Tue 2/16/16 Our Wedding 6:53 PM

ID Task Name Duration Start Finish


Qtr 4, 2015 Qtr 1, 2016
Nov Dec Jan Feb
0 SSI Wedding 16 190 days Fri 12/4/15 Thu 8/25/16
1
2 Agree budget and approach 10 days Fri 12/4/15 Thu 12/17/15 Bride,Groom
3
4 Set wedding date 1 day Tue 2/23/16 Tue 2/23/16
5 Wedding date set 0 days Tue 2/23/16 Tue 2/23/16
6
7 PREPARATION PHASE 169 days Fri 12/18/15 Wed 8/10/16
8 Attire 123 days Fri 1/8/16 Tue 6/28/16
9 Select and order wedding dress 104 days Fri 1/8/16 Wed 6/1/16
10 Select wedding dress 40 days Fri 1/8/16 Thu 3/3/16
11 Order dress 1 day Wed 3/23/16 Wed 3/23/16
12 Measurements and fittings 50 days Thu 3/24/16 Wed 6/1/16 Brid
13 Select and order bridesmaid dresses 70 days Tue 3/1/16 Mon 6/6/16 Brid
14 Select and order groom tuxedo 40 days Wed 3/23/16 Tue 5/17/16 Brid
15 Select and order best man tuxedo 30 days Wed 5/18/16 Tue 6/28/16
16 All attire ordered 0 days Mon 6/6/16 Mon 6/6/16
17 Guests 109 days Fri 12/18/15 Wed 5/18/16
18 Make Guest List 15 days Fri 12/18/15 Thu 1/7/16 Bride,Groom
19 Send out invitations 20 days Wed 2/24/16 Tue 3/22/16
20 Finalize Guest List 5 days Thu 5/5/16 Wed 5/11/16
21 Guest List finalized 0 days Wed 5/11/16 Wed 5/11/16

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: SSI Wedding 16.mpp
Summary Manual Summary Rollup Progress
Date: Tue 2/16/16
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1 of 6
Tue 2/16/16 Our Wedding 6:53 PM
ID Task Name Duration Start Finish
Qtr 4, 2015 Qtr 1, 2016
Nov Dec Jan Feb
22 Book guest accommodation 5 days Thu 5/12/16 Wed 5/18/16
23 Reception Venue 94 days Fri 1/8/16 Wed 5/18/16
24 Make reception venue short list 15 days Fri 1/8/16 Thu 1/28/16 Bride[50%],
25 Book reception venue 1 day Fri 2/19/16 Fri 2/19/16
26 Reception venue booked 0 days Fri 2/19/16 Fri 2/19/16
27 Plan and finalize seating arrangements 5 days Thu 5/12/16 Wed 5/18/16
28 Catering 124 days Fri 1/8/16 Wed 6/29/16
29 Make caterer short list 23.5 days Fri 1/8/16 Wed 2/10/16 Groo
30 Book caterer and finalize menu 15 days Wed 3/2/16 Tue 3/22/16
31 Make baker short list 15 days Thu 5/19/16 Wed 6/8/16
32 Select baker and order cake 15 days Thu 6/9/16 Wed 6/29/16
33 Flowers 30 days Thu 6/9/16 Wed 7/20/16
34 Make florist short list 15 days Thu 6/9/16 Wed 6/29/16
35 Select florist and order flowers 15 days Thu 6/30/16 Wed 7/20/16
36 Memories 30 days Thu 3/24/16 Wed 5/4/16
37 Make photographer short list 15 days Thu 3/24/16 Wed 4/13/16
38 Select and book photographer 15 days Thu 4/14/16 Wed 5/4/16 Pho
39 Details 80 days Wed 2/24/16 Tue 6/14/16
40 Select and buy rings 20 days Wed 5/18/16 Tue 6/14/16
41 Select and book entertainment 20 days Wed 2/24/16 Tue 3/22/16
42 Select and book transport 10 days Thu 5/19/16 Wed 6/1/16
43 Register wedding and get license 5 days Wed 2/24/16 Tue 3/1/16

