Global Energy Development
Ⅰ. Corporation Introduction Co., Ltd

General Information
Company name Global Energy Development Co,. Ltd.

Address #1214 New T-Castle, 429-1, Gasan-dong, Geumcheon-gu, Seoul


Capital USD 539,216
CEO Oak, Jang (張 鈺)

Tel (Fax) 82-2-413-5030(82-2-413-2580)

Business No. 215-87-65455

Business Detail Renewable energy business development, Heat combination & group energy
(Domestic) business, Biomass Pellet Exporting/ Importing business
Business Detail Forestation in South Asia, Biomass Pellet manufacturing plant operation and
(Overseas) development business, Biomass Pellet exporting business
Establishment
2nd. Mar.2012
Date
Homepage www.globalenergy.kr

1
Global Energy Development
Ⅰ. Corporation Introduction Co., Ltd

History of Company & Achievements

2
Global Energy Development
Ⅰ. Corporation Introduction Co., Ltd

History of Company & Achievements

3
Global Energy Development
Ⅰ. Corporation Introduction Co., Ltd

History of Company & Achievements

Name Position Participating History


ㅇ Planning of Heat combined power generation and group energy business utilizing Biomasses
ㅇ Performed feasibility review services of oceanic wind and solar power generation businesses
ㅇ Engaged in energy conversion of wastes (largest in Korea) and group energy business
ㅇ Led the business of “Saemangeum Landfill Comprehensive Development Business,” one of the biggest civil engineering projects in the world, as one of the
President
Jang Oak founding members

& CEO ㅇ Participated in airport highway project, the first SOC field’s private business, and as a result equipped with expert knowledge on related regulations and
laws
ㅇ Participated as an executive at an energy public enterprise for a long time, and served as an overall expert in office management, renewable business, CDM
reduction business, climate change business and planning, as well as national project evaluation committee member

ㅇ Renewable energy - geothermal heating and cooling (President & CEO)


ㅇ Combustion of renewable energy wastes (President & CEO)
Kwon Soon- Headquarte
ㅇ Head of career training center in computers and electronics for children of farming and fishing households

Jeong r Manager - Rural Development


ㅇ President, Sam-study Real-Time Education Center

ㅇ Oseong Environments Inc. (President & CEO)


Kim Gil-Hun Director ㅇ President & CEO of U-Line Inc.

Expert
ㅇ Korean energy engineering association (Director)
Kim Seong Ho committee
ㅇ Research and development special district promotion foundation (Expert committee member)
member

4
Global Energy Development
Ⅰ. Corporation Introduction Co., Ltd

Organizational Chart

President & CEO:


Auditor: Kim, Chang, Ok
Yeong Hee
Counsel Board of Directors
Group

Management Sales Overseas Business


Department Department Department

President Executiv Senior


Security,
es Managers
Managers Staff etc. Total

1 3 3 7 30 5 48

Organization chart expected as of January 2, 2015

5
Global Energy Development
Ⅰ. Corporation Introduction Co., Ltd

Achievement of patent & etc

Section Contents
Registration of a patent for the effective Biomass
Patent Cogeneration System(first patent of biomass power
plant in Korea)
Got BB grade of technical evaluation by Korea
Technology technology Finance of government(first certified in
certification Korea in heating supply business using wood pellet
and wood chip fuel)
R & D Center
R & D Center Certified from central government
Certification

Global Energy Development Corporation


Venture
certified as a Venture Business by a Technology
certification guaranteed fund of government on Oct 21. 2014.

6
Global Energy Development
Ⅰ. Corporation Introduction Co., Ltd

History of Company & Achievements

Our president (CEO, Jang Oak) has


been chosen to lead a biomass
renewable energy sector from the
south Korea innovation 55 leaders in
2014 by a monthly magazine that is
name as a Newsmaker.

