You are on page 1of 65

Republic of the Philippines

Province of Surigao del Norte

DETAILED ESTIMATES

PROJECT TITLE : DESIGN OF TWO-STOREY PENSION HOUSE


LOCATION : BRGY. LIPATA, SURIGAO CITY

Item 100 - CLEARING AND LAY-OUT


Quantity : 675.00 sq.m.

CLEARING:
Quantity Computation :
Area (L x W) : 15 m x 45 m : 675.00 sq.m.
Total : 675.00 sq.m.

Labor Computation :
Capability : 48 sq.m. / man-day
Using 4 Laborer :
No. of days required : 675.00 sq.m.
= 3.52 days
4 ( 48 ) sq.m. / man-day
say = 4.00 days

LAY-OUT (STAKING)
Quantity Computation :
150 pcs. 2 x 3 x 10 Coco or Lawaan lumber = 750 bd.ft

Labor Computation :
Capability : 100 bd.ft. / man-day
Using 2 Carpenter :
No. of days required : 750.00 bd.ft
= 3.75 day
2 ( 100 ) bd.ft. / man-day
say = 3.00 day

DIRECT COST
A. Materials
750.00 - bd.ft - Coco or Lawaan Lumber, 40 - 2" x 2" x 12' @ 30.00 /bd.ft. - P 22,500.00
120.00 - m - Trapal @ 62.00 /m - P 7,440.00
1.00 - kg - Nylon # 30 @ 350.00 /kg - P 350.00
3.00 - kg - CW Nails # 3 @ 80.00 /kg - P 240.00
Material Cost - P 30,530.00

B. Labor
2 Carpenter x 3.00 day @ 600.00 / day - P 3,600.00
2 Laborers x 4.00 day @ 500.00 / day - P 4,000.00
Labor Cost - P 7,600.00

MATERIAL COST - P 30,530.00


LABOR COST - P 7,600.00
TOTAL ITEM COST - P 38,130.00
Unit Cost P 56.49 / sq.m.

II - FORMS AND SCAFFOLDING


Quantity : 1.00 lot

Quantity Computation :
Column Form : 130 pcs PLYWOOD (8'x4'x1/4") @ 400.00 /pc - P 52,000.00
1340 pcs COCO LUMBER (2"x2"x10') @ 15.00 /pc - P 20,100.00
Beam Form : 102 pcs PLYWOOD (8'x4'x1/4") @ 400.00 /pc - P 40,800.00
888 pcs COCO LUMBER (2"x2"x10') @ 15.00 /pc - P 13,320.00
Concrete Slab Form 89 pcs PLYWOOD (8'x4'x1/4") @ 400.00 /pc - P 35,600.00
Septic Vault : 6.00 pcs PLYWOOD (8'x4'x1/4") @ 400.00 /pc - P 2,400.00
#3 Common Wire Nails 50 kg @ 90.00 /kg - P 4,500.00
#1 Common Wire Nails 40 kg @ 90.00 /kg - P 3,600.00
Scaffolding Rental 20 set @ 300.00 /kg - P 60,000.00

DIRECT COST
A. Material Cost
- Total Material Cost P 232,320.00
Material Cost - P 232,320.00
MATERIAL COST - P 232,320.00
TOTAL ITEM COST - P 232,320.00
Unit Cost P 232,320.00 / lot

ITEM 103 - STRUCTURE EXCAVATION


Quantity : 177.23 cu.m.

Quantity Computation :
Footing 1 : 3.00 x 3.00 x 1.90 x 2.00 = 34.20 cu.m.
Footing 2 : 3.20 x 3.20 x 1.90 x 1.00 = 19.46 cu.m.
Footing 3 : 2.60 x 2.60 x 1.90 x 6.00 = 77.06 cu.m.
Footing 4 : 1.90 x 1.90 x 1.90 x 9.00 = 61.73 cu.m.
Footing 5 : 2.10 x 2.10 x 1.90 x 4.00 = 33.52 cu.m.
Footing 6 : 2.25 x 2.25 x 1.90 x 4.00 = 38.48 cu.m.
Catch Basin 0.60 x 0.60 x 0.60 x 12.00 = 2.59 cu.m.
Septic Vault : 4.00 x 1.50 x 1.80 x 2.00 = 21.60 cu.m.
Total Volume = 96.18 cu.m.

Backfill :
Footing 1 : 3.00 x 3.00 x 1.40 x 2.00 = 25.20 cu.m.
Footing 2 : 3.20 x 3.20 x 1.40 x 1.00 = 14.34 cu.m.
Footing 3 : 2.60 x 2.60 x 1.40 x 6.00 = 56.78 cu.m.
Footing 4 : 1.90 x 1.90 x 1.40 x 9.00 = 45.49 cu.m.
Footing 5 : 2.10 x 2.10 x 1.40 x 4.00 = 24.70 cu.m.
Footing 6 : 2.25 x 2.25 x 1.40 x 4.00 = 28.35 cu.m.
Floor Slab : 35.00 x 8.00 x 0.10 = 28.00 cu.m.
Total Volume = 81.05 cu.m.

1. EXCAVATION
Capability : 1.50 cu.m./man-day
Using 6 Laborers :
No. of days required : 96.18 cu.m.
= 10.69 days
6 ( 1.50 ) cu.m./man-day
say = 11.00 days

2. BACKFILL
Capability : 3.00 cu.m./man-day
Using 6 Laborers :
No. of days required : 81.05 cu.m.
= 4.50 days
6 ( 3.00 ) cu.m./man-day
say = 5.00 days

DIRECT COST
A. Labor
6 Laborers x 5.00 days @ 500.00 / day - P 15,000.00
6 Laborers x 11.00 days @ 500.00 / day - P 33,000.00
Labor Cost - P 48,000.00

MATERIAL COST - P -
LABOR COST - P 48,000.00
TOTAL ITEM COST - P 48,000.00
Unit Cost P 270.84 / cu.m.

ITEM 405 - STRUCTURAL CONCRETE


Quantity : 344.01 cu.m.

Quantity Computation
Floor Slab : 36.00 x 20.00 x 0.12 = 86.40 cu.m.
Slab : 36.00 x 9.00 x 0.12 x 2 = 77.76 cu.m.
Beam 1 : 0.40 x 0.20 x 42.8 = 3.42 cu.m.
Beam 2 : 0.40 x 0.30 x 58.6 = 7.03 cu.m.
Beam 3 : 0.40 x 0.30 x 97.65 = 11.72 cu.m.
Beam 4 : 0.40 x 0.20 x 160.84 = 12.87 cu.m.
Wall Footing : 0.40 x 0.20 x 160.84 = 12.87 cu.m.
Footing 1 : 3.00 x 3.00 x 0.45 x 2 = 8.10 cu.m.
Footing 2 : 3.20 x 3.20 x 0.45 x 1 = 4.61 cu.m.
Footing 3 : 2.60 x 2.60 x 0.45 x 6 = 18.25 cu.m.
Footing 4 : 1.90 x 1.90 x 0.3 x 9 = 9.75 cu.m.
Footing 5 : 2.10 x 2.10 x 0.3 x 4 = 5.29 cu.m.
Footing 6 : 2.25 x 2.25 x 0.3 x 4 = 6.08 cu.m.
Column : 0.35 x 0.35 x 9.00 x 26 = 28.67 cu.m.
Septic Vault : 4.00 x 1.50 x 0.1 x 2 = 1.20 cu.m.
Total Volume = 344.01 cu.m.

Gravel and Gravel Bed


Floor Slab : 36.00 x 20.00 x 0.1 = 72.00 cu.m.
Footing 1 : 2.80 x 2.80 x 0.15 x 8 = 9.41 cu.m.
Footing 2 : 3.30 x 3.30 x 0.15 x 1 = 1.63 cu.m.
Footing 3 : 2.60 x 2.60 x 0.15 x 6 = 6.08 cu.m.
Footing 4 : 1.90 x 1.90 x 0.15 x 9 = 4.87 cu.m.
Footing 5 : 2.10 x 2.10 x 0.15 x 4 = 2.65 cu.m.
Footing 6 : 2.25 x 2.25 x 0.15 x 4 = 3.04 cu.m.
Wall Footing : 0.40 x 0.20 x 0.10 x 160.84 = 1.29 cu.m.
Septic Vault : 4.00 x 1.50 x 0.1 = 0.60 cu.m.
Total Volume = 101.57 cu.m.

Material Requirement
Cement : 344.01 x 9 /cu.m. = 3,096.07 bags say 3,097.00 bags
Sand : 344.01 x 0.5 /cu.m. = 172.00 cu.m. say 173.00 cu.m.
Gravel : 445.58 x 1.0 /cu.m. = 445.58 cu.m. say 446.00 cu.m.

Labor Requirement
A. - Fabrication, placing & dismantling of forms & scaffoldings
Crew : 5 - Carpenters & 5 - Laborers
Capability : 4.00 cu.m. / day
No. of days : 344.01 cu.m.
= 22 days say 22 days
16.00 cu.m./day

B. - Concreting
Crew : 2.00 - Masons & 8 - Laborers
Capability : : 3.50 cu.m. / day
No. of days : : 344.01 cu.m.
= 49.14 days say 50 days
7.00 cu.m./day

DIRECT COST
A. Materials
3,097.00 bags Portland Cement Type 1 @ 290.00 /bag - P 898,130.00
446.00 cu.m. Screened Gravel 3/4" @ 2,240.00 /cu.m. - P 999,040.00
173.00 cu.m. Washed Sand @ 1,000.00 /cu.m. - P 173,000.00
35.00 bags Waterproofing Cement - Sahara @ 50.00 /cu.m. - P 1,750.00
63.00 shts. Ordinary Plywood, 4' x 8' x 1/4" @ 400.00 /sht. - P 25,200.00
896.00 bd.ft. Coco or Lawaan Lumber, 100 pcs 2" x 3" x 12' @ 30.00 /bd.ft. - P 26,880.00
3,550.00 bd.ft. Coco or Lawaan Lumber, 100 pcs 2" x 2" x 12' @ 30.00 /bd.ft. - P 106,500.00
10.00 kgs. CW Nails # 1½" @ 90.00 /kl - P 900.00
15.00 kgs. CW Nails # 2½" @ 90.00 /kl - P 1,350.00
40.00 kgs. CW Nails # 4" @ 90.00 /kl - P 3,600.00
Material Cost - P 2,236,350.00

B. Labor
5 Carpenters x 13.000 days @ 600.00 / day - P 39,000.00
2 Masons x 50.00 days @ 600.00 / day - P 60,000.00
13 Laborers x 50.00 days @ 500.00 / day - P 325,000.00
Labor Cost - P 424,000.00

C. Equipment
1 Concrete Mixer x 50.00 days @ 1,376.00 / day - P 68,800.00
1 Concrete Vibrator x 50.00 days @ 1,195.00 / day - P 59,750.00
Labor Cost - P 128,550.00

MATERIAL COST - P 2,236,350.00


LABOR COST - P 424,000.00
EQUIPMENT COST - P 128,550.00
TOTAL ITEM COST - P 2,788,900.00
Unit Cost P 8,107.09 / cu.m.

ITEM 404 - REINFORCING STEEL


Quantity : 12,449.86 kgs.

Quantity Computation

Total No. of 12mm Ø 16mm Ø 20mm Ø #16 G.I. #16 GI Tie


Total Weight Total No. of Total Weight Total No. Total Weight RSB Total
Description 12mm Ø Weight/6m Weight/6m of 20mm Weight/6m Tie Wire Wire Total
(kg) 16mm Ø RSB (kg) Ø RSB (kg) Weight (kg)
RSB length (kg) length (kg) length (kg) Factor Weight (kg)
Footing - - 175.00 9.47 1,657.25 - - - 1,657.25 0.0215 35.63
Column 466.00 5.33 2,483.78 140.00 9.47 1,325.80 65.00 14.80 962.00 4,771.58 0.0215 102.59
Beam 441.00 5.33 2,350.53 6.00 - - 230.00 9.47 2,178.10 4,528.63 0.0215 97.37
Wall Footing 25.00 5.33 133.25 - - - - - 133.25 0.0215 2.86
Wall Partition 220.00 5.33 1,172.60 - - - - - - 1,172.60 0.0215 25.21
Floor Slab 805.00 - - - - - - - - 0.0215 -
Septic T & Catch B 35.00 5.33 186.55 - - - - - - 186.55 0.0215 4.01
Total 1,992.00 6,326.71 321.00 2,983.05 295.00 3,140.1 12,449.86 267.67

Labor Requirement :
Capability : 50.00 kg / 1 crew
One (1) Crew Composition : 1 Steelman and 1 Laborer

Using 4 Crews :
12,449.86 kgs.
No. of days : = 62.25 days say 63.00 days
1 x 4 x 50.00 kg / 1 crew

DIRECT COST
A. Materials
295.00 length Deformed Steel Bars, 20 mm Ø x 6.0 m (Grade 60) @ 670.00 / length - P 197,650.00
321.00 length Deformed Steel Bars, 16 mm Ø x 6.0 m (Grade 60) @ 430.00 / length - P 138,030.00
840.00 length Deformed Steel Bars, 12 mm Ø x 6.0 m (Grade 40) @ 220.00 / length - P 184,800.00
1,152.00 length Deformed Steel Bars, 12 mm Ø x 6.0 m (Grade 60) @ 250.00 / length - P 288,000.00
72.00 length Stainless Steel Handrail (100mm) @ 4,955.00 / length - P 356,760.00
15.00 pcs. Stainless Steel Handrail tube (100mm) @ 825.00 / pc. - P 12,375.00
72.00 length steel @ 305.00 / length - P 21,960.00
268.00 kg G.I. Tie Wire, #16 @ 80.00 / kg. - P 21,440.00
45.00 pcs. Hacksaw Blade @ 75.00 / pc. - P 3,375.00
Material Cost - P 1,224,390.00

B. Labor
4.00 Steelmen x 63.00 days @ 600.00 / day - P 151,200.00
4.00 Laborers x 63.00 days @ 500.00 / day - P 126,000.00
Labor Cost - P 277,200.00

C. Equipment
2 Bar Bender x 63.00 days @ 1,380.00 / day - P 173,880.00
2 Bar Cutter x 63.00 days @ 2,850.00 / day - P 359,100.00
Labor Cost - P 532,980.00

MATERIAL COST - P 1,224,390.00


LABOR COST - P 277,200.00
EQUIPMENT COST - P 532,980.00
TOTAL ITEM COST - P 2,034,570.00
Unit Cost P 163.42 / kgs.

ITEM 506 - MASONRY WORKS :


Quantity : 1,001.77 sq.m.

Quantity Computation :

Exterior Area = 530.92 sq.m. = 530.92 sq.m.


Interior Area = 415.05 sq.m. = 415.05 sq.m.
Septic Vault = 41.4 sq.m. = 41.40 sq.m.
Catch Basin = 14.4 sq.m. = 14.40 sq.m.
Total Gross Area 1,001.77 sq.m.

No. of 4" CHB = 1,001.77 x 12.50 pcs/sq.m. = 12,522.08 say 12,523.00


Cement = 522.92 bags say 523.00 (1:3 mix)
Sand = 43.58 cu.m. say 44.00

Labor Requirement :

Crew : 4.00 - Masons & 4 - Helpers


Capabilty : 24.00 sq.m. / day
1,001.77 sq.m.
= 41.74 days say 42.00 days
No. of days : 24.00 sq.m./day

DIRECT COST
A. Materials
12,523 pcs. CHB (4" x 8" x 16") @ 30.00 / pc. - P 375,690.00
523 bags Portland Cement Type 1 @ 290.00 / bag - P 151,670.00
44 cu.m. Washed Sand @ 1,000.00 / cu.m. - P 44,000.00
Material Cost - P 571,360.00

B. Labor
4.00 Masons x 42.00 days @ 600.00 / day - P 100,800.00
4.00 Laborers x 42.00 days @ 500.00 / day - P 84,000.00
Labor Cost - P 184,800.00

MATERIAL COST - P 571,360.00


LABOR COST - P 184,800.00
TOTAL ITEM COST - P 756,160.00
Unit Cost P 754.83 / sq.m.

ITEM 1027 - CEMENT PLASTER FINISH :


Quantity : 2,003.54 sq.m.

Quantity Computation :

Exterior Area = 530.92 sq.m. = 530.92 sq.m.


Interior Area = 415.05 sq.m. = 415.05 sq.m.
Septic Vault = 41.4 sq.m. = 41.40 sq.m.
Catch Basin = 14.4 sq.m. = 14.40 sq.m.
Total Gross Area 1,001.77 sq.m.

Net Area 2,003.54 sq.m.

Material Requirement :
Cement = 2,003.54 x 0.192 bags/sq.m. = 384.68 bags ; say 385.00 bags

Sand = 2,003.54 x 0.016 cu.m./sq.m. = 32.06 cu.m. ; say 33.00 cu.m.

Labor Requirement :

One (1) Crew : 1 - Mason & 1 - Helper


Capabilty : 6.00 sq.m. / day

Using 4 Crews :
2,003.54 sq.m.
= 83.48 days say 84.00 days
No. of days : 4.00 x 6 sq.m./day

DIRECT COST
A. Materials
385.00 bags Portland Cement Type 1 @ 290.00 / bag - P 111,650.00
33.00 cu.m. Washed Sand @ 1,000.00 / cu.m. - P 33,000.00
Material Cost - P 144,650.00

B. Labor
4.00 Masons x 84.00 days @ 600.00 / day - P 201,600.00
4.00 Laborers x 84.00 days @ 500.00 / day - P 168,000.00
Labor Cost - P 369,600.00

MATERIAL COST - P 144,650.00


LABOR COST - P 369,600.00
TOTAL ITEM COST - P 514,250.00
Unit Cost P 256.67 / sq.m.

ITEM 1018 - TILEWORKS


Quantity : 249.55 sq.m.

