Professional Documents
Culture Documents
STRUCTURES
The purpose of this method is to reinforce the shear capacity of the soils and
also to reduce settlement by “Reinforcing” the soil.
The randomness of the inclusions allow for significantly longer stress paths to
dissipate the stresses.
This was originally considered for the underpinning of the Leaning Tower of
Pisa in Italy. However, a different procedure was employed which was a novel
application of soil mechanics and soil deformations.
UNDERPINNING OF STRUCTURES-
Insitu Stabilization
In cases where headroom or interior clearances are
available, Insitu Stabilization will be a an alternative
procedure that can be deployed.
This pier supports an LRT bridge crossing across the San Juan River
with a total span of sixty (60) meters. It is supported on six (6) 1500
mm diameter bored piles designed to extend down to 17 meters or
socketed into bedrock at least 2.0 meters based on design
requirements. The structure started to settle during the erection of the
superstructure when the dead load reached about 700 metric tons.
Total settlement was about 42 mm when the erection was halted at a
dead load of about 1600 metric tons.
The pier was designed to carry a maximum total load of about 2100
metric tons (DL + LL).
The settlements were alarming as the pier was supported on bored piling
that is supposed to be socketed at least 2000 mm into bedrock. This
initial settlement of 36mm caused concern and was continuing
progressively until loading and other construction activities were halted.
By that time, a total of 45.7mm maximum settlement had already
resulted. Fig. 1 shows the settlement profile.
The erection subcontractor for the Precast Concrete Box Girder segments
specified a maximum short-term settlement of 30mm and a total
maximum long-term settlement of 45mm.
Clearly, the recorded initial settlements have already actually violated
these values and the Box Girders have to be raised by jacking in order to
level the Girders.
The as installed set up was investigated by drilling at the
center of the Bored Piles at all 6 locations.
Pile Pile Depth Gap/Sock Remarks
No. Toe of et
Bedrock This required continuous drilling into hardened concrete
Inadequate
BP-1 15.11 15.12 .01 Gap Socket of the bored pile using Diamond Coring Bits.
Depth
Inadequate
BP-2 15.11 15.12 .01 Gap Socket The results indicated that not only were the Bored piles
Depth
Inadequate
not even socketed into bedrock but also the tip of the
BP-3 15.00 (14.76)* -.24 Socket bored piles rested on about 8 to 6 inches of cuttings even
(Socket) Depth
Inadequate after the initial settlements have occurred.
BP-4 15.09 (14.76)* -.24 Socket
(Socket) Depth
Inadequate Gaps at the tip of the bored piles were detected through
BP-5 15.02 14.4 -.62 Socket
(Socket) Depth the boring and sampling procedures.
Inadequate
BP-6 14.99 14.4 -.62 Socket
(Socket) Depth This is consistent with the Recorded Settlements of the
Deck Girders.
Table 1. Tabulated Values of Bored Pile Lengths and computed gap
between Pile Toe and Bedrock.
*From Linear Interpolation. The Soil/Bedrock interface inferred from two
A decision was therefore made to Grout the bottom of the
Borehole records BH-1 and BH-2. Drilling done after significant
settlements were detected.
bored piles using high pressure jetting to remove the soft
clays and cuttings and replace this with Concrete grout.
1st Flag - Settlement was observed and recorded after installation of the Girders
2nd Flag – Installation of Deck was halted and settlements even out.
3rd Flag - Girders were again reinstalled and further settlements occurred.
4th Flag - Soil Exploration and coring through Girders started.
5th Flag - Jet Grouting Started. Further observations did not reveal any additional settlements after
Remediation
Final Solution of Underpinning by Jet Grouting
The remediation layout is as shown in plan.
BOREDPILE
VERY SOFT
CLAY/CUTTINGS
82mm 112mm
WEATHERED
BEDROCK
UNDERPINNING OF STRUCTURES – The Remediated LRT PIER
JET
GROUTED
PILES
BORED
PILES
DOWELS
GROUTED
2.0M INTO
BEDROCK
UNDERPINNING OF STRUCTURES
UNDERPINNING OF STRUCTURES IN LOW HEADROOM
INTERIOR APPLICATIONS