Professional Documents
Culture Documents
1.01B Provide and install or refurbish signs and km post P.Sum 6,000,000.00
2.02 Scarify failed sections of existing asphaltic surface m2 16000 1,990.00 31,840,000.00 1,524.20 139.30 99.50 - 227.00 1,990.00 24,387,200.00 2,228,800.00 1,592,000.00 - 3,632,000.00 31,840,000.00
2.04 Filling m3 3600 9,000.00 32,400,000.00 2,875.00 630.00 900.00 3,182.00 1,413.00 9,000.00 10,350,000.00 2,268,000.00 3,240,000.00 11,455,200.00 5,086,800.00 32,400,000.00
2.06 Excavate unsuitable materials m3 1250 7,000.00 8,750,000.00 1,590.00 490.00 350.00 - 4,570.00 7,000.00 1,987,500.00 612,500.00 437,500.00 - 5,712,500.00 8,750,000.00
2.11 Provide and lay gravel filter layer(200mm max. size) 300mm thick m3 4800 24,000.00 115,200,000.00 8,073.00 1,680.00 1,200.00 10,337.00 2,710.00 24,000.00 38,750,400.00 8,064,000.00 5,760,000.00 49,617,600.00 13,008,000.00 115,200,000.00
2.15 Excavate trapezoidal open earth drain comp. with conc. Blinding m 500 12,500.00 6,250,000.00 2,087.00 875.00 1,250.00 1,048.00 7,240.00 12,500.00 1,043,500.00 437,500.00 625,000.00 524,000.00 3,620,000.00 6,250,000.00
BILL No.2 CARRIED TO SUMMARY 225,440,000.00 17,939.20 4,024.30 3,949.50 14,567.00 17,010.00 57,490.00 92,398,600.00 15,780,800.00 13,204,500.00 61,596,800.00 42,459,300.00 225,440,000.00
3.20 Ditto but for lined drains m3 180 2,800.00 504,000.00 624.00 196.00 560.00 - 1,420.00 2,800.00 112,320.00 35,280.00 100,800.00 - 255,600.00 504,000.00
BILL No.3 CARRIED TO SUMMARY 43,704,000.00 1,968.00 322.00 650.00 - 1,660.00 4,600.00 32,368,320.00 3,059,280.00 2,260,800.00 - 6,015,600.00 43,704,000.00
4.03 Crushed stone base - 150mm thick m3 3000 28,000.00 84,000,000.00 10,422.00 1,960.00 2,800.00 10,998.00 1,820.00 28,000.00 31,266,000.00 5,880,000.00 8,400,000.00 32,994,000.00 5,460,000.00 84,000,000.00
4.04 Prime coat sm 20000 900.00 18,000,000.00 554.00 63.00 45.00 158.00 80.00 900.00 11,080,000.00 1,260,000.00 900,000.00 3,160,000.00 1,600,000.00 18,000,000.00
4.05 Surface dressing sm 4000 1,500.00 6,000,000.00 35.00 105.00 150.00 365.00 845.00 1,500.00 140,000.00 420,000.00 600,000.00 1,460,000.00 3,380,000.00 6,000,000.00
4.06 Ditto but with 12mm chippings sm 4000 1,400.00 5,600,000.00 (6.00) 98.00 140.00 323.00 845.00 1,400.00 (24,000.00) 392,000.00 560,000.00 1,292,000.00 3,380,000.00 5,600,000.00
4.07 Binder course - 60mm thick sm 16000 7,100.00 113,600,000.00 2,590.00 497.00 1,420.00 1,773.00 820.00 7,100.00 41,440,000.00 7,952,000.00 22,720,000.00 28,368,000.00 13,120,000.00 113,600,000.00
4.08 Wearing course - 40mm thick sm 16000 5,500.00 88,000,000.00 1,889.00 385.00 1,100.00 1,306.00 820.00 5,500.00 30,224,000.00 6,160,000.00 17,600,000.00 20,896,000.00 13,120,000.00 88,000,000.00
