Professional Documents
Culture Documents
DETAILED ESTIMATES
CLEARING:
Quantity Computation :
Area (L x W) : 15 m x 45 m : 675.00 sq.m.
Total : 675.00 sq.m.
Labor Computation :
Capability : 48 sq.m. / man-day
Using 4 Laborer :
No. of days required : 675.00 sq.m.
= 3.52 days
4 ( 48 ) sq.m. / man-day
say = 4.00 days
LAY-OUT (STAKING)
Quantity Computation :
150 pcs. 2 x 3 x 10 Coco or Lawaan lumber = 750 bd.ft
Labor Computation :
Capability : 100 bd.ft. / man-day
Using 2 Carpenter :
No. of days required : 750.00 bd.ft
= 3.75 day
2 ( 100 ) bd.ft. / man-day
say = 3.00 day
DIRECT COST
A. Materials
750.00 - bd.ft - Coco or Lawaan Lumber, 40 - 2" x 2" x 12' @ 30.00 /bd.ft. - P 22,500.00
120.00 - m - Trapal @ 62.00 /m - P 7,440.00
1.00 - kg - Nylon # 30 @ 350.00 /kg - P 350.00
3.00 - kg - CW Nails # 3 @ 80.00 /kg - P 240.00
Material Cost - P 30,530.00
B. Labor
2 Carpenter x 3.00 day @ 600.00 / day - P 3,600.00
2 Laborers x 4.00 day @ 500.00 / day - P 4,000.00
Labor Cost - P 7,600.00
Quantity Computation :
Column Form : 130 pcs PLYWOOD (8'x4'x1/4") @ 400.00 /pc - P 52,000.00
1340 pcs COCO LUMBER (2"x2"x10') @ 15.00 /pc - P 20,100.00
Beam Form : 102 pcs PLYWOOD (8'x4'x1/4") @ 400.00 /pc - P 40,800.00
888 pcs COCO LUMBER (2"x2"x10') @ 15.00 /pc - P 13,320.00
Concrete Slab Form 89 pcs PLYWOOD (8'x4'x1/4") @ 400.00 /pc - P 35,600.00
Septic Vault : 6.00 pcs PLYWOOD (8'x4'x1/4") @ 400.00 /pc - P 2,400.00
#3 Common Wire Nails 50 kg @ 90.00 /kg - P 4,500.00
#1 Common Wire Nails 40 kg @ 90.00 /kg - P 3,600.00
Scaffolding Rental 20 set @ 300.00 /kg - P 60,000.00
DIRECT COST
A. Material Cost
- Total Material Cost P 232,320.00
Material Cost - P 232,320.00
MATERIAL COST - P 232,320.00
TOTAL ITEM COST - P 232,320.00
Unit Cost P 232,320.00 / lot
Quantity Computation :
Footing 1 : 3.00 x 3.00 x 1.90 x 2.00 = 34.20 cu.m.
Footing 2 : 3.20 x 3.20 x 1.90 x 1.00 = 19.46 cu.m.
Footing 3 : 2.60 x 2.60 x 1.90 x 6.00 = 77.06 cu.m.
Footing 4 : 1.90 x 1.90 x 1.90 x 9.00 = 61.73 cu.m.
Footing 5 : 2.10 x 2.10 x 1.90 x 4.00 = 33.52 cu.m.
Footing 6 : 2.25 x 2.25 x 1.90 x 4.00 = 38.48 cu.m.
Catch Basin 0.60 x 0.60 x 0.60 x 12.00 = 2.59 cu.m.
Septic Vault : 4.00 x 1.50 x 1.80 x 2.00 = 21.60 cu.m.
Total Volume = 96.18 cu.m.
Backfill :
Footing 1 : 3.00 x 3.00 x 1.40 x 2.00 = 25.20 cu.m.
Footing 2 : 3.20 x 3.20 x 1.40 x 1.00 = 14.34 cu.m.
Footing 3 : 2.60 x 2.60 x 1.40 x 6.00 = 56.78 cu.m.
Footing 4 : 1.90 x 1.90 x 1.40 x 9.00 = 45.49 cu.m.
Footing 5 : 2.10 x 2.10 x 1.40 x 4.00 = 24.70 cu.m.
Footing 6 : 2.25 x 2.25 x 1.40 x 4.00 = 28.35 cu.m.
Floor Slab : 35.00 x 8.00 x 0.10 = 28.00 cu.m.
Total Volume = 81.05 cu.m.
1. EXCAVATION
Capability : 1.50 cu.m./man-day
Using 6 Laborers :
No. of days required : 96.18 cu.m.
= 10.69 days
6 ( 1.50 ) cu.m./man-day
say = 11.00 days
2. BACKFILL
Capability : 3.00 cu.m./man-day
Using 6 Laborers :
No. of days required : 81.05 cu.m.
= 4.50 days
6 ( 3.00 ) cu.m./man-day
say = 5.00 days
DIRECT COST
A. Labor
6 Laborers x 5.00 days @ 500.00 / day - P 15,000.00
6 Laborers x 11.00 days @ 500.00 / day - P 33,000.00
Labor Cost - P 48,000.00
MATERIAL COST - P -
LABOR COST - P 48,000.00
TOTAL ITEM COST - P 48,000.00
Unit Cost P 270.84 / cu.m.
Quantity Computation
Floor Slab : 36.00 x 20.00 x 0.12 = 86.40 cu.m.
Slab : 36.00 x 9.00 x 0.12 x 2 = 77.76 cu.m.
Beam 1 : 0.40 x 0.20 x 42.8 = 3.42 cu.m.
Beam 2 : 0.40 x 0.30 x 58.6 = 7.03 cu.m.
Beam 3 : 0.40 x 0.30 x 97.65 = 11.72 cu.m.
Beam 4 : 0.40 x 0.20 x 160.84 = 12.87 cu.m.
Wall Footing : 0.40 x 0.20 x 160.84 = 12.87 cu.m.
Footing 1 : 3.00 x 3.00 x 0.45 x 2 = 8.10 cu.m.
Footing 2 : 3.20 x 3.20 x 0.45 x 1 = 4.61 cu.m.
Footing 3 : 2.60 x 2.60 x 0.45 x 6 = 18.25 cu.m.
Footing 4 : 1.90 x 1.90 x 0.3 x 9 = 9.75 cu.m.
Footing 5 : 2.10 x 2.10 x 0.3 x 4 = 5.29 cu.m.
Footing 6 : 2.25 x 2.25 x 0.3 x 4 = 6.08 cu.m.
Column : 0.35 x 0.35 x 9.00 x 26 = 28.67 cu.m.
Septic Vault : 4.00 x 1.50 x 0.1 x 2 = 1.20 cu.m.
Total Volume = 344.01 cu.m.
Material Requirement
Cement : 344.01 x 9 /cu.m. = 3,096.07 bags say 3,097.00 bags
Sand : 344.01 x 0.5 /cu.m. = 172.00 cu.m. say 173.00 cu.m.
Gravel : 445.58 x 1.0 /cu.m. = 445.58 cu.m. say 446.00 cu.m.
Labor Requirement
A. - Fabrication, placing & dismantling of forms & scaffoldings
Crew : 5 - Carpenters & 5 - Laborers
Capability : 4.00 cu.m. / day
No. of days : 344.01 cu.m.
= 22 days say 22 days
16.00 cu.m./day
B. - Concreting
Crew : 2.00 - Masons & 8 - Laborers
Capability : : 3.50 cu.m. / day
No. of days : : 344.01 cu.m.
= 49.14 days say 50 days
7.00 cu.m./day
DIRECT COST
A. Materials
3,097.00 bags Portland Cement Type 1 @ 290.00 /bag - P 898,130.00
446.00 cu.m. Screened Gravel 3/4" @ 2,240.00 /cu.m. - P 999,040.00
173.00 cu.m. Washed Sand @ 1,000.00 /cu.m. - P 173,000.00
35.00 bags Waterproofing Cement - Sahara @ 50.00 /cu.m. - P 1,750.00
63.00 shts. Ordinary Plywood, 4' x 8' x 1/4" @ 400.00 /sht. - P 25,200.00
896.00 bd.ft. Coco or Lawaan Lumber, 100 pcs 2" x 3" x 12' @ 30.00 /bd.ft. - P 26,880.00
3,550.00 bd.ft. Coco or Lawaan Lumber, 100 pcs 2" x 2" x 12' @ 30.00 /bd.ft. - P 106,500.00
10.00 kgs. CW Nails # 1½" @ 90.00 /kl - P 900.00
15.00 kgs. CW Nails # 2½" @ 90.00 /kl - P 1,350.00
40.00 kgs. CW Nails # 4" @ 90.00 /kl - P 3,600.00
Material Cost - P 2,236,350.00
B. Labor
5 Carpenters x 13.000 days @ 600.00 / day - P 39,000.00
2 Masons x 50.00 days @ 600.00 / day - P 60,000.00
13 Laborers x 50.00 days @ 500.00 / day - P 325,000.00
Labor Cost - P 424,000.00
C. Equipment
1 Concrete Mixer x 50.00 days @ 1,376.00 / day - P 68,800.00
1 Concrete Vibrator x 50.00 days @ 1,195.00 / day - P 59,750.00
Labor Cost - P 128,550.00
Quantity Computation
Labor Requirement :
Capability : 50.00 kg / 1 crew
One (1) Crew Composition : 1 Steelman and 1 Laborer
Using 4 Crews :
12,449.86 kgs.