CR Walling :
Total Perimeter : 85.90 m
Height : 1.50 m
Area : 1.5 x 85.90 = 128.85 sq.m.

CR Flooring :
Total Area : 7.00 x 3.5 x 2.00 = 49.00 sq.m.
: 1.57 x 1.57 x 7.00 = 17.23 sq.m.

Flooring :
Area : 72 sq.m = 71.70 sq.m.

Total Area : = 249.55 sq.m.

Labor Requirement :
One (1) Crew : 4 - Masons & 1 - Laborer
Capabilty : 7.50 sq.m. / day

Using 4 Crews :
249.55 sq.m.
= 8.32 days say 9.00 days
No. of days : 4.00 x 7.50 sq.m./day

DIRECT COST
A. Materials
450.00 pcs Unglazed Floor Tiles, 16" x 16" @ 180.00 / pc. - P 81,000.00
1,656.00 pcs Unglazed Floor Tiles, 8" x 8" @ 90.00 / pc. - P 149,040.00
3,225.00 pcs Ceramic Wall Tiles, 8" x 8" @ 90.00 / pc. - P 290,250.00
125.00 kgs. White Cement / Tile Grout @ 75.00 / kg. - P 9,375.00
90.00 m Tile Trim @ 65.00 / length - P 5,850.00
21.50 bags Portland Cement Type 1 @ 290.00 / bag - P 6,235.00
5.00 cu.m. Washed Sand @ 1,000.00 / cu.m. - P 5,000.00
Material Cost - P 546,750.00

B. Labor
4.00 Masons x 9.00 days @ 600.00 / day - P 21,600.00
4.00 Laborers x 9.00 days @ 500.00 / day - P 18,000.00
Labor Cost - P 39,600.00

C. Equipment
4 Electrical Grinder x 9.00 days @ 400.00 / day - P 14,400.00
Labor Cost - P 14,400.00

MATERIAL COST - P 546,750.00


LABOR COST - P 39,600.00
EQUIPMENT COST - P 14,400.00
TOTAL ITEM COST - P 600,750.00
Unit Cost P 2,407.33 / sq.m.

ITEM 1010 - DOORS AND WINDOWS


Quantity : 1.00 lot

DIRECT COST
A. Materials
2.00 units D-1: Double swing door (Glass) @ 15,000.00 / unit P 30,000.00
3.00 units D-2: Solid Core Door (Narra) @ 6,000.00 / unit P 18,000.00
27.00 units D-3: Hollow Core @ 4,000.00 / unit P 108,000.00
21.00 units D-4: PVC Hollow Panel Door, 0.8 m. x 2.10 m @ 2,000.00 / unit P 42,000.00
3.00 units W-1: Sliding Glass Window, 1.50m x 1.20m @ 3,500.00 / sq. m P 18,900.00
4.00 units W-2: Awning Glass & Fixed Glass Window, 4.70m x 2.30m @ 5,000.00 / sq. m P 20,000.00
1.00 units W-3: Sliding Glass Window, 2.0m x 0.50m @ 3,000.00 / sq. m P 3,000.00
5.00 units W-4: Sliding Glass Window, 1.0m x 0.50m @ 2,500.00 / sq. m P 6,250.00
6.00 units W-5: Awning Glass Window, 0.50m X 0.60m @ 1,500.00 / sq. m P 2,700.00
155.00 pcs. Loose Pin Hinges,4" x 4" (High Quality) @ 180.00 / pc P 27,900.00
52.00 pcs. Door Knob (High Quality) @ 900.00 / set P 46,800.00
Material Cost - P 323,550.00

B. Labor
2.00 Carpenter x 8.00 days @ 600.00 / day - P 9,600.00
2.00 Laborers x 8.00 days @ 500.00 / day - P 8,000.00
Labor Cost - P 17,600.00

MATERIAL COST - P 323,550.00


LABOR COST - P 17,600.00
TOTAL ITEM COST - P 341,150.00
Unit Cost P 341,150.00 / lot

ITEM 1003 - CEILING WORKS


Quantity : 518.00 sq.m.

Labor Requirement :
One (1) Crew Composition : 3 Carpenters and 3 Helpers
Capability : 9 Sheets / day
50 sheets
No. of days : = 5.56 days ; say 7.00 days
9 Sheets / day
DIRECT COST

A. Materials
710.00 pcs PVC ACOUSTIC GYPSUM BOARD (2'x4' ; 603mm x 1212mm x 9mm) @ 160.00 / pc 113,600.00
Material Cost - P 113,600.00

B. Labor
3.00 Carpenter x 7.00 days @ 600.00 / day - P 12,600.00
3.00 Laborers x 7.00 days @ 500.00 / day - 10,500.00
Labor Cost - P 23,100.00

C. Equipment
1 Electrical Grinder x 7.00 days @ 400.00 / day - P 2,800.00
1 Electrical Drill x 10.00 days @ 400.00 / day - P 4,000.00
Labor Cost - P 6,800.00

MATERIAL COST - P 113,600.00


LABOR COST - P 23,100.00
EQUIPMENT COST - P 6,800.00
TOTAL ITEM COST - P 143,500.00
Unit Cost P 277.03 / sq.m.

ITEM 1002 - PLUMBING WORKS


Quantity : 1.00 lot

DIRECT COST
A. Materials
Plumbing Fixtures Water Closet w/ complete accessories, Wall Hung type Lavatory, soap
19.00 sets holder, tissue holder @ 6,500.00 / set P 123,500.00
26.00 pcs. Stainless Floor Drain, 4" x 4" @ 280.00 / pc. P 7,280.00
Sewer Line
14.00 length PVC Pipe, 4" dia. X 3.0 m., S-1000 @ 795.00 / length P 11,130.00
4.00 length PVC Pipe, 2" dia. X 3.0m, S-1000 @ 290.00 / length P 1,160.00
24.00 pcs. PVC Elbow, 4" dia. X 90 deg. Bend @ 70.00 / pc. P 1,680.00
56.00 pcs. PVC Elbow, 4" dia. X 45 deg. Bend @ 70.00 / pc. P 3,920.00
11.00 length PVC Pipe, 4" dia. Coupling @ 95.00 /pc. P 1,045.00
20.00 pcs. PVC Wye Reducer, 4"Ø x 2"Ø dia. X 45 deg. Bend @ 80.00 / pc. P 1,600.00
56.00 pcs. PVC Wye, 4" x 4" dia. @ 95.00 / pc. P 5,320.00
20.00 pcs. PVC P-Trap, 2" dia. @ 65.00 / pc. P 1,300.00
17.00 pcs. PVC Clean Out Plug, 4" dia. @ 75.00 / pc. P 1,275.00
Water Line
60.00 length PPR Pipe, 1/2" x 3.0m @ 380.00 / length P 22,800.00
2.00 pc. Gate Valve, 1/2" dia. @ 255.00 / pc. P 510.00
54.00 pcs. PPR Elbow, 1/2" dia. @ 25.00 / pc. P 1,350.00
75.00 pcs. PPR Tee, 1/2" dia. @ 25.00 / pc. P 1,875.00
1.00 pcs. Water Pump (1.0HP) @ 12,800.00 / pc. P 12,800.00
20.00 pcs. Teflon Tape, 3/4" (big) @ 20.00 / pc. P 400.00
18.00 pints Solvent Cement @ 95.00 / pint P 1,710.00
2.00 pc Water Meter @ 1,800.00 / pc P 3,600.00
1.00 pc Water Storage Tank 5000L capacity @ 85,000.00 / pc P 85,000.00
Material Cost - P 289,255.00

B. Labor
1.00 Plumber x 20.00 days @ 600.00 / day - P 12,000.00
2.00 Laborers x 20.00 days @ 500.00 / day - P 20,000.00
Labor Cost - P 32,000.00

MATERIAL COST - P 289,255.00


LABOR COST - P 32,000.00
TOTAL ITEM COST - P 321,255.00
Unit Cost P 321,255.00 / lot

ITEM 1100 - ELECTRICAL WORKS


Quantity : 1.00 lot

DIRECT COST
A. Materials
53.00 pcs. Utility Boxes PVC, 2" x 4" @ 35.00 / pc. P 1,855.00
18.00 pcs. Junction Boxes PVC, 4" x 4" @ 35.00 / pc. P 630.00
100.00 length RSC Pipe, 3/4" dia. @ 420.00 / length P 42,000.00
30.00 pcs. Screw Insulator @ 35.00 / pc. P 1,050.00
16.00 boxes THHN / THWN Stranded Co. Wire, 2.0 mm² @ 3,500.00 / box P 56,000.00
20.00 boxes THHN / THWN Stranded Co. Wire, 5.5 mm² @ 3,500.00 / box P 70,000.00
10.00 boxes THHN / THWN Stranded Co. Wire, 8.0 mm² @ 3,500.00 / box P 35,000.00
100.00 pcs. PVC Clamp @ 7.00 / pc. P 700.00
70.00 pcs. Electrical Tape (Big) @ 35.00 / pc. P 2,450.00
87.00 pcs. Incadescent Lamp, 20 watts @ 250.00 / pc. P 21,750.00
2.00 pcs. Florecent Lamp, 40 watts @ 200.00 / pc. P 400.00
40.00 pcs. 1-Gang Switch, Flush Type @ 135.00 / pc. P 5,400.00
15.00 pcs. 2-Gang Switch, Flush Type @ 150.00 / pc. P 2,250.00
50.00 pcs. Duplex Convenience Outlet, Flush Type @ 95.00 / pc. P 4,750.00
2.00 pcs. Entrance Cap, 3/4" dia. @ 85.00 / pc. P 170.00
1.00 pc. Panel Board (6-Holes) branded @ 625.00 / pc. P 625.00
1.00 pc. Panel Board (18-Holes) branded @ 625.00 / pc. P 625.00
15.00 pc. Circuit Breaker 15 A @ 350.00 / pc. P 5,250.00
2.00 pc. Circuit Breaker 30 A @ 350.00 / pc. P 700.00
1.00 pc. Circuit Breaker 60 A @ 350.00 / pc. P 350.00
1.00 pc. Circuit Breaker 120 A @ 350.00 / pc. P 350.00
45.00 m Service Drop Wire, 8.0 @ 35.00 / m. P 1,575.00
2.00 unit KWHR meter w/ Base @ 4,500.00 / unit P 9,000.00
1.00 sets Manual Pull Switch @ 1,250.00 / set P 1,250.00
Material Cost - P 264,130.00

B. Labor
1.00 Electrician x 10.00 days @ 600.00 / day - P 6,000.00
2.00 Electrician x 10.00 days @ 500.00 / day - P 10,000.00
Labor Cost - P 16,000.00

MATERIAL COST - P 264,130.00

LABOR COST - P 16,000.00


TOTAL ITEM COST - P 280,130.00
Unit Cost P 280,130.00 / lot

ITEM 1032 - PAINTING WORKS


Quantity : 1,001.77 sq.m.

DIRECT COST
A. Materials
45.00 gals Concrete Putty @ 370.00 / gal. P 16,650.00
45.00 gals Glazing Putty @ 665.00 / gal. P 29,925.00
20.00 gals Concrete Neutralizer @ 250.00 / gal. P 5,000.00
20.00 gals Body Filler @ 590.00 / gal. P 11,800.00
15.00 gals Flat Latex White @ 490.00 / gal. P 7,350.00
25.00 gals Semi-Gloss Latex White @ 645.00 / gal. P 16,125.00
10.00 gals Flat Enamel White @ 540.00 / gal. P 5,400.00
15.00 gals Paint Thinner @ 285.00 / gal. P 4,275.00
10.00 pcs Paint Brush 4" @ 75.00 / pc. P 750.00
10.00 pcs Paint Brush 2" @ 30.00 / pc. P 300.00
5.00 sets Paint Roller 7" with Pan @ 95.00 / set P 475.00
3.00 pc Lettering Brush 1" @ 30.00 / pc. P 90.00
3.00 pc Lettering Brush 1/2" @ 30.00 / pc. P 90.00
40.00 pcs Sandpaper #100 @ 30.00 / pc. P 1,200.00
25.00 pcs Sandpaper #200 @ 35.00 / pc. P 875.00
Material Cost - P 100,305.00

B. Labor
4.00 Painter x 15.00 days @ 600.00 / day - P 36,000.00
4.00 Helper x 15.00 days @ 500.00 / day - P 30,000.00
Labor Cost - P 66,000.00

MATERIAL COST - P 100,305.00


LABOR COST - P 66,000.00
TOTAL ITEM COST - P 166,305.00
Unit Cost P 166.01 / sq.m.

ACCESSORIES & OTHERS


Quantity : 1.00 lot

DIRECT COST
A. Materials
3.00 pcs Fully Auto Washing Mashine @ 12,995.00 / pc P 38,985.00
2.00 pcs beverage cooler @ 21,950.00 / pc P 43,900.00
1.00 pcs refrigerator @ 18,999.00 / pc P 18,999.00
1.00 pcs freezer @ 16,650.00 / pc P 16,650.00
7.00 pcs dining set @ 5,499.00 / pc P 38,493.00
1.00 pcs sofa set @ 23,500.00 / pc P 23,500.00
6.00 pcs Queen size Bedroom Set @ 8,500.00 / pc P 51,000.00
16.00 pcs Single-bedroom set @ 5,000.00 / pc P 80,000.00
1.00 pcs 2hp Aircondition with Inverter @ 46,495.00 / pc P 46,495.00
6.00 pcs 1hp Aircondition with Inverter @ 31,295.00 / pc P 187,770.00
Material Cost - P 545,792.00

B. Labor
4.00 Helper x 15.00 days @ 500.00 / day - P 30,000.00
Labor Cost - P 30,000.00

MATERIAL COST - P 545,792.00


LABOR COST - P 30,000.00
TOTAL ITEM COST - P 575,792.00
Unit Cost P 575,792.00 / lot

CALENDAR DAYS - 363 DAYS

PREPARED BY: CONCURRED BY:

QUEENIE ANGELIE A. VILLAGONZA ENGR. VIRNE P. PORTUGUES


Researcher Panel Member 1

MARK JAMES B. CALUMPANG ENGR. ERLITO M. ORIT


Researcher Panel Member 2

JOSEPH CHRISTIAN G. MORDENO ARCH. MARLON C. SOLLOSO


Researcher Panel Member 3

NOTED BY: APPROVED BY:

ENGR. ELMARIO A. PEJAN, MBA ENGR. ROBERT R. BACARRO, MECE, MBA


Republic of the Philippines
Err:509
Err:509
Province of Surigao del Norte
Err:509
Err:509

Err:509

DESIGN OF TWO-STOREY PENSION HOUSE

DETAILED FREIGHT AND HANDLING


Hauling
RATE PER Arrastre from
No. of Arrastre Total Materials
DAY/ (Surigao Surigao Port to SP TOTAL (Port
ITEM DESCRIPTION QUANTITY UNIT Crew/ Total (Lantsa to Freight &
UNIT Port to Port to Site to Site) IK
Labor Libjo Port) Handling
COST Lantsa) Libjo
(Fare)

