDS-system modules for ore control. Prior to A study confirmed the attractiveness of this
this change, MEDS had been used primarily for area with an estimated reduction in average
long range planning. The surveyors used a haulage distance of $0.10/tonne in 1998 and with
separate software program. a cost savings of $1,000,000. Previous
agreements with the Ejido were reviewed and
A set of procedures was developed to modified to ensure the proposed waste dump was
standardize and improve ore control procedures. acceptable. In October 1997, a permit application
The model is updated quarterly with new blast was submitted to the office of SEMARNAP, the
hole information and is used by the short-range federal environmental agency. In February 1998
planner to prepare weekly and monthly mine the permit was approved for about 1/2 of the

5 Copyright © 1999 by SME


requested surface area and dumping began THE LA TRINIDAD MINE
immediately.
The La Trinidad mine is located in the state of
Implement Changes in Cost Accounting and Sinaloa, Mexico 100 kilometers southeast of the
Purchasing port city of Mazatlan. The mine is an open pit
heap leach mining operation that processes 60,000
The completion of the 1996-1997 expansion metric tons of ore and removes 100,000 metric
provided management the opportunity to focus on tons of waste per month. In 1997 the mine
cost center analysis. Detailed cost reports produced 29,810 ounces of gold at a cash
available through the SUN systems software were operating cost of $216. The 1998 plan called for
provided to department heads and general the depletion of reserves with waste dump
foremen on a monthly basis to review total and reclamation commencing immediately upon
unit cost histories. In addition, manpower completion of mining activities. The leaching of
statistics including overtime rates and productivity ore stacked on the pad would continue well into
provided clear measures of improvement. 1999 with all reclamation work to be completed
Overtime rates were reduced 60% by changing the by the end of 1999. The key points under
work schedules and by focusing on personnel consideration were:
requirements for individual assignments.
1. Balance production cash flow with
Purchasing procedures were strengthened and reclamation and operating costs.
provided the framework and discipline for 2. Reduce manpower requirements in
obtaining multiple quotations for services and incremental steps to avoid large severance
products. A centralized mine warehouse was also payments.
constructed and staffed to improve receiving and 3. Perform waste dump and pit reclamation
routine ordering practices. before the end of 1999.
4. Dispose of mine assets to assist in cash flow
Reduced Manpower requirements.
5. Reduce 1999 land occupation payments.
In mid-1997 manpower levels at the mine 6. Intensify mine contractor’s participation in
were assessed and a plan and implementation community relations’ activities.
schedule for phase reductions were developed.
The added social and statutory costs per employee Balance Production Cash Flow with Costs
are substantial and the effective cost to the
company for each employee is nearly three times The La Trinidad ore reserves were depleted by
the direct wage. Beyond the higher direct costs of the end of August 1998. The mine would
having excess employees, there is often an continue leaching the stacked ore throughout 1998
associated lower level of productivity. and the first half of 1999. The mine scheduled
2,000 ounces of gold production in the final four
Over a four-month period in 1997, the months of 1998. An additional 1,618 ounces of
permanent work force was reduced by nearly gold would be required in 1999 to reduce
30%. recoverable pad inventory to zero. By
accelerating the mine reclamation activities in
order to reduce costs, apply cost savings measures
SUMMARY throughout the mine and benefiting from the sale
of assets a balance in costs with income could be
The La Colorada mine was successful at achieved.
reducing costs and increasing production by
overhauling the mining operations. The success Reduction in Manpower
resulting from these changes can be seen in the
increased production and the decreases in costs The mine had a workforce of 23 professional
achieved in 1998. staff members and 85 laborers. Labor laws in
Mexico require a severance payment of three
months salary plus 20 days of pay per month for
each year of service. Careful planning was
required to reduce the workforce in stages so that
mine cash flow from gold production could pay

6 Copyright © 1999 by SME


for the reduction in workforce. It was decided March of 1997. This land was part of an
that a total of 14 professional staff members and exploration rental agreement. A payment of
55 laborers would be released between September $55,625 dollars was paid in December of each
and December 1998. Further reductions before year. The local communities were informed in
July of 1999 would reduce the workforce to 4 October 1998 that EESA would not renew the
professional staff members and 29 laborers. The exploration rental agreement. The local villages
29 laborers consisted of 12 security employees would be notified of the cancellation of the
and 7 camp laborers with the remaining assigned “temporary occupation” agreement before the end
to plant operations or reclamation. of 1999.

Contractor’s Support of the Local Communities


Waste Dump and Pit Reclamation
The La Trinidad mine contractor is the same
A total of $58,892 was budgeted for pit and contractor used at the La Colorada mine.
waste dump reclamation between September and Eldorado has always worked closely with the
December 1998. The contractor agreed to leave local communities and expects the mine
several pieces of heavy equipment behind to contractor to participate in community relations’
accelerate the waste dump and pit reclamation. activities. The contractor’s representative
The monthly cost of $14,649 fit in well with the attended local community meetings and met with
cash flow from pit production. The rainy season community leaders when concerns related to the
begins in late June and ends in early November. contractor were presented to Eldorado. It was
The lack of moisture during the dry months makes considered an important part of the mining
re-vegetation almost impossible. By performing operation to have the mine contractor support the
the waste dump reclamation during late 1998 it local communities. The La Trinidad contractor
would not be necessary to perform additional was responsible for road repairs, village road dust
work in 1999. suppressant, repairs to recreational facilities and
improvements in the community. During the
Disposal of Mine Assets transition from a fully operational mine to a mine
in closure the local communities felt apprehension
Once mine production ended a complete audit concerning the departure of personnel and mining
of disposable mine assets was prepared. The equipment. The contractor assured the
original cost for obtaining the mine assets came to communities that equipment would remain on the
3.3 million dollars. A schedule was prepared that property to assist in reclamation and community
outlined which assets could be sold and when improvements. The close relationship between
those assets would be available. Eldorado the company, contractor and community helped to
assigned their chief administrator the ease the tension felt by the villagers during the
responsibility of locating reliable parties that reduction of workforce and transitional period.
would be interested in purchasing some or all of
the mine assets. Within 45 days of completion of
mining activities bids were received for the SUMMARY
purchase of the crushing and conveying
equipment. The disposal of mine assets based on Though reclamation work continues at La
an equipment availability schedule eased the cash Trinidad Eldorado is following the original plan
flow requirements throughout mine closure. laid out in 1998. The staggered reduction of
manpower, careful planning of mine reclamation
Reduction of Land Payments work, close relationship with the local
communities and the sale of assets have enhanced
The La Trinidad land package consists of over Eldorado’s effort at balancing costs with income.
23,264 hectares. Two land agreements within The goal is to finish reclamation by the end of
the 23,264 hectares were made with the local 1999 with total closure costs not to exceed the
villages. The first land rental agreement signed in income created by leaching pad inventory and
December 1995 consisted of “temporary liquidating mine assets.
occupation” of 160 hectares used for the mining
operation. A payment of $31,000 per year is
made to the local villages. A second agreement
for the land rental of 772.5 hectares was signed in

7 Copyright © 1999 by SME


REFERENCES

Faust, W.A., Hernandez, S., 1998, “Recent


Improvements at La Colorada Mine,” SME
Annual Meeting, March 9-11.

Silva, Marcus Vinicius., 1998, “Sao Bento


Expansion,” Brazilian Gold Symposium,
September.

8 Copyright © 1999 by SME

You might also like