Project schedule

WBS ID TASK NAME PREDECESSOR DURATION Start End


(days) date date Resource
($)
1.0 implementing - 184 July 1 Jan 1 -
software package
1.1 installation - 31 July 15 Aug 2 $3900
1.2 feeding 1.1 31 Oct 1 Oct 31 $1000
information
1.2.1 vendor 1.1 10 Oct 1 Oct 10 400
information
1.2.2 customer details 1.1 10 Oct 11 Oct 20 -
1.2.3 inventory details 1.1 5 Oct 21 Oct 25 -
1.2.4 training details 1.1 6 Oct 25 Oct 31 -
1.3 vendor 1.2.1 10 Oct 1 Oct 10 350
management
1.3.1 vendor 1.2.1 10 Oct 1 Oct 10 -
information
1.3.2 flexibility to 1.2.1 10 Oct 1 Oct 10 -
modify vendor
details
1.3.3 vendors product 1.2.1 10 Oct 1 Oct 10 -
(resource)
1.3.4 multiple vendor 1.2.1 10 Oct 1 Oct 10 -
list
1.4 inventory 1.2.3 5 Oct 21 Oct 25 250
management
1.4.1 stock 1.2.3 5 Oct 21 Oct 25 -
management
1.4.2 purchase order 1.2.3 5 Oct 21 Oct 25 -
management
1.4.3 warehouse 1.2.3 5 Oct 21 Oct 25 -
management
1.4.4 material 1.2.3 5 Oct 21 Oct 25 -
requirement
1.5 training 1.2.4 6 Oct 25 Oct 31 100$
1.5.1 selecting suitable 1.2.4 6 Oct 25 Oct 31 10
employee
1.5.2 educating 1.2.4 6 Oct 25 Oct 31 50
employee about
the software
1.5.3 training 1.2.4 6 Oct 25 Oct 31 30
employee
1.5.4 training 1.2.4 6 Oct 25 Oct 31 10
employee for
maintaining the
software