2-Gang Switch, Flush Type 15.00 pcs. 150.00 2,250.00


Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509
Duplex Convenience Outlet, Flush Type 50.00 pcs. 95.00 4,750.00
Electrical Tape (Big) 70.00 pcs. 35.00 2,450.00
Entrance Cap, 3/4" dia. 2.00 pcs. 85.00 170.00 5.00 10.00 5.00 5.00 20.00 5.00
Junction Boxes PVC, 4" x 4" 18.00 pcs. 35.00 630.00
Err:509 Err:509 Err:509 Err:509 Err:509
PVC Clamp 100.00 pcs. 7.00 700.00
Err:509 Err:509 Err:509 Err:509 Err:509
Utility Boxes PVC, 2" x 4" 53.00 pcs. 35.00 1,855.00
KWHR meter w/ Base 2.00 unit 4,500.00 9,000.00
RSC Pipe, 3/4" dia. 100.00 length 420.00 42,000.00
Door Knob (High Quality) 52.00 pcs. 900.00 46,800.00
Loose Pin Hinges,4" x 4" (High Quality) 155.00 pcs. 180.00 27,900.00
Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509
15.00 25.00 15.00 15.00 70.00 15.00
Err:509 Err:509 Err:509 Err:509 Err:509
Lettering Brush 1" 3.00 pc 30.00 90.00
Lettering Brush 1/2" 3.00 pc 30.00 90.00
Paint Brush 2" 10.00 pcs 30.00 300.00
Paint Brush 4" 10.00 pcs 75.00 750.00
Sandpaper #100 40.00 pcs 30.00 1,200.00
Sandpaper #200 25.00 pcs 35.00 875.00
Semi-Gloss Latex White 25.00 gals 645.00 16,125.00
Err:509 Err:509 Err:509 Err:509 Err:509
Water Pump (1.0HP) 1.00 pcs. 12,800.00 12,800.00
PVC Clean Out Plug, 4" dia. 17.00 pcs. 75.00 1,275.00
Err:509 Err:509 Err:509 Err:509 Err:509
PPR Elbow, 1/2" dia. 54.00 pcs. 25.00 1,350.00
Err:509 Err:509 Err:509 Err:509 Err:509
Stainless Floor Drain, 4" x 4" 26.00 pcs. 280.00 7,280.00
PVC P-Trap, 2" dia. 20.00 pcs. 65.00 1,300.00
PPR Tee, 1/2" dia. 75.00 pcs. 25.00 1,875.00
15.00 25.00 15.00 15.00 70.00 15.00
Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509
PVC Elbow, 4" dia. X 45 deg. Bend 56.00 pcs. 70.00 3,920.00
PVC Elbow, 4" dia. X 90 deg. Bend 24.00 pcs. 70.00 1,680.00
Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509
PVC Wye Reducer, 4"Ø x 2"Ø dia. X 45 deg. Bend 20.00 pcs. 80.00 1,600.00
Page 9
PVC Wye, 4" x 4" dia. 56.00 pcs. 95.00 5,320.00
Hacksaw Blade 45.00 pcs. 75.00 3,375.00 0.50 1.00 0.50 - 2.00 -
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Screened Gravel 3/4" 446.00 cu.m. 2,240.00 999,040.00 -
Screw Insulator 30.00 pcs. 35.00 1,050.00 -
Solvent Cement 1.00 pints 95.00 95.00 0.50 1.00 0.50 2.00 -
Teflon Tape, 3/4" (big) 20.00 pcs. 20.00 400.00 -
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 4.00 10.00 4.00 2.00 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 2.00 5.00 2.00 2.00 Err:509 Err:509
Body Filler 20.00 gals 590.00 11,800.00 4.00 10.00 4.00 2.00 400.00 40.00
Unglazed Floor Tiles, 16" x 16" 450.00 pcs 180.00 81,000.00 1.00 2.00 1.00 1.00 2,250.00 450.00
Ceramic Wall Tiles, 8" x 8" 3,225.00 pcs 90.00 290,250.00 1.00 2.00 1.00 1.00 16,125.00 3,225.00
Florecent Lamp, 40 watts 2.00 pcs. 200.00 400.00 1.00 5.00 1.00 - 14.00 -
CHB (4" x 8" x 16") 12,523.00 pcs. 30.00 375,690.00 -
Err:509 Err:509 Err:509 Err:509 Err:509 2.00 5.00 2.00 - Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 2.00 5.00 2.00 - Err:509 Err:509
Circuit Breaker 60 A 1.00 pc. 350.00 350.00 2.00 5.00 2.00 - 9.00 -
Coco or Lawaan Lumber, 100 pcs 2" x 3" x 12' 896.00 bd.ft. 30.00 26,880.00 -
Coco or Lawaan Lumber, 100 pcs 2" x 2" x 12' 3,550.00 bd.ft. 30.00 106,500.00 -
Coco or Lawaan Lumber, 40 - 2" x 2" x 12' 750.00 bd.ft 30.00 22,500.00 -
Concrete Putty 45.00 gals 370.00 16,650.00 4.00 10.00 4.00 2.00 900.00 90.00
Concrete Neutralizer 20.00 gals 250.00 5,000.00 4.00 10.00 4.00 2.00 400.00 40.00
CW Nails # 1½" Err:509 kgs. 90.00 Err:509 0.50 1.00 0.50 1.00 Err:509 Err:509
CW Nails # 2½" Err:509 kgs. 90.00 Err:509 0.50 1.00 0.50 1.00 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 0.50 1.00 0.50 1.00 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 0.50 1.00 0.50 1.00 Err:509 Err:509
CW Nails # 4" Err:509 kgs. 90.00 Err:509 0.50 1.00 0.50 1.00 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 0.50 1.00 0.50 1.00 Err:509 Err:509
D-1: Double swing door (Glass) 2.00 units 15,000.00 30,000.00 -
D-2: Solid Core Door (Narra) 3.00 units 6,000.00 18,000.00 -
Deformed Steel Bars, 12 mm Ø x 6.0 m (Grade 60) 1,152.00 length 250.00 288,000.00 5.00 10.00 5.00 5.00 28,800.00 5,760.00
Deformed Steel Bars, 16 mm Ø x 6.0 m (Grade 60) 321.00 length 430.00 138,030.00 7.00 12.00 7.00 3.00 9,309.00 963.00
Deformed Steel Bars, 20 mm Ø x 6.0 m (Grade 60) 295.00 length 670.00 197,650.00 10.00 16.00 10.00 3.00 11,505.00 885.00
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Flat Enamel White 10.00 gals 540.00 5,400.00 4.00 10.00 4.00 2.00 200.00 20.00
Flat Latex White 15.00 gals 490.00 7,350.00 4.00 10.00 4.00 2.00 300.00 30.00
Err:509 Err:509 Err:509 Err:509 Err:509 2.00 5.00 2.00 1.00 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 10.00 25.00 10.00 5.00 Err:509 Err:509
G.I. Tie Wire, #16 268.00 kg 80.00 21,440.00 2.00 5.00 2.00 1.00 2,680.00 268.00
Gate Valve, 1/2" dia. 2.00 pc. 255.00 510.00 2.00 5.00 2.00 1.00 20.00 2.00
Glazing Putty 45.00 gals 665.00 29,925.00 4.00 10.00 4.00 2.00 900.00 90.00
Err:509 Err:509 Err:509 Err:509 Err:509 2.00 5.00 2.00 1.00 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 10.00 25.00 10.00 7.00 Err:509 Err:509
Nylon # 30 1.00 kg 350.00 350.00 -
Ordinary Plywood, 4' x 8' x 1/4" 63.00 shts. 400.00 25,200.00 10.00 25.00 10.00 7.00 3,276.00 441.00
Paint Roller 7" with Pan 5.00 sets 95.00 475.00 2.00 5.00 2.00 2.00 55.00 10.00
Paint Thinner 15.00 gals 285.00 4,275.00 4.00 10.00 4.00 2.00 300.00 30.00
Panel Board (18-Holes) branded 1.00 pc. 625.00 625.00 4.00 10.00 4.00 2.00 20.00 2.00
Portland Cement Type 1 4,026.50 bags 290.00 1,167,685.00 10.00 30.00 10.00 10.00 241,590.00 40,265.00
PPR Pipe, 1/2" x 3.0m 60.00 length 380.00 22,800.00 4.00 10.00 4.00 2.00 1,200.00 120.00
PVC Pipe, 2" dia. X 3.0m, S-1000 4.00 length 290.00 1,160.00 4.00 10.00 4.00 2.00 80.00 8.00
Err:509 Err:509 Err:509 Err:509 Err:509 4.00 10.00 4.00 5.00 Err:509 Err:509
PVC Pipe, 4" dia. X 3.0 m., S-1000 14.00 length 795.00 11,130.00 4.00 10.00 4.00 5.00 322.00 70.00
Err:509 Err:509 Err:509 Err:509 Err:509 4.00 10.00 4.00 3.00 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 4.00 10.00 4.00 3.00 Err:509 Err:509
PVC ACOUSTIC GYPSUM BOARD (2'x4' ; 603mm x 1212mm x 9mm) 710.00 pcs 160.00 113,600.00 10.00 25.00 10.00 7.00 624.00 4,970.00
Err:509 Err:509 Err:509 Err:509 Err:509 10.00 25.00 10.00 7.00 416.00 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 10.00 25.00 10.00 7.00 416.00 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 4.00 10.00 4.00 5.00 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 2.00 5.00 2.00 1.00 Err:509 Err:509
Service Drop Wire, 8.0 45.00 m 35.00 1,575.00 2.00 5.00 2.00 1.00 450.00 45.00
Page 10
Err:509 Err:509 Err:509 Err:509 Err:509 4.00 10.00 4.00 4.00 Err:509 Err:509
THHN / THWN Stranded Co. Wire, 5.5 mm² 20.00 boxes 3,500.00 70,000.00 4.00 10.00 4.00 2.00 400.00 40.00
Err:509 Err:509 Err:509 Err:509 Err:509 4.00 10.00 4.00 2.00 Err:509 Err:509
Tile Trim 90.00 m 65.00 5,850.00 2.00 5.00 2.00 1.00 900.00 90.00
W-1: Sliding Glass Window, 1.50m x 1.20m 3.00 units 3,500.00 10,500.00 20.00 40.00 10.00 15.00 255.00 45.00
W-2: Awning Glass & Fixed Glass Window, 4.70m x 2.30m 4.00 units 5,000.00 20,000.00 10.00 20.00 7.00 7.00 176.00 28.00
Err:509 Err:509 Err:509 Err:509 Err:509 10.00 20.00 7.00 7.00 Err:509 Err:509
Washed Sand 255.00 cu.m. 1,000.00 255,000.00 -
Water Closet w/ complete accessories, Wall Hung type Lavatory, soap holde 19.00 sets 6,500.00 123,500.00 50.00 100.00 50.00 40.00 4,560.00 760.00
White Cement / Tile Grout 125.00 kgs. 75.00 9,375.00 2.00 5.00 2.00 2.00 1,375.00 250.00
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
-
-
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509
-
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509
-
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509

-
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509
2.00 5.00 2.00 -
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
TOTAL Err:509 Err:509 Err:509

Prepared by: Noted by :

Err:509 JOVENAL L. BERNAT


0.00 Regional Community Infrastructure Specialist

Reviewed and Checked by: Approved by: Concurred by :

0.00 -
0.00 BSPMC Chairman Barangay Captain Municipal Mayor

Page 11
Page 12
Page 13
Page 14
DESIGN OF TWO-STOREY PENSION HOUSE

BILL OF QUANTITIES
RATE PER
No. of
DAY/
ITEM DESCRIPTION QUANTITY UNIT Crew/ Total
UNIT
Labor
COST
A. DIRECT COST
Item 100 - CLEARING AND LAY-OUT 675.00 sq.m.
A. Materials
Coco or Lawaan Lumber, 40 - 2" x 2" x 12' 750.00 bd.ft 30.00 22,500.00
Trapal 120.00 m 62.00 7,440.00
Nylon # 30 1.00 kg 350.00 350.00
CW Nails # 3 3.00 kg 80.00 240.00
Sub-Total 30,530.00
B. Labor
Carpenter 3.00 day 2.00 600.00 3,600.00
Laborers 4.00 day 2.00 500.00 4,000.00
Sub-Total 7,600.00
TOTAL FOR CLEARING AND LAY-OUT 38,130.00

A. DIRECT COST
II. FORMS AND SCAFFOLDING Quantity 1 lot
A. Material Cost
PLYWOOD (8'x4'x1/4") 233.00 pc 400.00 93,200.00
COCO LUMBER (2"x2"x10') 1,633.00 pc 15.00 24,495.00
#3 Common Wire Nails 35.00 kg 90.00 3,150.00
#1 Common Wire Nails 25.00 kg 90.00 2,250.00
Scaffolding Rental 15.00 set 400.00 60,000.00
Sub-Total 183,095.00
TOTAL FOR FORMS AND SCAFFOLDING 183,095.00

ITEM 103 = STRUCTURE EXCAVATION


A. Labor
Laborers 16.00 days 6.00 500.00 48,000.00
Sub-Total 48,000.00
TOTAL FOR STRUCTURE EXCAVATION 48,000.00

ITEM 405 - STRUCTURAL CONCRETE 344.01 cu.m.


A. Materials
Portland Cement Type 1 3,097.00 bags 290.00 898,130.00
Screened Gravel 3/4" 446.00 cu.m. 2,240.00 999,040.00
Washed Sand 173.00 cu.m. 1,000.00 173,000.00
Waterproofing Cement - Sahara 35.00 bags 50.00 1,750.00
Ordinary Plywood, 4' x 8' x 1/4" 63.00 shts. 400.00 25,200.00
Coco or Lawaan Lumber, 100 pcs 2" x 3" x 12' 896.00 bd.ft. 30.00 26,880.00
Coco or Lawaan Lumber, 100 pcs 2" x 2" x 12' 3,550.00 bd.ft. 30.00 106,500.00
CW Nails # 1½" 10.00 kgs. 90.00 900.00
CW Nails # 2½" 15.00 kgs. 90.00 1,350.00
CW Nails # 4" 40.00 kgs. 90.00 3,600.00
Sub-Total 2,236,350.00
B. Labor
Carpenters 13.00 days 5.00 600.00 39,000.00
Masons 50.00 days 2.00 600.00 60,000.00
Laborers 50.00 days 13.00 500.00 325,000.00
Sub-Total 424,000.00
C. Equipment
Concrete Mixer 50.00 days 1.00 1,376.00 68,800.00
Concrete Vibrator 50.00 days 1.00 1,195.00 59,750.00
Sub-Total 128,550.00
TOTAL FOR STRUCTURAL CONCRETE 2,788,900.00

ITEM 404 - REINFORCING STEEL 12,449.86 kgs.


A. Materials
Deformed Steel Bars, 20 mm Ø x 6.0 m (Grade 60) 295.00 length 670.00 197,650.00
Deformed Steel Bars, 16 mm Ø x 6.0 m (Grade 60) 321.00 length 430.00 138,030.00
Deformed Steel Bars, 12 mm Ø x 6.0 m (Grade 40) 840.00 length 220.00 184,800.00
Deformed Steel Bars, 12 mm Ø x 6.0 m (Grade 60) 1,152.00 length 250.00 288,000.00
Stainless Steel Handrail (100mm) 72.00 length 4,955.00 356,760.00
Stainless Steel Handrail tube (100mm) 15.00 pcs. 825.00 12,375.00
steel 72.00 length 305.00 21,960.00
G.I. Tie Wire, #16 268.00 kg 80.00 21,440.00
Hacksaw Blade 45.00 pcs. 75.00 3,375.00
Sub-Total 1,224,390.00
B. Labor
Steelmen 63.00 days 4.00 600.00 151,200.00
Laborers 63.00 days 4.00 500.00 126,000.00
Sub-Total 277,200.00
C. Equipment
Bar Bender 63.00 days 2.00 1,380.00 173,880.00
Bar Cutter 63.00 days 2.00 2,850.00 359,100.00
Sub-Total 532,980.00
TOTAL FOR REINFORCING STEEL 2,034,570.00

ITEM 506 - MASONRY WORKS 1,001.77 sq.m.


A. Materials
CHB (4" x 8" x 16") 12,523.00 pcs. 30.00 375,690.00
Portland Cement Type 1 523.00 bags 290.00 151,670.00
Washed Sand 44.00 cu.m. 1,000.00 44,000.00
Sub-Total 571,360.00
B. Labor
Masons 42.00 days 4.00 600.00 100,800.00
Laborers 42.00 days 4.00 500.00 84,000.00
Sub-Total 184,800.00
TOTAL FOR MASONRY WORKS 756,160.00

ITEM 1027 - CEMENT PLASTER FINISH 2,003.54 sq.m.


A. Materials
Portland Cement Type 1 385.00 bags 290.00 111,650.00
Washed Sand 33.00 cu.m. 1,000.00 33,000.00
Sub-Total 144,650.00
B. Labor
Masons 84.00 days 4.00 600.00 201,600.00
Laborers 84.00 days 4.00 500.00 168,000.00
Sub-Total 369,600.00
TOTAL FOR CEMENT PLASTER FINISH 514,250.00

ITEM 1018 - TILEWORKS 249.55 sq.m.


A. Materials
Unglazed Floor Tiles, 16" x 16" 450.00 pcs 180.00 81,000.00
Unglazed Floor Tiles, 8" x 8" 1,656.00 pcs 90.00 149,040.00
Ceramic Wall Tiles, 8" x 8" 3,225.00 pcs 90.00 290,250.00
White Cement / Tile Grout 125.00 kgs. 75.00 9,375.00
Tile Trim 90.00 m 65.00 5,850.00
Portland Cement Type 1 21.50 bags 290.00 6,235.00
Washed Sand 5.00 cu.m. 1,000.00 5,000.00
Sub-Total 546,750.00
B. Labor
Masons 9.00 days 4.00 600.00 21,600.00
Laborers 9.00 days 4.00 500.00 18,000.00
Sub-Total 39,600.00
C. Equipment
Electrical Grinder 9.00 days 4.00 400.00 14,400.00
Sub-Total 14,400.00
TOTAL FOR TILEWORKS 600,750.00

ITEM 1010 - DOORS AND WINDOWS 1.00 lot


A. Materials
D-1: Double swing door (Glass) 2.00 units 15,000.00 30,000.00
D-2: Solid Core Door (Narra) 3.00 units 6,000.00 18,000.00
D-4: PVC Hollow Panel Door, 0.8 m. x 2.10 m 21.00 units 2,000.00 42,000.00
W-1: Sliding Glass Window, 1.50m x 1.20m 3.00 units 3,500.00 10,500.00
W-2: Awning Glass & Fixed Glass Window, 4.70m x 2.30m 4.00 units 5,000.00 20,000.00
W-3: Sliding Glass Window, 2.0m x 0.50m 1.00 units 3,000.00 3,000.00
W-4: Sliding Glass Window, 1.0m x 0.50m 5.00 units 2,500.00 12,500.00
W-5: Awning Glass Window, 0.50m X 0.60m 6.00 units 1,500.00 9,000.00
D-3: Hollow Core 27.00 units 4,000.00 108,000.00
Loose Pin Hinges,4" x 4" (High Quality) 155.00 pcs. 180.00 27,900.00
Door Knob (High Quality) 52.00 pcs. 900.00 46,800.00
Sub-Total 327,700.00
B. Labor
Carpenter 8.00 days 2.00 600.00 9,600.00
Laborers 8.00 days 2.00 500.00 8,000.00
Sub-Total 17,600.00
TOTAL FOR DOORS AND WINDOWS 345,300.00

ITEM 1003 - CEILING WORKS 518.00 sq.m.