No. of days : = 62.25 days say 63.00 days
1 x 4 x 50.00 kg / 1 crew
DIRECT COST
A. Materials
295.00 length Deformed Steel Bars, 20 mm Ø x 6.0 m (Grade 60) @ 670.00 / length - P 197,650.00
321.00 length Deformed Steel Bars, 16 mm Ø x 6.0 m (Grade 60) @ 430.00 / length - P 138,030.00
840.00 length Deformed Steel Bars, 12 mm Ø x 6.0 m (Grade 40) @ 220.00 / length - P 184,800.00
1,152.00 length Deformed Steel Bars, 12 mm Ø x 6.0 m (Grade 60) @ 250.00 / length - P 288,000.00
72.00 length Stainless Steel Handrail (100mm) @ 4,955.00 / length - P 356,760.00
15.00 pcs. Stainless Steel Handrail tube (100mm) @ 825.00 / pc. - P 12,375.00
72.00 length steel @ 305.00 / length - P 21,960.00
268.00 kg G.I. Tie Wire, #16 @ 80.00 / kg. - P 21,440.00
45.00 pcs. Hacksaw Blade @ 75.00 / pc. - P 3,375.00
Material Cost - P 1,224,390.00
B. Labor
4.00 Steelmen x 63.00 days @ 600.00 / day - P 151,200.00
4.00 Laborers x 63.00 days @ 500.00 / day - P 126,000.00
Labor Cost - P 277,200.00
C. Equipment
2 Bar Bender x 63.00 days @ 1,380.00 / day - P 173,880.00
2 Bar Cutter x 63.00 days @ 2,850.00 / day - P 359,100.00
Labor Cost - P 532,980.00
Quantity Computation :
Labor Requirement :
DIRECT COST
A. Materials
12,523 pcs. CHB (4" x 8" x 16") @ 30.00 / pc. - P 375,690.00
523 bags Portland Cement Type 1 @ 290.00 / bag - P 151,670.00
44 cu.m. Washed Sand @ 1,000.00 / cu.m. - P 44,000.00
Material Cost - P 571,360.00
B. Labor
4.00 Masons x 42.00 days @ 600.00 / day - P 100,800.00
4.00 Laborers x 42.00 days @ 500.00 / day - P 84,000.00
Labor Cost - P 184,800.00
Quantity Computation :
Material Requirement :
Cement = 2,003.54 x 0.192 bags/sq.m. = 384.68 bags ; say 385.00 bags
Labor Requirement :
Using 4 Crews :
2,003.54 sq.m.
= 83.48 days say 84.00 days
No. of days : 4.00 x 6 sq.m./day
DIRECT COST
A. Materials
385.00 bags Portland Cement Type 1 @ 290.00 / bag - P 111,650.00
33.00 cu.m. Washed Sand @ 1,000.00 / cu.m. - P 33,000.00
Material Cost - P 144,650.00
B. Labor
4.00 Masons x 84.00 days @ 600.00 / day - P 201,600.00
4.00 Laborers x 84.00 days @ 500.00 / day - P 168,000.00
Labor Cost - P 369,600.00
CR Walling :
Total Perimeter : 85.90 m
Height : 1.50 m
Area : 1.5 x 85.90 = 128.85 sq.m.
CR Flooring :
Total Area : 7.00 x 3.5 x 2.00 = 49.00 sq.m.
: 1.57 x 1.57 x 7.00 = 17.23 sq.m.
Flooring :
Area : 72 sq.m = 71.70 sq.m.
Labor Requirement :
One (1) Crew : 4 - Masons & 1 - Laborer
Capabilty : 7.50 sq.m. / day
Using 4 Crews :
249.55 sq.m.
= 8.32 days say 9.00 days
No. of days : 4.00 x 7.50 sq.m./day
DIRECT COST
A. Materials
450.00 pcs Unglazed Floor Tiles, 16" x 16" @ 180.00 / pc. - P 81,000.00
1,656.00 pcs Unglazed Floor Tiles, 8" x 8" @ 90.00 / pc. - P 149,040.00
3,225.00 pcs Ceramic Wall Tiles, 8" x 8" @ 90.00 / pc. - P 290,250.00
125.00 kgs. White Cement / Tile Grout @ 75.00 / kg. - P 9,375.00
90.00 m Tile Trim @ 65.00 / length - P 5,850.00
21.50 bags Portland Cement Type 1 @ 290.00 / bag - P 6,235.00
5.00 cu.m. Washed Sand @ 1,000.00 / cu.m. - P 5,000.00
Material Cost - P 546,750.00
B. Labor
4.00 Masons x 9.00 days @ 600.00 / day - P 21,600.00
4.00 Laborers x 9.00 days @ 500.00 / day - P 18,000.00
Labor Cost - P 39,600.00
C. Equipment
4 Electrical Grinder x 9.00 days @ 400.00 / day - P 14,400.00
Labor Cost - P 14,400.00
DIRECT COST
A. Materials
2.00 units D-1: Double swing door (Glass) @ 15,000.00 / unit P 30,000.00
3.00 units D-2: Solid Core Door (Narra) @ 6,000.00 / unit P 18,000.00
27.00 units D-3: Hollow Core @ 4,000.00 / unit P 108,000.00
21.00 units D-4: PVC Hollow Panel Door, 0.8 m. x 2.10 m @ 2,000.00 / unit P 42,000.00
3.00 units W-1: Sliding Glass Window, 1.50m x 1.20m @ 3,500.00 / sq. m P 18,900.00
4.00 units W-2: Awning Glass & Fixed Glass Window, 4.70m x 2.30m @ 5,000.00 / sq. m P 20,000.00
1.00 units W-3: Sliding Glass Window, 2.0m x 0.50m @ 3,000.00 / sq. m P 3,000.00
5.00 units W-4: Sliding Glass Window, 1.0m x 0.50m @ 2,500.00 / sq. m P 6,250.00
6.00 units W-5: Awning Glass Window, 0.50m X 0.60m @ 1,500.00 / sq. m P 2,700.00
155.00 pcs. Loose Pin Hinges,4" x 4" (High Quality) @ 180.00 / pc P 27,900.00
52.00 pcs. Door Knob (High Quality) @ 900.00 / set P 46,800.00
Material Cost - P 323,550.00
B. Labor
2.00 Carpenter x 8.00 days @ 600.00 / day - P 9,600.00
2.00 Laborers x 8.00 days @ 500.00 / day - P 8,000.00
Labor Cost - P 17,600.00
Labor Requirement :
One (1) Crew Composition : 3 Carpenters and 3 Helpers
Capability : 9 Sheets / day
50 sheets
No. of days : = 5.56 days ; say 7.00 days
9 Sheets / day
DIRECT COST
A. Materials
710.00 pcs PVC ACOUSTIC GYPSUM BOARD (2'x4' ; 603mm x 1212mm x 9mm) @ 160.00 / pc 113,600.00
Material Cost - P 113,600.00
B. Labor
3.00 Carpenter x 7.00 days @ 600.00 / day - P 12,600.00
3.00 Laborers x 7.00 days @ 500.00 / day - 10,500.00
Labor Cost - P 23,100.00
C. Equipment
1 Electrical Grinder x 7.00 days @ 400.00 / day - P 2,800.00
1 Electrical Drill x 10.00 days @ 400.00 / day - P 4,000.00
Labor Cost - P 6,800.00
DIRECT COST
A. Materials
Plumbing Fixtures Water Closet w/ complete accessories, Wall Hung type Lavatory, soap
19.00 sets holder, tissue holder @ 6,500.00 / set P 123,500.00
26.00 pcs. Stainless Floor Drain, 4" x 4" @ 280.00 / pc. P 7,280.00
Sewer Line
14.00 length PVC Pipe, 4" dia. X 3.0 m., S-1000 @ 795.00 / length P 11,130.00
4.00 length PVC Pipe, 2" dia. X 3.0m, S-1000 @ 290.00 / length P 1,160.00
24.00 pcs. PVC Elbow, 4" dia. X 90 deg. Bend @ 70.00 / pc. P 1,680.00
56.00 pcs. PVC Elbow, 4" dia. X 45 deg. Bend @ 70.00 / pc. P 3,920.00
11.00 length PVC Pipe, 4" dia. Coupling @ 95.00 /pc. P 1,045.00
20.00 pcs. PVC Wye Reducer, 4"Ø x 2"Ø dia. X 45 deg. Bend @ 80.00 / pc. P 1,600.00
56.00 pcs. PVC Wye, 4" x 4" dia. @ 95.00 / pc. P 5,320.00
20.00 pcs. PVC P-Trap, 2" dia. @ 65.00 / pc. P 1,300.00
17.00 pcs. PVC Clean Out Plug, 4" dia. @ 75.00 / pc. P 1,275.00
Water Line
60.00 length PPR Pipe, 1/2" x 3.0m @ 380.00 / length P 22,800.00
