Professional Documents
Culture Documents
2020 01 27 Relatorio Situacao Das Apos Periodo Chuvoso Mina Da Fabrica e Gongo Soco PDF
2020 01 27 Relatorio Situacao Das Apos Periodo Chuvoso Mina Da Fabrica e Gongo Soco PDF
RESPONSE REVISION 0
25 JANUARY 2020 INQUIRY
STATUS OF STRUCTURES AT FÁBRICA MINE AND GONGO SOCO MINE AFTER SEVERE
RAINFALL EVENTS
Thank you for your email of 25 January 2020 requesting information related to the status of
the structures in RIZZO International, Inc. (RIZZO) audit scope after recent severe rainfall
events. RIZZO deployed inspection teams on both 26 January 2020 and 27 January 2020 to
assess the status of the structures. We provide a summary of the observations and
recommendations made by RIZZO for Fábrica and Gongo Soco Sites.
RIZZO deployed a dam inspection team consisting of dam engineers and geologists to
Fábrica Mine. The RIZZO Team discussed pluviometric data and conditions on critical
structures after the severe rainfall events last week. Rainfall at Fábrica Mine was less intense
than in other areas in Minas Gerais. Rainfall at Fábrica Mine was measured from a
pluviometric station located near the offices/control room; measurements in 24-hour
increments indicated:
The numbers above are 24-hour measurements from 9 a.m. to 9 a.m. the next day. Based on
preliminary information provided by VALE staff, no major issues were found after the rain
events; only minor slope failures and erosion along some roads. It should be noted that in
CPX Mine (near Belo Horizonte), 240 mm of rain were reported in 24 hours on 24 January
2020, which could potentially represent the 100-year rain event.
RIZZO staff reviewed some of the monitoring data which was being recorded at that time in
the geotechnical Control Room. RIZZO and VALE staff decided to prioritize the
inspections. The plan was to start with Forquilha III following with Forquilha I, II, and IV
and finally the open pit in Area 18 (adjacent Freitas Dike). Afterwards, one team went to the
Geotechnical Monitoring Center at MAC (Belo Horizonte) to discuss instrumentation and
monitoring of critical structures and the other team stayed in Fábrica Mine and continued
with inspection of other structures: Grupo, Prata and Mares II.
The inspections were aided by small unmanned aerial vehicles (sUAV) or “drones”.
L-MPMG-29 196029/20
Dr. Andressa de Oliveira Lanchotti 3 27 January 2020
FIGURE 1
LOCALIZED SLOPE FAILURE IN AREA OF DRAINAGE PIPE AT FORQUILA III
RESERVOIR
FIGURE 2
SLOPE CRACK AT PUMPING AREA FORQUILA III RESERVOIR
L-MPMG-29 196029/20
Dr. Andressa de Oliveira Lanchotti 4 27 January 2020
There are two dewatering pumps in the Forquilha III reservoir. Each pump has a
capacity of 400 m3/h. However, only one pump is currently operational. VALE
staff is currently repairing the other pump.
The drop inlet spillway is spilling water which indicates that the reservoir level is
above its crest (Figure 3). Flows from the dewatering pump are also discharged
into the spillway.
VALE staff indicated that the reservoir level increased approximately 1 m due to
the recent storm events; they estimate that it will probably take two full days to
lower the reservoir level back to its previous level, without additional rainfall.
RIZZO staff performed a drone reconnaissance over Forquilha III Dam. Based on
visual observations from the right abutment, no anomalies were identified that
could represent an imminent dam safety concern. No seepage or apparent
deformations were identified; however, we will have to review the drone footage
in more detail to confirm this information.
VALE staff indicated that after evaluating the most recent monitoring data results,
they could not identify any anomalies that may be of concern. VALE cross
referenced data from two radar stations and compared them with the robotic total
station. Apparently, there is one radar that is showing displacements in some
areas but after checking these results against the other instruments (redundancy);
VALE’s interpretation is that these results are noise from the vegetation cover
and/or rain/humidity.
FIGURE 3
ACTIVATED DROP INLET SPILLWAY (INTAKE TOWER) AT FORQUILA III
RESERVOIR
L-MPMG-29 196029/20
Dr. Andressa de Oliveira Lanchotti 5 27 January 2020
FIGURE 4
EROSION OF SADDLE DIKE AT THE BOTTOM OF FORQUILHA I DAM
L-MPMG-29 196029/20
Dr. Andressa de Oliveira Lanchotti 6 27 January 2020
FIGURE 5
EROSION OF SADDLE DIKE AT THE BOTTOM OF FORQUILHA I DAM
(CLOSE UP)
1.4 FORQUILHA IV
The RIZZO Team observed an erosion gully at the groin on the left
abutment of Forquilha IV Dam. Apparently this feature did not
significantly increase in size after the storm events. Drone footage will
be reviewed to evaluate this condition in more detail. VALE staff
indicated that they have a plan to remediate the erosion in both abutments
after access is allowed. This plan also includes the replacement of five
pumps in Forquilha IV reservoir; currently only one is operating.