A. Materials
PVC ACOUSTIC GYPSUM BOARD (2'x4' ; 603mm x 1212mm x
9mm) 710.00 pcs 160.00 113,600.00
Sub-Total 113,600.00
B. Labor
Carpenter 7.00 days 3.00 600.00 12,600.00
Laborers 7.00 days 3.00 500.00 10,500.00
Sub-Total 23,100.00
C. Equipment
Electrical Grinder 7.00 days 1.00 400.00 2,800.00
Electrical Drill 10.00 days 1.00 400.00 4,000.00
Sub-Total 6,800.00
TOTAL FOR CEILING WORKS 143,500.00

ITEM 1002 - PLUMBING WORKS 1.00 lot


A. Materials
Plumbing Fixtures
Water Closet w/ complete accessories, Wall Hung type Lavatory, s 19.00 sets 6,500.00 123,500.00
Stainless Floor Drain, 4" x 4" 26.00 pcs. 280.00 7,280.00
Sewer Line
Err:509 Err:509 Err:509 Err:509 Err:509
PVC Pipe, 4" dia. X 3.0 m., S-1000 14.00 length 795.00 11,130.00
PVC Pipe, 2" dia. X 3.0m, S-1000 4.00 length 290.00 1,160.00
Err:509 Err:509 Err:509 Err:509 Err:509
PVC Elbow, 4" dia. X 90 deg. Bend 24.00 pcs. 70.00 1,680.00
PVC Elbow, 4" dia. X 45 deg. Bend 56.00 pcs. 70.00 3,920.00
Err:509 Err:509 Err:509 Err:509 Err:509
PVC Pipe, 4" dia. Coupling 11.00 length 95.00 1,045.00
Err:509 Err:509 Err:509 Err:509 Err:509
PVC Wye Reducer, 4"Ø x 2"Ø dia. X 45 deg. Bend 20.00 pcs. 80.00 1,600.00
PVC Wye, 4" x 4" dia. 56.00 pcs. 95.00 5,320.00
PVC P-Trap, 2" dia. 20.00 pcs. 65.00 1,300.00
PVC Clean Out Plug, 4" dia. 17.00 pcs. 75.00 1,275.00
Err:509
Err:509 Err:509 pcs. Err:509 Err:509
Err:509 Err:509 pcs. Err:509 Err:509
Err:509 Err:509 pcs. Err:509 Err:509
Err:509 Err:509 pcs. Err:509 Err:509
Err:509 Err:509 pcs. Err:509 Err:509
Err:509 Err:509 pcs. Err:509 Err:509
Err:509 Err:509 pcs. Err:509 Err:509
Err:509 Err:509 pcs. Err:509 Err:509
Err:509 Err:509 pcs. Err:509 Err:509
Err:509 Err:509 pcs. Err:509 Err:509
Err:509 Err:509 pcs. Err:509 Err:509
Err:509 Err:509 pcs. Err:509 Err:509
Err:509 Err:509 pcs. Err:509 Err:509
Err:509 Err:509 pcs. Err:509 Err:509
Err:509 Err:509 pcs. Err:509 Err:509
Err:509 Err:509 pcs. Err:509 Err:509
Err:509 Err:509 pcs. Err:509 Err:509
Err:509 Err:509 pcs. Err:509 Err:509
Err:509 Err:509 pcs. Err:509 Err:509
Err:509 Err:509 pcs. Err:509 Err:509
Err:509 Err:509 pcs. Err:509 Err:509
Water Line
PPR Pipe, 1/2" x 3.0m 60.00 length 380.00 22,800.00
Gate Valve, 1/2" dia. 2.00 pc. 255.00 510.00
PPR Elbow, 1/2" dia. 54.00 pcs. 25.00 1,350.00
PPR Tee, 1/2" dia. 75.00 pcs. 25.00 1,875.00
Water Pump (1.0HP) 1.00 pcs. 12,800.00 12,800.00
Teflon Tape, 3/4" (big) 20.00 pcs. 20.00 400.00
Solvent Cement 18.00 pints 95.00 1,710.00
Water Meter 2.00 pc 1,800.00 3,600.00
Water Storage Tank 5000L capacity 1.00 pc 85,000.00 85,000.00
Err:509
Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509
Sub-Total Err:509
B. Labor
Plumber 20.00 days 1.00 600.00 12,000.00
Laborers 20.00 days 2.00 500.00 20,000.00
Sub-Total 32,000.00
TOTAL FOR PLUMBING WORKS Err:509

ITEM 1100 - ELECTRICAL WORKS 1.00 lot


A. Materials
Utility Boxes PVC, 2" x 4" 53.00 pcs. 35.00 1,855.00
Junction Boxes PVC, 4" x 4" 18.00 pcs. 35.00 630.00
RSC Pipe, 3/4" dia. 100.00 length 420.00 42,000.00
Screw Insulator 30.00 pcs. 35.00 1,050.00
THHN / THWN Stranded Co. Wire, 2.0 mm² 16.00 boxes 3,500.00 56,000.00
THHN / THWN Stranded Co. Wire, 5.5 mm² 20.00 boxes 3,500.00 70,000.00
THHN / THWN Stranded Co. Wire, 8.0 mm² 10.00 boxes 3,500.00 35,000.00
PVC Clamp 100.00 pcs. 7.00 700.00
Electrical Tape (Big) 70.00 pcs. 35.00 2,450.00
Incadescent Lamp, 20 watts 87.00 pcs. 250.00 21,750.00
Florecent Lamp, 40 watts 2.00 pcs. 200.00 400.00
1-Gang Switch, Flush Type 40.00 pcs. 135.00 5,400.00
2-Gang Switch, Flush Type 15.00 pcs. 150.00 2,250.00
Duplex Convenience Outlet, Flush Type 50.00 pcs. 95.00 4,750.00
Entrance Cap, 3/4" dia. 2.00 pcs. 85.00 170.00
Panel Board (18-Holes) branded 1.00 pc. 625.00 625.00
Circuit Breaker 15 A 15.00 pc. 350.00 5,250.00
Circuit Breaker 30 A 2.00 pc. 350.00 700.00
Circuit Breaker 60 A 1.00 pc. 350.00 350.00
Circuit Breaker 120 A 1.00 pc. 350.00 350.00
Service Drop Wire, 8.0 45.00 m 35.00 1,575.00
KWHR meter w/ Base 2.00 unit 4,500.00 9,000.00
Manual Pull Switch 1.00 sets 1,250.00 1,250.00
Sub-Total 263,505.00
B. Labor
Electrician 10.00 days 1.00 600.00 6,000.00
Electrician 10.00 days 2.00 500.00 10,000.00
Sub-Total 16,000.00
TOTAL FOR ELECTRICAL WORKS 279,505.00

ITEM 1032 - PAINTING WORKS 1,001.77 sq.m.


A. Materials
Concrete Putty 45.00 gals 370.00 16,650.00
Glazing Putty 45.00 gals 665.00 29,925.00
Concrete Neutralizer 20.00 gals 250.00 5,000.00
Body Filler 20.00 gals 590.00 11,800.00
Flat Latex White 15.00 gals 490.00 7,350.00
Semi-Gloss Latex White 25.00 gals 645.00 16,125.00
Flat Enamel White 10.00 gals 540.00 5,400.00
Paint Thinner 15.00 gals 285.00 4,275.00
Paint Brush 4" 10.00 pcs 75.00 750.00
Paint Brush 2" 10.00 pcs 30.00 300.00
Paint Roller 7" with Pan 5.00 sets 95.00 475.00
Lettering Brush 1" 3.00 pc 30.00 90.00
Lettering Brush 1/2" 3.00 pc 30.00 90.00
Sandpaper #100 40.00 pcs 30.00 1,200.00
Sandpaper #200 25.00 pcs 35.00 875.00
Sub-Total 100,305.00
B. Labor
Painter 15.00 days 4.00 600.00 36,000.00
Helper 15.00 days 4.00 500.00 30,000.00
Sub-Total 66,000.00
TOTAL FOR PAINTING WORKS 166,305.00

ACCESSORIES & OTHERS 1.00 lot


A. Materials
Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509
freezer 1.00 pcs 16,650.00 16,650.00
Single-bedroom set 16.00 pcs 5,000.00 80,000.00
1hp Aircondition with Inverter 6.00 pcs 31,295.00 187,770.00
Sub-Total Err:509
B. Labor
Helper 15.00 days 4.00 500.00 30,000.00
Sub-Total 30,000.00
TOTAL FOR ACCOUSTIC ACCESSORIES & OTHERS Err:509

TOTAL FOR DIRECT COST Err:509


B. INDIRECT COST
OVERHEAD COST
Project Supervisor 40.00 days 1.00 800.00 32,000.00
TOTAL FOR OVERHEAD COST 32,000.00
PRE-ENGINNERING
Reproduction of Plans 3,500.00
TOTAL FOR PRE-ENGINEERING 3,500.00
ENGINEERING SUPERVISION 5.00 days 1.00 800.00 4,000.00
TOTAL FOR ENGINEERING SUPERVISION 4,000.00
PERMITS AND LICENSES 5,000.00
TOTAL FOR PERMITS AND LICENSES 5,000.00
P.P.E./HANDTOOLS
Shovel w/ handle 5.00 pcs. 500.00 2,500.00
Crow Bar 3.00 pcs. 300.00 900.00
Concrete Pail 10.00 pcs. 165.00 1,650.00
Safety Belt 5.00 pcs. 900.00 4,500.00
Rubber Boots 10.00 pcs. 420.00 4,200.00
Hard Hat 10.00 pcs. 250.00 2,500.00
Hand Glove 10.00 pcs. 90.00 900.00
Construction Mask 10.00 pcs. 35.00 350.00
TOTAL FOR P.P.E./HANDTOOLS 17,500.00
MATERIAL TESTING 5,000.00
TOTAL FOR MATERIAL TESTING 5,000.00
TREASURER'S BOND 4,000.00
TOTAL FOR TREASURER'S BOND 4,000.00
FREIGHT & HANDLING 2,500.00
TOTAL FOR FREIGHT & HANDLING 2,500.00
CONTINGENCY Err:509
TOTAL FOR CONTINGENCY Err:509
TOTAL INDIRECT COST Err:509
TOTAL ESTIMATED PROJECT COST Err:509
GRANT ALLOCATION:

PREPARED BY: CONCURRED BY:

LOREN E. IJAPON ENGR. VIRNE P. PORTUGUES


Researcher Panel Member 1

JAY MARK C. SABUBU ENGR. ERLITO M. ORIT


Researcher Panel Member 2

NOEME D. QUINALAGAN ENGR. ELMARIO A. PEJAN, MBA


Researcher Panel Member 3

NOTED BY: NOTED BY:

ARCH. LUFREY B. POTENTE ENGR. ROBERT R. BACARRO, MECE, MBA


Co- author Panel Chair
Republic of the Philippines
Province of Surigao del Norte

PROJECT PROGRAM OF WORK

Sub-Project Title DESIGN OF TWO-STOREY PENSION HOUSE


Physical Target 100.00 sq.m.
Sub-Project Duration 363 CALENDAR DAYS
PROJECT DESCRIPTION : Construction of Three- Storey Equipment/ Tools Needed
Building Technical Personnel TF/ME
Foreman
Item no. Scope of Work ( Direct Cost ) % Wt. Quantity Unit Unit Price Total Amount
100 CLEARING AND LAY-OUT Err:509 675.00 sq.m. 56.49 38,130.00
FORMS AND SCAFFOLDING Err:509 1.00 lot 183,095.00 183,095.00
103 STRUCTURE EXCAVATION Err:509 53.18 cu.m. 902.59 48,000.00
405 STRUCTURAL CONCRETE Err:509 344.01 cu.m. 8,107.09 2,788,900.00
404 REINFORCING STEEL Err:509 12,449.86 kgs. 163.42 2,034,570.00
506 MASONRY WORKS Err:509 1,001.77 sq.m. 754.83 756,160.00
1027 CEMENT PLASTER FINISH Err:509 2,003.54 sq.m. 256.67 514,250.00
1018 TILEWORKS Err:509 249.55 sq.m. 2,407.33 600,750.00
1003 CEILING WORKS Err:509 420.00 pcs 341.67 143,500.00
1010 DOORS AND WINDOWS Err:509 1.00 lot 345,300.00 345,300.00
1012 PLUMBING WORKS Err:509 1.00 lot Err:509 Err:509
1100 ELECTRICAL WORKS Err:509 1.00 lot 279,505.00 279,505.00
1032 PAINTING WORKS Err:509 1,001.77 sq.m. 166.01 166,305.00
ACCESSORIES & OTHERS Err:509 1.00 lot Err:509 Err:509
Total Err:509 Err:509

BREAKDOWN OF ESTIMATED EXPENDITURES:


A. DIRECT COST
TOTAL COST OF MATERIALS Err:509
TOTAL COST OF LABOR: ₱1,535,500.00
TOTAL COST OF EQUIPMENT: ₱682,730.00
TOTAL ESTIMATED EXPENDITURES: Err:509
B. INDIRECT COST
OTHER CONTINGENCIES/MISCELLANEOUS Err:509
TOTAL ESTIMATED PROJECT WORK Err:509

PREPARED BY: CONCURRED BY:


QUEENIE ANGELIE A. VILLAGONZA ENGR. VIRNE P. PORTUGUES
Researcher Panel Member 1

MARK JAMES B. CALUMPANG ENGR. ERLITO M. ORIT


Researcher Panel Member 2

JOSEPH CHRISTIAN G. MORDENO ARCH. MARLON C. SOLLOSO


Researcher Panel Member 3

NOTED BY: APPROVED BY:

ENGR. ELMARIO A. PEJAN, MBA ENGR. ROBERT R. BACARRO, MECE, MBA


Co- author Panel Chair
BARANGAY SUB-PROJECT WORK SCHEDULE & PHYSICAL PROGRESS REPORT

DESIGN OF TWO-STOREY PENSION Total Sub-Project Cost : #NAME? LABOR No. of days Ave. rate per day
Name of Sub-Project:
HOUSE
Direct Cost : #NAME? MALE
SKILLED
Physical Target : 100.00 sq.m. Indirect Cost : #NAME? FEMALE
Region : CARAGA Region Date Started : 9-Mar-15 MALE
UNSKILLED
Province : Dinagat Island Target Completion Date : 7-May-15 FEMALE
Municipality : Libjo : MALE
TOTAL
Barangay: : Plaridel Mode of Implementation : CFA / LSG FEMALE
I. To be filled up by Deputy Area Coordinator
WEIGHT PHYSICAL
Item No. DESCRIPTION (%) TARGET
DURATION
QTY UNIT AMOUNT Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8
#NAME? Planned #NAME? #NAME?
100 CLEARING AND LAY-OUT 675.00 sq.m. 38,130.00
0.00% Actual 0.00%
#NAME? Planned #NAME? #NAME? #NAME?
103 STRUCTURE EXCAVATION 53.18 cu.m. 48,000.00
0.00% Actual 0.00%
#NAME? Planned #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME? #NAME?
0.00% Actual 0.00%
#NAME? Planned #NAME? #NAME? #NAME? #NAME? #NAME?
405 STRUCTURAL CONCRETE 344.01 cu.m. 2,788,900.00
0.00% Actual 0.00%
#NAME? Planned #NAME? #NAME? #NAME? #NAME? #NAME?
404 REINFORCING STEEL 12,449.86 kgs. 2,034,570.00
0.00% Actual 0.00%
#NAME? Planned #NAME? #NAME? #NAME? #NAME?
506 MASONRY WORKS 1,001.77 sq.m. 756,160.00
0.00% Actual 0.00%
#NAME? Planned #NAME? #NAME?
1027 CEMENT PLASTER FINISH 2,003.54 sq.m. 514,250.00
0.00% Actual 0.00%
#NAME? Planned #NAME? #NAME?
1018 TILEWORKS 249.55 sq.m. 600,750.00
0.00% Actual 0.00%
#NAME? Planned #NAME? #NAME? #NAME?
1003 CEILING WORKS 420.00 pcs 143,500.00
0.00% Actual 0.00%
#NAME? Planned #NAME? #NAME?
1010 DOORS AND WINDOWS 1.00 lot 345,300.00
0.00% Actual 0.00%
#NAME? Planned #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME? #NAME?
0.00% Actual 0.00%
Err:509 Planned Err:509 Err:509
1012 PLUMBING WORKS 1.00 lot Err:509
0.00% Actual 0.00%
#NAME? Planned #NAME? #NAME?
1100 ELECTRICAL WORKS 1.00 lot 279,505.00
0.00% Actual 0.00%
Err:509 Planned Err:509 Err:509 Err:509
0 ACCESSORIES & OTHERS 1.00 lot Err:509
0.00% Actual 0.00%
#NAME? Planned #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME? #NAME?
0.00% Actual 0.00%
#NAME? Planned #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME? #NAME?
0.00% Actual 0.00%
#NAME? Planned #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME? #NAME?
0.00% Actual 0.00%
#NAME? Planned
TOTAL #NAME?
0.00% Actual
PERIODIC #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? Err:509 #NAME?
% PROGRESS (PLANNED)
CUMMULATIVE #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? Err:509 #NAME?
PHYSICAL
PERIODIC
% PROGRESS (ACTUAL)
CUMMULATIVE

II. Major Issues Encountered: III. Recommendation:

Prepared by: Concurred by:

0
- PIT Chairman MIT Chairman

Approved by:
Reviewed and Checked by:

0 JOVENAL L. BERNAT
BSPMC Chairman 0 Regional Community Infrastructure Specialist
ENHANCED PLANNED COMMUNITY PROCUREMENT PACKAGING

Date Prepared : November 19, 2014 Name of Proposed Sub-Project: DESIGN OF TWO-STOREY PENSION HOUSE
Barangay : Plaridel Total Estimated Cost (Cash): #NAME?
Municipality : Libjo Sub-project Duration: 60 calendar days
Province : DINAGAT ISLANDS

Sources of Funds Pecentage Weight to Fund Source Amount


Description KC-NCDDP Total KC-NCDDP Legend
LCC Cash LCC Cash
GRANT GRANT KC-NCDDP Grant #NAME?
1st Tranche (Php) #NAME? - #NAME? #NAME? 0.00% LCC : #NAME?
2nd Tranche (Php) #NAME? #NAME? #NAME? #NAME? 0.00% In-kind #NAME?
Cash #NAME?
Mode of Implementation : CFA TOTAL #NAME? #NAME? #NAME? #NAME? 0.00% TOTAL COST #NAME?