BILL No.4 CARRIED TO SUMMARY 387,200,000.00 14,979.00 4,298.00 7,355.00 26,923.00 7,845.00 61,400.00 112,728,000.00 27,104,000.00 57,980,000.00 138,570,000.00 50,818,000.00 387,200,000.00
Bill No 2 225,440,000.00 17,939.20 4,024.30 3,949.50 14,567.00 17,010.00 57,490.00 92,398,600.00 15,780,800.00 13,204,500.00 61,596,800.00 42,459,300.00 225,440,000.00
Bill No 3 43,704,000.00 1,968.00 322.00 650.00 - 1,660.00 4,600.00 32,368,320.00 3,059,280.00 2,260,800.00 - 6,015,600.00 43,704,000.00
Bill No 4 387,200,000.00 14,979.00 4,298.00 7,355.00 26,923.00 7,845.00 61,400.00 112,728,000.00 27,104,000.00 57,980,000.00 138,570,000.00 50,818,000.00 387,200,000.00
TOTAL 656,344,000.00 34,886.20 8,644.30 11,954.50 41,490.00 26,515.00 123,490.00 237,494,920.00 45,944,080.00 73,445,300.00 200,166,800.00 99,292,900.00 656,344,000.00
Bill Summary
Bill No.2 Site Clearance and Earthworks 225,440,000.00 17,939.20 4,024.30 3,949.50 14,567.00 17,010.00 57,490.00 92,398,600.00 15,780,800.00 13,204,500.00 61,596,800.00 42,459,300.00 225,440,000.00
Bill No.3 Culverts and Drains 43,704,000.00 1,968.00 322.00 650.00 - 1,660.00 4,600.00 32,368,320.00 3,059,280.00 2,260,800.00 - 6,015,600.00 43,704,000.00
Bill No.4 Pavement and Surfacing 387,200,000.00 14,979.00 4,298.00 7,355.00 26,923.00 7,845.00 61,400.00 112,728,000.00 27,104,000.00 57,980,000.00 138,570,000.00 50,818,000.00 387,200,000.00
Sub-Total 1 656,344,000.00 34,886.20 8,644.30 11,954.50 41,490.00 26,515.00 123,490.00 237,494,920.00 45,944,080.00 73,445,300.00 200,166,800.00 99,292,900.00 656,344,000.00
Total Permanent Works 656,344,000.00 34,886.20 8,644.30 11,954.50 41,490.00 26,515.00 123,490.00 237,494,920.00 45,944,080.00 73,445,300.00 200,166,800.00 99,292,900.00 656,344,000.00
1
P.W NIGERIA LIMITED
DRAINS 0 m - - - - -
BINDER COURSE (60mm) 2256 tons 117 749 214 171 1,005
175 3 7,371 672 327 226 9,940 11,436 578 312 2,011
STONE
CEMENT REBAR BASE SUBBASE FILLING 60/70 KEROSINE 3/4'' 1/2'' 3/8'' DUST
(Bags) (tonnes) (tonnes) (trips) (trips) (tonnes) (litres) (tonnes) (tonnes) (tonnes) (tonnes)
TOTAL QUANTITY 175 3 7,371 672 327 226 9,940 11,436 578 312 2,011
P.W NIGERIA LIMITED
BADAGRY ROAD PROJECT
201,255,794.21
COST RECONCILIATION BREAK DOWN
2.04 Filling
20 Tons = 11.00 m3
11.00 m3 = N 35,000.00
:. Cost/Unit = N 3,181.82 m3
13.64 m3 = N 141,000.00
:. Cost/Unit = N 10,337.24 m3
Thickness = 0.05 m
= 25.00 m3
= N 524,000.00
Quantity = 500.00 m
:. Cost/Unit = N 1,048.00 m
20 Tons = 12.50 m3
12.50 m3 = N 75,000.00
:. Cost/Unit = N 6,000.00 m3
12.50 m3 = N 75,000.00
:. Cost/Unit = N 6,000.00 m3
30 Tons = 12.82 m3
12.82 m3 = N 141,000.00
:. Cost/Unit = N 10,998.44 m3
4.04 Prime coat
Quantity = 20,000.00 m2
Bitumen
Quantity = 4,000.00 m2
= N 238.10 /m2
Quantity 4,000.00 m2
= N 126.90 /m2
Quantity = 4,000.00 m2
= 84.60 /m2
N 28,362,300.00
Quantity = 16,000.00 m2
:. Cost/unit = N 1,772.64 /m2
N 20,894,100.00