2.00 pc. Gate Valve, 1/2" dia. @ 255.00 / pc. P 510.00
54.00 pcs. PPR Elbow, 1/2" dia. @ 25.00 / pc. P 1,350.00
75.00 pcs. PPR Tee, 1/2" dia. @ 25.00 / pc. P 1,875.00
1.00 pcs. Water Pump (1.0HP) @ 12,800.00 / pc. P 12,800.00
20.00 pcs. Teflon Tape, 3/4" (big) @ 20.00 / pc. P 400.00
18.00 pints Solvent Cement @ 95.00 / pint P 1,710.00
2.00 pc Water Meter @ 1,800.00 / pc P 3,600.00
1.00 pc Water Storage Tank 5000L capacity @ 85,000.00 / pc P 85,000.00
Material Cost - P 289,255.00
B. Labor
1.00 Plumber x 20.00 days @ 600.00 / day - P 12,000.00
2.00 Laborers x 20.00 days @ 500.00 / day - P 20,000.00
Labor Cost - P 32,000.00
DIRECT COST
A. Materials
53.00 pcs. Utility Boxes PVC, 2" x 4" @ 35.00 / pc. P 1,855.00
18.00 pcs. Junction Boxes PVC, 4" x 4" @ 35.00 / pc. P 630.00
100.00 length RSC Pipe, 3/4" dia. @ 420.00 / length P 42,000.00
30.00 pcs. Screw Insulator @ 35.00 / pc. P 1,050.00
16.00 boxes THHN / THWN Stranded Co. Wire, 2.0 mm² @ 3,500.00 / box P 56,000.00
20.00 boxes THHN / THWN Stranded Co. Wire, 5.5 mm² @ 3,500.00 / box P 70,000.00
10.00 boxes THHN / THWN Stranded Co. Wire, 8.0 mm² @ 3,500.00 / box P 35,000.00
100.00 pcs. PVC Clamp @ 7.00 / pc. P 700.00
70.00 pcs. Electrical Tape (Big) @ 35.00 / pc. P 2,450.00
87.00 pcs. Incadescent Lamp, 20 watts @ 250.00 / pc. P 21,750.00
2.00 pcs. Florecent Lamp, 40 watts @ 200.00 / pc. P 400.00
40.00 pcs. 1-Gang Switch, Flush Type @ 135.00 / pc. P 5,400.00
15.00 pcs. 2-Gang Switch, Flush Type @ 150.00 / pc. P 2,250.00
50.00 pcs. Duplex Convenience Outlet, Flush Type @ 95.00 / pc. P 4,750.00
2.00 pcs. Entrance Cap, 3/4" dia. @ 85.00 / pc. P 170.00
1.00 pc. Panel Board (6-Holes) branded @ 625.00 / pc. P 625.00
1.00 pc. Panel Board (18-Holes) branded @ 625.00 / pc. P 625.00
15.00 pc. Circuit Breaker 15 A @ 350.00 / pc. P 5,250.00
2.00 pc. Circuit Breaker 30 A @ 350.00 / pc. P 700.00
1.00 pc. Circuit Breaker 60 A @ 350.00 / pc. P 350.00
1.00 pc. Circuit Breaker 120 A @ 350.00 / pc. P 350.00
45.00 m Service Drop Wire, 8.0 @ 35.00 / m. P 1,575.00
2.00 unit KWHR meter w/ Base @ 4,500.00 / unit P 9,000.00
1.00 sets Manual Pull Switch @ 1,250.00 / set P 1,250.00
Material Cost - P 264,130.00
B. Labor
1.00 Electrician x 10.00 days @ 600.00 / day - P 6,000.00
2.00 Electrician x 10.00 days @ 500.00 / day - P 10,000.00
Labor Cost - P 16,000.00
DIRECT COST
A. Materials
45.00 gals Concrete Putty @ 370.00 / gal. P 16,650.00
45.00 gals Glazing Putty @ 665.00 / gal. P 29,925.00
20.00 gals Concrete Neutralizer @ 250.00 / gal. P 5,000.00
20.00 gals Body Filler @ 590.00 / gal. P 11,800.00
15.00 gals Flat Latex White @ 490.00 / gal. P 7,350.00
25.00 gals Semi-Gloss Latex White @ 645.00 / gal. P 16,125.00
10.00 gals Flat Enamel White @ 540.00 / gal. P 5,400.00
15.00 gals Paint Thinner @ 285.00 / gal. P 4,275.00
10.00 pcs Paint Brush 4" @ 75.00 / pc. P 750.00
10.00 pcs Paint Brush 2" @ 30.00 / pc. P 300.00
5.00 sets Paint Roller 7" with Pan @ 95.00 / set P 475.00
3.00 pc Lettering Brush 1" @ 30.00 / pc. P 90.00
3.00 pc Lettering Brush 1/2" @ 30.00 / pc. P 90.00
40.00 pcs Sandpaper #100 @ 30.00 / pc. P 1,200.00
25.00 pcs Sandpaper #200 @ 35.00 / pc. P 875.00
Material Cost - P 100,305.00
B. Labor
4.00 Painter x 15.00 days @ 600.00 / day - P 36,000.00
4.00 Helper x 15.00 days @ 500.00 / day - P 30,000.00
Labor Cost - P 66,000.00
DIRECT COST
A. Materials
3.00 pcs Fully Auto Washing Mashine @ 12,995.00 / pc P 38,985.00
2.00 pcs beverage cooler @ 21,950.00 / pc P 43,900.00
1.00 pcs refrigerator @ 18,999.00 / pc P 18,999.00
1.00 pcs freezer @ 16,650.00 / pc P 16,650.00
7.00 pcs dining set @ 5,499.00 / pc P 38,493.00
1.00 pcs sofa set @ 23,500.00 / pc P 23,500.00
6.00 pcs Queen size Bedroom Set @ 8,500.00 / pc P 51,000.00
16.00 pcs Single-bedroom set @ 5,000.00 / pc P 80,000.00
1.00 pcs 2hp Aircondition with Inverter @ 46,495.00 / pc P 46,495.00
6.00 pcs 1hp Aircondition with Inverter @ 31,295.00 / pc P 187,770.00
Material Cost - P 545,792.00
B. Labor
4.00 Helper x 15.00 days @ 500.00 / day - P 30,000.00
Labor Cost - P 30,000.00
Err:509
-
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509
2.00 5.00 2.00 -
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
TOTAL Err:509 Err:509 Err:509
0.00 -
0.00 BSPMC Chairman Barangay Captain Municipal Mayor
Page 11
Page 12
Page 13
Page 14
DESIGN OF TWO-STOREY PENSION HOUSE
BILL OF QUANTITIES
RATE PER
No. of
DAY/
ITEM DESCRIPTION QUANTITY UNIT Crew/ Total
UNIT
Labor
COST
A. DIRECT COST
Item 100 - CLEARING AND LAY-OUT 675.00 sq.m.
A. Materials
Coco or Lawaan Lumber, 40 - 2" x 2" x 12' 750.00 bd.ft 30.00 22,500.00
Trapal 120.00 m 62.00 7,440.00
Nylon # 30 1.00 kg 350.00 350.00
CW Nails # 3 3.00 kg 80.00 240.00
Sub-Total 30,530.00
B. Labor
Carpenter 3.00 day 2.00 600.00 3,600.00
Laborers 4.00 day 2.00 500.00 4,000.00
Sub-Total 7,600.00
TOTAL FOR CLEARING AND LAY-OUT 38,130.00
A. DIRECT COST
II. FORMS AND SCAFFOLDING Quantity 1 lot
A. Material Cost
PLYWOOD (8'x4'x1/4") 233.00 pc 400.00 93,200.00
COCO LUMBER (2"x2"x10') 1,633.00 pc 15.00 24,495.00
#3 Common Wire Nails 35.00 kg 90.00 3,150.00
#1 Common Wire Nails 25.00 kg 90.00 2,250.00
Scaffolding Rental 15.00 set 400.00 60,000.00
Sub-Total 183,095.00
TOTAL FOR FORMS AND SCAFFOLDING 183,095.00
DESIGN OF TWO-STOREY PENSION Total Sub-Project Cost : #NAME? LABOR No. of days Ave. rate per day
Name of Sub-Project:
HOUSE
Direct Cost : #NAME? MALE
SKILLED
Physical Target : 100.00 sq.m. Indirect Cost : #NAME? FEMALE
Region : CARAGA Region Date Started : 9-Mar-15 MALE
UNSKILLED
Province : Dinagat Island Target Completion Date : 7-May-15 FEMALE
Municipality : Libjo : MALE
TOTAL
Barangay: : Plaridel Mode of Implementation : CFA / LSG FEMALE
I. To be filled up by Deputy Area Coordinator
WEIGHT PHYSICAL
Item No. DESCRIPTION (%) TARGET
DURATION
QTY UNIT AMOUNT Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8
#NAME? Planned #NAME? #NAME?
