NO % COMPLETE TASK NAME DURATION START FINISH

1 LIFTER
75% VENDOR 4 DAYS 11/28/2018 12/3/2018
0% PO 1 DAY 12/4/2018 12/4/2018
0% ICOMING PART (ESTIMATION) 30 DAYS 12/5/2018 1/2/2019
0% DELIVERY 1 DAY 1/3/2019 1/3/2019

2 Mezanine rack dan SPR rack


75% VENDOR 4 DAYS 11/28/2018 12/3/2018
0% PO 1 DAY 12/4/2018 12/4/2018
0% ICOMING PART (ESTIMATION) 60 DAYS 12/5/2018 1/30/2019
0% DELIVERY 1 DAY 1/31/2019 1/31/2019
ACTUAL START ACTUAL FINISH