FILING SYSTEM
Cover letter with priced BOQ, Tender bond, Program & histogram, MOU,
C1 Form of Tender
Letter of Acceptance, Contract Agreement and Site Handing Over Letter
C2 Original Contract Documents Same as tender documents but stamped as "Contract Documents"
1 Mobilization Site Staff, Site Mobilisation Plan, Site Equipments, Program, Labour Histogram
In and Out separated. File in cronological order & maintain an active and up-
3 CLIENT Correspondace
to-date log
MAIN CONTRACT
4A File in cronological order. Maintain an active and up-to-date log
Correspondance In
MAIN CONTRACT
4B File in cronological order. Maintain an active and up-to-date log
Correspondance Out
5 Insurance and Bank Labours, Equipments, Store, Productivity etc… (each in a separate file)
6A Payment Certificates In GCGC submitted payment applications & approved payment certificates
6B Payement Certificates Out Subcontractors' submitted payment applications & approved payment
certificates
Page 1 of 2
Form # fm 01-05 Issue 1
FILING SYSTEM
9 Meetings With the MAIN CONTRACT/ CLIENT & authorities. Each Meeting type in
separate file
11 Site Reports Labours, Equipments, Store, Productivity etc… (each in a separate file)
12 Quotations By Item
General Program of Works, from 1st submission till approval in and out
13A Programs
sequense (by date)
14A Quantities and Cost Control Quantities separate and cost control separate
16 Tests & Results By type of test. Maintain an active and up-to-date log
17 Safety Submitted and approved Safety Plan, tool box talks, instructions, Violations,
Assessment, Accidents
18 QA/QC Submitted and approved QA/QC Plan. Check requests for material & work