Quantity = 16,000.00 m2
7,536,000.00
Quantity = 24,000.00 m2
:. Cost/Unit = 314.00 m2
2,784,000.00
Quantity = 16,000.00 m2
:. Cost/Unit = 174.00 m2
1,392,000.00
Quantity = 4,000.00 m2
:. Cost/Unit = 348.00 m2
2.04 Filling
NO OF EST. NO
DESCRIPTION RATE/DAY MACHINES OF DAYS AMOUNT (₦)
3,912,000.00
Quantity = 3,600.00 m2
:. Cost/Unit = 1,086.67 m2
2.06 Excavate unsuitable materials
NO OF EST. NO
DESCRIPTION RATE/DAY MACHINES OF DAYS AMOUNT (₦)
4,392,000.00
Quantity = 1,250.00 m2
:. Cost/Unit = 3,513.60 m2
9,984,000.00
Quantity = 4,800.00 m2
:. Cost/Unit = 2,080.00 m2
2,784,000.00
Quantity = 500.00 m
:. Cost/Unit = 5,568.00 m
4,320,000.00
Quantity = 24,000.00 m2
:. Cost/Unit = 180.00 m2
3.20 Desilt sand and debris from carriageway
NO OF EST. NO
DESCRIPTION RATE/DAY MACHINES OF DAYS AMOUNT (₦)
196,000.00
Quantity = 180.00 m2
:. Cost/Unit = 1,088.89 m2
4,128,000.00
Quantity = 3,600.00 m2
:. Cost/Unit = 1,146.67 m2
4,128,000.00
Quantity = 4,800.00 m2
:. Cost/Unit = 860.00 m2
4,200,000.00
Quantity = 3,000.00 m3
:. Cost/Unit = 1,400.00 m3
4.04 Prime Coat
NO OF EST. NO
DESCRIPTION RATE/DAY MACHINES OF DAYS AMOUNT (₦)
1,176,000.00
Quantity = 20,000.00 m2
:. Cost/Unit = 58.80 m2
Quantity = 4,000.00 m2
:. Cost/Unit = 648.00 m2
2,592,000.00
Quantity = 4,000.00 m2
:. Cost/Unit = 648.00 m2
10,080,000.00
Quantity = 16,000.00 m2
:. Cost/Unit = 630.00 m2
4.08 Wearing course (40mm)
NO OF EST. NO
DESCRIPTION RATE/DAY MACHINES OF DAYS AMOUNT (₦)
10,080,000.00
Quantity = 16,000.00 m2
:. Cost/Unit = 630.00 m2
A.G.O's USAGE BREAK DOWN
9,120.00 1,459,200.00
Quantity = 24,000.00 m2
:. Cost/Unit = 60.80 m2
3,360.00 537,600.00
Quantity = 16,000.00 m2
:. Cost/Unit = 33.60 m2
Quantity = 4,000.00 m2
:. Cost/Unit = 67.20 m2
2.04 Filling
QTY/DAY NO. OF EST. NO. TOTAL QTY COST PER TOTAL
DESCRIPTION (ltrs) MACHINES OF DAYS (ltrs) LITRE (N) AMOUNT (N)
Grader 100.00 1 24 2,400.00 160.00 384,000.00
5,280.00 844,800.00
Quantity = 3,600.00 m2
:. Cost/Unit = 234.67 m2
2.06 Excavate unsuitable materials
QTY/DAY NO. OF EST. NO. TOTAL QTY COST PER TOTAL
DESCRIPTION (ltrs) MACHINES OF DAYS (ltrs) LITRE (N) AMOUNT (N)
Quantity = 1,250.00 m2
:. Cost/Unit = 614.40 m2
12,960.00 2,073,600.00
Quantity = 4,800.00 m2
:. Cost/Unit = 432.00 m2
3,000.00 480,000.00
Quantity = 500.00 m
:. Cost/Unit = 960.00 m
4,800.00 768,000.00
Quantity = 24,000.00 m2
:. Cost/Unit = 32.00 m2
3.20 Desilt sand and debris from carriageway
QTY/DAY NO. OF EST. NO. TOTAL QTY COST PER TOTAL
DESCRIPTION (ltrs) MACHINES OF DAYS (ltrs) LITRE (N) AMOUNT (N)
Quantity = 180.00 m2
:. Cost/Unit = 231.11 m2
5,280.00 844,800.00
Quantity = 3,600.00 m2
:. Cost/Unit = 234.67 m2
5,280.00 844,800.00
Quantity = 4,800.00 m2
:. Cost/Unit = 176.00 m2
5,280.00 844,800.00
Quantity = 3,000.00 m3
:. Cost/Unit = 281.60 m3
4.04 Prime Coat
QTY/DAY NO. OF EST. NO. TOTAL QTY COST PER TOTAL