100 CLEARING AND LAY-OUT 675.00 sq.m. 38,130.00
0.00% Actual 0.00%
#NAME? Planned #NAME? #NAME? #NAME?
103 STRUCTURE EXCAVATION 53.18 cu.m. 48,000.00
0.00% Actual 0.00%
#NAME? Planned #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME? #NAME?
0.00% Actual 0.00%
#NAME? Planned #NAME? #NAME? #NAME? #NAME? #NAME?
405 STRUCTURAL CONCRETE 344.01 cu.m. 2,788,900.00
0.00% Actual 0.00%
#NAME? Planned #NAME? #NAME? #NAME? #NAME? #NAME?
404 REINFORCING STEEL 12,449.86 kgs. 2,034,570.00
0.00% Actual 0.00%
#NAME? Planned #NAME? #NAME? #NAME? #NAME?
506 MASONRY WORKS 1,001.77 sq.m. 756,160.00
0.00% Actual 0.00%
#NAME? Planned #NAME? #NAME?
1027 CEMENT PLASTER FINISH 2,003.54 sq.m. 514,250.00
0.00% Actual 0.00%
#NAME? Planned #NAME? #NAME?
1018 TILEWORKS 249.55 sq.m. 600,750.00
0.00% Actual 0.00%
#NAME? Planned #NAME? #NAME? #NAME?
1003 CEILING WORKS 420.00 pcs 143,500.00
0.00% Actual 0.00%
#NAME? Planned #NAME? #NAME?
1010 DOORS AND WINDOWS 1.00 lot 345,300.00
0.00% Actual 0.00%
#NAME? Planned #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME? #NAME?
0.00% Actual 0.00%
Err:509 Planned Err:509 Err:509
1012 PLUMBING WORKS 1.00 lot Err:509
0.00% Actual 0.00%
#NAME? Planned #NAME? #NAME?
1100 ELECTRICAL WORKS 1.00 lot 279,505.00
0.00% Actual 0.00%
Err:509 Planned Err:509 Err:509 Err:509
0 ACCESSORIES & OTHERS 1.00 lot Err:509
0.00% Actual 0.00%
#NAME? Planned #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME? #NAME?
0.00% Actual 0.00%
#NAME? Planned #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME? #NAME?
0.00% Actual 0.00%
#NAME? Planned #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME? #NAME?
0.00% Actual 0.00%
#NAME? Planned
TOTAL #NAME?
0.00% Actual
PERIODIC #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? Err:509 #NAME?
% PROGRESS (PLANNED)
CUMMULATIVE #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? Err:509 #NAME?
PHYSICAL
PERIODIC
% PROGRESS (ACTUAL)
CUMMULATIVE
0
- PIT Chairman MIT Chairman
Approved by:
Reviewed and Checked by:
0 JOVENAL L. BERNAT
BSPMC Chairman 0 Regional Community Infrastructure Specialist
ENHANCED PLANNED COMMUNITY PROCUREMENT PACKAGING
Date Prepared : November 19, 2014 Name of Proposed Sub-Project: DESIGN OF TWO-STOREY PENSION HOUSE
Barangay : Plaridel Total Estimated Cost (Cash): #NAME?
Municipality : Libjo Sub-project Duration: 60 calendar days
Province : DINAGAT ISLANDS
PROPOSED IMPLEMENTATION
Estimated Cost Involved and Schedule of Delivery SCHEDULE
PACKAGES
PROC
REMARKS
PACKAGE ITEMS QTY UNIT UNIT COST TOTAL 1st Tranche 2nd Tranche SUB-TOTAL TOTAL MONTH
METHOD
KC-NCDDP
KC-NCDDP GRANT LCC Cash KC-NCDDP GRANT LCC Cash LCC Cash 1 2 3
GRANT
2-Gang Switch, Flush Type 15.00 pcs. 150.00 2,250.00 2,250.00 2,250.00 - 2,250.00
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Body Filler 20.00 gals 590.00 11,800.00 11,800.00 11,800.00 - 11,800.00
Unglazed Floor Tiles, 16" x 16" 450.00 pcs 180.00 81,000.00 81,000.00 81,000.00 - 81,000.00
Ceramic Wall Tiles, 8" x 8" 3225.00 pcs 90.00 290,250.00 290,250.00 290,250.00 - 290,250.00
Florecent Lamp, 40 watts 2.00 pcs. 200.00 400.00 400.00 400.00 - 400.00
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Circuit Breaker 60 A 1.00 pc. 350.00 350.00 350.00 350.00 - 350.00
Concrete Putty 45.00 gals 370.00 16,650.00 16,650.00 16,650.00 - 16,650.00
Concrete Neutralizer 20.00 gals 250.00 5,000.00 5,000.00 5,000.00 - 5,000.00
CW Nails # 1½" Err:509 kgs. 90.00 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
CW Nails # 2½" Err:509 kgs. 90.00 Err:509 Err:509 Err:509 - Err:509
CW Nails # 3 Err:509 kg 80.00 Err:509 Err:509 Err:509 - Err:509
CW Nails # 4" Err:509 kgs. 90.00 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Deformed Steel Bars, 12 mm Ø x 6.0 m (Grade 60) 1152.00 length 250.00 288,000.00 288,000.00 288,000.00 - 288,000.00
Deformed Steel Bars, 16 mm Ø x 6.0 m (Grade 60) 321.00 length 430.00 138,030.00 138,030.00 138,030.00 - 138,030.00
Deformed Steel Bars, 20 mm Ø x 6.0 m (Grade 60) 295.00 length 670.00 197,650.00 197,650.00 197,650.00 - 197,650.00
Door Knob (High Quality) 52.00 pcs. 900.00 46,800.00 46,800.00 46,800.00 - 46,800.00
Duplex Convenience Outlet, Flush Type 50.00 pcs. 95.00 4,750.00 4,750.00 4,750.00 - 4,750.00
Electrical Tape (Big) 70.00 pcs. 35.00 2,450.00 2,450.00 2,450.00 - 2,450.00
Entrance Cap, 3/4" dia. 2.00 pcs. 85.00 170.00 170.00 170.00 - 170.00
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Water Pump (1.0HP) 1.00 pcs. 12800.00 12,800.00 12,800.00 12,800.00 - 12,800.00
Flat Enamel White 10.00 gals 540.00 5,400.00 5,400.00 5,400.00 - 5,400.00
Flat Latex White 15.00 gals 490.00 7,350.00 7,350.00 7,350.00 - 7,350.00
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
G.I. Tie Wire, #16 268.00 kg 80.00 21,440.00 21,440.00 21,440.00 - 21,440.00
Gate Valve, 1/2" dia. 2.00 pc. 255.00 510.00 510.00 510.00 - 510.00
Glazing Putty 45.00 gals 665.00 29,925.00 29,925.00 29,925.00 - 29,925.00
Hacksaw Blade 45.00 pcs. 75.00 3,375.00 3,375.00 3,375.00 - 3,375.00
Junction Boxes PVC, 4" x 4" 18.00 pcs. 35.00 630.00 630.00 630.00 - 630.00
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
LSG
Service Drop Wire, 8.0 45.00 m 35.00 1,575.00 1,575.00 1,575.00 - 1,575.00
KWHR meter w/ Base 2.00 unit 4,500.00 9,000.00 9,000.00 9,000.00 - 9,000.00
Sub-Total 10,575.00 10,575.00 - - - 10,575.00 - 10,575.00
PACKAGE 7 - FURNITURE MATERIALS
D-1: Double swing door (Glass) 2.00 units 15,000.00 30,000.00 30,000.00 30,000.00 - 30,000.00
D-2: Solid Core Door (Narra) 3.00 units 6,000.00 18,000.00 18,000.00 18,000.00 - 18,000.00
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
LSG
#NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? - #NAME?
