Exercise 4a
Questions: 1. How many weeks in advance of the film release should Virginia Shop start its marketing
campaign? What are the critical paths?
2. If activities I and J were not necessary, what impact would this have on the critical path and the
number of weeks needed to complete the marketing campaign?
It wont necessarily have an impact on the critical path, because the critical path will remain the same. If
disregard activities I and J, the final design phase will be completed earlier.
1. Identify the critical paths. How long does the project takes?
K,L,M,N,Q,R,V,W,Y,Z
4. Will work breakdown structure useful in a project like this? Take the 26 activities and break them into
what you think should be level 2, level 3, and level 4 tasks?