7
Global Energy Development
Ⅰ. Corporation Introduction Co., Ltd

Printed DONA-A ILBO(Aug.01.2014) and Sisa Today(Aug.01.2014 ~ Aug.07.2014)

8
Global Energy Development
Ⅱ. Core competence Co., Ltd

Source of Our Competitiveness

Excellent Sufficient High Productivity


Capability Preparation • Selected as the joint venture company of
Chinese biomass heat combination power
generation business (business size is KRW
• Management from outstanding • 2 years of preparation to start the 1.7 trillion)
backgrounds including Korea’s #1 business (Biomass heat • Selected as the main corporation to carry
undergraduate degrees (SNU ,etc.) combination power generation, out the feasibility research services for
• Sustained training to enhance waste heat combination power 10mw power generation business in
capacities offered generation, solar power generation Indonesia (government-subsidized
• Significant experiences businesses, etc.) business)
• Expert group of biomass fuels • Identified and undertaking 6 domestic
• Overseas networks established projects including Nonsan biomass heat
• Group of experts who planned heat- • Securing an overseas biomass fuel combination power generation project, etc..
combination power generation
facility
• Experts on turning wastes into fuel
and engaging on heat combined power • Engaging in heat power generation
generation business of overseas biomasses,
etc.

9
Global Energy Development
Ⅱ. Core competence Co., Ltd

Management philosophy

Social
responsibility!

Environment
protection!
Sustainable
management!
Creative
challenge! Strategic Thinking!

10
Global Energy Development
Ⅲ. Strategic directions Co., Ltd

Direction of Business Strategy

1. Wood Pellet(Biomass Fuel) Supply


2. Biomass Power Plant, Community Energy Service
3. Excavation and Development of the New Renewable Energy Business

Domestic Overseas

ㅇRenewable energy development business ㅇ Biomass power generation business


- Contacting overseas Buyers, collaboration ㅇ Power generation business using wastes
- New business model designed ㅇ Renewable fuel development business
- Turning wastes into fuels - Forestation of Southeast Asia
ㅇ Biomass utilization business standardized (Myanmar, Malaysia etc.)
- Biomass power plant - Securing Biomass (Contracts with farms, etc.)
(Nonsan, Yangju, Nammyeon, Geomjun, etc.) (Indonesia’s Lampung Region etc.)
- Group energy business (Heat Sales) ㅇ Biomass utilization
ㅇ Biomass importing/ sales business - Operation of Biomass production plant
ㅇ Solar power and wind power generation business - Local power generation business
ㅇ Wind power generation business (Mongolian region)
ㅇ Turning solar waste into energy

11
Global Energy Development
Ⅲ. Strategic directions Co., Ltd

Main Business and Law

Biomass power plant business


•Act on the Promotion of the Development, Use and Diffusion of
NEW&Renewable energy(since 2012)
•Framework act on Low Carbon, Green growth(since 2012)

Steam/Heat Supplying business


•Intergrated Energy Supply Act
•Framework act on Low Carbon, Green growth
•Act on the Allocation and Trading of Greenhouse-Gas Emission
Permits(since 2015)

Biomass Fuel Business


•Act on the Promotion of saving and recycling of resources(since 2012)
•Act on the Allocation and Trading of Greenhouse-Gas Emission Permits

※Overall, our company business are closely related with laws in force in field of environment and
renewable energy since 2012.
12
Global Energy Development
Ⅲ. Strategic directions Co., Ltd

Advantages of the Biomass power plant Business


 Electricity is sold to the power
company(KEPCO).
 Registe to Korea Power Exchange(KPX)

Electricity
sales

 Sale to power company(public energy


corporation)  sale to cement maker(recycling)
 Legally mandatory starting in 2012  Because of environment law, Incineration
Business ash can be recycled
structure

REC sales Incineration


ash sales

13
Global Energy Development
Ⅲ. Strategic directions Co., Ltd

Advantages of the Biomass power plant Business

Advantage of durability Profitability


◊ Because sales of electricity and REC at
◊ Because low sulfur and cloride, the the same time, higher profitability is
facility durability is very long.
possible.

Strong point!

Environmental friendly Minimize electicity transmission


effect loss
◊ Biomass power generation system minim
◊ Greenhouse gas emission is very low. izes the power loss as a typical
※ For that reason, the Global biomass power plant is Spread
out rapidly.
distributed power supply system

14
Global Energy Development
Ⅲ. Strategic directions Co., Ltd

• Cost Reduction
• Reduction of greenhouse gas
Supply • Energy-saving
Electricity & Steam