PROPOSED IMPLEMENTATION
Estimated Cost Involved and Schedule of Delivery SCHEDULE
PACKAGES

PROC

REMARKS
PACKAGE ITEMS QTY UNIT UNIT COST TOTAL 1st Tranche 2nd Tranche SUB-TOTAL TOTAL MONTH
METHOD
KC-NCDDP
KC-NCDDP GRANT LCC Cash KC-NCDDP GRANT LCC Cash LCC Cash 1 2 3
GRANT

PACKAGE 1 - AGGREGATES & FILLING MATERIALS

Err:509 Err:509 Err:509 - Err:509


Err:509 Err:509 Err:509 Err:509 LSG
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Screened Gravel 3/4" 446.00 cu.m. 2240.00 999,040.00 999,040.00 999,040.00 - 999,040.00
Washed Sand 255.00 cu.m. 1000.00 255,000.00 255,000.00 255,000.00 - 255,000.00
Sub-Total Err:509 Err:509 - - - Err:509 - Err:509

PACKAGE 2 - CONCRETE HOLLOW BLOCKS


LSG
CHB (4" x 8" x 16") 12523.00 pcs. 30.00 375,690.00 375,690.00 375,690.00 - 375,690.00
Sub-Total 375,690.00 375,690.00 - - - 375,690.00 - 375,690.00

PACKAGE 3 - CONSTRUCTION MATERIALS

2-Gang Switch, Flush Type 15.00 pcs. 150.00 2,250.00 2,250.00 2,250.00 - 2,250.00
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Body Filler 20.00 gals 590.00 11,800.00 11,800.00 11,800.00 - 11,800.00
Unglazed Floor Tiles, 16" x 16" 450.00 pcs 180.00 81,000.00 81,000.00 81,000.00 - 81,000.00
Ceramic Wall Tiles, 8" x 8" 3225.00 pcs 90.00 290,250.00 290,250.00 290,250.00 - 290,250.00
Florecent Lamp, 40 watts 2.00 pcs. 200.00 400.00 400.00 400.00 - 400.00
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Circuit Breaker 60 A 1.00 pc. 350.00 350.00 350.00 350.00 - 350.00
Concrete Putty 45.00 gals 370.00 16,650.00 16,650.00 16,650.00 - 16,650.00
Concrete Neutralizer 20.00 gals 250.00 5,000.00 5,000.00 5,000.00 - 5,000.00
CW Nails # 1½" Err:509 kgs. 90.00 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
CW Nails # 2½" Err:509 kgs. 90.00 Err:509 Err:509 Err:509 - Err:509
CW Nails # 3 Err:509 kg 80.00 Err:509 Err:509 Err:509 - Err:509
CW Nails # 4" Err:509 kgs. 90.00 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Deformed Steel Bars, 12 mm Ø x 6.0 m (Grade 60) 1152.00 length 250.00 288,000.00 288,000.00 288,000.00 - 288,000.00
Deformed Steel Bars, 16 mm Ø x 6.0 m (Grade 60) 321.00 length 430.00 138,030.00 138,030.00 138,030.00 - 138,030.00
Deformed Steel Bars, 20 mm Ø x 6.0 m (Grade 60) 295.00 length 670.00 197,650.00 197,650.00 197,650.00 - 197,650.00
Door Knob (High Quality) 52.00 pcs. 900.00 46,800.00 46,800.00 46,800.00 - 46,800.00
Duplex Convenience Outlet, Flush Type 50.00 pcs. 95.00 4,750.00 4,750.00 4,750.00 - 4,750.00
Electrical Tape (Big) 70.00 pcs. 35.00 2,450.00 2,450.00 2,450.00 - 2,450.00
Entrance Cap, 3/4" dia. 2.00 pcs. 85.00 170.00 170.00 170.00 - 170.00
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Water Pump (1.0HP) 1.00 pcs. 12800.00 12,800.00 12,800.00 12,800.00 - 12,800.00
Flat Enamel White 10.00 gals 540.00 5,400.00 5,400.00 5,400.00 - 5,400.00
Flat Latex White 15.00 gals 490.00 7,350.00 7,350.00 7,350.00 - 7,350.00
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
G.I. Tie Wire, #16 268.00 kg 80.00 21,440.00 21,440.00 21,440.00 - 21,440.00
Gate Valve, 1/2" dia. 2.00 pc. 255.00 510.00 510.00 510.00 - 510.00
Glazing Putty 45.00 gals 665.00 29,925.00 29,925.00 29,925.00 - 29,925.00
Hacksaw Blade 45.00 pcs. 75.00 3,375.00 3,375.00 3,375.00 - 3,375.00
Junction Boxes PVC, 4" x 4" 18.00 pcs. 35.00 630.00 630.00 630.00 - 630.00
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509

Local Shopping for Goods


Lettering Brush 1" 3.00 pc 30.00 90.00 90.00 90.00 - 90.00
Lettering Brush 1/2" 3.00 pc 30.00 90.00 90.00 90.00 - 90.00
Loose Pin Hinges,4" x 4" (High Quality) 155.00 pcs. 180.00 27,900.00 27,900.00 27,900.00 - 27,900.00
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Nylon # 30 1.00 kg 350.00 350.00 350.00 350.00 - 350.00
Ordinary Plywood, 4' x 8' x 1/4" 63.00 shts. 400.00 25,200.00 25,200.00 25,200.00 - 25,200.00
Paint Brush 2" 10.00 pcs 30.00 300.00 300.00 300.00 - 300.00
Paint Brush 4" 10.00 pcs 75.00 750.00 750.00 750.00 - 750.00
Paint Roller 7" with Pan 5.00 sets 95.00 475.00 475.00 475.00 - 475.00
Paint Thinner 15.00 gals 285.00 4,275.00 4,275.00 4,275.00 - 4,275.00
Panel Board (18-Holes) branded 1.00 pc. 625.00 625.00 625.00 625.00 - 625.00
Portland Cement Type 1 4026.50 bags 290.00 1,167,685.00 1,167,685.00 1,167,685.00 - 1,167,685.00
PVC Clamp 100.00 pcs. 7.00 700.00 700.00 700.00 - 700.00
PVC Clean Out Plug, 4" dia. 17.00 pcs. 75.00 1,275.00 1,275.00 1,275.00 - 1,275.00
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
PPR Elbow, 1/2" dia. 54.00 pcs. 25.00 1,350.00 1,350.00 1,350.00 - 1,350.00
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
PVC Elbow, 4" dia. X 45 deg. Bend 56.00 pcs. 70.00 3,920.00 3,920.00 3,920.00 - 3,920.00
PVC Elbow, 4" dia. X 90 deg. Bend 24.00 pcs. 70.00 1,680.00 1,680.00 1,680.00 - 1,680.00

Err:509 Err:509 - Err:509


Err:509 Err:509 Err:509 Err:509 Err:509
PPR Pipe, 1/2" x 3.0m 60.00 length 380.00 22,800.00 22,800.00 22,800.00 - 22,800.00
PVC Pipe, 2" dia. X 3.0m, S-1000 4.00 length 290.00 1,160.00 1,160.00 1,160.00 - 1,160.00
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
PVC Pipe, 4" dia. X 3.0 m., S-1000 14.00 length 795.00 11,130.00 11,130.00 11,130.00 - 11,130.00
PVC P-Trap, 2" dia. 20.00 pcs. 65.00 1,300.00 1,300.00 1,300.00 - 1,300.00
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
PPR Tee, 1/2" dia. 75.00 pcs. 25.00 1,875.00 1,875.00 1,875.00 - 1,875.00
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
PVC Wye Reducer, 4"Ø x 2"Ø dia. X 45 deg. Bend 20.00 pcs. 80.00 1,600.00 1,600.00 1,600.00 - 1,600.00
PVC Wye, 4" x 4" dia. 56.00 pcs. 95.00 5,320.00 5,320.00 5,320.00 - 5,320.00
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
RSC Pipe, 3/4" dia. 100.00 length 420.00 42,000.00 42,000.00 42,000.00 - 42,000.00
Sandpaper #100 40.00 pcs 30.00 1,200.00 1,200.00 1,200.00 - 1,200.00
Sandpaper #200 25.00 pcs 35.00 875.00 875.00 875.00 - 875.00
Screw Insulator 30.00 pcs. 35.00 1,050.00 1,050.00 1,050.00 - 1,050.00
Semi-Gloss Latex White 25.00 gals 645.00 16,125.00 16,125.00 16,125.00 - 16,125.00
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Solvent Cement 1.00 pints 95.00 95.00 95.00 95.00 - 95.00
Stainless Floor Drain, 4" x 4" 26.00 pcs. 280.00 7,280.00 7,280.00 7,280.00 - 7,280.00
Teflon Tape, 3/4" (big) 20.00 pcs. 20.00 400.00 400.00 400.00 - 400.00
THHN / THWN Stranded Co. Wire, 5.5 mm² 20.00 boxes 3500.00 70,000.00 70,000.00 70,000.00 - 70,000.00
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Tile Trim 90.00 m 65.00 5,850.00 5,850.00 5,850.00 - 5,850.00
Utility Boxes PVC, 2" x 4" 53.00 pcs. 35.00 1,855.00 1,855.00 1,855.00 - 1,855.00
Water Closet w/ complete accessories, Wall Hung type Lavator 19.00 sets 6500.00 123,500.00 123,500.00 123,500.00 - 123,500.00
White Cement / Tile Grout 125.00 kgs. 75.00 9,375.00 9,375.00 9,375.00 - 9,375.00
Sub-Total Err:509 Err:509 - - - Err:509 - Err:509
PACKAGE 4 - ROOFING MATERIALS

PVC ACOUSTIC GYPSUM BOARD (2'x4' ; 603mm x


1212mm x 9mm) 113,600.00 113,600.00 - 113,600.00

Local Shopping for Goods


710.00 pcs 160.00 113,600.00
Err:509
Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509
Err:509
Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Sub-Total Err:509 Err:509 - - - Err:509 - Err:509
PACKAGE 5 - LUMBER MATERIALS
Coco or Lawaan Lumber, 40 - 2" x 2" x 12' 750.00 bd.ft 30.00 22,500.00 22,500.00 22,500.00 - 22,500.00
Coco or Lawaan Lumber, 100 pcs 2" x 3" x 12' 896.00 bd.ft. 30.00 26,880.00 26,880.00 26,880.00 - 26,880.00
Coco or Lawaan Lumber, 100 pcs 2" x 2" x 12' 3,550.00 bd.ft. 30.00 106,500.00 106,500.00 106,500.00 - 106,500.00
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Local Shopping for Goods

Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509


Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509
Local Shop
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Sub-Total Err:509 Err:509 - - - Err:509 - Err:509
PACKAGE 6 - KILOWATTHOUR METER

LSG
Service Drop Wire, 8.0 45.00 m 35.00 1,575.00 1,575.00 1,575.00 - 1,575.00
KWHR meter w/ Base 2.00 unit 4,500.00 9,000.00 9,000.00 9,000.00 - 9,000.00
Sub-Total 10,575.00 10,575.00 - - - 10,575.00 - 10,575.00
PACKAGE 7 - FURNITURE MATERIALS
D-1: Double swing door (Glass) 2.00 units 15,000.00 30,000.00 30,000.00 30,000.00 - 30,000.00
D-2: Solid Core Door (Narra) 3.00 units 6,000.00 18,000.00 18,000.00 18,000.00 - 18,000.00
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509

Local Shopping for Goods


Err:509
- - - -
- - - -
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509
- - - -
- - - -
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509
- - - -
- - - -
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Sub-Total Err:509 Err:509 - - - Err:509 - Err:509
PACKAGE 8 - GLASS JALOUSIE WINDOW
W-1: Sliding Glass Window, 1.50m x 1.20m
10,500.00 10,500.00 - 10,500.00
3.00 units 3,500.00 10,500.00
W-2: Awning Glass & Fixed Glass Window, 4.70m x
2.30m 20,000.00 20,000.00 - 20,000.00
4.00 units 5,000.00 20,000.00
Err:509
Err:509 Err:509 - Err:509

Local Shopping for Goods


Err:509 Err:509 Err:509 Err:509
Sub-Total Err:509 Err:509 - - - Err:509 - Err:509

PACKAGE 9 - PLASTIC CHAIR


Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509
Err:509 - - - -
Sub-Total Err:509 Err:509 - Err:509 - Err:509 - Err:509

PACKAGE 10 - STEEL BILLBOARD


LSG

Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509


Sub-Total Err:509 Err:509 - - - Err:509 - Err:509

PACKAGE 11 - STAINLESS BUILDING MARKER


LSG

Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - Err:509


Sub-Total Err:509 Err:509 - Err:509 - Err:509 - Err:509
Total Material Cost (Cash) Err:509 Err:509 - Err:509 - Err:509 - Err:509
LABOR
CFA

Skilled #NAME? #NAME? 13,640.00 #NAME? - #NAME?


CFA
Unskilled #NAME? #NAME? 24,395.00 #NAME? - #NAME?
Total Labor Cost (Cash) #NAME? #NAME? - 38,035.00 - #NAME? - #NAME?
TOTAL DIRECT COST #NAME? #NAME? - Err:509 - #NAME? - #NAME?
INDIRECT COST
#NAME? #NAME? #NAME? 5,000.00 #NAME? - #NAME?
#NAME? #NAME? #NAME? #NAME? - #NAME?
PACKAGE 12 - FILING CABINET - - - -

LSG
#NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? - #NAME?
Sub-Total #NAME? #NAME? - - - #NAME? - #NAME?
#NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
PACKAGE 13 - HANDTOOLS AND PPE
Shovel w/ handle 3.00 pcs. 453.00 1,359.00 1,359.00 1,359.00 - 1,359.00
Crow Bar 1.00 pcs. 253.00 253.00 253.00 253.00 - 253.00
Concrete Pail 10.00 pcs. 153.00 1,530.00 1,530.00 1,530.00 - 1,530.00
Safety Belt 2.00 pcs. 900.00 1,800.00 1,800.00 1,800.00 - 1,800.00
Rubber Boots 10.00 pcs. 403.00 4,030.00 4,030.00 4,030.00 - 4,030.00
Hard Hat 10.00 pcs. 210.00 2,100.00 2,100.00 2,100.00 - 2,100.00
Hand Glove 10.00 pcs. 78.00 780.00 780.00 780.00 - 780.00
Construction Mask 10.00 pcs. 20.00 200.00 200.00 200.00 - 200.00
#NAME? 12,052.00 12,052.00 - - - 12,052.00 - 12,052.00
#NAME? #NAME? #NAME? #NAME? - #NAME?
#NAME? #NAME? #NAME? #NAME? - #NAME?
#NAME? #NAME? #NAME? #NAME? #NAME? - #NAME?
Total Indirect Cost (Cash) #NAME? #NAME? #NAME? #NAME? - #NAME? #NAME? #NAME?
GRAND TOTAL (Cash) #NAME? #NAME? #NAME? #NAME? - #NAME? #NAME? #NAME?
850,000.00
Workshop output of: Checked and Reviewed by: Err:509 765,000.00 Approved by: Noted by:
#NAME? #NAME?

0 0
Procurement Team Head - 0 BSPMC
KALAHI-CIDSS NATIONAL COMMUNITY DRIVEN DEVELOPMENT PROJECT

COMMUNITY PROCUREMENT PLAN (CPP)

Name of Proposed Community Project : CONSTRUCTION OF ONE UNIT DAY CARE CENTER
Barangay : PLARIDEL Municipality : LIBJO
Total Estimated Cost: 877,341.00
Community Project Duration: 60 CALENDAR DAYS Proposed Project Implement
Type of Plan: ( ) Initial ( ) Actual

