γs := 1.8
3
m
π
θ1 := 20 θ := θ1 = 0.349 rad
180
tonf
σt := 1.5
2
m
kgf
u := 0.5 SC := 0
m
predimecionamiento
e1 := 0.5m min
e1
e4 := 0m min
kgf
f´c := 210 kgf
2 fy := 4200
cm 2
cm
hep := 8m
hp´ := hep + e4 = 8 m
hp´
e3´ := = 1.143 m min
7
e3 := 2 m
1 sen 35
Ka = = 0.271
1 + sen 35
2
sin( ψ θ)
Ka := = 0.49
2
2
sin( ψ) sin( ψ δ´) 1 +
sin( θ + δ´) sin( θ β)
sin( ψ δ´) sin( ψ + β)
b := 1m
1 tonf
γs Ka hp´ = 7.06
m m
1 2
Ep := γs Ka b hp´ = 28.241 tonf Epsc := SC Ka hp´ = 0 ton
2
- Por flexión :
ϕ := 0.9
hp´ hp´
Mp := Ep + Epsc = 75.309 tonf m
3 2
fy
M U = Ø f y b d 2 1 0.59
f 'c
Mpu
d´ := = 63.594 cm
ϕ ρ fy b 1 0.59 ρ
fy
f´c
- Por corte :
V´ := Ep = 28.241 tonf
4
V´u := 1.8 V´ = 4.612 10 kgf
V´u
d´´ :=
0.85 0.53 f´´c b
d´´ = 70.638 cm
Luego: usaremos
recubrimiento
r := 4cm
e´2 := d´´´ + r = 74.638 cm
e2 := 75cm digito
d := e2 5cm = 70 cm
Dimensionamiento de la zapata:
b = 1m
tonf
γc := 2.4
3
m
e1 = 0.5 m hp´ = 8 m
e2 = 0.75 m
1 2
e3 = 2 m empuje := γs Ka ( hp´ + e3) b + SC Ka ( hp´ + e3) = 44.126 tonf
2
e4 = 0
previo para calcular
u = 0.5
B1 := 5m aplicar tanteo
V1 := ( e2 e1)
hp´
γc b = 2.4 tonf
2
B2 := 3m
V2 := ( e1 hp´) ( γc b) = 9.6 tonf
( V1 + V2 + V3 + V4) u
FSD´ := = 1.265
empuje
Volteo
2
X1 := B2 + ( e2 e1) = 3.167 m M1 := V1 X1 = 7.6 tonf m
3
X2 := B2 + e2 0.5 e1 = 3.5 m M2 := V2 X2 = 33.6 tonf m
X3 := B2 + 0.5 ( e2 + B1) = 5.875 m M3 := V3 X3 = 162.15 tonf m
X4 := B2 + e2 + 0.5 B1 = 6.25 m M4 := V4 X4 = 450 tonf m
X5 := 0.5 B2 = 1.5 m
M5 := V5 X5 = 21.6 tonf m
M1 + M2 + M3 + M4 + M5 = 674.95 tonf m
FSV := 1.8
M1 + M2 + M3 + M4 + M5
FSV´ := = 4.589
( hp´ + e3)
empuje
3