DESCRIPTION (ltrs) MACHINES OF DAYS (ltrs) LITRE (N) AMOUNT (N)
1,200.00 192,000.00
Quantity = 20,000.00 m2
:. Cost/Unit = 9.60 m2
3,600.00 576,000.00
Quantity = 4,000.00 m2
:. Cost/Unit = 144.00 m2
3,600.00 576,000.00
Quantity = 4,000.00 m2
:. Cost/Unit = 144.00 m2
Quantity = 16,000.00 m2
:. Cost/Unit = 124.80 m2
4.08 Wearing course (40mm)
QTY/DAY NO. OF EST. NO. TOTAL QTY COST PER TOTAL
DESCRIPTION (ltrs) MACHINES OF DAYS (ltrs) LITRE (N) AMOUNT (N)
12,480.00 1,996,800.00
Quantity = 16,000.00 m2
:. Cost/Unit = 124.80 m2
LUBRICANTS's USAGE BREAK DOWN
912.00 319,200.00
Quantity = 24,000.00 m2
:. Cost/Unit = 13.30 m2
336.00 117,600.00
Quantity = 16,000.00 m2
:. Cost/Unit = 7.35 m2
Quantity = 4,000.00 m2
:. Cost/Unit = 14.70 m2
2.04 Filling
QTY/DAY NO. OF EST. NO. TOTAL QTY COST PER TOTAL
DESCRIPTION (ltrs) MACHINES OF DAYS (ltrs) LITRE (N) AMOUNT (N)
Grader 10.00 1 24 240.00 350.00 84,000.00
528.00 184,800.00
Quantity = 3,600.00 m2
:. Cost/Unit = 51.33 m2
2.06 Excavate unsuitable materials
QTY/DAY NO. OF EST. NO. TOTAL QTY COST PER TOTAL
DESCRIPTION (ltrs) MACHINES OF DAYS (ltrs) LITRE (N) AMOUNT (N)
Quantity = 1,250.00 m2
:. Cost/Unit = 134.40 m2
1,296.00 453,600.00
Quantity = 4,800.00 m2
:. Cost/Unit = 94.50 m2
300.00 105,000.00
Quantity = 500.00 m
:. Cost/Unit = 210.00 m
480.00 168,000.00
Quantity = 24,000.00 m2
:. Cost/Unit = 7.00 m2
3.20 Desilt sand and debris from carriageway
QTY/DAY NO. OF EST. NO. TOTAL QTY COST PER TOTAL
DESCRIPTION (ltrs) MACHINES OF DAYS (ltrs) LITRE (N) AMOUNT (N)
Quantity = 180.00 m2
:. Cost/Unit = 50.56 m2
528.00 184,800.00
Quantity = 3,600.00 m2
:. Cost/Unit = 51.33 m2
528.00 184,800.00
Quantity = 4,800.00 m2
:. Cost/Unit = 38.50 m2
528.00 184,800.00
Quantity = 3,000.00 m3
:. Cost/Unit = 61.60 m3
4.04 Prime Coat
QTY/DAY NO. OF EST. NO. TOTAL QTY COST PER TOTAL
DESCRIPTION (ltrs) MACHINES OF DAYS (ltrs) LITRE (N) AMOUNT (N)
120.00 42,000.00
Quantity = 20,000.00 m2
:. Cost/Unit = 2.10 m2
360.00 126,000.00
Quantity = 4,000.00 m2
:. Cost/Unit = 31.50 m2
360.00 126,000.00
Quantity = 4,000.00 m2
:. Cost/Unit = 31.50 m2
1,248.00 436,800.00
Quantity = 16,000.00 m2
:. Cost/Unit = 27.30 m2
4.08 Wearing course (40mm)
QTY/DAY NO. OF EST. NO. TOTAL QTY COST PER TOTAL
DESCRIPTION (ltrs) MACHINES OF DAYS (ltrs) LITRE (N) AMOUNT (N)
1,248.00 436,800.00
Quantity = 16,000.00 m2
:. Cost/Unit = 27.30 m2
PLANT COST RECONSILIATION FOR
REPAIRS OF MASAMASA (CH 8+000) - OKOKOMAIKO (CH 20+500)
BOTH BOUNDS ALONG
LAGOS - BADAGRY - SEME BORDER DUAL CARRIAGEWAY IN LAGOS II WEST (SECTION 1)
BILL No. 1: GENERAL
S/No. DESCRIPTION UNIT REVISED QTY RATE REVISED AMOUNT DRIVERS A.G.O. LUBS, OIL ETC PLANT TOTAL DRIVERS A.G.O. LUBS, OIL ETC PLANT TOTAL
1.01 Project supervision and administration P.Sum 25,000,000.00
1.01B Provide and install or refurbish signs and km post P.Sum 6,000,000.00