Unit of
Package No. Items to be Procured Quantity Unit Cost
Measure
Package No. 1 AGGREGATES & FILLING MATERIALS
1 Err:509 Err:509 Err:509 Err:509
2 Err:509 Err:509 Err:509 Err:509
3 Screened Gravel 3/4" 446.00 cu.m. 2240.00
4 Washed Sand 255.00 cu.m. 1000.00
Sub-Total
Package No. 2 CONCRETE HOLLOW BLOCKS
1 CHB (4" x 8" x 16") 12523.00 pcs. 30.00
Sub-Total
Package No. 3 CONSTRUCTION MATERIALS
1 2-Gang Switch, Flush Type 15.00 pcs. 150.00
2 Err:509 Err:509 Err:509 Err:509
3 Err:509 Err:509 Err:509 Err:509
4 Err:509 Err:509 Err:509 Err:509
5 Body Filler 20.00 gals 590.00
6 Unglazed Floor Tiles, 16" x 16" 450.00 pcs 180.00
7 Ceramic Wall Tiles, 8" x 8" 3225.00 pcs 90.00
8 Florecent Lamp, 40 watts 2.00 pcs. 200.00
9 Err:509 Err:509 Err:509 Err:509
10 Err:509 Err:509 Err:509 Err:509
11 Circuit Breaker 60 A 1.00 pc. 350.00
12 Concrete Putty 45.00 gals 370.00
13 Concrete Neutralizer 20.00 gals 250.00
14 CW Nails # 1½" Err:509 kgs. 90.00
15 Err:509 Err:509 Err:509 Err:509
16 CW Nails # 2½" Err:509 kgs. 90.00
17 CW Nails # 3 Err:509 kg 80.00
18 CW Nails # 4" Err:509 kgs. 90.00
19 Err:509 Err:509 Err:509 Err:509
20 Deformed Steel Bars, 12 mm Ø x 6.0 m (Grade 1152.00 length 250.00
21 Deformed Steel Bars, 16 mm Ø x 6.0 m (Grade 321.00 length 430.00
22 Deformed Steel Bars, 20 mm Ø x 6.0 m (Grade 295.00 length 670.00
23 Door Knob (High Quality) 52.00 pcs. 900.00
24 Duplex Convenience Outlet, Flush Type 50.00 pcs. 95.00
25 Electrical Tape (Big) 70.00 pcs. 35.00
26 Entrance Cap, 3/4" dia. 2.00 pcs. 85.00
27 Err:509 Err:509 Err:509 Err:509
28 Water Pump (1.0HP) 1.00 pcs. 12800.00
29 Flat Enamel White 10.00 gals 540.00
30 Flat Latex White 15.00 gals 490.00
31 Err:509 Err:509 Err:509 Err:509
32 Err:509 Err:509 Err:509 Err:509
33 G.I. Tie Wire, #16 268.00 kg 80.00
34 Gate Valve, 1/2" dia. 2.00 pc. 255.00
35 Glazing Putty 45.00 gals 665.00
36 Hacksaw Blade 45.00 pcs. 75.00
37 Junction Boxes PVC, 4" x 4" 18.00 pcs. 35.00
38 Err:509 Err:509 Err:509 Err:509
39 Err:509 Err:509 Err:509 Err:509
40 Err:509 Err:509 Err:509 Err:509
41 Err:509 Err:509 Err:509 Err:509
42 Err:509 Err:509 Err:509 Err:509
43 Lettering Brush 1" 3.00 pc 30.00
44 Lettering Brush 1/2" 3.00 pc 30.00
45 Loose Pin Hinges,4" x 4" (High Quality) 155.00 pcs. 180.00
46 Err:509 Err:509 Err:509 Err:509
47 Err:509 Err:509 Err:509 Err:509
48 Err:509 Err:509 Err:509 Err:509
49 Nylon # 30 1.00 kg 350.00
50 Ordinary Plywood, 4' x 8' x 1/4" 63.00 shts. 400.00
51 Paint Brush 2" 10.00 pcs 30.00
52 Paint Brush 4" 10.00 pcs 75.00
53 Paint Roller 7" with Pan 5.00 sets 95.00
54 Paint Thinner 15.00 gals 285.00
55 Panel Board (18-Holes) branded 1.00 pc. 625.00
56 Portland Cement Type 1 4026.50 bags 290.00
57 PVC Clamp 100.00 pcs. 7.00
58 PVC Clean Out Plug, 4" dia. 17.00 pcs. 75.00
59 Err:509 Err:509 Err:509 Err:509
60 PPR Elbow, 1/2" dia. 54.00 pcs. 25.00
61 Err:509 Err:509 Err:509 Err:509
62 Err:509 Err:509 Err:509 Err:509
63 Err:509 Err:509 Err:509 Err:509
64 PVC Elbow, 4" dia. X 45 deg. Bend 56.00 pcs. 70.00
65 PVC Elbow, 4" dia. X 90 deg. Bend 24.00 pcs. 70.00
66 Err:509 Err:509 Err:509 Err:509
67 PPR Pipe, 1/2" x 3.0m 60.00 length 380.00
68 PVC Pipe, 2" dia. X 3.0m, S-1000 4.00 length 290.00
69 Err:509 Err:509 Err:509 Err:509
70 PVC Pipe, 4" dia. X 3.0 m., S-1000 14.00 length 795.00
71 PVC P-Trap, 2" dia. 20.00 pcs. 65.00
72 Err:509 Err:509 Err:509 Err:509
73 PPR Tee, 1/2" dia. 75.00 pcs. 25.00
74 Err:509 Err:509 Err:509 Err:509
75 PVC Wye Reducer, 4"Ø x 2"Ø dia. X 45 deg. Be 20.00 pcs. 80.00
76 PVC Wye, 4" x 4" dia. 56.00 pcs. 95.00
77 Err:509 Err:509 Err:509 Err:509
78 Err:509 Err:509 Err:509 Err:509
79 RSC Pipe, 3/4" dia. 100.00 length 420.00
80 Sandpaper #100 40.00 pcs 30.00
81 Sandpaper #200 25.00 pcs 35.00
82 Screw Insulator 30.00 pcs. 35.00
83 Semi-Gloss Latex White 25.00 gals 645.00
84 Err:509 Err:509 Err:509 Err:509
85 Solvent Cement 1.00 pints 95.00
86 Stainless Floor Drain, 4" x 4" 26.00 pcs. 280.00
87 Teflon Tape, 3/4" (big) 20.00 pcs. 20.00
88 THHN / THWN Stranded Co. Wire, 5.5 mm² 20.00 boxes 3500.00
89 Err:509 Err:509 Err:509 Err:509
90 Tile Trim 90.00 m 65.00
91 Utility Boxes PVC, 2" x 4" 53.00 pcs. 35.00
Water Closet w/ complete accessories, Wall
92 19.00 sets 6500.00
Hung type Lavatory, soap holder, tissue holder
93 White Cement / Tile Grout 125.00 kgs. 75.00
Sub-Total
Package No. 4 ROOFING MATERIAS
PVC ACOUSTIC GYPSUM BOARD (2'x4' ;
1 710 pcs 160
603mm x 1212mm x 9mm)
2 Err:509 Err:509 Err:509 Err:509

3 Err:509 Err:509 Err:509 Err:509


4 Err:509 Err:509 Err:509 Err:509
5 Err:509 Err:509 Err:509 Err:509
6 Err:509 Err:509 Err:509 Err:509
7 Err:509 Err:509 Err:509 Err:509
8 Err:509 Err:509 Err:509 Err:509
Sub-Total
Package No. 5 LUMBER MATERIALS
1 Coco or Lawaan Lumber, 40 - 2" x 2" x 12' 750.00 bd.ft 30.00
2 Coco or Lawaan Lumber, 100 pcs 2" x 3" x 12' 896.00 bd.ft. 30.00
3 Coco or Lawaan Lumber, 100 pcs 2" x 2" x 12' 3,550.00 bd.ft. 30.00
4 Err:509 Err:509 Err:509 Err:509
5 Err:509 Err:509 Err:509 Err:509
6 Err:509 Err:509 Err:509 Err:509
7 Err:509 Err:509 Err:509 Err:509
8 Err:509 Err:509 Err:509 Err:509
9 Err:509 Err:509 Err:509 Err:509
10 Err:509 Err:509 Err:509 Err:509
11 Err:509 Err:509 Err:509 Err:509
12 Err:509 Err:509 Err:509 Err:509
13 Err:509 Err:509 Err:509 Err:509
14 Err:509 Err:509 Err:509 Err:509
15 Err:509 Err:509 Err:509 Err:509
16 Err:509 Err:509 Err:509 Err:509
17 Err:509 Err:509 Err:509 Err:509
18 Err:509 Err:509 Err:509 Err:509
Sub-Total
Package No. 6 KILOWHATTHOUR METER
1 Service Drop Wire, 8.0 45 m 35
2 KWHR meter w/ Base 2 unit 4500
Sub-Total
Package No. 7 FURNITURE MATERIALS
1 D-1: Double swing door (Glass) 2.00 units ###
2 D-2: Solid Core Door (Narra) 3.00 units 6,000.00
3 Err:509 Err:509 Err:509 Err:509

Err:509

4 Err:509 Err:509 Err:509 Err:509

Err:509

5 Err:509 Err:509 Err:509 Err:509

Err:509

6 Err:509 Err:509 Err:509 Err:509


Sub-Total
Package No. 8 GLASS JALOUSIE WINDOW
1 W-1: Sliding Glass Window, 1.50m x 1.20m 3 units 3500
W-2: Awning Glass & Fixed Glass Window,
2 4 units 5000
4.70m x 2.30m
3 Err:509 Err:509 Err:509 Err:509
Sub-Total
Package No. 9 PLASTIC CHAIR
1 Err:509 Err:509 Err:509 Err:509
Err:509
Sub-Total
Package No. 10 STEEL BILLBOARD
1 Err:509 Err:509 Err:509 Err:509
Sub-Total
Package No. 11 PROJECT MARKER
1 Err:509 Err:509 Err:509 Err:509
Sub-Total
Package No. 12 FILING CABINET
1 #NAME? #NAME? #NAME? #NAME?
Sub-Total
Package No. 13 HANDTOOLS AND PPE
1 Shovel w/ handle 3.00 pcs. 453.00
2 Crow Bar 1.00 pcs. 253.00
3 Concrete Pail 10.00 pcs. 153.00
4 Safety Belt 2.00 pcs. 900.00
5 Rubber Boots 10.00 pcs. 403.00
6 Hard Hat 10.00 pcs. 210.00
7 Hand Glove 10.00 pcs. 78.00
8 Construction Mask 10.00 pcs. 20.00
Sub-Total
GRAND TOTAL

Prepared by: Reviewed by:


ARTURO B. MILLANA JR.
Procurement Team Head TF/Municipal Engineer
(Name and Signature) (Name and Signature)
VEN DEVELOPMENT PROJECT

T PLAN (CPP)

Date Prepared : __________________


Province : DINAGAT ISLANDS

Proposed Project Implementation Schedule: ___________________

Procurement Schedule of Comments /


Total Cost
Method Procurement Remarks

Err:509
Err:509 Local
Shopping for Feb. 4-6,2015
999,040.00 Goods
255,000.00
Err:509

375,690.00 LSG Feb. 4-6,2015


375,690.00

2,250.00
Err:509
Err:509
Err:509
11,800.00
81,000.00
290,250.00
400.00
Err:509
Err:509
350.00
16,650.00
5,000.00
Err:509
Err:509
Err:509
Err:509
Local Shopping of Goods

Err:509
Err:509
288,000.00
138,030.00
197,650.00
46,800.00
4,750.00
2,450.00
170.00
Err:509
12,800.00
5,400.00
7,350.00
Err:509
Err:509
21,440.00
510.00
29,925.00
3,375.00
630.00
Err:509
Err:509
Err:509
Err:509
Err:509
90.00
Local Shopping of Goods

90.00
27,900.00
Err:509
Err:509
Err:509 Feb. 4-6,2015
350.00
25,200.00
300.00
750.00
475.00
4,275.00
625.00
###
700.00
1,275.00
Err:509
1,350.00
Err:509
Err:509
Err:509
3,920.00
1,680.00
Err:509
22,800.00
1,160.00
Err:509
Local Shopping for Goods

11,130.00
1,300.00
Err:509
1,875.00
Err:509
1,600.00
5,320.00
Err:509
Err:509
42,000.00
1,200.00
875.00
1,050.00
16,125.00
Err:509
95.00
7,280.00
400.00
70,000.00
Err:509
5,850.00
1,855.00
123,500.00
9,375.00
Err:509

113,600.00
Local Shopping for Goods

Err:509

Err:509
Feb. 4-6,2015
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509

22,500.00
26,880.00
106,500.00
Err:509
Err:509
Local Shopping for Goods

Err:509
Err:509
Err:509
Err:509
Feb. 4-6,2015
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509

1,575.00
LSG 5th-6th week
9,000.00
10,575.00

30,000.00
oods
18,000.00
Err:509

Local Shopping for Goods


Err:509
Feb. 4-6,2015

Err:509

Err:509
Err:509

10,500.00
Local
20,000.00 Shopping for 5th -6th week
Goods
Err:509
Err:509

Err:509
LSG 5th -6th week
Err:509

Err:509 LSG Feb. 4-6,2015


Err:509

Err:509 LSG 5th -6th week


Err:509

#NAME? LSG Feb. 4-6,2015


#NAME?

1,359.00
253.00
1,530.00
1,800.00 Local
Shopping for Feb. 4-6,2015
4,030.00 Goods
2,100.00
780.00
200.00
12,052.00
Err:509

Approved by:
BSPMC Chairperson
(Name and Signature)
S

Barangay Sta. Ines Municipality San Luis Province: Agusan del Sur Region: Caraga
caraga
A. GENERAL INFORMATION
Name of proposed sub-project: Construction of One (1) Unit -Two (2) Classroom Elementary School Building
Category: Public Goods X Enterprise Human Resource Dev't.

What needs of the community will the proposed sub-project address?


1
2
3

B. TECHNICAL DESCRIPTION
Physical target: sq.m 129.22 Cost parameter: sq.m / 11.287.10
Person/s who assisted in the preparation of techical proposal: DAC, Municiapal Engr. .&
l.m 273.50
Service Provider
Proposed scope of works to be undertaken:
333.33
333.33
Construction of 1unit 2cl HS Building, 164 sq.m floor area
333.33
333.33
Manpower requirement / sources: (skilled) Carpenter, Mason, Steelman, Laborer
Equipment requirement / sources: None
Other component included in the proposal (e.g. trainings)
Procurement Method/s to be adopted:
Local Shopping for Goods and CFA
C. FINANCIAL ECONOMIC ASPECT
Total Estimated Cost : #REF!
Cost Sharing Arrangement: Direct Cost Indirect Cost Total % total
Grant Amount #REF! #REF! #REF! #REF!
LCC: BLGU #REF! #REF! #REF! #REF!
Community #REF! #REF! #REF! #REF!
MLGU #REF! #REF! #REF! #REF!
sub-total #REF! #REF! #REF! #REF!
Total LCC Cash #REF! #REF! #REF!
Total LCC In-kind #REF! #REF! #REF!

Total number of Household (HH) in the barangay: Total population


Number of HH currently without access to the needed services that % to total
can be served by the proposed sub-project:
Current expenses without the proposed SP
Expected expenses after completion of proposed SP:
Other benefits can be derived from the proposed sub-project: cents/container 30

D. SAFEGUARD CONCERNS
Any displacement or relocation of community members during implementation? Yes No x
Acquisition of proposed site/location? Deed of Sale Donated x LGU Ownd others specify
Proposed site within the reservation areas? Yes No x
Necessary permit/s accomplished? (e.g ECC, CNC) Yes No EMP Only x
Mitigating measures to be undertaken for the environmental impacts of the sub-project?

E. SP SUSTAINABILITY
Is there an existing O&M group or still to be organized?
Is the community willing to pay for Tariff and by How much?
Other sources of funds for the operation and maintenance activities?
Identified capability building requirements for O&M group? O & M Training
How do we plan to maintain the completed sub-project?

Prepared by: Approved for endorsement to the MIBF

Head, Project Preparation Team Brgy. Chairperson BSPMC Chairperson

Approved for endorsement to KALAHI-CIDSS: Technical Verification by:

Municipal Mayor/MIBF Convenor Area Coordinator MIAC Representative


ENHANCED PLANNED COMMUNITY PROCUREMENT PACKAGING

Date Prepared : February 1, 2011 Name of Proposed Sub-Project : Construction of One(1) Unit Two(2) Classroom
Barangay : BALIT Total Cash (Php) : #REF!
Municipality : SAN LUIS Sub-project Duration : 80 C.D

Province : AGUSAN DEL SUR SOURCES OF FUNDS


DESCRIPTION
KC Grant:
1st Tranche (Php) #REF!
2nd Tranche (Php) #REF!
3rd Tranche (Php) #REF!
Mode of Implementation : Community Force Account (CFA) TOTAL CASH (Php) #REF!

QUANTITY
UNIT COST
PACKAGES

No. of Crew/ TOTAL UNIT PROC


PACKAGE ITEMS Unit TOTAL
Labor UNIT RATE/RATE PER ADD: FREIGHT &
COST METHOD 1st Tranche
DAY HANDLING COST
KC Grant LCC Cash
3" CW Nails #REF! #REF! #REF! 48.00 #REF! #REF!
Nylon # 16 #REF! #REF! #REF! #REF! 30.00 #REF! #REF!
3mm thk. 2"x 4"x 20' C- Purlins #REF! #REF! #REF! #REF! 440.00 #REF! #REF!
3mm thk. x 25mm x 25mm x 6m Angular Bar (Fasci #REF! #REF! #REF! #REF! 420.00 #REF! #REF!
1/4"thk.x4'x8' Marine Plywood #REF! #REF! #REF! 392.00 #REF! #REF!
1/4x4x8 ord. Plywood #REF! #REF! #REF! 360.00 #REF! #REF!
10 mm.dia.x6.0m. Def.steel bars #REF! #REF! #REF! 150.00 #REF! #REF!
10mm square bar #REF! #REF! #REF! 210.00 #REF! #REF!
12 mm.dia.x6.0m. Def.steel bars #REF! #REF! #REF! 210.00 #REF! #REF!
25 mm x 6.0m Flat bar #REF! #REF! #REF! 220.00 #REF! #REF!
3-1/2"x3-1/2" Loose pin Hinges (quality brand) #REF! #REF! #REF! 30.00 #REF! #REF!
8x8 ceramic glazed tiles #REF! #REF! #REF! 12.50 #REF! #REF!
8x8 ceramic unglazed tiles #REF! #REF! #REF! 14.00 #REF! #REF!
Blind rivets 1/8" dia. X 2" #REF! #REF! #REF! #REF! 0.50 #REF! #REF!
PACKAGE 1

cwn 1" #REF! #REF! #REF! #REF! 60.00 #REF! #REF!


cwn 2" #REF! #REF! #REF! 48.00 #REF! #REF!
CWNail 2-1/2" 55.00 #REF! #REF! 48.00 2,640.00 2,640.00
CWNails 1" #REF! #REF! #REF! 60.00 #REF! #REF!
CWNails 3" #REF! #REF! #REF! 45.00 #REF! #REF!
CWNails 4" 95.00 #REF! #REF! 45.00 4,275.00 4,275.00
Door knob (QUALITY BRAND) #REF! #REF! #REF! 280.00 #REF! #REF!
Hacksaw blade #REF! #REF! #REF! 30.00 #REF! #REF!
Portland Cement T-1 (40 kgs) 437.00 #REF! #REF! 235.00 102,695.00 102,695.00
Roof Sealant #REF! #REF! #REF! 380.00 #REF! #REF!
Tex Screw 2 1/2" (for steel) #REF! #REF! #REF! #REF! 2.00 #REF! #REF!
Tie wire (#16) #REF! #REF! #REF! 63.00 #REF! #REF!
tile frame #REF! #REF! #REF! 45.00 #REF! #REF!
tile grout #REF! #REF! #REF! 50.00 #REF! #REF!
sub total #REF! #REF! #REF!
CHB (4"x8"x16") #REF! #REF! #REF! - #REF! #REF!
P-2

sub total #REF! - #REF! -


25- 2" x 2" x 12' Coco Lumber #REF! #REF! #REF! #REF! 10.00 #REF! #REF!
100 pcs 2x2x12 lumber lawaan #REF! #REF! #REF! #REF! 25.00 #REF! #REF!
100 pcs 2x4x12 lumber lawaan #REF! #REF! #REF! #REF! 25.00 #REF! #REF!
1"x12"x12' yakal facia board #REF! #REF! #REF! #REF! 35.00 #REF! #REF!
2'x6"x 10' Yakal Window jamb #REF! #REF! #REF! #REF! 35.00 #REF! #REF!
2'x6"x 8' Yakal Window jamb #REF! #REF! #REF! #REF! 35.00 #REF! #REF!
PACKAGE 3