Sub-Total #NAME? #NAME? - - - #NAME? - #NAME?
#NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
PACKAGE 13 - HANDTOOLS AND PPE
Shovel w/ handle 3.00 pcs. 453.00 1,359.00 1,359.00 1,359.00 - 1,359.00
Crow Bar 1.00 pcs. 253.00 253.00 253.00 253.00 - 253.00
Concrete Pail 10.00 pcs. 153.00 1,530.00 1,530.00 1,530.00 - 1,530.00
Safety Belt 2.00 pcs. 900.00 1,800.00 1,800.00 1,800.00 - 1,800.00
Rubber Boots 10.00 pcs. 403.00 4,030.00 4,030.00 4,030.00 - 4,030.00
Hard Hat 10.00 pcs. 210.00 2,100.00 2,100.00 2,100.00 - 2,100.00
Hand Glove 10.00 pcs. 78.00 780.00 780.00 780.00 - 780.00
Construction Mask 10.00 pcs. 20.00 200.00 200.00 200.00 - 200.00
#NAME? 12,052.00 12,052.00 - - - 12,052.00 - 12,052.00
#NAME? #NAME? #NAME? #NAME? - #NAME?
#NAME? #NAME? #NAME? #NAME? - #NAME?
#NAME? #NAME? #NAME? #NAME? #NAME? - #NAME?
Total Indirect Cost (Cash) #NAME? #NAME? #NAME? #NAME? - #NAME? #NAME? #NAME?
GRAND TOTAL (Cash) #NAME? #NAME? #NAME? #NAME? - #NAME? #NAME? #NAME?
850,000.00
Workshop output of: Checked and Reviewed by: Err:509 765,000.00 Approved by: Noted by:
#NAME? #NAME?
0 0
Procurement Team Head - 0 BSPMC
KALAHI-CIDSS NATIONAL COMMUNITY DRIVEN DEVELOPMENT PROJECT
Name of Proposed Community Project : CONSTRUCTION OF ONE UNIT DAY CARE CENTER
Barangay : PLARIDEL Municipality : LIBJO
Total Estimated Cost: 877,341.00
Community Project Duration: 60 CALENDAR DAYS Proposed Project Implement
Type of Plan: ( ) Initial ( ) Actual
Unit of
Package No. Items to be Procured Quantity Unit Cost
Measure
Package No. 1 AGGREGATES & FILLING MATERIALS
1 Err:509 Err:509 Err:509 Err:509
2 Err:509 Err:509 Err:509 Err:509
3 Screened Gravel 3/4" 446.00 cu.m. 2240.00
4 Washed Sand 255.00 cu.m. 1000.00
Sub-Total
Package No. 2 CONCRETE HOLLOW BLOCKS
1 CHB (4" x 8" x 16") 12523.00 pcs. 30.00
Sub-Total
Package No. 3 CONSTRUCTION MATERIALS
1 2-Gang Switch, Flush Type 15.00 pcs. 150.00
2 Err:509 Err:509 Err:509 Err:509
3 Err:509 Err:509 Err:509 Err:509
4 Err:509 Err:509 Err:509 Err:509
5 Body Filler 20.00 gals 590.00
6 Unglazed Floor Tiles, 16" x 16" 450.00 pcs 180.00
7 Ceramic Wall Tiles, 8" x 8" 3225.00 pcs 90.00
8 Florecent Lamp, 40 watts 2.00 pcs. 200.00
9 Err:509 Err:509 Err:509 Err:509
10 Err:509 Err:509 Err:509 Err:509
11 Circuit Breaker 60 A 1.00 pc. 350.00
12 Concrete Putty 45.00 gals 370.00
13 Concrete Neutralizer 20.00 gals 250.00
14 CW Nails # 1½" Err:509 kgs. 90.00
15 Err:509 Err:509 Err:509 Err:509
16 CW Nails # 2½" Err:509 kgs. 90.00
17 CW Nails # 3 Err:509 kg 80.00
18 CW Nails # 4" Err:509 kgs. 90.00
19 Err:509 Err:509 Err:509 Err:509
20 Deformed Steel Bars, 12 mm Ø x 6.0 m (Grade 1152.00 length 250.00
21 Deformed Steel Bars, 16 mm Ø x 6.0 m (Grade 321.00 length 430.00
22 Deformed Steel Bars, 20 mm Ø x 6.0 m (Grade 295.00 length 670.00
23 Door Knob (High Quality) 52.00 pcs. 900.00
24 Duplex Convenience Outlet, Flush Type 50.00 pcs. 95.00
25 Electrical Tape (Big) 70.00 pcs. 35.00
26 Entrance Cap, 3/4" dia. 2.00 pcs. 85.00
27 Err:509 Err:509 Err:509 Err:509
28 Water Pump (1.0HP) 1.00 pcs. 12800.00
29 Flat Enamel White 10.00 gals 540.00
30 Flat Latex White 15.00 gals 490.00
31 Err:509 Err:509 Err:509 Err:509
32 Err:509 Err:509 Err:509 Err:509
33 G.I. Tie Wire, #16 268.00 kg 80.00
34 Gate Valve, 1/2" dia. 2.00 pc. 255.00
35 Glazing Putty 45.00 gals 665.00
36 Hacksaw Blade 45.00 pcs. 75.00
37 Junction Boxes PVC, 4" x 4" 18.00 pcs. 35.00
38 Err:509 Err:509 Err:509 Err:509
39 Err:509 Err:509 Err:509 Err:509
40 Err:509 Err:509 Err:509 Err:509
41 Err:509 Err:509 Err:509 Err:509
42 Err:509 Err:509 Err:509 Err:509
43 Lettering Brush 1" 3.00 pc 30.00
44 Lettering Brush 1/2" 3.00 pc 30.00
45 Loose Pin Hinges,4" x 4" (High Quality) 155.00 pcs. 180.00
46 Err:509 Err:509 Err:509 Err:509
47 Err:509 Err:509 Err:509 Err:509
48 Err:509 Err:509 Err:509 Err:509
49 Nylon # 30 1.00 kg 350.00
50 Ordinary Plywood, 4' x 8' x 1/4" 63.00 shts. 400.00
51 Paint Brush 2" 10.00 pcs 30.00
52 Paint Brush 4" 10.00 pcs 75.00
53 Paint Roller 7" with Pan 5.00 sets 95.00
54 Paint Thinner 15.00 gals 285.00
55 Panel Board (18-Holes) branded 1.00 pc. 625.00
56 Portland Cement Type 1 4026.50 bags 290.00
57 PVC Clamp 100.00 pcs. 7.00
58 PVC Clean Out Plug, 4" dia. 17.00 pcs. 75.00
59 Err:509 Err:509 Err:509 Err:509
60 PPR Elbow, 1/2" dia. 54.00 pcs. 25.00
61 Err:509 Err:509 Err:509 Err:509
62 Err:509 Err:509 Err:509 Err:509
63 Err:509 Err:509 Err:509 Err:509
64 PVC Elbow, 4" dia. X 45 deg. Bend 56.00 pcs. 70.00
65 PVC Elbow, 4" dia. X 90 deg. Bend 24.00 pcs. 70.00
66 Err:509 Err:509 Err:509 Err:509
67 PPR Pipe, 1/2" x 3.0m 60.00 length 380.00
68 PVC Pipe, 2" dia. X 3.0m, S-1000 4.00 length 290.00
69 Err:509 Err:509 Err:509 Err:509
70 PVC Pipe, 4" dia. X 3.0 m., S-1000 14.00 length 795.00
71 PVC P-Trap, 2" dia. 20.00 pcs. 65.00
72 Err:509 Err:509 Err:509 Err:509
73 PPR Tee, 1/2" dia. 75.00 pcs. 25.00
74 Err:509 Err:509 Err:509 Err:509
75 PVC Wye Reducer, 4"Ø x 2"Ø dia. X 45 deg. Be 20.00 pcs. 80.00
76 PVC Wye, 4" x 4" dia. 56.00 pcs. 95.00
77 Err:509 Err:509 Err:509 Err:509
78 Err:509 Err:509 Err:509 Err:509
79 RSC Pipe, 3/4" dia. 100.00 length 420.00
80 Sandpaper #100 40.00 pcs 30.00
81 Sandpaper #200 25.00 pcs 35.00
82 Screw Insulator 30.00 pcs. 35.00
83 Semi-Gloss Latex White 25.00 gals 645.00
84 Err:509 Err:509 Err:509 Err:509
85 Solvent Cement 1.00 pints 95.00
86 Stainless Floor Drain, 4" x 4" 26.00 pcs. 280.00
87 Teflon Tape, 3/4" (big) 20.00 pcs. 20.00
88 THHN / THWN Stranded Co. Wire, 5.5 mm² 20.00 boxes 3500.00
89 Err:509 Err:509 Err:509 Err:509
90 Tile Trim 90.00 m 65.00
91 Utility Boxes PVC, 2" x 4" 53.00 pcs. 35.00
Water Closet w/ complete accessories, Wall
92 19.00 sets 6500.00
Hung type Lavatory, soap holder, tissue holder
93 White Cement / Tile Grout 125.00 kgs. 75.00
Sub-Total
Package No. 4 ROOFING MATERIAS
PVC ACOUSTIC GYPSUM BOARD (2'x4' ;
1 710 pcs 160
603mm x 1212mm x 9mm)
2 Err:509 Err:509 Err:509 Err:509
Err:509
Err:509
Err:509
T PLAN (CPP)
Err:509
Err:509 Local
Shopping for Feb. 4-6,2015
