Tugas RTBT
Tugas RTBT
NIM : 1710813210002
Mata Kuliah : Rekayasa Tambang BawahTanah
TUGAS!!!
1. Penambangan room and pillar, menggunakan continuous mining dengan alat
angkut shuttle car. Kondisi kerja adalah sebagai berikut:
Working place= 6 x 20 ft(1.8 x 6.0 m)
Working time= 7 hr/shift, 2 shifts/day, 250 days/yr
Working section= 14
Advance/cut (10 ft,width) = 40 ft( 12 m)
Tonnage factor = 24 ft3/ton (0.75 m3/tonne)
Required shift production = 1000 tons/machine
Net shift working time = 6 hr55 min
Number of shuttle cars per miner = 2
Capacity of car = 6.25 tons
Delays while loading car = 0.6 min
Delay while changing cars = 0.4 min
Delay while miner place changing = 3 min/cut
Cuts/shift= 12