2'x6"x8' yakal Door jamb #REF! #REF! #REF! #REF! 35.00 #REF! #REF!
2'x6"x12' yakal Door jamb #REF! #REF! #REF! #REF! 35.00 #REF! #REF!
2"x2"x12' for studs & ceiling joist lawaan #REF! #REF! #REF! #REF! 25.00 #REF! #REF!
2"x3"x12' form lumber lawaan #REF! #REF! #REF! #REF! 25.00 #REF! #REF!
2"x2"x14' form lumber lawaan #REF! #REF! #REF! #REF! 25.00 #REF! #REF!
1"x2"x8' form lumber lawaan #REF! #REF! #REF! #REF! 25.00 #REF! #REF!
1"x1"x8' lawaan for air vent #REF! #REF! #REF! #REF! 25.00 #REF! #REF!
sub total #REF! - #REF! #REF!
1.0x2.10m Hard Panel Door (Tugas or Narra)
#REF! #REF! #REF! #REF! #REF! #REF!
INSTALLED
PACKAGE 4

#REF!
0.80 x 2.10m Flush Type Door(Narra or Tugas
#REF! #REF! #REF! #REF! #REF! #REF!
Framing)INSTALLED #REF!
sub total #REF! - - #REF!
0.60m x 15 blades jalousie glass with alluminum
#REF! #REF! #REF! - #REF!
frame (INSTALLED)
PACKAGE 5

#REF!
0.60m x 5 blades jalousie glass with alum.frame
#REF! #REF! #REF! - #REF!
(INSTALLED) #REF!
sub total #REF! - - #REF!
Colorib Longspan 0.40mm x 1.10m x 5.5m (Green) #REF! #REF! #REF! #REF! 1,694.55 #REF! #REF!
PACKAGE 6

Colorib No. 24, x 8' Pre formed Side Gutter (Green) #REF! #REF! #REF! #REF! 490.62 #REF! #REF!
Colorib No. 24, x 8' Pre formed Ridgeroll (Green) #REF! #REF! #REF! #REF! 352.67 #REF! #REF!
Colorib No. 24, x 8' Pre formed Side End Flashing #REF! #REF! #REF! #REF! 490.62 #REF! #REF!
sub total #REF! - #REF! -
Water Closet (Royal Tern or equiv.) #REF! #REF! #REF! - #REF! #REF!
Lavatory Wall Hung type w/ complete accessories #REF! #REF! #REF! - #REF!
#REF!
Stainless Tank (500 liters capacity) #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Towel Holder #REF! #REF! #REF! - #REF! #REF!
Toilet Paper Holder #REF! #REF! #REF! - #REF! #REF!
Soap Holder #REF! #REF! #REF! - #REF! #REF!
4x4 Floor strainer steel #REF! #REF! #REF! - #REF! #REF!
4"dia.x3.0m. PVC pipe #REF! #REF! #REF! - #REF! #REF!
P-Trap 2"dia. PVC #REF! #REF! #REF! - #REF! #REF!
2"dia.x3.0m. PVC pipe #REF! #REF! #REF! - #REF! #REF!
PACKAGE 7

4"dia. PVC Elbow (90* bend) #REF! #REF! #REF! - #REF! #REF!
4"dia. PVC Tee #REF! #REF! #REF! - #REF! #REF!
4"dia. Clean Out Plug #REF! #REF! #REF! - #REF! #REF!

Page 38 of 65
QUANTITY
UNIT COST
PACKAGES
PACKAGE 7

No. of Crew/ TOTAL UNIT PROC


PACKAGE ITEMS Unit TOTAL
Labor UNIT RATE/RATE PER ADD: FREIGHT &
COST METHOD 1st Tranche
DAY HANDLING COST
KC Grant LCC Cash
4"dia.x2"dia. Reducer Tee #REF! #REF! #REF! - #REF! #REF!
2"dia.x3.0m. PVC pipe (VTR) #REF! #REF! #REF! - #REF! #REF!
2"dia. PVC Coupling #REF! #REF! #REF! - #REF! #REF!
PVC Solvent #REF! #REF! #REF! - #REF! #REF!
PVCpipe 1/2"x6.0m. Sch.40 #REF! #REF! #REF! - #REF! #REF!
1/2" dia. PVC. Coupling sch.40 #REF! #REF! #REF! - #REF! #REF!
1/2" dia PVC Tee sch 40 #REF! #REF! #REF! - #REF! #REF!
Faucet (1/2") brass ( US Brand) #REF! #REF! #REF! - #REF! #REF!
sub total #REF! - #REF! -
Panel Board (4 branches) #REF! #REF! #REF! 435.00 #REF!
Circuit breaker (60A, 20A, 15A) #REF! #REF! #REF! 540.00 #REF!
#14 THW Wire (stranded) #REF! #REF! #REF! 2,785.00 #REF!
#12 THW Wire (stranded) #REF! #REF! #REF! 3,780.00 #REF!
#10 THW Wire #REF! #REF! #REF! 37.00 #REF!
PVC Junction box #REF! #REF! #REF! 27.00 #REF!
PVC Utility box #REF! #REF! #REF! 20.00 #REF!
Flash Type Convenience Outlet (3-Gang) #REF! #REF! #REF! 180.00 #REF!
Switch Flush Type(2 gang) #REF! #REF! #REF! 135.00 #REF!
Switch Flush Type(1 gang) #REF! #REF! #REF! 95.00 #REF!
PACKAGE 8

Flourescent assembly (40w) (branded) #REF! #REF! #REF! 375.00 #REF!


Bulb 50 w #REF! #REF! #REF! 31.00 #REF!
PVC Receptacle #REF! #REF! #REF! 27.00 #REF!
Female Plug Screw Type #REF! #REF! #REF! 27.00 #REF!
3/4"dia.x3.0m. PVC pipe #REF! #REF! #REF! 98.00 #REF!
1/2" dia. Flexible hose #REF! #REF! #REF! 700.00 #REF!
3/4"dia. PVC Entrance Cap #REF! #REF! #REF! 50.00 #REF!
1/2" wood screw #REF! #REF! #REF! 0.75 #REF!
3/4" dia. C-clamp 20.00 pcs. #REF! 5.00 100.00
Electrical Tape (big) #REF! rolls #REF! 27.00 #REF!
sub total #REF! - - -
Chair wooden #REF! #REF! #REF! - #REF! #REF!
Table wooden #REF! #REF! #REF! - #REF! #REF!
P-9

sub total #REF! - - #REF!


Concrete Neutralizer #REF! #REF! #REF! 460.00 #REF!
Raw Shienna Tinting Color Latex #REF! #REF! #REF! 49.00 #REF!
Latex Gloss (Choco Brown) #REF! #REF! #REF! 390.00 #REF!
Red Oxide Metal Primer (red) #REF! #REF! #REF! 422.00 #REF!
Rust Converter #REF! #REF! #REF! 486.00 #REF!
Enamel Gloss (Choco Brown) #REF! #REF! #REF! 475.00 #REF!
Flat Wall Latex White #REF! #REF! #REF! 515.00 #REF!
PACKAGE 9

Latex Gloss white #REF! #REF! #REF! 605.00 #REF!


Flatwall enamel white #REF! #REF! #REF! 568.00 #REF!
Gloss enamel white #REF! #REF! #REF! 621.00 #REF!
Paint Thinner #REF! #REF! #REF! 233.00 #REF!
Sand Paper #250 #REF! #REF! #REF! 14.00 #REF!
Putty Pallet #REF! #REF! #REF! 17.00 #REF!
Concrete putty #REF! #REF! #REF! 315.00 #REF!
Wooden Putty #REF! #REF! #REF! 620.00 #REF!
sub total #REF! - - -
Supply and Install Community Project Steel
PACKAGE 10

#REF! #REF! #REF! #REF! 10,000.00 #REF!


Billboard #REF!
Supply and Install Bronze Building Marker #REF! #REF! #REF! #REF! #REF! #REF! #REF!
sub total #REF! - - #REF!
TOTAL MATERIALS DIRECT COST (cash) #REF! - #REF! #REF!
Labor:
Skilled 19,800.00 (10,355.00)
CFA
P 11

Unskilled 12,100.00 (18,625.80)


sub-total 31,900.00 (28,980.80) -
TOTAL CASH DIRECT COST #REF! #REF! #REF!
Indirect Cost
PACKAGE 12

Administrative Cost 40,000.00 40,000.00


Material Testing 4,000.00 4,000.00
CFA

Treasurer's Bond 3,375.00 3,375.00


Contingency Cost 72,110.00
Sub-Total 119,485.00 4,000.00 43,375.00
GRAND TOTAL CASH #REF! #REF! #REF!
SAY #REF! #REF!
% #REF! #REF!
#REF!
Workshop output of: Checked by: #REF! Reviewed by: #REF!

Procurement Team Head PPT Municipal Engineer Deputy Area Coordinator

Page 39 of 65
LANNED COMMUNITY PROCUREMENT PACKAGING

Construction of One(1) Unit Two(2) Classroom Building

SOURCES OF FUNDS PERCENTAGE WEIGHT LEGEND: FUND SOURCE


TOTAL
LCC: TO KC GRANT TO LCC CASH KC GRANT
- #REF! #REF! #REF! TOTAL LCC
#REF! #REF! #REF! #REF! LCC - In-kind
- #REF! #REF! #REF! LCC - Cash
#REF! #REF! #REF! #REF! TOTAL

TRANCHES
TOTAL
2nd Tranche 3rd Tranche SUB-TOTAL
KC Grant LCC Cash KC Grant LCC Cash KC Grant LCC Cash
- #REF! #REF!
- #REF! #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
- #REF! #REF!
#REF! - #REF!
- #REF! #REF!
- #REF! #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
2,640.00 - 2,640.00
#REF! - #REF!
#REF! - #REF!
4,275.00 - 4,275.00
- #REF! #REF!
#REF! - #REF!
102,695.00 - 102,695.00
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
- - - - #REF! #REF! #REF!
#REF! - #REF!
- - - - #REF! - #REF!
- #REF! #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
- - - - #REF! #REF! #REF!

- #REF! #REF!

- #REF! #REF!
- - - - - #REF! #REF!

- #REF! #REF!

- #REF! #REF!
- - - - - #REF! #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
- - - - #REF! - #REF!
#REF! - #REF!

#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!

Page 40 of 65
TRANCHES
TOTAL
2nd Tranche 3rd Tranche SUB-TOTAL
KC Grant LCC Cash KC Grant LCC Cash KC Grant LCC Cash
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
#REF! - #REF!
- - - - #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
100.00 100.00
#REF! #REF! - #REF!
#REF! - - - #REF! - #REF!
- #REF! #REF!
- #REF! #REF!
- - - - - #REF! #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! #REF! - #REF!
#REF! - #REF! - #REF! - #REF!

- #REF! #REF!
- #REF! #REF!
- - - - - #REF! #REF!
#REF! - #REF! - #REF! #REF! #REF!

30,155.00 19,800.00 - 19,800.00


30,312.40 413.40 12,100.00 - 12,100.00
60,467.40 - 413.40 - 31,900.00 - 31,900.00
#REF! - #REF! - #REF! #REF! #REF!

- 40,000.00 40,000.00
4,000.00 - 4,000.00
- 3,375.00 3,375.00
72,110.00 72,110.00 - 72,110.00
- - 72,110.00 - 76,110.00 43,375.00 119,485.00
#REF! - #REF! - #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!

Submitted by: Noted by:

MACRINO L. SUMAGANG
BSMPC Regional Community Infra. Engineer

Page 41 of 65
Repub

Province

DESIGN OF TWO

BILL O
RATE
PER DAY/
ITEM DESCRIPTION QUANTITY UNIT
UNIT
COST
Coco or Lawaan Lumber, 40 - 2" x 2" x 12' 750.00 bd.ft 30.00
Coco or Lawaan Lumber, 100 pcs 2" x 3" x 12' 896.00 bd.ft. 30.00
Coco or Lawaan Lumber, 100 pcs 2" x 2" x 12' 3,550.00 bd.ft. 30.00
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509

CHB (4" x 8" x 16") 12,523.00 pcs. 30.00

### Err:509 Err:509 Err:509


### Err:509 Err:509 Err:509
Screened Gravel 3/4" 446.00 cu.m. 2,240.00
Washed Sand 173.00 cu.m. 1,000.00
Washed Sand 5.00 cu.m. 1,000.00
Washed Sand 44.00 cu.m. 1,000.00
Washed Sand 33.00 cu.m. 1,000.00
2-Gang Switch, Flush Type 15.00 pcs. 150.00
### Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
Body Filler 20.00 gals 590.00
Unglazed Floor Tiles, 16" x 16" 450.00 pcs 180.00
Ceramic Wall Tiles, 8" x 8" 3,225.00 pcs 90.00
Florecent Lamp, 40 watts 2.00 pcs. 200.00
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
Circuit Breaker 60 A 1.00 pc. 350.00
Concrete Putty 45.00 gals 370.00
Concrete Neutralizer 20.00 gals 250.00
CW Nails # 1½" 10.00 kgs. 90.00
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
CW Nails # 2½" 15.00 kgs. 90.00
### Err:509 Err:509 Err:509
CW Nails # 3 3.00 kg 80.00
### Err:509 Err:509 Err:509
CW Nails # 4" 40.00 kgs. 90.00
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
Deformed Steel Bars, 12 mm Ø x 6.0 m (Grade 60) 1,152.00 length 250.00
Deformed Steel Bars, 16 mm Ø x 6.0 m (Grade 60) 321.00 length 430.00
Deformed Steel Bars, 20 mm Ø x 6.0 m (Grade 60) 295.00 length 670.00
Door Knob (High Quality) 52.00 pcs. 900.00
Duplex Convenience Outlet, Flush Type 50.00 pcs. 95.00
Electrical Tape (Big) 70.00 pcs. 35.00
Entrance Cap, 3/4" dia. 2.00 pcs. 85.00
### Err:509 Err:509 Err:509
Water Pump (1.0HP) 1.00 pcs. 12,800.00
Flat Enamel White 10.00 gals 540.00
Flat Latex White 15.00 gals 490.00
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
G.I. Tie Wire, #16 268.00 kg 80.00
Gate Valve, 1/2" dia. 2.00 pc. 255.00
Glazing Putty 45.00 gals 665.00
Hacksaw Blade 45.00 pcs. 75.00
Junction Boxes PVC, 4" x 4" 18.00 pcs. 35.00
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
Lettering Brush 1" 3.00 pc 30.00
Lettering Brush 1/2" 3.00 pc 30.00
Loose Pin Hinges,4" x 4" (High Quality) 155.00 pcs. 180.00
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
Nylon # 30 1.00 kg 350.00
Ordinary Plywood, 4' x 8' x 1/4" 63.00 shts. 400.00
Paint Brush 2" 10.00 pcs 30.00
Paint Brush 4" 10.00 pcs 75.00
Paint Roller 7" with Pan 5.00 sets 95.00
Paint Thinner 15.00 gals 285.00
Panel Board (18-Holes) branded 1.00 pc. 625.00
Portland Cement Type 1 3,097.00 bags 290.00
Portland Cement Type 1 523.00 bags 290.00
Portland Cement Type 1 385.00 bags 290.00
Portland Cement Type 1 21.50 bags 290.00
PVC Clamp 100.00 pcs. 7.00
PVC Clean Out Plug, 4" dia. 17.00 pcs. 75.00
### Err:509 Err:509 Err:509
PPR Elbow, 1/2" dia. 54.00 pcs. 25.00
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
PVC Elbow, 4" dia. X 45 deg. Bend 56.00 pcs. 70.00
PVC Elbow, 4" dia. X 90 deg. Bend 24.00 pcs. 70.00
### Err:509 Err:509 Err:509
PPR Pipe, 1/2" x 3.0m 60.00 length 380.00
PVC Pipe, 2" dia. X 3.0m, S-1000 4.00 length 290.00
### Err:509 Err:509 Err:509
PVC Pipe, 4" dia. X 3.0 m., S-1000 14.00 length 795.00
PVC P-Trap, 2" dia. 20.00 pcs. 65.00
### Err:509 Err:509 Err:509
PPR Tee, 1/2" dia. 75.00 pcs. 25.00
### Err:509 Err:509 Err:509
PVC Wye Reducer, 4"Ø x 2"Ø dia. X 45 deg. Bend 20.00 pcs. 80.00
PVC Wye, 4" x 4" dia. 56.00 pcs. 95.00
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
RSC Pipe, 3/4" dia. 100.00 length 420.00
Sandpaper #100 40.00 pcs 30.00
Sandpaper #200 25.00 pcs 35.00
Screw Insulator 30.00 pcs. 35.00
Semi-Gloss Latex White 25.00 gals 645.00
### Err:509 Err:509 Err:509
Solvent Cement 1.00 pints 95.00
Stainless Floor Drain, 4" x 4" 26.00 pcs. 280.00
Teflon Tape, 3/4" (big) 20.00 pcs. 20.00
THHN / THWN Stranded Co. Wire, 5.5 mm² 20.00 boxes 3,500.00
### Err:509 Err:509 Err:509
Tile Trim 90.00 m 65.00
Utility Boxes PVC, 2" x 4" 53.00 pcs. 35.00
Water Closet w/ complete accessories, Wall Hung type L 19.00 sets 6,500.00
White Cement / Tile Grout 125.00 kgs. 75.00

Service Drop Wire, 8.0 45.00 m 35.00


KWHR meter w/ Base 2.00 unit 4,500.00
### Err:509 Err:509 Err:509
Err:509

D-1: Double swing door (Glass) 2.00 units 15,000.00


D-2: Solid Core Door (Narra) 3.00 units 6,000.00
### Err:509 Err:509 Err:509
Err:509
### Err:509 Err:509 Err:509
Err:509
### Err:509 Err:509 Err:509
Err:509
### Err:509 Err:509 Err:509