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: SSI Wedding 16.mpp
Summary Manual Summary Rollup Progress
Date: Tue 2/16/16
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2 of 6
Tue 2/16/16 Our Wedding 6:53 PM
ID Task Name Duration Start Finish
Qtr 4, 2015 Qtr 1, 2016
Nov Dec Jan Feb
44 Wedding registered and licensed 0 days Tue 3/1/16 Tue 3/1/16
45 Wedding Venue 17 days Fri 1/29/16 Mon 2/22/16
46 Make wedding venue short list 15 days Fri 1/29/16 Thu 2/18/16
47 Book wedding venue 1 day Mon 2/22/16 Mon 2/22/16
48 Wedding venue booked 0 days Mon 2/22/16 Mon 2/22/16
49 Honeymoon 30 days Thu 6/30/16 Wed 8/10/16
50 Make honeymoon destination short list 20 days Thu 6/30/16 Wed 7/27/16
51 Select honeymoon destination and book 10 days Thu 7/28/16 Wed 8/10/16
honeymoon
52
53 Rehearsal 1 day Tue 8/16/16 Tue 8/16/16
54 Wedding day 1 day Thu 8/25/16 Thu 8/25/16

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: SSI Wedding 16.mpp
Summary Manual Summary Rollup Progress
Date: Tue 2/16/16
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 3 of 6
Tue 2/16/16 Our Wedding 6:53 PM

6 Qtr 2, 2016 Qtr 3, 2016 Qtr 4, 2016


Feb Mar Apr May Jun Jul Aug Sep Oct Nov De

2/23

Bride[20%]
Bride[50%],Bride's attire[$4,100.00]
Bride[10%]
Bridesmaid 1[20%],Bride[10%],Bridesmaid 2[20%],Bridesmaids' attire[$1,600.00]
Bride[20%],Groom's attire[$1,100.00]
Best Man's attire[$800.00],Groom[10%]
6/6

ide,Groom
Groom[50%],Stationery[$520.00]
Bride[50%],Groom[50%]
5/11

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: SSI Wedding 16.mpp
Summary Manual Summary Rollup Progress
Date: Tue 2/16/16
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 4 of 6
Tue 2/16/16 Our Wedding 6:53 PM

6 Qtr 2, 2016 Qtr 3, 2016 Qtr 4, 2016


Feb Mar Apr May Jun Jul Aug Sep Oct Nov De
Groom[50%]

Bride[50%],Groom[50%]
Bride[50%],Reception venue[$6,950.00]
2/19
Bride[50%]

Groom[50%],Bride[10%]
Bride[20%],Groom[20%],Catering[$5,100.00]
Groom[50%],Bride[10%]
Bride[20%],Groom[20%],Cake[$450.00]

Groom[50%],Bride[10%]
Bride[20%],Groom[20%],Flowers[$750.00]

Bride[50%],Groom[10%]
Photographer[$1,500.00],Bride[20%],Groom[20%]

Wedding rings[$1,000.00],Bride[20%],Groom[20%]
Bride[50%],Groom[20%],Entertainment[$900.00]
Bride[20%],Groom[20%]
Groom[20%],Bride[20%]

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: SSI Wedding 16.mpp
Summary Manual Summary Rollup Progress
Date: Tue 2/16/16
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 5 of 6
Tue 2/16/16 Our Wedding 6:53 PM

6 Qtr 2, 2016 Qtr 3, 2016 Qtr 4, 2016


Feb Mar Apr May Jun Jul Aug Sep Oct Nov De
3/1

Bride[50%],Groom[50%]
Bride[20%],Wedding venue[$4,500.00]
2/22

Bride[40%],Groom[40%]
Bride[20%],Groom[20%],Honeymoon cost[$5,000.00]

Bride,Groom
8/25

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: SSI Wedding 16.mpp
Summary Manual Summary Rollup Progress
Date: Tue 2/16/16
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 6 of 6