999,040.00 Goods
255,000.00
Err:509
2,250.00
Err:509
Err:509
Err:509
11,800.00
81,000.00
290,250.00
400.00
Err:509
Err:509
350.00
16,650.00
5,000.00
Err:509
Err:509
Err:509
Err:509
Local Shopping of Goods
Err:509
Err:509
288,000.00
138,030.00
197,650.00
46,800.00
4,750.00
2,450.00
170.00
Err:509
12,800.00
5,400.00
7,350.00
Err:509
Err:509
21,440.00
510.00
29,925.00
3,375.00
630.00
Err:509
Err:509
Err:509
Err:509
Err:509
90.00
Local Shopping of Goods
90.00
27,900.00
Err:509
Err:509
Err:509 Feb. 4-6,2015
350.00
25,200.00
300.00
750.00
475.00
4,275.00
625.00
###
700.00
1,275.00
Err:509
1,350.00
Err:509
Err:509
Err:509
3,920.00
1,680.00
Err:509
22,800.00
1,160.00
Err:509
Local Shopping for Goods
11,130.00
1,300.00
Err:509
1,875.00
Err:509
1,600.00
5,320.00
Err:509
Err:509
42,000.00
1,200.00
875.00
1,050.00
16,125.00
Err:509
95.00
7,280.00
400.00
70,000.00
Err:509
5,850.00
1,855.00
123,500.00
9,375.00
Err:509
113,600.00
Local Shopping for Goods
Err:509
Err:509
Feb. 4-6,2015
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
22,500.00
26,880.00
106,500.00
Err:509
Err:509
Local Shopping for Goods
Err:509
Err:509
Err:509
Err:509
Feb. 4-6,2015
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
1,575.00
LSG 5th-6th week
9,000.00
10,575.00
30,000.00
oods
18,000.00
Err:509
Err:509
Err:509
Err:509
10,500.00
Local
20,000.00 Shopping for 5th -6th week
Goods
Err:509
Err:509
Err:509
LSG 5th -6th week
Err:509
1,359.00
253.00
1,530.00
1,800.00 Local
Shopping for Feb. 4-6,2015
4,030.00 Goods
2,100.00
780.00
200.00
12,052.00
Err:509
Approved by:
BSPMC Chairperson
(Name and Signature)
S
Barangay Sta. Ines Municipality San Luis Province: Agusan del Sur Region: Caraga
caraga
A. GENERAL INFORMATION
Name of proposed sub-project: Construction of One (1) Unit -Two (2) Classroom Elementary School Building
Category: Public Goods X Enterprise Human Resource Dev't.
B. TECHNICAL DESCRIPTION
Physical target: sq.m 129.22 Cost parameter: sq.m / 11.287.10
Person/s who assisted in the preparation of techical proposal: DAC, Municiapal Engr. .&
l.m 273.50
Service Provider
Proposed scope of works to be undertaken:
333.33
333.33
Construction of 1unit 2cl HS Building, 164 sq.m floor area
333.33
333.33
Manpower requirement / sources: (skilled) Carpenter, Mason, Steelman, Laborer
Equipment requirement / sources: None
Other component included in the proposal (e.g. trainings)
Procurement Method/s to be adopted:
Local Shopping for Goods and CFA
C. FINANCIAL ECONOMIC ASPECT
Total Estimated Cost : #REF!
Cost Sharing Arrangement: Direct Cost Indirect Cost Total % total
Grant Amount #REF! #REF! #REF! #REF!
LCC: BLGU #REF! #REF! #REF! #REF!
Community #REF! #REF! #REF! #REF!
MLGU #REF! #REF! #REF! #REF!
sub-total #REF! #REF! #REF! #REF!
Total LCC Cash #REF! #REF! #REF!
Total LCC In-kind #REF! #REF! #REF!
D. SAFEGUARD CONCERNS
Any displacement or relocation of community members during implementation? Yes No x
Acquisition of proposed site/location? Deed of Sale Donated x LGU Ownd others specify
Proposed site within the reservation areas? Yes No x
Necessary permit/s accomplished? (e.g ECC, CNC) Yes No EMP Only x
Mitigating measures to be undertaken for the environmental impacts of the sub-project?
E. SP SUSTAINABILITY
Is there an existing O&M group or still to be organized?
Is the community willing to pay for Tariff and by How much?
Other sources of funds for the operation and maintenance activities?
Identified capability building requirements for O&M group? O & M Training
How do we plan to maintain the completed sub-project?
Date Prepared : February 1, 2011 Name of Proposed Sub-Project : Construction of One(1) Unit Two(2) Classroom
Barangay : BALIT Total Cash (Php) : #REF!
Municipality : SAN LUIS Sub-project Duration : 80 C.D
QUANTITY
UNIT COST
PACKAGES
2'x6"x8' yakal Door jamb #REF! #REF! #REF! #REF! 35.00 #REF! #REF!
2'x6"x12' yakal Door jamb #REF! #REF! #REF! #REF! 35.00 #REF! #REF!
2"x2"x12' for studs & ceiling joist lawaan #REF! #REF! #REF! #REF! 25.00 #REF! #REF!
2"x3"x12' form lumber lawaan #REF! #REF! #REF! #REF! 25.00 #REF! #REF!
2"x2"x14' form lumber lawaan #REF! #REF! #REF! #REF! 25.00 #REF! #REF!
1"x2"x8' form lumber lawaan #REF! #REF! #REF! #REF! 25.00 #REF! #REF!
1"x1"x8' lawaan for air vent #REF! #REF! #REF! #REF! 25.00 #REF! #REF!
sub total #REF! - #REF! #REF!
1.0x2.10m Hard Panel Door (Tugas or Narra)
#REF! #REF! #REF! #REF! #REF! #REF!
INSTALLED
PACKAGE 4
#REF!
0.80 x 2.10m Flush Type Door(Narra or Tugas
#REF! #REF! #REF! #REF! #REF! #REF!
Framing)INSTALLED #REF!
sub total #REF! - - #REF!
0.60m x 15 blades jalousie glass with alluminum
#REF! #REF! #REF! - #REF!
frame (INSTALLED)
PACKAGE 5
#REF!
0.60m x 5 blades jalousie glass with alum.frame
#REF! #REF! #REF! - #REF!
(INSTALLED) #REF!
sub total #REF! - - #REF!
Colorib Longspan 0.40mm x 1.10m x 5.5m (Green) #REF! #REF! #REF! #REF! 1,694.55 #REF! #REF!
PACKAGE 6
Colorib No. 24, x 8' Pre formed Side Gutter (Green) #REF! #REF! #REF! #REF! 490.62 #REF! #REF!
Colorib No. 24, x 8' Pre formed Ridgeroll (Green) #REF! #REF! #REF! #REF! 352.67 #REF! #REF!
Colorib No. 24, x 8' Pre formed Side End Flashing #REF! #REF! #REF! #REF! 490.62 #REF! #REF!
sub total #REF! - #REF! -
Water Closet (Royal Tern or equiv.) #REF! #REF! #REF! - #REF! #REF!
Lavatory Wall Hung type w/ complete accessories #REF! #REF! #REF! - #REF!
#REF!
Stainless Tank (500 liters capacity) #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Towel Holder #REF! #REF! #REF! - #REF! #REF!
Toilet Paper Holder #REF! #REF! #REF! - #REF! #REF!
Soap Holder #REF! #REF! #REF! - #REF! #REF!
4x4 Floor strainer steel #REF! #REF! #REF! - #REF! #REF!
4"dia.x3.0m. PVC pipe #REF! #REF! #REF! - #REF! #REF!
P-Trap 2"dia. PVC #REF! #REF! #REF! - #REF! #REF!
2"dia.x3.0m. PVC pipe #REF! #REF! #REF! - #REF! #REF!
PACKAGE 7
4"dia. PVC Elbow (90* bend) #REF! #REF! #REF! - #REF! #REF!
4"dia. PVC Tee #REF! #REF! #REF! - #REF! #REF!
4"dia. Clean Out Plug #REF! #REF! #REF! - #REF! #REF!