Protection of the environment

Gain a foothold of the Global TOP 10 in 2017

15
Global Energy Development
Ⅳ. Business Overview Co., Ltd

1. Major accomplishments

Biomass power plant & Improvement of steam supply system in domestic

Division Contents
Installing 9.9MW/H Biomass power plant
Nonsan Biomass Power plant
Producing and Selling electricity and Renewable Energy Certificates
Installing 9.9MW/H Biomass power plant
Yangju Biomass power plant
Producing and Selling electricity and Renewable Energy Certificates.
Installing 9.9MW/H Biomass power plant
Nammyeon Biomass power plant
Producing and Selling electricity and Renewable Energy Certificates
Installing 9.9MW/H Biomass power plant
Geomjun Biomass power plant
Producing and Selling electricity and Renewable Energy Certificates
Installing 29.7MW/H Biomass Cogeneration system and
Yeongjongdo project with Incheon
Improvement in accommodation & fuel replacement & heat(hot
Airport Energy
water) supplying service

20MWH Biomass Gasification Installing 20MW/H Biomass power plant


cogeneration plant in Hansol artone Producing and Selling electricity and Renewable Energy Certificates
paper Daejeon factory And selling process steam

16
Global Energy Development
Ⅳ. Business Overview Co., Ltd

1. Major accomplishments

Biomass business and power plant business in overseas (Early stage project)

Division Business contents


Biomass cogeneration  Budget: 1.5billion USD for 5years
system business
 Install biomass cogeneration power plants in China with China energy company and funds

 Budget: 35million USD


Wood pellet and wood  Area: Russia of far east area(Khabarovsk)
chip business  Make a wood pellet and wood chip and supply to Korea and sell wood to the Japan,China,
Korea

Wood pellet and wood  Budget: 50 million USD


chip projects in Vietnam  Area: Vietnam, Thailand,etc
and Thailand  Make a wood pellet & wood chip and supply it to the Asia as a fuel

Budget: 1,440,000 USD


Wood pellet and wood
 Area: Kalimantan Selatan provance of Indonesia
chip projects in Indonesia
 Make a wood pellet & wood chip and supply it to the Asia as a fuel

17
Global Energy Development
Ⅳ. Business Overview Co., Ltd

1. Major accomplishments

Completed “20MWh Biomass Cogeneration system Feasibility Study In the Lampung Indonesia”

• Capacity : 20MW/h
• Contents : Construction of corn pellet manufacturing factory and biomass power plant in
Lampung
• Service charges: USD 96,000 ( Total project cost is about USD 60,000,000 )
• Financing : Government funds by Korea New&Renewable Energy Association on Nov. 2011
• participation agency : Gunhwa Co.,
• Current situation: Project of Feasibility study is completed in May. 2013.
Business was end.

Lampung Province Bandar Mataram

Project site

20km

40km

60km

18
Global Energy Development
Ⅳ. Business Overview Co., Ltd

2. Ongoing Projects
A. Internal

content In detail
name Nonsan Biomass Power Plant
rigion Nonsan-si , Chungnam, Korea
Date of start Feb. 2015 (by Posco )
Date of Dec. 2016
completion
Capacity 9.9 MW/h

< Specialties>
 This is the first case of wood pellet power
plant of 9.9mw project that received
license in Korea
 First planned using pure wood pellet
power plant in Asia.
- Since that, about 40~50 biomass power plants
received a license from government in
Korea, but most of them can’t execute their
project, because they do not get REC
agreement with large fossil fuel power plant
companies.
19
Global Energy Development
Ⅳ. Business Overview Co., Ltd

2. Ongoing Projects
A. Internal
Nonsan Biomass Power Plant

We received a license and made a


Power Purchase Agreement from the
central Government of Korea to
operate a Nonsan power plant on 4th
November 2013.

◆ Summary
- Project name : Nonsan Biomass Power Plant
(New-renewable Energy Business)
- Capacity : 9.9MWh
- Fuel : Pure Wood pellet

20
Global Energy Development
Ⅳ. Business Overview Co., Ltd

2. Ongoing Projects
A. Internal
Yangju Biomass Power Plant

We received a license and made a


Power Purchase Agreement from the
central Government of Korea to
operate a Yangju power plant on 1st
October 2014.

◆ Summary
- Project name : Yangju Biomass Power Plant
(New-renewable Energy Business)
- Capacity : 9.9MWh
- Fuel : Pure Wood pellet or Pure Wood Chip

21
Global Energy Development
Ⅳ. Business Overview Co., Ltd

2. Ongoing Projects
A. Internal
Yangju Biomass Power Plant

REC Contracted with Korea Districted Heating Corp(public


energy company). about 1 power plant.