2.03 Scarify failed sections of existing surface dressed shoulder m2 4000 450.00 1,800,000.00 20.10 67.20 14.70 348.00 450.00 80,400.00 268,800.00 58,800.00 1,392,000.00 1,800,000.00
2.04 Filling m 3
3600 1,413.00 5,086,800.00 40.33 234.67 51.33 1,086.67 1,413.00 145,200.00 844,800.00 184,800.00 3,912,000.00 5,086,800.00
2.06 Excavate unsuitable materials m3 1250 4,570.00 5,712,500.00 307.60 614.40 134.40 3,513.60 4,570.00 384,500.00 768,000.00 168,000.00 4,392,000.00 5,712,500.00
2.11 Provide and lay gravel filter layer(200mm max. size) 300mm thick m 3
4800 2,710.00 13,008,000.00 103.50 432.00 94.50 2,080.00 2,710.00 496,800.00 2,073,600.00 453,600.00 9,984,000.00 13,008,000.00
2.15 Excavate trapezoidal open earth drain comp. with conc. Blinding m 500 7,240.00 3,620,000.00 502.00 960.00 210.00 5,568.00 7,240.00 251,000.00 480,000.00 105,000.00 2,784,000.00 3,620,000.00
BILL No.2 CARRIED TO SUMMARY 42,459,300.00 997.48 2,402.67 525.58 13,084.27 17,010.00 1,836,300.00 6,432,000.00 1,407,000.00 32,784,000.00 42,459,300.00
BILL No.3 CARRIED TO SUMMARY 6,015,600.00 70.44 263.11 57.56 1,268.89 1,660.00 512,900.00 809,600.00 177,100.00 4,516,000.00 6,015,600.00
4.02 Base 200mm thick m3 4800 1,120.00 5,376,000.00 45.50 176.00 38.50 860.00 1,120.00 218,400.00 844,800.00 184,800.00 4,128,000.00 5,376,000.00
4.04 Prime coat sm 20000 80.00 1,600,000.00 9.50 9.60 2.10 58.80 80.00 190,000.00 192,000.00 42,000.00 1,176,000.00 1,600,000.00
4.05 Surface dressing sm 4000 845.00 3,380,000.00 21.50 144.00 31.50 648.00 845.00 86,000.00 576,000.00 126,000.00 2,592,000.00 3,380,000.00
4.06 Ditto but with 12mm chippings sm 4000 845.00 3,380,000.00 21.50 144.00 31.50 648.00 845.00 86,000.00 576,000.00 126,000.00 2,592,000.00 3,380,000.00
4.07 Binder course - 60mm thick sm 16000 820.00 13,120,000.00 37.90 124.80 27.30 630.00 820.00 606,400.00 1,996,800.00 436,800.00 10,080,000.00 13,120,000.00
4.08 Wearing course - 40mm thick sm 16000 820.00 13,120,000.00 37.90 124.80 27.30 630.00 820.00 606,400.00 1,996,800.00 436,800.00 10,080,000.00 13,120,000.00
BILL No.4 CARRIED TO SUMMARY 50,818,000.00 312.93 1,239.47 271.13 6,021.47 7,845.00 2,248,000.00 7,872,000.00 1,722,000.00 38,976,000.00 50,818,000.00
Bill No 2 42,459,300.00 997.48 2,402.67 525.58 13,084.27 17,010.00 1,836,300.00 6,432,000.00 1,407,000.00 32,784,000.00 42,459,300.00
Bill No 3 6,015,600.00 70.44 263.11 57.56 1,268.89 1,660.00 512,900.00 809,600.00 177,100.00 4,516,000.00 6,015,600.00
Bill No 4 50,818,000.00 312.93 1,239.47 271.13 6,021.47 7,845.00 2,248,000.00 7,872,000.00 1,722,000.00 38,976,000.00 50,818,000.00
TOTAL 99,292,900.00 1,380.86 3,905.24 854.27 20,374.62 26,515.00 4,597,200.00 15,113,600.00 3,306,100.00 76,276,000.00 99,292,900.00
Bill Summary