Page 38 of 65
QUANTITY
UNIT COST
PACKAGES
PACKAGE 7
Page 39 of 65
LANNED COMMUNITY PROCUREMENT PACKAGING
TRANCHES
TOTAL
2nd Tranche 3rd Tranche SUB-TOTAL
KC Grant LCC Cash KC Grant LCC Cash KC Grant LCC Cash
- #REF! #REF!
- #REF! #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
- #REF! #REF!
#REF! - #REF!
- #REF! #REF!
- #REF! #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
2,640.00 - 2,640.00
#REF! - #REF!
#REF! - #REF!
4,275.00 - 4,275.00
- #REF! #REF!
#REF! - #REF!
102,695.00 - 102,695.00
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
- - - - #REF! #REF! #REF!
#REF! - #REF!
- - - - #REF! - #REF!
- #REF! #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
- - - - #REF! #REF! #REF!
- #REF! #REF!
- #REF! #REF!
- - - - - #REF! #REF!
- #REF! #REF!
- #REF! #REF!
- - - - - #REF! #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
- - - - #REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
Page 40 of 65
TRANCHES
TOTAL
2nd Tranche 3rd Tranche SUB-TOTAL
KC Grant LCC Cash KC Grant LCC Cash KC Grant LCC Cash
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
- - - - #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
100.00 100.00
#REF! #REF! - #REF!
#REF! - - - #REF! - #REF!
- #REF! #REF!
- #REF! #REF!
- - - - - #REF! #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! - #REF! - #REF! - #REF!
- #REF! #REF!
- #REF! #REF!
- - - - - #REF! #REF!
#REF! - #REF! - #REF! #REF! #REF!
- 40,000.00 40,000.00
4,000.00 - 4,000.00
- 3,375.00 3,375.00
72,110.00 72,110.00 - 72,110.00
- - 72,110.00 - 76,110.00 43,375.00 119,485.00
#REF! - #REF! - #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
MACRINO L. SUMAGANG
BSMPC Regional Community Infra. Engineer
Page 41 of 65
Repub
Province
DESIGN OF TWO
BILL O
RATE
PER DAY/
ITEM DESCRIPTION QUANTITY UNIT
UNIT
COST
Coco or Lawaan Lumber, 40 - 2" x 2" x 12' 750.00 bd.ft 30.00
Coco or Lawaan Lumber, 100 pcs 2" x 3" x 12' 896.00 bd.ft. 30.00
Coco or Lawaan Lumber, 100 pcs 2" x 2" x 12' 3,550.00 bd.ft. 30.00
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
P.P.E./HANDTOOLS
Shovel w/ handle 3.00 pcs. 453.00
Crow Bar 1.00 pcs. 253.00
Concrete Pail 10.00 pcs. 153.00
Safety Belt 2.00 pcs. 900.00
Rubber Boots 10.00 pcs. 403.00
Hard Hat 10.00 pcs. 210.00
Hand Glove 10.00 pcs. 78.00
Construction Mask 10.00 pcs. 20.00
Republic of the Philippines
Err:509
Err:509
Province of Surigao del Norte
Err:509
Err:509
Err:509
BILL OF QUANTITIES
COST SHARING
Total KC-NCDDP COMMUNITY BLGU MLGU
GRANT CONTRIBUTION IN-
KIND
CASH IN-KIND CASH IN-KIND
22,500.00 22,500.00
26,880.00 26,880.00
106,500.00 106,500.00
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
375,690.00 375,690.00
Err:509 Err:509
Err:509 Err:509
999,040.00 999,040.00
173,000.00 173,000.00
5,000.00 #REF! #REF!
44,000.00 44,000.00
33,000.00 33,000.00
2,250.00 2,250.00
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
11,800.00 11,800.00
81,000.00 81,000.00
290,250.00 290,250.00
400.00 400.00
Err:509 Err:509
Err:509 Err:509
350.00 350.00
16,650.00 16,650.00
5,000.00 5,000.00
900.00 900.00
Err:509 Err:509
Err:509 Err:509
1,350.00 1,350.00
Err:509 Err:509
240.00 240.00
Err:509 Err:509
3,600.00 3,600.00
Err:509 Err:509
Err:509 Err:509
288,000.00 288,000.00
138,030.00 138,030.00
197,650.00 197,650.00
46,800.00 46,800.00
4,750.00 4,750.00
2,450.00 2,450.00
170.00 170.00
Err:509 Err:509
12,800.00 12,800.00
5,400.00 5,400.00
7,350.00 7,350.00
Err:509 Err:509
Err:509 Err:509
21,440.00 21,440.00
510.00 510.00
29,925.00 29,925.00
3,375.00 3,375.00
630.00 630.00
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
90.00 90.00
90.00 90.00
27,900.00 27,900.00
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
350.00 350.00
25,200.00 25,200.00
300.00 300.00
750.00 750.00
475.00 475.00
4,275.00 4,275.00
625.00 625.00
898,130.00 898,130.00
151,670.00 151,670.00
111,650.00 111,650.00
6,235.00 6,235.00
700.00 700.00
1,275.00 1,275.00
Err:509 Err:509
1,350.00 1,350.00
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
3,920.00 3,920.00
1,680.00 1,680.00
Err:509 Err:509
22,800.00 22,800.00
1,160.00 1,160.00
Err:509 Err:509
11,130.00 11,130.00
1,300.00 1,300.00
Err:509 Err:509
1,875.00 1,875.00
Err:509 Err:509
1,600.00 1,600.00
5,320.00 5,320.00
Err:509 Err:509
Err:509 Err:509
42,000.00 42,000.00
1,200.00 1,200.00
875.00 875.00
1,050.00 1,050.00
16,125.00 16,125.00
Err:509 Err:509
95.00 95.00
7,280.00 7,280.00
400.00 400.00
70,000.00 70,000.00
Err:509 Err:509
5,850.00 5,850.00
1,855.00 1,855.00
123,500.00 123,500.00
9,375.00 9,375.00
1,575.00 1,575.00
9,000.00 9,000.00
Err:509 Err:509
30,000.00 30,000.00
18,000.00 18,000.00
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
10,500.00 10,500.00
20,000.00 20,000.00
Err:509 Err:509
113,600.00 113,600.00
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
-
1,359.00 1,359.00
253.00 253.00
1,530.00 1,530.00
1,800.00 1,800.00
4,030.00 4,030.00
2,100.00 2,100.00
780.00 780.00
200.00 200.00
PLGU TOTAL LCC TOTAL
- - 375,690.00
- Err:509 Err:509
- - Err:509
- - 999,040.00
- - 173,000.00
- #REF! #REF!
