Subcontractor Starting

Packages Starting Schedule Ending Schedule


Schedule

Passenger Terminal and center MRT


01.09.2020 28.02.2022 01.09.2020
tunnel
Passenger Terminal Left 01.09.2020 28.02.2022 01.09.2020
Passenger Terminal Right 01.09.2020 28.02.2022 01.09.2020
Multilevel Car Park 01.01.2022 30.11.2022 01.01.2022
Cargo Terminal 01.10.2020 30.12.2021 01.10.2020
Other Buildings 01.05.2021 30.06.2023 01.05.2021
Subcontractor
Ending Schedule

09.01.2022

03.01.2022
03.01.2022
03.12.2022
21.12.2021
29.06.2023