Bill No.2 Site Clearance and Earthworks 42,459,300.00 997.48 2,402.67 525.58 13,084.27 17,010.00 1,836,300.00 6,432,000.00 1,407,000.00 32,784,000.00 42,459,300.00
Bill No.3 Culverts and Drains 6,015,600.00 70.44 263.11 57.56 1,268.89 1,660.00 512,900.00 809,600.00 177,100.00 4,516,000.00 6,015,600.00
Bill No.4 Pavement and Surfacing 50,818,000.00 312.93 1,239.47 271.13 6,021.47 7,845.00 2,248,000.00 7,872,000.00 1,722,000.00 38,976,000.00 50,818,000.00
Sub-Total 1 99,292,900.00 1,380.86 3,905.24 854.27 20,374.62 26,515.00 4,597,200.00 15,113,600.00 3,306,100.00 76,276,000.00 99,292,900.00
25
PRELIMINARIES BREAK DOWN
1 Mobilisation = N 3,000,000.00
9 Staff
Project Manager (50% on site) = N 550,000.00 x 6 N 3,300,000.00
Site Supervisor = N 750,000.00 x 6 N 4,500,000.00
Engineer = N 100,000.00 x 6 N 600,000.00
Q.S = N 80,000.00 x 6 N 480,000.00
Accountant = N 80,000.00 x 6 N 480,000.00
Office Boy = N 40,000.00 x 6 N 240,000.00
Nurse = N 40,000.00 x 6 N 240,000.00
Cleaner = N 40,000.00 x 6 N 240,000.00
Cook = N 40,000.00 x 6 N 240,000.00
Securities (4 nr) = N 160,000.00 x 6 N 960,000.00
10 Generator
Perkins 60KVA @ N18,000/day = N 432,000.00 x 6 N 2,592,000.00
Diesel for Generator @ N15,000/day = N 360,000.00 x 6 N 2,160,000.00
11 Miscellaneous = N 5,000,000.00
1.00 CEMENT
2.00 BLOCKS
3.00 GRANITE
4.00 SAND
Bitumen
Asphalt
1,400.00
2,500.00
1,100.00
130.00
95.00
1,800.00
2,000.00
2,100.00
2,100.00
2,100.00
1,100.00
1,650.00
1,300.00
14,500.00
1,300.00
130,000.00
RATES
TENDER PRICE
280.00
350.00
3,200.00
35.00
50.00
150.00
50.00
190.00
1,250.00
62,000.00
65,000.00
19,030.00
88.00
70.00
80.00
196.00
MATERIAL
B.) PLANTS/INSTRUMENTS
D.) LABOUR
1 Supervision 4 No Ls 35,000.00
6 Admin 4 No 8,000.00
SUMMARY
Material 1,116,500.00
Plant/Instruments 401,500.00
Diesel/Petrol 206,740.00
Labour 125,400.00
=N 37,002.80
P.W. NIGERIA LIMITED
QUARRY
IBADAN QUARRY DAILY REPORT
DATE: 09-07-2013
ITEM DESCRIPTION
1 CRUSHER
(a) HOU 7.00 HRS (AVAILABILITY) %
(b) TOTA 1,775.00 TONS
(b) PROD - m3/HR
(c) STAN 3.00 HRS
REMARKS:
(i) CRUSHING STARTED @ 7.10AM DUE TO DELAY AS A RESULT OF STONE JAM IN THE PRIMARY JAW
(ii) AND PATCHING OF MESH ON THE FINAL SCREEN
(iii)………………………………………………………………………………………………………………………………………………
TOTAL 1,775.00
TOTAL
4 DELIVERIES TO QUARRY
(a) MC1… - Tons
(b) S125… - Tons
(c) 60/70….. - Tons
5 BLASTING
PRIMARYSECONDARY
A. ……..HOLES - -
B. EXPLOSIVES - -
C. ANFO (kg) - -
D. NONT DET - -
E. N DET CONT - -
F. CORD - -
G. ELECTRIC DET - -
REMARKS …………………………………………………………………………………………………………………………………………..
……………………………………………………………………………………………………………………………………………………………
6 DRILLING - ACTIVITIES
REMARKS: ……………………………………………………………………………………………………………………………………………….
…………………………………………………………………………………………………………………..…………………………………………
7 EXPLOSIVE
REMARKS …………………………………………………………………………………………………………………………………..
……………………………………………………………………………………………………………………………………………………