- - 44,000.00
- - 33,000.00
- - 2,250.00
- - Err:509
- - Err:509
- - Err:509
- - 11,800.00
- - 81,000.00
- - 290,250.00
- - 400.00
- - Err:509
- - Err:509
- - 350.00
- - 16,650.00
- - 5,000.00
- - 900.00
- - Err:509
- - Err:509
- - 1,350.00
- - Err:509
- - 240.00
- - Err:509
- - 3,600.00
- - Err:509
- - Err:509
- - 288,000.00
- - 138,030.00
- - 197,650.00
- - 46,800.00
- - 4,750.00
- - 2,450.00
- - 170.00
- - Err:509
- - 12,800.00
- - 5,400.00
- - 7,350.00
- - Err:509
- - Err:509
- - 21,440.00
- - 510.00
- - 29,925.00
- - 3,375.00
- - 630.00
- - Err:509
- - Err:509
- - Err:509
- - Err:509
- - Err:509
- - 90.00
- - 90.00
- - 27,900.00
- - Err:509
- - Err:509
- - Err:509
- - 350.00
- - 25,200.00
- - 300.00
- - 750.00
- - 475.00
- - 4,275.00
- - 625.00
- - 898,130.00
- - 151,670.00
- - 111,650.00
- - 6,235.00
- - 700.00
- - 1,275.00
- - Err:509
- - 1,350.00
- - Err:509
- - Err:509
- - Err:509
- - 3,920.00
- - 1,680.00
- - Err:509
- - 22,800.00
- - 1,160.00
- - Err:509
- - 11,130.00
- - 1,300.00
- - Err:509
- - 1,875.00
- - Err:509
- - 1,600.00
- - 5,320.00
- - Err:509
- - Err:509
- - 42,000.00
- - 1,200.00
- - 875.00
- - 1,050.00
- - 16,125.00
- - Err:509
- - 95.00
- - 7,280.00
- - 400.00
- - 70,000.00
- - Err:509
- - 5,850.00
- - 1,855.00
- - 123,500.00
- - 9,375.00
- - 1,575.00
- - 9,000.00
- - Err:509
- - 30,000.00
- - 18,000.00
- - Err:509
- - Err:509
- - Err:509
- - Err:509
- - 10,500.00
- - 20,000.00
- - Err:509
- - 113,600.00
- - Err:509
- - Err:509
- - Err:509
- - Err:509
- - Err:509
- - Err:509
- - Err:509
- - Err:509
- - Err:509
- - -
- - 1,359.00
- - 253.00
- - 1,530.00
- - 1,800.00
- - 4,030.00
- - 2,100.00
- - 780.00
- - 200.00
PROPOSED ONE-STOREY RESIDENTIAL BU
MONITORING CHART / WORK SCHEDULE
Legend:
Schedule
PERT-CPM
DURATION
NODE ACTIVITY
(DAYS)
A MOBILIZATION 2
B #REF! 6
C STRUCTURAL EXCAVATION 6
D FORMS AND SCAFFOLDINGS 13
E #REF! 0
F #REF! 0
G #REF! 0
H #REF! days
I #REF! 0
J CEILING WORKS 0
K #REF! 0
L #REF! 0
M #REF! 0
N #REF! 0
O ACOUSTIC ACCESSORIES 0
P DEMOBOLIZATION 2
29
EY RESIDENTIAL BUILDING
GANTT CHART
DURATION 209 CALENDAR DAYS (4 WEEKS PER MONTH)
MAY JUNE JULY AUGUST SEPTEMBER
START DURATION
CLEARING AND ### 6
FORMS AND SCA ### 13
STRUCTURE EXC ### 6
STRUCTURAL C ### 28
REINFORCING S ### 63
MASONRY WORK ### 28
CEMENT PLASTE ### 15
TILEWORKS 9/21/2020 7
CEILING WORKS
9/14/2020 6
DOORS AND WI ### 10
PLUMBING WOR ### 20
ELECTRICAL WO ### 10
PAINTING WORK
9/21/2020 20
ACCESSORIES & ### 15
###
###
OCTOBER NOVEMBER
PERT-CPM
ACTIVITY NODE PREDECESSOR
A CLEARING AND LAY-OUT A -
B STRUCTURE EXCAVATION B A
C STRUCTURAL CONCRETE C B
D REINFORCING STEEL D C
E CEMENT PLASTER FINISH E B
F MASONRY WORKS F E
G TILEWORKS G F
H CEILING WORKS H C
I DOORS AND WINDOWS I G
J PLUMBING WORKS J I
K ELECTRICAL WORKS K J
L PAINTING WORKS L K
M ACCESSORIES & OTHERS M L
TOTAL
CRITICAL PATH:
A-B-C-E-F-G-I-J-K-L = 135 DAYS
ending
4/4/2019
###
6/3/2019
###
###
###
###
###
8/3/2019
###
###
###
8/5/2019
PERT-CPM
DURATION
NODE ACTIVITY PREDECESSOR
(DAYS)
A MOBILIZATION - 2
B CLEARING AND LAY-OUT A 6
C STRUCTURAL EXCAVATION B 6
D FORMS AND SCAFFOLDINGS C 13
E REINFORCING STEEL C 63
F STRUCTURAL CONCRETE D,E,L,M 50
G CEMENT PLASTER FINISH H 42
H MASONRY WORKS F 84
I TILEWORKS J 9
J CEILING WORKS K 7
K DOORS AND WINDOWS G 8
L PLUMBING WORKS C 20
M ELECTRICAL WORKS C 10
N PAINTING WORKS J 15
O ACOUSTIC ACCESSORIES & OTHERS I,N 15
P DEMOBOLIZATION O 2
TOTAL 352
DESIGN OF A 3-STOREY SOUNDPROOF BUILDING USING FOAM BRICKS STICKER WALLPAPER
Project Title: DESIGN OF A 3-STOREY SOUNDPROOF BUILDING USING FOAM BRICKS STICKER WALLPAPER
Location: BRGY. LIPATA, SURIGAO CITY
Contractor: RJB CONSTRUCTION
Contract Amount: 1,80Err:509 S-CURVE
APRIL MAY JUNE JULY AUGUST SEP
Item no. DESCRIPTION AMOUNT W.F START FINISH DURATION wk1 wk2 wk3 wk4 wk5 wk6 wk7 wk8 wk9 wk10 wk11 wk12 wk13 wk14 wk15 wk16 wk17 wk18 wk19 wk20 wk21
100 CLEARING AND LAY-OUT 38,130.00 Err:509 WK1 WK1 1 ###
0 FORMS AND SCAFFOLDING 183,095.00 Err:509 WK3 WK5 3 Err:509 Err:509 Err:509
103 STRUCTURE EXCAVATION 48,000.00 Err:509 WK2 WK2 1 Err:509
405 STRUCTURAL CONCRETE 2,788,900.00 Err:509 WK13 WK17 5 Err:509 Err:509 Err:509 Err:509 Err:509
404 REINFORCING STEEL 2,034,570.00 Err:509 WK3 WK12 10 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 ###
506 MASONRY WORKS 756,160.00 Err:509 WK18 WK20 3 Err:509 Err:509 Err:509
1027 CEMENT PLASTER FINISH 514,250.00 Err:509 WK21 WK25 5 ###
1018 TILEWORKS 600,750.00 Err:509 WK28 WK28 1
1003 CEILING WORKS 143,500.00 Err:509 WK27 WK27 1
1010 DOORS AND WINDOWS 345,300.00 Err:509 WK26 WK27 2
1012 PLUMBING WORKS Err:509 Err:509 WK3 WK6 4 Err:509 Err:509 Err:509 Err:509
1100 ELECTRICAL WORKS 279,505.00 Err:509 WK3 WK5 3 Err:509 Err:509 Err:509
1032 PAINTING WORKS 166,305.00 Err:509 WK28 WK30 3
ACCESSORIES & OTHERS Err:509 Err:509 WK30 WK32 3
Err:509 Err:509
WEEKLY PROGRESS TOTAL (%) Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
CUMMULATIVE PROGRESS (%) Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
ACTUAL WEEKLY PROGRESS (%) 1.00% 1.00% 7.20% 6.71% 6.80% 6.00% 3.30% 2.90% 3.10% 2.90% 2.70% 2.40% 4.45% 3.87% 3.87% 4.32% 4.30% 5.23% 5.24% 5.23% 0.39%
ACTUAL CUMMULATIVE PROGRESS (%) 1.0% 2.0% 9.2% 15.9% 22.7% 28.7% 32.0% 34.9% 38.0% 40.9% 43.6% 46.0% 50.5% 54.3% 58.2% 62.5% 66.8% 72.1% 77.3% 82.5% 82.9%
Legend: S-CURVE SUBMITTED BY: JAY MARK
Schedule APPROVED BY: ENGR. ELMARIO
Actual BSCE INS
START DURATION START FINISH DURATION
CLEARING AND LAY-OU ### 6 WK1 WK1 1
FORMS AND SCAFFOLDI ### 13 WK3 WK5 3
STRUCTURE EXCAVATI ### 6 WK2 WK2 1
STRUCTURAL CONCRET ### 28 WK13 WK17 5
REINFORCING STEEL ### 63 WK3 WK12 10
MASONRY WORKS ### 15 WK18 WK20 3
CEMENT PLASTER FINIS ### 28 WK21 WK25 5
TILEWORKS 9/21/2020 7 WK28 WK28 1
CEILING WORKS 9/14/2020 6 WK27 WK27 1
DOORS AND WINDOWS ### 10 WK26 WK27 2
PLUMBING WORKS ### 20 WK3 WK6 4
ELECTRICAL WORKS ### 10 WK3 WK5 3
PAINTING WORKS 9/21/2020 20 WK28 WK30 3
ACCESSORIES & OTHER ### 15 WK30 WK32 3
247
PERT-CPM
DURATION
NODE ACTIVITY
PREDECESSOR
(DAYS)
A MOBILIZ - 2
B CLEARIN A 6
C STRUCTU B 6
D FORMS A C 13
E REINFOR C 63
F STRUCTD,E,L,M 50
G CEMENT H 42
H MASONR F 84
I TILEWO J 9
J CEILING K 7
K DOORS G 8
L PLUMBI C 20
M ELECTRI C 10
N PAINTIN J 15
O ACOUSTI I,N 15
P DEMOBOL O 2
TOTAL 352
SEPTEMBER OCTOBER NOVEMBER
wk22 wk23 wk24 wk25 wk26 wk27 wk28 wk29 wk30 wk31 wk32
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
0.50% 0.49% 0.32% 0.41% 2.00% 3.25% 5.23% 0.89% 2.47% 1.21% 0.32%
83.4% 83.9% 84.2% 84.6% 86.6% 89.9% 95.1% 96.0% 98.5% 99.7% 100.0%
AY MARK. SABUBU
ELMARIO A. PEJAN ,MBA
BSCE INSTRUCTOR