22
Global Energy Development
Ⅳ. Business Overview Co., Ltd

2. Ongoing Projects
A. Internal
Nammyeon Biomass Power Plant

We received a license and made a


Power Purchase Agreement from the
central Government of Korea to
operate a Nammyeon power plant
on 1st October 2014.

◆ Summary
- Project name : Nammyeon Biomass Power Plant
(New-renewable Energy Business)
- Capacity : 9.9MWh
- Fuel : Pure Wood pellet or Pure Wood Chip

23
Global Energy Development
Ⅳ. Business Overview Co., Ltd

2. Ongoing Projects
A. Internal
Nammyeon Biomass Power Plant

MOU Contracted of REC with Korea Hydro & Nuclear power (public)
Corp. about 1 power plant

24
Global Energy Development
Ⅳ. Business Overview Co., Ltd

2. Ongoing Projects
A. Internal
Geomjun Biomass Power Plant

We received a license and made a


Power Purchase Agreement from the
central Government of Korea to
operate a Geomjun power plant on
1st October 2014.

◆ Summary
- Project name : Geomjun Biomass Power Plant
(New-renewable Energy Business)
- Capacity : 9.9MWh
- Fuel : Pure Wood pellet or Pure Wood Chip

25
Global Energy Development
Ⅳ. Business Overview Co., Ltd

2. Ongoing Projects
A. Internal
Geomjun Biomass Power Plant
MOU Contracted of REC with Korea Southern power (public)
Corp. about 1 power plant

26
Global Energy Development
Ⅳ. Business Overview Co., Ltd

2. Ongoing Projects
A. Internal

Yeongjongdo project with Incheon Airport Energy


 site : 272, Gonghangdong-ro, Jung-gu, Incheon, Korea
 Content : Install 29.7MW/H biomass cogeneration power plant near the Incheon Airport. Shall supply of
Hot Water to airport and near the residential district.
 total cost : about USD 109,090,909
current state : Consultation on steam supply system with Incheon International Airport Public Co.,

27
Global Energy Development
Ⅳ. Business Overview Co., Ltd

2. Ongoing Projects
A. Internal

20MWh Biomass Gasification Cogeneration plant in Hansol Artone paper Deajeon factory
 site : Hansol artone paper-manufacturing factory in Daedeok-gu, Daejeon-si, Korea
 Content : Install 20MW/H biomass gasification cogeneration plant in the factory.
Producing and Selling electricity and Renewable Energy Certificates And selling
process steam.
 total cost : USD 70,000,000
 current state : confer contract terms. Adjustment of business schedule,

28
Global Energy Development
Ⅳ. Business Overview Co., Ltd

2. Ongoing Projects
A. Internal

Photovoltaic power generation at the roof-top of factory and solar tunnel in the highway

 Content : Install Photovoltaic power generation in


the efficient locations. Such as roof-top of
factory and solar tunnel in the highway and
bonded warehouse, etc.
 Our company already has lots of co-work
experience with government office.

29
Global Energy Development
Ⅳ. Business Overview Co., Ltd

2. Ongoing Projects
B. Overseas

Biomass Cogeneration system in China

 site : eco-industrial park,Gannan ,Qiqihar City,Heilongjiang Province, China


 Content : Install biomass cogeneration power plants in China with China energy company and
funds. China government want this sort of environment friendly power plant
 total cost : USD 1.5billion for 5years
 current state : China energy company appointed Mr. Jang Oak to the C.T.O in china field.
prepare the funds for a commercial undertaking

30
Global Energy Development
Ⅳ. Business Overview Co., Ltd

2. Ongoing Projects
B. Overseas

Biomass Cogeneration system in China

Global Energy Development Corporation is ongoing to Install biomass


cogeneration power plants in China with China energy company and funds.
Currently China government want this sort of environment friendly power
plant. Belows documents are prove that China energy company appointed
Mr. Jang Oak to the C.T.O in china field.

31
Global Energy Development
Ⅳ. Business Overview Co., Ltd

2. Ongoing Projects
B. Overseas

Wood pellet and wood chip business in Russia


 area : Russia of far east area(Khabarovsk)
 Felling rights size: 257,253ha
 Content : Make a wood pellet and wood chip and supply to Korea
and sell wood to the Japan, China, Korea
 total cost : USD 35 million
 current state : make ready for the field survey

Contracted MOA with Russian Company as for doing timber harvesting business and
pellet manufacturing business and developing natural resources in Russia.

