SCEDULE PEMADAMAN SUTT CL 150 kV

ID Task Name Duration Start Finish 11 Oct '09 18 Oct '09 25 Oct '09 01 Nov '09 08 Nov '09 15 Nov '09
SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTW
1 Milestone Pemadaman 16 days Thu 29/10/09 Fri 13/11/09

2 Pemadaman Jalur CIK 4 4 days Thu 29/10/09 Sun 01/11/09 29/10 01/11

3 Pemadaman Jalur CIK 3 4 days Mon 02/11/09 Thu 05/11/09 02/11 05/11

4 Pemadaman Jalur BBL1 4 days Fri 06/11/09 Mon 09/11/09 06/11 09/11

5 Pemadaman Jalur BBL2 4 days Tue 10/11/09 Fri 13/11/09 10/11 13/11

6 Erection Tower CM 4N/MB 4N (4EE6+36) 8 days Mon 12/10/09 Mon 19/10/09

7 Pekerjaan Stringing & Connecting Konduktor 31 days Wed 14/10/09 Fri 13/11/09

8 Persiapan Stringing 5 days Wed 14/10/09 Sun 18/10/09

9 Penarikan CIK 3, CIK 4, BBL 1, dan BBL 2 (CM3N-CM4N/MB4N-MB3S) 10 days Mon 19/10/09 Wed 28/10/09

10 Relokasi CIK 4 (CM 7.1S-MB 3S) dan (CM 4N - CM 3N) 4 days Thu 29/10/09 Sun 01/11/09

11 Relokasi CIK 3 (CM 7.1S-MB 3S) dan (CM 4N - CM 3N) 4 days Mon 02/11/09 Thu 05/11/09

12 Relokasi BBL1 (CM 7.1S-MB 3S) dan (CM 4N - MB 4.1N) (MB 11N - MB 12N) 4 days Fri 06/11/09 Mon 09/11/09

13 Relokasi BBL2 (CM 7.1S-MB 3S) dan (CM 4N - MB 4.1N) (MB 11N - MB 12N) 4 days Tue 10/11/09 Fri 13/11/09

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
Project: Schedule Pemadaman SU Milestone Inactive Task Manual Summary Rollup Progress
Summary Inactive Milestone Manual Summary Manual Progress
Project Summary Inactive Summary Start-only

Page 1