Item Quantity   Method Output Plant Labour Duration Reference

(days)
BQ NO.2 –
DEMOLITIO
N AND
RECTIFICAT
ION WORKS

Demolition Demolish including foundation base, remove all debris


Works away from site, make good all defects (fill measured
separately).
176m - Monsoon Drain 3.4 hr/m Back hoe 4 labours 19 days Appendix
198m - Chain Link Fencing 3.4 hr/m Dump track 4 labours 21 days 2(a)
Bill 2 –
Dismantle including foundation base, remove all debris Demolition
away from site, make good all defects (fill measured
separately).
1 NO - Main Gates Back hoe 3 labours 1 day
Dump truck

Rectification Hack off and remove surplus spoil from site to


Works Contractor’s own dump.
90m2 - Concrete floor slab 0.4hr/ m2 Concrete 5 labours 1 day Appendix
20m2 - Concrete floor surface 0.4hr/ m2 breaker/Ha 1 day 2(b)
10m2 - Floor tile 8hr/ m2 cker 2 days Bill 2 –
1365m2 - Wall tile 1.2hr/ m2 Air 41 day Rectificatio
1481m2 - Aluminium foil 1.1hr/ m2 compressor 41 day n works
54m2 - Composite timber louvre panel 4.8hr/ m2 7 day
700m2 - Ceiling finishes 3.5hr/ m2 61 day

Dismantle and remove surplus soil from site to


Contractor’s own dump.
7 NO - Door frame 0.4hr/no Jack 2 labours 1 day
7 NO - Door leaf 0.6hr/no hammer 1 day