W-1: Sliding Glass Window, 1.50m x 1.20m 3.00 units 3,500.00


W-2: Awning Glass & Fixed Glass Window, 4.70m x 4.00 units 5,000.00
2.30m
Err:509 Err:509 Err:509 Err:509

PVC ACOUSTIC GYPSUM BOARD (2'x4' ; 603mm x


1212mm x 9mm) 710.00 pcs 160.00
Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509

Err:509 Err:509 Err:509 Err:509


Err:509 Err:509 Err:509 Err:509

P.P.E./HANDTOOLS
Shovel w/ handle 3.00 pcs. 453.00
Crow Bar 1.00 pcs. 253.00
Concrete Pail 10.00 pcs. 153.00
Safety Belt 2.00 pcs. 900.00
Rubber Boots 10.00 pcs. 403.00
Hard Hat 10.00 pcs. 210.00
Hand Glove 10.00 pcs. 78.00
Construction Mask 10.00 pcs. 20.00
Republic of the Philippines
Err:509
Err:509
Province of Surigao del Norte
Err:509
Err:509

Err:509

DESIGN OF TWO-STOREY PENSION HOUSE

BILL OF QUANTITIES
COST SHARING
Total KC-NCDDP COMMUNITY BLGU MLGU
GRANT CONTRIBUTION IN-
KIND
CASH IN-KIND CASH IN-KIND
22,500.00 22,500.00
26,880.00 26,880.00
106,500.00 106,500.00
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509

375,690.00 375,690.00

Err:509 Err:509
Err:509 Err:509
999,040.00 999,040.00
173,000.00 173,000.00
5,000.00 #REF! #REF!
44,000.00 44,000.00
33,000.00 33,000.00
2,250.00 2,250.00
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
11,800.00 11,800.00
81,000.00 81,000.00
290,250.00 290,250.00
400.00 400.00
Err:509 Err:509
Err:509 Err:509
350.00 350.00
16,650.00 16,650.00
5,000.00 5,000.00
900.00 900.00
Err:509 Err:509
Err:509 Err:509
1,350.00 1,350.00
Err:509 Err:509
240.00 240.00
Err:509 Err:509
3,600.00 3,600.00
Err:509 Err:509
Err:509 Err:509
288,000.00 288,000.00
138,030.00 138,030.00
197,650.00 197,650.00
46,800.00 46,800.00
4,750.00 4,750.00
2,450.00 2,450.00
170.00 170.00
Err:509 Err:509
12,800.00 12,800.00
5,400.00 5,400.00
7,350.00 7,350.00
Err:509 Err:509
Err:509 Err:509
21,440.00 21,440.00
510.00 510.00
29,925.00 29,925.00
3,375.00 3,375.00
630.00 630.00
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
90.00 90.00
90.00 90.00
27,900.00 27,900.00
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
350.00 350.00
25,200.00 25,200.00
300.00 300.00
750.00 750.00
475.00 475.00
4,275.00 4,275.00
625.00 625.00
898,130.00 898,130.00
151,670.00 151,670.00
111,650.00 111,650.00
6,235.00 6,235.00
700.00 700.00
1,275.00 1,275.00
Err:509 Err:509
1,350.00 1,350.00
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
3,920.00 3,920.00
1,680.00 1,680.00
Err:509 Err:509
22,800.00 22,800.00
1,160.00 1,160.00
Err:509 Err:509
11,130.00 11,130.00
1,300.00 1,300.00
Err:509 Err:509
1,875.00 1,875.00
Err:509 Err:509
1,600.00 1,600.00
5,320.00 5,320.00
Err:509 Err:509
Err:509 Err:509
42,000.00 42,000.00
1,200.00 1,200.00
875.00 875.00
1,050.00 1,050.00
16,125.00 16,125.00
Err:509 Err:509
95.00 95.00
7,280.00 7,280.00
400.00 400.00
70,000.00 70,000.00
Err:509 Err:509
5,850.00 5,850.00
1,855.00 1,855.00
123,500.00 123,500.00
9,375.00 9,375.00

1,575.00 1,575.00
9,000.00 9,000.00
Err:509 Err:509

30,000.00 30,000.00
18,000.00 18,000.00
Err:509 Err:509

Err:509 Err:509

Err:509 Err:509

Err:509 Err:509

10,500.00 10,500.00
20,000.00 20,000.00
Err:509 Err:509

113,600.00 113,600.00
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509

Err:509 Err:509
Err:509 Err:509

-
1,359.00 1,359.00
253.00 253.00
1,530.00 1,530.00
1,800.00 1,800.00
4,030.00 4,030.00
2,100.00 2,100.00
780.00 780.00
200.00 200.00
PLGU TOTAL LCC TOTAL

CASH CASH IN-KIND


- - 22,500.00
- - 26,880.00
- - 106,500.00
- - Err:509
- - Err:509
- - Err:509
- - Err:509
- - Err:509
- - Err:509
- - Err:509
- - Err:509
- - Err:509
- - Err:509
- - Err:509
- - Err:509
- - Err:509
- - Err:509
- - Err:509

- - 375,690.00

- Err:509 Err:509
- - Err:509
- - 999,040.00
- - 173,000.00
- #REF! #REF!
- - 44,000.00
- - 33,000.00
- - 2,250.00
- - Err:509
- - Err:509
- - Err:509
- - 11,800.00
- - 81,000.00
- - 290,250.00
- - 400.00
- - Err:509
- - Err:509
- - 350.00
- - 16,650.00
- - 5,000.00
- - 900.00
- - Err:509
- - Err:509
- - 1,350.00
- - Err:509
- - 240.00
- - Err:509
- - 3,600.00
- - Err:509
- - Err:509
- - 288,000.00
- - 138,030.00
- - 197,650.00
- - 46,800.00
- - 4,750.00
- - 2,450.00
- - 170.00
- - Err:509
- - 12,800.00
- - 5,400.00
- - 7,350.00
- - Err:509
- - Err:509
- - 21,440.00
- - 510.00
- - 29,925.00
- - 3,375.00
- - 630.00
- - Err:509
- - Err:509
- - Err:509
- - Err:509
- - Err:509
- - 90.00
- - 90.00
- - 27,900.00
- - Err:509
- - Err:509
- - Err:509
- - 350.00
- - 25,200.00
- - 300.00
- - 750.00
- - 475.00
- - 4,275.00
- - 625.00
- - 898,130.00
- - 151,670.00
- - 111,650.00
- - 6,235.00
- - 700.00
- - 1,275.00
- - Err:509
- - 1,350.00
- - Err:509
- - Err:509
- - Err:509
- - 3,920.00
- - 1,680.00
- - Err:509
- - 22,800.00
- - 1,160.00
- - Err:509
- - 11,130.00
- - 1,300.00
- - Err:509
- - 1,875.00
- - Err:509
- - 1,600.00
- - 5,320.00
- - Err:509
- - Err:509
- - 42,000.00
- - 1,200.00
- - 875.00
- - 1,050.00
- - 16,125.00
- - Err:509
- - 95.00
- - 7,280.00
- - 400.00
- - 70,000.00
- - Err:509
- - 5,850.00
- - 1,855.00
- - 123,500.00
- - 9,375.00

- - 1,575.00
- - 9,000.00
- - Err:509

- - 30,000.00
- - 18,000.00
- - Err:509

- - Err:509

- - Err:509

- - Err:509

- - 10,500.00
- - 20,000.00
- - Err:509

- - 113,600.00
- - Err:509
- - Err:509
- - Err:509
- - Err:509
- - Err:509
- - Err:509
- - Err:509

- - Err:509
- - Err:509

- - -
- - 1,359.00
- - 253.00
- - 1,530.00
- - 1,800.00
- - 4,030.00
- - 2,100.00
- - 780.00
- - 200.00
PROPOSED ONE-STOREY RESIDENTIAL BU
MONITORING CHART / WORK SCHEDULE

Project Title: DESIGN OF TWO-STOREY PENSION HOUSE


Location: BRGY. LIPATA, SURIGAO CITY
Contractor: RJB CONSTRUCTION
Contract Amount: Err:509
Item % % %
DESCRIPTION AMOUNT
no. W.F. Accomp. Prog APRIL
100 CLEARING AND LAY-OUT 38,130.00 Err:509 0.0% 0.0%
0 FORMS AND SCAFFOLDING 183,095.00 Err:509
103 STRUCTURE EXCAVATION 48,000.00 Err:509 0.0% 0.0%
405 STRUCTURAL CONCRETE 2,788,900.00 Err:509 0.0% 0.0%
404 REINFORCING STEEL 2,034,570.00 Err:509 0.0% 0.0%
506 MASONRY WORKS 756,160.00 Err:509 0.0% 0.0%
1027 CEMENT PLASTER FINISH 514,250.00 Err:509 0.0% 0.0%
1018 TILEWORKS 600,750.00 Err:509 0.0% 0.0%
1003 CEILING WORKS 143,500.00 Err:509 0.0% 0.0%
1010 DOORS AND WINDOWS 345,300.00 Err:509 0.0% 0.0%
1012 PLUMBING WORKS Err:509 Err:509 0.0% 0.0%
1100 ELECTRICAL WORKS 279,505.00 Err:509 0.0% 0.0%
1032 PAINTING WORKS 166,305.00 Err:509 0.0% 0.0%
0 ACCESSORIES & OTHERS Err:509 Err:509 0.0% 0.0%
TOTAL Err:509 Err:509

Legend:
Schedule

PERT-CPM
DURATION
NODE ACTIVITY
(DAYS)
A MOBILIZATION 2
B #REF! 6
C STRUCTURAL EXCAVATION 6
D FORMS AND SCAFFOLDINGS 13
E #REF! 0
F #REF! 0
G #REF! 0
H #REF! days
I #REF! 0
J CEILING WORKS 0
K #REF! 0
L #REF! 0
M #REF! 0
N #REF! 0
O ACOUSTIC ACCESSORIES 0
P DEMOBOLIZATION 2
29
EY RESIDENTIAL BUILDING

GANTT CHART
DURATION 209 CALENDAR DAYS (4 WEEKS PER MONTH)
MAY JUNE JULY AUGUST SEPTEMBER

SUBMITTED BY: JAY MARK. SABUBU


APPROVED BY: ENGR. ELMARIO A. PEJAN ,MBA
BSCE INSTRUCTOR

START DURATION
CLEARING AND ### 6
FORMS AND SCA ### 13
STRUCTURE EXC ### 6
STRUCTURAL C ### 28
REINFORCING S ### 63
MASONRY WORK ### 28
CEMENT PLASTE ### 15
TILEWORKS 9/21/2020 7
CEILING WORKS
9/14/2020 6
DOORS AND WI ### 10
PLUMBING WOR ### 20
ELECTRICAL WO ### 10
PAINTING WORK
9/21/2020 20
ACCESSORIES & ### 15

###
###
OCTOBER NOVEMBER
PERT-CPM
ACTIVITY NODE PREDECESSOR
A CLEARING AND LAY-OUT A -
B STRUCTURE EXCAVATION B A
C STRUCTURAL CONCRETE C B
D REINFORCING STEEL D C
E CEMENT PLASTER FINISH E B
F MASONRY WORKS F E
G TILEWORKS G F
H CEILING WORKS H C
I DOORS AND WINDOWS I G
J PLUMBING WORKS J I
K ELECTRICAL WORKS K J
L PAINTING WORKS L K
M ACCESSORIES & OTHERS M L
TOTAL

CRITICAL PATH:
A-B-C-E-F-G-I-J-K-L = 135 DAYS
ending
4/4/2019
###
6/3/2019
###
###
###
###
###
8/3/2019
###
###
###
8/5/2019

K-L = 135 DAYS

PERT-CPM
DURATION
NODE ACTIVITY PREDECESSOR
(DAYS)
A MOBILIZATION - 2
B CLEARING AND LAY-OUT A 6
C STRUCTURAL EXCAVATION B 6
D FORMS AND SCAFFOLDINGS C 13
E REINFORCING STEEL C 63
F STRUCTURAL CONCRETE D,E,L,M 50
G CEMENT PLASTER FINISH H 42
H MASONRY WORKS F 84
I TILEWORKS J 9
J CEILING WORKS K 7
K DOORS AND WINDOWS G 8
L PLUMBING WORKS C 20
M ELECTRICAL WORKS C 10
N PAINTING WORKS J 15
O ACOUSTIC ACCESSORIES & OTHERS I,N 15
P DEMOBOLIZATION O 2
TOTAL 352
DESIGN OF A 3-STOREY SOUNDPROOF BUILDING USING FOAM BRICKS STICKER WALLPAPER
Project Title: DESIGN OF A 3-STOREY SOUNDPROOF BUILDING USING FOAM BRICKS STICKER WALLPAPER
Location: BRGY. LIPATA, SURIGAO CITY
Contractor: RJB CONSTRUCTION
Contract Amount: 1,80Err:509 S-CURVE
APRIL MAY JUNE JULY AUGUST SEP
Item no. DESCRIPTION AMOUNT W.F START FINISH DURATION wk1 wk2 wk3 wk4 wk5 wk6 wk7 wk8 wk9 wk10 wk11 wk12 wk13 wk14 wk15 wk16 wk17 wk18 wk19 wk20 wk21
100 CLEARING AND LAY-OUT 38,130.00 Err:509 WK1 WK1 1 ###
0 FORMS AND SCAFFOLDING 183,095.00 Err:509 WK3 WK5 3 Err:509 Err:509 Err:509
103 STRUCTURE EXCAVATION 48,000.00 Err:509 WK2 WK2 1 Err:509
405 STRUCTURAL CONCRETE 2,788,900.00 Err:509 WK13 WK17 5 Err:509 Err:509 Err:509 Err:509 Err:509
404 REINFORCING STEEL 2,034,570.00 Err:509 WK3 WK12 10 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 ###
506 MASONRY WORKS 756,160.00 Err:509 WK18 WK20 3 Err:509 Err:509 Err:509
1027 CEMENT PLASTER FINISH 514,250.00 Err:509 WK21 WK25 5 ###
1018 TILEWORKS 600,750.00 Err:509 WK28 WK28 1
1003 CEILING WORKS 143,500.00 Err:509 WK27 WK27 1
1010 DOORS AND WINDOWS 345,300.00 Err:509 WK26 WK27 2
1012 PLUMBING WORKS Err:509 Err:509 WK3 WK6 4 Err:509 Err:509 Err:509 Err:509
1100 ELECTRICAL WORKS 279,505.00 Err:509 WK3 WK5 3 Err:509 Err:509 Err:509
1032 PAINTING WORKS 166,305.00 Err:509 WK28 WK30 3
ACCESSORIES & OTHERS Err:509 Err:509 WK30 WK32 3
Err:509 Err:509
WEEKLY PROGRESS TOTAL (%) Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
CUMMULATIVE PROGRESS (%) Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
ACTUAL WEEKLY PROGRESS (%) 1.00% 1.00% 7.20% 6.71% 6.80% 6.00% 3.30% 2.90% 3.10% 2.90% 2.70% 2.40% 4.45% 3.87% 3.87% 4.32% 4.30% 5.23% 5.24% 5.23% 0.39%
ACTUAL CUMMULATIVE PROGRESS (%) 1.0% 2.0% 9.2% 15.9% 22.7% 28.7% 32.0% 34.9% 38.0% 40.9% 43.6% 46.0% 50.5% 54.3% 58.2% 62.5% 66.8% 72.1% 77.3% 82.5% 82.9%
Legend: S-CURVE SUBMITTED BY: JAY MARK
Schedule APPROVED BY: ENGR. ELMARIO
Actual BSCE INS
START DURATION START FINISH DURATION
CLEARING AND LAY-OU ### 6 WK1 WK1 1
FORMS AND SCAFFOLDI ### 13 WK3 WK5 3
STRUCTURE EXCAVATI ### 6 WK2 WK2 1
STRUCTURAL CONCRET ### 28 WK13 WK17 5
REINFORCING STEEL ### 63 WK3 WK12 10
MASONRY WORKS ### 15 WK18 WK20 3
CEMENT PLASTER FINIS ### 28 WK21 WK25 5
TILEWORKS 9/21/2020 7 WK28 WK28 1
CEILING WORKS 9/14/2020 6 WK27 WK27 1
DOORS AND WINDOWS ### 10 WK26 WK27 2
PLUMBING WORKS ### 20 WK3 WK6 4
ELECTRICAL WORKS ### 10 WK3 WK5 3
PAINTING WORKS 9/21/2020 20 WK28 WK30 3
ACCESSORIES & OTHER ### 15 WK30 WK32 3
247

PERT-CPM
DURATION
NODE ACTIVITY
PREDECESSOR
(DAYS)
A MOBILIZ - 2
B CLEARIN A 6
C STRUCTU B 6
D FORMS A C 13
E REINFOR C 63
F STRUCTD,E,L,M 50
G CEMENT H 42
H MASONR F 84
I TILEWO J 9
J CEILING K 7
K DOORS G 8
L PLUMBI C 20
M ELECTRI C 10
N PAINTIN J 15
O ACOUSTI I,N 15
P DEMOBOL O 2
TOTAL 352
SEPTEMBER OCTOBER NOVEMBER
wk22 wk23 wk24 wk25 wk26 wk27 wk28 wk29 wk30 wk31 wk32

Err:509 Err:509 ### ###


Err:509
###
Err:509 ###

Err:509 Err:509 Err:509


Err:509 ### ###

Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
0.50% 0.49% 0.32% 0.41% 2.00% 3.25% 5.23% 0.89% 2.47% 1.21% 0.32%
83.4% 83.9% 84.2% 84.6% 86.6% 89.9% 95.1% 96.0% 98.5% 99.7% 100.0%
AY MARK. SABUBU
ELMARIO A. PEJAN ,MBA
BSCE INSTRUCTOR

You might also like