L-MPMG-29 196029/20
Dr. Andressa de Oliveira Lanchotti 7 27 January 2020
FIGURE 6
UPSTREAM SLOPE AND BEACH OF FORQUILHA IV DAM
1.5 FORQUILHA V
The slope failures due to uncontrolled seepage through the benches are
deteriorating from lack of maintenance and excessive rainfall.
VALE staff indicated that they have geophysical testing results in this
area which have not been interpreted. These data will provide valuable
information for the regrading and seepage control/dewatering design.
VALE indicated that the rehabilitation design will be provided to RIZZO
by the end of this week.
The continuous deterioration of Area 18 Pit could impact Freitas Dike and
reservoir if erosion in the Pit is not controlled in a timely manner.
L-MPMG-29 196029/20
Dr. Andressa de Oliveira Lanchotti 8 27 January 2020
FIGURE 7
EROSION IN AREA 18 PIT AND FREITAS DIKE
1.7 FREITAS
1.8 GRUPO
Very little water is visible in the Grupo reservoir, and wide beach at the
Dam.
RIZZO staff flew reconnaissance with the drone over Grupo Dam.
1.9 MARÉS II
L-MPMG-29 196029/20
Dr. Andressa de Oliveira Lanchotti 9 27 January 2020
Two pumps are in operation. One is rated to 450 m3/h and the other at
50 m3/h. For a total of 500 m3/h. Both were in operation on 26 January
2020.
RIZZO staff flew reconnaissance with the drone over Marés II (Figure 8).
FIGURE 8
MARÉS II
As of this writing, RIZZO expects to obtain additional reports from VALE with additional
information on the structures inspected by RIZZO on 26 January 2020. RIZZO will also
provide observations on additional structures inspected on 27 January 2020. Following is a
list of structures that will be addressed in a revised Report:
Marés I
Barnabé
Baixo João Pereira
Alto Jacutinga
Barnabé 1
CB-3
Gambá
Mata Porcos
Prata
L-MPMG-29 196029/20
Dr. Andressa de Oliveira Lanchotti 10 27 January 2020
RIZZO’s main focus at Gongo Soco Mine was the close inspection of Sul Inferior Dam via
helicopter and drone surveys. RIZZO makes the following observations and
recommendations.
Observations:
L-MPMG-29 196029/20
Dr. Andressa de Oliveira Lanchotti 11 27 January 2020
The pumping system remains idle, despite the urgent need for it to be
functional.
Obstructions (debris and vegetation) are observed in the crest drain to
the left of the Dam.
Surveys conducted on 27 January 2020 indicate the following confirmed
elevations for the crest of Sul Inferior Dam and the water level of Sul
Inferior Reservoir:
Recommendations:
Photographs of Sul Inferior Dam are provided on Figure 9 through Figure 15.
L-MPMG-29 196029/20
Dr. Andressa de Oliveira Lanchotti 12 27 January 2020
FIGURE 9
SUL INFERIOR DAM (DOWNSTREAM FACE – LOOKING UPSTREAM)
FIGURE 10
SUL INFERIOR RESERVOIR AT THE TOE OF SUL SUPERIOR
(LOOKING UPSTREAM)
L-MPMG-29 196029/20
Dr. Andressa de Oliveira Lanchotti 13 27 January 2020
FIGURE 11
SUL INFERIOR DAM – GENERAL VIEW OF EROSION OF UPSTREAM SLOPE
FIGURE 12
SUL INFERIOR DAM – LATERAL VIEW 1 OF EROSION OF UPSTREAM SLOPE
L-MPMG-29 196029/20
Dr. Andressa de Oliveira Lanchotti 14 27 January 2020
FIGURE 13
SUL INFERIOR DAM – LATERAL VIEW 2 OF EROSION OF UPSTREAM SLOPE
FIGURE 14
SUL INFERIOR DAM – LATERAL VIEW 3 OF EROSION OF UPSTREAM SLOPE
L-MPMG-29 196029/20
Dr. Andressa de Oliveira Lanchotti 15 27 January 2020
FIGURE 15
SUL INFERIOR DAM – SPILLWAY
RIZZO plans to revise this Letter Report to include additional information gathered today
onsite, as well as to provide post-processed images and footing from drone surveys.
If you have any questions, please do not hesitate to contact me by telephone at +1 (412) 825-
2210 or by email at juan.gutierrez@rizzointl.com.
Respectfully submitted,
RIZZO International, Inc.
Juan Gutierrez
Senior
Engineer ,Rizzo
International, Inc.
Juan J. Gutiérrez, Ph.D., P.E.
Chief Infrastructure Engineer
JJG/ljr
L-MPMG-29 196029/20