Item Quantity Method Output Plant Labour Duration Reference
(days) BQ NO.2 – DEMOLITIO N AND RECTIFICAT ION WORKS
Demolition Demolish including foundation base, remove all debris
Works away from site, make good all defects (fill measured separately). 176m - Monsoon Drain 3.4 hr/m Back hoe 4 labours 19 days Appendix 198m - Chain Link Fencing 3.4 hr/m Dump track 4 labours 21 days 2(a) Bill 2 – Dismantle including foundation base, remove all debris Demolition away from site, make good all defects (fill measured separately). 1 NO - Main Gates Back hoe 3 labours 1 day Dump truck
Rectification Hack off and remove surplus spoil from site to
Works Contractor’s own dump. 90m2 - Concrete floor slab 0.4hr/ m2 Concrete 5 labours 1 day Appendix 20m2 - Concrete floor surface 0.4hr/ m2 breaker/Ha 1 day 2(b) 10m2 - Floor tile 8hr/ m2 cker 2 days Bill 2 – 1365m2 - Wall tile 1.2hr/ m2 Air 41 day Rectificatio 1481m2 - Aluminium foil 1.1hr/ m2 compressor 41 day n works 54m2 - Composite timber louvre panel 4.8hr/ m2 7 day 700m2 - Ceiling finishes 3.5hr/ m2 61 day
Dismantle and remove surplus soil from site to
Contractor’s own dump. 7 NO - Door frame 0.4hr/no Jack 2 labours 1 day 7 NO - Door leaf 0.6hr/no hammer 1 day