32
Global Energy Development
Ⅳ. Business Overview Co., Ltd

2. Ongoing Projects
B. Overseas

Wood pellet and wood chip projects in Vietnam and Thailand


 area : Vietnam, Thailand, etc
 Content : Make a wood pellet & wood chip and supply it to the
Asia as a fuel
 total cost : USD 50 million
 current state : make ready for the field survey and funding,
South east Asia area have a rich potential of
biomass business

Wood pellet and wood chip projects in Indonesia


 area : Kalimantan Selatan province of Indonesia
 Content : Make a wood pellet & wood chip and supply it to the
Asia as a fuel
 total cost : USD 1,440,000
 current state : make ready for the field survey and funding,
Indonesia has rich potential of biomass business,
Don’t need to buy project site. It is already confirm to
lease.

33
Global Energy Development
Ⅳ. Business Overview Co., Ltd

Buyer meeting

Have a sales meeting with Have a sales meeting with


a buyer from America a buyer from Pakistan

Meeting with Indonesia PT. PLN

34
Global Energy Development
Ⅳ. Business Overview Co., Ltd

The progress of Biomass power plant in China

Conclusion of a contract with At the scheduled


Gannan government business site

At the Gannan At the scheduled


Government office business site

35
Global Energy Development
Ⅳ. Business Overview Co., Ltd

 Balance sheet of Global Energy Development Co., Ltd (2012, 2013 ,2014)

[ Unit : USD ]

Content 2012 2013 2014


Current asset 95,903 38,345 534,543
Non-current asset 42,533 37,700 123,034
Total assets 138,436 76,045 657,577
Current liabilities 110,658 192,382 114,128
Non-current liabilities 0 90,909 199,508
Total liabilities 110,658 283,291 313,636
Capital 136,364 136,364 500,000
Capital surplus 0 0 0
Earned surplus -108,586 -343,610 -156,059
Total capital 27,778 -207,246 343,941

36
Global Energy Development
Ⅳ. Business Overview Co., Ltd

 Profit & Loss of Global Energy Development Co., Ltd (2012, 2013 ,2014)

[ Unit : USD ]

Content 2012 2013 2014


Sales 0 0 500,476
Cogs 0 0 13,850
Gross profits 0 0 486,626
Selling and
143,470 270,610 293,303
Admin. Expense
Operating income -143,470 -270,610 193,323
Net income -108,586 -235,023 187,550

37
Best Your Partner!

38
Global Energy Development
Attached Co., Ltd

Articles on the Yangju Biomass Power Plant

39
Global Energy Development
Attached Co., Ltd

Got certification Venture Business


• Global Energy Development Corporation
created R&D Department at Sep 05. 2014.
• Global Energy Development Corporation
certified as a Venture Business by a Technology
guaranteed fund on Oct 21. 2014.

40
Global Energy Development
Attached Co., Ltd

Got BB grade of technical evaluation by Korea technology Finance

• Global Energy Development Corporation


is working on “Improvement of steam supply
system using biomass fuel” projects since Aug.
2014.
• Global Energy Development Corporation
got BB grade of technical evaluation by Korea
Technology Finance for this project.

41
Global Energy Development
Attached Co., Ltd

Registration of a patent for the effective Biomass Cogeneration System

Global Energy Development Corporation


Got a patent on July 08, 2015.

Title : Bio Cogeneration system using exhaust


gas and residual heat of the steam
Content : The object of the present invention is
aimed at reduce unnecessary waste heat from
boiler of the cogeneration system and these
are used for heating or hot water.

42
Global Energy Development
Attached Co., Ltd

WOOD CHIP CONTRACT STATUS

QUANTITY PRICE(U$)
NO ORIGIN COMPANY Final price (KRW/TON)
(TON) (CFR )

CFR Incheon port 93,500


1 VIETNAM ‘L’ company 240,000 85
DDP(\) 122,621

CFR Incheon port 90,200


2 VIETNAM ‘N’ company 140,000 82
DDP(\) 119,321

CFR Incheon port 90,200


3 VIETNAM ‘H’ company 120,000 82
DDP(\) 119,321

CFR Incheon port 90,200


4 VIETNAM ‘E’ company 240,000 82
DDP(\) 119,321

5 KOREA ‘Y’ company 60,000 - DDP(\)70,000

6 KOREA ‘M’ company 60,000 - DDP(\)70,000

7 KOREA ‘G’ company 60,000 - DDP(\)70,000

43